1 Teaching Fundamentals of Process Dynamics and Control Using Dynamic Simulator of an Integrated Gasification Combined Cycle (IGCC) plant with CO 2 Capture Debangsu Bhattacharyya 1,2, Richard Turton 1,2 and Stephen E. Zitney 1 1 AVESTAR Center, NETL, Morgantown, WV 2 West Virginia University, Morgantown, WV 1

2 Objectives Use IGCC dynamic simulator and operator training system (OTS) to: o o o o o Demonstrate real life applications of control theory Show students where current course work fits into the process and power plant Demonstrate crucial role that control system plays Demonstrate interactions between different equipment, systems, and variables Provide students with a big picture view, as well as finer details as much as tractable and applicable in about 4 hours of simulator time 2

3 Dynamics and Controls Course at a Glance Course focuses on dynamics and control of chemical processes. Senior year course for Chemical Engineering undergraduates. Currently there are 42 students in this class. Only course to date for the undergraduates concentrating on both process dynamics and control. Linear single input single output (SISO) systems are mostly studied. The control software environment used is in the class is Matlab/Simulink from The Mathworks. The OTS demonstrations make use of DYNSIM dynamic simulation software and InTouch human-machine interface (HMI) software, both from Invensys Operations Management. 3

4

5 AVESTAR TM Center Advanced Virtual Energy Simulation Training And Research Mission: Comprehensive training, education, and R&D on the efficient, safe, and reliable operation of clean energy systems Tools: Dynamic Simulators with Operator Training Systems (OTS) 3D virtual Immersive Training Systems (ITS) Simulators: IGCC w/ CO 2 capture (OTS March 2011, ITS Nov. 2011) Facilities: NETL, WVU/NRCCE in Morgantown, WV Key Partners: Customers: Utilities, E&Cs, Equipment vendors (Engineers, Operators, Trainers, Managers) Universities (Researchers, Students)

6 IGCC Power Plant with CO2 Capture Dynamic Simulator and Operator Training System

7 IGCC with CO 2 Capture Dynamic Simulator Reference Plant (2 Trains) Plant Section Gasification Description Entrained-flow Gasifier Air Separation Elevated-P Cryogenic ASU (95% vol O 2 ) H 2 S Separation Sulfur Recovery CO 2 Separation CO 2 Compression Gas Turbines Steam Cycle Power Output Physical Solvent AGR 1 st Stage Claus Plant Physical Solvent AGR 2 nd Stage Four stage (2200 psia) Adv. F Class (232 MW output each) Subcritical (1,800 psig/1,000ºf/1,000ºf) 746 MW gross (556 MW net) References IGCC Case #2, Cost and Performance Baseline for Fossil Energy Power Plants Study, Volume 1: Bituminous Coal and Natural Gas to Electricity, National Energy Technology Laboratory, DOE/NETL 2010/1397, November 2010.

8 IGCC Dynamic Simulator/OTS Capabilities and Features Simulator Scope Gasification with CO 2 Capture Combined Cycle Electrical System Fuel Switching and Co firing Coal, Petcoke, Biomass High Fidelity Dynamic Model Mulitzonal kinetic reactor models Normal base load operations Startup, shutdown, load following Model Performance Slow (0.5X), real time, fast (2.5X) Multiple dynamic engines running in parallel Operator Features Human-Machine Interface (HMI) Variable and Group Trends Audible and Visual Alarms Instructor Features Initial Condition (IC) and Scenario management Remote Functions (RFs) Malfunctions (Default/Programmed) Trainee Performance Monitor Controls DCS control emulation Regulatory PID control loops Coordinated control Gasifier and Gas turbine lead Partner: Invensys Operations Management; Software: Dynsim, InTouch

9 IGCC Immersive Training System/ITS Capabilities and Features 3D Virtual Plant Model 3D computer aided design (CAD) 3D visualization model Plant photos for photorealism IGCC Puertollano, Spain IGCC Wabash River, IN Coal to Ammonia Coffeyville, KS 3D Immersive Interaction Avatar represents field operator Navigation using game pad Single operator 3D visor with head tracking Multiple operators Projectors/screens (10 ) or 3D LCDs (65 ) with 3D glasses Partner: Invensys Operations Management; Software: EYESim

10 IGCC Dynamic Simulator/OTS and ITS Software Invensys Operations Management Dynsim TM Gasification and CO 2 capture through gas turbine Process controls Dynsim Power TM Steam cycle InTouch TM Human machine interface (HMI) Look and feel of plant DCS operator interface EYESim TM Virtual engines for ITS Sim4Me Executive for integration of dynamic engines Distribution of engines across CPUs for real time performance

11 Demonstration Outlines Course can be broadly divided into two strongly coupled sections: Process Dynamics Process Control OTS will be utilized for better understanding of each of these sections Process Dynamics examples shown here: First principles dynamic model Implementation of ideal forcing functions Time-delay systems Process Control examples shown here: Open-loop unstable systems Closed-loop stability: Proportional gain for stability limits Feedback-augmented feedforward control Cascade control 11

12 Process Dynamics Example 12

13 First Principles Dynamic Model Due to class time constraints, only simple, first principles dynamic models (e.g., CSTR, jacketed vessel, single flash vessel, etc.) can be developed Thus, more complex and interesting process dynamics cannot be captured as these equipment significantly interact with themselves and other equipment in the plant When these equipment items are shown in the dynamic simulator/ots model, students can better understand how these equipment fit into a real plant and how they interact Big picture view as well as smaller details Quick view of plant design, P&ID, and dynamic simulation. Show flowsheet level view followed by equipment level details Example: Gasifier feed and cooling section of an IGCC plant (PFD not shown here due to brevity) 13

14 Gasifier Feed and Cooling Section in IGCC Plant Steady-state process model in PRO/II TM 14

15 Gasifier Feed and Cooling Section in IGCC Plant Process & Instrumentation Diagram Reference DOE/NETL IGCC Dynamic Simulator Research and Training Center, Volume 2: IGCC Process Descriptions, DOE/NETL 2008/1324, June 2008.

