6 Road network rehabilitation programme

Size: px
Start display at page:

Download "6 Road network rehabilitation programme"

Transcription

1 6 Road network rehabilitation programme

2 114 6 Road network rehabilitation programme 6.1 Introduction Strategic focus The Master Plan has concluded that roads will continue to be the dominant domestic mode only roads can provide access to all parts of the country and many trips made by other modes will inevitably use roads for their initial and final stages. The Master Plan has consequently concluded that Liberia should: rehabilitate the all-weather strategic primary network 41 that links Monrovia to the county capitals and to its main border points with Sierra Leone, Guinea and the Ivory Coast including pavement if funds are available; and construct two new links that could save substantial travel costs reduction: these are Buchanan totappita and Buchanan to Harper, on condition that these new development will not negatively impact resources to maintain existing infrastructure assets in maintainable condition. Addition links may be identified, provided that sufficient funding is provided to keep existing infrastructure in maintainable condition and these links can be justified on the basis of technical survey studying the financial, economic, social and environmental impacts. Given the high costs of current travel and the level of frustrated demand that is believed to exist, the Master Plan proposes to have this rehabilitated network completed as rapidly as possible and a five year timetable is proposed for re-establishing basic functionality. To speedily restoring the living conditions in Liberia as soon as possible, the National Transport Master Plan aims at providing access to all sections of the population and facilitating safe, comfortable transport at a design standard of 60 miles per hour or lower depending on the classification of road on the primary, secondary and feeder road network. The National Transport Master Plan adopts a flexible approach. With the focus of transport policy centred on the need for speedy improvements, Government of Liberia chooses to take optimum use of its limited resources. Provided funding is available, the National Transport Master Plan proposes to apply design standards at an economic optimum. In case of budget constraints, the National Transport Master Plan suggests to select design standards at the least life-cycle costs. A summary of the general 5 years Road Rehabilitation Plan and the 10 years Maintenance Program is shown in Table Introduction to the Roads Economic Decision (RED) Model The principal tool adopted for the prioritisation of these investments has been the World Bank s Roads Economic Decision Model (RED). The RED Model User Manual 42 (see appendix F on CD) states that the model was developed to improve the decision-making process for the development (...) of low-volume rural roads. The model performs an economic evaluation of road investment options using the consumer surplus approach and is customised to the characteristics and needs of low-volume roads such as the high uncertainty 41 The base network which has been analysed to date consists of approximately 2,300 km of mainly primary (but some secondary) roads. The full picture will, however, only emerge when data has been collected and analyses have been undertaken of the full primary and secondary networks. 42 Sub-Saharan African Transport Policy Program (SSATP) Working Paper 78, The Roads Economic Decision Model (RED) for the Economic Evaluation of Low Volume Roads Software User Guide and Case Studies ; Rodrigo Archondo-Callao.

3 Road network rehabilitation programme of the assessment of model inputs, particularly the traffic on and condition of unpaved roads, the importance of vehicle speeds for model validation, the need for a comprehensive analysis of generated and induced traffic (...) RED computes benefits for normal, generated, induced and diverted traffic and takes into account changes in road length, condition, geometry, type accidents and days per year when the passage of vehicles is further disrupted by a highly deteriorated road condition (wet season) (...) The model is presented on a series of Excel 2000 Workbooks that collects all user inputs, presents the results in an efficient manner and performs sensitivity, switching value and risk analyses. The model presents its results in the form of investment programme which initially assumes an Unconstrained Budget. The user has, however, the option to develop alternative investment programmes/options based on up to five constrained (fixed) budgets. With the limited data-base currently available in Liberia, RED is, thus, a highly appropriate tool for prioritising road rehabilitation works RED input data: the Liberian context General RED requires: link-by-link road description data; link-by-link road traffic data; vehicle utilisation and unit price data; estimates of the values of passenger-time, cargo-holding times and accident costs; capital and maintenance costs for a do nothing base option and for a series of up to six rehabilitation options; and some additional data pertinent to general conditions in Liberia and the nature of the analyses to be undertaken. In the sections below, the project-specific approach to the gathering and analysis of this data is reported. The RED User Manual (appendix F on CD) should be referred to for definitions and for a description of how RED manipulates the data that is input Link-by-link road characteristics In the project context the most important data are: Link lengths: in most cases these were project GPS measured lengths and the information used in these RED analyses therefore supersedes information held on previous Liberian data, i.e. the National Roads Register. Existing and future widths: in most cases these were as measured during the on-site project data collection, RCS, inventory. Terrain description: RED allows three different categories to be defined for modelling purposes in the Liberian context these have been described as flat, rolling and mountainous with each link assigned to a specific category.

4 116 Road network rehabilitation programme Present and future surface types and conditions derived in terms of: surface type: RED allows three different categories to be defined for modelling purposes in the Liberian context these were paved, gravel and earth with each link assigned to a specific category. the International Roughness Index (IRI): which is measure of the average extents of all rises and all falls experienced by the vehicle s suspension per km of travel. As no roughness measuring devices were available to the project, the Roughness of each link was determined via a proxy. Usefully RED can apply algorithms that convert comfortable driving speed to an approximation of roughness on a link-by-link basis Link-by-Link road traffic data In general RED requires dry and wet season base present annual average daily traffic volumes for each of up to nine different vehicle categories. The user selects from sixteen predetermined motorised and four predetermined non-motorised vehicle categories that best describe the categories for which classified count data is available. For the project, eight of the RED-defined categories (all motorised) were used for modelling, viz; 1. motorcycle; 2. car small; 3. car medium (taxi); 4. bus mini; 5. bus medium 6. four-wheel drive; 7. truck medium; 8. truck articulated; In addition, the following data were necessary: separate annual traffic growth forecasts for each of the above-listed vehicle categories which can be adjusted upwards or downwards at the end of each five-years in the analysis period; and estimates for the volumes of generated and/or induced traffic. A brief description of the approach to these inputs is provided below. Traffic volumes: dry and wet season base volumes For the two seasons, the RED applied base traffic volumes derive from a number of sources each of which is described below: When both dry and wet season classified count data were available: both data sets have been used in the RED analyses the RED-estimated economic returns, in these instances, can consequently be considered most reliable. When only wet or dry season classified count data were available: the missing seasonal traffic data-set has been estimated from (i) the one data-set available and (ii) from generalised information on the ratio between wet and dry season traffic.

