1 APPENDIX A City of Cardiff Council Improving Scrutiny Project: Project Brief, January 2015 Project Purpose Cardiff is proud of its scrutiny arrangements and the important part scrutiny plays in Council improvement, and in representing citizens in holding to account the Cabinet for the decisions it makes. However, the Council is going through significant change in many ways, and will look very different in five years time. Effective local governance relies on a cohesive web of accountability, of which internal review is an intrinsic part. The purpose of the Project will be to ensure that scrutiny remains agile and able to play its role as a critical friend, in an environment that will see greater emphasis on partnership, collaboration, commissioning and other alternative models of delivery. Project Aim To equip Cardiff s Scrutiny function to meet the current needs and anticipated future challenges facing the Council s Executive and non-executive Members. To ensure that the Council s scrutiny structure enables Members to provide robust and effective overview and scrutiny that is relevant to the priorities of the organisation s Corporate Plan and operational challenges. To seek evidence to support recommendations for Members to agree any potential changes to current governance arrangements, as part of a wider major transformation of the City of Cardiff Council s services and structures. Project Objectives To take forward the learning from Cardiff s participation in the 2013 Wales Audit Office Improving Scrutiny Study, especially by using the 15 characteristics in the newly developed Framework for Effective Scrutiny in Wales as a mechanism for self-evaluation of the quality of scrutiny in Cardiff, and the planning of future Scrutiny Work Programmes.
2 To assess and make recommendations on the structures and arrangements that will be most appropriate to manage the scrutiny of the Council s transformation in coming years. To consult upon politically and organisationally, and take proposals forward for inclusion in the Council s 2016/17 Budget proposals. To address recommendations in the Local Government Measure (Wales) 2011, and subsequent recommendations in the Williams Review, to consider opportunities for improvement to current collaborative scrutiny arrangements with partners. Key Project Themes The purpose of Scrutiny as part of a holistic and effective governance framework in Cardiff, and its likely future challenges and priorities. The appropriate balance of priority achieved between holding to account, policy development and review, performance and improvement monitoring, finance and budget scrutiny etc. Maximising the impact of Scrutiny in Cardiff, and also to measure that impact so that resources can be most effectively targeted towards areas of highest impact. Setting in place effective and appropriate Scrutiny arrangements to deliver agreed priorities. Optimising interfaces between scrutiny and: External regulators, auditors and inspectors to ensure effective Council performance and minimise the burden of external regulation. The local population, so that the public has confidence in local democracy in the city, and sees Scrutiny as an accessible and effective avenue to represent its views and concerns. Cabinet Members, managers and key stakeholders so that everyone is clear about their role in supporting effective governance in Cardiff. Optimising arrangements for the scrutiny of partnerships, as public sector collaboration, transformation and commissioning grow ever more complex. Appropriate arrangements for maximising Scrutiny Member and officer skills and competency. Project Key Stakeholders Council Scrutiny Committee Chairs and Members; Council Leader and Cabinet; Opposition Party Group Leaders; Council Members; Chief Executive and senior management of the Council; Cardiff Third Sector Council and community and voluntary organisations regularly connecting with Scrutiny; Local strategic partners, key stakeholders and stakeholder organisations; Professional partners in the world of regulation, audit and inspection, regional and local government in Wales; The Centre for Public Scrutiny, WLGA Scrutiny Chairs Network and National Scrutiny Officers Network; Regional local government partners.
