SOL: Transport Sector Development Project
|
|
|
- Kerry Stevens
- 9 years ago
- Views:
Transcription
1 Transport Sector Development Project (RRP SOL 41171) Scope and Technical Report PART I: Land Transport Infrastructure Subproject (St. Martin Road) Project Number: November 2010 SOL: Transport Sector Development Project
2 ii ABBREVIATIONS ADB Asian Development Bank ADT average daily traffic AS Australian Standard Ch Chainage CPIU Central Project Implementation Unit EIRR economic internal rate of return LBES labor-based, equipment-supported MID Ministry of Infrastructure Development PPTA project preparatory technical assistance SI$ Solomon Islands dollar SIRIP Solomon Islands Road Improvement (Sector) Project
3 iii TABLE OF CONTENTS Page I. SUMMARY FACT SHEET 1 II. INTRODUCTION 1 III. DESCRIPTION OF THE SAMPLE ROAD SUBPROJECT 2 A. LOCATION AND SITE 2 B. EXISTING ROAD CONDITIONS 3 C. SURVEYS 4 D. TRAFFIC FLOWS 5 E. PROJECT OBJECTIVE 6 F. PROPOSED REHABILITATION WORKS 6 IV. RELIMINARY ENGINEERING DESIGN 7 A. FUNCTIONAL REQUIREMENTS 7 B. DESIGN STANDARDS AND CONSIDERATIONS 7 C. ROAD SAFETY CONSIDERATIONS 14 D. IMPLEMENTATION STRATEGY AND PROJECT RISKS 15 E. REHABILITATION COSTS 16 F. MAINTENANCE COSTS 17 ATTACHMENT 1 19 ATTACHMENT 2 36 ATTACHMENT 3 40 ATTACHMENT 4 56
4 1 I. SUMMARY FACT SHEET Province/Island Location Project Connectivity Existing structure type Existing traffic Projected traffic, 2030 Estimated traffic growth rate Proposed improvement Estimated Cost; Rehabilitation Maintenance Environmental Impacts Social Impacts Guadalcanal Province 6 km east of Honiara International Airport St. Martin Road Rehabilitation (8.5 km) Feeder Road connecting to Honiara-Aola Main Road and servicing access to two schools, a clinic, a community centre, several villages and market gardens Gravel road Appr. 50 vehicles per day Appr vehicles per day 2.0% - 3.0% p.a. Spot improvements, reshape pavement, drainage provision and maintenance App. $ 487,000 (SI$ 3,848,900) App. $ 24,500 per annum (SI$ 194,000) See initial environmental examination Provide public transport access and improve social cohesion. Induce residential development. See PSA. II. INTRODUCTION 1. This subproject is to rehabilitate St. Martin Road, a feeder road leading from Honiara- Aola Main Road (Kukum Highway), east of the Honiara International airport, to a more serviceable and maintainable condition. This road is on the priority list of the Ministry of Infrastructure Development (MID) for reconstruction but has not been included in the recent road rehabilitation project list for tendering. 2. A preliminary analysis has been carried out by Solomon Islands Road Improvement Project (SIRIP) 1 comparing the economic internal rate of return (EIRR) with a group of other feeder roads in the area requiring rehabilitation or upgrade based on limited secondary data. 3. This project preparatory technical assistance (PPTA) 2 aims to establish a uniform methodology for a multi-criteria analysis to prioritise transport infrastructures including roads, wharfs and airstrips. This project has been identified to serve as a sample subproject. 1 ADB Report and Recommendation of the President to the Board of Directors on Proposed Grants to Solomon Islands for the Road Improvement (Sector) Project. Manila (Grant 0048/0049/0050). 2 ADB Technical Assistance to the Solomon Islands for Preparing the Transport Sector Development Project. Manila (TA 7335-SOL).
5 2 4. This paper documents the findings of a technical investigation and survey and produces preliminary design; proposal of works with an initial cost estimate to rehabilitate the road to a maintainable condition. III. DESCRIPTION OF THE SAMPLE ROAD SUBPROJECT A. Location and Site 5. The proposed subproject for evaluation is St. Martin Road located at approximately 6km east from the Honiara International airport in Guadalcanal Province. The total length of the subject road is approximately 8.5 km, and it connects to the Honiara-Aola Main Road (Henderson Highway) in the north and attends near the School on the access road to the new Gold Ridge Relocation settlement area. The subject road provides access to St. Joseph s High School, St Martin s Technical School, a rice research farm, a clinic and several village settlements. 6. The location of the proposed sub-project is shown in Figure 1 below and the project site is shown in Figure 2. Figure 1: Road Location
6 3 Figure 2: Project Site B. Existing Road Conditions 7. The length of the road is approximately 8.5 km measured from the edge of the road at Henderson highway to the Clinic on Gold Ridge Resettlement access road. The road pavement width varies from section to section. The first section from the Highway to St. Martin s School (approximately 2.0 km) averages approximately 6.0 m. The next section between Chainage (Ch) 2,000 and 4,500 measures approximately between m. The third section between Ch 4,500 and Ch 7,300 measures 4.0 m average. The last section of the access road ending at the school and clinic is a fairly recent development, and average 4.0 m. 8. The vertical alignment is relatively flat with occasional rolling sections. Locations where road damages occurred are mainly found at the bottom of depressions where water accumulates after rains. 9. The existing wearing course consists of river gravel mixed with sand and clay. Pavement thickness varies from section to section with an average of about mm based on field observation and the condition survey carried out. 10. Results of the condition surveys undertaken by the PPTA team indicate that the riding conditions of the road varies from section to section along its length, with speeds well below 30 km/hour for most of the road due to large potholes and depressions filled with water. The damages are particularly severe where drainage provision is either absent or dysfunctional due to vegetation overgrowth or shoulder erosion and obstruction.
7 4 11. Figure 3 below illustrates typical conditions of the road at various locations, including some severe damages to the road pavement. Details of the condition surveys are attached in Attachment 1. Figure 3: Existing Road Conditions C. Surveys 12. No previous survey information was available of the road, apart from some initial assessment of the scope of work by SIRIP for project prioritization purpose. For the purpose of this subproject engineering evaluation, the following surveys were identified and conducted. (i) Road inventory and condition survey comprising visual inspections of topography, land use/vegetation, subsoil type, road surface type, access service level, road carriageway width, and road drainage condition. For this purpose, a road condition assessment form appended to this paper was designed and used (see Attachment 1).
