DCMA EVMS COMPLIANCE REPORT I LOCKHEED MARTIN AERONAUTICS CO.
|
|
|
- Kerry Thompson
- 9 years ago
- Views:
Transcription
1 POST ACCEPTANCE REVIEW FOR CAUSE COMPLIANCE REPORT FOR THE LOCKHEED MARTIN AERONAUTICS COMPANY FORT WORTH, TEXAS PREPARED BY: DEFENSE CONTRACT MANAGEMENT AGENCY (DCMA) EARNED VALUE MANAGEMENT (EVM) CENTER REPORT NUMBER CTR ALEXANDRIA, VA I PATUXENT RIVER, MD PREPARED FOR: OFFICE OF THE UNDER SECRETARY FOR DEFENSE FOR ACQUISITION, TECHNOLOGY, & LOGISTICS NOVEMBER 19, 2007 >1
2 TABLE OF CONTENTS PREFACE EXECUTIVE SUMMARY RECOMMENDATIONS SECTION A. INTRODUCTION BACKGROUND 7 TEAM ROSTER EVM POLICY 9 OBJECTIVES 10 SCOPE 10 METHODOLOGY GUIDELINE RATINGS SECTION B. MAJOR SUMMARY FINDINGS SECTION C. ANSI-748 GUIDELINE ASSESSMENT >2
3 PREFACE Earned Value Management (EVM) plays an increasingly important role for successfully delivering acquisition programs at the desired cost, schedule, and technical performance levels. Since 1996, when the Defense Contract Management Agency (DCMA) was appointed DoD Executive Agent for Earned Value Management Systems (EVMS), the responsibility to oversee the Department's primary program management process has never been more vital than it is today. In its simplest form, EVM is the discipline of managing programs successfully by planning and controlling authorized work to achieve cost, schedule, and performance objectives. EVM places special emphasis on efficiently and effectively executing work through the development and operation of management control system that includes people, systematic processes, and innovative tools and techniques. The intent of EVM is to help program managers, and the teams who support them, be successful by allowing them to operate productively in the high-risk environments surrounding them. Input* Output >3
4 EXECUTIVE SUMMARY The DCMA EVMS compliance review, conducted August 2007, found that Lockheed Martin Aeronautics Company (LM-Aero), Fort Worth, Texas, is not following, nor consistently applying, the American National Standard Electronic Industries Alliance Earned Value Management Systems (ANSI/EIA-748-A) guidelines during the execution of Department Programs. The findings of the review indicate that, under LM-Aero stewardship, the utility of the EVMS has declined to a level where it does not serve its intended purpose and the government is not obtaining useful program performance data to anticipate and mitigate program risks. Key LM-Aero EVMS processes and procedures are below standard and do not provide the requisite definition and discipline to properly plan and control complex, multibillion dollar weapon systems acquisition programs. Documented findings indicate that a large percentage of LM-Aero Control Account Managers (CAM) are disconnected from basic LM-Aero EVMS functions and ran not satisf actorily demonstrate that they understand and use documented EVM processes, procedures and tools to manage their work. These weaknesses adversely impact the validity of the data used in internal and external decision-making processes and are fully discussed in this report. Specifically, LM-Aero was found to be non-compliant in 19 of 32 industry guidelines. Significant findings, resulting in lack of planning and control disciplines include: Using vague and confusing EVMS documentation; Lack of clearly delineated roles and responsibilities; Using management reserve to alter internal and subcontract performance levels and overruns; Work authorization and change control processes that do not extend to appropriate levels; Cost and schedule integration problems that undermine the validity of data; Inappropriate earned value techniques used for the assessment of material, subcontracts, and rework; and The inability of LM-Aero CAMs to demonstrate a working level understanding of key EVMS processes including the definition and use of a > 4
5 program critical path, situational awareness of cost and schedule variances for course correction, and the substantiation of completion cost estimates. These and the other identified deficiencies raise significant concerns regarding LM-Aero management processes and practices and the Company's ability to mitigate emerging cost and schedule issues in a timely manner. Because the accuracy and validity of LM-Aero performance measurement data is suspect, the Department's ability to use EVM data to determine product delivery dates and to develop timely and accurate estimates of program completion costs is adversely impacted. It was apparent during discussions with LM-Aero CAMs that their involvement in performing