Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit

Size: px
Start display at page:

Download "Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit"

Transcription

1 Internal Audit Report Toll Operations Contract Management TxDOT Office of Internal Audit

2 Objective To determine whether the Toll Operations Division (TOD) contract management structure is designed and operating to drive effective vendor performance. This audit covered contract management activity and oversight to examine business activities related to the TxTag billing and customer service processes from June 28, 2013 (contract acceptance) to February 28, Opinion Based on the audit scope areas reviewed, control mechanisms are unreliable in addressing risk factors and exposures considered significant relative to impacting reporting reliability and operational execution. The organization's system of internal controls does not provide reasonable assurance that key goals and objectives will be achieved. Control gap corrections are pervasive and resulting in material negative impacts to the organization. Progress can be made within two quarters in addressing the highest risk areas. Overall Engagement Assessment Unsatisfactory Title Findings Control Design Operating Effectiveness Finding 1 Contract Management/Oversight Framework x x Unsatisfactory Finding 2 Performance Measure Achievement x Unsatisfactory Management concurs with the above findings as identified during the audit test period noted. Management has prepared management action plans and begun to take action to address deficiencies. Control Environment Toll Operations Division (TOD) is responsible for developing, operating, and maintaining TxDOT-owned toll facilities in Austin, Laredo, and the Houston region. TOD currently operates with a staff of 17 full-time equivalent employees, with assistance from a vendor who provides system design, marketing, web support, systems integration, call center/customer service center operations, violation identification, collections, and court representation. TOD also relies on a separate third-party vendor to provide consulting, operational support, integration coordination and subject matter expertise of toll operations. TOD and these two vendors began a conversion process in July 2013 (i.e., notice to proceed) to transition from a previous vendor's toll operations system to a more modern customer service center system. Delays were experienced throughout the conversion process through the go-live date of July 9, 2014 due to issues with the migration, conversion, and implementation of tolling data from the legacy system. These delays and issues drove further issues with system reporting and customer statement releases. Additionally, the vendor had not completed specific performance related tasks which have delayed important contractual milestones from being achieved timely. Effective May 11, 2015, a new Director of the Toll Operations Division was hired to fill the role vacated through retirement. Rating August

3 Summary Results Finding Scope Area Evidence TOD s contract management and oversight activities during the tolling system conversion/implementation noted the following: Documentation did not exist to effectively evaluate achievement of: o system implementation o Customer Service Center (CSC) operations, o established transaction processing goals Documentation could not be provided to define the Quality Control/Quality Assurance process used to validate system data and performance indicators Limited documentation demonstrating monitoring of third-party vendor performance in integration coordination and support of toll operations Billing/Customer Service 1 2 Contract Performance Actions/Damages Contract Performance Actions/Damages Limited documentation to support the following key decisions: o approval for extension to complete contractual milestones o vendor completion of deliverables per milestone o approval to process customer billings Evaluation of milestone completion for system implementation noted the following: Operations Commencement (Milestone 7): Required system testing was not completed as scheduled for the site acceptance, system integration, and parallel operations testing, resulting in delayed implementation of system go-live Retention of the previous toll operations vendor resulted in that vendor receiving additional fees and having damages forgiven to ensure continued operations due to data conversion delays Final Acceptance (Milestone 8): System Final Acceptance scheduled for June 2014 had not occurred resulting in additional delays in the ability to monitor vendor performance Reports requested for ten performance indicators tested were either incomplete or calculations could not be reperformed as data from the system was deemed unreliable or incomplete. Audit Scope The audit included the assessment of contractual liquidated damages related to vendor achievement of milestones including data migration, commencement of operations, and August

4 operational readiness. There were eight milestones that were to be completed by the golive date of July 9, 2014, but as of this report date, two milestones have not been completed. Finally, an audit evaluation was performed of the TOD oversight and monitoring of vendor performance through 1) contract and invoice review, 2) inquiry of key management personnel from TOD and vendors, and 3) other documentation review for the same audit test period. The audit was performed by Tracey Garza, Krista Gronniger, Jaime Resendez, Jennifer Stanush, Kathy Baca, and Bill Hunter (Engagement Lead). Audit fieldwork was conducted during the period from February 6, 2015 to March 24, 2015 to examine business activities conducted from June 28, 2013 (contract acceptance) to February 28, Methodology The methodology used to complete the objectives of this audit included: Vendor contract reviews Review of TOD and vendor plans for data migration and system implementation Testing of specific identified issues for accuracy and reliability of reporting, including: o Selected a judgmental sample of TxTag accounts with pay by mail billing activity and reviewed to determine how statement issues were identified and the corrective action taken o Selected a judgmental sample of merged toll customer accounts and reviewed the process for merging these accounts and validation of accounts to determine accuracy and completeness of conversion o Reviewed planned billing cycles compared to the statement distribution log to identify variances in billing dates o Selected a judgmental sample of toll accounts with duplicate transactions and reviewed to determine how issues were identified and the corrective action taken Reviewed vendor processes for testing interoperability between toll entities Determined contract-related milestones and performance measures Reviewed vendor self-reported performance and evaluated liquidated damages, to date Tested vendor invoices for payments and verified TOD s assessment of damages Reviewed documentation to support monitoring and verification of vendor performance Reviewed communications between TOD and the vendors to determine level of oversight Background This report is prepared for the Texas Transportation Commission and for the Administration and Management of TxDOT. The report presents the results of the audit of Toll Operations Contract Management which was conducted as part of the Fiscal Year 2015 Audit Plan. All toll road revenue has grown from $77 million in FY 2011 to $211 million in FY The current vendor contract was bid using the FY 2011 revenue numbers. August