3 Project Methodology Desk Research (October 2014 to March 2015) Scan the horizon for legislative and policy changes in the wider environment that will influence Scrutiny in Cardiff over the coming 10 years. Identify from past reviews and evaluation of scrutiny in Cardiff the key learning points that have been derived, and to test how they can be applied. Glean from best practice analysis criteria for measuring the impact of scrutiny. Benchmark how effective scrutiny is conducted elsewhere, and how lessons can be applied to Cardiff. Face to face interviews (October 2014 to March 2015) Identify from key Project stakeholders their view on the key project themes identified above. Structured conversations (March and April 2015) Arrange events with Members and officers to Scrutiny Chairs to shape evidence from the desk research and interviews into draft key findings. Project Report (May 2015) Scrutiny Chairs to craft a report with key findings and recommendations for Cabinet to consider, and to enable implementation of agreed future arrangements. Project Governance Recognising the connections this Project makes between the organisational and the political, the Project will have a hybrid governance structure: It will operate as a joint scrutiny task and finish inquiry comprising the Council s five scrutiny chairs, and report through the Policy Review and Performance Committee. It will serve as a PQA Project within the Improved Governance strand of the Council s Programme of Organisational Change. Paul Keeping (Operational Manager, Scrutiny Services) will be Project Manager, and Marie Rosenthal (County Clerk and Monitoring Officer) will be Senior Responsible Officer. The Project will apply the Council s Service Review methodology to achieve its aims. The Project will be undertaken in partnership with the Centre for Public Scrutiny, a charity providing expertise and capacity in non-executive governance, as one of nine major case studies featured in a UK wide analysis of local authority transformation. For further details please contact: Monitoring Officer and County Clerk: Marie Rosenthal, Cardiff [email protected]
4 Operational Manager: Paul Keeping, Cardiff
5 Improving Scrutiny Project - Project Plan Timescale Action Purpose Sept 2014 Advisory support from CfPS confirmed Increase capacity and expertise Oct 2014 Project scoped and Scrutiny Chairs engaged as Project leads Provide Project leadership Agreement of Project governance arrangement within Org Devt Programme Provide Project governance Early Nov 2014 Project Mandate agreed Provide Project direction 18 Nov 2014 Scrutiny Chairs Liaison Forum Develop methodology CfPS interviews with: Scrutiny Chairs; Scrutiny officers; Monitoring Officer; Chief Officer, Change and Improvement. Give initial direction for Project methodology Scrutiny chairs discuss Project with Council Leader and Chief Executive Develop consensus for Project aims Nov Dec 2014 Desk Research on Core Cities scrutiny performance monitoring arrangements 8 Dec 2014 Project launched at Member Governance Seminar, and Briefed to Council Members and senior Communicate Project aims and Member managers involvement opportunities 8 Jan 2015 Scrutiny Chairs Liaison Forum Develop methodology 26 & 27 Jan 2015 CfPS interviews with key Project stakeholders (including Council Leader, Chief Executive, Cabinet Portfolio Member, Leaders of Liberal Democrat, Conservative and Independent Groups, Scrutiny Councillors who requested interviews, Director of Communities, representatives in WLGA and Welsh Government, Challenge Forum Advisor on Performance Management) Feb 2015 Further interviews with key stakeholders (through the month) March 2015 April 2015 Desk Research into Scrutiny Process and good practice (through the month) Scrutiny Chairs Liaison Forum (late Feb) Scrutiny Committees asked to establish a joint Scrutiny task and finish Inquiry (early March) Project Seminar for Scrutiny Members (early March) Scrutiny Chairs Liaison Forum (mid March) Interim Project findings circulated (mid March) Member and Manager Project Symposium (late March) Scrutiny Chairs Liaison Forum (early April) Develop methodology Enable Scrutiny Inquiry report to Cabinet Agree interim findings Prepare for Project Symposium Seek consensus for key findings Agree report, key findings & recommendations Draft Scrutiny Inquiry Report circulated (mid April) Seek final feedback on draft report May 2015 Final Draft Scrutiny Inquiry Report adopted by Scrutiny Committees and submitted to Cabinet Formally adopt draft report Tbc 2015 Cabinet receives and considers Draft Scrutiny Inquiry Report Make decisions on way forward Aug 2015 Implementation of agreed recommendations begins Implement decisions reached by Cabinet This timescale will enable managers to implement arrangements in time for the start of the 2016/17 financial year.