their EVM responsibilities was superficial at best. Most CAM functions are being performed, with little management control, by the business operations personnel assigned to Integrated Product Teams (IPT). The result is a serious deterioration of system discipline. This undisciplined approach to program management and towards the maintenance of the EVMS, will ultimately jeopardize the long-term stability of LM-Aero programs at Fort Worth, Texas facilities and diminishes the purchasing power of the Department. Given the nature of the risks involved in the achievement of programmatic objectives, the LM-Aero management systems and processes reviewed did not provide reasonable assurance that established Department objectives for supplier EVMS would be achieved. Therefore, we believe significant corrective actions are needed immediately to help ensure compliance with applicable regulations, policies and procedures, and good business practices. RECOMMENDATIONS We recommend that: 1. Under Secretary of Defense for Acquisition, Technology, and Logistics should establish incentives for implementing and maintaining EVM Systems. For all new contracts include a contract clause for withholding up to 5-10 percent from supplier payments for failure to adequately implement and maintain a validated EVM System. For existing contracts, add a provision within the program award fee plan to establish similar incentives; 2. Lockheed Martin should review each LM-Aero location to ensure that the LM-Aero EVMS is properly implemented and that LM-Aero Fort Worth, TX findings are not systemic throughout the LM-Aero division; >5
6 3. LM-Aero and the Program Management Office should jointly develop and provide to the DCMA, no later than February 8, 2008, a plan of corrective action plan and milestones to address all compliance and program application issues in order to retain EVMS certification. The corrective action plan should contain a root cause analysis of system deficiencies and include measurable steps to correct them. The action plan should conclude with a follow-on compliance review in 4Q CY2008; 4. DCMA CMO Fort Worth should notify relevant Department stakeholders, including service SAE and PEO of the results of the compliance review and next steps; and 5. DCMA CMO Fort Worth should develop and adopt a risk based staffing approach to ensure for the proper levels of oversight needed for supplier EVMS implementation. >6
IT Baseline Management Policy. Table of Contents
Table of Contents 1. INTRODUCTION... 1 1.1 Purpose... 2 1.2 Scope and Applicability... 2 1.3 Compliance, Enforcement, and Exceptions... 3 1.4 Authority... 3 2. ROLES, RESPONSIBILITIES, AND GOVERNANCE...
THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC 20301 3010
THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC 20301 3010 ACQUlsmON, TECHNOLOGY AND LOG ISTICS AUG 1 0 2011 MEMORANDUM FOR SECRETARIES OF THE MILITARY DEPARTMENTS CHAIRMAN OF THE JOINT
Supplier Risk Management. Presented By Bill Gibson, DCMA HQ Date: May 2001
Supplier Risk Management Presented By Bill Gibson, DCMA Q Date: May 2001 Agenda Introduction One Book Policy Structure Policy Overview Risk Assessment and Management Program (RAMP) Summary Introduction
July 6, 2015 11(1) CHAPTER 11
July 6, 2015 11(1) CHAPTER 11 Table of Contents Paragraph Page 11-000 Audit of Contractor Compliance with Contract Financial Management Requirements 11-001 Scope of Chapter... 1101 11-100 Section 1 ---
Defense Logistics Agency INSTRUCTION
Defense Logistics Agency INSTRUCTION DLAI 2105 Effective May 13, 2013 SUBJECT: Earned Value Management (EVM) Systems Performance, Oversight, and Governance Referenses: (a) DLA Instruction 2105, Earned
DOECAA Spring Conference Presentation. Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule
DOECAA Spring Conference Presentation Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule Mary Karen Wills, CPA Director/Leader, BRG Government Contracts 2014 Berkeley Research Group
Achieving Desired Results with Less: Supply Chain Management. Vincent Feck, Colonel, USAF Commander DCMA Lockheed Martin Fort Worth
Achieving Desired Results with Less: Supply Chain Management Vincent Feck, Colonel, USAF Commander DCMA Lockheed Martin Fort Worth Mission: To provide Contract Administration Services to the Department
The Program Managers Guide to the Integrated Baseline Review Process
The Program Managers Guide to the Integrated Baseline Review Process April 2003 Table of Contents Foreword... 1 Executive Summary... 2 Benefits... 2 Key Elements... 3 Introduction... 4 IBR Process Overview...
