1 Basic Financial Requirements for Government Contracting The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Accounting System Requirements Page 2 1
2 Prior to Contract Award Contracting Office or DCMA conducts Preaward Survey to consider responsibility of prospective contractor Design of the Accounting System is part of the Preaward Survey (SF 1408 Criteria) DCAA requested to evaluate design of Accounting System Page 3 Preaward Accounting System Audit Evaluates design of Accounting System to determine if it is acceptable for prospective contract DCAA or Buying Command will request contractor complete Preaward Accounting System Checklist Contractor should be prepared to demonstrate how accounting system satisfies SF 1408 criteria at initial meeting Page 4 2
3 Preaward Accounting System Checklist Based on SF 1408 criteria Generally used by contractors new to government contracting that the Government plans to award a cost type contract (cost reimbursement contracts, or for contractors that will receive progress payments based on cost) Assesses whether the requirements for an adequate accounting system have been met Page 5 Preaward Accounting System Compliance Requirements Generally Accepted Accounting Practices (GAAP) Proper Segregation of Costs Direct Costs by Contract Allocation of Indirect Costs Accumulation of Costs Under General Ledger Control Timekeeping System Labor Distribution Interim Determination of Costs Exclusion of Unallowables Costs by Contract Line Item Preproduction Costs Limitation of Costs Billings Adequate, Reliable Data Page 6 3
4 After the Audit is Completed Issue report to Contracting Officer with an opinion that the accounting system is or is not suitably designed, in all material respects, for award of a prospective contract. Includes a completed SF 1408 An opinion that the system is not suitably designed means that the contractor cannot be awarded a cost type contract of the award will be delayed until corrective action is taken and a follow-up audit can be performed Page 7 Common Deficiencies Contractors not making interim (at least monthly) determination of costs charged through routine posting to books of account Failure to properly segregate direct and indirect costs Improper timekeeping Failure to exclude unallowable costs Page 8 4
5 Incurred Cost Submission Page 9 Due Dates of Submissions Incurred cost claims are due six months after completion of the contractor s fiscal year end Per the Allowable Cost and Payment Clause (FAR (d)(2)) Allowable cost and payment clause applies to cost-reimbursement type contracts (FAR ) Page 10 5
6 Incurred Cost Electronically Model (ICE) ICE is an excel spreadsheet It includes all schedules required for an adequate submission per FAR ICE is not a requirement but a tool to assist in preparation of an adequate incurred cost submission The submission of an adequate proposal may expedite contract closings Page 11 Delinquent Submissions If submissions are six months delinquent, DCAA will recommend a decrement factor and for the CO to make a unilateral determination. (FAR (c)(2)) Page 12 6
7 Provisional Billing Rates (PBRs) Page 13 Purpose of PBRs Established to approximate the contractor s final yearend rates, as adjusted for any unallowable costs Used for interim purposes until settlement is reached on the final indirect rates for the contractor s fiscal year FAR Billing Rates - provides procedures and guidance for establishing PBRs The contracting officer or auditor shall establish PBRs on the basis of information resulting from recent review, previous rate audits or experience, or similar reliable data or experience of other contracting activities. Page 14 7
8 When Should We Submit? Prior to the beginning of the fiscal year (once budgets are complete) or when the established billing rates are no longer representative of final year end rates due to unforeseen circumstances. PBRs should be submitted at least annually. Vouchers and progress payments can be returned if submitted without properly established billing rates. Page 15 Monitoring PBRs should be monitored: Throughout the year Immediately after year-end Upon submission of the final indirect rate proposal PBRs may be adjusted by either party at any time to prevent substantial under or over payment FAR (c). If PBRs are adjusted, the contractor should submit adjustment vouchers accordingly. Page 16 8
9 Common Deficiencies Failure to remove unallowable costs from the billing rate projections. Failure to adjust provisional billing rates based on actual experience: Before year end, if there are known or reasonably anticipated significant variances. After year end once actual rates, net of unallowable expenses, are calculated. Page 17 Public Vouchers Page 18 9
