DET NORSKE VERITAS. Major Hazard Incidents Arctic Offshore Drilling Review. National Energy Board

Size: px
Start display at page:

Download "DET NORSKE VERITAS. Major Hazard Incidents Arctic Offshore Drilling Review. National Energy Board"

Transcription

1 Major Hazard Incidents Arctic Offshore Drilling Review National Energy Board Report No.: NEB /DNV Reg. No.: ANECA 851 February 2011

2 Executive Summary On 11 May 2010 the National Energy Board (Board) announced that it would conduct a review of Arctic safety and environmental offshore drilling requirements (the Arctic Review). The Arctic Review will examine the best available information concerning the hazards, risks and mitigation measures associated with offshore drilling activities in the Canadian Arctic and measures to both prevent and respond to accidents and malfunctions. Investigations conducted into previous major accidents reveal that systemic or organizational deficiencies lead or contributed to those accidents. Understanding whether there are any trends, such as specific management system failures which put an organization at greater risk for a catastrophic event, would be of interest in the context of the Arctic Review. In November 2010 the Board contracted Det Norske Veritas (DNV) to conduct a comparative analysis of major accidents in order to identify trends related to root cause(s) and contributing factors. The major accidents selected for the assessment includes: Ocean Ranger 1982, Chernobyl 1986, Piper Alpha 1988, Westray 1992, Longford 1998, Columbia 2003 and Texas City The assessment of each accident includes a context and synopsis of the event, key findings and an analysis. The key findings are summarized from the information obtained from the official investigation or inquiry reports which were supplied to DNV by the NEB. The list of reports provided is included in the Reference section at the end of this report. In order to be able to identify trends and conduct a direct comparison of the findings from the various accidents, the key findings were categorized on the basis of the NEB Management and Protection Program Evaluation and Audit Protocol. The protocol is used by the NEB to assess the adequacy and effectiveness of companies management and protection programs. The assessment of these accidents indicated that, although formal safety programs or management systems had been developed, they were not effectively implemented or reviewed on a regular basis to monitor their adequacy and effectiveness. Also, for most of the incidents an adequate hazard identification and risk assessment process had not been followed. The relevance of these issues become important because the basic responsibility for the safe operation of any activity lies with management of the organization which must ensure all the applicable programs and systems are implemented, reviewed and updated on a regular basis to reflect any required improvements. In addition, in most cases the applicable regulatory oversight was not comprehensive or focused enough to ensure gaps were identified and the required corrective and preventive actions were developed and implemented. Date : February 2011 Page i

3 Table of Contents EXECUTIVE SUMMARY...i OCEAN RANGER Context...1 Synopsis Of The Event...2 Key Findings...3 Analysis...7 CHERNOBYL Context...10 Synopsis Of The Event...11 Key Findings Of The Insag-7 Report...12 Analysis...14 PIPER ALPHA Context...17 Synopsis Of The Event...18 Key Findings...19 Analysis...22 WESTRAY Context...25 Synopsis Of The Event...25 Key Findings...26 Analysis...28 LONGFORD Context...31 Synopsis Of The Event...32 Key Findings...33 Date : February 2011 Page ii

4 Analysis...35 COLUMBIA Context...38 Synopsis of the event...38 Key Findings...39 Analysis...41 TEXAS CITY Context...44 Synopsis of the event...45 Key Findings...46 Analysis...49 REFERENCES...51 Appendices Appendix A - Management and Regulatory Comparison Tables Appendix B - NEB Management and Protection Program Evaluation and Audit Protocol Date : February 2011 Page iii

5 List of Figures Figure 1 Structural components and working areas of the Ocean Ranger...2 Figure 2 - RBMK Reactor, Source: OECD NEA...11 Figure 3 Pipeline Connections of the Piper Field...17 Figure 4 Piper Alpha platform: simplified east elevation...18 Figure 5 Southwest 2 Section of the mine, showing the location of the equipment at the time of the explosion...26 Figure 6 Gas Pipelines...31 Figure 7 Lean oil / Rich oil circulation...32 Figure 8 Tower overfill and blowdown drum hydrocarbons release...44 Figure 9 Heating of feed in the splitter tower...45 Date : February 2011 Page iv

6 OCEAN RANGER 1982 Context The Ocean Ranger was the largest self-propelled semi-submersible offshore drilling unit owned by Ocean Drilling and Exploration Co (ODECO) when launched in In 1980 its registry was transferred to the United States which made it subject to regulations of the International Maritime Organization. When the Ocean Ranger began to drill off the east coast of Canada in November 1980, for Mobil Oil Canada Ltd. (Mobil), the drilling operation was governed by the conditions of the permits issued to Mobil by the Government of Canada and the Government of Newfoundland & Labrador. However, Canada Oil and Gas Lands Administration (COGLA) and the Newfoundland and Labrador Petroleum Directorate (the Petroleum Directorate) relied on the certificate issued by the American Bureau of Shipping and the U.S. Coast Guard to attest to the safety of the marine operations of the rig. The drilling operations and in fact all operations on the rig and even the rig itself were under the control of the toolpusher, the senior ODECO person on the rig. All the crew, except Mobil personnel and Mobil-contracted personnel, reported directly or indirectly to the toolpusher. Mobil always had a drilling foreman on the rig whose responsibility was to represent Mobil s interests by monitoring the operation to ensure that drilling was completed as expeditiously and economically as possible. On February 15 th, 1982, the Ocean Ranger with 84 crew members on board capsized and sank in a fierce storm in the area of the Hibernia oil field on the Grand Banks of Newfoundland. There were no survivors. It was determined that the rig sank after seawater entered its ballast control room through a broken porthole and caused an electrical malfunction in the ballast panel controlling the rig's stability. Two other rigs in the area, the Sedco 706 and the Zapata Ugland, survived the storm. The Ocean Ranger accident together with similar tragedies such as the Alexander Kielland in 1980 and the Glomar Java Sea in 1983, focussed concern on and raised questions about the reliability of the technology involved in offshore drilling operations under adverse environmental conditions and the adequacy of the regulatory agencies whose function is, at least in part, to ensure these operations are carried out safely. Date : February 2011 Page 1

7 Figure 1 Structural components and working areas of the Ocean Ranger Synopsis of the event On February 1982, Mobil was operating the Ocean Ranger and two other semi-submersible drilling units. On Saturday February 13, a series of weather forecasts were received. They identified a developing storm with high speed winds, heavy seas, flurries and freezing spray anticipated by Sunday night. On Sunday, drilling operations continued until 4:30 p.m. at which time the crew started to disconnect from the wellhead and hang-off due to the fast approaching storm. There was little communication between the Ocean Ranger and Mobil personnel onshore; however an internal radio communication describing the breaking of a portlight (window) and water in the ballast control room was overheard by the Sedco 706 and a stand-by vessel, both of which were in the area. The radio conversation continued stating the control panel was wet and discharging shocks, the valves were opening and closing on their own which required the assistance of an electrical technician. By 10:00 pm, platform staff contacted personnel located onshore to provide a status update on the incident. They reported that the ballast control system had no problem and all equipment was functioning normally. There was no report from the Ocean Ranger that the rig was experiencing difficulties other than the weather conditions. At 1:00 a.m. on February 15th, the senior drill foremen on the Ranger notified onshore Mobil personnel of a listing of the rig to the port side and requested that the Coast Guard be alerted. Date : February 2011 Page 2

8 Attempts to isolate the problem and to implement countermeasure to address the list were ineffective. A mayday call was sent out from the Ocean Ranger requesting immediate assistance. A request for assistance was sent to helicopters under contract with Mobil, stand-by vessels for the Ocean Ranger and two near-by drilling units. The last communication at 1:30 a.m. indicated that the crew was going to lifeboat stations. At 3:28 a.m., it was reported from the nearby rig Sedco 706 that the Ocean Ranger had disappeared from the radar. The Royal Commission on the Ocean Ranger Marine Disaster stated in its Report: The failure of the crew to adopt and follow a proper and prudent operational practice closing deadlights in storm conditions allowed the first link in the chain of events to be forged. In attempting to remedy the problem caused by the ingress of water into the ballast control room, the crew, because the lack of understanding of the ballast system as a whole, reactivated the panel as part of the maintenance process and unintentionally allowed water to enter the port pontoon. Then, in attempting to remedy the port forward list of the rig by pumping out forward tanks, they failed to realize the possibility that one or more valves to ballast tanks were open, and actually increased the forward list by unintentionally pumping out of the tanks. The crew did not understand the proper function of the manual control rods and inserted them in a mistaken attempt to close the valves. This resulted in the opening of up to 15 ballast tank valves, which allowed ballast water to gravitate forward and accelerated the rate of forward trim. 1 The crew tried to evacuate using the lifeboats, however only one launched but was damaged under the storm conditions. The stand-by vessel took approximately one hour to get to the scene and did not have the appropriate equipment to rescue the men. All 84 crew members of the Ocean Ranger lost their lives in the accident. Key Findings The capsizing of what was then the largest self-propelled semi-submersible started with the breakage of a small porthole that escalated through a series of events which eventually resulted in the accident. The Royal Commission Report identified the following deficiencies: 1. Exposed Location of Ballast Control Room The location of the ballast control room was within the wave-splashing range of the ocean. 2. Weakness caused by Portlights in the column Portlights with inadequate glass strength were located in the columns of the drill rig. 1 From The Royal Commission on the Ocean Ranger Marine Disaster Report Date : February 2011 Page 3