5 In conjunction with its third-party consultant, TOD issued a Request for Proposal and entered into an agreement with a vendor to modernize the customer service center system in June This modernization included converting existing toll accounts to a new system, merging accounts to simplify account maintenance for the customer, implementing a new interactive voice response system, and updating customer service capabilities to improve the customer experience. Table 1 below provides a timeline of key events related to the conversion. Table 1 Conversion Timeline: Key Events (May 2013-November 2014) *Milestones 6 and 8 are not completed as of the report date Source: Contract documentation provided by Toll Operations Division Toll operations customer billing is divided into two primary types of transactions: 1) tag holders (including private and business TxTag accounts with interoperability with other toll systems across the state) and 2) pay-by-mail customers (those without a TxTag). Private tag holders can prepay a deposit on their accounts and have the ability to maintain their accounts online. As the deposit is expended, the tag holder can opt to make additional payments or setup an automatic replenishment option using a credit card set up on the account. Account activity is charged at the higher pay-by-mail rate for customers whose account balances reach zero and do not make either additional payments or opt for the automatic replenishment option. We conducted this performance audit in accordance with Generally Accepted Government Auditing Standards and in conformance with the International Standards for the Professional Practice of Internal Auditing. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives. Recommendations to mitigate risks identified were provided to management during the engagement to assist in the formulation of the management action plans included in this report. The Office of Internal Audit uses the Committee of Sponsoring Organizations of the Treadway Commission (COSO) Internal Control Integrated Framework version A defined set of control objectives was utilized to focus on reporting and operational goals for the identified scope areas. Our audit opinion is an assessment of the health of the overall control environment based on (1) the effectiveness of the enterprise risk management activities throughout the audit period and (2) the degree to which the defined control objectives were being met. Our audit opinion is not a guarantee against reporting misstatement and reliability or operational sub-optimization particularly in areas not included in the scope of this audit. August

6 Detailed Findings and Management Action Plans (MAP) Finding No. 1: Contract Management/Oversight Framework Condition Toll Operations Division (TOD) contract management and oversight activities during the conversion to the new customer service center system were not fully designed, documented, and executed to provide reasonable assurance that 1) the implementation of the customer service center system was completed timely, and 2) implementation, billing, and operational issues identified during the conversion process were prioritized and addressed to achieve effective resolution. Additionally, there was no independent assessment by TOD of vendor performance measures to determine whether customer service and billing activities were performed or computed in accordance with contract requirements or proper control techniques. Effect/Potential Impact The new customer service center system implementation experienced delays in data migration, system testing, operations commencement, and achievement of project acceptance. Since commencement of operations on July 9, 2014, customer service and billing issues were experienced. A complete assessment of vendor contract performance and any resulting damages that might be incurred based on that performance could not be properly determined for the two outstanding milestones and on-going customer service performance measures. Criteria Industry guidance such as The State of Texas Contract Management Guide provides guidelines on performance monitoring and administration: Monitoring contractor performance ensures performance is in accordance with the contract and allows the managing division to be aware of and address any developing problems or issues Development of performance measure deliverables, which clearly outline how results will be measured, are the sole responsibility of the managing division Maintaining a complete contract administration file provides a source to settle claims and disputes that may arise and should contain items such as: o copies of all general correspondence related to the contract o records/minutes of all meetings including sign-in sheets and/or agendas o copies of all routine reports required by the contract such as approval requests and inspection reports Other industry standards, such as the PMI Project Management Body of Knowledge (PMBOK Guide) Fifth Edition, also provide the following guidance: Project governance provides a comprehensive, consistent method of controlling the project, and ensuring success by defining, documenting, and communicating reliable, repeatable practices To ensure project success, the project team should perform the following: o Select appropriate processes required to meet project objectives o Use a defined approach that can be adapted to meet requirements August

7 o Establish and maintain appropriate communication and engagement with stakeholders o Comply with requirements to meet stakeholder needs and expectations o Balance the competing constraints of scope, schedule, budget, quality, resources, and risk to produce the specified product, service or result Activities that should be performed by the project management team (i.e., TOD) include: o Develop, review, analyze, and understand the scope including the project and product requirements, criteria, assumptions, constraints, and other influences related to a project, and how each will be managed or addressed within the project o Measure and monitor the project s progress and take appropriate action to meet project objectives Cause The process to migrate and convert toll data between the legacy vendor and the current vendor did not work effectively to meet contractual and transitional timelines as originally expected by TxDOT. This included a complex conversion of 8 years of tolling data from a multiple account structure to a single account structure to help drive efficient statement reporting for toll customers. Without fully implementing an independent TOD validation protocol for quality control or quality assurance responsibilities, TOD primarily relied on the vendor to self-monitor and self-report on customer service and billing activities from their data. Evidence The audit work performed was to substantiate the timing and transparency of when issues were detected, who was involved in determining corrective actions, root causes, and the escalation path used to notify TxDOT management and administration. Audit work concluded that limited documented information was created or retained to substantiate who was involved in the discussions or who took accountability for actions that were to follow in resolving the operational and reporting issues. A review of TOD s management processes over system implementation and operations identified the following: Limited documentation to support key decisions made during the project, (i.e., approval of extension of time to complete milestones, the determination of the vendor's completion of individual deliverables within a milestone, and approval to process tolling customer billings), could be provided No documented operational design existed for process or procedures to effectively evaluate achievement of system implementation, Customer Service Center (CSC) operations, and timely transaction processing goals o Preliminary key performance indicator (KPI) monitoring techniques used were drafted after contract commencement by the vendor and had not been finalized or enforced, as of audit fieldwork completion August

8 TOD provided no documentation of a process or procedures for a Quality Control/Quality Assurance protocol which would be used to validate tolling data and performance indicators when provided Limited documentation demonstrating TOD s monitoring of the third-party vendor s performance in integration coordination and support of toll operations In reviewing and evaluating system implementation contractual milestones, the following were noted: Required system implementation tests for operations commencement, including the site acceptance test, system integration test, and parallel operations test, were not completed as scheduled resulting in delayed implementation of go-live from the original contract date of March 28, 2014 until July 9, 2014 The Operations Commencement Milestone was delayed for three months leading up to the go-live date; this resulted in additional fees and forgiveness of damages to the previous toll operation s vendor to ensure continued operations. System Final Acceptance scheduled for June 2014 had not occurred, resulting in continued delays in TOD s ability to monitor vendor performance and to independently assess data integrity. Management Action Plan (MAP): Rick Nelson, Director, Toll Operations Division MAP 1.1: Project Management Processes TxDOT will implement Project Management Institute (PMI) PMBOK guideline usage by TxDOT, consultants, and vendor to ensure a well-designed process is implemented and becomes standard operating procedure for contract and project management. October 15, 2015 Roland Silva, Toll Operations Division MAP 1.2: Standard Operating Procedure Development - Phase 1 TOD will continue its development of TOD staff Standard Operating Procedures (SOPs) which will address each TOD Subject Matter Expert s (SME) specific oversight and monitoring activities. SOPs will define monitoring and process review of operational activities and Key Performance Indicators. Given the work effort required to complete this MAP and the impending Operational Observation Period (OOP) schedule, TOD will use the OOP to understand and document its KPI monitoring SOPs. Therefore, KPI related SOPs will be completed during Phase 1 and the remaining operational SOPs will be completed in Phase 2. August