10 Public Vouchers Cost type contracts provide for interim payments for costs on a Standard Form (SF) 1034 public voucher. DCAA will perform voucher reviews based on risk. Fixed price contracts are subject to FAR Part 32 financing methods. Page 19 Contractor Responsibilities Contact the cognizant DCAA office after contract award Ensure DCAA has the necessary information to process contract billings, such as current provisional billing rates, copy of the contract, any special contract provisions, etc. Maintain adequate billing system internal controls Ensure adequate support is maintained for amounts billed Submit timely incurred cost proposals and final vouchers in accordance with FAR Page 20 10
11 Preparation of Vouchers The contractor is responsible for preparing and submitting claims for reimbursement according to the terms of the contract. Vouchers should not be submitted more than once every two weeks. All vouchers should be submitted through WAWF unless contract terms require hard copy vouchers to be submitted. Public voucher claims for reimbursement must be prepared on the prescribed Government forms: First voucher on a contract is an interim voucher, as are all subsequent vouchers prior to the final voucher. Final voucher will not be submitted until all contract work is completed Page 21 Common Deficiencies Math errors Billed costs not allowed per the contract terms (e.g. overtime) Incorrect provisional billing rates (indirect costs) Billing over contract ceiling amounts Page 22 11
12 DCAA Internet Resources Audit Process Overview Information for Contractors Manual DCAA Pre-award Accounting System Checklist DoD Contract Proposal Adequacy Checklist DCAA Incurred Cost Adequacy Checklist Incurred Cost Electronically (ICE) Model Links to Acquisition Regulations Small Business Seminar Slides Page 23 Contact Information DoD Office of Small Business Programs DCAA Page 24 12
Basic Financial Requirements for Government Contracting
Basic Financial Requirements for Government Contracting 2014 National SBIR/STTR Conference The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations
More informationPre-Award Accounting Systems
Pre-Award Accounting Systems 2013 National SBIR Conference Christopher Andrezze, CPA Special Assistant to the Deputy Director May 16, 2013 The views expressed in this presentation are DCAA's views and
More informationAccounting System Requirements
Accounting System Requirements Further information is available in the Information for Contractors Manual under Enclosure 2 The views expressed in this presentation are DCAA's views and not necessarily
More informationDefense Contract Audit Agency NAVAIR Small Business Aviation Technology Conference
Defense Contract Audit Agency NAVAIR Small Business Aviation Technology Conference November 29-30, 2006 t Defense Contract Audit Agency Established in 1965 Separate Agency of the Department of Defense
More informationDCAA and the Small Business Innovative Research (SBIR) Program
Defense Contract Audit Agency (DCAA) DCAA and the Small Business Innovative Research (SBIR) Program Judice Smith and Chang Ford DCAA/Financial Liaison Advisors NAVAIR 2010 Small Business Aviation Technology
More informationDCAA Our Role. Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE. Page 1. DCAA 1965-2015: Celebrating 50 Years of Excellence
DCAA Our Role Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE DCAA 1965-2015: Celebrating 50 Years of Excellence Page 1 Topics About DCAA Typical DCAA Audits for Small Businesses Basic Roles of
More informationSlide 1. Slide 2. Slide 3 Standard Form 1408 ACCOUNTING SYSTEM ESSENTIALS
Slide 1 Slide 2 ACCOUNTING SYSTEM ESSENTIALS P r e p a r e d f o r Alliance Northwest 2014 By T e r r y S. N u z z o, C P A, C G M A P a c i f i c N o r t h w e s t C o n s u l t a n t s, L L C Slide 3
More informationDCAA Overview and Resources Available for Small Businesses
DCAA Overview and Resources Available for Small Businesses The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Page 1 Department of Defense
More informationPreaward and Post Award Accounting System Audits. November 17, 2011 Pikes Peak NCMA Roland Wick
Preaward and Post Award Accounting System Audits November 17, 2011 Pikes Peak NCMA Roland Wick OVERVIEW This presentation will provide: 1. The basic criteria for the Preaward and Post Award accounting
More informationDCAA Overview and Resources Available for Small Businesses
DCAA Overview and Resources Available for Small Businesses The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Page 1 Department of Defense
More informationWhat Exactly is an Acceptable Accounting System?