9 An operator was required to observe draft marks on outer legs by opening the deadlight which led to the habit of leaving the deadlight open at all times. 3. Lack of protection from flooding in Ballast Control Room There was a lack of watertight protection on the control panel as the ballast control room was considered a dry zone. 4. Lack of an adequate manual system for the ballast valves the rig had a mechanical backup system to manually control the ballast valves from the ballast control room and bypass the panel in case of electrical failure. There was no diagram or instructions to operate the system. The operator was not formally trained on either system. 5. Vulnerability of the chain lockers to flooding The locker rooms located at the top of the four outer legs were used to store wire rope and anchor chains. These were vulnerable to flooding due to large open entry holes without weather-tight covers and no permanently installed means of pumping out water. 6. Lack of evacuation procedures during emergencies in the Marine Operating Manual Mobil s contingency plan and emergency procedures specified procedures in case of oil spills, iceberg encroachment, severe weather, loss of a supply vessel or crash of a helicopter, but did not provide contingency procedures for the evacuation of the rig. In addition, there was no copy of the plan available on board the Ocean Ranger and ODECO personnel were not familiar with it. Also, ODECO s Emergency Procedures Manual was different from Mobil s with variances in procedures, criteria for cessation of drilling, and site responsibilities. 7. Lack of manuals and technical information regarding the ballast control room The location of the tank level sensors at the end of the tank instead of the center may have led to misinterpretations of the ballast tank levels. Conversion tables provided in the Booklet of Operating Conditions were used for the rig s stability. The tables were accurate only under level conditions and did not contain corrections which would apply to sloping tanks. The water pumping system could not pump from the forward tanks as the forward list created a vertical distance that exceeded the suction available. 8. Lack of adequate marine training for the key personnel. Ballast operators were not formally trained nor did they have to pass tests to determine whether they understood the systems and their operation. After their regular 12-hour work shift was completed, personnel interested in becoming ballast control operators were permitted to spend time in the ballast control room and complement this experience with private studies. Date : February 2011 Page 4

10 The formal training policy of ODECO followed the general drilling industry approach where inexperienced employees could learn from the bottom up. This required a minimum of 80 weeks of experience on the rig before a crew member could be recruited to train as a ballast operator. The actual practice was to identify candidates to train for the position and promote them without the minimum requirements identified above. With the basic understanding on how to operate the control panel and complete daily calculations and stability logs, a candidate could be appointed as full-time operator. In addition, no specific training for abnormal conditions was provided. The organizational structure and roles and responsibilities on the rig were organized similarly to those on land-based rigs. The marine operations that involved stability and safety of the rig were considered support operations instead of primary core operations as it would be on a ship. While the rig was lifting its anchor and moving, it was the master who was in command, but when the rig was moored on location, it was the toolpusher who was in command even though he had no marine certification or knowledge of the principles of stability. The master also had specific roles and responsibilities, but did not have proper training to operate the ballast control systems. In addition, he had no crew under his direct and exclusive control. The master s presence was mainly to ensure compliance with the requirements of the Certificate of Inspection. The scope of emergency training was not specified by regulations which stipulated only the test frequency for emergency response systems. The emergency drills conducted were not sufficiently thorough to ensure that the systems were effective. The supervisors in charge and the crew typically had no marine training, and lifeboats were rarely lowered to the sea during exercises making real-life evacuations that much more difficult. 9. Lack of knowledge of the operation of the ballast control system led directly to the disaster The control panel operated electric solenoids which, using compressed air, controlled valves in the pontoons. These valves, located along the pontoons, controlled the trim of the rig with the use of water. If the supply of electricity or compressed air was lost, all remotely operated valves closed automatically. This fail-safe mechanism was to ensure a valve would never be left open unintentionally if a power failure should occur. If power was lost the ballast valves and pumps could be operated manually from the pump rooms. The valves could also be controlled with the insertion or removal of brass rods into the solenoid valves. The rig operator on duty at the time of the incident appeared to believe that inserting brass rods in the solenoids would close the valves, not open them. 10. Inadequate interpretation of weather forecasting and weather reporting procedures Date : February 2011 Page 5

11 Misunderstandings existed between NORDCO (Newfoundland Oceans Research and Development Corp.), Mobil and ODECO regarding terminology used in weather forecasts. However, operational decisions were based on weather conditions as they occurred not on weather forecasts. 11. Inadequate lifesaving equipment The primary lifesaving equipment for the rig included 4 fibreglass lifeboats, 10 life rafts, 127 life preservers, 25 buoyant work vests, 15 life rings with lines and a helipad. The evidence indicated that only the lifeboats and life preservers were actually used. Not all of the four lifeboats were available to the crew. At the time of the loss, although one of the new Watercraft lifeboats was installed, it is not known whether it was provisioned and fully operable and the other was stored on deck awaiting installation. Also, it is not known whether the crew received instructions in the operation of the Watercraft lifeboats since the release mechanism on the Watercraft lifeboats differed from that on the Harding lifeboats. A Harding lifeboat located on the stern was launched during evacuation with 30 or more crew members on board, but it was badly damaged which led to its capsize. The Watercraft lifeboat located on the stern was not recovered. The Harding lifeboat located on the bow and the uninstalled Watercraft lifeboat were recovered, but neither showed any signs of having been occupied. In 1979, the U.S. Coast Guard had directed ODECO to replace the existing lifeboats with davit-launched life rafts or an acceptable substitute. ODECO had not replaced or changed the existing lifeboats, and opted to install two additional lifeboats rather than davitlaunched life rafts. The deployment method for the 20-person life rafts required them to be thrown overboard and entered from the water, an impractical mode of escape during severe storm conditions. There were no full-immersion survival suits designed to resist cold water and hypothermia on board. These suits were not a regulatory requirement at the time, but in June of 1981 COGLA had recommended that survival suits be installed on all MODUs and support craft operating on the East Coast of Canada and in the Arctic. The industry and COGLA did not move quickly in implementing this recommendation. 12. Inadequate Standby Vessel capability The stand-by vessels and helicopters which were called for assistance provided regular supply and support to the rig. They were not equipped with gear for rescue attempts. Only one lifeboat was encountered with a number of occupants in it. All occupants perished, some from exposure, and some while trying to climb onto the supply boat during a rescue attempt using improvised life ring lines. Date : February 2011 Page 6

12 13. Communications issues A combined public address and intercom system was used for communicating onboard and for sounding the fire and rig abandonment alarm. In the event of a loss of power, these systems were inoperative. A telephone system was the backup to the public address system however no units were installed in the ballast control room or pump rooms. The manual ballasting operations, which could be performed in the pump rooms, would have had to be coordinated from the ballast control room where the ballast control gauges were located, but the failure of the public address system and the lack of a telephone system between these locations would have made this activity difficult. 14. Regulatory issues At the time of the accident, both Federal and Provincial governments had policies that applied to the offshore industry in regards to the local labour content. The efficiency and safety of the drilling contractor s operation depended on the skills of its crew. The requirement to replace the regular crew with local residents could increase inefficiencies and risk to the operation. The Ocean Ranger Inquiry Panel suggested that the rate of phase in of local residents ought to be controlled to ensure acceptable standards of safety are not compromised. The Panel also indicated that there was no evidence that the insistence by the Provincial Government of the hiring of local residents caused or contributed in any way to the loss of the rig and its crew. COGLA and the Newfoundland Petroleum Directorate had made the incorrect assumption that ODECO would comply with the 1979 Certificate of Inspection issued by the U.S. Coast Guard. However, the U.S. Coast Guard never monitored or followed-up on the conditions attached to the certificate. Canadian authorities did not conduct regulatory oversight of the foreign registered unit even though it could have done so under the drilling permit issued to the operator. Analysis Policy and Commitment - ODECO s career management policy focused on growth through experience without formal training. Employees could acquire various qualifications through exposure to various job activities. This industry approach was not supported by sufficient training measures which showed a lack of commitment to formally improve employees and overall company performance in the area of safety. Planning - The chain of events which resulted in the loss of the Ocean Ranger resulted from a coincidence of severe storm conditions, design inadequacies and a lack of knowledgeable human intervention. Human error, lack of knowledge of the vulnerability of the rig and its ballast Date : February 2011 Page 7