9 Action Completed MAP 1.3: Standard Operating Procedure Development - Phase 2 TOD will continue its development of TOD staff SOPs which will address each TOD SME s specific oversight and monitoring activities of specific operations processes. November 15, 2015 Brian Smallwood, Director, Operational Excellence Toll Operations Division MAP 1.4: Verification & Validation Processes TOD will expand its verification/validation activities to include process audits by TOD operational area SMEs which will be subject to review and audit by the TOD QA/QC Team. Activities identified on MAP 1.2 monitoring SOPs will be audited periodically according to a TOD QC Audit Schedule and subject to regular spot checks. Results and any recommendations will be reported to the Director of Operational Excellence and Toll Operations Director when needed and/or on a quarterly basis. In the interim, TOD will continue its monitoring of identified key processes and coordinate appropriate actions with vendor through existing regularly scheduled Issues Review, Release Planning and QA/QC meetings. October 15, 2015 Rick Nelson, Director, Toll Operations Division MAP 1.5: Independent 3rd party review of operations TOD will work with an independent consultant to provide an independent information technology assessment of contract management and review of operations to provide specific areas of focus to improve both. Consultant will also provide an independent validation of vendor contract and performance by implementing tools using Tableau and Crystal Reports. These tools will be owned and used by TOD to monitor contract performance after the initial assessment. December 15, 2015 August

10 MAP 1.6: Additional PMO process Third party PMP certified consultant implementation of a project matrix detailing approved projects, project owners, resources assigned, percentage of employees time assigned to project, project approved schedule by budget assigned and expended by month. This matrix will include all planned and approved activities for the next 18 months and project and/or contract managers will report monthly at TOD staff meetings on these projects. October 15, 2015 Linda Sexton, Deputy Director, Toll Operations Division MAP 1.7: Atkins PMO Certified Managers TOD will direct their third party consultant in writing to provide the PMP certified project manager(s) required by contract and to adhere to PMBOK guidelines. September 15, 2015 MAP Owners: Rick Nelson, Director, Toll Operations Division Linda Sexton, Deputy Director, Toll Operations Division MAP 1.8: TOD Organization TOD will evaluate its present organizational structure and provided a recommendation to the TXDOT CFO of any needed changes required to address unsatisfactory ratings noted in this Internal Audit Report. November 15, 2015 MAP 1.9: TxDOT PMO Certified Managers TOD will require all identified TOD project managers to obtain PMP certification and use PMBOK guidelines in managing projects. Phase 1 certification of three TxDOT project managers will be completed by December 15, Phase 2 will provide a plan to certify all remaining TxDOT TOD project managers. February 15, 2016 August

11 MAP Owners: Rick Nelson, Director, Toll Operations Division Teresa Lemons, Toll Operations Division MAP 1.10: Procure Project Management Software Develop action plan to procure and implement third party software for Project Management designed around the PMBOK guidelines to provide a dashboard/score card using both qualitative and quantitative information on all approved tasks and projects. Said software shall provide a transparent dashboard/score card and shall be accessible 24 x7 to senior management of TOD and any other users approved by TxDOT CFO. January 15, 2016 Teresa Lemons, Toll Operations Division MAP 1.11: TOD Budget Officer Recruit and hire an individual who is a Certified Public Accountant to fill the Budget Officer position to provide Generally Accepted Accounting Principles compliance guidance to TOD. September 15, 2015 August

12 Finding No. 2: Performance Measure Achievement Condition Achievement of contractual performance measures by the vendor in categories such as Customer Service Center (CSC) Operations, CSC Information Systems, and Timely Processing, were not being consistently monitored or evaluated by Toll Operations Division (TOD). Performance monitoring was scheduled to start 60 days after system implementation. Effect/Potential Impact There was no assurance that the vendor was meeting performance goals in accordance to the contract. Additionally, performance problems or issues that would be identified with the proper assessment of performance measures may not be timely addressed and resolved. Criteria The vendor contract requires payment of damages for failure to meet various performance measures related to the CSC Operations, CSC Information Systems, and Timely Processing. Texas Government Code 2262 requires that state agencies comply with the State of Texas Contract Management Guide (Guide) for monitoring contract performance. The Guide provides guidelines on performance monitoring including the development of performance measure deliverables that clearly outline the methods and procedures to measure results. Cause TOD has elected to not calculate or validate performance measure achievement until all milestones are completed. Currently, there is a reliance on the vendor to self-report performance measurement results with no documented or independent TOD validation protocol. Evidence A review of 10 of 27 contractual performance measures for CSC Operations, CSC Information Systems, and Timely Processing indicated the data used to calculate the measures could not be independently validated as all contractual milestones had not been completed by the vendor. As of the February 28, 2015, reports requested for the 10 performance measures listed in the table below were either incomplete or the data pulled from the system and used in the calculation could not be re-performed to assure reliability. Those performance measures, which are tied to system implementation milestones that are not yet complete, include: August

