1 Rail Growth Package Project Reference: DEV 189 Location: T:\DEV000 Projects\DEV189 Leeds growth package\100 project management\project & Programme Management (PPM) Documentation\Communication Plan Date: March 2014 Business Case Owner: Project Manager: Approvals: Chris Mason, Development Rebecca Cheung Version control: Version Number Change Date 1 Inherited version 12/04/ PPM tailored Updated for FA Submission 03/12/ /03/2014
2 CONTENTS 1. INTRODUCTION 1.1 PURPOSE OF THE COMMUNICATIONS PLAN 2. STAKEHOLDER 3. INFORMATION REQUIRED AND PROVIDER 4. METHODOLOGY
3 1. INTRODUCTION 1.1 Purpose of this Communication Plan The objective of the communication plan is to: Increase awareness Ensure stakeholder support Provide evidence of consultation Improve scheme design To define all parties with an interest in the project and the means and frequency of communication between them and the project. Communication among stakeholders is a key element to this project to ensure stakeholder support. The following meetings will be arranged on a regular basis to ensure all parties will receive the information required: Meeting Frequency Stakeholders Lead Design progress meeting Commence at a monthly frequency Northern Rail, City of Bradford politan District Council (CBMDC), Leeds City Council (LCC), Network Rail, C Spenser and CEG Network Rail meeting At least every 4 months and may require more frequent meeting. Frequency to be determined by the. Senior representatives from CBMDC, LCC,, Network Rail, CEG and Northern with support from SDG Legal meeting As when required Legal (), Projects () with support from DLA Portfolio Board Prior to each formal submission to DfT s internal key Portfolio Board Members s Executive Board meeting Prior to each formal submission to DfT or when capital approval is required. Board members Timetabling meeting As when required Northern, Network Rail and
4 2. Stakeholders Stakeholder Contact Name Contact detail Project Manager Senior Responsible Owner/ Business Case Owner: David Hoggarth Director Development Rebecca Cheung Rail Development Team Leader Project Support Phil Wilson ICT Services N/A - Finance Tom Edwards, Assistant Director, Finance Public Relations Gary Taylor, Public Relations Officer, Public Relations Internal Audit Russell Gott [email protected] Legal Nick Winney, Solicitor, Legal PTA N/A - Other Departments Derek Robinson District Councils Richard Gelder, CBMDC Andrew Hall, LCC [email protected] User Forums Tim Calow, AVRUG (Aire Valley Rail Users Group) The Secretary, Bradford Rail Users Group (BRUG) Keighley & Worth Valley Railway Marion Armstrong, Settle and Carlisle Railway Development Company Peter Johnson (Secretary) WRUG (Wharfedale Rail Users Group) [email protected] [email protected] [email protected] [email protected] [email protected] Bus Operators Via s Bus Area Coordinator -
5 Stakeholder Contact Name Contact detail Stakeholders Peter Myers, Stakeholder Manager, Northern Rail Russell Bates, Network Rail Charlie Sunderland, DfT Consultants Steve Hunter, SDG Mike Holmes, WSP Information Required and Provider Organisation Information Required (with means and frequency) Information Provider Cost, Risks, timescales Project Manager (via Highlights reports at ) Project Manager Cost information, risks, programme of different work packages (via update at design progress Network Rail and CBMDC to provide meeting) ICT Services N/A - Finance Cost, spending profile and forecast (as required) Project Manager Public Relations Consultation, Press Release and Launch (at major milestones such as secure of FA approval, commencement of construction and completion) Phil Wilson, Projects Internal Audit N/A - Legal Legal cost, contracts and implications Robert Smith, DLA and Nick Winney, Javid Daji PTA Other Departments Timescales, risks and costs (when capital approval is required) Derek Robinson - Any implications on Facilities resources (Before detailed design is finalised) Alison Piling marketing campaign (prior to the opening of the stations) - Project Manager District Councils User Forums Planning information, design details, progress update (as when required) Design specification and progress update (as when required) Project Manager Projects Manager Bus Operators Pedestrian route to and from bus stops Project Support Stakeholders Design, approvals, implications and cost Project Support
6 Consultants Project update, BCR, business case Project Support Public Through website (update on an on-going basis) Project Support