Code of Corporate Governance
www.surreycc.gov.uk Making Surrey a better place Code of Corporate Governance October 2013 1 This page is intentionally blank 2 CONTENTS PAGE Commitment to good governance 4 Good governance principles
CHILDREN AND YOUNG PEOPLE'S PLAN: PLANNING AND PERFORMANCE MANAGEMENT STRATEGY
CHILDREN AND YOUNG PEOPLE'S PARTNERSHIP BOARD CHILDREN AND YOUNG PEOPLE'S PLAN: PLANNING AND PERFORMANCE MANAGEMENT STRATEGY 1 Introduction 1.1 The purposes of this strategy are to set out: i) the arrangements
GOVERNING BODY MEETING held in public 29 July 2015 Agenda Item 4.4
GOVERNING BODY MEETING held in public 29 July 2015 Agenda Item 4.4 APPENDIX A Strategic Planning Process 2016/17 Strategic Planning Process 2016/17 Interlocking processes 5 Year strategic process: reviewed
2015 EDUCATION PAYROLL LIMITED STATEMENT OF INTENT
2015 EDUCATION PAYROLL LIMITED STATEMENT OF INTENT Published in August 2015 Education Payroll Limited 2015 EDUCATION PAYROLL LIMITED STATEMENT OF INTENT CONTENTS Foreword 3 Who We Are 4 What We Do 5 How
Appendix A: ICT and Information Management Strategy
Appendix A: ICT and Information Management 2014 2019 Head of Information and Business Change Sarah Caulkin October 2014 1 Version Control: Date Version Author Comments 04/08/14 0.1 Jo Harley First draft
Base for Work: Usk and Magor in Monmouthshire, with flexibility according to needs of the service.
ROL PROFIL Post: PROGRAMM MANAGR; Monmouthshire s 21C Schools Programme 5 year fixed term contract Post ID: CYP 003 Salary: Chief Officer range: 75,900 Responsible to: Chief Officer Children and Young
Performance Management and Service Improvement Framework
Performance Management and Service Improvement Framework Author Marcus Evans, Operational Director - Performance and Customer Insight Date: September 2014 Contents Page 1. Introduction 3 2. Strategic ning
Customer Service Strategy 2010-2013
Service Strategy 2010-2013 Introduction Our vision for customer service is: Oxfordshire County Council aims to deliver excellent customer service by putting our customers at the heart of everything we
Confident in our Future, Risk Management Policy Statement and Strategy
Confident in our Future, Risk Management Policy Statement and Strategy Risk Management Policy Statement Introduction Risk management aims to maximise opportunities and minimise exposure to ensure the residents
Technology Review Feedback Vale of Glamorgan Council
Technology Review Feedback Vale of Glamorgan Council Audit year: Annual Improvement Assessment 2011 Issued: October 2011 Document reference: 538A2011 Status of report The person who delivered the work
Consultation and Engagement Strategy
Consultation and Engagement Strategy Contents: 1. Introduction 2 2. Purpose 3 3. Aims and Objectives 4 4. Key principles 5 5. Delivery of the Strategy 6 6. Action Plan 2011-12 7 Appendix 1 Understanding
The Risk Management strategy sets out the framework that the Council has established.
Derbyshire County Council Management Policy Statement The Authority adopts a proactive approach to Management to achieve Best Value and continuous improvement and is committed to the effective management
BROMSGROVE DISTRICT COUNCIL PERFORMANCE MANAGEMENT BOARD 16 DECEMBER 2008 PERFORMANCE MANAGEMENT BOARD PROPOSED PROGRAMME 2008/09
BROMSGROVE DISTRICT COUNCIL PERFORMANCE MANAGEMENT BOARD 16 DECEMBER 2008 PERFORMANCE MANAGEMENT BOARD PROPOSED PROGRAMME 2008/09 Responsible Member Responsible Head of Service Councillor - James Duddy,
SKILLED, ENGAGED & MOTIVATED STAFF
Leadership and Management Capability Flexibility of Staff SKILLED, ENGAGED & MOTIVATED STAFF Skills Assurance Reward and Recognition Scottish Court Service People Strategy 2012 2015 1 Why have a People
CABINET RESPONSE TO REPORT OF COMMITTEE TITLED THE IMPACT OF UNDER OCCUPATION OF SOCIAL HOUSING (BEDROOM TAX) WELFARE REFORM IN CARDIFF.
