Reliability Growth Planning with PM2
|
|
|
- Dorthy Russell
- 9 years ago
- Views:
Transcription
1 FOR OFFICIAL USE ONLY FOR OFFICIAL USE ONLY Reliability Growth Planning with PM2 Shawn Brady, AMSAA Martin Wayne, AMSAA Karen O Brien, ATEC 40 Years of
2 Agenda Terminology Test-fix-test reliability growth process Relationship between reliability demonstration and reliability growth planning Planning curve development Risk assessments for planning curve Model demo 2
3 Terminology Failure Mode The manner by which a failure is observed Generally describes the way the failure occurs and its impact on equipment operation Corrective Actions (fixes) Changes to the design, manufacturing process, operating or maintenance procedures for the purpose of improving reliability Repair The refurbishment or replacement of a failed part with an identical unit in order to restore the system to be operationally capable 3
4 Reliability Growth Process (It s more than just developing a curve) Design for Reliability (DfR) Component-level Testing Physics of Failure (PoF) Results in initial system design Developmental Testing (DT) Enter DT with Initial MTBF (M I ) Discover Failure Modes Grow to Goal MTBF in DT (M G ) Failure Mode Analysis & Corrective Action Implementation Root Cause Analysis Reject Development of Corrective Actions Failure Prevention and Review Board Corrective Action Review and Approval Assignment of Fix Effectiveness Factors Accept Demonstration Test (IOT) Fixed Configuration Test to Demonstrate Req t w/ Confidence Enter with Goal MTBF in IOT (M R+ ) Verification of Corrective Actions Corrective Action Implementation to Prototypes 4
5 Reliability vs. Time Requirement Reliability DfR DT & IOT Production & Sustainment Materiel Solution Analysis A B C Engineering & Technology Manufacturing Development Development Time Production & Deployment Operations & Support Pre-Systems Acquisition Systems Acquisition Sustainment DfR can provide the most reliability improvement in the shortest time 5
6 Importance of Rel. Growth Planning Establish a realistic RGPC that provides interim reliability goals and serves as a baseline against which reliability assessments can be compared Determine the extent of DfR activities that need to occur prior to system-level DT Establish a test schedule and corrective action strategy that optimizes test resources Obtain necessary resources (test articles, facilities, support equipment, test personnel, data collectors, analysts, engineers, etc.) Identify and mitigate potential risks in order to increase the likelihood of passing the demonstration test Estimate O&S costs 6
7 MTBF 40 Years of Relationship Between Planning and Demonstration Idealized Reliability Growth Planning Curve (RGPC) Demonstration Test DT M G M I IOT Planning: Establish goals for surfacing failure modes and implementing corrective actions to allow the system to grow from an initial reliability (M I ) to a goal reliability (M G ) Multiple test phases followed by Corrective Action Periods (CAPs), evolving configuration, stressed per OMS/MP Demonstration: Test Hours Demonstrate the reliability requirement with high statistical confidence Fixed length, fixed configuration, stressed per OMS/MP 7
8 Planning Process Step 1: Determine a DT reliability goal (M G ) that provides a high probability of demonstrating the requirement in IOT Step 2: Develop a feasible reliability growth plan that uses management metrics and DT test time to achieve M G PM2 uses a backwards planning approach 8
9 Planning Process Step 1: Determine a DT reliability goal (M G ) that provides a high probability of demonstrating the requirement in IOT Step 2: Develop a feasible reliability growth plan that uses management metrics and DT test time to achieve MG 9
10 Risks Associated with Reliability Demonstration Testing Before developing a reliability growth plan, program management needs to establish how the reliability requirements will be demonstrated Typically, programs conduct a demonstration test (e.g. IOT) to allow the Government to determine if the system meets the MTBF requirement, M R IOT should be designed to mitigate the risk of making a wrong decision Decision at end of Demonstration Test System s True MTBF At or Above M R Below M R Pass Probability of Acceptance (P(A)) Consumer s (Government s) Risk Fail Producer s (Contractor s) Risk Confidence Use OC Curve to mitigate risks = Right Decision = Wrong Decision 10