What Exactly is an Acceptable Accounting System? Kristen Soles, CPA Member Stephanie Widzinski, CPA Senior Manager September 27, 2012 Agenda Review DFARS Business System Rule What Agency is Responsible
More informationPreaward Survey of Prospective Contractor Accounting System Checklist
PRE-AWARD SURVEY (SF 1408) OF PROSPECTIVE CONTRACTOR ACCOUNTING SYSTEM Date: XX/XX/201X Company Name, Contract Number, and Full Address: Commercial and Government Agency (CAGE) Code Number: (found at http://www.dlis.dla.mil/cage_welcome.asp)
More informationDCAA Current Trends and Practices. SCS GovCon Seminar October 24, 2013
DCAA Current Trends and Practices SCS GovCon Seminar October 24, 2013 What s Hot 2 Incurred Cost Submissions Requirements Common Deficiencies Closer Cost Scrutiny Travel Costs Restructuring Costs Consultant
More informationCHAPTER 2. 2-000 Preaward Surveys of Prospective Contractor Accounting Systems
CHAPTER 2 2-000 Preaward Surveys of Prospective Contractor Accounting Systems 2-101 Preaward Survey Overview A preaward survey is an evaluation, usually made by the cognizant contract administration office,
More informationCurrent Initiatives May 2015
DHG 20 th Annual Government Contracting Update Current Initiatives May 2015 Mr. Ken Saccoccia Deputy Director Page 1 One Agency One Mission DCAA Overview Priorities and Better Buying Power Small Business
More informationCertificate of Accounting, Billing and Property System Adequacy
Certificate of Accounting, Billing and Property System Adequacy This certifies that, to the best of my knowledge and belief, Contractor s Accounting, Billing and/or Property System and related internal
More informationPublic Vouchers. Further information is available in the Information for Contractors Manual under Enclosure 5
Public Vouchers Further information is available in the Information for Contractors Manual under Enclosure 5 The views expressed in this presentation are DCAA's views and not necessarily the views of other
More informationWELCOME. Accounting Systems for DOD Contracts
WELCOME Accounting Systems for DOD Contracts Moderator: Layli Pietri, Small Business Manager, Balfour Beatty Construction Speaker: Kay Papin, Government Compliance Manager, McCarthy Group Inc. Accounting
More informationPost Award Accounting System Audit at Nonmajor Contractors
Activity Code 17740 B-1 Planning Considerations Post Award Accounting System Audit at Nonmajor Contractors To provide general guidance for the audit of the adequacy and suitability of nonmajor contractor
More informationPost Award Accounting System Audit at Nonmajor Contractors
Activity Code 17741 Version 3.1, dated November 2015 B-01 Planning Considerations Post Award Accounting System Audit at Nonmajor Contractors Audit Specific Independence Determination Members of the audit
More informationIntroduction and DCAA Overview
Introduction and DCAA Overview Industry Engagement Session 10/29/2015 The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations DCAA 1965-2015:
More informationPreaward Survey of Prospective Contractor Accounting System
Activity Code 17740 B-1 Planning Considerations Preaward Survey of Prospective Contractor Accounting System Purpose and Scope The major objectives of this audit are to obtain an understanding of the accounting
More informationGOVERNMENT ACCOUNTING REQUIREMENTS
GOVERNMENT ACCOUNTING REQUIREMENTS Basic Accounting Systems Time Reporting DCAA Encounters CRITICAL ELEMENTS OF AN ACCOUNTING SYSTEM Designed in Accordance with GAAP Proper Segregation of Direct and Indirect
More informationHow To Audit A Government Contractor
Activity Code 17740 Version 6.11, dated November 2015 B-1 Planning Considerations Preaward Survey of Prospective Contractor Accounting System Audit Specific Independence Determination Members of the audit
More informationSmall Business Conference San Diego Regional Innovation Cluster February 25, 2014
Small Business Conference San Diego Regional Innovation Cluster February 25, 2014 The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Agenda
More informationTHE DCAA AUDIT BECOMING DCAA COMPLIANT
THE DCAA AUDIT Created to oversee government spending on behalf of the American tax-payer, the Defense Contract Audit Agency (DCAA) is responsible for supervising all Department of Defense (DoD) contracts.
More informationDefense Contract Audit Agency: What Do They Do and How Does It Affect ME as a Resource Manager? (Breakout #63)
Defense Contract Audit Agency: What Do They Do and How Does It Affect ME as a Resource Manager? (Breakout #63) Pat Fitzgerald Director Defense Contract Audit Agency The views expressed in this presentation
More informationIf you require a copy of this presentation, please provide your contact information to either Christopher Weir or Bob Eyer and we will be sure to
How do I survive an audit of an incurred cost submission? If you require a copy of this presentation, please provide your contact information to either Christopher Weir or Bob Eyer and we will be sure
More informationDCAA Compliant Accounting Systems
DCAA Compliant Accounting Systems State Designated as Florida s Principal Provider of Business Assistance [ 288.001, Fla. Stat.] Helping Businesses Grow & Succeed About Your Presenter Jenny W. Clark With
More informationDCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System
DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System Breakout Session A Alfred J. Massey, Western Region, Special Programs Manager,
More informationDCAA Guidelines. How the SBIR firm can work effectively with the Defense Contract Audit Agency
DCAA Guidelines How the SBIR firm can work effectively with the Defense Contract Audit Agency Today s Presenters OUTLINE Presenter Introduction DCAA & DCMA DCAA Overview Types of DCAA Audits What it takes
More informationGovernment Accounting, Estimating, and Billing Systems: Pitfalls and Answers
Curtis Matthews, Managing Partner Government Accounting, Estimating, and Billing Systems: Pitfalls and Answers Findley Gillespie, Senior Manager May 18, 2011 1 The material appearing in this presentation
More informationManaging Cost Type Contracts
Managing Cost Type Contracts October 9, 2013 By: Tom Marcinko Donna Dominguez 2013 All Rights Reserved 805 King Farm Boulevard Suite 300 Rockville, Maryland 20850 301.231.6200 P 301.231.7630 F www.aronsonllc.com
More informationAudit Expectations for Small Businesses
Audit Expectations for Small Businesses DEFENSE CONTRACT CONSULTING Joseph A. Dalton, CGFM/CFE/CAP Over 31 Years -Supervisory/Auditor Service- DCAA Retired Captain, U. S. Naval Reserve 1996 BUSINESS NO.
More informationIncurred Cost Submissions
Incurred Cost Submissions Further information is available in the Information for Contractors Manual under Enclosure 2 The views expressed in this presentation are DCAA's views and not necessarily the
More informationHow to Survive a DCAA Audit
How to Survive a DCAA Audit www.paulgunn.com 1 How to Survive a DCAA Audit - Overview Areas of interest and expectations of a typical audit: 1. Introduction o 2. The DCAA and Types of audits 3. Preparing
More informationGovernment Contract Accounting Are You DCAA Compliant? Procurement Technical Assistance Program (PTAP)
Government Contract Accounting Are You DCAA Compliant? Procurement Technical Assistance Program (PTAP) NH Presentation October 20, 2010 Presented by: Fred Kline, MBA, CPA Tom Martin MBA, CPA Malcolm Young,
More informationYou've successfully subscribed to this feed! Updated content can be viewed in Internet Explorer and other programs that use the Common Feed List.
Page 1 of 5 You've successfully subscribed to this feed! Updated content can be viewed in Internet Explorer and other programs that use the Common Feed List. View my feeds DCAA News Thursday, May 28, 2009,
More informationSurviving a DCAA. Audit. Nicole Mitchell, CPA Director Aronson LLC. March 29, 2011
Surviving a DCAA Incurred Cost Submission Audit Nicole Mitchell, CPA Director Aronson LLC March 29, 2011 2011 All Rights Reserved 805 King Farm Boulevard Suite 300 Rockville, Maryland 20850 301.231.6200
More informationImplementing a FAR Part 31 Compliant Cost Accounting System
Implementing a FAR Part 31 Compliant Cost Accounting System Breakout Session #: F11 Presented by: Robert E. Jones, CFCM, CCCM Date: July 23, 2013 Time: 4:00 PM 5:15 PM Agenda 1. Choosing a System 2. Designing
More informationStrategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012
Strategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012 1 Panelists Robert A. ( Rob ) Burton, Partner, Venable LLP A 30-year veteran
More informationCOST PLUS AWARD FEE CONTRACT ADMINISTRATION DESKGUIDE
COST PLUS AWARD FEE CONTRACT ADMINISTRATION DESKGUIDE 1. Introduction. This Guide does not cover all aspects of administering a cost plus award fee (CPAF) contract. As all of the Directorates of Contracting
More informationTime s Up: DCAA s Renewed Focus on Incurred Cost Submissions
Time s Up: DCAA s Renewed Focus on Incurred Cost Submissions Nicole Mitchell, CPA Donna Dominguez Aronson LLC May 1, 2013 2013 All Rights Reserved 805 King Farm Boulevard Suite 300 Rockville, Maryland
More informationINTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006
INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006 1. MANAGEMENT REVIEWS The contractor should have policies and procedures for periodic monitoring of the billing
More informationWHAT MAKES AN ACCOUNTING SYSTEM COMPLIANT
WHAT MAKES AN ACCOUNTING SYSTEM COMPLIANT Presented by: Laura Davis OVERVIEW Why Do I Need a Compliant Accounting System Auditor s Judgment Definitions Key Components Audits How to be prepared for an audit
More informationAccounting Systems: Complying with FAR Requirements. John S. Sroka, CPA Acquisition Cost/Price Analyst
Accounting Systems: Complying with FAR Requirements John S. Sroka, CPA Acquisition Cost/Price Analyst Background Information FAR Requirements FAR Part 9: Contractor Qualifications FAR Part 16: Cost-reimbursement
More informationWomen Accessing Capital Training 207:
Women Accessing Capital Training 207: Setting up an Accounting System For Government Contractors Course Instructor: Michelle Hoffman, CPA CEO, Hoffman CFO Consulting The Voice for Women in Business in
More informationStatement of Mr. William H. Reed Director, Defense Contract Audit Agency Senate Armed Services Committee April 19, 2007
1 Statement of Mr. William H. Reed Director, Defense Contract Audit Agency Senate Armed Services Committee April 19, 2007 Mr. Chairman, members of the Committee, my statement will summarize the Defense
More informationFinancial Management Guide for Government Contractors
Financial Management Guide for Government Contractors Overview You are a Government Contractor or wish to be a Government Contractor. Congratulations. It is important you know that the challenges facing
More informationDCAA Audit R 4 Rights to Records, Requirements & Remedies
San Diego Chapters Present DCAA Audit R 4 Rights to Records, Requirements & Remedies A Seminar with Panel Discussion and Audience Participation February 18, 2009 This Morning s Agenda 8:30 Introduction
More informationWORKING WITH THE U.S. GOVERNMENT YOUR GUIDE TO THE DCAA
WORKING WITH THE U.S. GOVERNMENT YOUR GUIDE TO THE DCAA The DCAA Audit Created to oversee government spending on behalf of the American tax-payer, the Defense Contract Audit Agency (DCAA) is responsible
More informationGovernment Contractor Business Systems and Overview of System Assessments
Government Contractor Business Systems and Overview of System Assessments Agenda Overview of business systems rules and environment today 3 rd party assessments Practical solutions Contractor perspective
More informationAre you in Compliance with the Financial Rules for 8(a) Companies?
Are you in Compliance with the Financial Rules for 8(a) Companies? Sales Less than $1M Withdrawals exceeding $250,000 are considered excessive. Compiled financial statements are required within 90 days
More informationFAR UPDATE 52.216-7, Allowable Cost and Payment (Jun 2013)
FAR UPDATE 52.216-7, Allowable Cost and Payment (Jun 2013) "It's never too early to prepare for your incurred cost submission (A webinar sponsored by Pleasant Valley Business Solutions) 1 Objective Know
More informationIs Your Accounting System Making the Grade? Attributes of an Acceptable Accounting System April 26, 2012
Is Your Accounting System Making the Grade? Attributes of an Acceptable Accounting System April 26, 2012 2012 All Rights Reserved 805 King Farm Boulevard Suite 300 Rockville, Maryland 20850 301.231.6200
More informationDEFENSE CONTRACT AUDIT AGENCY 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219. PPS June 26, 2012 INFORMATION FOR CONTRACTORS
DEFENSE CONTRACT AUDIT AGENCY 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 PPS June 26, 2012 DCAA MANUAL NO. 7641.90 INFORMATION FOR CONTRACTORS 1. PURPOSE. This manual supersedes
More informationDEFENSE CONTRACT AUDIT AGENCY
DEFENSE CONTRACT AUDIT AGENCY Fundamental Building Blocks for an Acceptable Accounting System Presented by Sue Reynaga DCAA Branch Manager San Diego Branch Office August 24, 2011 Report Documentation Page
More informationFederal Regulatory Compliance Best Practices Washington Technology Webcast. September 27, 2012
Federal Regulatory Compliance Best Practices Washington Technology Webcast September 27, 2012 Agenda Topic Minutes Regulatory compliance overview 5 Major areas of financial compliance risk 15 Best practices
More informationJanuary 2004 6(1) CHAPTER 6. Table of Contents
January 2004 6(1) Paragraph CHAPTER 6 Table of Contents 6-000 Incurred Costs Audit Procedures Page 6-001 Scope of Chapter... 601 6-100 Section 1 --- Introduction to Incurred Cost Audit Objectives 6-101
More informationDEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219
DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 IN REPLY REFER TO PSP 730.8.B.1/2010-003 February 18, 2011 11-PSP-003(R) MEMORANDUM
More informationMaster Document Audit Program. Version 1.5, dated September 2015 B-01 Planning Considerations
Activity Code 11070 Version 1.5, dated September 2015 B-01 Planning Considerations Accounting System Audit Audit Specific Independence Determination Members of the audit team and internal specialists consulting
More informationHow to Survive a DCAA Pre-Award Audit
How to Survive a DCAA Pre-Award Audit February 27, 13 Presented by: Paul H. Calabrese Senior Manager 301-214-4137 pcalab@rubino.com Bio http://www.rubino.com/company/staff/11- paul_h_calabrese/view LinkedIn
More informationACCOUNTING & AUDIT GUIDELINES FOR CONTRACTS WITH CALTRANS
ACCOUNTING & AUDIT GUIDELINES FOR CONTRACTS WITH CALTRANS Mendocino County Page 1 of 5 INTRODUCTION The purpose of this brochure is to outline for you, a potential contractor with the California State
More informationPresenting the Numbers: Accounting Systems for Government Contractors
Presenting the Numbers: Accounting Systems for Government Contractors William D. Craven, CPA Senior Cost/Price Analyst CH2M HILL Plateau Remediation Company William D. Craven, CPA, CMA, CIA Cost/Price
More informationDOECAA Spring Conference Presentation. Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule
DOECAA Spring Conference Presentation Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule Mary Karen Wills, CPA Director/Leader, BRG Government Contracts 2014 Berkeley Research Group
More informationProvisional Billing Rates. Beth Citeroni Acquisition Cost/Price Analyst
Provisional Billing Rates Beth Citeroni Acquisition Cost/Price Analyst Definition FAR 42.701 Provisional rate or billing rate is an established temporary indirect rate applicable to a specified period
More informationComplying With DCAA (Defense Contract Audit Agency)
Complying With DCAA (Defense Contract Audit Agency) Project Cost Accounting for Government Contractors EXECUTIVE GUIDE SERIES November 2007 Executive Summary In a commercial contract, the deliverable is
More informationDOD's Business Systems Rule: The Challenge Measuring Government Contractor Compliance Against Subjective Criteria and Perceived Risks
DOD's Business Systems Rule: The Challenge Measuring Government Contractor Compliance Against Subjective Criteria and Perceived Risks Breakout Session #: B04 Presented by: Michael E. Steen, CPA Date: July
More informationREAL-TIME LABOR EVALUATIONS. The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations
REAL-TIME LABOR EVALUATIONS The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations 1 Real-Time Labor Evaluation What is a Real-Time Labor Evaluation?
More informationThe Devil is in the Details Compliance with the Business Systems Rule
Metropolitan Area Corporate Counsel Association WMACCA Conference on Ethics and Compliance for Government Contractors The Devil is in the Details Compliance with the Business Systems Rule April 1, 2014
More informationGOVERNMENT CONTRACTING MICROSOFT DYNAMICS AX AND
GOVERNMENT CONTRACTING AND MICROSOFT DYNAMICS AX White paper on Government Contracting requirements and considerations in planning for a Dynamics AX implementation. 1 Government Contracting and Microsoft
More informationHow to Establish an SBIR Accounting System that Can Withstand a Government Audit
In cooperation with Connecticut Innovations 4/16/14 How to Establish an SBIR Accounting System that Can Withstand a Government Audit Edward G. Jameson, CPA Managing Partner Jameson & Company, CPAs www.jamesoncpa.com
More informationThank You for Joining Us, The Webinar Will Begin Shortly. While you are waiting please check out the Upcoming Webinars on www.giveme5.com.
Thank You for Joining Us, The Webinar Will Begin Shortly. While you are waiting please check out the Upcoming Webinars on www.giveme5.com. Before we begin just a few notes: During the presentation lines
More informationGovernment Contracting in 2015: Balancing Risks to Reap Rewards - Compliance Update
Government Contracting in 2015: Balancing Risks to Reap Rewards - Compliance Update Baker Tilly Beers & Cutler, PLLC, is a wholly-owned subsidiary of Baker Tilly Virchow Krause, LLP. 2015 Baker Tilly Beers
More informationPresented by: Laura Davis, President Strategic Consulting Solutions, Inc. PDS Consulting Solutions, LLC November 12, 2015
Presented by: Laura Davis, President Strategic Consulting Solutions, Inc. PDS Consulting Solutions, LLC November 12, 2015 Agenda Introductions RFP Process Types of Costs Pricing of Direct Costs Pricing
More informationThe Essential Role of Adequate Accounting Systems for Government Contractors
The Essential Role of Adequate Accounting Systems for Government Contractors Jerrold Rosenberg, CPA, CFP Judith H. Lasley, CPA John Pace, CPA, CVA February 29, 2012 American Legion Washington Conference
More informationThe Changing Government Contractor Environment
The Changing Government Contractor Environment 1 Federal Government Contracting DCAA FY 2014 Report to Congress DCAA Audit Guidance Business systems Federal regulatory rule changes State Contracting (Dept.
More informationMonitoring Subcontracts. The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations
Monitoring Subcontracts The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Subcontracts What should a contractor know about subcontracting:
More informationHow to Establish an SBIR Accounting System that Can Withstand a Government Audit
In cooperation with Connecticut Innovations 2/27/14 How to Establish an SBIR Accounting System that Can Withstand a Government Audit Edward G. Jameson, CPA Managing Partner Jameson & Company, CPAs www.jamesoncpa.com
More informationCracking the ICE: Ensuring a Compliant Incurred Cost Submission. Carlos Alvarado, VP, FP&A
Cracking the ICE: Ensuring a Compliant Incurred Cost Submission Carlos Alvarado, VP, FP&A Agenda Introduction Incurred Cost Proposal ICE Model Leveraging Reporting Applications Inadequacy Letters Q&A 2
More informationSeptember 16, 2015 6(1) CHAPTER 6
September 16, 2015 6(1) CHAPTER 6 Paragraph Table of Contents 6-000 Incurred Costs Audit Procedures Page 6-001 Scope of Chapter... 601 6-100 Section 1 --- Introduction to Incurred Cost Audit Objectives
More informationPAS 730.3.B.2.4 April 24, 2012 12-PAS-012(R)
DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 IN REPLY REFER TO April 24, 2012 MEMORANDUM FOR REGIONAL DIRECTORS, DCAA DIRECTOR,
More informationINFORMATION FOR CONTRACTORS
DCAAP 7641.90 January 2005 INFORMATION FOR CONTRACTORS DEPARTMENT OF DEFENSE DEFENSE CONTRACT AUDIT AGENCY DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT
More informationEnsure Compliance For Government Contractors
Ensure Compliance For Government Contractors Topics Overview NeoSystems Corp 2009-2012 ENSURE COMPLIANCE FOR GOVERNMENT CONTRACTORS TABLE OF CONTENTS V15C Learning Objectives... 4 Introduction... 5 Government
More informationLabor Costs Interpretive Guidance Labor Costs: Timekeeping, Direct Labor Base, Labor Transfers & Direct to Indirect Labor Ratio
Labor Costs Interpretive Guidance Labor Costs: Timekeeping, Direct Labor Base, Labor Transfers & Direct to Indirect Labor Ratio External Audits Architectural and Engineering (A&E) Contracts This Document
More informationChapter 6 Labor-Charging Systems and Other Considerations
6 Chapter 6 Labor-Charging Systems and Other Considerations The purpose of this chapter is to provide interpretive guidance only. This chapter is not intended to be authoritative or to supersede the FAR.