CITY OF CARDIFF COUNCIL CYNGOR DINAS CAERDYDD COMMUNITY & ADULT SERVICES SCRUTINY COMMITTEE AGENDA ITEM 2 nd July 2014 CABINET RESPONSE TO REPORT OF COMMITTEE TITLED THE IMPACT OF UNDER OCCUPATION OF SOCIAL
Subject: ANNUAL GOVERNANCE STATEMENT 2014/15
ITEM NO: 7 Report To: OVERVIEW (AUDIT) PANEL Date: 21 September 2015 Reporting Officer: Ben Jay Assistant Executive Director (Finance) Wendy Poole Head of Risk Management and Audit Services Subject: ANNUAL
External Audit BV Performance Report: Delivering Change Management and Financial Sustainability
CLACKMANNANSHIRE COUNCIL THIS PAPER RELATES TO ITEM 05 ON THE AGENDA Report to: Resources and Audit Committee Date of Meeting: 24 September 2015 Subject: External Audit BV Performance Report: Delivering
Corporate Director Environment & Community Services
CABINET Meeting date: 23 July 2015 From: Corporate Director Environment & Community Services DIGITAL STRATEGY 1.0 EXECUTIVE SUMMARY 1.1 This paper presents Cabinet with a draft Digital Strategy for approval.
Performance Management Framework
Purpose of the framework: To explain how we manage in Poole. It applies to all directly managed services of the Council. Introduction: Effective management at the council will: Ensure our goals are prioritised
Investors in People 2013 - Communications Plan. Introduction What is IiP?
Investors in People 2013 - Communications Plan Introduction What is IiP? Investors in People specialises in transforming business performance through our employees. It is designed to help the Council achieve
DELIVERING OUR STRATEGY
www.lawsociety.org.uk DELIVERING OUR STRATEGY Our three year plan 2015 2018 >2 > Delivering our strategy Catherine Dixon Chief executive Foreword Welcome to our three year business plan which sets out
MARCH 2012. Strategic Risk Policy Update March 2012 v1.10.doc
MARCH 2012 Version 1.10 Strategic Risk Policy Update March 2012 v1.10.doc Document History Current Version Document Name Risk Management Policy Statement and Strategic Framework Last Updated By Alan Till
Version No: 2 Date: 27 July 2015. Data Quality Policy. Assistant Chief Executive. Planning & Performance. Data Quality Policy
Version No: 2 Date: 27 July 2015 Data Quality Policy Assistant Chief Executive Planning & Performance Data Quality Policy Contents 1. Summary Statement 2. Context 3. Purpose 4. Scope 5. Detail of the policy
Performance Detailed Report. May 2008. Review of Performance Management. Norwich City Council. Audit 2007/08
Performance Detailed Report May 2008 Review of Performance Management Audit 2007/08 External audit is an essential element in the process of accountability for public money and makes an important contribution
Council Meeting, 26/27 March 2014
Council Meeting, 26/27 March 2014 HCPC response to the Final Report of A Review of the NHS Hospitals Complaint System Putting Patients Back in the Picture by Right Honourable Ann Clwyd MP and Professor
Welsh Government Response to the Report of the National Assembly for Wales Public Accounts Committee on Grant Management in Wales Final Report
Welsh Government Response to the Report of the National Assembly for Wales Public Accounts Committee on Grant Management in Wales Final Report The Welsh Government appreciates both the time and effort
Annual Governance Statement 2014/2015
Annual Governance Statement 2014/2015 This is a signed statement by the Executive Leader and Chief Executive certifying that governance arrangements are adequate and operating effectively within the Council.