5 Road network rehabilitation programme When neither wet nor dry season data available but there was some old 1981 data (from the GIZ Economic Development Plan for Liberia, 1983) where the present traffic has been estimated by increasing the 1981 volumes by the average annualised growth rate since that date 43. When neither wet nor dry season data was available and there is no 1981 data: estimates for present traffic has been made by either: moving observer counts: as this is the most crude of all the methods used, the RED-estimated economic returns must be treated with most caution; or inputting a nominal single vehicle in each season: in this case the link is included in the analyses only in order to allow future estimates of economic returns when proper traffic data becomes available the RED estimated economic returns for these links are not meaningful. 117 Base traffic volumes: adjustments for night-time traffic The results from three night-time (18:00 to 06:00) classified count surveys are summarised on Table A.65 in Appendix A (see attached CD). On the same table, adjustment factors to convert the 12-hour counts to 24-hour estimates of AADT are also provided. Base traffic volumes: traffic growth Traffic is forecast to grow at the rates derived on Table 5-10 and takes account of the forecast growth in GDP, forecasts of population growth and the elasticity between growth in GDP and growth in travel by each vehicle type. The forecasts are, therefore, different for each vehicle type. Base traffic volumes: summarised traffic inputs A link-by-link summary of the RED-modelled dry and wet season base-traffic volumes and of the numbers of days assumed per year for each season is provided in Appendix N. Also shown on this table are the link-by-link applied: night-time correction multipliers for different vehicle types (multipliers for links in and around Monrovia and away from Monrovia are shown separately); seasonal correction multipliers: multipliers for stations with only wet season counts are separated from those for stations with only dry season counts; and multipliers for links in and around Monrovia and away from Monrovia are shown separately. when appropriate, the approaches adopted to forecasting for links with neither dry nor wet season counts are indicated. Generated traffic There is insufficient data to make separate link-by-link estimates of generated traffic. As there is believed to be much frustrated demand, an elasticity of demand with price of 1.0 has been applied. This means that for every 10% reduction in cost there will be a corresponding 10% increase in travel. On links where costs are reduced the most, the volume of generated traffic will consequently also be highest. As the model predicts reductions in cost of the order 30-40%, there is likely to be much generated traffic. This assumption in regard to generated traffic should, however, be revisited after data on traffic before and after rehabilitation becomes available. 43 This information is provided in appendix D on CD. As the traffic forecasting method is crude, the RED-estimated economic returns for these roads must be treated with caution.

6 118 Road network rehabilitation programme Vehicle utilisation and unit price data Comprehensive vehicle utilisation and unit price data is required by RED. The data derives from a number of sources within Liberia and also from neighbouring countries. As and when better locally-derived data becomes available, this should replace the data presently being applied Estimates of values of passenger times, cargo holding times and accident costs The applied values of passenger time are all based on working time. For the purposes of the RED evaluations, it has been assumed that the majority of passenger trips have ultimate origins or destinations in the Monrovia region and that most passenger trips are generated by higher income groups. It has been assumed that small car and 4-wheel drive vehicle passenger trips are generated by the highest income groups, groups with an average annual income of about USD 2,000 (or about USD1 per hour (40 hrs per week; 50 weeks per year); taxi passenger trips are assumed to be generated by groups with an average income of about USD 1,200 per year (60 US cents per hour), bus and truck passenger trips are assumed to be generated by groups with an average income of about USD 1,000 per year (50 US cents per hour). As it is noted that the tariffs for motorcycle (taxi) trips are higher than those for motor-car taxi trips the average income has been estimated as USD 1,500 per year (75 US cents per hour). Cargo holding times are relevant only when there is much freight that has a high per tonne value (for example, manufactured electronic goods) and/or which is perishable. This Master Plan, as is the case with most economic appraisals for road investments with low traffic volumes, does not incorporate this data. Insufficient data on the present severity, cost and frequency of accidents on roads of different standards was available and the incorporation of accident benefits was unnecessary in order to justify the rehabilitation programme. The incorporation of this data should, however, be considered when data does become available. It is, however, unlikely to significantly affect the priority order of a rehabilitation programme Capital and maintenance costs for a do nothing base option and for the rehabilitation options Expected capital rehabilitation and recurrent maintenance costs are provided on Table N-1; Table N-2, Table N-3, Table N-4, Table N-5 and Table N-6 in appendix N (see attached CD) Additional data pertinent to general conditions in Liberia and the nature of the analyses The analysis is based on: an opportunity cost of capital of 12% which consistent with the appraisals for other sectors; an analysis/benefit stream of ten years that is consistent with the appraisals for the other sectors and appropriate given that the appraisal focus on emergency rehabilitation ; 2010 constant prices and a 2010 base year; A Roads Agency economic cost factor of 0.9 defined as the assumed ratio between economic and financial costs applicable to the proposed investments in rehabilitation and maintenances. In its simplest form this ratio would be that which derives when taxes are removed from the costs,

7 Road network rehabilitation programme though it is often appropriate to value resources in over-supply (particularly unskilled labour) at rates that are much less than local-market costs and to value resources which are in short-supply, (frequently foreign-sourced items) at rates that are higher than local-market costs. Given the expected high rates of return and the present emphasis on priority ordering this initial simplification is considered acceptable Modelling conclusions - rehabilitation programmes The RED analyses have indicated that a substantial rehabilitation programme and the construction of two missing links would have substantial economic benefits. A five-year unconstrained emergency rehabilitation investment program is recommended by RED and is set out on the following pages. The required total expenditure over the emergency rehabilitation programme s projected fiveyear life would be about USD 172 million (see Table N-1 in Appendix Y). Additionally, about USD 18 million per year would have to be spent on recurrent maintenance to ensure that the network does not return to its present unacceptable condition. The construction of the two missing links would add another about USD 10 million. Five-year rehabilitation programmes based on total 5-year emergency rehabilitation reduced budgets of USD 100 million, USD 75 million, USD 50 million, USD 17 million, USD 10 million and, in the last case, just USD 5 million are shown on Table N-2, Table N-3, Table N-4, Table N-5 and Table N-6. An examination of Table N-2, Table N-3, Table N-4, Table N-5 and Table N-6 shows that as the available budgets fall: increasing proportions of the roads are recommended to be initially rehabilitated at reduced standards; and the rehabilitation of some other roads, where only basic standards are proposed fall out of the initial programme. A preliminary economic justification of the two missing links is provided in appendix G on CD. These are the routes: from Monrovia via Buchanan to Tappita (and thence to the Ivory Coast Border); and from Monrovia via Buchanan along the South Coast to Harper, Fishtown and Barclayville. The estimated cost of providing both links is USD 9.9 million. As the estimated economic returns are very high, these roads would ideally be constructed simultaneously with the emergency rehabilitation programme. Additional investments to bring the network to full, economically-justified, standards must, of course, be applied in a post-emergency rehabilitation follow-on period.