13 Performance Measure Damages Average Speed to Answer Calls answered by $5,000 per month live agents within 60 seconds, 85% of time and within 120 seconds, 95% of time Wait-time to Answer - Calls coming into the $5,000 per month Interactive Voice Response (IVR) requesting a live agent must have a maximum wait time of 5 minutes, 99% of time Escalations - A maximum of 10% of calls $5,000 per month answered by a live agent are allowed to be escalated. IVR - 25% of calls received, handled through IVR $10,000 per month Inquiries, Requests, and Disputes - Responded $5,000 per month with findings and/or resolution within 3 days, 85% of time, and within 5 days, 100% of time. Statements - Mailed/ ed to customers $5,000 per month within 5 days, 97% of time and within 10 days, 3% of time Website - Excluding scheduled downtime, $1,000 per hour website available 99% of time Timely Notification of TxTag Transactions within Variable pricing of $ $0.050 per paid 60 calendar days toll transactions based on the total number of Timely Notification of Video Transactions within 60 calendar days Timely Notification of Violation Transactions within 60 calendar days Management Action Plan (MAP): transactions posted in the month $0.31 per paid toll transaction based on the total number of transactions posted in the month $0.325 per paid toll transaction based on violation transactions (pre-collection) Brian Smallwood, Director of Operational Excellence Toll Operations Division MAP 2.1: Complete Implementation Milestones TOD will continue to coordinate with the vendor to identify and prioritize the resolution of incomplete implementation milestones. TOD is meeting with the vendor twice weekly to identify issues impeding implementation and to prioritize the evaluating of solution releases through Issues and Release Planning meetings. October 15, 2015 MAP 2.2: Complete Key Performance Indicator (KPI) Reports TOD will continue to evaluate KPI reports available and drive this report review effort, including validation and approval of vendor performance reporting. TOD will deliver a formal August

14 report Validation and Release process document to the vendor to facilitate the validation of the KPI reports. TOD currently meets with the vendor's Technical Reporting team daily to resolve KPI report issues and prioritize their report fixes or enhancement necessary for accurate and complete KPI reporting. A meeting will also be scheduled targeted at gaining a more comprehensive understanding of Vector 4G data and database relationships to facilitate report and data validation. November 15, 2015 Rick Nelson, Director, Toll Operations Division MAP 2.3: Milestone Documentation TOD will request all vendors provide action plans in writing to address missed or late milestone dates. Vendor action plans will require a fully loaded resource schedule so TOD can monitor vendor s effort in meeting milestones. Action Completed MAP Owners: Rick Nelson, Director, Toll Operations Division Linda Sexton, Deputy Director, Toll Operations Division MAP 2.4: System Monitoring Improvements TOD will implement third party software to automate lane audits and monitor system performance. December 15, 2015 MAP Owners: Linda Sexton, Deputy Director, Toll Operations Division Brian Smallwood, Director of Operational Excellence, Toll Operations Division MAP 2.5: Interim Performance Reporting TOD will calculate performance measure achievement by using statistics provided by the vendor and independently evaluate the data to assess damages. This will be done until such time as required reports are approved by TxDOT through Operational Observation Period and available for use. November 15, 2015 August

15 Summary Results Based on Enterprise Risk Management Framework Rating Assessment Grid Exemplary Satisfactory Needs Improvement Unsatisfactory Closing Comments The results of this audit were discussed with management of Toll Operations Division and TxDOT Administration. We appreciate the assistance and cooperation received from the management and employees contacted during this audit. August

MNLARS Project Audit Checklist

MNLARS Project Audit Checklist Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?

More information

Internal Audit Report. Receivables Management Statement of Cost TxDOT Office of Internal Audit

Internal Audit Report. Receivables Management Statement of Cost TxDOT Office of Internal Audit Internal Audit Report Receivables Management Statement of Cost TxDOT Office of Internal Audit Objective The audit objective is to evaluate whether monitoring and accounting for outstanding construction

More information

Department of Administration Portfolio Management System 1.3 June 30, 2010

Department of Administration Portfolio Management System 1.3 June 30, 2010 E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2

More information

Internal Audit Report. Right of Way Acquisition TxDOT Office of Internal Audit

Internal Audit Report. Right of Way Acquisition TxDOT Office of Internal Audit Internal Audit Report Right of Way Acquisition TxDOT Office of Internal Audit Objective Evaluate the right of way acquisition process for efficiency and compliance. Opinion Based on the audit scope areas

More information

Internal Audit Report. Highway Condition Reporting TxDOT Office of Internal Audit

Internal Audit Report. Highway Condition Reporting TxDOT Office of Internal Audit Internal Audit Report Highway Condition Reporting TxDOT Office of Internal Audit Objective To evaluate data integrity in the Highway Condition Report. Opinion Based on the audit scope areas reviewed, control

More information

December 2014 Report No. 15-017. An Audit Report on The Telecommunications Managed Services Contract at the Health and Human Services Commission

December 2014 Report No. 15-017. An Audit Report on The Telecommunications Managed Services Contract at the Health and Human Services Commission John Keel, CPA State Auditor An Audit Report on The Telecommunications Managed Services Contract at the Health and Human Services Commission Report No. 15-017 An Audit Report on The Telecommunications

More information

June 2008 Report No. 08-038. An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers

June 2008 Report No. 08-038. An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers John Keel, CPA State Auditor An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers Report No. 08-038 An Audit Report on The Department of Information

More information

PHASE 8: IMPLEMENTATION PHASE

PHASE 8: IMPLEMENTATION PHASE PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the

More information

Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview

Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program

More information

Florida PALM Quarterly Project Oversight Report: Comprehensive Review For January March 2015

Florida PALM Quarterly Project Oversight Report: Comprehensive Review For January March 2015 Department of Financial Services Florida Planning, Accounting, and Ledger Management (PALM) For Period: January March 2015 Quarter Ending: 3/31/2015 Agency Name: Department of Financial Services Project

More information

Draft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing

Draft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing STATE OF MICHIGAN SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing Executive Summary The State of Michigan has dedicated integrated team of resources for the

More information

July 2013 Report No. 13-042

July 2013 Report No. 13-042 John Keel, CPA State Auditor An Audit Report on Selected State Contracts at the Texas Education Agency Report No. 13-042 An Audit Report on Selected State Contracts at the Texas Education Agency Overall

More information

Social Services Contract Monitoring Audit

Social Services Contract Monitoring Audit City of Austin AUDIT REPORT A Report to the Austin City Council Mayor Lee Leffingwell Mayor Pro Tem Sheryl Cole Social Services Contract Monitoring Audit October 2011 Council Members Chris Riley Mike Martinez

More information

SCHEDULE 3. Milestones and Deliverables. Redacted Version

SCHEDULE 3. Milestones and Deliverables. Redacted Version SCHEDULE 3 Milestones and Deliverables Redacted Version This Schedule 3 sets out the Service Provider s obligations in respect of the milestones and deliverables relating to the implementation and operation

More information

Project Management Guidelines

Project Management Guidelines Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.

