1 Data Center Relocation Take One! Joseph E. Ford, RCDD Craig A. Lowe, RCDD/OSP,LEED AP Robert G. Hall, MCSD Bala Consulting Engineers, Inc.
2 Target Enterprise One or more of the following: Data center over about 100 devices Enterprise with 24x7 operations Dealing with life safety or finances Complex applications Growing well and improving IT management to match Setting goals Measuring progress Managing to expectations Smaller DC need less time but the same steps
3 Project Plan Benchmark View Start the Project Build New DC Facility Information Transport System Establish LAN / WAN / SAN Move Equipment / Server Waves Decommission Old DC Close the Project 5%± Project Management View Charter Discover Requirements Design (and Budget) Validation Build / Execute Test Review and Close
4
5
6 Project Charter Establish relationship with champion and PM Select initial core team Kickoff meeting Logistics and meeting schedule Start Project Plan and Presentation
7 Prepare for Data Center Relocation As you do discovery, you will find systems that cannot be moved as they are This is a placeholder for projects that must be monitored to assure they are on track for the move Examples: Eliminate equipment that is too fragile to move (but probably running very important programs that nobody living knows how to support) Systems that depend on hard coded IP addresses that will not transfer to the new Data Center Applications that must be virtualized so they can move electronically
8 Sidebar Projects These are subprojects that may develop in addition to moving equipment These are usually separate because they are funded separately Examples: Confirming that the Operation Center will function as expected Projects to design future changes to be compatible with the new data center
9 Discovery for Facility Establish Inventory of hardware units Extend into power, cooling, and cabling estimate Extrapolate technology and growth changes Add summary to Presentation Client signs off Basis of Design
10 Discovery for Facility Assist with floor plan for cabinets and racks Add floor plan to Presentation Monitor MEPS design process of DC, MDF, IDF, NOC Review fire suppression, security, and environmental design Review new building access for services and docks Add summary to Presentation Help with budget approval(s)
11 Build and Commission Facility Monitor construction schedule Guest internet at new DC Confirm walls, floors, ceilings, electrical, cooling, etc. Commissioning Add summary to Presentation
12
13 Information Transport System Discovery Add connection information to inventory Design Design prototype cabinet(s) for topology modeling Assist in topology decisions Design patch and switch elevations Add prototype and elevations to Presentation Manage bidding and leveling Help with budget and purchase orders
14 Pull Schedule Plan View Single Line Diagram
15 Tray Plan Cabinet Elevations Data Center Plan
16 Information Transport System Build Coordinate schedules for cabinets, racks, trays, UTP and fiber Connect PDU to power strips Confirm demarcation points Test Test inventory and labeling of cables Test switch patching
17 Design WAN LAN SAN & Storage WAN connects other business locations and the two Data Centers LAN and SAN must be operational at both locations If refreshing equipment or changing technology, you may buy new for the new data center Otherwise, you may rent equipment for the old data center so you can move your equipment to the new data center Long lead times for WAN LAN & SAN Communication services New storage equipment may be burned in with the network Design must allow a couple of devices to provide a period of solid service before real hardware waves
18
19 OK Where Are We? HW inventory is verified with power and service connection fields noted Location is chosen and facility changes are underway Service connections are enumerated and ordered Network topology has been selected Information Transport System is at least being designed and is probably out to bid WAN, LAN and SAN design is settled and equipment ordered Cabinets and racks are ordered along with power strips, security and KVM equipment
20 OK Where Are We?
21 What Can Go Wrong From Here? You can shut down critical systems in error You can forget part of a system A piece of equipment may not come up You can lose a truck You can move too much at one time You must know how to connect each device Networks must be ready for applications We must finish discovery and plan a safe move during facility outfitting