7 4. Methodology The is attended by senior representatives from, CEG, Network Rail, Northern Rail, LCC and CBMDC. The project Board receives information from Project Design meetings. The will meet as and when required to provide strategic direction to the Project Manager and for Project Design meetings. Public Consultation A public consultation event was at Apperley Bridge and Kirkstall in May and June The main objective of the event was to explain the scheme to the general public and local residents and businesses and to gather feedback. Public will continue to be engaged throughout the project via the following: Provide update through PCC meetings Provide update at Neighbourhood Forum or meet with residents (before construction) Update through websites Respond to any project related queries through Customer Responses Management (CRM) system. Letter drops (regarding construction timescales) prior to construction works Project Website Update information of the project will be provided on website on a regular basis. Project A project address was established to allow public feedback and enquiries to be collated during and after the public consultation exercise [email protected] Local Press Further press releases will be prepared for: - Full Approval - Prior to commencing construction
8 - Prior to station opening
High Speed Two (HS2) Ltd Board Meeting held on 16 October 2014. Minutes. HS2 Ltd Board room, One Canada Square, London E14 5AB
High Speed Two (HS2) Ltd Board Meeting held on 16 October 2014 Minutes HS2 Ltd Board room, One Canada Square, London E14 5AB Present: David Higgins, Chair Simon Kirby, Chief Executive Richard Brown Christine
Author: Mike Younghusband, Hertfordshire County Council
HERTFORDSHIRE LOCAL TRANSPORT BODY 4 th March 2014 TRANSPORT PROJECT GATEWAYS Author: Mike Younghusband, Hertfordshire County Council 1 Purpose of Report 1.1 To inform the LTB of Hertfordshire County Council
18 November 2015 At a meeting of the Select Committee held at 10.30 a.m. at County Hall, Chichester.
Environmental & Community Services Select Committee 18 November 2015 At a meeting of the Select Committee held at 10.30 a.m. at County Hall, Chichester. Present: Mr Tyler (Chairman) Mr Barrett-Miles Mr
Asset Management Policy March 2014
Asset Management Policy March 2014 In February 2011, we published our current Asset Management Policy. This is the first update incorporating further developments in our thinking on capacity planning and
TfL and Network Rail s consultation on Crossrail 2 Response from London First
TfL and Network Rail s consultation on Crossrail 2 Response from London First The online consultation (including background material) can be accessed via the following link. http://www.tfl.gov.uk/corporate/projectsandschemes/27405.aspx
APPENDIX C. Internal Audit Report South Holland District Council Project Management
APPENDIX C Internal Audit Report South Holland District Council Project Management Date: 20th December 2012 Contents Introduction and Scope 1 Executive Summary Assurance Opinion Key Messages 2 3 Management
Consultation on possible location of main site
THE HIGH SPEED RAIL COLLEGE Consultation on possible location of main site MARCH 2014 Contents Contents...2 The high speed rail college: consultation on possible location of main site...3 1. Introduction...4
Claughton Medical Centre Travel Plan
Claughton Medical Centre Travel Plan June 2011 1 Contents Page 1. Introduction 2 2. Objectives 3 3. Targets 5 4. Site Audit 6 5. Travel Survey 11 6. Marketing strategy 13 7. Monitoring and review 15 8.
8.0 Project Management
8.0 Project Management 8.1 Project Management Costs The LCN+ project operates on an annual budget from TfL. This budget includes individual borough allocations, Sector Leader costs and Project Management
LCR Ltd. Freedom of Information Act 2000. LCR Publication Scheme
LCR Ltd Freedom of Information Act 2000 LCR Publication Scheme 1. Introduction The Freedom of Information Act 2000 (FOIA) requires every public authority to have and maintain a publication scheme in order
Seamless journeys from door to door. www.bettertransport.org.uk
Seamless journeys from door to door www.bettertransport.org.uk Seamless journeys from door to door If public transport is to offer a real and attractive alternative to cars, it needs to offer the same
ASSOCIATION OF COLLEGES
MINUTES of the AoC BOARD MEETING ASSOCIATION OF COLLEGES Held at 9.30am on Wednesday, 9 July 2014 in Rooms 9 10, Radisson Blu Edwardian Kenilworth, 97 Great Russell Street, London, WC1B 3LB. 1. WELCOME
Roads for All. The Trunk Road Network. Disability Equality Scheme. and. Action Plan
Roads for All The Trunk Road Network Disability Equality Scheme and Action Plan Transport Scotland Glasgow 4 December 2006 Acknowledgements This Trunk Road Network Disability Equality Scheme and Action
BUSINESS CONTINUITY MANAGEMENT POLICY