11 Determine Test Duration & Max Failures MTBF Requirement (M R ): 148 hr MTBF to be demonstrated with 80% confidence What is confidence? Confidence = 1 Consumer s Risk Consumer s (Govt s) Risk = probability that Govt accepts a system that has a true MTBF < M R Consumer s Risk is mitigated by designing an IOT that utilizes a LCB to demonstrate M R Question: What test durations and max number of failures allow M R to be demonstrated with 80% confidence? Answer: For a desired IOT Duration, find the maximum number of allowable failures, c, where c is the largest positive integer k such that IOT Duration IOT Duration k M exp R M R i0 i! i Consumer' s Risk For a 2,400 hour IOT, the maximum number of allowable failures is i0 2, i 2,400 exp 148 i! 0.20 (Equation 1) Failures Equation Results
12 Determine MTBF Goal in IOT (M R+ ) Question: For a 2,400 hour test with a max of 12 failures, what should the MTBF goal in IOT (M R+ ) be? The answer depends on the desired probability of acceptance What is Probability of Acceptance? P(A) = 1 Producer's Risk The Producer s (Contractor s) Risk = probability that Gov t rejects a system that has a true MTBF M R Producer s Risk is mitigated using OC Curve to determine MTBF Goal when entering IOT (known as M R+ ) The OC Curve is the P(A) plotted as a function of the system s MTBF, M Answer: Plot the OC Curve for the selected IOT Duration and maximum number of allowable failures, c: c i0 IOT Duration M i IOT Duration exp M i! (Equation 2) For a desired P(A) of 70%, determine the M that corresponds with 70%; this is the system s M R + 12 i0 2, i 2,400 exp 221 i! 0.70 Therefore, in order to have a 70% P(A) in IOT, the system s M R + must be at least 221 MTBF M + R Equation Results OC = Operating Characteristic 12
13 Probability of Acceptance in IOT 40 Years of Solution Using OC Curve M R = 148 Consumer s Risk = 0.20 Producer s Risk = 0.30 IOT Duration = 2,400 Max Failures = OC Curve Test Duration = 2400 Max Failures = P(A) Consumer s Risk OC Curve tells us that for a 2,400 hr IOT with a max of 12 failures, the system must enter IOT with a true MTBF of 221 in order to have a 70% prob of demonstrating M R with 80% confidence M R M R + True MTBF If the system enters IOT with an M R+ of 190 (instead of 221), the P(A) is reduced to Even though 190 > 148, the system would fail the test half of the time. Passing the test at the specified confidence level would be like flipping a coin! 13
14 MTBF 40 Years of Building the RGPC PM2-Continuous Reliability Growth Planning Curve Requirement IOT IOT Goal = Requirement = Test Time 14
15 Determine Goal MTBF in DT (M G ) 1) Determine Goal MTBF in IOT (M R+ ) using OC Curve M R + = 221 hours from previous chart 2) Determine expected degradation factor to account for drop in reliability when moving from DT environment to IOT environment Should be based on what can realistically be expected 10% for this example 3) Solve for DT Goal by applying degradation factor to M R + M G M R 1- Degradation
16 MTBF 40 Years of Building the RGPC PM2-Continuous Reliability Growth Planning Curve Requirement Hypothetical Last Step IOT DT Goal = 246 IOT Goal = Requirement = Test Time 16
17 Planning Process Step 1: Determine a DT reliability goal (M G ) that provides a high probability of demonstrating the requirement in IOT Step 2: Develop a feasible reliability growth plan that uses management metrics and DT test time to achieve M G 17
18 Determine Management Strategy (MS) & Fix Effectiveness Factor (FEF) Should be chosen based on what can realistically be achieved Based on past performance, type of system, etc. MS is the proportion of total failure intensity that is addressed with corrective actions Let MS = 0.95 for this example FEF is the fraction reduction in the failure rate for a failure mode that has been addressed via corrective action Average FEF (μ d ) used for planning Let μ d = 0.70 for this example 18
19 MTBF Growth Potential (1 of 2) System Failure Intensity After Testing (at time t) l A : contribution from A-modes (1m d ) [l B h(t)]: contribution from observed B-modes remaining after corrective actions m d [l B h(t)]: contribution from observed B-modes removed after corrective actions h(t): contribution from unseen B-modes System Failure Intensity at Growth Potential l A : contribution from A-modes (1m d ) l B : contribution from observed B- modes remaining after corrective actions m d (l B ): contribution from observed B- modes removed after corrective actions The System Growth Potential failure intensity (ρ GP ) is the rate of occurrence of failures that would occur if all potential B-modes are mitigated Contribution from unseen B-modes is completely removed For k failure modes, can represent as l (1 d ) l k GP A i i i1 19