16 Dynamic Process Model in Dynsim TM

17 Detailed GasifierModel 17

18 Details of Kinetic Model for One Zone of Multizonal Gasifier Model 18

19 Gasifier Feed and Cooling Section at HMI level

20 Implementation of Ideal Forcing Functions Ideal forcing functions (step, ramp, etc.) are widely discussed and utilized in introductory process dynamics and control classes. Can they be realized in actual plant? If yes, how? Lean solvent flow control valve is stepped up and the flow is monitored. 20

21 Time Delay Systems Show how time-delay occurs in an actual plant Use step response data for identifying process model Coal feed to plant is step decreased Transient response in CO 2 composition at inlet of H 2 S absorber is recorded 21

22 Coal feed/syngas Flow Path Gasifier 22

23 Syngas Flow Path Syngas Scrubber 23

24 Syngas Flow Path Shift Reactors 24

25 Syngas Flow Path Syngas Cooling 25

26 Syngas Flow Path Mercury Removal 26

27 CO 2 Concentration at CO 2 Absorber Inlet 27

28 Process Control Example 28

29 Open Loop Unstable Systems Case 1: Closed-loop system Case 2: Open-loop system, emergency controller takes over Case 3: Open-loop system, No emergency controller, plant shuts down Demonstration example: Radiant Syngas Cooler (RSC) steam generator 29

30 Case 1: Closed loop system : Coal feed-flow is step increased : Demonstrate control loop performance for disturbance rejection : Demonstrate how different systems interact in an actual plant 30

31 Transient Response of RSC Steam Drum Pressure 31

32 Interaction of RSC Steam Drum with Other Systems Main HP Steam Generation System 32

33 HP Steam Header Interaction of RSC Steam Drum with Other Systems 33

34 Case 2: Open-loop system; emergency controller takes over : Plant still operates normally with loss of efficiency : Demonstrate necessity of good design for which dynamic consideration is crucial 34

35 Case 3: Open-loop system; No emergency controller; plant shuts down : Drum level decreases to very low level triggering plant shutdown : Demonstrate other lines of defense - emergency shutdown system 35

36 Closed-loop stability: Proportional Gain for Stability Limits Students carry out closed-loop stability analysis (by Routh stability analysis, direct substitution, etc.) to determine limiting proportional gain for stability of closed-loop system. Demonstration of theory with RSC pressure control by slowly modifying proportional gain. K c =1 K c =3 K c =1 K c =1 K c =3 K c =1 36

37 Feedback augmented Feed Forward Control Demonstrate role of feedforward compensator in improved disturbance rejection characteristics Vary magnitude of disturbance Demonstration example: H 2 S/SO 2 ratio control at inlet of 1 st Claus Reactor; Feedforward H 2 S flow in inlet feed 37

38 Feedback loop: H 2 S/SO 2 ratio at inlet of 1 st Claus Reactor 38

39 Cascade Control Demonstrate role of cascade control for disturbance rejection Modify tuning of inner loop and demonstrate its effect on control loop performance Demonstration example: Selexol Unit Stripper 39

40 Additional Teaching Points Show role of inventory/thermal hold-up in dynamic response, especially its role during plant startup/shutdown Identify typical candidate first order/second order processes from step response data and then analyze them. Carry out stability analysis on identified model. For example, students can calculate required proportional gain based on identified process model and then test on actual process. Determine appropriate tuning parameters based on identified model and then test its performance Demostrate startup/shutdown dynamics and control challenges and many more 40

41 Practical Control Test A few sample questions: 1. Choose any arbitrary flowsheet and any arbitrary controller. What are the input and output of the controller that you have selected? What are the inputs and outputs of the process that you have selected? 2. Draw a block diagram of the closed loop system. 3. Is this system open-loop stable? Why or why not? [Note: you can answer this question theoretically or by carrying out an experiment] 4. What are the disturbance variables(s) for this system? 5. Check the controller performance for servo control. How did you check it? What will you do to improve its performance for servo control further? 6. Check the controller performance for regulatory control. How did you check it? What will you do to improve its performance for regulatory control further? 7. Please note any loop interaction that you have observed while testing the regulatory control. 41

42 Conclusions State-of-the-art, high-fidelity, real-time dynamic simulator and operator training system is used for teaching process dynamics and control to undergraduate chemical engineering students. A few examples are cited. Many other possibilities are being explored. Suggestions are welcome. 42

Presenter: Richard Turton, West Virginia University

Presenter: Richard Turton, West Virginia University Experience in Augmenting the Undergraduate Chemical Engineering Curriculum with OTS and ITS Technology Presenter: Richard Turton, West Virginia University Background West Virginia University is a land

More information

How To Run A Power Plant

How To Run A Power Plant CO 2 Capture at the Kemper County IGCC Project 2011 NETL CO 2 Capture Technology Meeting Kemper County IGCC Overview 2x1 Integrated Gasification Combined Cycle (IGCC) 2 TRansport Integrated Gasifiers (TRIG

More information

Best Practices for Controller Tuning

Best Practices for Controller Tuning Best Practices for Controller Tuning George Buckbee, P.E. ExperTune, Inc. 2009 ExperTune, Inc. Page 1 Best Practices for Controller Tuning George Buckbee, P.E., ExperTune Inc. 2009 ExperTune Inc Summary

More information

054414 PROCESS CONTROL SYSTEM DESIGN. 054414 Process Control System Design. LECTURE 6: SIMO and MISO CONTROL

054414 PROCESS CONTROL SYSTEM DESIGN. 054414 Process Control System Design. LECTURE 6: SIMO and MISO CONTROL 05444 Process Control System Design LECTURE 6: SIMO and MISO CONTROL Daniel R. Lewin Department of Chemical Engineering Technion, Haifa, Israel 6 - Introduction This part of the course explores opportunities