8 5 (ii) Daily traffic and pedestrian counts (Note: Due to school holidays, traffic counts would not have provided reliable results. Thus, an estimation of current traffic amounts was made from questionnaire surveys conducted for social assessments). Future surveys to be undertaken in connection with detailed design of its rehabilitation should be detailed, for establishing quantities of work, and should include detailed topographic surveys, and sub-base soil sampling. 13. Figure 4 below shows the project engaged surveyor discussing aspects of field surveys with the local Village Chief. Figure 4: Community Consultation D. Traffic Flows 14. Most vehicles currently using the road beyond the first 2 km are four-wheel drive vehicles. Surveys indicated that buses, taxis and other commercial vehicles are reluctant to enter beyond the first 2 km. The current traffic volume (average daily traffic = ADT) of the road is estimated at 50 vehicles per day. The first 2 km of the road is more trafficked than the remainder due to the presence of schools, Church facilities and the rice research farm. The survey team also observed that there is a considerable amount of pedestrian traffic on the road, as many people are required to walk to the Henderson Highway in order to catch public transport to Honiara town centre and vice versa.
9 6 15. It is expected that traffic volumes will increase faster than the normal traffic growth rate on the section currently in poor condition, once the road is rehabilitated (access restored) and well-maintained. Based on the current level of traffic increase of approximately 2-2.5% p.a. on the Guadalcanal Island, and the expected additional traffic generation on the road, the ADT in 2030 can be projected at vehicles per day. E. Project Objective 16. The main objective of the road rehabilitation is to improve access to local communities within the zone of influence of the road, and businesses and public service facilities along the road. It is part of the overall objective of improving the road network in the Solomon Islands stipulated in the National Transport Plan. Short term benefits include better accessibility (for both vehicles and pedestrians), reduced road safety hazards and immediate improvement in facilitation of service delivery. In the longer term, the rehabilitated road is likely to attract land use developments such as market gardens and increased cash crop farming with prospects of increasing employment and community income. 17. The objective of the subproject is to reinstate road access. F. Proposed Rehabilitation Works 18. The existing road can be brought to adequate maintainable condition through rehabilitation (spot improvements). The proposed rehabilitation works will allow continuing access for road users (vehicles and pedestrians) during all weather conditions. The proposed works include: (i) (ii) For the first 2 km of the road, i.e. between the junction with Henderson highway and Chainage 2,000, provision of a new bituminous pavement, surface dressing/chip seal, maintaining the existing road width of 6.0 m with standard camber of c. 4%, and side drains, and cross drainage pipes (culverts) where required. The key proposed works for the remaining 5.5 km of the road will include: Scarifying, reshaping and re-grading of the existing road structure/ pavement, filling the depressions where required and adding a wearing course using river gravel hauled from the Lungga River. Improving drainage by clearing all debris of existing drains, and where required, excavating and providing appropriate drainage structures. Maintaining existing road alignment and road width of 4.5 m throughout. Provide a camber of 6% (after compaction). Reshaping the vertical alignment and lifting the road structure on low spots with provision of culverts where required. 19. A provision of a labour-based maintenance contract (say renewable every three years) is to be included with the following tasks: (i) (ii) (iii) Vegetation control (clearing overgrowth blocking drainage channels and fall branches). Removal of potholes and corrugations and re-grading and compacting the road surface De-silting and cleaning drainage inlets and outlets, catch-water and mitre drains.
10 7 20. The maintenance tasks are to be carried out with appropriate intervals as suggested and shown in Table 7 in Section IV F. IV. PRELIMINARY ENGINEERING DESIGN A. Functional Requirements 21. Must Have Fulfill the principle of network connectivity ( roads and bridges must be part of an integrated network to serve areas of economic activities and improve access to services and income earning opportunities) All weather accessibility Appropriate geometric and structural design Adequate drainage provision to withstand flows of large amounts of storm waters after severe storms and heavy rainfalls. Considerations for environmental protection and adaptation to climate change. Adequate provision for maintenance after the rehabilitation (either included in the rehabilitation Contractor s contract or separately) 22. Preferred to Have Appropriate provision for future road upgrading, due to road traffic increase Appropriate traffic management provisions and road safety protection in the long term, e.g. guardrails, guide posts, hazard warning signs and devices. B. Design Standards and Considerations 23. Apart from recommendations by design engineers of different road rehabilitation and reconstruction projects, the no clearly adopted uniform national technical standards for road design exist in the Solomon Islands. The following considerations are recommended for future preparation of national standard design guidelines: (i) Road widths for different traffic flow volumes a minimum design standard should be considered for feeder and local roads carrying low traffic volumes. It would be appropriate to vary the design criteria in accordance with a road s projected traffic, although it would be prudent to keep a uniform road reserve width for future upgrading needs. (ii) Standard Cross section with sufficient camber many low traffic unsealed roads do not have sufficient camber for the purpose of surface water draining from the road carriageway properly. The flat cross sections contribute to water locking and pavement damage by heavy rainfalls. Drainage considerations standard cross drainage design for various drainage needs should be considered. (iii) Standards for use of coral materials see discussions later in this section. (iv) Low cost bituminous pavement for upgrading roads with coral stone pavement this consideration should be incorporated into the design standards for more heavily trafficked roads to reduce maintenance costs.
11 8 (v) Climate change adaptation measures distance and levels from rivers or seaside should be considered in upgrading roads adjacent to river banks and in coastal areas to avoid climate change impacts. 24. The following text discusses design standards appropriate to the subproject and its equivalent road class. 1. Road Classification 25. There is no formal road classification in the Solomon Islands under the current Roads Act, although for functional purposes, roads in the Solomon Islands can generally be said to fall into three classes: Primary or Main Roads, Secondary Roads (or Feeder Roads) and Tertiary Roads (or Local Roads). Roads in urban areas (within the boundary of a township) are Urban Roads. Other roads fall into the Rural Roads category. 26. Based on the above definition, the subject road falls into the Feeder Road category, and as it is not within the urban boundary of Honiara, it is therefore a rural road. 27. Table 1 below shows a general functional road network classification in the Solomon Islands. Table 1: Functional Road Classification Road Class Function Typical Road Configurations Primary Major thoroughfare, carrying inter regional traffic 2-4 lane sealed or unsealed roads Secondary Feeder roads usually off the Primary Road network accessing 2-lane roads either sealed or to major developments, and unsealed providing access roads to residential villages or industries Tertiary Local access road to small industrial, agricultural or 1-2 lane unsealed roads residential areas 2. Road Alignment 28. Based on the current and projected traffic usage of St. Martin road, no change is proposed in terms of horizontal alignment in connection with the rehabilitation. 29. In the longer term, if and when road realignment is required because of traffic growth and for road safety purposes, the design standards adopted in Papua New Guinea for rural roads with low traffic volumes may be referred to as shown in Table 2 below. However, it is suggested that design standards for the Solomon Islands will be created, and adequate technical, economic and other country-specific considerations may be made.