20 MTBF Growth Potential (2 of 2) M GP is the upper bound on the MTBF that can be achieved if ALL failure modes in the system that can be addressed are corrected with the specified FEF, μ d M GP is a function of M I, MS, and μ d M GP M 1- MS I m d Ratio of Goal MTBF in DT (M G ) to M GP should be less than or equal to 0.80 Ratio M M G GP
21 Determine Initial MTBF (M I ) M I is the system s initial MTBF when entering DT DfR activities should result in a high M I M I should be chosen based on what can realistically be achieved M I can be obtained 2 ways 1) Estimate M I based on insights from reliability models, previous test results, M I for similar systems, etc. 2) Establish a lower bound for M I using the planning parameters (MS and μ d ) and the desired M G /M GP Ratio M I ( 1-MS m ) d MG Ratio M I ( ) M I
22 MTBF 40 Years of Building the RGPC PM2-Continuous Reliability Growth Planning Curve Requirement Hypothetical Last Step IOT DT Goal = 246 IOT Goal = Requirement = M I = M GP ( ) 307 Test Time Ratio
23 Test Schedule 4 Developmental Test (DT) events totaling 5,306 hours Customer Test: 650 hrs DT: 1,280 hrs LUT: 2,400 hrs DT2: 976 hrs Corrective Action Periods (CAPs) after each event 2,400 hour Initial Operational Test (IOT) 23
24 Corrective Action Periods and Lag Time Growth cannot occur without corrective actions, which either occur during test or during CAPs CAPs are calendar periods where testing stops and CAs are implemented Important for maintaining configuration control For example, assume the following 12 month test scenario: 8 month test phase 100 test hours per month 4 month CAP after test phase 6 month delay for incorporating CAs into CAP 1 Failure modes surfaced in the final 2 months of the test phase cannot be addressed until the following CAP. Lag Time = 6 month Delay 4 month CAP = 2 months = 200 hours Only failures surfaced in the first 6 months will be addressed in CAP 1 Cum. Months Cum. Hours DT Test Phase 1 (8 months) CAP 1 (4 months) Reduced Test Phase Lag Time 24
25 MTBF 40 Years of Building the RGPC PM2-Continuous Reliability Growth Planning Curve Requirement Customer Test DT1 LUT DT2 Hypothetical Last Step IOT Idealized Curve CAP CAP CAP2 Requirement = CAP Test Time 25
26 Continuous Reliability Growth Planning Curve Risk Assessment (1/2) Category Low Risk Medium Risk High Risk MTBF Goal (DT) MTBF Grow thpotential < 70% 70-80% > 80% IOT&E Producer s Risk 20% % > 30% IOT&E Consumer s Risk 20% % > 30% Management Strategy < 90% 90-96% > 96% Fix Effectiveness Factor 70% % > 80% MTBF Goal (DT) MTBF Initial Time to Incorporate and Validate Fixes in IOT&E Units Prior to Test < > 3 Adequate time and resources to have fixes implemented & verified with testing or strong engineering analysis Time and resources for almost all fixes to be implemented & most verified w/ testing or strong engineering analysis Many fixes not in place by IOT&E and limited fix verification + indicates strictly greater than 26
27 Continuous Reliability Growth Planning Curve Risk Assessment (2/2) Category Low Risk Medium Risk High Risk Corrective Action Periods (CAPs) 5 or more CAPs which contain adequate calendar time to implement fixes prior to major milestones 3-4 CAPs but some may not provide adequate calendar time to implement all fixes 1-2 CAPs of limited duration Reliability Increases after CAPs Moderate reliability increases after each CAP result in lower-risk curve that meets goals Some CAPs show large jumps in reliability that may not be realized because of program constraints Majority of reliability growth tied to one or a couple of very large jumps in the reliability growth curve Percent of Initial Problem Mode Failure Intensity Surfaced Growth appears reasonable (i.e. a small number of problem modes surfaced over the growth test do not constitute a large fraction of the initial problem mode failure intensity) Growth appears somewhat inflated in that a small number of the problem modes surfaced constitute a moderately large fraction of the initial problem mode failure intensity Growth appears artificially high with a small number of problem modes comprising a large fraction of the initial problem mode failure intensity 27
28 Conclusions Reliability growth planning curves can be powerful management tools Portray the planned reliability achievement as a function of program resources Serve as a baseline against which demonstrated reliability estimates may be compared Illustrate and quantify the feasibility of the test program in achieving the interim and final reliability goals Curves possess a series of management metrics that may be used to: Assess the effectiveness of potential reliability growth plans Assess the reliability maturity of complex systems as they progress through DT program 28