Government Contracting and Earned Value Management (EVM)
Government Contracting and Earned Value Management (EVM) Ida Davis, EVP, PMP, MBA Earned Value Manager DynPort Vaccine Company LLC, A CSC Company Note: This presentation is the property of DynPort Vaccine
DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Defense Acquisition Executive Summary (DAES)
DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Defense Acquisition Executive Summary (DAES) Portfolio Management and Integration Directorate DCMA-INST 406 DCMA-PII Validated current,
Scheduling Process Maturity Level Self Assessment Questionnaire
Scheduling Process Maturity Level Self Assessment Questionnaire Process improvement usually begins with an analysis of the current state. The purpose of this document is to provide a means to undertake
Recognizing and Mitigating Risk in Acquisition Programs
Professional Development Institute May 27 th to May 29 th 2015 Recognizing and Mitigating Risk in Acquisition Programs D e b r a E. H a h n D e b b i e. h a h n @ d a u. m i l 703-805- 2830 1 DoD Risk
Click to edit Master title style
Click to edit Master title style Click The to Business edit Master title style Operations Center and CPSRs Breakout Third Session level # D08 Andrew C. Obermeyer, Director, DCMA Business Operations Center
Report No. DoDIG-2012-081 April 27, 2012. Navy Organic Airborne and Surface Influence Sweep Program Needs Defense Contract Management Agency Support
Report No. DoDIG-2012-081 April 27, 2012 Navy Organic Airborne and Surface Influence Sweep Program Needs Defense Contract Management Agency Support Additional Copies To obtain additional copies of this
DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System
DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System Breakout Session A Alfred J. Massey, Western Region, Special Programs Manager,
Validating Third Party Software Erica M. Torres, CRCM
Validating Third Party Software Erica M. Torres, CRCM Michigan Bankers Association Risk Management & Compliance Institute September 29, 2014 MEMBER OF PKF NORTH AMERICA, AN ASSOCIATION OF LEGALLY INDEPENDENT
Status of Enterprise Resource Planning Systems Cost, Schedule, and Management Actions Taken to Address Prior Recommendations
Report No. DODIG-2013-111 I nspec tor Ge ne ral Department of Defense AUGUST 1, 2013 Status of Enterprise Resource Planning Systems Cost, Schedule, and Management Actions Taken to Address Prior s I N T
Design and Development of Dallas/Fort Worth International Airport s [DFW s] Compliance-Focused Environmental Management System [EMS] 1
EMS - INTRODUCTION Design and Development of Dallas/Fort Worth International Airport s [DFW s] Compliance-Focused Environmental Management System [EMS] 1 Acknowledgments 2 Information contributing to DFW
ROOT CAUSE ANALYSIS CONTRACT AND PROJECT MANAGEMENT APRIL 2008
ROOT CAUSE ANALYSIS CONTRACT AND PROJECT MANAGEMENT APRIL 2008 Root Cause Analysis: Contract and Project Management APRIL 2008 Executive Summary The U.S. Department of Energy (hereafter referred to as
The Changing Government Contractor Environment
The Changing Government Contractor Environment 1 Federal Government Contracting DCAA FY 2014 Report to Congress DCAA Audit Guidance Business systems Federal regulatory rule changes State Contracting (Dept.
Overview of SAE s AS6500 Manufacturing Management Program. David Karr Technical Advisor for Mfg/QA AFLCMC/EZSM 937-255-7450 [email protected].