12 9 Table 2: Design Standards for Realignment (for long term consideration) Feature Sealed Road Unsealed Road Design Speed 50 km/hour 40 km/hour (min) Stopping Sight Distance 55 m 60 m Minimum radii of Horizontal Curve 70 m* 80 m Minimum camber 4% 5%-6% *Note: Austroads Guide for rural road design recommends a desirable minimum radius of 60 m for operating speed of 50 km/h on flat terrain with a superelevation e=3%. 30. The adopted minimum design standards for the rehabilitation of the St. Martin road are shown in Table 3 below. Table 3: Minimum Design Standard Design Speed 40 km/h Stopping Sight Distance 50 km/h Horizontal curve radius 55 m Camber 6% 3. Pavement 31. The design life of a road pavement is defined as the length of time (expressed in years) before it is anticipated that rehabilitation of the pavement will be required to restore the normal serviceability of the road. It is closely related to its pavement structure and/or type of rehabilitation work and is influenced by many factors such as maintenance regime and traffic loading. Appropriate functional road classification should be established by criteria based on ultimate traffic loading of the road to sustain its design life. 32. Some typical design lives as indicated in the Austroads Pavement Design Guide are: New granular pavement 20 to 25 years [note: does not apply to the Solomon Islands] New rigid pavement 20 to 40 years Asphalt overlay 10 to 15 years Granular overlay 10 to 20 years [note: does not apply to the Solomon Islands] 33. However, the actual service life of a pavement will very much depend on other design factors, such as traffic loading and provision of an effective drainage system. 34. The cost of road rehabilitation also depends on the thickness of pavement, gradation of material, compaction to be provided. This in turn depends on the ultimate design life loading. 35. For rehabilitation of the road surface for the subproject road, similar materials to the existing composition should be used to ensure uniformity of wear and tear. A dry density test or a suitable in-site testing method may be appropriate to ensure the right amount of compaction required. 36. The existing pavement thickness (i.e., approximately 150 mm) is constructed of river gravel mixed with sand and clay over the majority of the road. This pavement will suffice for the
13 10 present traffic usage and the expected traffic in the medium term. Only when traffic volumes and loads increase substantially, future upgrading to a higher bearing load wearing course considered, either by increasing thickness or overlay with other materials. 4. Materials 37. Materials for base and sub-base courses should be selected from materials free from vegetable matter, clay lumps, top soil, over burden and other perishable materials. 38. The recommended requirements for material selection are shown in Table 4 below: Table 4: Material Selection Standards Sub-base Course Base Course Sealed Unsealed Sealed Unsealed CRB (moisture content > 5%) 30% 30% 80% 65% 1. Shall not contain particles with size >= 50% of compacted layers Particle size thickness specified. 2. Shall not contain more than 30% by mass passing through AS0.075 mm sieve. Plasticity 1 Modulus >= 500 >= 800 >= 1000 >= 1000 Shrinkage 2 Modulus Plasticity Index multiplied by percentage materials passing through AS0.425 mm sieve. 2 Linear shrinkage multiplied by percentage materials passing through AS0.425 mm sieve. 39. Coral materials that comply with the requirements in Table 4 can be used for base course and sub-base course pavement. The use of coral materials relies on good compaction to produce a dense interlocking structure. The achievement of a correct density is essential to minimise water seeping through to the road base. PNG Laboratory tests recommend compacted layer thickness should not exceed 150 mm. This can vary depending on results of in-situ testing. 40. Figure 5 shows a comparison of road surfaces with compacted river gravel and coral pavement material. When selecting materials to be used, the following factors need to be considered: Material availability nearby Suitability (quality) of the materials Cost of extracting and hauling Maintainability Environmental aspects
14 11 Figure 5: Compacted Road Surfaces Compacted river gravel surface Compacted coronous material pavement 5. Source of Aggregates 41. Apart from the river gravels sourced from the Lungga River, there are several aggregate mining companies in Honiara which hold building material permits from the government and can supply graded aggregates for road works. A list of the suppliers with details of company activities is attached in Attachment Drainage 42. Any road should have adequate drainage provision to: Maintain natural flow of water prior to reconstruction Collect water from road surface to suitable discharge points Protect the road from overland flow from adjacent areas; and Provide appropriate level of service. 43. An effective design will balance a number of factors against cost. These factors include: Flooding effects on traffic delays and access difficulties Possible structural damage due to severe storms and prolonged flooding Service life of drainage system and cost of replacement or improvement Road maintenance costs. 44. A detailed design for rehabilitating the existing road to a standard design cross section must consider the following issues: Grading of the roadway with respect to flood levels, groundwater levels and tidal levels Estimated runoff Maximum permissible flow width of the carriageway Size of cross culverts and outlet conditions
15 12 Surface drainage Weather changes and severe storms and greater average return intervals than the standard design value. 45. The existing drainage provision for the subproject is considered poor and mostly depends on natural surface flow. This is one of the major causes of road damage in locations where water is lodged within the road pavement due to poor or no drainage provision. The proposed rehabilitation work will include provision of trapezoidal earth (unlined) catch drains for the first 2.5 km of the road and other locations where natural surface flow is blocked by earth mounts or vegetations which are not removable. Cross-road drainage pipes will be considered for low spot locations where the road surface will require lifting to avoid accumulation of water on the road surface due to heavy rain periods. 46. A typical unlined catch drain to be used for this project is shown in Figure 6 below: Figure 6: Typical Design for Unlined Catch Drain 47. It does not appear that any major structural drainage culverts will be necessary on the subject road. Areas requiring drainage improvements have been identified during field observation including cross road RDC pipes, earth catch drains and masonry box drains recommended for minor access roads and driveways. For major access roads and cross road drainage, a minimum of 600 mm RCP with appropriate cover and end treatments is recommended. 48. A typical design for a masonry box drain is shown in Figure Calculations have been done in order to arrive at preliminary cost estimates of the rehabilitation.