BUSINESS CONTINUITY MANAGEMENT POLICY Version No: 1 Issue Status: awaiting Trust Board approval Date of Ratification: 11th April 2012 Ratified by: Risk Management Committee Policy Author(s): Stuart Coalwood
Review of Transport Asset Management Plans For the Department for Transport
Review of Transport Asset Management Plans For the Department for Transport January 2008 Executive Summary Local Transport Plan guidance encourages local authorities to develop Transport Asset Management
RTU Staff College. Business Plan 2008-2009
RTU Staff College Business Plan -2009 The Regional Training Unit provides leadership, coordination and direction in the planning and delivery of training at regional level. The direction and policies of
NORTHERN IRELAND TRANSPORT HOLDING COMPANY
NORTHERN IRELAND TRANSPORT HOLDING COMPANY Summary Minutes of the 171st Group Board Meeting of the Directors held on Wednesday 17 th April 2013 at 9.30am at Chamber of Commerce House, Belfast PRESENT:
MedCo Framework Review Call for Evidence
MedCo Framework Review Call for Evidence This Call for Evidence begins on Thursday 16 July 2015 This Call for Evidence ends on Friday 4 September 2015 MedCo Framework Review Call for Evidence A Call for
Access Fund for Sustainable Travel Guidance on Bidding. Moving Britain Ahead
Access Fund for Sustainable Travel Guidance on Bidding Moving Britain Ahead July 2016 The Department for Transport has actively considered the needs of blind and partially sighted people in accessing this
Property Management Service Level Agreement
Property Management Service Level Agreement 2014 comms:3292 www.lancashire.gov.uk 2 Contents 3 Welcome Mission Statement 4 Customer Charter 5 Introduction 6 Responsibilities and Choices 7 Service Level
LTAS18.3 Recommendation for approval of the MSc, Postgraduate Diploma and Postgraduate Certificate in Professional Accountancy Programme (UCL)
Recommendation for approval of the MSc, Postgraduate Diploma and Postgraduate Certificate in Professional Accountancy Programme (UCL) Purpose Members of the Learning, Teaching and Assessment Sub-committee
Senior management team
June 2015 Senior management team Chief Executive s Office Peter Lauener, Chief Executive of the Skills Funding Agency The chief executive leads the agency and takes responsibility for all paid staff who
Customer requirements. Asset management planning Inspection and assessment Route asset planning Annual work plans Contracting strategy
Section 8 Output monitoring Inputs Customer requirements Safety standards Outputs and funding SRA and Government Policy Network stewardship strategy Asset and operational policies Maintenance & renewal
Business Services Authority
Student Services provided by Business Services Authority Issue 11 - April 2014 If you re from a university, college or assessment centre that works with students who are eligible for NHS or social work
Non Housing Capital Programme. PROJECT Outline Business Case
Non Housing Capital Programme PROJECT Outline Business Case Originating Service: Continuous Improvement. 1. Part A: Basic Proposal Details A.1 Description of proposal: (Please include details of any premises
Report of the Student Feedback Project Steering Group
Report of the Student Feedback Project Steering Group May 2003 Introduction 1. The Student Feedback Project Steering Group (SFPSG) was established in June 2002 in order to oversee: a. The development of
EXECUTIVE BURNLEY TOWN HALL
EXECUTIVE BURNLEY TOWN HALL Tuesday, 20 th September 2011 PRESENT MEMBERS Councillors Charlie Briggs (in the Chair), Roger Frost, Peter McCann, Neil Mottershead, Jeff Sumner and Linda White. OFFICERS Steve
Joint Audit Report for South Lakeland District Council. & Eden District Council
Joint Audit Report for South Lakeland District Council & Eden District Council Audit of IT Data Backup and Recovery Arrangements Audit of Development Management 22nd May 2015 11 th June 2015 0 Page 0 Audit
EMR Capacity Market Implementation Coordination Workshop
EMR Capacity Market Implementation Coordination Workshop Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight
MINUTES OF THE RESOURCES COMMITTEE MEETING HELD ON THURSDAY 15 MAY 2014 AT 2.00PM IN WATERSIDE TOWER, BELFAST
NORTHERN IRELAND POLICING BOARD MINUTES OF THE RESOURCES COMMITTEE MEETING HELD ON THURSDAY 15 MAY 2014 AT 2.00PM IN WATERSIDE TOWER, BELFAST PRESENT: POLICE SERVICE OF NORTHERN IRELAND IN ATTENDANCE:
Appendix 1e. DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA. Performance Management Framework
Appendix 1e DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA Performance Management Framework DISTRIBUTION LIST Audit Team David Esling, Head of Audit and Assurance - Risk Management