29 Model Demo 29
30 Backup 30
31 Operating Characteristic (OC) Curve Analysis Set consumer (government) risk a = 1 - confidence = 0.20 for this example Determine maximum number of allowable failures (12 for example) c largest k s.t k i0 T M Dem R i T exp M i! Dem R a, where T M Dem R IOT Test Length, MTBFRequirement Develop probability of acceptance based on allowable failures, requirement, and test time Plot c i0 T M Dem i T exp M i! Dem as functionof M 31
32 PM2 Failure Intensity Initial l A : contribution from A modes After Testing (time t) l A : contribution from A modes (1m d ) [l B h(t)]: observed B mode remainder after fixes l B = h(0) : contribution from B modes Definitions: A mode: No corrective action made B mode: Corrective action made if discovered Planned average fix effectiveness factor: m d Idealized curve for PM2 model based on 1 M ( t) la md lb h t h t t ( t) h(t) : contribution from unseen B modes m d [l B h(t)]: observed B mode portion removed All portions of the system failure intensity are welldefined 1 ( 1 ) ( ) ( ) for [ 0, ) 32
33 Expected # Modes PM2 Planning Metrics Percent λ B Observed l m 1 B ( t) ln( t) t ( t) 1 t Rate of Occurrence of New Modes Mean Time Between Failures h ( t) lb 1 t ( ) ( ) l ( 1 m ) l ( ) M t A d B h t h t 1 PM2 planning metrics can be used to determine feasibility of growth plan 33
34 PM2 Inputs 34
35 PM2 Inputs 35
36 PM2 Inputs & Feasibility Metrics 3 failure modes encompass 37% of the failure intensity 15 failure modes encompass 87% of the failure intensity 36
37 Percent of Initial B-mode Failure Intensity Surfaced 40 Years of Feasibility Metrics Percent of Initial B-mode Failure Intensity Surfaced by Time t θ(t) Curve ,130, ,306, ,730, , Test Time 37
38 Expected Number of B-modes 40 Years of Feasibility Metrics Expected Number of B-modes Surfaced by Time t μ(t) Curve 16 5,306, ,130, ,730, , Test Time 38
39 Risk Assessment Matrix 39
GUIDANCE FOR ASSESSING THE LIKELIHOOD THAT A SYSTEM WILL DEMONSTRATE ITS RELIABILITY REQUIREMENT DURING INITIAL OPERATIONAL TEST.
GUIDANCE FOR ASSESSING THE LIKELIHOOD THAT A SYSTEM WILL DEMONSTRATE ITS RELIABILITY REQUIREMENT DURING INITIAL OPERATIONAL TEST. 1. INTRODUCTION Purpose The purpose of this white paper is to provide guidance
Brillig Systems Making Projects Successful
Metrics for Successful Automation Project Management Most automation engineers spend their days controlling manufacturing processes, but spend little or no time controlling their project schedule and budget.
Pearson Education Limited 2003
156 Activities Activity 9.1 (PP. 357 358) [Project planning exercise] You are required to construct a project plan for the following information system development project. Your objective is to schedule
The Application Readiness Level Metric
The Application Readiness Level Metric NASA Application Readiness Levels (ARLs) The NASA Applied Sciences Program has instituted a nine-step Application Readiness Level (ARL) index to track and manage
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN April 2009 SLAC I 050 07010 002 Risk Management Plan Contents 1.0 INTRODUCTION... 1 1.1 Scope... 1 2.0 MANAGEMENT
Session 4. System Engineering Management. Session Speaker : Dr. Govind R. Kadambi. M S Ramaiah School of Advanced Studies 1
Session 4 System Engineering Management Session Speaker : Dr. Govind R. Kadambi M S Ramaiah School of Advanced Studies 1 Session Objectives To learn and understand the tasks involved in system engineering
Risk Assessment Worksheet and Management Plan
Customer/Project Name: The Basics There are four steps to assessing and managing risks, and effective risk management requires all four of them. 1. Identify the risks 2. Qualify the risks a. Assess each
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
Measurement Information Model
mcgarry02.qxd 9/7/01 1:27 PM Page 13 2 Information Model This chapter describes one of the fundamental measurement concepts of Practical Software, the Information Model. The Information Model provides
Risk Management. Software SIG. Alfred (Al) Florence. The MITRE. February 26, 2013. MITRE Corporation
Risk Management Software SIG MITRE Corporation February 26, 2013 The MITRE Alfred (Al) Florence MITRE Corporation The MITRE Agenda Introduction Risk Management References Contact Information Al Florence
DCMA 14-Point Assessment Metrics
DCMA 14-Point Assessment Metrics The integrity of a CPM schedule is one of the critical factors in improving a project s likelihood of success 1! There is a well-established correlation between the quality,
Your Software Quality is Our Business. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc.
INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc. February 2013 1 Executive Summary Adnet is pleased to provide this white paper, describing our approach to performing
System (of Systems) Acquisition Maturity Models and Management Tools
System (of Systems) Acquisition Maturity Models and Management Tools Brian J. Sauser, Ph.D. Jose Ramirez-Marquez, Ph.D. Stevens Institute of School of Systems and Enterprise Readiness Level (TRL) System
Recognizing and Mitigating Risk in Acquisition Programs
Professional Development Institute May 27 th to May 29 th 2015 Recognizing and Mitigating Risk in Acquisition Programs D e b r a E. H a h n D e b b i e. h a h n @ d a u. m i l 703-805- 2830 1 DoD Risk
NEEDS BASED PLANNING FOR IT DISASTER RECOVERY
The Define/Align/Approve Reference Series NEEDS BASED PLANNING FOR IT DISASTER RECOVERY Disaster recovery planning is essential it s also expensive. That s why every step taken and dollar spent must be
This is the software system proposal document for the <name of the project> project sponsored by <name of sponsor>.
Guide to Preparing the SOFTWARE PROJECT MANAGEMENT PLAN R. Buckley CSc 190 Senior Project Department of Computer Science - College of Engineering and Computer Science California State University, Sacramento
Fundamentals of Measurements
Objective Software Project Measurements Slide 1 Fundamentals of Measurements Educational Objective: To review the fundamentals of software measurement, to illustrate that measurement plays a central role
Security Engineering Best Practices. Arca Systems, Inc. 8229 Boone Blvd., Suite 750 Vienna, VA 22182 703-734-5611 [email protected].
Tutorial: Instructor: Topics: Biography: Security Engineering Best Practices Karen Ferraiolo, Arca Systems, Inc. 8229 Boone Blvd., Suite 750 Vienna, VA 22182 703-734-5611 [email protected] This tutorial
Empire State Building - Project Management and Budget Planning
Your Facilities Master Plan: Building a Better Business Case Presented by Jim Turner Contents Learning Objectives Consider this project A simplified five-step process Develop Objectives Prepare Criteria
PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and
PRODUCTIVITY & GROWTH
Productivity Financial Tools There are a number of financial tools that can be used to measure the financial performance and potential contribution of improvement projects to the productivity of a business.
WORKFORCE COMPOSITION CPR. Verification and Validation Summit 2010
WORKFORCE COMPOSITION CPR PEO IEW&S Organizational Assessment VCSA Brief Date 2010 October 13, 2010 This briefing is UNCLASSIFIED/FOUO PREDECISIONAL LIMITED DISTRIBUTION AS OF: 11 Sep 2010 Verification
Phases, Activities, and Work Products. Object-Oriented Software Development. Project Management. Requirements Gathering
Object-Oriented Software Development What is Object-Oriented Development Object-Oriented vs. Traditional Development An Object-Oriented Development Framework Phases, Activities, and Work Products Phases,
Root Cause Analysis Concepts and Best Practices for IT Problem Managers
Root Cause Analysis Concepts and Best Practices for IT Problem Managers By Mark Hall, Apollo RCA Instructor & Investigator A version of this article was featured in the April 2010 issue of Industrial Engineer
Developing Work Breakdown Structures
Developing Work Breakdown Structures International Cost Estimating & Analysis Association June 2014 Neil F. Albert MCR, LLC [email protected] 703-506-4600 2014 MCR, LLC Distribution prohibited without express
An Introduction to. Metrics. used during. Software Development
An Introduction to Metrics used during Software Development Life Cycle www.softwaretestinggenius.com Page 1 of 10 Define the Metric Objectives You can t control what you can t measure. This is a quote
MATH 140 Lab 4: Probability and the Standard Normal Distribution
MATH 140 Lab 4: Probability and the Standard Normal Distribution Problem 1. Flipping a Coin Problem In this problem, we want to simualte the process of flipping a fair coin 1000 times. Note that the outcomes
B2B Software Technologies Ltd. Service Level Agreement (SLA)
Service Level Agreement (SLA) Overview This document describes a Service Level Agreement (SLA) between Customer and B2B Software Technologies. It outlines the services offered by B2B for NAVISION ADDON
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
A Performance Study of IP and MPLS Traffic Engineering Techniques under Traffic Variations
A Performance Study of IP and MPLS Traffic Engineering Techniques under Traffic Variations Sukrit Dasgupta Department of ECE Drexel University Philadelphia, PA, USA [email protected] Jaudelice C. de
Project management. Objectives. Topics covered. Organizing, planning and scheduling software projects DISCUSSION
Project management 1 Objectives 2 Organizing, planning and scheduling software projects DISCUSSION Project Managers? To introduce software project management and to describe its distinctive characteristics
CHAPTER 7 Software Configuration Management
CHAPTER 7 Software Configuration Management ACRONYMS CCB CM FCA MTBF PCA SCCB SCI SCM SCMP SCR SCSA SEI/CMMI SQA SRS USNRC INTRODUCTION Configuration Control Board Configuration Management Functional Configuration
Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs
HUMAN RESOURCE MANAGEMENT Organizational planning Staff Acquisition Project interfaces such as organizational interfaces, technical interfaces and interpersonal interfaces. Staffing requirements Staffing
Testing Metrics. Introduction
Introduction Why Measure? What to Measure? It is often said that if something cannot be measured, it cannot be managed or improved. There is immense value in measurement, but you should always make sure
The Power of Business Intelligence in the Revenue Cycle
The Power of Business Intelligence in the Revenue Cycle Increasing Cash Flow with Actionable Information John Garcia August 4, 2011 Table of Contents Revenue Cycle Challenges... 3 The Goal of Business
A Framework for Project Metrics
A Framework for Project Metrics Deciding what to measure and how to measure it August 13, 2007 Dr. Gary J. Evans, PMP CVR/IT Consulting LLC www.cvr-it.com Welcome! Focus of this workshop: Project Metrics
Program Management Toolkit Concept and Contents
Program Management Toolkit Concept and Contents Audrey Taub Charlene McMahon 15 Feb 2001 Organization: W063 Project: 01CCG100 Purpose of PM Toolkit The purpose of the this Toolkit is to provide convenient
Effective Software Security Management
Effective Software Security Management choosing the right drivers for applying application security Author: Dharmesh M Mehta [email protected] / [email protected] Table of Contents Abstract... 1
System/Data Requirements Definition Analysis and Design
EXECUTIVE SUMMARY This document provides an overview of the Systems Development Life-Cycle (SDLC) process of the U.S. House of Representatives. The SDLC process consists of seven tailored phases that help
IA Metrics Why And How To Measure Goodness Of Information Assurance
IA Metrics Why And How To Measure Goodness Of Information Assurance Nadya I. Bartol PSM Users Group Conference July 2005 Agenda! IA Metrics Overview! ISO/IEC 21827 (SSE-CMM) Overview! Applying IA metrics
Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman
Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government
Course: 8911B: Installation and Deployment in Microsoft Dynamics CRM 4.0
Course: 8911B: Installation and Deployment in Microsoft Dynamics CRM 4.0 Description: This two-day instructor-led course provides students with the tools to install and configure Microsoft The course focuses
Project Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft
PROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
// Taming an Unruly Schedule Using the 14-Point Schedule Assessment
// Taming an Unruly Schedule Using the 14-Point Schedule Assessment Dr. Dan Patterson, PMP CEO & President, Acumen February 2010 www.projectacumen.com Table of Contents Introduction... 3 The 14-Point Assessment...
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
Supporting Workflow Overview. CSC532 Fall06
Supporting Workflow Overview CSC532 Fall06 Objectives: Supporting Workflows Define the supporting workflows Understand how to apply the supporting workflows Understand the activities necessary to configure
The purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision of resources to support service requirements.
CAPACITY AND AVAILABILITY MANAGEMENT A Project Management Process Area at Maturity Level 3 Purpose The purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision
( ) = ( ) = {,,, } β ( ), < 1 ( ) + ( ) = ( ) + ( )
{ } ( ) = ( ) = {,,, } ( ) β ( ), < 1 ( ) + ( ) = ( ) + ( ) max, ( ) [ ( )] + ( ) [ ( )], [ ( )] [ ( )] = =, ( ) = ( ) = 0 ( ) = ( ) ( ) ( ) =, ( ), ( ) =, ( ), ( ). ln ( ) = ln ( ). + 1 ( ) = ( ) Ω[ (
Make Better Decisions with Optimization
ABSTRACT Paper SAS1785-2015 Make Better Decisions with Optimization David R. Duling, SAS Institute Inc. Automated decision making systems are now found everywhere, from your bank to your government to
Supplier Risk Management. Presented By Bill Gibson, DCMA HQ Date: May 2001
Supplier Risk Management Presented By Bill Gibson, DCMA Q Date: May 2001 Agenda Introduction One Book Policy Structure Policy Overview Risk Assessment and Management Program (RAMP) Summary Introduction
Availability and Cost Monitoring in Datacenters. Using Mean Cumulative Functions
Availability and Cost Monitoring in Datacenters Using Mean Cumulative Functions David Trindade, Swami Nathan Sun Microsystems Inc. {david.trindade,swami.nathan} @sun.com Keywords : Availability analysis,
Cost Management. How Much Will This Project Cost?
Cost Management How Much Will This Project Cost? Moderator Janelle Abaoag Project Insight Marketing, Public Relations [email protected] www.projectinsight.net All participants will be on
Systems Analysis and Design
Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis
Project Management Challenges in Software Development
Abstract Research Journal of Management Sciences ISSN 2319 1171 Project Management Challenges in Software Development Uma Sankar S.S. 1 and R. Jubi 2 1 Research and Development Centre, Bharathiar University,
Key Aspects of Configuration Management. NOvA Working Group Meeting 1
Key Aspects of Configuration Management NOvA Working Group Meeting 1 Excerpts from ANSI/EIA-649 on Configuration Management The purpose and benefits of configuration management include the following: Product
Vamshi K. Katukoori Graduate Student: NAME University Of New Orleans. Standardizing Availability Definition
Vamshi K. Katukoori Graduate Student: NAME University Of New Orleans Standardizing Availability Definition Table of Contents 1.) Foreword 2.) Availability 3.) Introduction 4.) Availability Classification
PMO Metrics Recommendations
Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project
Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:
Project Audit & Review Checklist The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Relevance (at this time) Theory & Practice (How relevant is this attribute
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Earned Value Management Systems Application Guide
National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide May 4, 2011 Revision 1* National Defense Industrial Association (NDIA) 2111
Point Biserial Correlation Tests
Chapter 807 Point Biserial Correlation Tests Introduction The point biserial correlation coefficient (ρ in this chapter) is the product-moment correlation calculated between a continuous random variable
Schedule analytics tool
Schedule analytics tool As capital project spend increases and aggressive deadlines are built into project schedules, the reliance on accurate, transparent and meaningful schedule practices is growing.
SECURITY METRICS: MEASUREMENTS TO SUPPORT THE CONTINUED DEVELOPMENT OF INFORMATION SECURITY TECHNOLOGY
SECURITY METRICS: MEASUREMENTS TO SUPPORT THE CONTINUED DEVELOPMENT OF INFORMATION SECURITY TECHNOLOGY Shirley Radack, Editor Computer Security Division Information Technology Laboratory National Institute
CDC UNIFIED PROCESS JOB AID
CDC UNIFIED PROCESS JOB AID Independent Verification & Validation Activities Document Purpose This Job Aid is a brief document listing the items to be noted, checked, remembered, and delivered when completing
How To Manage Project Management
CS/SWE 321 Sections -001 & -003 Software Project Management Copyright 2014 Hassan Gomaa All rights reserved. No part of this document may be reproduced in any form or by any means, without the prior written
Project Risks. Risk Management. Characteristics of Risks. Why Software Development has Risks? Uncertainty Loss
Project Risks Risk Management What can go wrong? What is the likelihood? What will the damage be? What can we do about it? M8034 @ Peter Lo 2006 1 M8034 @ Peter Lo 2006 2 Characteristics of Risks Uncertainty
ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES
1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through
REDUCING UNCERTAINTY IN SOLAR ENERGY ESTIMATES
REDUCING UNCERTAINTY IN SOLAR ENERGY ESTIMATES Mitigating Energy Risk through On-Site Monitoring Marie Schnitzer, Vice President of Consulting Services Christopher Thuman, Senior Meteorologist Peter Johnson,
Application Management Services (AMS)
Contents 1. AMS : An Overview 2. AMS : Models 3. Delivery Organization 4. Processes & Tools 5. Transition Methodology 6. Pricing Application Management Services (AMS) Enterprise Application Services Capability
Mastering Microsoft Project 2010
Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project
SYSTEMS ENGINEERING FUNDAMENTALS
Introduction Systems Engineering Fundamentals SYSTEMS ENGINEERING FUNDAMENTALS January 2001 SUPPLEMENTARY TEXT PREPARED BY THE DEFENSE ACQUISITION UNIVERSITY PRESS FORT BELVOIR, VIRGINIA 22060-5565 i Systems
Iterative Project Management 1
Iterative Project Management Module 2 Objectives Understand issues for Project Managers (PM) who use iterative development by: Learning how the PM monitors and steers an iterative project towards success.
Microsoft Project Professional
Microsoft Project Professional A 100% practical workshop to master Microsoft Project, training the main features of the application for project management. Objective Insight into the functions required
IMCPM04 Project Scheduling and Cost Control. Course Outline
IMCPM04 Project Scheduling and Cost Control Course Outline January 2012 Project Scheduling and Cost Control Course Aim Project Scheduling and Cost Control is a five-day (5 day) course which provides participants
MICROSOFT PROJECT 2013 INTRODUCTION
Phone:08092595489 / 08168510709 Email: [email protected] MICROSOFT PROJECT 2013 INTRODUCTION Generate a group quote today or register now for the next public course date COURSE LENGTH: 1.0 DAYS
CSTE Mock Test - Part I - Questions Along with Answers
Note: This material is for Evaluators reference only. Caters to answers of CSTE Mock Test - Part I paper. 1. A branch is (Ans: d) a. An unconditional transfer of control from any statement to any other
Systems Engineering Complexity & Project Management
Systems Engineering Complexity & Project Management Bob Ferguson, PMP NDIA: CMMI Technology Conference November 2007 Outline A conversation Defining complexity and its effects on projects Research into
Two Correlated Proportions (McNemar Test)
Chapter 50 Two Correlated Proportions (Mcemar Test) Introduction This procedure computes confidence intervals and hypothesis tests for the comparison of the marginal frequencies of two factors (each with
Risk and return (1) Class 9 Financial Management, 15.414
Risk and return (1) Class 9 Financial Management, 15.414 Today Risk and return Statistics review Introduction to stock price behavior Reading Brealey and Myers, Chapter 7, p. 153 165 Road map Part 1. Valuation
Truly Managing a Project and Keeping Sane While Wrestling Elegantly With PMBOK, Scrum and CMMI (Together or Any Combination)
Truly Managing a Project and Keeping Sane While Wrestling Elegantly With PMBOK, Scrum and CMMI (Together or Any Combination) Neil Potter The Process Group Lead Appraiser / Improvement Coach Organization
Building Business Case for the Enterprise From Vision to Outcomes IIBA Boston Sept. 20, 2012 Joseph Raynus ShareDynamics, Inc.
Building Business Case for the Enterprise From Vision to Outcomes IIBA Boston Sept. 20, 2012 Joseph Raynus ShareDynamics, Inc. Presentation Focus Business Situation Risk Assessment Sensitivity Analysis
CoolaData Predictive Analytics
CoolaData Predictive Analytics 9 3 6 About CoolaData CoolaData empowers online companies to become proactive and predictive without having to develop, store, manage or monitor data themselves. It is an
Mastering Microsoft Project 2013
This three-day, instructor-led course is intended for individuals who are interested in expanding their knowledge base and technical skills about Microsoft Project. The course begins with the basic concepts
Beyond Prospects: How Data Mining can Uncover Insights and Guide Program Decisions
Beyond Prospects: How Data Mining can Uncover Insights and Guide Program Decisions Christopher Seguin Vice-President, Advancement, Thompson Rivers University Celeste Bannon Waterman Vice-President, Research
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
How To Use P6 For A Project Scheduling System
Managing Assets Through Enterprise - Wide Scheduling Scott Lowe, P.E. Principal, Trauner Consulting Services, Inc. Scott Lowe, Principal, Trauner Consulting Services CPM Scheduler Claims Analyst Expert
Risk/Issue Management Plan
Risk/Issue Management Plan Centralized Revenue Opportunity System November 2014 Version 2.0 This page intentionally left blank Table of Contents 1. Overview... 3 1.1 Purpose... 3 1.2 Scope... 3 2. Roles