More informationUncompensated Overtime
Uncompensated Overtime 1 Table of Contents Risk Assessment Research and Planning Risk Assessment Labor System Entrance Conference Preliminary Analytical Procedures Audit Team Brainstorming for Fraud Risk
More informationAccounting Principles Critical to Success Presented By: C. P. Krishnan. www.cakintl.com
Accounting Principles Critical to Success Presented By: C. P. Krishnan Basic Accounting You Need to Know Assets, Liabilities, Equity, Income, & Expenses Assets Includes what you have and what people owe
More informationUnderstanding the Rate Cycle. Presented By: Rich Wilkinson, VP Client Services
Understanding the Rate Cycle Presented By: Rich Wilkinson, VP Client Services The Rate Cycle and Related Trivia Basics of Indirect Rates The Traditional Structures Developing Rates Prospective Rate Submissions
More informationIncurred Cost Submissions. John S. Sroka, CPA Acquisition Cost/Price Analyst
Incurred Cost Submissions John S. Sroka, CPA Acquisition Cost/Price Analyst Incurred Cost Proposals Allowable cost and payment clause requires the submission (FAR 52.216-7) Requires a signed certification
More informationDEFENSE CONTRACT AUDIT AGENCY CHECKLIST FOR DETERMINING ADEQUACY OF CONTRACTOR INCURRED COST PROPOSAL
Instructions: This form should be completed for each proposal submission and maintained in the permanent file. Adequacy reviews of contractor incurred cost proposals include an assessment for completeness
More informationCONTRACTOR INVOICE REVIEW AND APPROVAL PROCESS
SECTION XVI. CONTRACTOR INVOICE REVIEW AND APPROVAL PROCESS For purposes of this Guidebook, the terms "voucher" and "invoice" are used interchangeably. A. PURPOSE The purpose of this document is to provide
More information4 Essentials to Becoming a Successful Government Contractor
4 Essentials to Becoming a Successful Government Contractor Synergy Business Solutions W H I T E P A P E R RULES TOOLS CONTROLS SCHOOLS How to tap expertise and systems to pass government audits and fulfill
More informationPresented by Albert D. Goldwasser, CPA Government Contractor Consultant
Presented by Albert D. Goldwasser, CPA Government Contractor Consultant Agenda DCAA s Objectives Accounting 101 Indirect Cost Allocations SF 1408 Passing the DCAA Audit References What does the DCAA want?
More informationFebruary 3, 2016 12(1) CHAPTER 12
February 3, 2016 12(1) CHAPTER 12 Table of Contents Paragraph Page 12-000 Auditing Contract Termination, Delay/Disruption, and Other Price Adjustment Proposals or Claims 12-001 Contract Terminations and
More informationEvaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies
Inspector General U.S. Department of Defense Report No. DODIG-2016-001 OCTOBER 1, 2015 Evaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies INTEGRITY
More informationDCAA Contract Audits: Current Trends and Issues
DCAA Contract Audits: Current Trends and Issues Presented to: NCMA Huntsille, AL Chapter August 25, 2011 Darryl L. Walker, CPA Technical Director Beason & Nalley, Inc. Copyright 2011 Beason & Nalley, Inc.
More informationSubmitting a Quality Report. Presented by Laura Davis, Strategic Consulting Solutions, Inc.
Submitting a Quality Report Presented by Laura Davis, Strategic Consulting Solutions, Inc. Started in 2004 Based in Oak Ridge, TN Offices in Charleston, SC & Fayetteville, NC Focus on Government Contracting
More informationINCURRED COST ELECTRONICALLY (ICE) MANUAL
INCURRED COST ELECTRONICALLY (ICE) MANUAL TABLE OF CONTENTS VERSION 2.0.1c A. INTRODUCTION 1. Purpose 2. Benefits of Using ICE 3. Hardware/Software Requirements B. ICE SOFTWARE APPLICATIONS PACKAGE 1.
More informationTestimony. Patrick J. Fitzgerald Director, Defense Contract Audit Agency. before the. Commission on Wartime Contracting In Iraq and Afghanistan
Testimony of Patrick J. Fitzgerald Director, Defense Contract Audit Agency before the Commission on Wartime Contracting In Iraq and Afghanistan July 26, 2010 Chairman Thibault, Chairman Shays, and members
More information