13 control system and a mistaken reaction to the malfunction of the equipment compounded the design shortcomings and led directly to the disaster. Implementation - The organizational command on board changed depending on the activities being carried out by the rig. When the rig was moored on location, it was the toolpusher who was in command even though he had no marine certification or knowledge of the principles of stability. The master, who was in command while the rig was lifting its anchor and moving, was responsible for the ballast system during drilling operations but did not have proper training to operate the ballast control systems and had no crew under his direct and exclusive control. In effect, the offshore drilling semi-submersible was regarded as an industrial operation in a marine setting with no marine training for its crew. The Mobil representative onboard had little influence as he had no decision powers with respect to the rig activities. The company failed to provide the required specific training for key positions. The emphasis of on-the-job training was not complemented with formal training. Emergency training was not mandatory and did not ensure evacuation procedures were well understood by the crew. Poor knowledge of the systems and wrong assumptions made by the workers during the emergency were contributing factors to the disaster. Overall guiding documentation was not reviewed or revised on a regular basis. The crew relied on experience in order to perform its duties. There was a lack of manuals, technical information, adjusted calculation charts for the ballast control room, and proper emergency procedures. Evacuation procedures were not posted nor enforced by managers. Under normal operation the ballast control panel had a level of uncertainty where operators were not fully aware of the effects of actions taken. Inaccurate measurements required for stability could compromise the safety of operations. Measures taken during abnormal situations were not understood due to lack of training and knowledge of the system. The lack of a secondary communication system between the ballast control room and the pump room prevented coordination of manual operations in case of complete electrical failure. The lack of applicable evacuation exercises did not allow awareness of the operation and practice of the evacuation plan and safety equipment. Checking and Corrective Actions - Non compliances and corrective actions identified by regulatory authorities were not immediately addressed. The addition of appropriate on-load 2 release life rafts and survival suits could have saved lives. 2 Mechanism that allows boarding on the ship and release at any time Date : February 2011 Page 8

14 The draft marks, which were attached to the four corner columns and were up to 200 ft. away from the ballast control room, were monitored visually through the portlights located in the ballast control room. This was a difficult task during normal operations and impossible during bad weather or heavy seas. No action was taken to improve the monitoring methods although remote reading gauges were commercially available and were being used on other similar drilling rigs. Management Review The Ocean ranger had been operating off the East Coast of Canada for more than one year before the tragedy. No established process was in place to conduct a management review of the operations to ensure the applicable programs and systems had been developed, implemented and improved when required. A management system with regular monitoring could have identified shortcomings and prevented the development of undocumented practices. Date : February 2011 Page 9

15 CHERNOBYL 1986 Context The Chernobyl Nuclear Power Plant was located in Pripyat, Ukraine which was part of the Union of Soviet Socialist Republics (USSR) at the time of the incident. The explosion of one of the RBMK 3 reactors resulted in the emission of a plume of radioactive graphite and debris over an extensive area, including Pripyat. The plume eventually drifted over large parts of the western Soviet Union, Belarus, the Ukraine and also much of Europe. On April 26 th, 1986, the Chernobyl Unit 4 suffered a nuclear accident during experiments to see if after steam was shut off from the turbine, the still rotating generator would create enough power before auxiliary motors could be brought online in the event of loss of external power sources. The disaster and its consequences are considered the worst nuclear plant accident in history. The first report on the incident from the International Nuclear Safety Advisory Group (INSAG) suggested that the accident occurred due to a low probability coincidence of a number of violations of rules and procedures by the operating staff and those responsible for authorizing the test (INSAG-1). After the INSAG-1 report was published in September 1986, considerable analysis by various international experts led to new insights into the physical characteristics of the RBMK reactor and also into some details of the progression of the accident. Those insights led to a need to revise some of the details of the scenario presented in INSAG-1 and to alter some important conclusions. The results of these additional investigations were released in the INSAG-7 report which was published in Soviet light water cooled graphite moderated reactor Date : February 2011 Page 10

16 Figure 2 - RBMK Reactor, Source: OECD NEA Synopsis of the event On April 25 th, 1986, an experiment was scheduled at the Chernobyl Nuclear Power Plant to test whether, in the event of a loss of external power, the reactor core could be cooled down using the rotational momentum of the steam turbine to generate electricity to run the main cooling water pumps until the back-up diesel generators could take over. The experiment was to take place following a normal shutdown procedure, and was not anticipated to compromise the safety of the reactor. At 01:06 a.m. on that day, operators started the reduction of the reactor power output from 3200 MW using 31 manual control rods 4. When the reactor reached half of the output, a series of control measurements were performed. This was followed by the disconnection of the emergency core cooling system (ECCS) as part of the procedure to avoid interference with the test. At that point, a request was received from the Kiev electrical grid controller to postpone further reduction of Chernobyl's power output to meet demand. The test was postponed until 23:10, close to the shift change. On April 26 th at 00:05 a.m., the power level was lowered to 720 MW, which was within the safe region for the test. However, the power continued to decrease and resulted in a precipitous drop in power output to 30 MW, well below the minimum safe level established for the test. Measures 4 Graphite rods inserted into the reactor core to flatten the power distribution Date : February 2011 Page 11

17 to increase the power and avoid a reactor shutdown were taken and as a result, thermal power started increasing and stabilized at 200 MW, and preparations for the test continued. Subsequently, two additional water circulation pumps were activated which led to overcooling and a reduction in steam generation. A variation in the flow rate of feed water and removal of control rod were used to stabilize the core temperature and steam generation, and maintain power to start the test. At this point, the reactor was in an extremely unstable configuration and clearly outside its safe operating envelope. The test was initiated though the closure of the turbine emergency stop valves and the shut-down of water circulating pumps powered from the turbine generator which was being run down. The expected reduction in steam quantity did not occur and instead, steam began to increase. The emergency button was pressed and the emergency and manual control rods started to move down into the core; however, their insertion from the top of the core concentrated reactivity at the bottom. A sharp increase of pressure in the reactor and a failure of the automatic power controller and measuring system and subsequent rupture of a fuel channel resulted in explosions from steam and fuel vapours. One specific thermal-hydraulic feature of the test was the increased initial coolant flow rate through the reactor over the rated level. During the test, the steam quality was at the minimum level and the coolant temperature at the core inlet was below boiling point. These combined effects had a direct impact on the failure of the test. Key Findings of the INSAG-7 Report The first investigation report s conclusion (INSAG-1) focused on operator errors. A subsequent revision, based on new information relevant to the accident (INSAG-7), helped clarify deficiencies in design features, operator s actions and the overall safety framework at the plant. 1. The plant fell well short of the safety standards in effect when it was designed and even incorporated unsafe features. Control rod position led to conflict with the simultaneous requirement to maintain shutdown capability and appropriate value of the power coefficient 5. These design features made the plant vulnerable to human errors. The control room did not have necessary instrumentation to monitor the Operating Reactivity Margin (ORM) 6 parameter. 5 The Power coefficient of reactivity is the ratio between the total reactivity change produce and the change in power causing it. Under normal operation, the power coefficient remained negative. Date : February 2011 Page 12

18 The configuration of control rods controlled the minimum ORM required for safe operation and it was not incorporated into the reactor s protection system. The layout made it difficult to detect unsafe reactor conditions. 2. Insufficient attention to independent safety review and analysis INSAG indicated that the design and operation of Chernobyl Unit 4 as well as other RBMK reactors should have received a great deal more attention through an independent technical review and safety analysis. It was felt that the improved understanding derived from the review, coupled with a regime requiring independent and formal approval for changes to safety related aspects of design and operating procedures, would have gone a long way towards averting the accident altogether. 3. Inadequate and ineffective exchange of important safety information both between operators and between operators and designers There was a widespread view that the operating conditions that triggered the positive scram effect 7 could never occur. Insertion of safety rods worsened the conditions because of the positive power coefficient. It was known to designers that there were potential issues operating the reactor with low power and a positive coefficient but the operating restrictions were not communicated to the operators. Two previous reactor incidents 8 identified the existence of design problems and potential for accidents; however, no thorough analysis was performed to understand their significance and they were ignored. 4. Inadequate understanding by operators of the safety aspects of their plant The developer of the testing programs had a poor understanding of the characteristic and potential behaviour of the reactor under the planned operating conditions. Operators were not aware of the potential consequences of operating under the test conditions. 5. Insufficient respect on the part of the operators for the formal requirements of operational and test procedures There was no formal prohibition to operating or testing the reactor at power levels below 700 MW. The prescribed test procedure required a minimum of 700 MW of power; however, the test was initiated at 200 MW due to inability to restore the power. The procedure was not 6 ORM is expressed in terms of the number of equivalent control rods of nominal worth remaining within the core. Its importance was in the number of control elements in the core adequate for manoeuvring to keep the power distribution balanced throughout. 7 Insertion of positive reactivity by the manual and emergency control rods 8 Leningrad nuclear power plant in 1975 and Ignalina plant in 1983 Date : February 2011 Page 13

19 strictly followed and instead, the test conditions were modified to adjust to the prevailing conditions without any evaluation of the contemplated changes. Poor quality of operating procedures and instructions and their conflicting character resulted in additional load to operation personnel and managers. 6. An insufficient regulatory regime that was unable to counter pressures for production At the time of the accident, USSR did not have a dedicated operating organization and a strong regulatory regime with all the necessary enforcement powers. Areas like design, operation safety analysis, training requirements, safety culture and regulatory enforcement were ineffective. Regulations did not require the plant manager to obtain approvals for the test from the general designer and regulatory body. The basic design of the RBMK reactors was approved despite the lack of conformity to many requirements for nuclear power plants. 7. A general lack of safety culture in nuclear matters, at the national level as well as locally The unnecessary disabling of three components of the reactor protection for an extended period during the test, are indicative of an absence of safety culture. INSAG-7 confirmed the view that safety culture had not been instilled in nuclear power plants in the USSR prior to the Chernobyl accident. Many of the requirements seem to have existed in regulations, but these were not enforced. Many other necessary features of safety culture did not exist at all. Analysis Policy and Commitment INSAG-7 did not indicate that there were any policy statements in place for the Chernobyl plant, but the report does indicate there was a general lack of safety culture at both the operating and regulatory regime. Planning - Poor attention was given to identification of risk and the vulnerability of the design of the reactor led to the incorrect analysis of the operational safety. The existence of the positive scram effect had been understood prior to the accident but design and procedural changes were not implemented. There was a widespread view that the conditions under which the positive scram effect would be important would never occur. However they did appear in almost every detail in the course of the actions leading to the accident. The regulatory regime in the USSR at the time of the incident was ineffective in many important areas, such as analyzing the safety of the design and operation of plants, in requirements for training and in the enforcement of regulations. The basic design of the RBMK reactors was approved despite the lack of conformity to many of the USSR s design requirements for nuclear plants. Date : February 2011 Page 14