8 120 Road network rehabilitation programme Figure 6-1: RED scenario unconstrained budget

9 Ministry of Transport Parker House / Broad Street Monrovia, Liberia Ministry of Public Works Lynch Street Monrovia, Liberia

PAVEMENT MANAGEMENT ANALYSIS USING RONET: CASE OF THE FREE STATE PROVINCE. SARF/IRF 2014 2-4 September, South Africa

PAVEMENT MANAGEMENT ANALYSIS USING RONET: CASE OF THE FREE STATE PROVINCE. SARF/IRF 2014 2-4 September, South Africa PAVEMENT MANAGEMENT ANALYSIS USING RONET: CASE OF THE FREE STATE PROVINCE DR. M MOSTAFA HASSAN MR. TJ MOSIANEDI SARF/IRF 2014 2-4 September, South Africa PRESENTATION LAYOUT Current condition of Free State

More information

The World Bank. 1 System choice

The World Bank. 1 System choice Selecting road management systems (Source: Robinson, R, 1995. Rethinking policy, strategy and information under severe budget constraints: management information and tools to prioritise works. In: World

More information

Demand for Long Distance Travel

Demand for Long Distance Travel Demand for Long Distance Travel April 2011 Demand for long distance travel 1 Structure of this paper 1.1 This paper is structured as follows: Section 2 sets out past trends in the demand for long distance

More information

Road Asset Management vs Pavement Management A new Paradigm. Arthur Taute Stewart Russell

Road Asset Management vs Pavement Management A new Paradigm. Arthur Taute Stewart Russell Road Asset Management vs Pavement Management A new Paradigm Arthur Taute Stewart Russell Contents Background Definitions Improvements over PMS TMH22 elements Conclusions BACKGROUND Municipal AMS GRAP17

More information

Mary Immaculate College. Travel and Expenses Policy

Mary Immaculate College. Travel and Expenses Policy 1. Introduction Mary Immaculate College Travel and Expenses Policy Adopted by ABR Pro Tem on 17 Dec. 2014 Updated to comply with Circular 05/2015 from 1 st July 2015 The M.I.C. Travel & Expenses Policy

More information

Debt Financing for MP2030

Debt Financing for MP2030 CHAPTER 7 FUNDING ASSESSMENT 7.1 Under the Airport Authority Ordinance, AAHK is required to conduct its business according to prudent commercial principles. It has maintained an efficient capital structure

More information

Draft TMH 22 ROAD ASSET MANAGEMENT MANUAL

Draft TMH 22 ROAD ASSET MANAGEMENT MANUAL -- South Africa COTO Committee of Transport Officials Draft TMH 22 ROAD ASSET MANAGEMENT MANUAL M a r c h 2013 C ommittee of Transport Officials Contents Background Process Contents of Manual Quo Vadis

More information

Cycle Strategy 2006 2011

Cycle Strategy 2006 2011 Cycle Strategy 2006 2011 TABLE OF CONTENTS 1 INTRODUCTION... 1 2 POLICY BACKGROUND... 2 3 BACKGROUND... 6 4 MAIN OBJECTIVES... 8 5 TARGETS... 9 6 THE CYCLE NETWORK... 10 7 CONCLUSION... 13 Appendix A:

More information

TEC Capital Asset Management Standard January 2011

TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining

More information

Project Evaluation Guidelines

Project Evaluation Guidelines Project Evaluation Guidelines Queensland Treasury February 1997 For further information, please contact: Budget Division Queensland Treasury Executive Building 100 George Street Brisbane Qld 4000 or telephone

More information

A SUSTAINABLE. ANNEx 9: USEr S GUIDE To TEChNICAL FoLDErS

A SUSTAINABLE. ANNEx 9: USEr S GUIDE To TEChNICAL FoLDErS A SUSTAINABLE journey To work IN SoUTh yorkshire ANNEx 9: USEr S GUIDE To TEChNICAL FoLDErS CONTENTS 1. Introduction...2 1.1. The Annex Documents...2 1.2. This Document...2 2. Folder A -Walking and Cycling

More information

GIS a Tool for Transportation Infrastructure Planning in Ghana A Case Study to the Department of Feeder Roads

GIS a Tool for Transportation Infrastructure Planning in Ghana A Case Study to the Department of Feeder Roads GIS a Tool for Transportation Infrastructure Planning in Ghana A Case Study to the Department of Stephen Yao FIATORNU, Ghana Key words: SUMMARY With the development of GIS technology, network transportation

More information

Development of a Concept for the Public Transport Interconnectivity for Savaria International Airport. Report

Development of a Concept for the Public Transport Interconnectivity for Savaria International Airport. Report Development of a Concept for the Public Transport Interconnectivity for Savaria International Airport Report CENTRAL EUROPE Programme Project CHAMPIONS February 2012 Development of a Concept for the Public

More information

Asset Management Plan Overview

Asset Management Plan Overview Council Strategy Asset Management Plan Overview City of Albany 2013 File Ref: CM.STD.6 Synergy Ref: NMP1331749 102 North Road, Yakamia WA 6330 Version: 25/06/2013 PO Box 484, ALBANY WA 6331 Tel: (08) 9841

More information

Welsh Ambulance Services NHS Trust

Welsh Ambulance Services NHS Trust Welsh Ambulance Services NHS Trust Financial Support to replace obsolete Ambulance Vehicles 2008/09 BUSINESS JUSTIFICATION CASE Version No: Page 1 of 10 VERSION HISTORY Version Date Brief Summary of Change

More information

TH 23 Access Management Study Richmond to Paynesville

TH 23 Access Management Study Richmond to Paynesville TH 23 Access Management Study Richmond to Paynesville Prepared For: Minnesota Department of Transportation District 8 Prepared By: Short Elliott Hendrickson Inc. July 2015 Table of Contents I. Introduction...

More information

Section Description Page

Section Description Page Foreword This Transport Asset Management Plans (TAMP) sets out the County Council's proposed 15 year strategy to maintain and improve the transport asset network in Lancashire between now and 2029. Lancashire

More information

Better Connected. Economic Appraisal Report. April 2014. Norfolk County Council

Better Connected. Economic Appraisal Report. April 2014. Norfolk County Council Better Connected Economic Appraisal Report April 2014 Norfolk County Council Document Control Sheet Project Title Report Title Better Connected Economic Appraisal Report Report ref no. 1059214 Version

More information

Discussion Paper 01: Aviation Demand Forecasting

Discussion Paper 01: Aviation Demand Forecasting Airports Commission Discussion Paper 01: Aviation Demand Forecasting Response from Kent County Council and Medway Council Q1: To what extent do you consider that the DfT forecasts support or challenge

More information

Hamilton Truck Route Study

Hamilton Truck Route Study Prepared for the City of Hamilton March 2012 Pavlos S. Kanaroglou, Ph.D. Vivek Korikanthimath, Ph.D. McMaster Institute of Transportation and Logistics McMaster University Hamilton, Ontario March 2012

More information

Road Asset Management Research Program In Finland

Road Asset Management Research Program In Finland Langfassung / long version Road Asset Management Research Program In Finland Abstract Mr. Vesa Männistö, M.Sc. (Statistics) Inframan Ltd Länsituulentie 10, 02100 Espoo, Finland Tel +358-9-8567 7715, fax

More information

Phase Attribute Identification using GPS Technology

Phase Attribute Identification using GPS Technology Phase Attribute Identification using GPS Technology Date 11 June 2009 John Sinclair Power Quality Manager Slide 1 Topics of Discussion Remote Phase Identification How it works Principals of operation Benefits

More information

Finding the best fare structure for Opal

Finding the best fare structure for Opal Independent Pricing and Regulatory Tribunal Finding the best fare structure for Opal Public transport fares in Sydney and surrounds Transport Issues Paper July 2015 Finding the best fare structure for

More information

Virtual Weigh Stations: The Business Case

Virtual Weigh Stations: The Business Case Virtual Weigh Stations: The Business Case Technical Memorandum Prepared for Partners for Advanced Transit and Highways (PATH) Institute of Transportation Studies University of California, Berkeley and

More information

SAFETY IN NUMBERS: EVALUATING CANADIAN RAIL SAFETY DATA

SAFETY IN NUMBERS: EVALUATING CANADIAN RAIL SAFETY DATA Volume 6 Issue 2 April 2014 SPP Communiqués are brief articles that deal with a singular public policy issue and are intended to provide the reader with a focused, concise critical analysis of a specific

More information

Slough Borough Council. Highway Asset Management Strategy

Slough Borough Council. Highway Asset Management Strategy Slough Borough Council Highway Asset Management Strategy OUR AMBITION USING RESOURCES WISELY By 2019 the Council s income and the value of its assets will be maximised 1 Key Priorities 1.1 We understand

More information

www.nams.au.com AN INNOVATIVE APPROACH TO LOCAL GOVERNMENT ROAD NETWORK MANAGEMENT

www.nams.au.com AN INNOVATIVE APPROACH TO LOCAL GOVERNMENT ROAD NETWORK MANAGEMENT AN INNOVATIVE APPROACH TO LOCAL GOVERNMENT ROAD NETWORK MANAGEMENT Peter Clewer: Asset Management Officer (Roads), Mornington Peninsula Shire Amy Wade, Manager Axim - A Downer EDI Works Business Abstract

More information

TRAFFIC GROWTH RATE ESTIMATION USING TRANSPORT DEMAND ELASTICITY METHOD: A CASE STUDY FOR NATIONAL HIGHWAY-63

TRAFFIC GROWTH RATE ESTIMATION USING TRANSPORT DEMAND ELASTICITY METHOD: A CASE STUDY FOR NATIONAL HIGHWAY-63 TRAFFIC GROWTH RATE ESTIMATION USING TRANSPORT DEMAND ELASTICITY METHOD: A CASE STUDY FOR NATIONAL HIGHWAY-63 Hemanth. M Kamplimath 1, Varuna. M 2, Vijay Kumar 3, Yashas Bhargav 4 1 Post Graduate Student,

More information

ROADING ASSET MANAGEMENT PLAN

ROADING ASSET MANAGEMENT PLAN ROADING ASSET MANAGEMENT PLAN 1 EXECUTIVE SUMMARY 1.1 Overview This Roading Asset Management Plan (RAMP) follows the format recommended by the National Asset Management Steering Group (NAMS) and is largely

More information

Bicycle Safety Webinar December 1 st 2010

Bicycle Safety Webinar December 1 st 2010 Bicycle Safety Webinar December 1 st 2010 Kay Teschke Kay Teschke is Professor in the Schools of Population and Public Health and of Environmental Health at the University of British Columbia. She is principal

More information

Capital Planning Guidelines

Capital Planning Guidelines Capital Planning Guidelines Contents Capital Planning Guidelines... 1 1. INTRODUCTION... 3 2. CAPITAL PROJECTS EVALUATION PROCESS... 3 3. APPRAISAL PROCESS UNDERTAKEN BY DEPARTMENTS... 4 3.1 Extension

More information

GO Skegness. Economic Appraisal Report. April 2014. Lincolnshire County Council

GO Skegness. Economic Appraisal Report. April 2014. Lincolnshire County Council GO Skegness Economic Appraisal Report April 2014 Lincolnshire County Council Document Control Sheet Project Title Report Title GO Skegness Economic Appraisal Report Report ref no. 1055898 Version 1.0 Status

More information

CAPITAL PLANNING GUIDELINES

CAPITAL PLANNING GUIDELINES CAPITAL PLANNING GUIDELINES 1. INTRODUCTION... 2 2. EXTENSION OF EXISTING INFRASTRUCTURE PROJECTS... 2 3. NEW CAPITAL PROJECTS... 2 4. MINIMUM INFORMATION REQUIRED... 3 5. PREPARATORY WORK... 3 5.1 NEEDS

More information

Week 3: Road Asset Management. Day 1 - Monday 10 June 2002. Road Asset Management Principles

Week 3: Road Asset Management. Day 1 - Monday 10 June 2002. Road Asset Management Principles Week 3: Road Asset Management Day 1 - Monday 10 June 2002 Road Asset Management Principles CONTENTS Road Asset Management...1 Introduction... 1 Asset management planning... 1 Benefits of Asset Planning...

More information

Travel and subsistence policy

Travel and subsistence policy Travel and subsistence policy Contents 1 Introduction... 3 2 Policy and principles... 3 3 Roles and responsibilities... 3 4 Dispensations... 4 5 Errors... 4 6 Travel costs... 4 7 Travel by road... 5 8

More information

Water Mains Rehabilitation Framework (NI) Northern Ireland Water

Water Mains Rehabilitation Framework (NI) Northern Ireland Water PROJECT: CLIENT: MAIN CONTRACTOR: Water Mains Rehabilitation Framework (NI) Northern Ireland Water Farrans Background Northern Ireland Water manages a water mains infrastructure that supplies 625 million

More information

Ohio Standard Small/Medium MPO Travel Demand Forecasting Model. Theoretical Training May 10-11, 2006 Abridged to Freight Focus Sept 2010

Ohio Standard Small/Medium MPO Travel Demand Forecasting Model. Theoretical Training May 10-11, 2006 Abridged to Freight Focus Sept 2010 Ohio Standard Small/Medium MPO Travel Demand Forecasting Model Theoretical Training May 10-11, 2006 Abridged to Freight Focus Sept 2010 Model Overview Key Features Modeling of highway and non highway modes

More information

How should we prioritise incident management deployment?

How should we prioritise incident management deployment? Marschke, Ms Kath and Ferreira, Dr Luis and Bunker, Dr Jonathan (2005) How should we prioritise incident management deployment?. In Proceedings Australasian Transport Research Forum, Sydney 2005. How should

More information

2013 Benefit-Cost Analyses Guidance for TIGER Grant Applicants

2013 Benefit-Cost Analyses Guidance for TIGER Grant Applicants 2013 Benefit-Cost Analyses Guidance for TIGER Grant Applicants Each applicant should provide evidence that the expected benefits of the project justify the costs (recognizing that some costs and benefits

More information

Asset Management Plan

Asset Management Plan Wandering Shire Council Roads Asset Management Plan TABLE OF CONTENTS 1 Executive Summary... 2 Context... 2 Questions you may have... 4 2. INTRODUCTION... 5 2.1 Background... 5 2.2 Goals and objectives

More information

CHAPTER 2 PAVEMENT MANAGEMENT SYSTEM

CHAPTER 2 PAVEMENT MANAGEMENT SYSTEM CHAPTER 2 PAVEMENT MANAGEMENT SYSTEM 2.1. INTRODUCTION TO PAVEMENT MANAGEMENT The ability of a pavement system to serve a society is largely a function of planning. Planning is the intersection between

More information

Roads Task Force - Technical Note 10 What is the capacity of the road network for private motorised traffic and how has this changed over time?

Roads Task Force - Technical Note 10 What is the capacity of the road network for private motorised traffic and how has this changed over time? Roads Task Force - Technical Note 10 What is the capacity of the road network for private motorised traffic and how has this changed over time? Introduction This paper forms one of a series of thematic

More information

Economic Analysis Reports: Briefing. Transportation Finance Panel

Economic Analysis Reports: Briefing. Transportation Finance Panel Economic Analysis Reports: 1. I-84 Viaduct in Hartford 2. I-84/Rt8 Mixmaster in Waterbury 3. New Haven Rail Line Briefing for Transportation Finance Panel Nov 23, 2015 Economic analyses 1 & 2 1. I-84 Viaduct

More information

Cycling Demonstration Towns Development of Benefit-Cost Ratios

Cycling Demonstration Towns Development of Benefit-Cost Ratios Cycling Demonstration Towns Development of Benefit-Cost Ratios Executive summary 1. In 2005, Cycling England launched a Cycling Demonstration Town programme to invest in measures to stimulate increased

More information

Improved Decision-Making Through Effective Asset Management

Improved Decision-Making Through Effective Asset Management Improved Decision-Making Through Effective Asset Management Rob Corazzola, P.Eng., Hansen Canada Co-authored by Jon Poli, PE, Hansen Paper prepared for presentation At the Roadway Inventory and Condition

More information

Ex-Post Monitoring Report Trans-Island Highway Construction Project (I) (II) in Papua New Guinea

Ex-Post Monitoring Report Trans-Island Highway Construction Project (I) (II) in Papua New Guinea Ex-Post Monitoring Report Trans-Island Highway Construction Project (I) (II) in Papua New Guinea Evaluator:Atsushi Hashimoto (Maenam Advisory) Field Survey: June 2008 1. Outline of the Project and Japan

More information

Concept for Railway and Transportation in Southern Norway. High Speed Line Oslo Hadeland Gjøvik Moelv. with High Speed Line Oslo Trondheim / Ålesund

Concept for Railway and Transportation in Southern Norway. High Speed Line Oslo Hadeland Gjøvik Moelv. with High Speed Line Oslo Trondheim / Ålesund Concept for Railway and Transportation in Southern Norway High Speed Line with High Speed Line Oslo Trondheim / Ålesund DB International GmbH Ottmar Grein Gjøvik, 28.10.2011 Concept for Railway and Transportation

More information

THE PROJECTED ECONOMIC AND FISCAL IMPACTS OF A TENNESSEE HISTORIC REHABILITATION INVESTMENT INCENTIVE

THE PROJECTED ECONOMIC AND FISCAL IMPACTS OF A TENNESSEE HISTORIC REHABILITATION INVESTMENT INCENTIVE THE PROJECTED ECONOMIC AND FISCAL IMPACTS OF A TENNESSEE HISTORIC REHABILITATION INVESTMENT INCENTIVE February 2014 Prepared by: Economic Impact Group, LLC. Copyright 2014 Economic Impact Group, LLC. EXECUTIVE

More information

Compliance Plan for Ministry of Labour Order Regarding Driver Training

Compliance Plan for Ministry of Labour Order Regarding Driver Training Compliance Plan for Ministry of Labour Order Regarding Driver Training The Corporation of the City of Windsor places the safety of its staff members as one of its highest priorities. An order issued by

More information

CITY OF GREATER SUDBURY. Municipal Roads, Structures and Related Infrastructure. Final Report. July 10, 2012

CITY OF GREATER SUDBURY. Municipal Roads, Structures and Related Infrastructure. Final Report. July 10, 2012 CITY OF GREATER SUDBURY Financial Planning for Municipal Roads, Structures and Related Infrastructure Final Report July 10, 2012 Financial Planning for Roads Table of Contents I. Financial Planning for

More information

Commercialization of Transport and Logistics Storage Logistics Supply Logistics Administrative Management of International Trade

Commercialization of Transport and Logistics Storage Logistics Supply Logistics Administrative Management of International Trade EUROPASS DIPLOMA SUPPLEMENT TITLE OF THE DIPLOMA (ES) Técnico Superior en Transporte y Logística TRANSLATED TITLE OF THE DIPLOMA (EN) (1) Higher Technician in Transports and Logistics ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

More information

Estimating urban traffic and congestion cost trends for Australian cities. Working Paper No 71

Estimating urban traffic and congestion cost trends for Australian cities. Working Paper No 71 Estimating urban traffic and congestion cost trends for Australian cities Working Paper No 71 Bureau of Transport and Regional Economics Estimating urban traffic and congestion cost trends for Australian

More information

Freight Modelling. TAG Unit 3.1.4. June 2003. Department for Transport. Transport Analysis Guidance (TAG)

Freight Modelling. TAG Unit 3.1.4. June 2003. Department for Transport. Transport Analysis Guidance (TAG) TAG Unit 3.1.4 June 2003 Department for Transport Transport Analysis Guidance (TAG) This Unit is part of a family which can be accessed at www.webtag.org.uk Contents 1 1 1.1 Introduction 1 2 References

More information

2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines

2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines 2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines Introduction The guidelines below provide departments and entities with information to make budget submissions for capital projects

More information

Vision Fleet: Fleet Assessment Overview Alternative fuel vehicles for fleets: Low Cost, Low Carbon, Low Hassle

Vision Fleet: Fleet Assessment Overview Alternative fuel vehicles for fleets: Low Cost, Low Carbon, Low Hassle Vision Fleet: Fleet Assessment Overview Alternative fuel vehicles for fleets: Low Cost, Low Carbon, Low Hassle Overview: A Vision Fleet Opportunity Assessment is both quantitative and qualitative and will

More information

INDOT 2000-2025 Long Range Plan

INDOT 2000-2025 Long Range Plan Chapter 9 INDOT 2000-2025 Long Range Plan Highway Needs Analysis Overview The statewide transportation planning process provides for the identification of highway needs through a comprehensive process

More information

Thailand s Logistics

Thailand s Logistics Thailand s Logistics Over the past fourteen years, overall international trade with Thailand has grown 340% and manufacturing trade 370%; this growth, aided in part by the nation s bilateral trade agreements

More information

Reported Road Casualties Great Britain: 2013 Annual Report

Reported Road Casualties Great Britain: 2013 Annual Report Reported Road Casualties Great Britain: 2013 Annual Report Focus on pedal cyclists Key findings The key findings from this article include: Pedal cyclist deaths have seen a long-term fall, but have fluctuated

More information

Ethiopian Road Sector Development Program

Ethiopian Road Sector Development Program Performance Monitoring System Of the Ethiopian Road Sector Development Program (June 14, 2004) RSDP MONITORING INDICATORS Structure of presentation 1) Background 2) Brief Definition of the Indicator 3)

More information

Railway Demand Forecasting and Service Planning Processes. Prepared for: Rail Freight Service Review

Railway Demand Forecasting and Service Planning Processes. Prepared for: Rail Freight Service Review Railway Demand Forecasting and Service Planning Processes Prepared for: Rail Freight Service Review March 2010 Table of Contents 1. Purpose of the Project... 4 2. General Approach... 5 3. Demand Forecasting...

More information

ROAD NETWORK ASSET MANAGEMENT AS A BUSINESS PROCESS. Paper prepared for the REAAA Conference in Japan, 4 9 September 2000

ROAD NETWORK ASSET MANAGEMENT AS A BUSINESS PROCESS. Paper prepared for the REAAA Conference in Japan, 4 9 September 2000 ROAD NETWORK ASSET MANAGEMENT AS A BUSINESS PROCESS Paper prepared for the REAAA Conference in Japan, 4 9 September 2000 Florentina Mihai, BEng, GDipMgt, MIEAust Main Roads Western Australia Neville Binning,

More information

SUSTAINABLE DEVELOPMENT TECHNOLOGY CANADA Travel & Accommodation Expense Guidelines and Policy

SUSTAINABLE DEVELOPMENT TECHNOLOGY CANADA Travel & Accommodation Expense Guidelines and Policy SUSTAINABLE DEVELOPMENT TECHNOLOGY CANADA Travel & Accommodation Expense Guidelines and Policy Purpose The purpose of this policy is to establish equitable standards and provide fair and consistent treatment

More information

ROADS ALLIANCE ASSET MANAGEMENT COMMUNIQUÉ AUGUST 2010 LOCAL GOVERNMENT ASSOCIATION OF QUEENSLAND LTD

ROADS ALLIANCE ASSET MANAGEMENT COMMUNIQUÉ AUGUST 2010 LOCAL GOVERNMENT ASSOCIATION OF QUEENSLAND LTD ROADS ALLIANCE ASSET MANAGEMENT COMMUNIQUÉ AUGUST 2010 LOCAL GOVERNMENT ASSOCIATION OF QUEENSLAND LTD Contents 4 Glossary 6 Background 9 Purpose of Communiqué 9 Australian and State Government Drivers

More information

Bedford s Network Management Strategy (2011 2021) November 2010

Bedford s Network Management Strategy (2011 2021) November 2010 Bedford s Network Management Strategy (2011 2021) November 2010 Page 1 of 13 1. Introduction 1.1. The Bedford Borough Council Network Management Strategy has been developed to support local and national

More information

Chapter 3 Alternatives to air travel: highspeed rail and videoconferencing

Chapter 3 Alternatives to air travel: highspeed rail and videoconferencing Chapter 3 Alternatives to air travel: highspeed rail and videoconferencing 66 In Chapter 2 we considered various demand projections reflecting different assumptions on fossil fuel prices, carbon prices,

More information

Network Rail October 2007 Strategic Business Plan. Supporting Document. Demand Forecasting in the SBP

Network Rail October 2007 Strategic Business Plan. Supporting Document. Demand Forecasting in the SBP Network Rail October 2007 Strategic Business Plan Supporting Document 2 Executive Summary The capacity strategy in the SBP is drawn from a range of sources. The HLOSs specify a small number of key schemes

More information

Roads and Footpaths Infrastructure Asset Management Plan

Roads and Footpaths Infrastructure Asset Management Plan Roads and Footpaths Infrastructure Asset Management Plan Version 2a November 2012 This page is left blank intentionally Prepared By: Rob Damhuis Senior Transport Asset Management Consultant Opus International

More information

Financial Management Strategy & Long Term Financial Plan 2014/2015 2023/2024

Financial Management Strategy & Long Term Financial Plan 2014/2015 2023/2024 Financial Management Strategy & Long Term Financial Plan 2014/2015 2023/2024 February 2014 Table of Contents Page 1.0 EXCUTIVE SUMMARY 1.1 Introduction 1.2 Financial Management Strategy 1.3 Long Term

More information

TOWN OF NEW HAVEN ROAD PLAN

TOWN OF NEW HAVEN ROAD PLAN 1 TOWN OF NEW HAVEN ROAD PLAN BACKGROUND The Town of New Haven, Vermont consists of 42 square miles of land and a population of approximately 1400 people. At the start of the 21 st century, it is served

More information

ASSET MANAGEMENT OF ROADS Bob Lloyd ARRB Transport Research Ltd

ASSET MANAGEMENT OF ROADS Bob Lloyd ARRB Transport Research Ltd 26 th Australasian Transport Research Forum Wellington New Zealand 1-3 October 2003 ABSTRACT ASSET MANAGEMENT OF ROADS ARRB Transport Research Ltd The World Bank s initial approach to road project / network

More information

Pavement Management Systems

Pavement Management Systems Pavement Management Systems Presented by Bill Weiss, P.E. Applied Pavement Technology, Inc. (APTech) At the 2015 Municipal Streets Seminar Ames, Iowa Why Pavement Management??? Pavements are expensive

More information

Fares Policy In London: Impact on Bus Patronage

Fares Policy In London: Impact on Bus Patronage Fares Policy In London: Impact on Bus Patronage Agenda Introduction to Transport for London Overview of Bus Patronage in London Changes in Policy and patronage since 2000 Fares Strategy Ticketing Strategy

More information

Transport Scotland Strategic Transport Projects Review Report 3 Generation, Sifting and Appraisal of Interventions Annex 2

Transport Scotland Strategic Transport Projects Review Report 3 Generation, Sifting and Appraisal of Interventions Annex 2 Detailed Appraisal D9: Integrated Ticketing Estimated total Public Sector Funding Requirement: Capital Costs/grant 50m - 100m Annual Revenue Support Present Value of Cost to Gvt BCR/PVB 1m - N/A - - -

More information

Update on Oklahoma Bridges and Highways

Update on Oklahoma Bridges and Highways Update on Oklahoma Bridges and Highways Oklahoma Department of Transportation November 2013 I-35 at Main Street in Cleveland County Oklahoma Bridges and Highways Oklahoma s State Highway Transportation

More information

COUNTRY EXPERIENCE ON EMISSION MEASUREMENT AND MITIGATION POLICIES. Republic of the Fiji Islands

COUNTRY EXPERIENCE ON EMISSION MEASUREMENT AND MITIGATION POLICIES. Republic of the Fiji Islands COUNTRY EXPERIENCE ON EMISSION MEASUREMENT AND MITIGATION POLICIES Republic of the Fiji Islands Major Exports (i)sugar $120m (ii) Tourism F$500m (iii) Fisheries F$30m (iv) Minerals F$40m Populated Islands

More information

Vehicle Replacement & Fleet Utilisation Policy To be considered as part of the overarching Fleet Strategy. Submitted: 29 September 2013

Vehicle Replacement & Fleet Utilisation Policy To be considered as part of the overarching Fleet Strategy. Submitted: 29 September 2013 Vehicle Replacement & Fleet Utilisation Policy To be considered as part of the overarching Fleet Strategy Submitted: 29 September 2013 To be Reviewed: September 2015 VERSION: AUTHOR: OWNER: v2.3 Barry

More information

CORPORATE TRAVEL PLAN. Key Messages

CORPORATE TRAVEL PLAN. Key Messages CORPORATE TRAVEL PLAN Key Messages Version 1.0 December 2010 Not protectively marked The aims and benefits of the corporate travel plan Our travel plan is a strategic management tool aimed at better managing

More information

Office of the Minister of Transport. Chair Cabinet NATIONAL LAND TRANSPORT FUND: FUTURE FUNDING. Proposal

Office of the Minister of Transport. Chair Cabinet NATIONAL LAND TRANSPORT FUND: FUTURE FUNDING. Proposal Chair Cabinet Office of the Minister of Transport NATIONAL LAND TRANSPORT FUND: FUTURE FUNDING Proposal 1. This paper advises on future transport expenditure and revenue pressures, discusses options for

More information

and the statewide and metropolitan transportation planning and programming process in California:

and the statewide and metropolitan transportation planning and programming process in California: Financial constraint... and the statewide and metropolitan transportation planning and programming process in California: A GUIDE TO FEDERAL AND STATE FINANCIAL PLANNING REQUIREMENTS Prepared by: Federal

More information

Journey to Work Patterns in the Auckland Region

Journey to Work Patterns in the Auckland Region Analysis of Census Data for 2001-2013 1 INTRODUCTION... 1 DEFINITIONS OF WORKERS, JOBS AND EMPLOYMENT... 1 2 SCOPE OF THE ANALYSIS... 2 2.1 LEVELS OF ANALYSIS... 2 2.2 DATA INCLUDED IN THE ANALYSIS...