22 What Can Go Wrong From Here?
23 Discovery Beyond Hardware Get application blueprinting Match applications to inventory Identify 'Fragile Artifacts Identify unique parts risks Map telephony Check both the routes and detours Walk and ride and walk
24 What s an Application Blue Print? An application centered view of how devices connect and service business transactions Includes: Devices (on inventory) IP addresses and network rules OS/DB versions and patch levels Virtual and physical attributes Recovery and DR concepts
25 Collecting Application Blueprints AppOwner: The Application Owner May be in one of several places in IT or be an internal customer depending on the enterprise Think about who approves scope changes in the application BPT: The BluePrint Team Members from Architecture, Application Development, DBA, SA, networking and business relationship Think about all groups that make a change to install or change an application Think about who will be the scribe Prepare About 2 weeks Identify AppOwner Request an interview AppOwner agrees on resources Invite the team and work out invitation counters Capture Interview (1-4hr) White board Capture data Identify gaps Assign tasks Follow-up (1-2day) BPT documents & formats data BPT creates diagrams Validate BPT sends to interviewee Interviewee reviews diagrams and data sheets (2-3day) Interviewee &BPT reconcile changes SignOff BPT sends proposed diagram and data sheets to AppOwner AppOwner reviews for accuracy (1 week) AppOwner signs off Distribute BPT provides copies to Operations, Application Development, Architecture, and Operations teams Iterations
26 Applications Move Together Cross reference devices and applications Every device should have known applications Every applications devices should be known Reduce unnecessary cross dependency Migrate storage, over time an enterprise tends to develop spider webs of applications sharing resources with each other
27 Design the Actual Relocation Decide on optimal waves size Plan physical and virtual servers in waves Publish the wave plans Arrange for smart hands and movers Assign locations in new DC Assign all patching Print initial copies of documents for waves
28 Rehearsal Design the Waves Make sure players understand the process Include essential services: Domain controller, DNS, etc. Base equipment for a VM farm Low hanging fruit Power and IP (UTP or Fiber) only Test case on each service Complex SAN connections, telephony, unique parts The rest of the story Fragile artifacts, redundant gear, retries But do NOT save the worst for last
29
30 Preparing for a Wave Confirm pre-test compliance Schedule a fix and test OS patches and software upgrades IP address and telephony changes Power down and power up Freeze machine Schedule backup, SA, DBA, testers Confirm core and edge patching Update, print and post (communicate!) Machine sheets, posters, elevations
31 Day of move: Team checks Go/no-go meeting Doing a Wave Weather, emergencies, road blocks, illness, etc. Food Zero hour: Manage war rooms Shared video and telephone conference lines Track every system
32 Doing a Wave - Continued Confirm backups Management approval to power down Ping to confirm down Uncable, unrack, shock sensor, load Loadmaster confirms each truck Unload, check for shocks, rack, patch Power up in sequence Ping to confirm up
33 Wave Need: Machine Sheets One sheet for each device Tape to device early on move day Travels with device Border indicates wave and truck Large print has Make, model and unique identifier Old rack and RTU number New rack and RU number Date truck and bin number Accurate rendition of attachment points Graphic and table of patch information IP patches with color, length and port ILO & console patches with same Fiber patches Power cord length, receptacles and ends Telephone lines Text boxes for overweight or special connections like USB or heartbeats Verified by smart-hands before and after
34 Wave Need: Posters Pull order at old site Mount order at new site Red to green criticality Group lines Post at least two copies Red system out last; in 1 st for shortest down time
35 Wave Need: Elevations New Data Center only Elevations by row posted on each row at new site Color coded by waves (avoid red) Single cabinet strips posted front and rear Current wave white
36 Testing Behind a Wave Confirmation from application test team Regular tests approach 95% accuracy A passed test means no errors were found A failed test might not be a new target flaw Be prepared to think Morning after walk both DC Check power Check patching Check placement Add summary of the wave to Presentation
37 Decommission Old DC and Wrap
38 Decommission Old DC and Wrap Return leased and rented equipment Dispose of other equipment Get leaser sign-off
39 Final Thoughts Use external communications you will move the systems that do your communication Statistics show you will still have about a 1% hardware failure rate reserve your focus for those Testing can give false positives
40
Automating Infrastructure A connectivity perspective for BICSI SEA meeting, November 2011
Automating Infrastructure A connectivity perspective for BICSI SEA meeting, November 2011 Opportunities in Automating Infrastructure Why Automation in Data Center? Tiers, compartments and complexity Work
More informationData Center Management
Data Center Management How Cisco IT Operates, Manages, and Protects Its Data Center A Cisco on Cisco Case Study: Inside Cisco IT 1 Overview The Cisco IT Operations Data Center on the San Jose, California
More informationAdvanced planning / change impact features
IT Inventory, Space and ivity Management Automated diagramming reduces workload and errors Find any device and it s connectivity (LAN/WAN/SAN/Power) quickly Reduce cost and risk of implementing infrastructure
More informationWhat is a Datacenter?