20 Lack of planning was evident with respect to the test as it was supposed to be completed by the day shift, but was eventually performed by night shift who had minimal time to prepare for and conduct the test. During the delay (approximately 11 hours) and during the test, three components of the reactor protection system had been purposely disabled. Implementation The organizational structure, roles and responsibilities was not discussed in INSAG-7. It was pointed out that when the reactor power could not be restored to the intended level of 700 MW, the operating staff modified the test procedure on an ad hoc basis and initiated the test at the 200 MW level. This was done without any formal approvals or evaluation of the consequences of not following the original test procedures. Designers were aware of the positive scram effect on the reactor and did not change the design to correct the problem. Also, the related procedural measures which were recommended by the Chief design engineer for RBMK were not included in plant operating instructions. In general operating procedures and instructions were of poor quality and conflicting character which included a deficient system for emergency shutdown, which laid the basis for the positive scram effect and increased reactivity. The data acquisition system was designed to provide guidance to operators on steady state control of power density distribution; however it was incapable of recording data under unstable conditions, and did not provide important data for investigation and learning opportunities. Inadequate operational controls were implemented by the operating staff who mistakenly believed that as long as the lower limit on ORM was satisfied, no matter what the rod configuration was, the demands of safety were met. There was no effective facility in the control room for informing the operators that there was a requirement to maintain a certain control rod configuration in order to maintain the minimum ORM. No procedure for proper rod positioning was applied during the test which led to the destruction of the reactor. Checking and Corrective Actions Previous incidents at the Leningrad and Ignalina plants were not adequately reviewed and the significance of the events was not fully understood by designers, operators or regulators and the information was essentially ignored. No independent technical review or safety analysis was conducted for the Chernobyl Unit 4 or any other of the RBMK reactors. A competent safety analysis would have helped create an environment of attention to safety as a primary objective and would underlie the importance of the effective transfer of the knowledge gained through safety analysis to operators. Date : February 2011 Page 15

21 Management Review Management failed to implement an effective system to assess the initial or continuing suitability of plant design or operating procedures and to make sure the procedures in place were not violated. Also, it failed to assess the effectiveness of the protection systems and the possibility of conflicting design objectives to maintain shutdown capability and appropriate values of the power coefficient which made the plant unduly reliant on sound operator action and increased exposure to the possibility of operator error. Date : February 2011 Page 16

22 PIPER ALPHA 1988 Context The Piper Alpha was an oil platform operated by Occidental Petroleum Ltd, located in a North Sea oil field, 177 km north-east of Aberdeen. The platform started production late Piper Alpha gathered gas and transported oil to shore by pipeline to the oil terminal at Flotta. In 1978, to comply with the gas conservation policy, it started pumping surplus gas to a Manifold Compression Platform, a platform named MCP-01. Piper was linked by 3 gas pipelines to the other platforms and by an oil pipeline to the terminal at Flotta. Claymore started production after Piper in 1977, 22 miles west from Piper and it was also operated by Occidental. Tartan was located 12 miles south-west from Piper and 18 miles from Claymore and was operated by Texaco North Sea UK Ltd. MCP-01 was located 34 miles to the north-west from Piper and was operated by Total Oil Marine. Flotta oil terminal received the oil from Piper, Claymore and Tartan. Figure 3 Pipeline Connections of the Piper Field On July 6, 1988, a catastrophic fire engulfed the Piper platform killing 165 out of 226 on board, and 2 located on a rescue vessel. The fire was initiated by a condensate gas leak in the Date : February 2011 Page 17

23 compression module, which exploded. The damage soon escalated and the fire enveloped the platform, resulting in its structural failure and collapse. The Cullen Inquiry concluded the permit-to-work system and shift turnover communication protocol were not properly followed which led to the incident. In addition, the incident highlighted the deficiencies of design guidelines and practices, the failure to adjust to new conditions and changes, issues with risk management, maintenance and inspection. Synopsis of the event On the morning of July 6, 1988, injection condensate pump A s pressure safety valve (PSV 504) was removed to be recertified. The valve was not located close to the pump; it was 15 ft above the floor, and was not visible from the pump. The condensate line was sealed with a blind flange, but the flange was not fully tightened. An open work permit was created but there was a failure in the permit hand-over system between shifts. As a result, the night shift lead production operator was not aware that the PSV had been removed. When the second condensate pump B tripped and could not be restarted, the night shift lead production operator and maintenance lead hand assumed it would be safe to restart pump A and the pump was switched on. Pressurized gas condensate flowed into the system and a leak initiated at the less than leak-tight blind flange location. Since the flange was located in the module above the pump, it was not visible to the workers. A high pressure gas leak noise was heard in several areas and was followed by high level gas alarms before the gas cloud found an ignition point and the first explosion occurred. Figure 4 Piper Alpha platform: simplified east elevation Date : February 2011 Page 18

24 The explosion blew through the firewall panels C&D, which were not designed to withstand blasts, and destroyed the control room located close to module B. The platform emergency shutdown was pressed but not the other 3 buttons for the gas pipelines connected to the other platforms. A projectile from the blast ruptured a condensate line creating a fire. With the control room destroyed, no communication or order to evacuate was issued. The fire prevented access to the single lifeboat location. The automatic fire-fighting system, driven by both diesel and electric pumps was under manual control due to Piper Alpha procedures when divers were in the water. The majority of personnel who were not on the night shift gathered in the D deck galley of the fireproof accommodation block and waited for further instructions. The intensification of the fire impaired the strength of some pipes; the Tartan platform gas riser burst and a second major explosion engulfed the platform. Claymore platform stopped pumping after the second explosion while Tartan continued pumping because managers either had no authority or had not received communication from the Occidental control room to shut in production. The Tharos fire-fighting vessel began to pull back from the platform due to the intensity of the fire that started to affect its structure when the Claymore gas riser ruptured. This rupture contributed to the accelerating deterioration of both the platform and the Module (D) where the fireproofed accommodation block was located. The entire platform, including the Module (D), slipped into the sea. Key Findings The platform was originally designed to send oil to shore. In order to accommodate new production and regulatory requirements, modifications were made without a comprehensive assessment of new operating conditions. The platform design, including the absence of blast walls, unplanned platform network growth and non observance of procedures all contributed to the disaster. 1. Poor design and layout The design of the platform was an integral part of the event s sequence. Flaws included the layout of the units, the location of the control room close to the production modules, the location of the radio room, the pipe distribution, running cables through modules, fireproofing, control mechanisms, spark arrestors, the deluge system and the lack of redundancy for loss of electrical power, equipment, and emergency and communication systems. The layout of the Piper Alpha platform was faulty and generally, did not take into account safety in the design philosophy. Date : February 2011 Page 19

25 Firewalls were designed to resist fire and not blast pressure and as a result, there was insufficient protection of critical equipment against blast projectiles and poor fire insulation. 2. Failures to comply with Occidental's Permit to Work (PTW) procedures There was a failure to follow the permit to work system which led to unsafe practices such as the re-commissioning of equipment still under maintenance. The pressure safety valve was not put back in place when the work could not be completed at the end of the shift. The crew did not follow procedures when they completed the fitting of the blind flange. The flange was not properly adjusted and the lead operator in charge did not ensure the inspections were completed as required in the procedures. In addition, the work situation and the status of the job was poorly communicated at the shift handover. 3. Inadequate training and competence The decision to promote personnel to Offshore Installation Manager (OIM) positions without sufficient experience and knowledge of the platform was evident during the emergency when the OIM was incapable of providing the proper orders. Poor training in emergency situations and poor assessment of the risk associated with major hazards contributed to a number of deaths. The contractor supervisor had not received any formal training in the PTW system. 4. Inadequate monitoring Safety was mainly managed through the implementation of the permit-to-work system and the absence of feedback was taken as an indication that all was going well. There was no systematic monitoring or verification of the PTW system. The records of operator s logs were used to monitor the platform activities however maintenance work was not registered in logs. Management failed to adequately review and monitor safety procedures. 5. Inadequate written procedures The Piper Alpha procedures required that the firefighting system be left in manual mode while divers were in the water despite an earlier audit recommendation that the procedure Date : February 2011 Page 20

26 be changed. The procedure for other platforms indicated that the system be put in manual mode only when the divers were in proximity to the platform suction piping. The PTW procedures did not address lock-out or tagging of equipment for maintenance work. 6. Inadequate accident investigation Management failed to investigate all equipment failures. Superficial responses were adopted when safety issues arose. Management failed to apply the lessons learned from the investigations into previous accidents. 7. Lack of emergency preparedness The design of the platform network (Piper Alpha, Claymore, Tartan, and MCP-01) eventually created a physically interdependent system which was conceived without the development of integrated emergency preparedness and response procedures necessary in case of an emergency. The platform personnel and management were not prepared for a major emergency even though the safety policies and procedures were in place. Issues included failure to provide the proper training, lack of emergency exercises and no proper planning of alternative evacuation routes. During the event, about 100 men moved to the fireproofed accommodation block to await further instructions that were never received. 8. Lack of formal hazard analysis Management ignored previous audits that warned that the platform could not survive prolonged exposure to high-intensity fires with grave consequences for the platform and its personnel. Management assumed, base on qualitative opinions rather than a formal analysis, that the probability of occurrence of such an event was low. 9. Lack of management of change Over time, new platforms were introduced to accommodate new needs. The physical interdependency between the four platforms had grown without preplanning and emergency shutdown systems were not adapted to match the new design. The decision to continue production in Phase 1 mode with high-pressure levels during maintenance work likely led to equipment strain. Also, personnel did not have sufficient work experience in this operation mode. Date : February 2011 Page 21

Shell s Health, Safety and Environment (HSE) management system (see Figure 11-1) provides the framework for managing all aspects of the development.