More information

Independent Auditors Report

Independent Auditors Report KPMG LLP Suite 12000 1801 K Street, NW Washington, DC 20006 Independent Auditors Report Administrator and Acting Inspector General United States General Services Administration: Report on the Financial

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

Information Technology Internal Audit Report

Information Technology Internal Audit Report Information Technology Internal Audit Report Report #2014-05 July 25, 2014 Table of Contents Page Executive Summary... 3 Background Information... 4 Background... 4 Audit Objectives... 4 Scope and Testing

More information

STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840

STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 MARYLAND STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 Bobbie S. Mack, Chairman David J. McManus, Jr., Vice Chairman Rachel T. McGuckian Patrick H. Murray Charles

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES 1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through

More information

PHASE 6: DEVELOPMENT PHASE

PHASE 6: DEVELOPMENT PHASE PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration

More information

Project Management Plan for

Project Management Plan for Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...

More information

PMP Examination Tasks Puzzle game

PMP Examination Tasks Puzzle game PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in

More information

REPORT 2016/035 INTERNAL AUDIT DIVISION

REPORT 2016/035 INTERNAL AUDIT DIVISION INTERNAL AUDIT DIVISION REPORT 2016/035 Audit of the use of consultants and individual contractors in the United Nations Stabilization Mission in Haiti Overall results relating to the effective hiring

More information

Crosswalk Between Current and New PMP Task Classifications

Crosswalk Between Current and New PMP Task Classifications Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the

More information

CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE

CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE STATE OF IDAHO DEPARTMENT OF ADMINISTRATION DIVISION OF PURCHASING REVISED 01 01 14 Table of Contents I. Purpose... 1 II. Overview of Contract Management and

More information

THIRD-PARTY RISK: HOW TO BETTER UTILIZE ENERGY VENDOR AUDITS 8/25/2015. August 27, 2015

THIRD-PARTY RISK: HOW TO BETTER UTILIZE ENERGY VENDOR AUDITS 8/25/2015. August 27, 2015 8/25/2015 THIRD-PARTY RISK: HOW TO BETTER UTILIZE ENERGY VENDOR AUDITS August 27, 2015 Shane Torkelson, CPE, CISA, CIA Director Enterprise Risk Solutions storkelson@bkd.com 1 TO RECEIVE CPE CREDIT Participate

More information

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Audit of Internal Controls Over Financial Reporting.

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Audit of Internal Controls Over Financial Reporting. Aboriginal Affairs and Northern Development Canada Internal Audit Report Audit of Internal Controls Over Financial Reporting Prepared by: Audit and Assurance Services Branch Project #: 14-05 November 2014

More information

Internal Audit Follow-Up Report. Equipment Maintenance and Repair. TxDOT Office of Internal Audit. Jan J

Internal Audit Follow-Up Report. Equipment Maintenance and Repair. TxDOT Office of Internal Audit. Jan J Internal Audit Follow-Up Report Equipment Maintenance and Repair TxDOT Office of Internal Audit Jan J Objective Assess the status of corrective actions for high risk Management Action Plans (MAPs) previously

More information

Sarbanes-Oxley Compliance Workbook. From Zero to SOX. Sarbanes-Oxley Compliance Workbook. sensiba san filippo www.ssfllp.com sox@ssfllp.

Sarbanes-Oxley Compliance Workbook. From Zero to SOX. Sarbanes-Oxley Compliance Workbook. sensiba san filippo www.ssfllp.com sox@ssfllp. From Zero to SOX Zero to SOX An Overview The goals of a program to meet SOX 404 requirements go far beyond compliance. The process of building a sustainable, comprehensive internal control environment

More information

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86

More information

Blend Approach of IT Service Management and PMBOK for Application Support Project

Blend Approach of IT Service Management and PMBOK for Application Support Project Blend Approach of IT Service and PMBOK for Application Support Project Introduction: This paper addresses the process area, phases and documentation to be done for Support Project using Project and ITSM

More information

The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004)

The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004) The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004) is the processes required to ensure that the various elements of the project are properly coordinated. the processes required to ensure

More information

ATTACHMENT 1: CONTRACTOR PAST PERFORMANCE REPORT CONSULTING SERVICES Note: Continuation sheets may be used if more space is required.

ATTACHMENT 1: CONTRACTOR PAST PERFORMANCE REPORT CONSULTING SERVICES Note: Continuation sheets may be used if more space is required. 1. Consultant Name and Address: 2. MCA Entity: Country: Point of Contact (POC) 3. [ ] Final Report From: To: [ ] Interim Report From: To: Name: POC Position: 4. Contract Number: 8. Total Value of Base

More information

LEXEVS OPERATIONS AND MAINTENCE SUPPORT PROJECT MANAGEMENT PLAN

LEXEVS OPERATIONS AND MAINTENCE SUPPORT PROJECT MANAGEMENT PLAN LEXEVS OPERATIONS AND MAINTENCE SUPPORT PROJECT MANAGEMENT PLAN Version Number: 1.0 Version Date: October 1, 2014 VERSION HISTORY Version Number Implemented By Revision Date Approved By Approval Date 1.0

More information

Overview of EAM Services. A Fully Integrated Global EAM Service Provider

Overview of EAM Services. A Fully Integrated Global EAM Service Provider A Fully Integrated Global EAM Service Provider Table of Contents Strategy & Process Services Overview... p. 3 Asset Reliability Services Overview... p. 4 Systems & Technology Services Overview... p. 7

More information

Contract and Vendor Management Guide

Contract and Vendor Management Guide Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier

More information

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided. Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60