More information

INTRODUCTION TO MATHEMATICAL MODELLING

INTRODUCTION TO MATHEMATICAL MODELLING 306 MATHEMATICS APPENDIX 2 INTRODUCTION TO MATHEMATICAL MODELLING A2.1 Introduction Right from your earlier classes, you have been solving problems related to the real-world around you. For example, you

More information

0.0 Curb Radii Guidelines Version 1.0.2

0.0 Curb Radii Guidelines Version 1.0.2 Background In early 2014, Transportation Services initiated a review of the Division's design guidelines and standards to move our organization in a direction consistent with the transportation departments

More information

A NEW METHOD FOR DEVELOPING THE MOST COST- EFFECTIVE REHABILITATION PROGRAMS FOR OUR AGEING SEWER NETWORKS

A NEW METHOD FOR DEVELOPING THE MOST COST- EFFECTIVE REHABILITATION PROGRAMS FOR OUR AGEING SEWER NETWORKS A NEW METHOD FOR DEVELOPING THE MOST COST- EFFECTIVE REHABILITATION PROGRAMS FOR OUR AGEING SEWER NETWORKS Introduction Toby Bourke (MWHSoft), Graham McGonigal (MWH) There is currently widespread concern

More information

Traffic Forecasting. Resource Guidebook. Florida Department of Transportation District Five

Traffic Forecasting. Resource Guidebook. Florida Department of Transportation District Five Traffic Forecasting Resource Guidebook Florida Department of Transportation District Five Florida Department of Transportation District Five November November 2006 2006 Traffic Forecasting Resource Guidebook

More information

DAY 2 SESSION 1 ROD ELLIS ROAD ASSET MANAGEMENT AN APPROACH FOR THE ROAD MANAGER

DAY 2 SESSION 1 ROD ELLIS ROAD ASSET MANAGEMENT AN APPROACH FOR THE ROAD MANAGER DAY 2 SESSION 1 ROD ELLIS ROAD ASSET MANAGEMENT AN APPROACH FOR THE ROAD MANAGER September 2004 Mr Rod Ellis BEng (Civil), MBA, GAICD, MIEAust, CPEng Director, Tonkin Consulting ABSTRACT In today s environment,

More information

ethekwini Metropolitan Municipality s

ethekwini Metropolitan Municipality s ethekwini Metropolitan Municipality s integrated approach to pavement asset management INTRODUCTION Recent asset management legislation has holistically incorporated a host of previously stand-alone principles

More information

11. Monitoring. 11.1 Performance monitoring in LTP2

11. Monitoring. 11.1 Performance monitoring in LTP2 178 11. Monitoring 11.1 Performance monitoring in LTP2 Performance against the suite of indicators adopted for LTP2 is shown in the following table. This shows progress between 2005/06 and 2009/10 (the

More information

P13 Route Plan. E216 Distribution &Transportation

P13 Route Plan. E216 Distribution &Transportation P13 Route Plan Vehicle Routing Problem (VRP) Principles of Good Routing Technologies to enhance Vehicle Routing Real-Life Application of Vehicle Routing E216 Distribution &Transportation Vehicle Routing

More information

Where Do We Want to Go? How Can We Get There?

Where Do We Want to Go? How Can We Get There? Where Do We Want to Go? How Can We Get There? The BRTB has adopted nine goals, with supporting strategies, performance measures, and performance targets. Together, these goals, strategies, measures, and

More information

Investment Brief for the Electricity Sector in Liberia

Investment Brief for the Electricity Sector in Liberia Investment Brief for the Electricity Sector in Liberia Overview Liberia s economic growth is severely constrained by an insufficient supply of reliable and affordable electricity. The only on- grid electricity

More information

CE Entrepreneurship. Investment decision making

CE Entrepreneurship. Investment decision making CE Entrepreneurship Investment decision making Cash Flow For projects where there is a need to spend money to develop a product or establish a service which results in cash coming into the business in

More information

Passenger Vehicle Occupant Fatality Rates by Type and Size of Vehicle

Passenger Vehicle Occupant Fatality Rates by Type and Size of Vehicle DOT HS 809 979 January 2006 Passenger Vehicle Occupant Fatality Rates by Type and Size of Vehicle By Rajesh Subramanian * Summary The National Highway Traffic Safety Administration (NHTSA) has routinely

More information

Whole Life Costing for Option Appraisal of Maintenance Schemes for Local Highway Authorities. June 2011

Whole Life Costing for Option Appraisal of Maintenance Schemes for Local Highway Authorities. June 2011 Whole Life Costing for Option Appraisal of Maintenance Schemes for Local Highway Authorities June 2011 Whole Life Costing for Option Appraisal of Maintenance Schemes for Local Highway Authorities ii Contents

More information

Monitoring and evaluation of walking and cycling (draft)

Monitoring and evaluation of walking and cycling (draft) Sustrans Design Manual Chapter 16 Monitoring and evaluation of walking and cycling (draft) November 2014 September 2014 1 About Sustrans Sustrans makes smarter travel choices possible, desirable and inevitable.

More information

Products and comprehensive solutions. NIS-M2M Group

Products and comprehensive solutions. NIS-M2M Group Products and comprehensive solutions NIS-M2M Group NIS-M2M Group products and comprehensive solutions NIS-M2M Group Navigation information market leader 3 Products: Software 4 TELEMATICS PLATFORMS Specialized

More information

The term marginal cost refers to the additional costs incurred in providing a unit of

The term marginal cost refers to the additional costs incurred in providing a unit of Chapter 4 Solutions Question 4.1 A) Explain the following The term marginal cost refers to the additional costs incurred in providing a unit of product or service. The term contribution refers to the amount

More information

Development of Shanghai Integrated Transport (2010-2015) XIAO Hui and GU Yu

Development of Shanghai Integrated Transport (2010-2015) XIAO Hui and GU Yu Development of Shanghai Integrated Transport (2010-2015) XIAO Hui and GU Yu Abstract This article summarises the general situation of Shanghai s integrated transport system and then determines the trends

More information

Traffic Management Systems with Air Quality Monitoring Feedback. Phil Govier City & County of Swansea

Traffic Management Systems with Air Quality Monitoring Feedback. Phil Govier City & County of Swansea Traffic Management Systems with Air Quality Monitoring Feedback Phil Govier City & County of Swansea The Swansea Project - what are we trying to achieve? Develop a working traffic emissions forecast model

More information

How To Improve Road Quality

How To Improve Road Quality A Customer Service Level Approach for Maine DOT s Asset Management System Jeffrey L. Zavitski, B.A. Senior Implementation Specialist Deighton Associates Limited Chip Getchell, P.E. Director, Work Plan

More information

ORANGE COUNTY TRANSPORTATION AUTHORITY. Final Long-Range Transportation Plan - Destination 2035. Attachment A

ORANGE COUNTY TRANSPORTATION AUTHORITY. Final Long-Range Transportation Plan - Destination 2035. Attachment A ORANGE COUNTY TRANSPORTATION AUTHORITY Final Long-Range Transportation Plan - Destination 2035 Attachment A DESTINATION 2035 DESTINATION 2035 EXECUTIVE SUMMARY ATTACHMENT A Moving Toward a Greener Tomorrow

More information