16 13 Figure 7: Typical Masonry Box Drain Design Length varies A A Plan View Section A-A Front Elevation Legend Precast concrete or timber slab Gravel with cement mix 1:4 cement/sand mix
17 14 7. Preferred Cross Section 50. Current road cross section dimensions vary from road section to section. It is recommended that the standard cross section design shown in Figure 8 below be adopted and adjusted as necessary to suit local environmental constraints. Figure 8: Standard Cross Section Design C. Road Safety Considerations 51. With the existing low volume and poor pavement surface, current operating vehicle speeds do not exceed the design speed of 50 km/h. No consideration has been made to improve the road safety aspect in rural road design requirements. 52. However, the subject road is capable of operating speed higher than the design speed and when the road is rehabilitated; operating speeds will increase with increasing risks of potential accidents. Field observations revealed the following possible attributes to accident risks: Sub-standard horizontal curves with below minimum sight distances Narrow pavement widths Lack of road edge definition Lack of pedestrian footpaths Overloading of vehicles Erosion of road edges due to flooding and/or severe storms 53. For a very low cost proportion of the total rehabilitation cost of the project, some warning devices such as guide posts and curve warning signs should be provided as part of the implementation requirement.
18 15 D. Implementation Strategy and Project Risks 53. The development of any transport infrastructure must include a strategy for the future land use and economic development and needs of hinterland population for access to transport services. 54. The network connectivity is the prime consideration for transport network planning. This has been emphasized by Australian Agency for International Development in the Australia- Solomon Islands Partnership Development in the Implementation Strategy for transport infrastructures and is consistent with ADB project preparation approach and the Solomon Islands National Transport Plan policy. 55. Maximizing connectivity across multi-modal links would increase effectiveness of development partner assistance to improve access to services and income earning opportunities. The whole transport network will therefore focus on sustainability, thus maintenance and rehabilitation will have priority rather than new construction. 56. It is MID s policy (which is consistent with the policies of the development partners) to encourage labour based methods for routine maintenance and rehabilitation works, supported by use of machines where required. The Hifab report (2010) considered labor-based, equipment-supported (LBES) methodology in all road works in the Solomon Islands, including routine and periodic maintenance, rehabilitation and upgrading, covering different classes of roads, and proposed the methodology matrix as shown in Table 5 below. Road / Pavement Category Table 5: Proposed LBES Methodology Matrix Rehabilitation Routine Periodic and Spot Maintenance Maintenance Improvement Upgrading and reconstruction 1 Unsealed access LBES LBES NA Equipment 2 Unsealed Feeder LBES LBES NA Equipment 3 Coral stone low LBES + traffic Equipment LBES Equipment Equipment 4 Coral stone medium LBES + LBES + traffic Equipment Equipment Equipment Equipment 5 Gravel low traffic LBES + Equipment LBES Equipment Equipment 6 Gravel medium LBES + LBES + traffic Equipment Equipment Equipment Equipment 7 Sealed road low LBES + medium-traffic Equipment LBES Equipment NA 8 Sealed road LBES + Equipment medium-high traffic Equipment Equipment NA Source: Review of Labour-Based Road Maintenance and Contracting Activities in Solomon Islands Hifab International AB March This subproject falls into Road/Pavement category 5 (gravel road with low traffic volumes), which can therefore be implemented using a labour based equipment supported method for rehabilitation works and labour based approach for routine maintenance and equipment bases approach for periodic maintenance.
19 This subproject consists of rehabilitation of the existing road surface to a condition which will be sustainable, with ensuing routine and periodic maintenance. The main rehabilitation task consists of reshaping and gravelling most sections of the road using river gravels hauled from Lungga River. An agreement between MID and the community will be required to ensure the supply of gravel material and local labour required. 59. Main project risks and their mitigation measures are identified as follows: (i) (ii) (iii) (iv) (v) Lack of suitably experienced contractors who could confidently carry out the tasks, which include the use of local labours can be mitigated by contractor training. Reliability of equipment and reluctance to invest in equipment and machinery due to uncertainty of continuation of work can be mitigated through the Solomon Islands Government ensuring a continuous financing and program of road maintenance and rehabilitation works. Construction supervision capability of MID can be mitigated by external contract management support to MID (in the form of a Central Project Implementation Unit: CPIU), and MID s capacity building. Delay in implementation may cause further damage to the road pavement to an extent that may require complete reconstruction, thus reducing the project viability due to increase in project costs can be mitigated through effective contract management supported by CPIU consultants. A suitable future maintenance strategy is required to sustain access service level can be mitigated by creating appropriate road asset management procedures and defining maintenance service level requirements. E. Rehabilitation Costs 60. The rehabilitation cost estimates of the subproject have been produced based on unit cost rates taken from previous similar projects. The final unit costs will be a result of the detailed design, the competitive bidding process and the implementation stage. A number of factors will contribute to the final costs such as: Change of horizontal and vertical alignment at the detail design stage. Use of different materials other than recommended for the preliminary concept. Change in drainage provision in the detailed design stage. Under estimate of labour capacity in undertaking the recommended tasks. Road furniture such as signage has not been included. Competition amongst the contracting industry at the time of tendering the contract 61. The cost estimates have been produced for the purpose of economic assessment. 62. Table 6 summarises the rehabilitation costs. Detailed cost calculations are shown in Attachment 2.