Shell s Health, Safety and Environment (HSE) management system (see Figure 11-1) provides the framework for managing all aspects of the development. Section 11.1 APPLICATION FOR APPROVAL OF THE DEVELOPMENT PLAN FOR NIGLINTGAK FIELD PROJECT DESCRIPTION INTRODUCTION 11.1.1 HSE MANAGEMENT SYSTEM Shell s Health, Safety and Environment (HSE) management

More information

Lessons from Offshore Accidents

Lessons from Offshore Accidents Lessons from Offshore Accidents Tekna Prosessikkerhet, Bergen 2007-11-27 Jon Erik Pettersvold/DNV Energy With extracts from Petrobras Presentation June 2001 Source: www.petrobras.com.br Lessons from Offshore

More information

Deepwater Horizon Accident Investigation Report

Deepwater Horizon Accident Investigation Report Deepwater Horizon Accident Investigation Report September 8, 2010 This is the report of an internal BP incident investigation team. The report does not represent the views of any individual or entity other

More information

On-Site Risk Management Audit Checklist for Program Level 3 Process

On-Site Risk Management Audit Checklist for Program Level 3 Process On-Site Risk Management Audit Checklist for Program Level 3 Process Auditor name: Date: I. Facility Information: Facility name: Facility location: County: Contact name: RMP Facility I.D. Phone Number:

More information

TECHNICAL INFORMATION

TECHNICAL INFORMATION Page: 1/6 This checklist recognizes the major accident hazards found by experience of previous HAZID studies. It is not intended to be totally exhaustive and feedback from users should be incorporated

More information

1 What is the purpose of this document?

1 What is the purpose of this document? Executive Summary Comparing the Oil and Gas Drilling Regulatory Regimes of the, the, the U.K,, and 1 What is the purpose of this document? The National Energy Board (NEB) regulates offshore oil and gas

More information

All Oil and Gas Companies under the Jurisdiction of the National Energy Board (the Board or NEB) and All Interested Parties

All Oil and Gas Companies under the Jurisdiction of the National Energy Board (the Board or NEB) and All Interested Parties File 172-A000-73 24 April 2002 To: All Oil and Gas Companies under the Jurisdiction of the National Energy Board (the Board or NEB) and All Interested Parties SECURITY AND EMERGENCY PREPAREDNESS AND RESPONSE

More information

Safety Management System Manual Guidebook

Safety Management System Manual Guidebook Safety Management System Manual Guidebook Developed by: Commandant (G-MSO-2) U.S. Coast Guard Table of Contents Chapter 1: Introduction 1 Chapter 2: Safety and Environmental Protection Policy 3 Chapter

More information

Nuclear Power Plant Electrical Power Supply System Requirements

Nuclear Power Plant Electrical Power Supply System Requirements 1 Nuclear Power Plant Electrical Power Supply System Requirements Željko Jurković, Krško NPP, zeljko.jurkovic@nek.si Abstract Various regulations and standards require from electrical power system of the

More information

OFFSHORE OIL & GAS SECTOR STRATEGY 2014 TO 2017

OFFSHORE OIL & GAS SECTOR STRATEGY 2014 TO 2017 STRATEGIC CONTEXT OFFSHORE OIL & GAS SECTOR STRATEGY 2014 TO 2017 1 This strategy sets out how HSE s Energy Division will regulate health and safety of the offshore oil and gas industry operating on the

More information

Case Study of Emergency Disconnect Sequence in the Gulf of Mexico

Case Study of Emergency Disconnect Sequence in the Gulf of Mexico Case Study of Emergency Disconnect Sequence in the Gulf of Mexico Trent Fleece Subsea BOP Operations Team Lead May 8, 2015 Case Study of Emergency Disconnect Sequence in Gulf of Mexico Industry Standards

More information

Preventing Overheated Boiler Incidents

Preventing Overheated Boiler Incidents Preventing Overheated Boiler Incidents PSE&G Appliance Service October 2012 Runaway Boiler Explosion Review Items Hazard Background Past Incidents PSE&G Emergency Response Future Process Improvements What

More information

MAJOR PLANNING CONSIDERATIONS CHECKLIST

MAJOR PLANNING CONSIDERATIONS CHECKLIST MAJOR PLANNING CONSIDERATIONS CHECKLIST The following checklist is provided as a guide to assure that relevant considerations are identified in the emergency management planning process. Use the blank

More information

Learning from the Piper Alpha Accident: A Postmortem Analysis of Technical and Organizational Factors

Learning from the Piper Alpha Accident: A Postmortem Analysis of Technical and Organizational Factors RkkAnalysk, Vol. 13, No. 2, 1993 Learning from the Piper Alpha Accident: A Postmortem Analysis of Technical and Organizational Factors M. Elisabeth PatC-Cornell (Received September 18, 1992; revised October

More information

Jefferson Parish Department of Water Emergency Plan

Jefferson Parish Department of Water Emergency Plan 1. Overview Jefferson Parish Department of Water Emergency Plan 1.1. Purpose The purpose of this document is to establish procedures for the Department of Water during natural disasters or terrorist acts.

More information

Belgian Stress tests specifications Applicable to all nuclear plants, excluding power reactors 22 June 2011

Belgian Stress tests specifications Applicable to all nuclear plants, excluding power reactors 22 June 2011 Belgian Stress tests specifications Applicable to all nuclear plants, excluding power reactors 22 June 2011 Introduction Considering the accident at the Fukushima nuclear power plant in Japan, the European

More information

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents Federal Wage System Job Grading Standards for Electric Power Controlling, 5407 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 SPECIAL ADDITIONAL RESPONSIBILITIES...

More information

Oil and Coolant Circulating Heating System. Model - OCSM

Oil and Coolant Circulating Heating System. Model - OCSM Oil and Coolant Circulating Heating System Model - OCSM Installation & Operation Manual 216280-000 REV 2 Identifying Your System The HOTSTART heating system is designed to heat fluids for use in marine

More information

The Piping System Model a New Life Cycle Document. Elements of the Piping System Model

The Piping System Model a New Life Cycle Document. Elements of the Piping System Model Piping System Model as a Life Cycle Document White Paper Introduction When designing piping systems, a variety of documents are created providing the details necessary to design, purchase, build, and test

More information

ITF CRUISE SHIP SAFETY POLICY

ITF CRUISE SHIP SAFETY POLICY ITF CRUISE SHIP SAFETY POLICY INTRODUCTION The ITF Cruise Ship Safety Policy reflects the additional measures required as a result of the great number of passengers and crew carried and builds upon the

More information

(2) Various fire sections enclosed by various classes of fire divisions; (3) Arrangement of fire detectors and manual fire alarm stations;

(2) Various fire sections enclosed by various classes of fire divisions; (3) Arrangement of fire detectors and manual fire alarm stations; (1979) (Rev.1 1990) (Rev.2 1996) (Rev.3 Jan 2012) Safety features.1 Fire protection and extinction.1.1 General Fire protection arrangements and fire extinguishing systems are to be in accordance with the

More information

Safety Challenges in the Arctic

Safety Challenges in the Arctic Safety Challenges in the Arctic International Conference on Integrated Operations in the Petroleum Industry Trondheim, 25.09.13 Børre Johan Paaske, DNV GL Agenda Defining the Arctic Safety and environmental

More information

APPENDIX O. Spill Prevention and Emergency Response Plan. G3 Terminal Vancouver Port Metro Vancouver Project Permit Application APPENDIX O

APPENDIX O. Spill Prevention and Emergency Response Plan. G3 Terminal Vancouver Port Metro Vancouver Project Permit Application APPENDIX O APPENDIX O Spill Prevention and Emergency Response Plan APPENDIX O G3 Terminal Vancouver Port Metro Vancouver Project Permit Application G3 TERMINAL VANCOUVER: PORT METRO VANCOUVER SPILL PREVENTION AND

More information

Risk Engineering Guideline

Risk Engineering Guideline www.hdi.global HDI Risk Consulting Risk Engineering Guideline Impairment of fire protection systems Basic protection systems should not be impaired without adequate replace compensation with provisions.