More information

FINAL AUDIT REPORT WITH RECOMMENDATIONS Internal Operations No. 12-001 BACKGROUND

FINAL AUDIT REPORT WITH RECOMMENDATIONS Internal Operations No. 12-001 BACKGROUND FINAL AUDIT REPORT WITH RECOMMENDATIONS Internal Operations No. 12-001 SUBJECT: Review of Contract CQ 7068 Safety Management Assessment and Enhancement Program DATE: February 14, 2012 FROM: OIG Helen Lew

More information

REQUEST FOR PROPOSAL RM 112649 E ZPASS CUSTOMER SERVICE CENTER Pre Proposal Meeting

REQUEST FOR PROPOSAL RM 112649 E ZPASS CUSTOMER SERVICE CENTER Pre Proposal Meeting REQUEST FOR PROPOSAL RM 112649 E ZPASS CUSTOMER SERVICE CENTER Pre Proposal Meeting 10:00 AM Monday February 23, 2015 Board Room of the Authority s Administration Building, 581 Main Street, Woodbridge,

More information

to conduct a review of the jobs reporting verification process employed by WEDC.

to conduct a review of the jobs reporting verification process employed by WEDC. December 22,2015 Senator Rob Cowles 118 South State Capitol Madison, Wl 53707 Representative Samantha Kerkman 315 North State Capitol Madison, Wl 53708 Dear Senator Cowles and Representative Kerkman: Enclosed

More information

Audit of Financial Management Governance. Audit Report

Audit of Financial Management Governance. Audit Report Audit of Financial Management Governance Audit Report March 2015 TABLE OF CONTENTS Executive Summary... 2 What we examined... 2 Why it is important... 2 What we found... 2 Background... 4 Objective...

More information

September 2014 Report No. 15-001

September 2014 Report No. 15-001 John Keel, CPA State Auditor An Audit Report on Selected Contracts at the Texas Facilities Commission Report No. 15-001 An Audit Report on Selected Contracts at the Texas Facilities Commission Overall

More information

Project Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1)

Project Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Date: October 1, 2014 Version: 3.1 DOCUMENT REVISION HISTORY Version Date Changes Updated By 0.1 02/13/014 Initial

More information

Audit of USAID's Staff Training and Development Activities Audit Report Number 9-000-02-005-P July 11, 2002

Audit of USAID's Staff Training and Development Activities Audit Report Number 9-000-02-005-P July 11, 2002 Audit of USAID's Staff Training and Development Activities Audit Report Number 9-000-02-005-P July 11, 2002 Washington, D.C. U.S. AGENCY FOR INTERNATIONAL DEVELOPMENT July 11, 2002 MEMORANDUM FOR: FROM:

More information

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 - ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and

More information

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010 Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning

More information

Colorado Department of Health Care Policy and Financing

Colorado Department of Health Care Policy and Financing Colorado Department of Health Care Policy and Financing Solicitation #: HCPFRFPCW14BIDM Business Intelligence and Data Management Services (BIDM) Appendix B BIDM Project Phases Tables The guidelines for

More information

Enterprise Projects Fiscal Year 2009/2010 Third Quarter Report

Enterprise Projects Fiscal Year 2009/2010 Third Quarter Report Enterprise Projects Fiscal Year 2009/2010 Third Quarter Report Enterprise Projects Fiscal Year 2009/2010 - Third Quarter Report The Enterprise Program Investment Council (EPIC) is responsible for governance

More information

Design Consultant Project Management Requirements

Design Consultant Project Management Requirements Design Consultant Project Management Requirements Version 2 April 25, 2013 AWTP Program Design Consultant Contents 1.0 Introduction... 1 2.0 General Management... 1 3.0 Project Management Plan... 1 4.0

More information

Information Technology Project Oversight Framework

Information Technology Project Oversight Framework i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11

More information

Procurement guidance Managing and monitoring suppliers performance

Procurement guidance Managing and monitoring suppliers performance Procurement guidance Managing and monitoring suppliers performance Procurement guidance: Managing and monitoring suppliers performance Page 2 of 16 Table of contents Table of contents... 2 Purpose of the

More information

The 10 Knowledge Areas & ITTOs

The 10 Knowledge Areas & ITTOs This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading

More information

Student Assessment Administrative Review Phase 1

Student Assessment Administrative Review Phase 1 Internal Audit Student Assessment Administrative Review Phase 1 Issue Date: March 2015 Report Number: FY2015-02 Executive Summary AUDIT OF: Student Assessment DATE: Fieldwork performed January 2015 February

More information

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement

More information

UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL

UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL AUDIT SERVICES August 24, 2015 Control Number ED-OIG/A04N0004 James W. Runcie Chief Operating Officer U.S. Department of Education Federal

More information

Department of Veterans Affairs

Department of Veterans Affairs Audit Report Department of Veterans Affairs December 2013 OFFICE OF LEGISLATIVE AUDITS DEPARTMENT OF LEGISLATIVE SERVICES MARYLAND GENERAL ASSEMBLY This report and any related follow-up correspondence

More information

Final Report. Audit of the Project Management Framework. December 2014

Final Report. Audit of the Project Management Framework. December 2014 Final Report Audit of the Project Management Framework December 2014 Audit of the Project Management Framework Table of Contents Executive summary... i A - Introduction... 1 1. Background... 1 2. Audit

More information

Audit of the Office of Emergency Management and Homeland Security: FEMA Urban Area Security Initiative Grant Management 2012 through 2014

Audit of the Office of Emergency Management and Homeland Security: FEMA Urban Area Security Initiative Grant Management 2012 through 2014 Audit of the Office of Emergency Management and Homeland Security: FEMA Urban Area Security Initiative Grant Management 2012 through 2014 MARTIN MATSON City Comptroller STACEY MAZMANIAN Audit Manager City

More information

ITSM Process Description

ITSM Process Description ITSM Process Description Office of Information Technology Incident Management 1 Table of Contents Table of Contents 1. Introduction 2. Incident Management Goals, Objectives, CSFs and KPIs 3. Incident Management

More information

PROJECT PROCUREMENT MANAGEMENT

PROJECT PROCUREMENT MANAGEMENT 12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,