20 17 Table 6: Summary of St Martin Road Rehabilitation Costs DESCRIPTION SI$ Local Foreign Total 1. Mobilisation, clearing and site establishment 190,000 60, , Vegetation clearing 66, , Pavement works 1,068, ,000 1,381, Drainage works 530, , , Day Works (labour) 420, , Day Works (machine and plant) 396, , ,000 Sub-total 2,671, ,500 3,346,850 Contingencies (15%) 502,028 Total 3,848,878 Exchange rate $1.00 = SI$ (as of 1 October 2010). $ 486,621 F. Maintenance Costs 1. Routine Maintenance 63. Maintenance contract can be either attached to the subproject rehabilitation contract for a certain period of time, or maintenance can be contracted separately. The annual routine maintenance cost is estimated to be approximately SI$ 50,500 and will mainly involve labourbased works. The estimated cost is based on the tasks and frequencies proposed as shown in Table 7 below. Activity Item 1 2 Table 7: Labor-Based Routine Maintenance Schedule Work description Frequency Season (No/year) Inspection and removal of litter and other road obstructions and debis De-silting of Culverts and clearing inlets and outlets 3 Clear side and mitre drains 4 4 Repair Erosion of shoulders and Drains NA 5 Repair Scour checks NA 6 Grub roadway (consider for machine based) 1 7 Clear structures and waterways NA 8 Fill potholes and ruts on carriageway 2 9 Cut grass and vegetable trimming and removal Before rainy season During wet weather At end of wet season During dry season Before rainy season At end of wet season During dry season Before rainy season During wet weather At end of wet season During dry season At end of wet season During dry season At end of wet season During dry season At end of wet season During dry season
21 Table 8 below sumarises the cost estimates for the recommended labor based routine maintenance contract. Table 8: Labor Based Routine Maintenance Cost Estimate for St. Martin Road A B C D E Quantity Output per Number of Daily Rate Work Item Unit workday (wd) workdays = A/B SI$ 1 Inspection and removal of litter and other road obstructions and debis 2 De-silting of Culverts and clearing inlets and outlets 3 Clear side and mitre drains 4 Repair Erosion of NA shoulders and Drains 5 Repair Scour checks NA 6 Grub and reshape roadway 7 Clear structures and NA waterways 8 Repair potholes on carriageway 9 Repair ruts on carriageway 10 Cut grass and vegetable Total Cost = CxD SI$ Km 8.5x4 0.5km ,720 no 153x3 15m ,240 m 240x4 20m ,920 m 2 600x2* 5m ,600 m 2 600x2* 5m ,600 m 600x2* 50m m 2 22,500x2 200m ,200 trimming and removal *Estimated Total Direct Labour Cost 36,240 Contingency 20% 7,248 Overhead 30% 10,872 Total Estimated Cost/year 54,360 Say 55,000 in $ 6,954 Note: Exchange rate $1.00 = SI$ (as of 1 October 2010). 2. Periodic Maintenance 65. It is envisaged that every five years (year 5, 15, etc.) the road pavement will receive periodic maintenance on the carriageway and spot resheeting (heavy grading with addition of wearing course material where it will be needed) and every ten years (year 10, 20 etc.) the periodic maintenance is expected to involve more massive resheeting and restoration of the drains to their original shape. The lighter periodic maintenance activity is estimated to cost about SI$ 50,000 per km and the heavier about SI$ 120,000 per km. 66. Using the cost estimates given, and assuming half of the routine maintenance costs on a year of periodic maintenance, the annualised maintenance costs (including both routine and periodic maintenance; in 2010 costs, not discounted) over the period of 20 years can be estimated at SI$ 22,820 per km, or $ 2,885 per km.
22 19 ATTACHMENT 1 Condition Survey Reports
23 20
24 21
25 22
26 23
27 24
28 25
29 26
30 27
31 28
32 29
33 30
34 31
35 32
36 33
37 34
38 35
39 36 ATTACHMENT 2 Construction Cost Estimates
40 Cost Estimates for Rehabilitation of St Martin Road Item Description Unit Quantity Rate SI$ Amount SI$ Amount $ A General 1 Mobilisation to site including transporting equipment and establishment of work site and workers camp etc LS 1 100, ,000 2 Demobilisation from site LS 1 100, ,000 3 Other overhead LS 1 50,000 50,000 Sub total A 250,000 31,608 B Cleaning and Scrubbing 2.1 Vegetation Cutting and grubbing(lb) m 2 25, , Remove cuttings litter and debris to dump(lb) m 3 1, ,200 Sub total B 66,200 8,370 C Rehab Pavements 3.1 Rip up, mix, reshape and re compact m 2 46, , Dispose off unsuitable m 3 2, , Place extra gravel to fill pot holes and raise pavements to designed levels, scarify, reshape with water and re compacted pavement to 95% MDD. m 3 3, ,100 Sub total C 1,381, ,647 D Drainage Provision 4.1 Excavate materials and remove high shoulders (LB) m 3 19, , Shape and provide earth drains (LB) m 15, ,000 37
41 4.3 Install masonry drains for driveways (LB) m , Install 900RCP cross culverts with end treatments m , Install 600RCP side culverts with end treatments m 30 1,800 54, Sub total D 673,200 85,114 E Day Works 5.2 Supervisor Month 6 17, , Surveyor Month 1 25,000 25, Foreman Month 6 15,000 90, Plant Operators Day , Tradesman Day , Mechanic Day , Truck Driver Day , Security Guard Day , Skilled Laborer Day , Unskilled Laborer Day ,000 Sub total E 420,100 53,114 F Machine and Plant 6.1 Concrete Mixer 0.3m 3 Day , Bull dozer NA 6.3 Grader CAT14H Day , , Loader 1.4 m 3 Day ,000 90, Backhoe 12T Day 30 3,000 90,000
42 6.6 Tipper Truck 8 m 3 Day ,500 75, Water Cart Day 30 1,500 45, Vibrating Roller Day 20 4,800 96,000 1 The unit costs for these item were derived from 2008 Basic Cost Data for Solomon islands adjusted for inflation (SIRIP) Sub total F 556,000 70,296 Total A+B+C+D+E+F 3,346, ,148 Contingencies (15%) 502,028 63,472 Total estimated cost 3,848, ,621 Conversion Rate: $ 1 = SI$
43 40 ATTACHMENT 3 Drawings
44 Example of Cross Section and Drain Design 41
45 Standard Culvert Details 1 42
46 Standard Culvert Details 2 43
47 St. Martin Road Design Plan Ch 00-Ch
48 St. Martin Road Design Plan Ch 700-Ch
49 St. Martin Road Design Plan Ch 1500-Ch
50 47 St. Martin Road Design Plan Ch 2300-Ch
51 St. Martin Road Design Plan Ch 3000-Ch