Overview of SAE s AS6500 Manufacturing Management Program David Karr Technical Advisor for Mfg/QA AFLCMC/EZSM 937-255-7450 [email protected] 1 Outline Background Objectives Requirements Implementation
Evaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies
Inspector General U.S. Department of Defense Report No. DODIG-2016-001 OCTOBER 1, 2015 Evaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies INTEGRITY
Contractor Purchasing System Review (CPSR)
Contractor Purchasing System Review (CPSR) Presentation References FAR 44.3 and DFARS 244.3 -- Contractors Purchasing Systems Reviews Consent to Subcontract FAR 44.2 2 What is a CPSR Contractor purchasing
Earned Value Management Systems Application Guide
National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide May 4, 2011 Revision 1* National Defense Industrial Association (NDIA) 2111
SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT
1 PMSC Quarterly Meeting, February 1 2, 2011, Fort Worth, Texas SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT Increasing the Probability Program of Success (PoPS)by Connect the dots between
DOD BUSINESS SYSTEMS MODERNIZATION. Additional Action Needed to Achieve Intended Outcomes
United States Government Accountability Office Report to Congressional Committees July 2015 DOD BUSINESS SYSTEMS MODERNIZATION Additional Action Needed to Achieve Intended Outcomes GAO-15-627 July 2015
F 35 Lightning II Program Quality Assurance and Corrective Action Evaluation
Report No. DODIG-2015-092 I nspec tor Ge ne ral U.S. Department of Defense MARCH 11, 2015 F 35 Lightning II Program Quality Assurance and Corrective Action Evaluation I N T E G R I T Y E F F I C I E N
Systems Thinking in DoD Program Management
Systems Thinking in DoD Program Management Bipin Chadha and John Welsh Lockheed Martin Advanced Technology Laboratories Amelia Ruzzo Placer Dome, Inc. Problem Major programs often encounter major cost
The following slides are not contractual in nature and are for information purposes only as of June 2015.
The following slides are not contractual in nature and are for information purposes only as of June 2015. 2015, Lockheed Martin Corporation. All Rights Reserved. 1 Corrective Action Webinar Lesson 1 -
DCAA Initiatives/Current Issues
Defense Contract Audit Agency DCAA Initiatives/Current Issues Maryland Association of CPAs 2010 Government Contractors' Conference September 21, 2010 Kenneth J. Saccoccia Assistant Director Policy and
FOREWORD. Page 2 of 88
FOREWORD Earned Value Management (EVM) is one of the DoD s and industry's most powerful program management tools. Government and industry program managers use EVM to assess cost, schedule and technical
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you
Allegations of the Defense Contract Management Agency s Performance in Administrating Selected Weapon Systems Contracts (D-2004-054)
February 23, 2004 Acquisition Allegations of the Defense Contract Management Agency s Performance in Administrating Selected Weapon Systems Contracts (D-2004-054) This special version of the report has
GAO DEFENSE CONTRACT MANAGEMENT AGENCY. Amid Ongoing Efforts to Rebuild Capacity, Several Factors Present Challenges in Meeting Its Missions
GAO United States Government Accountability Office Report to Congressional Requesters November 2011 DEFENSE CONTRACT MANAGEMENT AGENCY Amid Ongoing Efforts to Rebuild Capacity, Several Factors Present
Earned Value Management Systems Application Guide
National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide January 27, 2015 Revision 2 National Defense Industrial Association (NDIA)
STRENGTHENING DEPARTMENT OF DEFENSE LABORATORIES David Graham, Robert Leheny, and Susan Clark-Sestak
STRENGTHENING DEPARTMENT OF DEFENSE LABORATORIES David Graham, Robert Leheny, and Susan Clark-Sestak The Problem Department of Defense (DoD) laboratories primarily focus on sustaining innovation in known
Strategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012
Strategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012 1 Panelists Robert A. ( Rob ) Burton, Partner, Venable LLP A 30-year veteran
Program Management Office Provided Adequate Oversight of Two Contracts Supporting the Defense Enterprise Accounting and Management System
Report No. DODIG-2014-006 I nspec tor Ge ne ral U.S. Department of Defense OCTOBER 25, 2013 Program Management Office Provided Adequate Oversight of Two Contracts Supporting the Defense Enterprise Accounting
GAO DEFENSE CONTRACT AUDITS. Actions Needed to Improve DCAA's Access to and Use of Defense Company Internal Audit Reports
GAO United States Government Accountability Office Report to the Committee on Armed Services, U.S. Senate December 2011 DEFENSE CONTRACT AUDITS Actions Needed to Improve DCAA's Access to and Use of Defense
Property Management System (GPMS)
Property Management System (GPMS) Business System Overview Sep 20, 2013 Marcia D. Whitson, CPPM, CF NPMA National President DFARS 252.242-7005 Contractor Business Systems DoD Business Systems Rule - Clarifies
Introduction to AS 9100
Introduction to AS 9100 Rev. C 1 Questions we will cover today: What is AS9100? What does a company need to do to Register to AS9100 Rev C? What are the requirements? Section 4 General Requirements Section
BETTER BUYING POWER 2.0 INITIATIVES DESCRIPTIONS
BETTER BUYING POWER 2.0 INITIATIVES DESCRIPTIONS Achieve Affordable Programs Mandate affordability as a requirement: The initiative to provide affordability caps for unit production cost and sustainment
FEDERAL HOUSING FINANCE AGENCY ADVISORY BULLETIN AB 2014-07 OVERSIGHT OF SINGLE-FAMILY SELLER/SERVICER RELATIONSHIPS. Purpose
FEDERAL HOUSING FINANCE AGENCY ADVISORY BULLETIN AB 2014-07 OVERSIGHT OF SINGLE-FAMILY SELLER/SERVICER RELATIONSHIPS Purpose This advisory bulletin communicates the Federal Housing Finance Agency s (FHFA)
Review of Audits Issued by the Defense Contract Audit Agency in FY 2012 and FY 2013
Report No. DODIG-2014-109 Inspector General U.S. Department of Defense SEPTEMBER 8, 2014 Review of Audits Issued by the Defense Contract Audit Agency in FY 2012 and FY 2013 INTEGRITY EFFICIENCY ACCOUNTABILITY
GAO DCAA AUDITS. Allegations That Certain Audits at Three Locations Did Not Meet Professional Standards Were Substantiated
GAO United States Government Accountability Office Report to Congressional Addressees July 2008 DCAA AUDITS Allegations That Certain Audits at Three Locations Did Not Meet Professional Standards Were Substantiated
Government Contractor Business Systems and Overview of System Assessments
Government Contractor Business Systems and Overview of System Assessments Agenda Overview of business systems rules and environment today 3 rd party assessments Practical solutions Contractor perspective
Department of Defense Fiscal Year (FY) 2016 President's Budget Submission
Department of Defense Fiscal Year (FY) 2016 President's Budget Submission February 2015 Defense Contract Management Agency Defense Wide Justification Book Volume 5 of 5 Research,, Test & Evaluation, Defense-Wide
The Devil is in the Details Compliance with the Business Systems Rule
Metropolitan Area Corporate Counsel Association WMACCA Conference on Ethics and Compliance for Government Contractors The Devil is in the Details Compliance with the Business Systems Rule April 1, 2014
to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015
D to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015 This page has been left blank intentionally Page 2 of 24 Page 3 of 24 This page has been left blank intentionally Page 4 of 24 Strategic
TOPIC NO 30515 TOPIC Supplies and Materials Inventory Table of Contents Overview...2 Policy...4 Procedures...8 Internal Control...