More information

PTP-Global. Alarm Management An Introduction

PTP-Global. Alarm Management An Introduction Alarm Management An Introduction Presentation Contents 1. The Old and the New 2. Importance of Alarm Management & Historical Context 3. Guides, Standards and Regulations 4. Benefits & Design of Alarm Management

More information

Disaster Ready. By: Katie Tucker, Sales Representative, Rolyn Companies, Inc

Disaster Ready. By: Katie Tucker, Sales Representative, Rolyn Companies, Inc By: Katie Tucker, Sales Representative, Rolyn Companies, Inc Are you and your facility disaster ready? As reported by the Red Cross, as many as 40 percent of small businesses do not reopen after a major

More information

Boiler & Pressure Vessel Inspection discrepancies and failures

Boiler & Pressure Vessel Inspection discrepancies and failures Boiler & Pressure Vessel Inspection discrepancies and failures Water Heaters / Pressure Vessels Pressure Vessels are inspected once every three years. This requires a test of A: safety relief devices B:

More information

REQUIREMENTS RESPECTING THE SECURITY OF OFFSHORE FACILITIES

REQUIREMENTS RESPECTING THE SECURITY OF OFFSHORE FACILITIES REQUIREMENTS RESPECTING THE SECURITY OF OFFSHORE FACILITIES Definitions 1. In these requirements: C-NLOPB means the Canada-Newfoundland and Labrador Offshore Petroleum Board; Chief Safety Officer means

More information

SECTION A... 3 SECTION B... 7

SECTION A... 3 SECTION B... 7 BRITISH COLUMBIA SAFETY AUTHORITY Manual for Owners and Operators of Special Status Plants Risk Assessed and General Supervision Date: March 12, 2012 Controlled Document: MAN -4000-03 I TABLE OF CONTENTS

More information

FACILITY FIRE PREVENTION AND EMERGENCY PREPAREDNESS INSPECTION CHECKLIST

FACILITY FIRE PREVENTION AND EMERGENCY PREPAREDNESS INSPECTION CHECKLIST FACILITY FIRE PREVENTION AND EMERGENCY PREPAREDNESS INSPECTION CHECKLIST Date of Inspection: Conducted by: Location: Reviewed by: Date of Review: Comments or additional corrective action taken as a result

More information

Routine and Emergency Boiler Operation

Routine and Emergency Boiler Operation Routine and Emergency Boiler Operation Learning Outcome When you complete this module you will be able to: Describe the routine safe and efficient operation of a packaged boiler. Learning Objectives Here

More information

Safety Requirements Specification Guideline

Safety Requirements Specification Guideline Safety Requirements Specification Comments on this report are gratefully received by Johan Hedberg at SP Swedish National Testing and Research Institute mailto:johan.hedberg@sp.se -1- Summary Safety Requirement

More information

Emergency Preparedness Guidelines

Emergency Preparedness Guidelines DM-PH&SD-P7-TG6 رقم النموذج : I. Introduction This Guideline on supports the national platform for disaster risk reduction. It specifies requirements to enable both the public and private sector to develop

More information

EXHIBIT A SCOPE OF WORK

EXHIBIT A SCOPE OF WORK EXHIBIT A SCOPE OF WORK 1. (Contractor) shall provide fire alarm system maintenance/repair/testing services as described herein to the California Department of Veterans Affairs (hereinafter CDVA, CalVet,

More information

Fuel Treatment and Conditioning Systems

Fuel Treatment and Conditioning Systems RULES FOR CLASSIFICATION OF Ships PART 6 CHAPTER 14 NEWBUILDINGS SPECIAL EQUIPMENT AND SYSTEMS ADDITIONAL CLASS Fuel Treatment and Conditioning Systems JULY 2006 This chapter has been amended since the

More information

Bradlee Boilers Ltd. Instruction Manual for starting up Bradlee Hire Boiler from Cold

Bradlee Boilers Ltd. Instruction Manual for starting up Bradlee Hire Boiler from Cold Bradlee Boilers Ltd Instruction Manual for starting up Bradlee Hire Boiler from Cold To be read in conjunction with Bradlee Boiler guide to Commissioning Boilers Document Ref: HM001 1. Ensure that all

More information

MSC/Circ.1002 26 June 2001 GUIDELINES ON ALTERNATIVE DESIGN AND ARRANGEMENTS FOR FIRE SAFETY

MSC/Circ.1002 26 June 2001 GUIDELINES ON ALTERNATIVE DESIGN AND ARRANGEMENTS FOR FIRE SAFETY INTERNATIONAL MARITIME ORGANIZATION 4 ALBERT EMBANKMENT LONDON SE1 7SR Telephone: 020 7735 7611 Fax: 020 7587 3210 Telex: 23588 IMOLDN G IMO E Ref. MSC/Circ.1002 26 June 2001 GUIDELINES ON ALTERNATIVE

More information

Guidance on safety during abandon ship drills and fire drills on board ships *)

Guidance on safety during abandon ship drills and fire drills on board ships *) Guidance on safety during abandon ship drills and fire drills on board ships *) 1 GENERAL 1.1 Accidents during abandon ship drills and fire drills In recent years, the shipping industry has experienced

More information

Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1

Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1 Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1 Nuclear Power in Pakistan Nuclear Power Plants Capacity (MWe) Year of Commissioning In

More information

Liberty Mutual Insurance RISK ENGINEERING PROCEDURE. REP 07 Incident Planning For external use

Liberty Mutual Insurance RISK ENGINEERING PROCEDURE. REP 07 Incident Planning For external use Liberty Mutual Insurance RISK ENGINEERING PROCEDURE REP 07 Incident Planning For external use Risk Engineering Procedure Incident Planning CONTENTS Page PURPOSE... 3 BACKGROUND... 4 INCIDENT PLANNING PREPARATION...

More information

Risk Assessment / Risk Management Protocol

Risk Assessment / Risk Management Protocol 1 Canadian Pacific Railway Risk Assessment / Risk Management Protocol Overview / Outline At Canadian Pacific Railway, we conduct risk assessments of our activities and operations for a number of different

More information

Operating Performance: Accident Management: Severe Accident Management Programs for Nuclear Reactors REGDOC-2.3.2

Operating Performance: Accident Management: Severe Accident Management Programs for Nuclear Reactors REGDOC-2.3.2 Operating Performance: Accident Management: Severe Accident Management Programs for Nuclear Reactors REGDOC-2.3.2 September 2013 Accident Management: Severe Accident Regulatory Document REGDOC-2.3.2 Canadian

More information

HEALTH, SAFETY AND ENVIRONMENT HANDBOOK HSE

HEALTH, SAFETY AND ENVIRONMENT HANDBOOK HSE HEALTH, SAFETY AND ENVIRONMENT HANDBOOK HSE CNOOC Limited 1 Message from CEO Dear Colleagues, CNOOC Limited is the largest producer of offshore oil & gas in China and is one of the largest oil & gas exploration

More information

Georgia College Emergency Notification System Activation Protocols

Georgia College Emergency Notification System Activation Protocols Georgia College Emergency Notification System Activation Protocols Georgia College & State University Office of Emergency Preparedness and Occupational Safety December 2013 I. Introduction and Purpose

More information

Drilling for Deepwater Data: A Forensic Analysis of the Gulf of Mexico Deepwater Horizon Disaster

Drilling for Deepwater Data: A Forensic Analysis of the Gulf of Mexico Deepwater Horizon Disaster Paper SAS1865-2015 Drilling for Deepwater Data: A Forensic Analysis of the Gulf of Mexico Deepwater Horizon Disaster ABSTRACT Steve Walker and Jim Duarte, SAS Institute Inc., Cary, NC During the cementing

More information

The SPE Foundation through member donations and a contribution from Offshore Europe

The SPE Foundation through member donations and a contribution from Offshore Europe Primary funding is provided by The SPE Foundation through member donations and a contribution from Offshore Europe The Society is grateful to those companies that allow their professionals to serve as

More information

IAEA INTERNATIONAL FACT FINDING EXPERT MISSION OF THE NUCLEAR ACCIDENT FOLLOWING THE GREAT EAST JAPAN EARTHQUAKE AND TSUNAMI

IAEA INTERNATIONAL FACT FINDING EXPERT MISSION OF THE NUCLEAR ACCIDENT FOLLOWING THE GREAT EAST JAPAN EARTHQUAKE AND TSUNAMI IAEA INTERNATIONAL FACT FINDING EXPERT MISSION OF THE NUCLEAR ACCIDENT FOLLOWING THE GREAT EAST JAPAN EARTHQUAKE AND TSUNAMI Tokyo, Fukushima Dai-ichi NPP, Fukushima Dai-ni NPP and Tokai NPP, Japan 24

More information

Transformer Deluge Systems

Transformer Deluge Systems Transformer Deluge Systems How Do Transformer Fires Ignite? Common causes of transformer failure: Weather-related events such as lightning Short circuits in electrical equipment The most common cause is

More information

Simple Damage Control Aboard

Simple Damage Control Aboard Simple Damage Control Aboard By Marc A. Barredo Damage control aboard ship involves any prudent action that will; prevent or reduce expected damage to the ship, stabilize the situation caused by the damage,

More information

OVERLAND PIPELINE OPTIONS

OVERLAND PIPELINE OPTIONS Working Document of the NPC Study: Arctic Potential: Realizing the Promise of U.S. Arctic Oil and Gas Resources Made Available March 27, 2015 Paper #7-9 OVERLAND PIPELINE OPTIONS Prepared for the Technology

More information

WASTE Application Form - Dublin Waste to Energy SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE

WASTE Application Form - Dublin Waste to Energy SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE Describe the existing or proposed measures, including emergency procedures, to minimise the impact on the environment of an accidental emission or spillage.