52 St. Martin Road Design Plan Ch 3750-Ch
53 St. Martin Road Design Plan Ch 4500-Ch
54 St. Martin Road Design Plan Ch 5200-Ch
55 St. Martin Road Design Plan Ch 5900-Ch
56 St. Martin Road Design Plan Ch 6750-Ch
57 St. Martin Road Cross Section Ch 00-Ch
58 St. Martin Road Cross Section Ch 4000-Ch
59 56 ATTACHMENT 4 Aggregate Suppliers
60 57
61 58
H: Road Asset Management Plan February 2015
H: Road Asset Management Plan February 2015 Document Format This plan forms one part of a suite of Asset Management Plans that have been developed: A. Bridges B. Buildings C. Drainage D. Footpath E. Levee
SPECIFICATION FOR CONSTRUCTION OF UNBOUND GRANULAR PAVEMENT LAYERS
TNZ B/02:2005 SPECIFICATION FOR CONSTRUCTION OF UNBOUND 1. SCOPE This specification shall apply to the construction of unbound granular pavement layers. The term pavement layer shall apply to any layer
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
SECTION 3.3 - PAVEMENT DESIGN
SECTION 3.3-3.3.1 GENERAL 3.3.2 SUBSURFACE DRAINAGE 3.3.3 DETERMINATION OF DESIGN TRAFFIC 3.3.4 SUBGRADE EVALUATION 3.3.5 PAVEMENT THICKNESS 3.3.5.1 GRANULAR PAVEMENTS WITH THIN BITUMINOUS SURFACING 3.3.5.2
Safe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
This plan forms one part of a suite of Asset Management Plans that have been developed:
E: D1: Levee Footpath Bank Asset Management Plan March July 2014 2015 This plan forms one part of a suite of Asset Management Plans that have been developed: A. Bridges B. Buildings C. Drainage D. Footpaths
SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE
PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE 311.1 DESCRIPTION: This item shall consist of a cement treated subgrade base course composed of a mixture of local soil, portland
Rural Road Maintenance Handbook Module 16 Rural Road Maintenance Cost Estimate
After fulfilling Module 16, you will be able to: Understand the structure of cost estimating sheets and the steps to establish a cost estimate for rural road maintenance Establish cost estimate Self -
Guidelines for. Permeable Pavement
What is permeable pavement? Guidelines for Permeable Pavement When rainwater falls on conventional pavement, such as concrete, it accumulates and then flows across and off of this impervious surface as
Local Road Assessment and Improvement Drainage Manual
Local Road Assessment and Improvement Drainage Manual Donald Walker, T.I.C. Director, author Lynn Entine, Entine & Associates, editor Susan Kummer, Artifax, design Transportation Information Center University
Township of Enniskillen. Asset Management Plan
Township of Enniskillen Asset Management Plan 2014 1 TABLE OF CONTENTS Page A. Introduction 3 B. State of Local Infrastructure 4 C. Desired Levels of Service 7 D. Asset Management Strategy 8 E. Financing
PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE
REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0
INDEX 03010-1 DESCRIPTION 2 03010-2 MATERIALS 2 03010-3 APPROVAL OF SUBBASE COURSE 3 03010-4 CONSTRUCTION 4 03010-5 MEASUREMENT 6 03010-6 PAYMENT 6
03010_Dec22_2009.pdf Page 1 of 5 INDEX Page 03010-1 DESCRIPTION 2 03010-2 MATERIALS 2 03010-3 APPROVAL OF SUBBASE COURSE 3 03010-4 CONSTRUCTION 4 03010-5 MEASUREMENT 6 03010-6 PAYMENT 6 03010_Dec22_2009.pdf
ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT
ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT 1. BACKGROUND There has been an increasing awareness of design features, which produce poor whole-of-life costs. These poor whole-of-life costs manifest
CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS
December 2014 CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Construction Specifications...
Republic of Zambia Ministry of Works and Supply Roads Department Labor-based Routine Maintenance Contract Agreement. C. Kalangwa - Box 33545, Lusaka
August 2000 1) Parties to the Agreement Republic of Zambia Ministry of Works and Supply Roads Department Labor-based Routine Maintenance Contract Agreement 1.1 The Employer: The Roads Training School for
APPENDIX B. I. Background Information
APPENDIX B GUIDELINES FOR IDENTIFYING AND REPAIRING LOCALIZED AREAS OF DISTRESS IN AC PAVEMENTS PRIOR TO CAPITAL PREVENTIVE MAINTENANCE OR REHABILITATION REPAIRS I. Background Information A. AC Pavement
Engineering Policy 146. Severe Weather Management Plans
Engineering Policy 146 Severe Weather Management Plans January 2014 Contents Engineering Policy... 1 1 Policy statement... 1 2 Applicability... 1 3 Context... 1 4 Objectives and benefits... 1 5 Consultation...
SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
SECTION 31 20 00 EARTH MOVING
SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to
Pavement Asset Management Guidance Section 5.3: Condition Surveying and Rating - Drainage
Pavement Asset Management Guidance Section 5.3: Condition Surveying and Rating - Drainage December 2014 Document Information Title Author Description Pavement Asset Management Guidance, Section 5.3: Condition
Permeable Pavement Operation & Maintanence Guide
Permeable Pavement Operation & Maintanence Guide Permeable pavement at Olympic Park, Waitakere Final Construction result What are permeable pavements? Permeable pavements are hard surface paving systems
How To Improve Safety
Collision Diagrams Collision diagrams are used to display and identify similar accident patterns. They provide information on the type and number of accidents; including conditions such as time of day,
Division 2 Section 32 14 13.19 Section 02795
Note: The text must be edited to suit specific project requirements. It should be reviewed by a qualified civil or geotechnical engineer, or landscape architect familiar with the site conditions. Edit
Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
4-02 Gravel Base. 4-04 Ballast and Crushed Surfacing
Chapter 4 Bases 4-02 Gravel Base GEN 4-02.1 General Instructions Gravel Base is typically used in the construction of the roadway section and provides support for the pavement. For the pavement to provide
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.