What is a Datacenter? Telecom Room Primarily Cross Connect Equipment and switches. Computer room A room whose primary function is to house computer equipment. (Servers, Storage) 5 or less cabinets Small
More informationUsing Cisco UC320W with Windows Small Business Server
Using Cisco UC320W with Windows Small Business Server This application note explains how to deploy the Cisco UC320W in a Windows Small Business Server environment. Contents This document includes the following
More informationNetworking Systems (10102)
Networking Systems (10102) Rationale Statement: The goal of this course is to help students understand and participate in the significant impact of computer networking in their lives. Virtually any career
More informationOn the Move What you Need to Know When Moving Your Facility
On the Move What you Need to Know When Moving Your Facility Jonathan Jew J&M Consultants, Inc jew@j-and and-m.com 415-292 292-7734 2005 J&M Consultants, Inc. Preparation - Develop Organization Obtain high
More informationCHOOSING A RACKSPACE HOSTING PLATFORM
CHOOSING A RACKSPACE HOSTING PLATFORM Rackspace has years of experience in hosting and has learnt that the unique needs of our customers businesses often determines the level of accountability and project
More informationData Center Cabling Design Trends
Data Center Cabling Design Trends BICSI Regional Meeting Maurice Zetena Fiber Connect Infrastructure Trends Infrastructure Trends Any to All Trunk Cabling Trends: Data Center Infrastructure Media Choice:
More informationTIA-942 Data Centre Standards Overview WHITE PAPER
TIA-942 Data Centre Standards Overview WHITE PAPER TIA-942 Data Centre Standards Overview For the past 20 years, cabling standards have been the cornerstone of ensuring proper design, installation, and
More informationIntraVUE Plug Scanner/Recorder Installation and Start-Up
IntraVUE Plug Scanner/Recorder Installation and Start-Up The IntraVUE Plug is a complete IntraVUE Hardware/Software solution that can plug directly into any network to continually scan and record details
More informationLouisiana State University Information Technology Services (ITS) Frey Computing Services Center Data Center Policy
Louisiana State University Information Technology Services (ITS) Frey Computing Services Center Data Center Policy Access: If you have been granted a Frey Access Card with currently approved access to
More informationOrganizing and Managing Equipment Rooms
Organizing and Managing Equipment Rooms How you organize and maintain your equipment room can be just as important as maintaining the operating systems on the boxes themselves. Although many companies
More informationGigabit Passive Optical
Gigabit Passive Optical Networks Joseph E. Ford, RCDD Systems Specialist Bruce D. Osborn, RCDD Systems Specialist Bala Consulting Engineers, Inc. 1 Overview 2 2 Background 3 GPON Architecture 4 Infrast.
More informationSunGard Availability Services. White Paper Series. Ensuring a Smooth Transition: Guidelines for Successfully. WhitePaper. Migrating Data Centers
SunGard Availability Services White Paper Series Ensuring a Smooth Transition: Guidelines for Successfully WhitePaper Migrating Data Centers Chances are, you don t move a data center every day or even
More informationProposal for Data Center Migration & Logistic Support.
Proposal for Data Center Migration & Logistic Support. 1 Introductions: -----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------Opus
More informationSmart Choice Business Consulting Data Centre Migration Story Board
Smart Choice Business Consulting Data Centre Migration Story Board Introduction A data center relocation can be best described as a controlled disaster that involves high risk and requires a minute to
More informationData Center Visualization Using Visio
Data Center Visualization Using Visio 1. Data Centers and Visualisation 2. Linking Visio to data center management systems 3. Embedding data and hyperlinks into Visio shapes 4. Data Center Space - Floor
More informationCASE STUDY. Case Study #2 Hi-Tech Transportation, Inc Page 1
CASE STUDY Summary: This client made a decision to relocate to a new custom built facility housing corporate offices, a banking branch, their headquarters and a state of the art data center. Plans for
More informationIntroduction. What is a Remote Console? What is the Server Service? A Remote Control Enabled (RCE) Console
Contents Introduction... 3 What is a Remote Console?... 3 What is the Server Service?... 3 A Remote Control Enabled (RCE) Console... 3 Differences Between the Server Service and an RCE Console... 4 Configuring
More informationNext Steps for Federal Data Center Consolidation Initiative
Next Steps for Federal Data Center Consolidation Initiative Presented to: GDI Conference April 28 2011 Creating Value, Delivering Results 2011 eglobaltech Incorporated. Tech, Inc. All rights reserved.