More information

Oil Spill Emergency Response. Oil Spill Emergency

Oil Spill Emergency Response. Oil Spill Emergency Oil Spill Emergency Response 1 Oil Spill Emergency Response We work to prevent incidents that may result in spills of hazardous substances. This means making sure our facilities are well designed, safely

More information

Emergency planning at a major hazard facility

Emergency planning at a major hazard facility Guidance Note Emergency planning Advice for operators of major hazard facilities on developing an emergency plan. April 2011 1. Introduction 1 1.1 Features of a successful emergency plan 1 1.2 Key concepts

More information

STATEMENT OF DOUG SLITOR, ACTING CHIEF OFFICE OF OFFSHORE REGULATORY PROGRAMS BUREAU OF OCEAN ENERGY MANAGEMENT, REGULATION, AND ENFORCEMENT BEFORE THE COMMITTEE ON EDUCATION AND LABOR UNITED STATES HOUSE

More information

Isle of Man Regulations implementing the STCW Manila Amendments

Isle of Man Regulations implementing the STCW Manila Amendments MANX SHIPPING NOTICE DEPARTMENT OF ECONOMIC DEVELOPMENT MSN 050 Issued August 2014 Isle of Man Regulations implementing the STCW Manila Amendments This MSN provides information on the certification and

More information

Cyber Security Design Methodology for Nuclear Power Control & Protection Systems. By Majed Al Breiki Senior Instrumentation & Control Manager (ENEC)

Cyber Security Design Methodology for Nuclear Power Control & Protection Systems. By Majed Al Breiki Senior Instrumentation & Control Manager (ENEC) Cyber Security Design Methodology for Nuclear Power Control & Protection Systems By Majed Al Breiki Senior Instrumentation & Control Manager (ENEC) 1. INTRODUCTION In today s world, cyber security is one

More information

Alarm Management What, Why, Who and How?

Alarm Management What, Why, Who and How? Alarm Management What, Why, Who and How? Executive Summary The introduction of the DCS has made it possible to create alarms more easily and at a lower cost. Although software alarms are convenient, the

More information

DANISH ENERGY AGENCY S GUIDELINES ON SAFETY- AND HEALTH RELATED CONDITIONS ON OFFSHORE INSTALLATIIONS, ETC. HEALTH & SAFETY CASES

DANISH ENERGY AGENCY S GUIDELINES ON SAFETY- AND HEALTH RELATED CONDITIONS ON OFFSHORE INSTALLATIIONS, ETC. HEALTH & SAFETY CASES DANISH ENERGY AGENCY S GUIDELINES ON SAFETY- AND HEALTH RELATED CONDITIONS ON OFFSHORE INSTALLATIIONS, ETC. HEALTH & SAFETY CASES REV. 0 December 2012 TABLE OF CONTENT TABLE OF CONTENT... 2 DOCUMENT CONTROL...

More information

Offshore Structures. Offshore Drilling Equipment

Offshore Structures. Offshore Drilling Equipment Offshore Structures Offshore Drilling Equipment The drill string is lowered through a conduit (riser). The drill string consists of a drill bit, drill collar and drill pipe. Drill pipe sections are added

More information

IMPORTANT SAFETY NOTICE

IMPORTANT SAFETY NOTICE IMPORTANT SAFETY NOTICE To: Our Valued Customers User safety is a major focus in the design of our products. Following the precautions outlined in this manual will minimize your risk of injury. ITT Goulds

More information

Government Degree on the Safety of Nuclear Power Plants 717/2013

Government Degree on the Safety of Nuclear Power Plants 717/2013 Translation from Finnish. Legally binding only in Finnish and Swedish. Ministry of Employment and the Economy, Finland Government Degree on the Safety of Nuclear Power Plants 717/2013 Chapter 1 Scope and

More information

Report in respect of. Service Disruption on 9 April 2012

Report in respect of. Service Disruption on 9 April 2012 Report in respect of Service Disruption on 9 April 2012 1. Introduction On 9 April 2012, a power outage occurred in the Shatin Switching Centre, one of three switching centres deployed by SmarTone Mobile

More information

GUIDELINES FOR THE CONDUCT OF OIL, GAS & PETROCHEMICAL RISK ENGINEERING SURVEYS

GUIDELINES FOR THE CONDUCT OF OIL, GAS & PETROCHEMICAL RISK ENGINEERING SURVEYS GUIDELINES FOR THE CONDUCT OF OIL, GAS & PETROCHEMICAL RISK ENGINEERING SURVEYS Developed by: Ron Jarvis Andy Goddard Swiss Re, London Talbot Syndicate, London Contributions made by the London market engineers

More information

How To Clean Up A Reactor Water Cleanup

How To Clean Up A Reactor Water Cleanup General Electric Systems Technology Manual Chapter 2.8 Reactor Water Cleanup System TABLE OF CONTENTS 2.8 REACTOR CLEANUP SYSTEM... 1 2.8.1 Introduction... 2 2.8.2 System Description... 2 2.8.3 Component

More information

Reliability Modeling Software Defined

Reliability Modeling Software Defined Reliability Modeling Software Defined Using Titan Reliability Modeling Software May 30, 2014 Prepared by: The Fidelis Group 122 West Way, Suite 300 Lake Jackson, TX 77566 Fidelis Group, LLC All Rights

More information

Industrial Process Pump Safety Manual IMPORTANT SAFETY NOTICE

Industrial Process Pump Safety Manual IMPORTANT SAFETY NOTICE Industrial Process Pump Safety Manual IMPORTANT SAFETY NOTICE To: Our Valued Customers User safety is a major focus in the design of our products. Following the precautions outlined in this manual will

More information

May 23, 2011 Tokyo Electric Power Company

May 23, 2011 Tokyo Electric Power Company Analysis and evaluation of the operation record and accident record of Fukushima Daiichi Nuclear Power Station at the time of Tohoku-Chihou-Taiheiyou-Oki-Earthquake (summary) May 23, 2011 Tokyo Electric

More information

Competency Framework for Marine Engineer Class 6. Competency Framework for Marine Engineer Class 6

Competency Framework for Marine Engineer Class 6. Competency Framework for Marine Engineer Class 6 Table of Contents (MEC 6)... 1 Function: Operate Vessel Machinery and Systems... 1 Diesel engines.... 1 Operational procedures.... 3 Operate and monitor a vessel s engines and auxiliary equipment.... 4

More information

Belgian Stress tests specifications Applicable to power reactors 17 May 2011

Belgian Stress tests specifications Applicable to power reactors 17 May 2011 Belgian Stress tests specifications Applicable to power reactors 17 May 2011 Introduction Considering the accident at the Fukushima nuclear power plant in Japan, the European Council of March 24 th and

More information

DET NORSKE VERITAS TM

DET NORSKE VERITAS TM DET NORSKE VERITAS TM APPENDIX B HAZID REPORT NO./DNV REG NO.: 2013-4091 / 17TLT29-5 REV 1, 11.06.2013 DET NORSKE VERITAS Table of Contents Page 1 BACKGROUND AND SCOPE OF WORK... 2 2 METHODOLOGY... 4 3

More information

DISASTER RECOVERY PLANNING FOR CITY COMPUTER FACILITIES

DISASTER RECOVERY PLANNING FOR CITY COMPUTER FACILITIES APPENDIX 1 DISASTER RECOVERY PLANNING FOR CITY COMPUTER FACILITIES March 2008 Auditor General s Office Jeffrey Griffiths, C.A., C.F.E. Auditor General City of Toronto TABLE OF CONTENTS EXECUTIVE SUMMARY...1

More information

ANNUAL OFFSHORE STATISTICS & REGULATORY ACTIVITY REPORT 2013/2014

ANNUAL OFFSHORE STATISTICS & REGULATORY ACTIVITY REPORT 2013/2014 ANNUAL OFFSHORE STATISTICS & REGULATORY ACTIVITY REPORT 2013/2014 Date of release: December 2014 1 Preface HSE is responsible for regulating health & safety matters offshore. The Health and Safety at Work

More information

Accident Report. Injury Pacific Way. 26 November 2005 Class A

Accident Report. Injury Pacific Way. 26 November 2005 Class A Accident Report Injury Pacific Way 26 November 2005 Class A SUMMARY Pacific Way Injury A crewmember suffered an injury to his wrist when the handle connected to the manually powered windlass that he was

More information

How To Handle An Emergency

How To Handle An Emergency Company Name Address Telephone Contact Name Title Last Revision Date Policy and Organizational Statements Identify the goals and objectives for the emergency response plan. Define what your emergency response

More information

National Competency Based Skill Training Refrigeration and Air-conditioning Mechanic Logbook

National Competency Based Skill Training Refrigeration and Air-conditioning Mechanic Logbook National Competency Based Skill Training Refrigeration and Air-conditioning Mechanic Logbook Trainee:... Training Provider:... Year:... Trainee Contact no:... Competency Based Skill Training Logbook Introduction

More information

ISLE OF MAN FIRE & RESCUE SERVICE FIRE PRECAUTIONS LOGBOOK. Website www.iomfire.com

ISLE OF MAN FIRE & RESCUE SERVICE FIRE PRECAUTIONS LOGBOOK. Website www.iomfire.com ISLE OF MAN FIRE & RESCUE SERVICE FIRE PRECAUTIONS LOGBOOK Website www.iomfire.com ADDRESS OF PREMISES FIRE CERTIFICATE No. (where applicable).. LOCATION OF LOG BOOK. CONTENTS OF LOG BOOK Useful telephone

More information

Managing risks for lay-up of OSVs and Rigs

Managing risks for lay-up of OSVs and Rigs MARITIME ADVISORY Managing risks for lay-up of OSVs and Rigs 2015.10 1 DNV GL 2013 2014.03.05 SAFER, SMARTER, GREENER Lay-ups are cyclical, just like the industry 2 Managing risks of lay-up of OSVs and

More information

7.1 General 5 7.2 Events resulting in pressure increase 5

7.1 General 5 7.2 Events resulting in pressure increase 5 GUIDE YVL 2.4 / 24 Ma r ch 2006 Primary and secondary circuit pressure control at a nuclear power plant 1 Ge n e r a l 3 2 General design requirements 3 3 Pressure regulation 4 4 Overpressure protection

More information

Boiling Water Reactor Systems

Boiling Water Reactor Systems Boiling Water (BWR) s This chapter will discuss the purposes of some of the major systems and components associated with a boiling water reactor (BWR) in the generation of electrical power. USNRC Technical

More information

The Application of Rope Access Methods in the Construction, Inspection, Repair and Maintenance of Wind Turbines

The Application of Rope Access Methods in the Construction, Inspection, Repair and Maintenance of Wind Turbines The Application of Rope Access Methods in the Construction, Inspection, Repair and Maintenance of Wind Turbines Introduction IRATA International s rope access system is a safe method of working at height,

More information

INSPECTION AND TESTING OF EMERGENCY GENERATORS

INSPECTION AND TESTING OF EMERGENCY GENERATORS INSPECTION AND TESTING OF EMERGENCY GENERATORS Certification requirements NFPA 101(00), Sec. 7.9.2.3 requires that emergency generators be installed, tested and maintained in accordance with NFPA 110,

More information

The Orange County Farmers Museum Emergency Preparedness Plan

The Orange County Farmers Museum Emergency Preparedness Plan The Orange County Farmers Museum Emergency Preparedness Plan TABLE OF CONTENTS Section Page Introduction. 2 1. Coordination with an Emergency Response Agency. 2 2. Policies of the Board 2 3. Procedures

More information

Abnormal Operating Conditions Emergency Plans and Public Awareness Plans for Natural Gas Systems

Abnormal Operating Conditions Emergency Plans and Public Awareness Plans for Natural Gas Systems Abnormal Operating Conditions Emergency Plans and Public Awareness Plans for Natural Gas Systems Contact Information John West Transportation Specialist U.S. Department of Transportation PHMSA Office of

More information

( 1 ) Overview of Safety Measures ( 2 ) Overview of Measures for Attaining Greater Safety and Reliability

( 1 ) Overview of Safety Measures ( 2 ) Overview of Measures for Attaining Greater Safety and Reliability Contents 1 Effort for New Regulatory Requirements ( 1 ) Overview of a Gist of New Regulatory Requirements in Nuclear Regulation Authority ( 2 ) Major Requirements of a Gist of New Regulatory Requirements

More information

Flood Preparedness Checklist

Flood Preparedness Checklist Appendix A: Preparedness Checklists 1 Flood Preparedness Checklist The following checklist will help you prepare for how a flood could impact your business and your business continuity and disaster recovery

More information

UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, DC 20555-0001. June 16, 2011

UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, DC 20555-0001. June 16, 2011 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, DC 20555-0001 June 16, 2011 NRC INFORMATION NOTICE 2011-12: REACTOR TRIPS RESULTING FROM WATER INTRUSION INTO

More information

Federal Wage System Job Grading Standards for Air Conditioning Equipment Operating, 5415. Table of Contents

Federal Wage System Job Grading Standards for Air Conditioning Equipment Operating, 5415. Table of Contents Federal Wage System Job Grading Standards for Air Conditioning Equipment Operating, 5415 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 HELPER AND INTERMEDIATE JOBS...

More information

Call reduction guidance for false alarm/ unwanted fire signals

Call reduction guidance for false alarm/ unwanted fire signals Call reduction guidance for false alarm/ unwanted fire signals Acting to Protect & Save Introduction Devon & Somerset Fire & Rescue Service attend in excess of 20,000 incidents each year, approximately

More information

OCCUPATIONAL SAFETY AND HEALTH PROGRAM

OCCUPATIONAL SAFETY AND HEALTH PROGRAM OCCUPATIONAL SAFETY AND HEALTH PROGRAM As stated in NFPA 1500, Standard on Fire Department Occupational Safety and Health Program, "Firefighting has been recognized as the most hazardous occupation in

More information

CHAGUARAMAS TERMINALS LTD.

CHAGUARAMAS TERMINALS LTD. POLICY MANUAL All rights reserved to CrewsInn Limited. No part of this document may be reproduced in any form or by any means, without permission in writing from the company CHAGUARAMAS TERMINALS LTD.

More information

EMERGENCY MANAGEMENT PLANNING CRITERIA FOR AMBULATORY SURGICAL CENTERS

EMERGENCY MANAGEMENT PLANNING CRITERIA FOR AMBULATORY SURGICAL CENTERS EMERGENCY MANAGEMENT PLANNING CRITERIA FOR AMBULATORY SURGICAL CENTERS The following criteria are to be used when developing Comprehensive Emergency Management Plans (CEMP) for all ambulatory surgical

More information

Reconstruction Support after the Great East Japan Earthquake

Reconstruction Support after the Great East Japan Earthquake Advanced Maintenance, Energy Saving, Environment Reconstruction Support after the Great East Japan Earthquake Kan Kumagai Keyword Earthquake disaster reconstruction, Temporary restoration, Reuse, Diagnosis

More information

CONFINED SPACE ENTRY WORK STANDARD

CONFINED SPACE ENTRY WORK STANDARD CONFINED SPACE ENTRY WORK STANDARD CONFINED SPACE ENTRY WORK STANDARD Copyright 2007 All rights reserved. Reproduction of this document in whole or in part by any means is prohibited, unless authorized

More information

ANNEX 5 RESOLUTION MEPC.127(53) Adopted on 22 July 2005 GUIDELINES FOR BALLAST WATER MANAGEMENT AND DEVELOPMENT OF BALLAST WATER MANAGEMENT PLANS (G4)

ANNEX 5 RESOLUTION MEPC.127(53) Adopted on 22 July 2005 GUIDELINES FOR BALLAST WATER MANAGEMENT AND DEVELOPMENT OF BALLAST WATER MANAGEMENT PLANS (G4) RESOLUTION MEPC.127(53) Adopted on 22 July 2005 GUIDELINES FOR BALLAST WATER MANAGEMENT AND DEVELOPMENT OF BALLAST WATER MANAGEMENT PLANS (G4) THE MARINE ENVIRONMENT PROTECTION COMMITTEE, RECALLING Article

More information

26.3.3 The Ship/Shore Safety Check-List

26.3.3 The Ship/Shore Safety Check-List International Safety Guide for Oil Tankers and Terminal Fifth Edition 2006-12-05 26.3.3 The Ship/Shore Safety Check-List Ship's Name Berth Date of Arrival Port Time of Arrival Part `A' - Bulk Liquid General

More information

V K Raina. Reactor Group, BARC

V K Raina. Reactor Group, BARC Critical facility for AHWR and PHWRs V K Raina Reactor Group, BARC India has large reserves of Thorium Critical facility Utilisation of Thorium for power production is a thrust area of the Indian Nuclear

More information

Table of Contents ESF-3-1 034-00-13

Table of Contents ESF-3-1 034-00-13 Table of Contents Primary Coordinating Agency... 2 Local Supporting Agencies... 2 State, Regional, and Federal Agencies and Organizations... 3 Purpose... 3 Situations and Assumptions... 4 Direction and

More information

ESCAMBIA COUNTY FIRE-RESCUE 3105.005

ESCAMBIA COUNTY FIRE-RESCUE 3105.005 Patrick T Grace, Fire Chief Page 1 of 13 PURPOSE: Escambia County Fire-Rescue responds to a wide range of emergency incidents. In order to effectively manage personnel and resources and to provide for

More information

EUROPASS CERTIFICATE SUPPLEMENT

EUROPASS CERTIFICATE SUPPLEMENT EUROPASS CERTIFICATE SUPPLEMENT TITLE OF THE DIPLOMA (ES) Técnico en Mantenimiento y Control de la Maquinaria de Buques y Embarcaciones TRANSLATED TITLE OF THE DIPLOMA (EN) (1) Technician in Maintenance

More information