PUBLIC HEALTH WALES NHS TRUST CHIEF EXECUTIVE JOB DESCRIPTION
PUBLIC HEALTH WALES NHS TRUST CHIEF EXECUTIVE JOB DESCRIPTION Post Title: Accountable to: Chief Executive and Accountable Officer for Public Health Wales NHS Trust Trust Chairman and Board for the management
THE ROYAL BOROUGH OF KENSINGTON AND CHELSEA SOCIAL SERVICES COMMITTEE -13TH JUNE 2001 REPORT BY THE EXECUTIVE DIRECTOR OF HOUSING AND SOCIAL SERVICES
THE ROYAL BOROUGH OF KENSINGTON AND CHELSEA SOCIAL SERVICES COMMITTEE -13TH JUNE 2001 REPORT BY THE EXECUTIVE DIRECTOR OF HOUSING AND SOCIAL SERVICES BEST VALUE REVIEW OF ADULT LEARNING DISABILITY SERVICES
Richmond-upon-Thames Performance Management Framework
Richmond-upon-Thames Performance Management Framework Introduction Everyone at the Council has a role in Performance Management. It is therefore important that we all understand what is involved. This
CHANGE MANAGEMENT PLAN
Appendix 10 Blaby District Council Housing Stock Transfer CHANGE MANAGEMENT PLAN 1 Change Management Plan Introduction As part of the decision making process to pursue transfer, the Blaby District Council
Culture of Care Barometer: project plan
Culture of Care Barometer: project plan 1. Background to the Culture of Care Barometer: its origins The healthcare agenda over recent years has been dominated by quick fix solutions. As a result both the
Report of the Assistant Director Strategy & Performance to the meeting of Corporate Governance & Audit Committee to be held on 20 March 2009.
Report to the Corporate Governance & Audit Committee. Report of the Assistant Director Strategy & Performance to the meeting of Corporate Governance & Audit Committee to be held on 20 March 2009. Subject:
DATA QUALITY STRATEGY
DATA QUALITY STRATEGY If you or anybody you know requires this or any other council information in another language, please contact us and we will do our best to provide this for you. Braille, Audio tape
Appendix 1: Performance Management Guidance
Appendix 1: Performance Management Guidance The approach to Performance Management as outlined in the Strategy is to be rolled out principally by Heads of Service as part of mainstream service management.
Volunteering Australia
Project plan and time frame: Revised 6 June 2014 Project manager BNG: Julie Nyland Project manager VA SA NT: Olympia Vozvotecas Project Management Group: members of the National Standards Working Group
How Good is Our Council?
A guide to evaluating Council Services using quality indicators Securing the future... l Improving services l Enhancing quality of life l Making the best use of public resources Foreword Perth & Kinross
Councillor role descriptions
Councillor role descriptions All Councillors:- Community Leader Champion your division Deal with casework Represent the community within the Council and other agencies Campaign on local issues Keep in
City and County of Swansea. Human Resources & Workforce Strategy 2013-2017. Ambition is Critical 1
City and County of Swansea Human Resources & Workforce Strategy 2013-2017 Ambition is Critical 1 Delivering quality services for a safer, greener, smarter, fairer, healthier, richer Swansea Executive Summary
TRUST POLICY FOR EMERGENCY PLANNING
TRUST POLICY FOR EMERGENCY PLANNING Reference Number: CL-OP/ 2013/027 Version: 1.4 Status: New Draft Author: Ashley Reed Job Title: Head of Security and EPO Version / Amendment History Version Date Author
1.1 Terms of Reference Y P N Comments/Areas for Improvement
1 Scope of Internal Audit 1.1 Terms of Reference Y P N Comments/Areas for Improvement 1.1.1 Do Terms of Reference: a) Establish the responsibilities and objectives of IA? b) Establish the organisational
Data Quality Policy. Appendix A. 1. Why do we need a Data Quality Policy?... 2. 2 Scope of this Policy... 2. 3 Principles of data quality...