More information1. User Safety Instructions
Please note that this product is an Electromagnetic Compatibility (A-class) device that is meant to benefit a seller or user outside of home-use. It is the sole responsibility of the user to recover any
More informationIP Telephony Management
IP Telephony Management How Cisco IT Manages Global IP Telephony A Cisco on Cisco Case Study: Inside Cisco IT 1 Overview Challenge Design, implement, and maintain a highly available, reliable, and resilient
More informationC24 - Inside the Data Center Andrew J. Luca
C24 - Inside the Data Center Andrew J. Luca Inside the Data Center What an auditor needs to know Course Objectives Understand the looks and feel of a data center Know what to look for and what questions
More informationwww.commscope.com Data Center Topology Guide
www.commscope.com Data Center Topology Guide Data Center Areas 1 Network Operations Center (NOC) The network operations center or NOC is the location where control of all data center networking, server
More informationLEVEL 3 DATA CENTER ASSESSMENT
Nationwide Services Corporate Headquarters 410 Forest Street Marlborough, MA 01752 USA Tel: 800-342-5332 Fax: 508-303-0579 www.eecnet.com LEVEL 3 DATA CENTER ASSESSMENT Submitted by: Electronic Environments
More informationVertical Phone System Upgrades 2014. Scope of Work
Vertical Phone System Upgrades 2014 Scope of Work Project Overview Install new Vertical phone system and phones on site. Complete testing with API helpdesk. Remove old phone system, phones and box up for
More informationFederal Data Center Consolidation Initiative (FDCCI) FAQs May 2012
Federal Data Center Consolidation Initiative (FDCCI) FAQs May 2012 1. What is the Federal Data Center Consolidation Initiative (FDCCI)? The Federal CIO Vivek Kundra established the FDCCI in a memo dated
More information2301.1 Scope: Communications and Electronic Systems addressed in this section include:
Chapter 23 COMMUNICATIONS / ELECTRONIC SYSTEMS SECTION 2301 - GENERAL 2301.1 Scope: Communications and Electronic Systems addressed in this section include: 1. Fire Alarm System 2. Telecommunication and
More informationPolicy Title-Aquia Data Center Operational Policy & Procedure. Policy ID - TSD-ADC001. Version - Version: 1.0. Supersedes Version 1.
Policy Title-Aquia Data Center Operational Policy & Procedure Policy ID - TSD-ADC001 Version - Version: 1.0 Supersedes Version 1.0 Review Date One (1) year from effective date. Policy & Procedure - Provides
More informationANSI/TIA-942 Telecommunications Infrastructure Standards for Data Centers
ANSI/TIA-942 Telecommunications Infrastructure Standards for Data Centers Jonathan Jew jew@j-and and-m.com J&M Consultants, Inc Co-chair TIA TR-42.1.1 data center committee Co-chair BICSI data centers
More informationThe following are general terms that we have found being used by tenants, landlords, IT Staff and consultants when discussing facility space.
The following are general terms that we have found being used by tenants, landlords, IT Staff and consultants when discussing facility space. Terminology: Telco: Dmarc: NOC: SAN: GENSET: Switch: Blade
More informationDocumenting and Managing Infrastructure Connectivity
Documenting and Managing Infrastructure Connectivity David Cuthbertson Square Mile Systems Ltd david.cuthbertson@squaremilesystems.com www.squaremilesystems.com Square Mile Background Develop toolsets,
More informationFUSION R400 RAID USB 3.0
FUSION R400 RAID USB 3.0 1U Rackmount 4-Drive Hardware RAID 5 SATA Storage System with USB 3.0 Interface User s Guide For Windows Contents 1 Fusion R400 RAID USB 3.0 Features 1 2 Drive Installation and
More informationP-2024. Quick Start Guide. VoIP Analog Telephone Adaptor DEFAULT LOGIN. IP Address http://192.168.5.1 Password 1234. Version 3.60 7/2007 Edition 1
P-2024 VoIP Analog Telephone Adaptor Quick Start Guide Version 3.60 7/2007 Edition 1 DEFAULT LOGIN IP Address http://192.168.5.1 Password 1234 Copyright 2007. All rights reserved. Overview Use your P-2024
More informationThe Efficient Data Centre: Space, Power and Cooling
The Efficient Data Centre: Space, Power and Cooling SPS-01 David Palmer Stevens Systems Integrator Manager, PANDUIT 1 the Journey from Coal to the Server 60% Lost through chimney 5-10% distribution loss
More informationSquare Mile Systems Ltd. david.cuthbertson@squaremilesystems.com www.squaremilesystems.com
Webinar Data Center Capacity Management David Cuthbertson, Director Square Mile Systems Ltd david.cuthbertson@squaremilesystems.com www.squaremilesystems.com Capacity Management - Why? 1. Standards have
More informationADC-APC Integrated Cisco Data Center Solutions
Advanced Infrastructure Solution for Cisco Data Center 3.0 Ordering Guide ADC-APC Integrated Cisco Data Center Solutions The evolution of data centers is happening before our eyes. This is due to the
More informationDALLAS INDEPENDENT SCHOOL DISTRICT PURCHASING DEPARTMENT ADDENDUM No. 2 NETWORK ELECTRONICS
DALLAS INDEPENDENT SCHOOL DISTRICT PURCHASING DEPARTMENT ADDENDUM No. 2 REQUEST FOR PROPOSAL NO. BID #TF- 203970 NETWORK ELECTRONICS Amendment to RFP #TF-203970 NETWORK ELECTRONICS The purpose of Addendum
More informationHP StorageWorks 8Gb Simple SAN Connection Kit quick start instructions
HP StorageWorks 8Gb Simple SAN Connection Kit quick start instructions Congratulations on your purchase of the 8Gb Simple SAN Connection Kit. This guide provides procedures for installing the kit components,
More informationH&R Block Complete Data Center Migration A Case Study On Migrating Virtual Machines To A New Data Center
H&R Block Complete Data Center Migration A Case Study On Migrating Virtual Machines To A New Data Center Ron Rosenkoetter Senior Infrastructure Engineer H&R Block About H&R Block The largest consumer tax
More informationCalrec SoundGrid I/O. User Guide
Calrec SoundGrid I/O User Guide 1 TABLE OF CONTENTS 1. Introduction... 3 1.1 About SoundGrid and the Calrec Audio Interface... 3 1.2 Typical Uses... 4 1.3 Native/SoundGrid Comparison Table... 6 2. Hardware
More informationOffice IT Relocation. Chaos or Order? Revision 1.2
Chaos or Order? Revision 1.2 Morris W. Stemp, CPA, MBA Stemp Systems Group 11/1/2012 Office IT Relocation Chaos or Order? Are you planning an office move? Have you considered all the IT issues necessary
More informationSLA. Co-Managed. Do-It-Yourself
SLA Do-It-Yourself Co-Managed Co-Managed Fully Managed Operational Application Support DB Support Storage Planning Capacity planning Change Management Release Management Pro Services Systems Monitoring
More informationInfrastructure Configuration Management Techniques. Neal R. Firth VIZIM Worldwide, Inc.
Infrastructure Configuration Management Techniques Neal R. Firth VIZIM Worldwide, Inc. Agenda Introduction Automating Visio infrastructure diagrams Inventory and connectivity management Impact analysis
More informationState of Ohio Private Cloud Provisioning and De-provisioning Servers
State of Ohio Private Cloud April 28, 2014 Table of Contents 1... 3 1.1 Action or Event that Requires the Procedure... 3 1.2 Goal of the Procedure... 3 2 Provisioning: Procedure Flow and Narrative... 4
More informationContact us for a free consultation today! 630-936-4045 officemove@aie195.com
IT Relocation Schedule Moving offices? Often, relocating your IT infrastructure can be one of the most daunting aspects of the move, and it s also the most critical to business continuity. Servers, PCs,
More informationPackage Contents. D-Link DSN-3200/3400 Installation Guide. DSN-3200/3400 xstack Storage Area Network (SAN) Array. CD-ROM with User Guide.
Package Contents DSN-3200/3400 xstack Storage Area Network (SAN) Array CD-ROM with User Guide Keys Rack mount Rails Power Cables Hardware and Screws 2 If any of the above items are missing, please contact
More informationNetwork Design. Yiannos Mylonas
Network Design Yiannos Mylonas Physical Topologies There are two parts to the topology definition: the physical topology, which is the actual layout of the wire (media), and the logical topology, which
More informationADC Structured Cabling Solutions
ADC Structured Cabling Solutions The highest performing cross-connect system in the world HighBand Wall Mount Patching Solution Reliable, secure and cost effective ADC s HighBand cross connect solution
More informationManaging Change in Critical IT Infrastructure
Managing Change in Critical IT Infrastructure David Cuthbertson Managing Director Square Mile Systems Ltd sarah.bradbury@squaremilesystems.com www.squaremilesystems.com Housekeeping Fire evacuation Toilets
More informationEmerson Smart Firewall
DeltaV TM Distributed Control System Product Data Sheet Emerson Smart Firewall The Emerson Smart Firewall protects the DeltaV system with an easy to use perimeter defense solution. Purpose built for easy
More informationDealing with Thermal Issues in Data Center Universal Aisle Containment
Dealing with Thermal Issues in Data Center Universal Aisle Containment Daniele Tordin BICSI RCDD Technical System Engineer - Panduit Europe Daniele.Tordin@Panduit.com AGENDA Business Drivers Challenges
More informationChapter 15: Advanced Networks
Chapter 15: Advanced Networks IT Essentials: PC Hardware and Software v4.0 1 Determine a Network Topology A site survey is a physical inspection of the building that will help determine a basic logical
More informationStatement of Work. - 1 - Server Migration & Cable Management. Installation Services. Table of Contents. 1.0 Executive Summary. 2.0 Features & Benefits
Installation Services Statement of Work - 1 - Server Migration & Server Migration & Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0 Details of Service
More informationWireless Router Setup Manual
Wireless Router Setup Manual NETGEAR, Inc. 4500 Great America Parkway Santa Clara, CA 95054 USA 208-10082-02 2006-04 2006 by NETGEAR, Inc. All rights reserved. Trademarks NETGEAR is a trademark of Netgear,
More informationDocumentation for data centre migrations
Documentation for data centre migrations Data centre migrations are part of the normal life cycle of a typical enterprise. As organisations expand, many reach a point where maintaining multiple, distributed
More informationHow To Use 1Bay 1Bay From Awn.Net On A Pc Or Mac Or Ipad (For Pc Or Ipa) With A Network Box (For Mac) With An Ipad Or Ipod (For Ipad) With The
1-bay NAS User Guide INDEX Index... 1 Log in... 2 Basic - Quick Setup... 3 Wizard... 3 Add User... 6 Add Group... 7 Add Share... 9 Control Panel... 11 Control Panel - User and groups... 12 Group Management...
More informationMeraki MX50 Hardware Installation Guide
Meraki MX50 Hardware Installation Guide January 2011 Copyright 2010, Meraki, Inc. www.meraki.com 660 Alabama St. San Francisco, California 94110 Phone: +1 415 632 5800 Fax: +1 415 632 5899 Copyright: 2010
More informationTaurus Super-S3 LCM. Dual-Bay RAID Storage Enclosure for two 3.5-inch Serial ATA Hard Drives. User Manual March 31, 2014 v1.2 www.akitio.
Dual-Bay RAID Storage Enclosure for two 3.5-inch Serial ATA Hard Drives User Manual March 31, 2014 v1.2 www.akitio.com EN Table of Contents Table of Contents 1 Introduction... 1 1.1 Technical Specifications...
More informationTenant Managed Services- Basic. Rancho Cordova Data Center. Tenant Guide 2014-08
- Basic Rancho Cordova Data Center Tenant Guide 2014-08 TABLE OF CONTENTS 1 INTRODUCTION... 3 1.1 PURPOSE... 3 2 COMPUTER ROOM GUIDELINES... 4 2.1 GENERAL SITE GUIDELINES... 4 2.2 CABINET GUIDELINES...
More informationPackage Contents. D-Link DSN-3200/3400 Installation Guide. DSN-3200/3400 xstack Storage Area Network (SAN) Array. CD-ROM with User Guide.
Package Contents DSN-3200/3400 xstack Storage Area Network (SAN) Array CD-ROM with User Guide Keys Rack mount Rails Power Cables Hardware and Screws 2 If any of the above items are missing, please contact
More informationHP UPS R1500 Generation 3
HP UPS R1500 Generation 3 Installation Instructions Part Number 650952-001 NOTE: The rating label on the device provides the class (A or B) of the equipment. Class B devices have a Federal Communications
More informationin other campus buildings and at remote campus locations. This outage would include Internet access at the main campus.