More information

UNIVERSITY OF CALIFORNIA, DAVIS INTERNAL AUDIT SERVICES. University of California Davis Medical Center Electronic Medical Records Project #04-44

UNIVERSITY OF CALIFORNIA, DAVIS INTERNAL AUDIT SERVICES. University of California Davis Medical Center Electronic Medical Records Project #04-44 , DAVIS INTERNAL AUDIT SERVICES University of California Davis Medical Center Electronic Medical Records Project #04-44 October 2006 Fieldwork Performed by: Tim Bryan, Principal Auditor Reviewed by: Tom

More information

Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report

Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report The Enterprise Program Investment Council (EPIC) is responsible for governance

More information

COSO 2013: WHAT HAS CHANGED & STEPS TO TAKE TO ENSURE COMPLIANCE

COSO 2013: WHAT HAS CHANGED & STEPS TO TAKE TO ENSURE COMPLIANCE COSO 2013: WHAT HAS CHANGED & STEPS TO TAKE TO ENSURE COMPLIANCE COMMITTEE OF SPONSORING ORGANIZATIONS (COSO) 2013 The Committee of Sponsoring Organizations (COSO) Internal Controls Integrated Framework,

More information

Delaware Department of Transportation QUESTIONS AND ANSWERS E-ZPass Customer Service Center 1601 Request for Proposals Friday, February 1, 2013

Delaware Department of Transportation QUESTIONS AND ANSWERS E-ZPass Customer Service Center 1601 Request for Proposals Friday, February 1, 2013 85 84 83 82 What are the 2012 monthly and annual volumes for the following: Website traffic DMV Call Center E-ZPass CSC walk-up traffic E-Z Pass CSC calls offered and handled Violation transactions and

More information

Consultancy Services Proposal

Consultancy Services Proposal Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847

More information

Attachment 2 Performance Metrics

Attachment 2 Performance Metrics Attachment 2 Performance Metrics The following metrics are the metrics that the Contractor is required to meet to satisfy the Contract. In addition, the Contractor will be required to provide regular reports

More information

Systems Analysis and Design in a Changing World, Fifth Edition

Systems Analysis and Design in a Changing World, Fifth Edition Systems Analysis and Design in a Changing World, Fifth Edition Learning Objectives Explain the elements of project management and the responsibilities of a project manager Explain project initiation and

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

AUDIT REPORT THE ADMINISTRATION OF CONTRACTS AND AGREEMENTS FOR LINGUISTIC SERVICES BY THE DRUG ENFORCEMENT ADMINISTRATION AUGUST 2002 02-33

AUDIT REPORT THE ADMINISTRATION OF CONTRACTS AND AGREEMENTS FOR LINGUISTIC SERVICES BY THE DRUG ENFORCEMENT ADMINISTRATION AUGUST 2002 02-33 AUDIT REPORT THE ADMINISTRATION OF CONTRACTS AND AGREEMENTS FOR LINGUISTIC SERVICES BY THE DRUG ENFORCEMENT ADMINISTRATION AUGUST 2002 02-33 THE ADMINISTRATION OF CONTRACTS AND AGREEMENTS FOR LINGUISTIC

More information

June 2008 Report No. 08-037. An Audit Report on The Texas Education Agency s Oversight of Alternative Teacher Certification Programs

June 2008 Report No. 08-037. An Audit Report on The Texas Education Agency s Oversight of Alternative Teacher Certification Programs John Keel, CPA State Auditor An Audit Report on The Texas Education Agency s Oversight of Alternative Teacher Certification Programs Report No. 08-037 An Audit Report on The Texas Education Agency s Oversight

More information

Audit of Veterans Health Administration Blood Bank Modernization Project

Audit of Veterans Health Administration Blood Bank Modernization Project Department of Veterans Affairs Office of Inspector General Audit of Veterans Health Administration Blood Bank Modernization Project Report No. 06-03424-70 February 8, 2008 VA Office of Inspector General

More information

WILLIAM J. DOWLING VICE PRESIDENT, ENGINEERING

WILLIAM J. DOWLING VICE PRESIDENT, ENGINEERING June 28, 1999 WILLIAM J. DOWLING VICE PRESIDENT, ENGINEERING Subject: Tray Management System Software Management () As part of an ongoing audit of the Tray Management System, the Office of Inspector General

More information

Anatomy of an IT Outsourcing Deal. Bruce Laco Deloitte John Pickett IT World Canada Barry Sookman McCarthy Tetrault

Anatomy of an IT Outsourcing Deal. Bruce Laco Deloitte John Pickett IT World Canada Barry Sookman McCarthy Tetrault Anatomy of an IT Outsourcing Deal Bruce Laco Deloitte John Pickett IT World Canada Barry Sookman McCarthy Tetrault 3656867 Agenda Key Considerations for IT Outsourcing Decision Anatomy of an Outsourcing

More information

Information Technology Internal Audit Report

Information Technology Internal Audit Report Information Technology Internal Audit Report Report #2013-03 August 9, 2013 Table of Contents Page Executive Summary... 3 Background Information... 4 Background... 4 Audit Objectives... 4 Scope... 5 Testing

More information

PHASE 6: DEVELOPMENT PHASE

PHASE 6: DEVELOPMENT PHASE PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product

More information

Recommendations for Improving Purchasing Card Procedures

Recommendations for Improving Purchasing Card Procedures Recommendations for Improving Purchasing Card Procedures I. Cardholder Issues: 1. Receipts are not provided for all card charges. A. Current Policy Statement: The Cardholder must: Obtain all sales slips,

More information

September 2005 Report No. 06-009

September 2005 Report No. 06-009 An Audit Report on The Health and Human Services Commission s Consolidation of Administrative Support Functions Report No. 06-009 John Keel, CPA State Auditor An Audit Report on The Health and Human Services

More information

Construction Management Standards of Practice

Construction Management Standards of Practice Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388

More information

INFORMATION TECHNOLOGY PROJECT REQUESTS

INFORMATION TECHNOLOGY PROJECT REQUESTS INFORMATION TECHNOLOGY PROJECT REQUESTS Guidelines & Instructions for Maryland State Agencies Revised Two Step PPR/PIR Approval Process Fiscal Year 2013 Table of Contents Part 1: Overview... 2 1.1 Introduction...