Page 1 Revised 3/2/10 See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway. For New/Reconstruction projects: The cross slope of the driving lanes range from 1.5% to
3. QUALITY ASSURANCE REQUIREMENTS
3. QUALITY ASSURANCE REQUIREMENTS 3.1 General This section covers the Kaipara District Council requirements for monitoring and testing of physical asset construction to ensure that the final asset delivered
asphalt applications Construction and surfacing of footways and cycleways using asphalt mpa asphalt Asphalt Information Service
asphalt applications 11 Construction and surfacing of footways and cycleways using asphalt Asphalt Information Service mpa asphalt November 2009 Mineral Products Association Introduction The main use of
ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS
ENGINEERING DESIGN GUIDELINES for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS City of Birmingham Department of Planning, Engineering and Permits Engineering Division Office of the City Engineer 2008 TABLE
HIGHWAYS DEPARTMENT GUIDANCE NOTES ON ROAD SURFACE REQUIREMENTS FOR EXPRESSWAYS AND HIGH SPEED ROADS
HIGHWAYS DEPARTMENT GUIDANCE NOTES ON ROAD SURFACE REQUIREMENTS FOR EXPRESSWAYS AND HIGH SPEED ROADS Research & Development Division RD/GN/032 June 2007 1. Purpose ROAD SURFACE REQUIREMENTS FOR EXPRESSWAYS
Emergency Spillways (Sediment basins)
Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]
Riprap-lined Swale (RS)
Riprap-lined Swale (RS) Practice Description A riprap-lined swale is a natural or constructed channel with an erosion-resistant rock lining designed to carry concentrated runoff to a stable outlet. This
TRAFFIC MANAGEMENT PLAN
TRAFFIC MANAGEMENT PLAN For: The construction and operation of a Photovoltaic (PV) Facility in Dabenoris, South Africa Prepared for: Alternative Energy Solutions (Pty) Ltd PO Box 4939 Tygervalley, South
SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)
SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795) Note: This guide specification for U.S. applications describes construction of permeable interlocking concrete
CID STREET INFRASTRUCTURE ASSESSMENT
ABSTRACT An evaluation of the street infrastructure in Foxberry Estates Phase 1, including pavement condition, verification of construction techniques, and subgrade quality. Recommendations and costs for
Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
ROADING ASSET MANAGEMENT PLAN
ROADING ASSET MANAGEMENT PLAN 1 EXECUTIVE SUMMARY 1.1 Overview This Roading Asset Management Plan (RAMP) follows the format recommended by the National Asset Management Steering Group (NAMS) and is largely
CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT
Page 1 CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT CIVIC CENTRE 2141 MAJOR MACKENZIE DRIVE MAPLE ONTARIO L6A 1T1 905-832-2281 Page 2 SECTION 1 - GENERAL OBJECTIVES To provide
Section 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
Chapter 5: Drainage, Ditches, and Culverts
Chapter 5: Drainage, Ditches, and Culverts chapter contents Characteristics of Good Drainage 82 Elements of Good Surface Drainage 82 Crown 82 Shoulders 82 Slope 82 Ditches 83 Culverts 83 Inlets 83 Optimal
Cost components. Why estimate? You may ask; why do we need estimates? Estimating can help to: Total project costs. Profit added FINAL BID
Estimating costs for infrastructure projects is a very complex task which requires a lot of experience. It is important that you understand at least the principles of costing. Why estimate? You may ask;
Traffic Management Issue 1.0 Revision: v2 October 2014
Disclaimer IMPORTANT: The information in this guide is of a general nature, and should not be relied upon as individual professional advice. If necessary, legal advice should be obtained from a legal practitioner
RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.
RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover
Outlet stabilization structure
Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural
Road Maintenance Techniques
COLD CHON (GALWAY) LTD Cold Chon Road Maintenance Techniques Jim Campbell, Chief Engineer, Cold Chon www.coldchon.ie INTRODUCTION The maintenance of roads involves the co-ordination of a wide range of
Chapter Forty-seven. RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL
Chapter Forty-seven RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL Illinois RURAL TWO-LANE/MULTILANE STATE HIGHWAYS December 2009 2 Illinois
Permeable Pavement Construction Guide
Permeable Pavement Construction Guide Permeable pavement at Olympic Park, Waitakere Final Construction result What are permeable pavements? Permeable pavements are hard surface paving systems that reduce
TRAFFIC VOLUME AND ACCIDENT STUDIES ON NH-22 BETWEEN SOLAN AND SHIMLA, INDIA
TRAFFIC VOLUME AND ACCIDENT STUDIES ON NH-22 BETWEEN SOLAN AND SHIMLA, INDIA Rajiv Ganguly, PhD Ashok Kumar Gupta, PhD Mudit Mishra, M.Tech Department of Civil Engineering, Jaypee University of Information
Property Care White Papers. Site Drainage: Monitor and Maintain
Monitor and Maintain Site Drainage Good site drainage is an important part of keeping water issues from affecting the building. The upkeep of existing systems should be an important part of any maintenance
AUSTRALIAN PAVING CENTRE
AUSTRALIAN PAVING CENTRE The Concept 02 The concept of Ecopave permeable paving is already well established in many countries where development threatens already over-stretched drainage and river systems.
OHIO ASPHALT PAVING CONFERENCE
OHIO ASPHALT PAVING CONFERENCE 38 th Annual Conference Wednesday, 2/6/2013 Fawcett Center Campus of The Ohio State University 2400 Olentangy River Road Columbus, Ohio 43210 REHAB STRATEGIES FOR LOCAL
DESCRIPTION OF WORK:
DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works
SE-10 STORM DRAIN INLET PROTECTION. Objectives
STORM DRAIN INLET PROTECTION SE-10 Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Waste and Materials Management -
Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010
Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010 Background What are permeable interlocking concrete pavements (PICP)?
Porous Pavement Alternatives Cost Analysis
Porous Pavement Alternatives Cost Analysis Prepared by Century West Engineering for Metro This cost analysis compares the construction costs of six different types of pavement for three different scenarios.
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown
9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES. Hunter Underground Systems
9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES Hunter Underground Systems 9.01 General 9.02 Surface water Drainage 9.03 Groundwater Drainage 9.04 Dispersal of Septic Tank Effluent 9.01 The use of
STORM DRAINS CHAPTER 7
CHAPTER 7 Chapter 7 - Storm Drains A storm drain is a drainage system that conveys water or stormwater, consisting of two or more pipes in a series connected by one or more structures. Storm drains collect
Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
GUIDE TO SETTLEMENT OF CANTERBURY FLAT LAND CLAIMS
GUIDE TO SETTLEMENT OF CANTERBURY FLAT LAND CLAIMS April 2013 i Introduction This guide focuses on repair methods for some of the types of land damage that occurred on flat residential land as a result
Exhibit A Scope of Work
Exhibit A Scope of Work The agreement for S.P. 3116-142 (T.H. 169-Cross Range Expressway) includes final design plans for a 1.55 mile length of a 2 lane to 4 lane expansion project located 0.66 miles SW
SUSTAINABLE URBAN DRAINAGE SYSTEMS
overflow can lead into a permeable conveyance system to increase further the benefit and reduce the need for pipe systems. Pollutant removal rates have been shown to be high, with some pollutants being
PERMEABLE INTERLOCKING CONCRETE PAVEMENT
[NOTE TO SPECIFICATION WRITER: This guide specification for the use of permeable interlocking concrete pavers for pedestrian and vehicular traffic application was developed based on the use of an open-graded
How To Manage The County Of Simcoe'S Infrastructure
Asset Management Plan Asset Management Plan Table of Contents 1.0 Executive Summary... 2 2.0 Introduction... 4 3.0 State of County of Simcoe s Infrastructure... 7 4.0 Levels of Service... 14 5.0 Asset
Road Rehabilitation and Reconstruction Using AutoCAD Civil 3D
Road Rehabilitation and Reconstruction Using AutoCAD Civil 3D Contents Introduction... 3 Introduction to Corridor Targets... 3 Surface Targets... 4 Width and Offset Targets... 5 Elevation or Slope Targets...