Table of Contents Overview...2 Introduction...2 Effective management system...3 Maintenance versus value...3 Cost reduction...3 Policy...4 Inventory records...4 Considerations for agencies with large inventories...7
PURCHASE ORDER TERMS AND CONDITIONS FOR MANUFACTURING MANAGEMENT PROGRAMS MIL-STD-1528A APPENDIX 2
08/27/91 PURCHASE ORDER TERMS AND CONDITIONS FOR MANUFACTURING MANAGEMENT PROGRAMS MIL-STD-1528A APPENDIX 2 1. The Seller, upon acceptance of this purchase order, shall establish and/or maintain a Manufactured
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 AMSC Number: D7549 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing
Training Seminars. Description. Core Courses: The core courses consist of the following:
Training Seminars Description The POI consists of training courses known as core. The purpose of the core courses is to provide a principles or foundation knowledge baseline to the student in the fundamentals
PROJECT MANAGEMENT AND THE ACQUISITION OF MAJOR SYSTEMS
PROJECT MANAGEMENT AND THE ACQUISITION OF MAJOR SYSTEMS Guiding Principle: Sound planning and management of DOE s contracts for the acquisition of projects are essential to the success of the Department
GUIDANCE FOR MANAGING THIRD-PARTY RISK
GUIDANCE FOR MANAGING THIRD-PARTY RISK Introduction An institution s board of directors and senior management are ultimately responsible for managing activities conducted through third-party relationships,
Audit Quality Thematic Review
Thematic Review Professional discipline Financial Reporting Council January 2014 Audit Quality Thematic Review Fraud risks and laws and regulations The FRC is responsible for promoting high quality corporate
GAO MAJOR AUTOMATED INFORMATION SYSTEMS. Selected Defense Programs Need to Implement Key Acquisition Practices
GAO United States Government Accountability Office Report to Congressional Addressees March 2013 MAJOR AUTOMATED INFORMATION SYSTEMS Selected Defense Programs Need to Implement Key Acquisition Practices
Change Control Management Guide
NOT MEASUREMENT SENSITIVE DOE G 413.320 7292011 Change Control Management Guide [This Guide describes suggested nonmandatory approaches for meeting requirements. Guides are not requirements documents and
RISK MANAGEMENT GUIDE FOR DOD ACQUISITION
RISK MANAGEMENT GUIDE FOR DOD ACQUISITION Sixth Edition (Version 1.0) August, 2006 Department of Defense Preface The Department of Defense (DoD) recognizes that risk management is critical to acquisition
Master Document Audit Program. Version 7.4, dated November 2006 B-1 Planning Considerations. Purpose and Scope
Activity Code 24010 B-1 Planning Considerations Estimating System Survey (ICR) Purpose and Scope The major objectives of this audit are to: Evaluate the adequacy of and the contractor s compliance with
Fundamentals of Measurements
Objective Software Project Measurements Slide 1 Fundamentals of Measurements Educational Objective: To review the fundamentals of software measurement, to illustrate that measurement plays a central role
What Exactly is an Acceptable Accounting System?
What Exactly is an Acceptable Accounting System? Kristen Soles, CPA Member Stephanie Widzinski, CPA Senior Manager September 27, 2012 Agenda Review DFARS Business System Rule What Agency is Responsible
CONTACT: 1. Proposed rule BDO GOVERNMENT CONTRACTING PRACTICE GUIDANCE ON THE PROPOSED DOE BUSINESS SYSTEM RULE
BDO GOVERNMENT CONTRACTING PRACTICE GUIDANCE ON THE PROPOSED DOE BUSINESS SYSTEM RULE By Eric Sobota, Kelley Doran and Barron Avery Contractors that work for the Department of Energy (DOE) under agreements
How To Write Ansi/Eia Evm System Acceptanceance Guide
National Defense Industrial Association (NDIA) Program Management Systems Committee (PMSC) ANSI/EIA 748 Earned Value Management System Acceptance Guide Working Release For User Comment January 23, 2006
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN April 2009 SLAC I 050 07010 002 Risk Management Plan Contents 1.0 INTRODUCTION... 1 1.1 Scope... 1 2.0 MANAGEMENT