More information

Oversight of Information Technology Projects. Information Technology Audit

Oversight of Information Technology Projects. Information Technology Audit O L A OFFICE OF THE LEGISLATIVE AUDITOR STATE OF MINNESOTA FINANCIAL AUDIT DIVISION REPORT Oversight of Information Technology Projects Information Technology Audit May 29, 2009 Report 09-19 FINANCIAL

More information

Unemployment Insurance (UI) Information Technology (IT) Modernization Pre-Implementation Planning Checklist

Unemployment Insurance (UI) Information Technology (IT) Modernization Pre-Implementation Planning Checklist Unemployment Insurance (UI) Information Technology (IT) Modernization Pre-Implementation Planning Checklist Functionality is Fully Available or Workaround in Place for the following: All benefit and tax

More information

Audit of the Test of Design of Entity-Level Controls

Audit of the Test of Design of Entity-Level Controls Audit of the Test of Design of Entity-Level Controls Canadian Grain Commission Audit & Evaluation Services Final Report March 2012 Canadian Grain Commission 0 Entity Level Controls 2011 Table of Contents

More information

Report of Audit OFFICE OF INSPECTOR GENERAL. Information Technology Infrastructure Project Management A-07-02. Tammy Rapp Auditor-in-Charge

Report of Audit OFFICE OF INSPECTOR GENERAL. Information Technology Infrastructure Project Management A-07-02. Tammy Rapp Auditor-in-Charge OFFICE OF INSPECTOR GENERAL Report of Audit Information Technology Infrastructure Project Management A-07-02 Tammy Rapp Auditor-in-Charge FARM CREDIT ADMINISTRATION Memorandum Office of Inspector General

More information

Assessment of NCTD Program Management Framework for Positive Train Control Program

Assessment of NCTD Program Management Framework for Positive Train Control Program Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation

More information

Vendor Orientation Guide

Vendor Orientation Guide Vendor Orientation Guide Presentation to: Department of Community Health s Contract and Grant Vendors Presented by: Office of Vendor Management Date: September 2014 0 Mission The Georgia Department of

More information

Orlando-Orange County Expressway Authority

Orlando-Orange County Expressway Authority Orlando-Orange County Expressway Authority Right of Way Audit February 2012 Table of Contents Executive Summary 2 Summary Findings 5 Detailed Findings 7 Appendix A Testing Summary 17 Appendix B ROW Metrics

More information

ODIG-AUD (ATTN: Audit Suggestions) Department of Defense Inspector General 400 Army Navy Drive (Room 801) Arlington, VA 22202-4704

ODIG-AUD (ATTN: Audit Suggestions) Department of Defense Inspector General 400 Army Navy Drive (Room 801) Arlington, VA 22202-4704 Additional Copies To obtain additional copies of this report, visit the Web site of the Department of Defense Inspector General at http://www.dodig.mil/audit/reports or contact the Secondary Reports Distribution

More information

Section 7 RFP reference: 7.2.7 Quality Assurance, Page 64

Section 7 RFP reference: 7.2.7 Quality Assurance, Page 64 Section 1 Transmittal Letter Section 2 Introduction (Executive Summary) Section 3 Summary of the Bidder s Understanding of the Project Scope Section 4 Bidder s Products, Methodology, and Approach to the

More information

Innovation and Technology Department

Innovation and Technology Department PERFORMANCE AUDIT Innovation and Technology Department IT Inventory Asset Management January 11, 2016 Office of the City Manager Internal Audit Division Cheryl Johannes, Internal Audit Manager PERFORMANCE

More information

Why are PMO s are Needed on Large Projects?

Why are PMO s are Needed on Large Projects? Why are PMO s are Needed on Large Projects? Keeps Project Manager focused on: Priority risks Priority issues Stakeholder alignment Technical challenges Ensures administrative tasks are completed: Projects

More information

4.06 Consulting Services

4.06 Consulting Services MANAGEMENT BOARD SECRETARIAT AND MINISTRIES OF THE ENVIRONMENT, FINANCE, HEALTH AND LONG-TERM CARE, NATURAL RESOURCES, AND COMMUNITY SAFETY AND CORRECTIONAL SERVICES 4.06 Consulting Services (Follow-up

More information

AN AUDIT OF INTERNAL CONTROL OVER FINANCIAL REPORTING THAT IS INTEGRATED WITH AN AUDIT OF FINANCIAL STATEMENTS:

AN AUDIT OF INTERNAL CONTROL OVER FINANCIAL REPORTING THAT IS INTEGRATED WITH AN AUDIT OF FINANCIAL STATEMENTS: 1666 K Street, NW Washington, D.C. 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8430 www.pcaobus.org STAFF VIEWS AN AUDIT OF INTERNAL CONTROL OVER FINANCIAL REPORTING THAT IS INTEGRATED WITH AN

More information

How To Write A Project Management Plan

How To Write A Project Management Plan Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents

More information

Domain 1 The Process of Auditing Information Systems

Domain 1 The Process of Auditing Information Systems Certified Information Systems Auditor (CISA ) Certification Course Description Our 5-day ISACA Certified Information Systems Auditor (CISA) training course equips information professionals with the knowledge

More information

CREDIT CARDS CALIFORNIA STATE UNIVERSITY, EAST BAY. Audit Report 13-28 June 28, 2013

CREDIT CARDS CALIFORNIA STATE UNIVERSITY, EAST BAY. Audit Report 13-28 June 28, 2013 CREDIT CARDS CALIFORNIA STATE UNIVERSITY, EAST BAY Audit Report 13-28 June 28, 2013 Henry Mendoza, Chair Lupe C. Garcia, Vice Chair Rebecca D. Eisen Steven M. Glazer William Hauck Hugo N. Morales Members,

More information

PHASE 9: OPERATIONS AND MAINTENANCE PHASE

PHASE 9: OPERATIONS AND MAINTENANCE PHASE PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.

More information