16. ASSET MANAGEMENT POLICY
16. ASSET MANAGEMENT POLICY Asset Management Policy Document No.: WT-HRM-16.00 Approved By: Council Issue No.: 1.00 Approved On: 10 June 2014 Responsibility: Infrastructure Services Department Review Date:
ROAD MANAGEMENT PLAN
ROAD MANAGEMENT PLAN Document Date Description Authorised By Approved Original 23/11/04 Version 1.0 Council Report Council Revision 1 02/06/09 Updated links, adding walking tracks, Force Majeure clause,
Application by National Grid Gas plc for the River Humber Gas Pipeline replacement (the application)
Application by National Grid Gas plc for the River Humber Gas Pipeline replacement (the application) Examining Authority s (ExA) Record of Unaccompanied Inspection of Sites to Which the Application or
Traffic volumes adopted for pavement designs are based on the parameters contained in Section 7 of this report.
11. Pavements 11.1 Pavement design Preliminary pavement designs have been developed for the highway travel lanes (through carriageways), the inner and outer shoulders, on and off ramps and service roads.
There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.
Part 1926 Subpart P Introduction The Occupational Safety and Health Administration (OSHA) issued its first Excavation and Trenching Standard in 1971 to protect workers from excavation hazards. Since then,
Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS
TABLE OF CONTENTS 2.18 CONCRETE AND/OR CORRUGATED STEEL STORM SEWER... 1 2.18.1 GENERAL... 1 2.18.2 MATERIALS... 1 2.18.2.1 Storm Sewer Pipe... 1 2.18.2.2 Cement Mortar... 1 2.18.2.3 Granular Materials...
CLASS II BASE COURSE - Section 302
CLASS II BASE COURSE - Section 302 Class II Base Courses are similar to Class I Base Courses, with the exception that placement on a subgrade layer built in accordance with Specification Section 305 is
Building Your Interlocking Concrete Pavement to Last a Lifetime
Building Your Interlocking Concrete Pavement to Last a Lifetime A Guide for Consumers Contents Building Your Interlocking Concrete Pavement to Last a Lifetime.... 3 What Does Installation Involve?....
R E S I D E N T I A L H O U S I N G
HL 252 Rev. April 1997 R E S I D E N T I A L H O U S I N G CONTROLLING EXTERNALWATER PROBLEMS FOR RESIDENCES I II III IV V Lot Drainage Gutter Water Management Foundation Waterproofing Floor Slab Waterproofing
DIVISION 300 BASES SECTION 304 AGGREGATE BASE COURSE DESCRIPTION MATERIALS CONSTRUCTION REQUIREMENTS
304.06 DIVISION 300 BASES SECTION 304 AGGREGATE BASE COURSE DESCRIPTION 304.01 This work consists of furnishing and placing one or more courses of aggregate and additives, if required, on a prepared subgrade.
CODE OF PRACTICE - VOLUME TWO - TRAIN SYSTEM [CP2] TRANSADELAIDE INFRASTRUCTURE SERVICES. Issue: 2 Date: 26/09/08 Page: 1 of 21
Issue: 2 Date: 26/09/08 Page: 1 of 21 TRACK AND CIVIL INFRASTRUCTURE CODE OF PRACTICE VOLUME TWO - TRAIN SYSTEM [CP2] DRAINAGE 2004 No part of this document may be reproduced without prior written consent
Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY
Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY Policy: This policy will replace all previous policies regarding the selection of pipe material for cross drains, drive pipe, drop pipe, storm
Type of Sewer Systems. Solomon Seyoum
Type of Sewer Systems Solomon Seyoum 0 Learning objectives Upon completion of this lecture, the participants will be able to differentiate between types of sewer systems and discuss different aspects of
CITY UTILITIES DESIGN STANDARDS MANUAL
CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.
1.0 INDEX TO SHEETS URGENT STORM DAMAGE REPAIR AVON PARK AIR FORCE RANGE LOCATION MAP LEGEND LOCATION MAP
5 INDEX TO SHEETS. NOTES AND TYPICAL SECTIONS. H. R. SMITH RD.CULVERT.3 0/5 END BARRIER ACCESS ROAD REPAIR. KISSIMMEE RD. AT MORGAN HOLE CR. ROAD REPAIR.5 RANGE INFRASTRUCTURE REPAIR N 0 000' 3 0,000'
Storm Drain Inlet Protection
Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective
www.nams.au.com National Asset Management Strategy Australia
DEVELOPMENT OF A ROAD ASSET REGISTER USING DIGITAL VIDEO TECHNOLOGY DUNGOG SHIRE COUNCIL Matt Ryeland, mailto:[email protected] Senior Technical Officer, Management Services. Cardno Terry Wilson,
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection
Prattsville Berm Removal Project. 1.0 Project Location
Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed
Government of the People s Republic of Bangladesh Ministry of Communications Roads and Highways Department PAVEMENT INVENTORY SURVEY MANUAL
Government of the People s Republic of Bangladesh Ministry of Communications PAVEMENT INVENTORY SURVEY MANUAL MAY 2005 TABLE OF CONTENTS 1. INTRODUCTION... 3 2. ROAD NUMBERING... 4 2.1 OBJECTIVE...4 2.2
Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES
Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 1 PLAN SUBGRADES Geotechnical Bulletin GB1 was jointly developed by the Offices
BEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project.
Smart Transportation Smart Transportation is a key concept for the Paoli Roadway Improvement Project. PennDOT s Smart Transportation Guidebook (2008) outlines a comprehensive approach to transportation
Storm Drainage Systems 11.9-1
Storm Drainage Systems 11.9-1 11.9 Gutter Flow Calculations 11.9.1 Introduction Gutter flow calculations are necessary in order to relate the quantity of flow (Q) in the curbed channel to the spread of
Moyne Shire ROAD MANAGEMENT PLAN VERSION 3
Moyne Shire ROAD MANAGEMENT PLAN VERSION 3 Pursuant to Section 52 of the Road Management Act 2004 this Plan was adopted by Council on the 23 July 2013 DOCUMENT CONTROL SHEET Document: Road Management Plan
Table 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection