Improving EVM and Project Management Integration in the Dept. of Energy
|
|
|
- Shanon Gilmore
- 9 years ago
- Views:
Transcription
1 Improving EVM and Project Management Integration in the Dept. of Energy Melvin Frank Chief, Project Systems Division/MA-632 Office of Project Management/MA-60 Presentation for NDIA April 15,
2 Outline Project Management Improvements Improving EVM and Project Management Integration Current Endeavors Path Forward 2
3 From Secretary Ernest J. Moniz 12/01/2014: Improving Management of Projects - DOE manages some of the largest, most complex, and technically challenging projects in the public or private sector. Many are one-ofa-kind projects that involved the risks and challenges of nuclear operations. - Accomplishments: GAO High-Risk List narrowed focus to NNSA and Environmental projects greater than $750M - Reorganization to further improve management of projects: Provide a clear line of functional responsibility from the Under Secretary to the project owner to the Federal Project Director Establish a project assessment office with direct line of responsibility to the appropriate Under Secretary that does not have line management responsibility for project execution 3
4 Some New Terms and Definitions New terms from S-1 memo of Dec. 1, 2014, Improving the Department s Management of Projects Project Management Risk Committee (PMRC) - Provides enterprise-wide project management risk assessment and expert advice to the Secretary, CE, PMEs, and ESAAB on cost, schedule, and technical issues for projects $100M and greater Project Management Executive (PME) - Previously identified as the Acquisition Executive (AE) Chief Executive for Project Management (CE) - Previously identified as the Secretarial Acquisition Executive (SAE)
5 MA-63 Project Management Michael Peek, Director MA-631 Project Assessment John White, Chief MA-632 Policy and Systems Melvin Frank, Chief Karen Urschel (Contracted Augment Support) Robin Noyes Lead NNSA Zac West NNSA Tony Ermovick Lead EM / EERE Brian Kong EM / WTP Brian Huizenga Lead SC Pete Bako SC PARS Igor Pedan Cost Schedule Control & Analytics Vacancy Policy Ruben Sanchez Rick Blaisdell EM / NE Mike Fenn EM / FE Mark Sinichko (Contracted Augment Support) Vacancy Bob Loop Victoria Premaza Garrett Richardson 5
6 EVMS Requirements Tied to DOE s Acquisition Lifecycle Request PED Funds Operating Funds Begin using compliant EVMS Independent Review to Validate PB PED Funds Certify EVMS as compliant EIR for Major System Projects Construction Funds Operating Funds Initiation Definition Execution Closeout TPC Critical Decision CD-0 Approve Mission Need CD-1 Approve Alternative Selection and Cost Range CD-2 Approve Performance Baseline (PB) CD-3 Approve Start of Construction or Execution Projects Report Control Account EV $20M into PARS II CD-4 Approve Start of Operations or Project Completion PARS II Reporting for Projects $10M (top level reporting only) Surveillance of compliant EVMS Typical DOE Acquisition Management System for Line Item Capital Asset Projects 6
7 Why More Compliance Issues Identified? Continuous Improvement Federally led reviews Enhanced knowledge Better tools More sophisticated analytic capabilities Individual vs grouped CARs
8 Common EVMS Issues Planning and Scheduling Element of Cost (EoC) Integration of Cost and Schedule Baseline Control ETC/EAC Variance Analysis CAMs MR and Contingency (Budget vs Funds)
9 Other EVMS Issues Surveillance - Contractor - Site/Program Root Cause Analysis - VARs ~ Performance Issues - CARs ~ System Issues EVM Cost and Schedule systems - Licenses not current - Not maintained up to date - Current versions properly implemented enable compliance
10 Improving EVM and Project Management Integration 10
11 Improving EVM and PM Integration Purpose: Complete assessment of EVMS within DOE Capital Asset Projects Conducted by independent entity recognized and respected by government and industry as EVMS expert Goal: - Provide an executable path forward to obtain EVM excellence in a structured, well-defined, and clear approach - Achieve a fundamental paradigm shift across the DOE enterprise (Feds and Contractors) in Departmental buyin, accountability, and executability
12 Improving EVM and PM Integration People Resource Mapping Roles and Responsibilities Training Processes External Policies, Procedures, Regulations, Guidance, Best Practices DOE-wide Policies and Guidance OAPM Standard Operating Procedures Systems Reporting Systems Analysis Tools Communication Transmit Receive H&A collecting input for gap analysis to identify strengths, weaknesses, technical and cultural barriers, opportunities Create an executable corrective action plan - invest in the future
13 Initiative Timeline As Is Gap Analysis To Be Report / CAP Dec Jan Jan Apr Mar May May Jul Progress Report Progress Report Progress Report May 31: Draft June: Briefing July 31: Final 13
14 Initiative Deliverables The final report is a document to convey recommendations of improvement and a reasonable path to follow - It does not include the execution of the plan The environment is not static, i.e. work continues in OAPM on process development - Interim recommendations may have already been incorporated by time of delivery of the final plan - Examples: Consistency Improvements (more on these coming up) DOE EVMS Integration Handbook (EVMSIH) Use of Webinar to communicate EVMS Corrective Action SOP 14
15 Current Endeavors 15
16 Preliminary Survey Results Surveys sent to DOE Federal Staff, Federal contract support staff, and DOE Capital Asset Contractors 88 Survey responses to date: - Feds = 44 / Contractors = 44 - Coincidence that the responses are 50/50 The primary message is clear (and no coincidence): CONSISTENCY
17 DOE EVMS Integration Handbook (EVMSIH) Background Survey and feedback results regarding EVMS Provide clarity Add consistency in application Historically EVMS reviews have used a mixture of sources including NDIA IPMD Intent Guide Bowman Guide DCMA Interpretive Guide (Draft) EVMIG PASEG Contractor concerns that some of the sources were nondescript and difficult to access 17
18 Genesis 2/18/2015: The Department of Defense published the Earned Value Management System Interpretation Guide Replaced the NDIA IPMD Intent Guide with a government document High level focus Did not include evaluation methods OAPM Goal Provide Clarity and Consistency Develop a DOE EVMS Interpretation Handbook At the minimum compliance level Integrating the compliance intent with the evaluation methods and narrative explanations One stop handbook 18
19 Construct of the DOE EVMSIH Supports the EIA-748 EVMS Guidelines Qualifying Expectations Lines of Inquiry (QE LOIs) Minimum expectations of EVM compliance CARs will reference the non-compliant QE LOIs Narrative explanation of the QE LOI Impact of non-compliance Data Traces How OAPM verifies compliance with the QE LOI Interview Questions Verification of QE LOIs that cannot be done with data traces alone 19
20 Development Webinar held April 1 st, 2015 for release of the initial draft of QE LOIs for Internal DOE and DOE Contractor Comment After adjudication of QE LOIs, the draft EVMSIH will be released for comment by sections Inclusive of narrative discussions and verification steps 5/19/15: Release Organization; Planning, Scheduling and Budgeting 6/16/15: Release Analysis and Managerial Reporting; Accounting Considerations 7/14/15: Release Revisions and Data Maintenance; Indirect Considerations 20
21 Release of EVMSIH Release of EVMSIH Draft Early September 2015 OAPM will pilot the EVMSIH on several compliance reviews The EVMSIH Draft will be revised with lessons learned from pilots and another user comment period Release EVMSIH (Final) COMING SOON DOE EVMS Interpretation Handbook 21
22 Enhanced Data Analytics Data-driven approach (consistent with DCMA) Recent data-driven review issues datify compliance reviews and performance assessments Consistent PARS II and EVMS review data submissions - UN/CEFACT XML Schema Analyze data sets to detect patterns and uncover issues before they appear Targeted compliance and surveillance reviews - Increased efficiencies; reduce footprint and resource needs - Identify and localize issues; optimize surveillance and avoid disruptions
23 Project Assessment & Reporting System (PARS IIe) Purpose - Central Repository and official System of Record for capital asset project performance information - Same data as maintained in our contractors project management systems - Used by federal and contractor personnel across the nation to record and track the progress of capital asset projects Goal - Provide accurate, timely, complete, and verifiable project performance data - Provide greater transparency on the performance of specific projects - Facilitate the efforts of project analysts to analyze, track, and validate the data 23
24 PARS System Evolution PARS pre October Cumbersome, complex, insufficient level of detail, manual entry, limited automation, no reporting and analysis capabilities, etc. PARS II released October Powered by COTS product - Increased analysis and reporting capabilities, increased visibility and transparency into contractor performance PARS IIe released July Powered by SharePoint 2013 Development Platform - Advanced document management, information sharing, and collaboration capabilities - Scalability to meet current and future demands and strategic objectives
25 PARS II Current State Oversight Assessment
26 PARS II Current State PARS II Dekker Module Issues - IE Browser - Browser independency is a need, not a want - MS Office Software no longer supported by Microsoft - Impacts uploading, viewing, reporting processes Resolution is to transition: - O&A Module to SharePoint 2013 platform - CPP process from custom extraction to UN/CEFACT XML - CPP dashboards and reports to Business Intelligence platform
27 Transition to UN/CEFACT XML Electronic Data Interchange (EDI) format for toolagnostic data exchanges of project performance cost and schedule data Adopted by DoD as standard for project performance data reporting in 2012 Incorporated as standard data output by many software vendors (Deltek, Oracle, Microsoft, ARES, and others) 27
28 Controlled Unclassified Information (CUI) Will enable access to UCNI and OUO for authorized users System elevated to MODERATE impact level 60 day password expiration and 15 minute timeout limit Two-Factor Authentication (TFA) login (similar to online banking login process (e.g., Chase)
29 PARS IIe Enhancement in a Nutshell
30 New APM Handbooks Lifecycle Cost Handbook Statement of Work and Key Performance Handbook APM Glossary of Terms Handbook PARS IIe Policy & Guidance Repository DOE APM Website
31 Some Terms and Definitions Authorized Unpriced Work (AUW) Baseline Change Proposal (BCP) Budget Change Request (BCR) >BCR-P > BCR-M > BCR-C Contingency Management Reserve (MR) Over Target Baseline (OTB) Over Target Schedule (OTS) Undistributed Budget (UB) 31
32 Improved Training & Common Understanding Enhanced Federal EVMS training - EVMS Basic on-line: 24/7 DOE OLC (search EVMS) - Added Advanced EV course Encourage EV professionalism/certification - Earned Value Professional (EVP) - Planning and Scheduling Professional (PSP) EV training snippets for all, including contractors 32
33 EV Training Snippets Answers to your EVMS questions ready when you are 34 web-enabled snippets a range of EV topics Accessible 24/7-10 to 20 minutes in length DOE s Powerpedia ning_videos PARS II Policy & Guidance section in EVMS Training Snippets library EFCOG Website 33
34 EV Training Snippet Library 1.0 DOE Reviews: (8 ea.) Order EVM Reqts EVMS Review Approach EVMS Stage 1 Surveillance EVMS Stage 2 Surveillance EVMS Stage 3 Surveillance EVMS Review for Cause EVMS Certification Common EVMS Findings 2.0 EV Reporting: (4 ea.) CPR/IPMR Purpose and Use CPR/IPMR FPD Quick Check IPMR Data Item Description CFSR Overview & Reconciliation with IPMR/CPR 3.0 Schedules: (4 ea.) IMS Initial Baseline Review IMS Monthly Review Schedule Health Metrics Guidance & Resources 34
35 EV Training Snippet Library (Cont.) 4.0 Advance Topics: (9 ea.) OTB/OTS Implementation Integrated Baseline Reviews Budget vs. Funds / MR vs. Contingency Undistributed Budget Authorized Unpriced Work Baseline Control Methods FFP Subcontract and Prime EVM CAM Roles and Surveillance High Level EVM expectations 5.0 PARS II Analysis Reports: (7 ea.) Reports Overview Data Validity Reports Schedule Health Assessment Reports Variance Analysis Reports Trend Reports EAC Reasonableness and Independent EAC OAPM Monthly Report 6.0 Predictive Analysis: (2 ea.) Predictive Analysis Methods Applied Predictive Analysis 35
36 Path Forward 36
37 Conclusions and Goals Continue to improve Data-driven reviews are the norm Open and honest communication Mentor/coach/advisor also test administrator Contractor systems they are responsible Local surveillance (self-policing) EVMS expertise resides in field DOE (Feds and contract partners) recognized as best in government and industry
38 QUESTIONS? 38
39 Backup Slides 39
40 Document the As Is State Review and Document - Mission/Vision/CONOPS - External and internal EV-related policies, internal procedures, guidance, templates - Contractual language and special clauses - Tools for EV reporting and analysis 40
41 Document the As Is State Review and Document (continued) - Application of EVMS within the Department - Functional staffing (who, where, reporting structure) - EVMS Training - Communication - Compliance Issues, i.e. CARs Dependent on CAR database 41
42 Conduct Gap Analysis Primary Gap Analysis methods to be used - Benchmarking - Research - Surveys - Interviews - SWOT - Root cause analysis 42
43 Recommend the To Be Recommend an improvement plan based on Steps 2 and 3: - Areas to be covered are the same as Step 2 ( As Is ) - Plus any additional recommendations based on Step 3 Gap Analysis 43
44 Deliverables Deliver drafts of the Strategic Review Report and Strategic Improvement CAP Meeting to brief document findings and recommendations DOE provide comments Deliver final documents - Executive Summary - Analysis Methodology - Analysis and Results/Recommendations 44
45 Handbook Purpose LCC Handbook - procedures, information, examples, and tools to develop consistent and defensible life-cycle cost estimates (LCCE) and perform appropriate lifecycle cost analyses (LCCA) SOW & KPP Handbook - guidance and best practices for developing complete SOW and KPPs APM Glossary of Terms Handbook - definitions of commonly used APM terms to ensure consistent use in documents and discussions
PEP TALK. Policy EVMS - PARS. Department of Energy Acquisition and Project Management Workshop Federal Stewardship Providing the Value Proposition
2015 Department of Energy Acquisition and Project Management Workshop Federal Stewardship Providing the Value Proposition PEP TALK Policy EVMS - PARS Melvin Frank Chief, Project Systems Division/MA-632
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 AMSC Number: D7549 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing
Online Program Management Information System. PMI WDC Meeting November 17, 2009
Online Program Management Information System PMI WDC Meeting November 17, 2009 A PMIS Should Answer the Following How can Programs evolve and execute on projects throughout their lifecycles? How can Programs
Government Contracting and Earned Value Management (EVM)
Government Contracting and Earned Value Management (EVM) Ida Davis, EVP, PMP, MBA Earned Value Manager DynPort Vaccine Company LLC, A CSC Company Note: This presentation is the property of DynPort Vaccine
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor
Earned Value Management Systems Application Guide
National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide January 27, 2015 Revision 2 National Defense Industrial Association (NDIA)
Change Control Management Guide
NOT MEASUREMENT SENSITIVE DOE G 413.320 7292011 Change Control Management Guide [This Guide describes suggested nonmandatory approaches for meeting requirements. Guides are not requirements documents and
U.S. DEPARTMENT OF ENERGY CONTRACT AND PROJECT MANAGEMENT IMPROVEMENT. Closure Report
U.S. DEPARTMENT OF ENERGY CONTRACT AND PROJECT MANAGEMENT IMPROVEMENT Closure Report April 2012 Executive Summary The Department of Energy (DOE) is committed to making continuous improvements in contract
FOREWORD. Page 2 of 88
FOREWORD Earned Value Management (EVM) is one of the DoD s and industry's most powerful program management tools. Government and industry program managers use EVM to assess cost, schedule and technical
July 6, 2015 11(1) CHAPTER 11
July 6, 2015 11(1) CHAPTER 11 Table of Contents Paragraph Page 11-000 Audit of Contractor Compliance with Contract Financial Management Requirements 11-001 Scope of Chapter... 1101 11-100 Section 1 ---
Enhancing Earned Value (EV) Analysis Using Project Assessment & Reporting System (PARS II)
Enhancing Earned Value (EV) Analysis Using Project Assessment & Reporting System (PARS II) Presented by: Cathe Mohar and Karen Urschel Office of Acquisition and Project Management (APM) MA-60 U. S. Department
Earned Value Management Systems Application Guide
National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide May 4, 2011 Revision 1* National Defense Industrial Association (NDIA) 2111
Defense Logistics Agency INSTRUCTION
Defense Logistics Agency INSTRUCTION DLAI 2105 Effective May 13, 2013 SUBJECT: Earned Value Management (EVM) Systems Performance, Oversight, and Governance Referenses: (a) DLA Instruction 2105, Earned
Scheduling Process Maturity Level Self Assessment Questionnaire
Scheduling Process Maturity Level Self Assessment Questionnaire Process improvement usually begins with an analysis of the current state. The purpose of this document is to provide a means to undertake
THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC 20301 3010
THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC 20301 3010 ACQUlsmON, TECHNOLOGY AND LOG ISTICS AUG 1 0 2011 MEMORANDUM FOR SECRETARIES OF THE MILITARY DEPARTMENTS CHAIRMAN OF THE JOINT
IT Baseline Management Policy. Table of Contents
Table of Contents 1. INTRODUCTION... 1 1.1 Purpose... 2 1.2 Scope and Applicability... 2 1.3 Compliance, Enforcement, and Exceptions... 3 1.4 Authority... 3 2. ROLES, RESPONSIBILITIES, AND GOVERNANCE...
U.S. DEPARTMENT OF ENERGY CONTRACT AND P ROJ ECT MANAGEMENT ROOT CAUSE ANALYS IS AND CORRECTIVE ACTION P LAN CLOSURE REPORT FINAL
U.S. DEPARTMENT OF ENERGY CONTRACT AND P ROJ ECT MANAGEMENT ROOT CAUSE ANALYS IS AND CORRECTIVE ACTION P LAN CLOSURE REPORT FINAL FEBRUARY 2011 i Executive Summary The Department of Energy (DOE) is committed
How To Write Ansi/Eia Evm System Acceptanceance Guide
National Defense Industrial Association (NDIA) Program Management Systems Committee (PMSC) ANSI/EIA 748 Earned Value Management System Acceptance Guide Working Release For User Comment January 23, 2006
1.0 Purpose. 2.0 Roles and Responsibilities. Management System Description: Project Management. Management System Owner: Lorie Howard
Management System Description: Project Management Management System Owner: Lorie Howard Point of Contact: Lorie Howard EMCBC Home Page Issue Date: Revision: 1 1.0 Purpose The purpose of the Office of Environmental
U.S. DEPARTMENT OF ENERGY PROJECT REVIEW GUIDE FOR CAPITAL ASSET PROJECTS
NOT MEASUREMENT SENSITIVE U.S. DEPARTMENT OF ENERGY PROJECT REVIEW GUIDE FOR CAPITAL ASSET PROJECTS DOE G 413.3-9 [This Guide describes suggested non-mandatory approaches for meeting requirements. Guides
SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT
1 PMSC Quarterly Meeting, February 1 2, 2011, Fort Worth, Texas SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT Increasing the Probability Program of Success (PoPS)by Connect the dots between
FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011
FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight Outline EVMS History at the Lab FRA EVMS Documents
EDWARDS PROJECT SOLUTIONS NORTH AMERICAN INDUSTRY CERTIFICATION SYSTEM (NAICS) CODES QUALIFICATIONS WITH FULL DESCRIPTIONS
REVISED: J 5523920 PORTFOLIO MANAGEMENT SIZE STANDARD: $7.0M Edwards Project Solution ( ) provides portfolio management services through building enterprise project management solutions and providing portfolio
DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System
DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System Breakout Session A Alfred J. Massey, Western Region, Special Programs Manager,
IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN?
1 IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN? Presented at The Nexus of Agile Software Development and Earned Value Management, OSD-PARCA, February 19 20, 2015 Institute for Defense Analysis, Alexandria,
AACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
SENTINEL AUDIT V: STATUS OF
SENTINEL AUDIT V: STATUS OF THE FEDERAL BUREAU OF INVESTIGATION S CASE MANAGEMENT SYSTEM U.S. Department of Justice Office of the Inspector General Audit Division Audit Report 10-03 November 2009 Redacted
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
PROJECT MANAGEMENT AND THE ACQUISITION OF MAJOR SYSTEMS
PROJECT MANAGEMENT AND THE ACQUISITION OF MAJOR SYSTEMS Guiding Principle: Sound planning and management of DOE s contracts for the acquisition of projects are essential to the success of the Department
Training Seminars. Description. Core Courses: The core courses consist of the following:
Training Seminars Description The POI consists of training courses known as core. The purpose of the core courses is to provide a principles or foundation knowledge baseline to the student in the fundamentals
PROGRAM AND PROJECT MANAGEMENT FOR THE ACQUISITION OF CAPITAL ASSETS
ORDER DOE O 413.3B Approved: 11-29-2010 PROGRAM AND PROJECT MANAGEMENT FOR THE ACQUISITION OF CAPITAL ASSETS U.S. Department of Energy Washington, DC DOE O 413.3B 1 11-29-2010 1. PURPOSE. PROGRAM AND
Earned Value Management Tutorial Module 8: Reporting. Prepared by:
Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.
Memorandum. ACTION: Report on Computer Security Controls of Financial Management System, FTA FE-2000-098. May 23, 2000.
U.S. Department of Transportation Office of the Secretary of Transportation Office of Inspector General Memorandum ACTION: Report on Computer Security Controls of Financial Management System, FTA FE-2000-098
Project Management for Implementing the Smart Grid By Power System Engineering, Inc. Abstract PM Methodology Using a Repeatable Project Management
Project Management for Implementing the Smart Grid By Power System Engineering, Inc. Abstract PM Methodology Using a Repeatable Project Management Approach Project management solutions for the Smart Grid
Earned Value Management System (EVMS) Manual. System Description and Implementing Procedures
Manual System Description and Implementing Procedures Manual System Description and Implementing Procedures Contact Information This document is maintained, updated, and formally revised electronically
DCAA / DCMA: Progress or Status Quo? Presented By: Christine Williamson, CPA, Member Kristen Soles, CPA, Member
DCAA / DCMA: Progress or Status Quo? Presented By: Christine Williamson, CPA, Member Kristen Soles, CPA, Member Agenda State of the Agencies DCAA/DCMA What does GAO have to say? What does DOD IG have to
Application of DOE Order 413.3B to Office of Science
Program and Project Management for the Acquisition of Capital Asset Projects And Application of DOE Order 413.3B to Office of Science February 2011 Daniel R. Lehman Office of Project Assessment Office
Department of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
Plan of Action and Milestones (POA&M) Training Session
Plan of Action and Milestones (POA&M) Training Session Jamie Nicholson IM-31, Policy, Guidance, & Planning Division U.S. Department of Energy Office of the Associate CIO for Cyber Security 1 Objectives
LSF HEALTH SYSTEMS Information Technology Plan
LSF HEALTH SYSTEMS Information Technology Plan I. INTRODUCTION The LSF Health Systems software is a web-enabled, secure website providing access to LSF, the Provider Network and DCF. At this time, the
AUDIT REPORT. The Department of Energy's Management of Cloud Computing Activities
U.S. Department of Energy Office of Inspector General Office of Audits and Inspections AUDIT REPORT The Department of Energy's Management of Cloud Computing Activities DOE/IG-0918 September 2014 Department
Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP
Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program
Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report
Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report The Enterprise Program Investment Council (EPIC) is responsible for governance
Appendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
EARNED VALUE MANAGEMENT SYSTEMS (EVMS)
NOT MEASUREMENT SENSITIVE DOE G 413.3-10 XX-XX-08 EARNED VALUE MANAGEMENT SYSTEMS (EVMS) [This Guide describes suggested nonmandatory approaches for meeting requirements. Guides are not requirements documents
DODIG-2013-105 July 18, 2013. Navy Did Not Develop Processes in the Navy Enterprise Resource Planning System to Account for Military Equipment Assets
DODIG-2013-105 July 18, 2013 Navy Did Not Develop Processes in the Navy Enterprise Resource Planning System to Account for Military Equipment Assets Additional Copies To obtain additional copies of this
Capital Planning and Investment Control Guide
Department of Homeland Security Capital Planning and Investment Control Guide Version 4.0 May 2007 Prepared by the Office of the Chief Information Officer Document Version History Document Version Version
BY ORDER OF THE COMMANDER USTRANSCOM INSTRUCTION 33-48 UNITED STATES TRANSPORTATION COMMAND 22 JUNE 2015
BY ORDER OF THE COMMANDER USTRANSCOM INSTRUCTION 33-48 UNITED STATES TRANSPORTATION COMMAND 22 JUNE 2015 Communications and Information DATA MANAGEMENT POLICY AND RESPONSIBILITIES COMPLIANCE WITH THIS
DCMA EVMS COMPLIANCE REPORT I LOCKHEED MARTIN AERONAUTICS CO.
POST ACCEPTANCE REVIEW FOR CAUSE COMPLIANCE REPORT FOR THE LOCKHEED MARTIN AERONAUTICS COMPANY FORT WORTH, TEXAS PREPARED BY: DEFENSE CONTRACT MANAGEMENT AGENCY (DCMA) EARNED VALUE MANAGEMENT (EVM) CENTER
Best Practices for the Acquisition of COTS-Based Software Systems (CBSS): Experiences from the Space Systems Domain
GSAW 2004 Best Practices for the Acquisition of COTS-Based Software Systems (CBSS): Experiences from the Space Systems Domain Richard J. Adams and Suellen Eslinger Software Acquisition and Process Office
Appendix E Program Management Plan Template
Appendix E Program Management Plan Template Version 2 March 7, 2005 This page is intentionally left blank. Version 2 March 7, 2005 Title Page Document Control Panel Table of Contents List of Acronyms Definitions
Over Target Baseline and Over Target Schedule Guide
Over Target Baseline and Over Target Schedule Guide OUSD AT&L (PARCA) December 5, 2012 1 Table of Contents Section Page No. Introduction 4 Chapter 1. What is Formal Reprogramming? 5 1.1 Formal Reprogramming
Department of Defense Fiscal Year (FY) 2016 President's Budget Submission
Department of Defense Fiscal Year (FY) 2016 President's Budget Submission February 2015 Defense Contract Management Agency Defense Wide Justification Book Volume 5 of 5 Research,, Test & Evaluation, Defense-Wide
Prepare for Self-Certification of the Government Property Management System
Prepare for Self-Certification of the Government Property Management System By Jackie Luo, CEO, E-ISG Asset Intelligence Summary: Government Property Management is one of the 6 mandatory business systems
DICK BRODKORB 714.235.1485 FAX ( ) 3 THEN CHECK THE LOCATION YOU LL BE ATTENDING.
Instructors VENUE INFORMATION PROJECT SCHEDULING & EVMS LAS VEGAS, NV August 23-27, 2010 The M Resort, Spa and Casino 12300 Las Vegas Blvd. South Henderson, NV 89044 (877) 673-7678 Group block expires:
DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Small Business Process
DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Small Business Process Contracts Directorate DCMA-INST 119 OPR: DCMA-AQS 1. PURPOSE. This Instruction: a. Reissues and updates DCMA
Guide to IT Capital Planning and Investment Control (CPIC)
U.S. Department of Energy Guide to IT Capital Planning and Investment Control (CPIC) September 2010 Office of the Chief Information Officer TABLE OF CONTENTS 1.0 Preface... 1 2.0 Introduction... 2 2.1
Case Study Fleet Project Management
Case Study Fleet Project Management Version 0.0: 1/17/09 Developed by: Gregory Maisel, Senior Partner General Information The Westwind Group Address 6337 Sugar Pine Drive City, state, ZIP Code Wilmington,
Executive Branch IT Reorganization Project Plan
Office of Information Resource Management Executive Branch Project Plan Work Program Funded by for IT Appropriations Reorganization 2007, 2009 and Five Small Projects Date: August 2009 Version: 1.3 Revision
Manag. Roles. Novemb. ber 20122
Information Technology Manag gement Framework Roles and Respo onsibilities Version 1.2 Novemb ber 20122 ITM Roles and Version History Version ed By Revision Date Approved By Approval Date Description of
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
CONTACT: 1. Proposed rule BDO GOVERNMENT CONTRACTING PRACTICE GUIDANCE ON THE PROPOSED DOE BUSINESS SYSTEM RULE
BDO GOVERNMENT CONTRACTING PRACTICE GUIDANCE ON THE PROPOSED DOE BUSINESS SYSTEM RULE By Eric Sobota, Kelley Doran and Barron Avery Contractors that work for the Department of Energy (DOE) under agreements
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
ROOT CAUSE ANALYSIS CONTRACT AND PROJECT MANAGEMENT APRIL 2008
ROOT CAUSE ANALYSIS CONTRACT AND PROJECT MANAGEMENT APRIL 2008 Root Cause Analysis: Contract and Project Management APRIL 2008 Executive Summary The U.S. Department of Energy (hereafter referred to as
Status of Enterprise Resource Planning Systems Cost, Schedule, and Management Actions Taken to Address Prior Recommendations
Report No. DODIG-2013-111 I nspec tor Ge ne ral Department of Defense AUGUST 1, 2013 Status of Enterprise Resource Planning Systems Cost, Schedule, and Management Actions Taken to Address Prior s I N T
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
Government Contractor Business Systems and Overview of System Assessments
Government Contractor Business Systems and Overview of System Assessments Agenda Overview of business systems rules and environment today 3 rd party assessments Practical solutions Contractor perspective
Your Software Quality is Our Business. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc.
INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc. February 2013 1 Executive Summary Adnet is pleased to provide this white paper, describing our approach to performing
2015-233-B. Request for Information (RFI) for Contract Management and Project Management Software Solutions
2015-233-B Request for Information (RFI) for Contract Management and Project Management Software Solutions SECTION 1 GENERAL INFORMATION 1.1 INTRODUCTION The Purchasing Department for the City of Plano,
Internal Control Deliverables. For. System Development Projects
DIVISION OF AUDIT SERVICES Internal Control Deliverables For System Development Projects Table of Contents Introduction... 3 Process Flow... 3 Controls Objectives... 4 Environmental and General IT Controls...
Oracle Primavera Program Management Information System (PMIS) Solutions for Transportation Programs November, 2011
Oracle Primavera Program Management Information System (PMIS) Solutions for Transportation Programs November, 2011 Thank you for joining today s technical webinar Mute all call in phones are automatically
THE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
IT SYSTEM LIFE-CYCLE AND PROJECT MANAGEMENT
United States Department of Agriculture Agricultural Marketing Service Directive 3130.8 IT SYSTEM LIFE-CYCLE AND PROJECT MANAGEMENT I. PURPOSE... 1 II. POLICY... 1 III. DEFINITIONS... 1 IV. DOCUMENTATION
PSM. Using CMMI To Improve Contract Management Within DCMA. Guy Mercurio, DCMA Boston, MA
Using CMMI To Improve Contract Management Within DCMA Presented By: Guy Mercurio, DCMA Boston, MA Practical Software and Systems Measurement 2003 Users Group Conference Keystone, Co July 18, 2003 CMMI
The Changing Government Contractor Environment
The Changing Government Contractor Environment 1 Federal Government Contracting DCAA FY 2014 Report to Congress DCAA Audit Guidance Business systems Federal regulatory rule changes State Contracting (Dept.
Case Study. An example of a new government contract award to a private sector company required to demonstrate ANSI-748 Compliance
Case Study An example of a new government contract award to a private sector company required to demonstrate ANSI-748 Compliance Executive Summary Managing a government contract with ANSI-748 Earned Value
Project Monitoring and Control
Project Monitoring and Control ProPath Office of Information and Technology Table of Contents Project Monitoring and Control Process Maps... 1 Process: Project Monitoring and Control... 10 Project Monitoring
Overview of Florida Information Technology Project Management and Oversight Standards. Jason M. Allison, Executive Director
Overview of Florida Information Technology Project Management and Oversight Standards Jason M. Allison, Executive Director AGENCY FOR STATE TECHNOLOGY Statutory duties and responsibilities of AST: Establish
FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office
Student Success Collaborative at Indiana University
Student Success Collaborative Student Success Collaborative at Indiana University Regional Advisors Retreat May 31, 2013 eab.com Supporting the Academic Affairs Enterprise Helping Provosts and Their Teams
How To Write A Contract For Software Quality Assurance
U.S. Department of Energy Washington, D.C. NOTICE DOE N 203.1 Approved: Expires: 06-02-01 SUBJECT: SOFTWARE QUALITY ASSURANCE 1. OBJECTIVES. To define requirements and responsibilities for software quality