More information

Reliability of IGCC Power Plants

Reliability of IGCC Power Plants Reliability of IGCC Power Plants Gasification Technologies Conference San Francisco, 11 th October 2005 Chris Higman, Syngas Consultants Ltd. Sal DellaVilla, Bob Steele, Strategic Power Systems, Inc Overview

More information

Hybrid Power Generations Systems, LLC

Hybrid Power Generations Systems, LLC Coal Integrated Gasification Fuel Cell System Study Pre-Baseline Topical Report April 2003 to July 2003 Gregory Wotzak, Chellappa Balan, Faress Rahman, Nguyen Minh August 2003 Performed under DOE/NETL

More information

How To Make A Mine Guard Fosil Process

How To Make A Mine Guard Fosil Process UOP Amine Guard TM FS Technology for Acid Gas Removal 2009 UOP LLC. All rights reserved. UOP 5241B-01 Agenda Overview of the Amine Guard FS process UCARSOL TM Solvent characteristics Amine Guard FS flow

More information

Sixth Annual Conference on Carbon Capture & Sequestration

Sixth Annual Conference on Carbon Capture & Sequestration Sixth Annual Conference on Carbon Capture & Sequestration Expediting Deployment of Industrial Scale Systems Geologic Storage - EOR An Opportunity for Enhanced Oil Recovery in Texas Using CO 2 from IGCC

More information

A new motivation and perspective on teaching simulation and design:

A new motivation and perspective on teaching simulation and design: Invensys is now White Paper A new motivation and perspective on teaching simulation and design: Author: Richard Turton, P.E., Ph.D. As Presented at the ASEE conference Copyright ASEE What s Inside: 1.

More information

Liquefied Natural Gas (LNG)

Liquefied Natural Gas (LNG) Graduate Diploma in Petroleum Studies Major in Liquefied Natural Gas (LNG) INDUCTION Launching ceremony Week 39, 2012 Administration / Plant visit / Fundamentals of LNG and LNG main risks awareness Module

More information

COAL GASIFICATION AND CO 2 CAPTURE

COAL GASIFICATION AND CO 2 CAPTURE COAL GASIFICATION AND CO 2 CAPTURE an overview of some process options and their consequences Use this area for cover image (height 6.5cm, width 8cm) Evert Wesker Shell Global Solutions International B.V.

More information

PERFORMANCE EVALUATION OF NGCC AND COAL-FIRED STEAM POWER PLANTS WITH INTEGRATED CCS AND ORC SYSTEMS

PERFORMANCE EVALUATION OF NGCC AND COAL-FIRED STEAM POWER PLANTS WITH INTEGRATED CCS AND ORC SYSTEMS ASME ORC 2015 3rd International Seminar on ORC Power Systems 12-14 October 2015, Brussels, Belgium PERFORMANCE EVALUATION OF NGCC AND COAL-FIRED STEAM POWER PLANTS WITH INTEGRATED CCS AND ORC SYSTEMS Vittorio

More information

stable response to load disturbances, e.g., an exothermic reaction.

stable response to load disturbances, e.g., an exothermic reaction. C REACTOR TEMPERATURE control typically is very important to product quality, production rate and operating costs. With continuous reactors, the usual objectives are to: hold temperature within a certain

More information

Using Wireless Measurements in Control Applications

Using Wireless Measurements in Control Applications Using Wireless Measurements in Control Applications Terry Blevins, Mark Nixon, Marty Zielinski Emerson Process Management Keywords: PID Control, Industrial Control, Wireless Transmitters ABSTRACT Wireless

More information

Applicazione di tecniche di controllo predittivo multivariabile ad impianti di produzione a Ciclo Combinato

Applicazione di tecniche di controllo predittivo multivariabile ad impianti di produzione a Ciclo Combinato MPC of Combined Cycle Power Plants Torna al programma Applicazione di tecniche di controllo predittivo multivariabile ad impianti di produzione a Ciclo Combinato C. Aurora, P. Colombo, F. Pretolani - CESI

More information

Development of Coal Gasification System for Producing Chemical Synthesis Source Gas

Development of Coal Gasification System for Producing Chemical Synthesis Source Gas 27 Development of Coal Gasification System for Producing Chemical Synthesis Source Gas TAKAO HASHIMOTO *1 KOICHI SAKAMOTO *1 KATSUHIRO OTA *2 TAKASHI IWAHASHI *3 YUUICHIROU KITAGAWA *4 KATSUHIKO YOKOHAMA

More information

Capital Cost Scaling Methodology Quality Guidelines for Energy System Studies January 2013 Disclaimer

Capital Cost Scaling Methodology Quality Guidelines for Energy System Studies January 2013 Disclaimer DOE/NETL-341/013113 DOE/NETL-2010/???? Disclaimer This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency

More information

Outlook on Integrated Gasification Combined Cycle (IGCC) Technology

Outlook on Integrated Gasification Combined Cycle (IGCC) Technology The IGCC Process: From Coal To Clean Electric Power Outlook on Integrated Gasification Combined Cycle (IGCC) Technology Testimony of Edward Lowe Gas Turbine-Combined Cycle Product Line Manager General

More information

Simulation of a base case for future IGCC concepts with CO 2 capture

Simulation of a base case for future IGCC concepts with CO 2 capture Simulation of a base case for future IGCC concepts with CO 2 capture Christian Kunze, Hartmut Spliethoff Institute for Energy Systems TU München for 4 th Clean Coal Technology Conference 2009 18 20 May,

More information

Industrial Steam System Process Control Schemes

Industrial Steam System Process Control Schemes Industrial Steam System Process Control Schemes This paper was developed to provide a basic understanding of the different process control schemes used in a typical steam system. This is however a fundamental

More information

The Future of Coal-Based Power Generation With CCS UN CCS Summit James Katzer MIT Energy Initiative web.mit.edu/coal/

The Future of Coal-Based Power Generation With CCS UN CCS Summit James Katzer MIT Energy Initiative web.mit.edu/coal/ The Future of Coal-Based Power Generation With CCS UN CCS Summit James Katzer MIT Energy Initiative web.mit.edu/coal/ 1 Times Are Changing As Yogi Berra said: The Future Ain t What It Used to Be 2 Overview

More information

Sixth Annual Conference on Carbon Capture & Sequestration

Sixth Annual Conference on Carbon Capture & Sequestration Sixth Annual Conference on Carbon Capture & Sequestration Session Title: Retrofitting of Existing Coal-Fired Plants MHI s Post Combustion CO 2 Recovery Process for Coal Fired Power Stations: Requirement

More information

An Update on RTI s Warm Syngas Cleanup Demonstration Project

An Update on RTI s Warm Syngas Cleanup Demonstration Project An Update on RTI s Warm Syngas Cleanup Demonstration Project 2014 Gasification Technologies Council Conference October 28, 2014 David L. Denton RTI International is a trade name of Research Triangle Institute.

More information

HC900 for Boiler Control Applications

HC900 for Boiler Control Applications HC900 for Boiler Control Applications Background Until recent years, only the largest boilers could justify sophisticated boiler controls. Now high fuel costs make it necessary to improve boiler efficiency

More information

MHI Air-Blown IGCC Technology & Application to Chinese Project

MHI Air-Blown IGCC Technology & Application to Chinese Project MHI -Blown Technology & Application to Chinese Project Mitsubishi Blown in Japan November, 2011 Outline of MHI -blown System Gasification / Gas Clean-up Island Produce clean syngas from coal effectively

More information

Impact of coal quality and gasifier technology on IGCC performance

Impact of coal quality and gasifier technology on IGCC performance Impact of coal quality and gasifier technology on IGCC performance Ola Maurstad 1 *, Howard Herzog**, Olav Bolland*, János Beér** *The Norwegian University of Science and Technology (NTNU), N-7491 Trondheim,

More information

Maximization versus environmental compliance

Maximization versus environmental compliance Maximization versus environmental compliance Increase use of alternative fuels with no risk for quality and environment Reprint from World Cement March 2005 Dr. Eduardo Gallestey, ABB, Switzerland, discusses

More information

Siemens Fuel Gasification Technology at a Glance

Siemens Fuel Gasification Technology at a Glance Siemens Fuel Gasification Technology at a Glance Halsbrücker Str. 34 09599 Freiberg Germany Copyright Siemens AG 2008. All rights reserved. SFGT Facilities in Freiberg, Germany 5MW Office 3MW Freiberg

More information

HC900 Boiler Control. Background. Solution. Application Brief Industry: Manufacturing

HC900 Boiler Control. Background. Solution. Application Brief Industry: Manufacturing HC900 Boiler Control Application Brief Industry: Manufacturing Background Until recent years, only the largest boilers could justify sophisticated boiler controls. Now high fuel costs and occasional limited

More information

2014 Software Global Client Conference

2014 Software Global Client Conference SimSci Training Integrating Simulation and Computer Based Training with Learning Management Systems Graham Provost Mobile App: Please take a moment Check into Session by: Select Detailed Schedule Select

More information

SIEMENS technologies compatible with environmental requirements like reduction of CO 2 emissions. ISBF conference. Bratislava, 9-10 February 2009

SIEMENS technologies compatible with environmental requirements like reduction of CO 2 emissions. ISBF conference. Bratislava, 9-10 February 2009 SIEMENS technologies compatible with environmental requirements like reduction of CO 2 emissions ISBF conference Bratislava, 9-10 February 2009 Dr. Heimo Friede CCS: Siemens solutions for the emerging

More information

Tampa Electric Company. Biomass Test Burn Report Polk Power Station Unit 1

Tampa Electric Company. Biomass Test Burn Report Polk Power Station Unit 1 Tampa Electric Company Biomass Test Burn Report Polk Power Station Unit 1 April 2002 1.0 INTRODUCTION...2 2.0 BACKGROUND...2 2.1 BIOMASS FUEL HANDLING...2 2.2 PROCESS DATA COLLECTION...3 2.3 EMISSIONS

More information

RecoPhos Bench Scale Reactor

RecoPhos Bench Scale Reactor RecoPhos Bench Scale Reactor Design and Modelling Andreas Schönberg, Daniel Hariri RecoPhos Demonstration Event February 24th 2015 Content Basic of Development Setup and Design Modelling and Simulation

More information

MHI s Energy Efficient Flue Gas CO 2 Capture Technology and Large Scale CCS Demonstration Test at Coal-fired Power Plants in USA

MHI s Energy Efficient Flue Gas CO 2 Capture Technology and Large Scale CCS Demonstration Test at Coal-fired Power Plants in USA MHI s Energy Efficient Flue Gas CO 2 Capture Technology and Large Scale CCS Demonstration Test at Coal-fired Power Plants in USA 26 MASAKI IIJIMA *1 TATSUTO NAGAYASU *2 TAKASHI KAMIJYO *3 SHINSUKE NAKATANI

More information

Chemical Process Simulation

Chemical Process Simulation Chemical Process Simulation The objective of this course is to provide the background needed by the chemical engineers to carry out computer-aided analyses of large-scale chemical processes. Major concern

More information

ANCILLARY SERVICES SUPPLIED TO THE GRID: THE CASE OF THISVI CCGT POWER PLANT (GREECE)

ANCILLARY SERVICES SUPPLIED TO THE GRID: THE CASE OF THISVI CCGT POWER PLANT (GREECE) Claudio Cavandoli, Alessandro Crippa EDISON S.p.A., Engineering Department ANCILLARY SERVICES SUPPLIED TO THE GRID: THE CASE OF THISVI CCGT POWER PLANT (GREECE) 1 ANCILLARY SERVICES SUPPLIED TO THE GRID:

More information

Carbon Capture. Investment for the Future

Carbon Capture. Investment for the Future Carbon Capture Investment for the Future Doosan Carbon Capture Technologies Oxyfuel 160KWt at Doosan ERTF* ERTF Oxyfuel Conversion 40MWt OxyCoal TM Burner at Doosan CCTF Full Power Plant Demo Expected

More information

Dynamic Simulation Suite

Dynamic Simulation Suite Dynamic Simulation Suite For Simulation and Training Solutions Helping clients rise above the dynamic challenges of designing, controlling, and operating business safely, reliably, and profitably. Dynamic

More information

Performance Monitoring & Optimization

Performance Monitoring & Optimization Performance Monitoring & Optimization Fujairah Water and Power Plant Basic infrastructure like Power and Water production has come into focus due to the rapid growth witnessed in the Middle East. Hybrid

More information

Siemens Power Generation Innovationstrends bei Anlagen und Komponenten in der Energieerzeugung

Siemens Power Generation Innovationstrends bei Anlagen und Komponenten in der Energieerzeugung Siemens Power Generation 2006. All Rights Reserved Siemens Power Generation Innovationstrends bei Anlagen und Komponenten in der Energieerzeugung Nicolas Vortmeyer CTO, Siemens Power Generation Key Drivers

More information

Tips for burner modulation, air/fuel cross-limiting, excess-air regulation, oxygen trim and total heat control

Tips for burner modulation, air/fuel cross-limiting, excess-air regulation, oxygen trim and total heat control Boiler control Tips for burner modulation, air/fuel cross-limiting, excess-air regulation, oxygen trim and total heat control Boilers are often the principal steam or hot-water generators in industrial

More information

Study of a Supercritical CO2 Power Cycle Application in a Cogeneration Power Plant

Study of a Supercritical CO2 Power Cycle Application in a Cogeneration Power Plant Supercritical CO2 Power Cycle Symposium September 9-10, 2014 Pittsburg, Pennsylvania USA Study of a Supercritical CO2 Power Cycle Application in a Cogeneration Power Plant Dr. Leonid Moroz, Dr. Maksym

More information

SOLARPACES: Development of an integrated solar thermal power plant training simulator

SOLARPACES: Development of an integrated solar thermal power plant training simulator SOLARPACES: Development of an integrated solar thermal power plant training simulator Achaz von Arnim 1 and Ralf Wiesenberg 2 1 Dipl.Ing., Business Unit Energy E F IE ST BD, Business Development CSP, Siemens

More information

B0401 Abstract 029 Oral Presentation Session B04 Innovative Applications and Designs - Tuesday, July 1, 2008 16:00 h

B0401 Abstract 029 Oral Presentation Session B04 Innovative Applications and Designs - Tuesday, July 1, 2008 16:00 h Reference System for a Power Plant Based on Biomass Gasification and SOFC Richard Toonssen, Nico Woudstra, Adrian H.M. Verkooijen Delft University of Technology Energy Technology, Process & Energy department

More information

10 Nuclear Power Reactors Figure 10.1

10 Nuclear Power Reactors Figure 10.1 10 Nuclear Power Reactors Figure 10.1 89 10.1 What is a Nuclear Power Station? The purpose of a power station is to generate electricity safely reliably and economically. Figure 10.1 is the schematic of

More information

What Coal Technologies Can Do to Reduce Global CO2 Emission

What Coal Technologies Can Do to Reduce Global CO2 Emission What Coal Technologies Can Do to Reduce Global CO2 Emission December 17, 2014 Hiro Hatada Chief Representative, Washington, DC Office NEDO (New Energy and Industrial Technology Development Organization)

More information

Overview of Integrated Coal Gasification Combined-cycle Technology Using Low-rank Coal

Overview of Integrated Coal Gasification Combined-cycle Technology Using Low-rank Coal 19 Overview of Integrated Coal Gasification Combined-cycle Technology Using Low-rank Coal TAKAO HASHIMOTO *1 KOICHI SAKAMOTO *2 YOSHIKI YAMAGUCHI *3 KOJI OURA *4 KENICHI ARIMA *5 TAKESHI SUZUKI *6 Mitsubishi

More information

Control System Definition

Control System Definition Control System Definition A control system consist of subsytems and processes (or plants) assembled for the purpose of controlling the outputs of the process. For example, a furnace produces heat as a

More information

Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems

Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems Sandra Scalari Enel Ingegneria e Ricerca SpA Copenhagen, May 27-28 th 2014 Enel Presentation Generation Shift & Market in Europe Enel

More information

IGCC Technology Overview & Genoa Site Feasibility EXECUTIVE SUMMARY

IGCC Technology Overview & Genoa Site Feasibility EXECUTIVE SUMMARY IGCC Technology Overview & Genoa Site Feasibility September 3, 2008 Response to March 29, 2008, Vernon Electric Cooperative Resolution In response to the resolution passed at the VEC annual meeting, which

More information

Operator Training Simulators, Immersive Training Simulators, Augmented Reality & Gaming

Operator Training Simulators, Immersive Training Simulators, Augmented Reality & Gaming Operator Training Simulators, Immersive Training Simulators, Augmented Reality & Gaming Author: Janice Abel Principal Consultant ARC Advisory Group jabel@arcweb.com This presentation is copyrighted by

More information

From solid fuels to substitute natural gas (SNG) using TREMP

From solid fuels to substitute natural gas (SNG) using TREMP From solid fuels to substitute natural gas (SNG) using TREMP Topsøe Recycle Energy-efficient Methanation Process Introduction Natural gas is a clean, environmentally friendly energy source and is expected

More information

Making Coal Use Compatible with Measures to Counter Global Warming

Making Coal Use Compatible with Measures to Counter Global Warming Making Use Compatible with Measures to Counter Global Warming The J-POWER Group is one of the biggest coal users in Japan, consuming approximately 2 million tons of coal per year at eight coal-fired power

More information

FULL ELECTRICAL LNG PLANTS: HIGHEST AVAILABILITY AND ENERGY EFFICIENCY THROUGH OVERALL SYSTEM DESIGN

FULL ELECTRICAL LNG PLANTS: HIGHEST AVAILABILITY AND ENERGY EFFICIENCY THROUGH OVERALL SYSTEM DESIGN FULL ELECTRICAL LN PLANTS: HIHEST AVAILABILITY AND ENERY EFFICIENCY THROUH OVERALL SYSTEM DESIN Dr. Edwin Lerch Siemens A Infrastructure and Cities Sector, IC S SE PTI, ermany Phone: 49-9131-7-34052 Fax:

More information

System Assessment Capabilities for Fossil Fuel Power Stations

System Assessment Capabilities for Fossil Fuel Power Stations System Assessment Capabilities for Fossil Fuel Power Stations Technical Services LifeCycle Advantage Educational Services Consulting Technology Advantage The mission of Flowserve Technical Services is

More information

How To Make A Carbon Capture Plant Workable

How To Make A Carbon Capture Plant Workable IEA MOST Workshop: Advances in deployment of fossil fuel technology Beijing June 25, 2014 US DOE National Carbon Capture Center Power Systems Development Facility (PSDF) started combustion testing June

More information

Brief history of and introduction to process control

Brief history of and introduction to process control Brief history of and introduction to process control Flavio Manenti CMIC Giulio Natta Dept. Evolution of control theory 2 300 BC 1769 1868 A float regulator was employed by ancient Greece for the water

More information

Comparison of Pratt and Whitney Rocketdyne IGCC and Commercial IGCC Performance

Comparison of Pratt and Whitney Rocketdyne IGCC and Commercial IGCC Performance Comparison of Pratt and Whitney Rocketdyne IGCC and Commercial IGCC Performance DOE/NETL-401/062006 Final Report June 2006 Disclaimer This report was prepared as an account of work sponsored by an agency

More information

SKI Coal Gasification Technology. Feb. 23, 2012

SKI Coal Gasification Technology. Feb. 23, 2012 SKI Coal Gasification Technology Feb. 23, 2012 1 Contents Overview of SK Organization Coal SKI Coal Gasification Technology 2 SK Group [ Sales ] Unit: USD Billion SK Telecom SK C&C SK Broadband SK Telesys

More information

CO 2 Regulation and Electricity Pricing

CO 2 Regulation and Electricity Pricing CO 2 Regulation and Electricity Pricing Stefan Reichelstein Graduate School of Business Stanford University September 2011 Introduction CO 2 Regulations Existing and proposed regulations of CO 2 emissions

More information

Performance and costs of power plants with capture and storage of CO 2

Performance and costs of power plants with capture and storage of CO 2 ARTICLE IN PRESS Energy 32 (2007) 1163 1176 www.elsevier.com/locate/energy Performance and costs of power plants with capture and storage of CO 2 John Davison IEA Greenhouse Gas R&D Programme, Orchard

More information

Dynamic Behavior of BWR

Dynamic Behavior of BWR Massachusetts Institute of Technology Department of Nuclear Science and Engineering 22.06 Engineering of Nuclear Systems Dynamic Behavior of BWR 1 The control system of the BWR controls the reactor pressure,

More information

Degree programme in Automation Engineering

Degree programme in Automation Engineering Degree programme in Automation Engineering Course descriptions of the courses for exchange students, 2014-2015 Autumn 2014 21727630 Application Programming Students know the basis of systems application

More information

Introduction to Performing a Techno-Economic Analysis for Power Generation Systems

Introduction to Performing a Techno-Economic Analysis for Power Generation Systems Introduction to Performing a Techno-Economic Analysis for Power Generation Systems James C. Fisher II Office of Program Performance and Benefits Date: 06/23/2015 National Energy Technology Laboratory Text

More information

The Technology and Business of Power Andrew Valencia, P.E. Lower Colorado River Authority

The Technology and Business of Power Andrew Valencia, P.E. Lower Colorado River Authority The Technology and Business of Power Andrew Valencia, P.E. Lower Colorado River Authority 1 2 What is Efficiency? Efficiency: What you get divided by what you pay for Heatrate is a measure of plant efficiency

More information

Alain Nifenecker - General Electric Manager Controls Engineering

Alain Nifenecker - General Electric Manager Controls Engineering GE Energy Benefits of Integrating a Single Plant-Wide Control System Into a Standard Plant Design Philosophy Authors: Luis Cerrada Duque - Empresarios Agrupados Director of I&C Department Charles Weidner

More information

Combined Cycle Control Overview

Combined Cycle Control Overview Combined Cycle Control Overview Introduction The Combined Cycle (CC) solution provides for the control and monitoring of a typical CC power plant in a cost effective, preengineered package. Basic Architecture

More information

Evaluation Of Hybrid Air- Cooled Flash/Binary Power Cycle

Evaluation Of Hybrid Air- Cooled Flash/Binary Power Cycle INL/CON-05-00740 PREPRINT Evaluation Of Hybrid Air- Cooled Flash/Binary Power Cycle Geothermal Resources Council Annual Meeting Greg Mines October 2005 This is a preprint of a paper intended for publication

More information

Comparisons of Environmental Quality, Performance and Economics of Clean Coal Technologies for Carbon Capture

Comparisons of Environmental Quality, Performance and Economics of Clean Coal Technologies for Carbon Capture Technical Paper Comparisons of Environmental Quality, Performance and Economics of Clean Coal Technologies for Carbon Capture M. O Donnell The Babcock & Wilcox Company Barberton, Ohio, U.S.A. S. Provol

More information

Viresco Energy s Advanced Gasification Technology

Viresco Energy s Advanced Gasification Technology Viresco Energy s Advanced Gasification Technology Arun Raju, Director of Research Viresco Energy, LLC arun.raju@virescoenergy.com Presentation Outline 2 Introduction to Viresco Energy Gasification Technology

More information

Gasification of Solid Waste: Is this the recipe for trash to treasure?

Gasification of Solid Waste: Is this the recipe for trash to treasure? Gasification of Solid Waste: Is this the recipe for trash to treasure? Northwest CERT Darren D. Schmidt, P.E. April 27, 2006 Waste to Energy (WTE) Technologies Incineration Gasification Pyrolysis Proven,

More information

Tampa Electric Company Polk Power Station IGCC Project Project Status

Tampa Electric Company Polk Power Station IGCC Project Project Status Tampa Electric Company Polk Power Station IGCC Project Project Status Presented at: 1998 Gasification Technologies Conference San Francisco, California October 4-7, 1998 Authors: John E. McDaniel (Speaker)

More information

4 th EU Sout Africa Clean Coal Working Group Meeting

4 th EU Sout Africa Clean Coal Working Group Meeting 4 th EU Sout Africa Clean Coal Working Group Meeting Hybrid Concentrated Solar Power (CSP) Concept Case Study for the Medupi Power Stationy Falk Hoffmeister Head of Sales and Business Development. Dr.

More information

Yokogawa in the Midstream Industry

Yokogawa in the Midstream Industry Yokogawa in the Midstream Industry Natural Gas Gathering and Processing CEO Cognitive Enterprise Optimization Yokogawa Delivers Value Chain Excellence Value Chain Excellence... Midstream Natural Gas Gathering

More information

C. starting positive displacement pumps with the discharge valve closed.

C. starting positive displacement pumps with the discharge valve closed. KNOWLEDGE: K1.04 [3.4/3.6] P78 The possibility of water hammer in a liquid system is minimized by... A. maintaining temperature above the saturation temperature. B. starting centrifugal pumps with the

More information

The Benefits of using Dynamic Simulation and Training Systems for expanding Operator Knowledge and Understanding

The Benefits of using Dynamic Simulation and Training Systems for expanding Operator Knowledge and Understanding The Benefits of using Dynamic Simulation and Training Systems for expanding Operator Knowledge and Understanding Abstract Dynamic Simulation and Operator Training Systems (OTS) have been available in the

More information

Turbine Controls Update

Turbine Controls Update Turbine Controls Update David Cicconi, Business Development Manager Emerson Process Management Power & Water Solutions Define Project Scope and Objectives Address obsolescence Best solution for new operational

More information

Dr. Yeffry Handoko Putra, S.T., M.T

Dr. Yeffry Handoko Putra, S.T., M.T Tuning Methods of PID Controller Dr. Yeffry Handoko Putra, S.T., M.T yeffry@unikom.ac.id 1 Session Outlines & Objectives Outlines Tuning methods of PID controller: Ziegler-Nichols Open-loop Coon-Cohen

More information

Pressurized Water Reactor B&W Technology Crosstraining Course Manual. Chapter 9.0. Integrated Control System

Pressurized Water Reactor B&W Technology Crosstraining Course Manual. Chapter 9.0. Integrated Control System Pressurized Water Reactor B&W Technology Crosstraining Course Manual Chapter 9.0 Integrated Control System TABLE OF CONTENTS 9.0 INTEGRATED CONTROL SYSTEM... 1 9.1 Introduction... 1 9.2 General Description...

More information

Emulated Digital Control System Validation in Nuclear Power Plant Training Simulators

Emulated Digital Control System Validation in Nuclear Power Plant Training Simulators Digital Control System Validation in Nuclear Power Training s Gregory W. Silvaggio Westinghouse Electric Company LLC silvaggw@westinghouse.com Keywords: Validation, nuclear, digital control systems Abstract

More information

Enhancing Process Control Education with the Control Station Training Simulator

Enhancing Process Control Education with the Control Station Training Simulator Enhancing Process Control Education with the Control Station Training Simulator DOUG COOPER, DANIELLE DOUGHERTY Department of Chemical Engineering, 191 Auditorium Road, Room 204, U-222, University of Connecticut,

More information

The Piping System Model a New Life Cycle Document. Elements of the Piping System Model

The Piping System Model a New Life Cycle Document. Elements of the Piping System Model Piping System Model as a Life Cycle Document White Paper Introduction When designing piping systems, a variety of documents are created providing the details necessary to design, purchase, build, and test

More information

GENERATION TECHNOLOGY ASSESSMENT

GENERATION TECHNOLOGY ASSESSMENT SPO PLANNING ANALYSIS GENERATION TECHNOLOGY ASSESSMENT Technology Cost & Performance Milestone 2 Public Technical Conference OCTOBER 30, 2014 NOTE: ALL IRP MATERIALS ARE PRELIMINARY & SUBJECT TO CHANGE

More information

Michael Williams Gasification Technologies Council, 28 th October 2014. Smaller scale Fischer-Tropsch enables biomass-to-liquids

Michael Williams Gasification Technologies Council, 28 th October 2014. Smaller scale Fischer-Tropsch enables biomass-to-liquids Michael Williams Gasification Technologies Council, 28 th October 2014 Smaller scale Fischer-Tropsch enables biomass-to-liquids Velocys The company at the forefront of smaller scale GTL and BTL Leader

More information

SULFURIC ACID MIST PERFORMANCE TEST PROTOCOL. Duke Energy Florida, Inc. Crystal River Power Plant Units 4&5 Crystal River, Citrus County, Florida

SULFURIC ACID MIST PERFORMANCE TEST PROTOCOL. Duke Energy Florida, Inc. Crystal River Power Plant Units 4&5 Crystal River, Citrus County, Florida SULFURIC ACID MIST PERFORMANCE TEST PROTOCOL Duke Energy Florida, Inc. Crystal River Power Plant Units 4&5 Crystal River, Citrus County, Florida August 2013 CONTENTS SECTION 1.0 INTRODUCTION...3 SECTION

More information

Dow Solvent Technologies for CO 2 Removal

Dow Solvent Technologies for CO 2 Removal Dow Oil & Gas Jan Lambrichts AIChE Netherlands / Belgium Section 21 January 2014 Novotel, Antwerp Dow Solvent Technologies for CO 2 Removal Who We Are Dow combines the power of science and technology to

More information

Reliability Modeling Software Defined

Reliability Modeling Software Defined Reliability Modeling Software Defined Using Titan Reliability Modeling Software May 30, 2014 Prepared by: The Fidelis Group 122 West Way, Suite 300 Lake Jackson, TX 77566 Fidelis Group, LLC All Rights

More information

Jump Start: Aspen HYSYS Dynamics V7.3

Jump Start: Aspen HYSYS Dynamics V7.3 A Brief Tutorial (and supplement to training and online documentation) Glenn Dissinger, Product Director, Aspen Technology, Inc. Julie Levine, Associate Product Marketing Professional, Aspen Technology,

More information

ARC WHITE PAPER. The Business Value Proposition of Control in the Field THOUGHT LEADERS FOR MANUFACTURING, ENERGY, & SUPPLY CHAIN NOVEMBER 2009

ARC WHITE PAPER. The Business Value Proposition of Control in the Field THOUGHT LEADERS FOR MANUFACTURING, ENERGY, & SUPPLY CHAIN NOVEMBER 2009 ARC WHITE PAPER By ARC Advisory Group NOVEMBER 2009 The Business Value Proposition of Control in the Field Executive Overview... 3 Control in the Field Provides Enhanced Process Integrity... 5 Testing

More information

A Novel Storage Technology Opens New Opportunities for CSP

A Novel Storage Technology Opens New Opportunities for CSP A Novel Storage Technology Opens New Opportunities for CSP Reuel Shinnar Dept. of Chemical Engineering The City College of The City University of New York The Future of CSP CSP is at presently the only

More information

IDEAS tutor Simulator training for industrial processes

IDEAS tutor Simulator training for industrial processes IDEAS tutor Simulator training for industrial processes www.andritz.com We accept the challenge! The challenge: To train your operators on a process safely and expertly The solution: Simulate. Train. And

More information

Integrated Modeling of Carbon Management Technologies for Electric Power Systems. Some Questions to be Addressed

Integrated Modeling of Carbon Management Technologies for Electric Power Systems. Some Questions to be Addressed Integrated Modeling of Carbon Management Technologies for Electric Power Systems Edward S. Rubin and Anand B. Rao Department of Engineering & Public Policy Carnegie Mellon University July 20, 2000 Some

More information

QNET Experiment #06: HVAC Proportional- Integral (PI) Temperature Control Heating, Ventilation, and Air Conditioning Trainer (HVACT)

QNET Experiment #06: HVAC Proportional- Integral (PI) Temperature Control Heating, Ventilation, and Air Conditioning Trainer (HVACT) Quanser NI-ELVIS Trainer (QNET) Series: QNET Experiment #06: HVAC Proportional- Integral (PI) Temperature Control Heating, Ventilation, and Air Conditioning Trainer (HVACT) Student Manual Table of Contents

More information

FAST METHODS FOR SLOW LOOPS: TUNE YOUR TEMPERATURE CONTROLS IN 15 MINUTES

FAST METHODS FOR SLOW LOOPS: TUNE YOUR TEMPERATURE CONTROLS IN 15 MINUTES FAST METHODS FOR SLOW LOOPS: TUNE YOUR TEMPERATURE CONTROLS IN 15 MINUTES Michel Ruel P.E. President, TOP Control Inc 4734 Sonseeahray Drive 49, Bel-Air St, #103 Hubertus, WI 53033 Levis Qc G6W 6K9 USA

More information

Lambda Tuning the Universal Method for PID Controllers in Process Control

Lambda Tuning the Universal Method for PID Controllers in Process Control Lambda Tuning the Universal Method for PID Controllers in Process Control Lambda tuning gives non-oscillatory response with the response time (Lambda) required by the plant. Seven industrial examples show

More information

White Paper. Immersive Virtual Reality Plant. A Comprehensive Plant-Crew Training Solution Improves Process Reliability and Safety.

White Paper. Immersive Virtual Reality Plant. A Comprehensive Plant-Crew Training Solution Improves Process Reliability and Safety. Invensys is now White Paper Immersive Virtual Reality Plant Authors: Maurizio Rovaglio, Vice President, Solutions Services, Invensys Tobias Scheele, Vice President/ GM Advanced Applications, Invensys What

More information

Virtual Reality Training Program A Comprehensive Plant Crew Training Solution Improving Process Reliability and Safety

Virtual Reality Training Program A Comprehensive Plant Crew Training Solution Improving Process Reliability and Safety Virtual Reality Training Program A Comprehensive Plant Crew Training Solution Improving Process Reliability and Safety Co-Authors: Maurizio Rovaglio, Tobias Scheele, Norbert Jung Invensys Operations Management

More information

SCADA. The Heart of an Energy Management System. Presented by: Doug Van Slyke SCADA Specialist

SCADA. The Heart of an Energy Management System. Presented by: Doug Van Slyke SCADA Specialist SCADA The Heart of an Energy Management System Presented by: Doug Van Slyke SCADA Specialist What is SCADA/EMS? SCADA: Supervisory Control and Data Acquisition Retrieves data and alarms from remote sites

More information

John Bøgild Hansen, Haldor Topsøe. Energinet.dk s VE gas dag 2011 En industriaktørs synspunkter

John Bøgild Hansen, Haldor Topsøe. Energinet.dk s VE gas dag 2011 En industriaktørs synspunkter John Bøgild Hansen, Haldor Topsøe Energinet.dk s VE gas dag 2011 En industriaktørs synspunkter Topsoe SynGas Technologies Oryx GTL, Qatar 34,000 bbl/d 2000 TPD Methanol Plant Synthesis Gas Ammonia Hydrogen

More information

Estimating Future Costs of CO 2 Capture Systems

Estimating Future Costs of CO 2 Capture Systems Estimating Future Costs of Capture Systems Edward S. Rubin Department of Engineering and Public Policy Carnegie Mellon University Pittsburgh, Pennsylvania 8th International Capture Network Workshop Austin,

More information