Appendix A : Stroke Project Governance Arrangements. October 2008
Appendix A : Stroke Project Governance Arrangements October 2008 1.1 HfL Governance Structure The governance arrangements for all HfL projects within the overall HfL Programme are illustrated below. The
Lead Officer(s) Present Rachael Shimmin (Chair) Corporate Director, Adults, Wellbeing and Health, DCC
Meeting: Date & Time: Venue: Safe Durham Partnership Board Monday, 25 th July 2011, 2pm Committee Room 1A, County Hall Item Present Rachael Shimmin (Chair) Corporate Director, Adults, Wellbeing and Health,
Regulatory Information and Data Quality Assurance Policy
ISSUE 1.0 Page 1 of 7 Regulatory Information and Data Quality Assurance Policy Contents Policy Scope Responsibility for Data Quality and Assurance Reference Documents The Data Quality Assurance Process
SUFFOLK FLOOD RISK MANAGEMENT JOINT SCRUTINY PANEL ANNUAL REPORT 2010. Working in Partnership with
SUFFOLK FLOOD RISK MANAGEMENT JOINT SCRUTINY PANEL ANNUAL REPORT 2010 Working in Partnership with Suffolk Flood Risk Management Joint Scrutiny Panel Foreword by Councillor Gary Green, Chairman of the Suffolk
Southern Health NHS Foundation Trust. Service Change Outline Paper Change of Base. Children s Division. In Confidence
Southern Health NHS Foundation Trust Service Change Outline Paper Change of Base Children s Division In Confidence Consultation Document, January 2015 Summary: This service change outline paper consults
Climate Local Hampshire County Council Our progress on November 2013
Climate Local Hampshire County Council Our progress on November 2013 Since signing up to Climate Local on in July 2013 we have made the following progress towards achieving the commitments and actions
Appenidx 1a. DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA REVIEW OF HOUSING COMPLIANCE AUDIT PROGRAMME
Appenidx 1a DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA REVIEW OF HOUSING COMPLIANCE AUDIT PROGRAMME DISTRIBUTION LIST Audit Team David Esling, Head of Audit and Assurance
Customer Service Strategy 2010-2013
Service Strategy 2010-2013 Introduction Our vision for customer service is: Oxfordshire County Council aims to deliver excellent customer service by putting our customers at the heart of everything we
Public Transport Vehicle Management System. Request for Information
Public Transport Vehicle Management System Request for Information Public Transport Authority Western Australia Page 2 of 11 Table of Contents 1 INTRODUCTION... 3 1.1 Information for Respondents... 3 1.2
Minutes of Meeting of the VisitScotland Board held on 4 July 2014
Meeting Minutes Minutes of Meeting of the VisitScotland Board held on 4 July 2014 Present: In attendance: Apologies: Minutes: Mike Cantlay (Chairman) Stephen Carter Paddy Crerar Steve Dunlop Dorothy Fenwick
Network Certification Body
Network Certification Body Scheme rules for assessment of railway projects to requirements of the Railways Interoperability Regulations as a Notified and Designated Body 1 NCB_MS_56 Contents 1 Normative
Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding
Committee and Date Cabinet 14 th October 2015 Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding Responsible Officer
LINCOLNSHIRE COUNTY COUNCIL. JEM Number: 2099
LINCOLNSHIRE COUNTY COUNCIL JOB DESCRIPTION DIRECTORATE: Resources Division/Section/Branch: Business Improvement Service/Sub-Division: JOB TITLE: Customer Relationship Management Analyst JEM Number: 2099
Pavement Condition Information Systems support contract
Pavement Condition Information Systems support contract UK Roads Board Advisory Group Presented by Barry Cleave 17 th March 2009 Objective Support for Local Authority Pavement Condition Information Systems..to
WASH EAST COAST MANAGEMENT STRATEGY FUNDING GROUP MEETING
WASH EAST COAST MANAGEMENT STRATEGY FUNDING GROUP MEETING Minutes of the Meeting of the above held on Tuesday 29 September 2015 at 3.00pm in the Chief Executive s Office, King s Court, Chapel Street, King
Neath Port Talbot Council Senior Management Structure. Aiming to promote equality of opportunity in jobs and services
Neath Port Talbot Council Senior Management Structure Corporate Group Chief Executive Steven Phillips Environment John Flower Finance & Corporate Services Hywel Jenkins Social Services, Health & Housing
Trust Board Report. Review of the effectiveness of the IM&T Committee
1. Introduction Trust Board Report Review of the effectiveness of the The meets every eight weeks, with a specific responsibility for governance, strategic direction, approval and direction of developments
Report of the Assistant Director Strategy & Performance to the meeting of Corporate Governance & Audit Committee to be held on 20 March 2009.
Report to the Corporate Governance & Audit Committee. Report of the Assistant Director Strategy & Performance to the meeting of Corporate Governance & Audit Committee to be held on 20 March 2009. Subject:
Babergh & Mid Suffolk: Corporate Management Team (January 2014)
Babergh & Mid Suffolk: Corporate Team (January 2014) People Communities Strategic Director People: Mike Evans, 825746, 724804, email: [email protected] Head of Service: Jonathan Free, 826649,
HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK
HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK July 2013 1 P age Contents Page 1.0 Definition 3 2.0 Context 3 3.0 Purpose and aim of the policy 4 4.0 Policy Statement 4 5.0 Framework for Performance Management
Passenger Rail Service Satisfaction. 2014-15 Quarter 2 Statistical Release. 18 December 2014. Responsible Statistician: Dr Fazilat Dar
Passenger Rail Service Satisfaction 2014-15 Quarter 2 Statistical Release 18 December 2014 Responsible Statistician: Dr Fazilat Dar 020 7282 3705 Further information Media Enquiries: 020 7282 2094 Contents
Councillor Richard Blunt 01530 454510 [email protected]
NORTH WEST LEICESTERSHIRE DISTRICT COUNCIL POLICY DEVELOPMENT GROUP 19 MARCH 2013 Title of report EFFECTIVE ASSET MANAGEMENT ACCESS LICENCES Councillor Richard Blunt 01530 454510 [email protected]
Regulation Regulation Regulation. Conference Programme 2013. 02/07/13 America Square Conference Centre, London www.insuranceage.co.
02/07/13 America Square Conference Centre, London www. Conference Programme 2013 #iaregulation Dear colleague, I am delighted to announce the launch of an Insurance Age specific event: The Three R s. Join
UoD IT Job Description
UoD IT Job Description Role: Projects Portfolio Manager HERA Grade: 8 Responsible to: Director of IT Accountable for: Day to day leadership of team members and assigned workload Key Relationships: Management
Chairman Simon Cole Vice Chairman Bill Sadler
Overview and Scrutiny Committee Minutes of a meeting of the Overview and Scrutiny Committee held on Thursday 10 March 2016 at 6.00 pm at the Council Chamber, District Offices, College Heath Road, Mildenhall
DATA QUALITY STRATEGY
DATA QUALITY STRATEGY If you or anybody you know requires this or any other council information in another language, please contact us and we will do our best to provide this for you. Braille, Audio tape
Investors in People 2013 - Communications Plan. Introduction What is IiP?
Investors in People 2013 - Communications Plan Introduction What is IiP? Investors in People specialises in transforming business performance through our employees. It is designed to help the Council achieve
Advanced Practice (Public Health)
Advanced Practice (Public Health) Author: Claire Barley (Head of Professional and Organisational Development) and Kelly McFadyen (Professional and Organisational Development Manager) Date: 2 December 2014
Corporate Governance Report
Corporate Governance Report Corporate Governance Report Corporate Governance Practices The missions of the Corporation are to promote: stability of the banking sector wider home ownership development of
Community engagement: Developing a strategy
Community engagement: Developing a strategy Some questions to help with planning... This guidance outlines some important things to consider when planning a community engagement strategy for your project
Urgent and Emergency Care Project Governance
Urgent and Emergency Care Project Governance Introduction Improving Urgent and Emergency Care for people in Northern Devon is a key priority for both Commissioner and Provider. The slide inserted below
December 2011 Christmas media reception Bute House January 2012 Tom Bradby, Political Editor, ITV Interview
s with Proprietors, Editors and Media Executives August 2011 - August 2012 Alex Salmond MSP, First Minister September 2011 Derek Lambie, Editor & Ben Borland, Sunday Express September 2011 Rob Woodward,
U32803: Develop direct marketing plans PERFORMANCE CRITERIA. Unit Descriptor: Develop direct marketing plans
U32803: Unit Descriptor: This unit is about developing direct marketing plans and associated budgets. It includes establishing and coordinating the messages to be communicated, agreeing the direct marketing