FCPA 10 Hallmarks Self- Assessment
FCPA 10 Hallmarks Self- Assessment How exposed is your business to corruption risk? Take this assessment to find out if your systems are sufficiently robust to protect your business October 2014 Prepared
a GAO-02-635 GAO DOD CONTRACT MANAGEMENT Overpayments Continue and Management and Accounting Issues Remain
GAO United States General Accounting Office Report to the Chairman, Committee on Government Reform, House of Representatives May 2002 DOD CONTRACT MANAGEMENT Overpayments Continue and Management and Accounting
PROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
Risk Management. Software SIG. Alfred (Al) Florence. The MITRE. February 26, 2013. MITRE Corporation
Risk Management Software SIG MITRE Corporation February 26, 2013 The MITRE Alfred (Al) Florence MITRE Corporation The MITRE Agenda Introduction Risk Management References Contact Information Al Florence
ISO/IEC 17025 QUALITY MANUAL
1800 NW 169 th Pl, Beaverton, OR 97006 Revision F Date: 9/18/06 PAGE 1 OF 18 TABLE OF CONTENTS Quality Manual Section Applicable ISO/IEC 17025:2005 clause(s) Page Quality Policy 4.2.2 3 Introduction 4
RISK MANAGEMENT GUIDE FOR DOD ACQUISITION
RISK MANAGEMENT GUIDE FOR DOD ACQUISITION Sixth Edition (Version 1.0) August, 2006 Department of Defense Preface The Department of Defense (DoD) recognizes that risk management is critical to acquisition
QUALITY MANAGEMENT SYSTEM REVIEW AND APPROVAL TEMPLATE (DOE G 414.1-2A, Appendix A, 6-17-05)
QUALITY MANAGEMENT SYSTEM REVIEW AND APPROVAL TEMPLATE (DOE G 414.1-2A, Appendix A, 6-17-05) This review template is intended for use by the DOE for evaluating a DOE Site Office or Contractor Quality Assurance
GAO DEFENSE CONTRACTING. Contract Risk a Key Factor in Assessing Excessive Pass-Through Charges. Report to Congressional Committees
GAO United States Government Accountability Office Report to Congressional Committees January 2008 DEFENSE CONTRACTING Contract Risk a Key Factor in Assessing Excessive Pass-Through Charges GAO-08-269
Quality Assurance Program Plan. July 2006. U.S. Department of Energy Office of Legacy Management
U. S. Department of Energy Office of Legacy Management July 2006 July 2006 Page i DOE-LM Policy Statement The U.S. Department of Energy (DOE) Office of Legacy Management (LM) performs long-term surveillance
Risk Mitigation and Subcontract Management
Risk Mitigation and Subcontract Management Breakout Session # C13 Danielle Carr, MSM Program Acquisitions, HMS Technologies Stacey B. Dey-Foy Director Suspension & Debarment, EPA July 28, 2014 @ 4:00pm
PROGRAM MANAGEMENT IN DEFENSE SYSTEMS
Seminar s Title : PROGRAM MANAGEMENT IN DEFENSE SYSTEMS Purpose and Background : Program Management is one of the most important aspects of the entire defense acquisition process. It is the application
Material Transfers and Material Management and Accounting System (MMAS)
Material Transfers and Material Management and Accounting System (MMAS) The Scenario Risk Assessment-Research and Planning: The auditor was assigned an audit of major contractor MIL s Material Management
Program and Project Management Practices in the Federal Civilian Agencies
Progress through partnership National Defense Industry Association, Civilian Agencies Industry Working Group Program and Project Management Practices in the Federal Civilian Agencies White Paper Lawrence
DOD DIRECTIVE 4715.21 CLIMATE CHANGE ADAPTATION AND RESILIENCE
DOD DIRECTIVE 4715.21 CLIMATE CHANGE ADAPTATION AND RESILIENCE Originating Component: Office of the Under Secretary of Defense for Acquisition, Technology, and Logistics Effective: January 14, 2016 Releasability:
SUPERVISION GUIDELINE NO. 9 ISSUED UNDER THE AUTHORITY OF THE FINANCIAL INSTITUTIONS ACT 1995 (NO. 1 OF 1995) RISK MANAGEMENT
SUPERVISION GUIDELINE NO. 9 ISSUED UNDER THE AUTHORITY OF THE FINANCIAL INSTITUTIONS ACT 1995 (NO. 1 OF 1995) RISK MANAGEMENT Bank of Guyana July 1, 2009 TABLE OF CONTENTS 1.0 Introduction 2.0 Management