DATA CENTER The current Campus Data Center is located within historic Founders Hall which is in a less-than ideal location for a variety of reasons, but is typical of an existing campus IT infrastructure
More informationBuilding a Tier 4 Data Center on a Tier 1 Budget
Building a Tier 4 Data Center on a Tier 1 Budget A Walk Through of TIA-942 Peter P. Charland III, RCDD/NTS/WD, CET RTKL Associates Inc. March 27, 2008 BICSI South Central Region Meeting Denver, CO TIA-942
More informationACME Enterprises IT Infrastructure Assessment
Prepared for ACME Enterprises March 25, 2014 Table of Contents Executive Summary...2 Introduction...2 Background...2 Scope of IT Assessment...2 Findings...2 Detailed Findings for Key Areas Reviewed...3
More informationSmart Cam, CC-Smart-Cam, and Smart Cam Packages Installation and Quick Start Operating Instructions
Smart Cam, CC-Smart-Cam, and Smart Cam Packages Installation and Quick Start Operating Instructions 12/12/2013 FRONT VIEW BACK VIEW TYPICAL PACKAGE 1 Installation Assemble video coupler to the zoom body
More informationU.S. Department of State
U.S. Department of State IT Consolidation Executive Forum October 19, 2010 Cindy Cassil Director, Systems and Integration Office, U.S. Department of State 1 Agenda Department of State Challenge Keys to
More information10/2011 - English Edition 1. Quick Start Guide. NWA1100N-CE CloudEnabled Business N Wireless Access Point
10/2011 - English Edition 1 Quick Start Guide NWA1100N-CE CloudEnabled Business N Wireless Access Point Package Contents - 1 x ZyXEL NWA1100N-CE Access Point - 2 x Detachable Antennas - 1 x Power Adapter
More informationUC Berkeley Data Center Overview
UC Berkeley Data Center Overview Shelton Waggener Associate Vice Chancellor & Chief Information Office shelw@berkeley.edu August 2006 Berkeley s Data Center Opened July 2004 Our Previous Facility (don
More informationIntroduction to IT Infrastructure Components and Their Operation. Balázs Kuti
Introduction to IT Infrastructure Components and Their Operation Balázs Kuti Agenda Challenges faced by enterprises today, scale of the IT plant Diversity of an IT plant Key Server Infrastructure Components
More informationCPEi 800/825 Series. User Manual. * Please see the Introduction Section
CPEi 800/825 Series User Manual * Please see the Introduction Section Contents Introduction...iii Chapter 1: CPEi 800/825 User Guide Overview... 1-1 Powerful Features in a Single Unit... 1-2 Front of the
More informationNetwork Technology (10101)
Network Technology (10101) Rationale Statement: The goal of this course is to help students recognize the significant impact of computer networking in their lives. Virtually any career involves the use
More informationCHAPTER 6 NETWORK DESIGN
CHAPTER 6 NETWORK DESIGN Chapter Summary This chapter starts the next section of the book, which focuses on how we design networks. We usually design networks in six network architecture components: Local
More informationDRO-210i LOAD BALANCING ROUTER. Review Package Contents
DRO-210i LOAD BALANCING ROUTER Review Package Contents Make sure that the package contains the following items. DRO-210i Load Balancing Router 2 Straight Ethernet Cables 1 Cross Over Ethernet Cable 1 Power
More informationCompany Overview. Benefits. Your Business is Our Focus
Company Overview Quonix Networks Inc. is a leading regional provider of hosting, colocation, and managed datacenter services based in the Metro Philadelphia region. The company is focused on delivering
More informationTerms of Reference Microsoft Exchange and Domain Controller/ AD implementation
Terms of Reference Microsoft Exchange and Domain Controller/ AD implementation Overview Maldivian Red Crescent will implement it s first Microsoft Exchange server and replace it s current Domain Controller
More informationHow To Write An Infrastructural Standard For Data Center Infrastructure
Infrastructure Standard for Data Centers ANSI/CSA/EIA/TIA-942 (PN-3-0092) Introduction When approved, the standard will be: ANSI/CSA/EIA/TIA-942 Telecommunications Infrastructure Standard for Data Centers
More informationLab 4.5.2 Diagramming Intranet Traffic Flows
Lab 4.5.2 Diagramming Intranet Traffic Flows Objective Device Designation Device Name Address Subnet Mask Discovery Server Business Services 172.17.1.1 255.255.0.0 R1 FC-CPE-1 Fa0/1 172.17.0.1 Fa0/0 10.0.0.1
More information1. Hardware Installation
4 Port 10/100M Internet Broadband Router with USB Printer server Quick Installation Guide #4824904AXZZ0 1. Hardware Installation A. System Requirement Before you getting started, make sure that you meet
More informationRequest for Proposals Voice over Internet Protocol Unified Communications System 10-2015/2016
Request for Proposals Voice over Internet Protocol Unified Communications System 10-2015/2016 Addendum #2, September 22, 2015 Is there an electronic drawing that shows the system? Attached. What is the
More informationWhat the student will need:
COMPTIA SERVER+: The Server+ course is designed to help the student take and pass the CompTIA Server+ certification exam. It consists of Book information, plus real world information a student could use
More informationRaritan AMS Series Intelligent Electronic Asset Management
Raritan AMS Series Intelligent Electronic Asset Management Quick Setup Guide Thank you for purchasing Raritan AMS asset management sensors (asset sensors), which work with Raritan EMX, PX3TS transfer switches
More informationFacilities Planning and Management. Moving Guide. Table of Contents. Advance planning
Facilities Planning and Management Moving Guide Advance planning Move team Information Technology Services Central Stores Environmental Health and Safety Table of Contents Building Issues Signage Keys/building
More information21 st Century Campus Network Responsibility Matrix 5/26/10
Definitions: DoIT Standards This column details the minimal configuration, which DoIT has defined in order to provide a campus-wide standard level of service. Departments may request services, which exceeds
More informationData Center Build vs. Buy
2014 Data Center Build vs. Buy More information available on our website: /page/whitepapers Data Center Build vs. Buy 2014 When considering colocating your data center, first you must understand your technical
More informationUsing a Fabric Extender with a Cisco Nexus 5000 Series Switch
CHAPTER Using a Fabric Extender with a Cisco Nexus 5000 Series Switch This chapter describes the Cisco Nexus 000 Series Fabric Extenders (FEXs) and includes these sections: Information About, page - Cisco
More informationStarWind iscsi SAN Software: Tape Drives Using StarWind and Symantec Backup Exec
StarWind iscsi SAN Software: Tape Drives Using StarWind and Symantec Backup Exec www.starwindsoftware.com Copyright 2008-2011. All rights reserved. COPYRIGHT Copyright 2008-2011. All rights reserved. No
More informationVirtual Appliance for VMware Server. Getting Started Guide. Revision 2.0.2. Warning and Disclaimer
Virtual Appliance for VMware Server Getting Started Guide Revision 2.0.2 Warning and Disclaimer This document is designed to provide information about the configuration and installation of the CensorNet
More informationDESIGN GUIDELINES. Local Area Network
DESIGN GUIDELINES Local Area Network The total oversight and management responsibilities for information assurance (IA) and protection of DoDEA s critical infrastructure fall under the purview of the DoDEA
More informationBINGO TRAINING. Last Updated August 2014
BINGO TRAINING Last Updated August 2014 Overview The Weekly Sunday Bingo at St John s is by far our greatest money maker. For the 2013-2014 Year, we made close to $225,000 in profit from Bingo. This effort
More informationStruxureWare Data Center Operation Troubleshooting Guide
StruxureWare Data Center Operation Troubleshooting Guide Versions 7.4 and 7.4.5 1. Power Tool Tip Troubleshooting............................................................................ 2 2. Troubleshooting
More informationBeaver Dam Unified School District Request for Proposal Video Surveillance and Door Access Control Systems
Beaver Dam Unified School District Request for Proposal Video Surveillance and Door Access Control Systems The Beaver Dam Unified School District (BDUSD) is requesting proposals from qualified companies
More informationPhysically secure facilities will better protect your computing equipment from theft, vandalism and accidental damage
ITS Service Level Agreement Last Changed: July 31, 2014 Co-Location Service What is Co Location? Co Location is an ITS service that allows departments and researchers at the University of Hawaii to locate
More informationTelecommunications Infrastructure Standard for Data Centers. 802.3 Tutorial
Telecommunications Infrastructure Standard for Data Centers 802.3 Tutorial Prepared by: Jonathan Jew - J&M Consultants and Chris DiMinico - MC Communications - Co-chairs TR42.1.1 TR42: Data Center Standard
More informationSouth Colonie Central School District Server Virtualization and Disaster Recovery Plan
Server Virtualization and Disaster Recovery Plan Prepared by Lucid Solutions Group Table of Contents Executive Summary... 2 Disaster Recovery Overview... 2 Data Corruption, Accidental Deletion and Prevention...
More informationADDENDUM 1 September 22, 2015 Request for Proposals: Data Center Implementation
Following are the questions submitted on or before September 18, 2015, in accordance with RFP specifications. All questions are published verbatim as received, without regard to errors in spelling, punctuation,
More informationData Center Operational Policy
POLICY NAME: Data Center Operational Policy Effective Date: Policy Owner: Policy Number: Related Policies: Purpose: Scope: Policy Statement: Definitions: Responsibilities: The policy will become effective
More informationData Center Colocation - SLA
1 General Overview This is a Service Level Agreement ( SLA ) between and Data Center Colocation to document: The technology services Data Center Colocation provides to the customer The targets for response
More information