Data Quality Policy Appendix A Updated August 2011 Contents 1. Why do we need a Data Quality Policy?... 2 2 Scope of this Policy... 2 3 Principles of data quality... 3 4 Applying the policy... 4 5. Roles
POLICY ON CORPORATE GOVERNANCE FOR LESOTHO PUBLIC ENTERPRISES, GOVERNMENT AGENCIES AND ENTITIES
POLICY ON CORPORATE GOVERNANCE FOR LESOTHO PUBLIC ENTERPRISES, GOVERNMENT AGENCIES AND ENTITIES PREAMBLE The Government of Lesotho has noted the increasing demand of the citizens for better control and
Bridgend County Borough Council. Corporate Risk Management Policy
Bridgend County Borough Council Corporate Risk Management Policy December 2014 Index Section Page No Introduction 3 Definition of risk 3 Aims and objectives 4 Strategy 4 Accountabilities and roles 5 Risk
7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers
Contents Page 1 Introduction 2 2 Objectives of the Strategy 2 3 Data Quality Standards 3 4 The National Indicator Set 3 5 Structure of this Strategy 3 5.1 Awareness 4 5.2 Definitions 4 5.3 Recording 4
HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK
HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK July 2013 1 P age Contents Page 1.0 Definition 3 2.0 Context 3 3.0 Purpose and aim of the policy 4 4.0 Policy Statement 4 5.0 Framework for Performance Management
Trust Board Report. Review of the effectiveness of the IM&T Committee
1. Introduction Trust Board Report Review of the effectiveness of the The meets every eight weeks, with a specific responsibility for governance, strategic direction, approval and direction of developments
BPU Head of Service Position Statement
BPU Head of Service Position Statement The aim of this paper is to provide a position statement regarding the identified BPU functions within the Annual Council Reporting Framework. Workforce It is considered
DATA QUALITY POLICY April 2010 Updated January 2015 1
DATA QUALITY POLICY April 2010 Updated January 2015 1 Contents page 1. Introduction 3 2. Context and Purpose 3 3. Why is data quality important? 4 4. Characteristics of good quality data 5 5. Policy Objectives
Housing Association Regulatory Assessment
Welsh Government Housing Directorate - Regulation Housing Association Regulatory Assessment Melin Homes Limited Registration number: L110 Date of publication: 20 December 2013 Welsh Government Housing
council s Budget and Financial Planning Framework
Basildon District Council Financial Planning Framework 1. Introduction The Financial Planning Framework underpins the Council s Medium Term Financial Strategy and sets out the financial planning processes
SUBJECT: Talent Management Strategy 2016 2020. Councillor Sandra Walmsley (Cabinet Member for Resources and Regulation)
REPORT FOR DECISION DECISION OF: CABINET DATE: 13 APRIL 2016 SUBJECT: Talent Management Strategy 2016 2020 REPORT FROM: Councillor Sandra Walmsley (Cabinet Member for Resources and Regulation) CONTACT
How councils work: an improvement series for councillors and officers. Managing performance: are you getting it right?
How councils work: an improvement series for councillors and officers Managing performance: are you getting it right? Prepared for the Accounts Commission October 2012 The Accounts Commission The Accounts
How To Manage A Corporate Council
JOB DESCRIPTION POST: SERVICE: GRADE: Audit and Governance Manager Corporate Governance and Support SE1 MAIN PURPOSE The Governance Manager will form part of the Council s bronze level of management and
EVALUATION OF THE CORPORATE PERFORMANCE MANAGEMENT FRAMEWORK
Appendix A EVALUATION OF THE CORPORATE PERFORMANCE MANAGEMENT FRAMEWORK 1. Introduction and Background 1.1 The County Council introduced a new corporate performance management framework in September 2002.
CARE HOME/PROVIDER GOVERNANCE: UPDATE REPORT
QUALITY & SAFETY COMMITTEE 09 OCTOBER 2014 AGENDA ITEM 3.2 CARE HOME/PROVIDER GOVERNANCE: UPDATE REPORT Report of Paper prepared by Purpose of Paper Action/Decision required To update the on the outcomes
Risk Management & Business Continuity Manual 2011-2014
ANNEX C Risk Management & Business Continuity Manual 2011-2014 Produced by the Risk Produced and by the Business Risk and Business Continuity Continuity Team Team February 2011 April 2011 Draft V.10 Page
Appendix 1 Action Plan and Progress Against Current Status of Peer Review and Ofsted Fostering Report Recommendations
Appendix 1 Action Plan and Progress Against Current Status of Peer Review and Ofsted Fostering Report Recommendations Peer Review Recommendations Recommendation Timescale Lead officer Actions Evidence/Impact
Project, Programme and Portfolio Management Delivery Plan 6
Report title Agenda item Project, Programme and Portfolio Management Delivery Plan 6 Meeting Performance Management and Community Safety Panel 27 April 2009 Date Report by Document number Head of Strategy
Business Plan 2012/13
Business Plan 2012/13 Contents Introduction 3 About the NFA..4 Priorities for 2012/13 4 Resources.6 Reporting Arrangements.6 Objective 1 7 To raise the profile and awareness of fraud among individuals,
Hertsmere Borough Council. Data Quality Strategy. December 2009 1
Hertsmere Borough Council Data Quality Strategy December 2009 1 INTRODUCTION Public services need reliable, accurate and timely information with which to manage services, inform users and account for performance.
Mary Immaculate College. Human Resources Strategy 2014-2016
1.0 Introduction Mary Immaculate College Human Resources Strategy 2014-2016 1.1 Mary Immaculate College Strategic Plan 2012-2016 rests on 7 foundational pillars, each pillar representing a thematic imperative
Rachael Shimmin, Corporate Director of Adults, Wellbeing and Health. Councillor Morris Nicholls, Portfolio Holder for Adult Services
Cabinet 24 July 2012 Local HealthWatch Transition Plan including NHS Complaints Advocacy Service [Key Decision AWH 03/12] Report of Corporate Management Team Rachael Shimmin, Corporate Director of Adults,
Implementation Plan: Development of an asset and financial planning management. Australian Capital Territory
Implementation Plan: Development of an asset and financial planning management framework for TAMS Australian Capital Territory NATIONAL PARTNERSHIP AGREEMENT TO SUPPORT LOCAL GOVERNMENT AND REGIONAL DEVELOPMENT
Care and Social Services Inspectorate Wales
Care and Social Services Inspectorate Wales Care Standards Act 2000 Adoption and Children Act 2002 Inspection Report Voluntary Adoption Agencies In Wales St David`s Children Society 28 Park Place Cardiff
The ISO 14001 standard
The ISO 14001 standard ISO14001 is designed for any organisation wishing to demonstrate to customers, insurers, regulators, the public and financial institutions, that the organisation is committed to
GUIDELINES FOR THE CONDUCT OF PERFORMANCE AUDITS
GUIDELINES FOR THE CONDUCT OF PERFORMANCE AUDITS NOVEMBER 2013 THE ANAO S LEGISLATIVE FRAMEWORK The Auditor-General Act 1997 (the Act) sets out the functions, mandate and powers of the Auditor-General
HPF Tool. Template for the Performance and Accountability Statement Second round reviews. Amended December 2012
HPF Tool Template for the Performance and Accountability Statement Second round reviews Amended December 2012 The High Performance Framework was developed by the Public Sector Performance Commission. This
Manchester City Council Report for Information. Managing Attendance (Real Time Absence Reporting)
Manchester City Council Report for Information Report to: Subject: Overview and Scrutiny Human Resources Subgroup - 25 January 2011 Managing Attendance (Real Time Absence Reporting) Report of: Assistant
Information Governance Strategy
Information Governance Strategy ONCE PRINTED OFF, THIS IS AN UNCONTROLLED DOCUMENT. PLEASE CHECK THE INTRANET FOR THE MOST UP TO DATE COPY Target Audience: All staff employed or working on behalf of the
NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013
APPENDIX 1 NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013 Page 1 of 10 1. INTRODUCTION It is widely recognised that asset management is a core component of effective
34 12.03.2009 Resources
34 RESOURCES OVERVIEW AND SCRUTINY COMMITTEE Minutes of the proceedings at a meeting of the Committee held in the Georgian Room at the Town Hall, Kendal on Thursday 12 March 2009, at 2.00 p.m. Present
Health and Safety Improvement Program (Continuous Self- Assessment) CSA Guidelines. October, 2014
Health and Safety Improvement Program (Continuous Self- Assessment) CSA Guidelines October, 2014 Contents 1 Executive Summary... 2 2 More information... 2 3 Context... 2 3.1 Continuous Self-Assessment