1 Technical Bulletin Corporate: P.O. Box 397 Fortson Georgia FAX Technical: FAX MW# Topic: Stucco Cracking Stucco is a field mixed and applied product. Sourcing can vary from a Master Wall One Coat Stucco (OCS), Master Wall Cemplaster Stucco or traditional stucco, which is a mixture of cement, sand and lime and a Master Wall Superior Finish. While all stuccos are manufactured with quality materials, even the best mixed and applied stucco can crack from time to time. This bulletin explores some of the various causes and strategies for minimizing cracking in stucco. Like any construction project, there are several factors involved including the owner s expectations, basic stucco design, project scheduling & construction, shrinkage cracks and structural cracking. All have a bearing on the quality of the finished project. Owner s Expectations Some owner s expect the best. In stucco that would mean a very smooth looking project with very minimal cracking, if any. Specifiers and applicators can be prepared to deliver with an improved stucco, which would include Stucco co Ad-Liquid Liquid, a second reinforced base coat using F&M, MBB or F&M Plus and Standard Mesh, Primecoat, and a Superior Elastomeric Finish. Lesser stucco systems can still perform extremely well, but the owner or architect needs to fully describe the expectations and the degree of quality required. Disclaimer This Technical Bulletin is published for general informational purposes only and is not intended to imply that these are the only materials, procedures, or methods, which are available or suitable. The products and manufacturer trade names and product use are believed reliable and not guaranteed. Materials, procedures, or methods may vary according to the particular circumstances, local building code requirements, design conditions, or statutory and regulatory requirements. While the information in this Technical Bulletin is believed to be accurate and reliable, it is presented without guarantee or responsibility on the part of Master Wall Inc Master Wall Inc. Page 1 of 6 6/05
2 Basic Stucco Design There are two basic standards for stucco, ASTM C926, Standard Specification for Application of Portland Cement-Based Plaster and ASTM C1063, Standard Specification for Installation of Lathing and Furring to Receive Interior and Exterior Portland Cement- Based Plaster. These publications are available from the American Society for Testing and Materials ( Parge coats may be applied directly to clean, unpainted concrete and masonry according to this standard. More commonly, stucco is applied over a sheathing, which requires the use of control joints These joints help to control the cracking in stucco. In general, the following guidelines apply for stucco over sheathing: A. Structural 1. Design for maximum allowable system deflection, normal to the plane of the wall, of L/ Design wall assembly for wind load in conformance with code requirements. B. Moisture Control Prevent the accumulation of water into or behind the Portland cement-based plaster (stucco), either by condensation or leakage into the wall construction, in the design and detailing of the wall assembly. a. Provide corrosion resistant flashing to direct water to the exterior where it is likely to penetrate components in the wall assembly, including, above window and door heads, beneath window and door sills, at roof/wall intersections, decks, abutments of lower walls with higher walls, above projecting features, and at the base of the wall. b. Wall System Design design wall to eliminate vapor condensation within the wall assembly. c. Weather Resistant Barrier Provide a barrier over framed construction consisting of a minimum of one (International Residential Code) to two-layers (International Building Code) asphalt felt meeting ASTM D-226, Type 1, Grade D or building code-approved alternate. Verify requirements with local building code authority. 1. Protect sills of rough openings with water resistant barrier or peel and stick type membranes recognized by local codes. Where casing bead is used back-to-back at expansion joints back joints with barrier membrane. Refer to Master Wall details. 2. Slope sills and other areas a minimum of 1:2 to shed water. 2
3 C. Grade Condition 1. Keep stucco a minimum of 6 to 8 above grade in framed construction (varies by Code). D. Aesthetic Projections 1. Aesthetic projections may be formed out of stucco or EPS Foam. Slope all projections a minimum of 1:2 to shed water. Follow local code guidelines for the installation of foam plastic insulation (maximum 4 thick). E. Expansion Joints 1. Provide expansion joints where directed by the design professional. Common locations include the following: A. Where building movement is anticipated. B. At dissimilar substrates. C. At floor lines in certain wood framed constructions. D. Where the stucco meets dissimilar materials. 2. Expansion joint design depends upon the anticipated movement. Master Wall suggests the following minimum sizes, subject to design acceptance and detailing: Windows/Doors 3/8, Building Expansion/Dissimilar Substrates & Materials ½, Floor Line (shrinkage) ¾. F. Control Joints 1. Provide control joints where directed by the design professional. Common locations include the following: A. To limit cracking in the system at a maximum area of 144 ft 2 (13.4 m 2 ). B. Length to width ratio should not be more than 2.5:1. C. At dissimilar substrates. 2. Increase joint requirements where thicker stucco or special structural conditions exist. 3. Typically control joints are tied to the metal lath, which is cut to make two discontinuous slabs. 4. When stucco is bonded to a solid substrate such as concrete or masonry the control joint requirements may be revised. Control joints may be aligned with any control joints in the plaster base. G. Sealing or caulking of V-grooves, exposed ends, and edges of plaster panels exterior work to prevent entry of water shall be provided by sealant trades (07920). H. The designer shall indicate location of joints, accessories and accessory type on architectural drawings. 3
4 Project Scheduling & Construction Scheduling and construction has a bearing on the amount of stucco cracking. Preferably, the stucco should be installed near the end of the project for best results. Builders should look to correct the following conditions prior to the application of stucco: Build on a solid foundation and verify that site has proper compaction prior to stucco application. Make sure carpenters install outside framing members crown out for a consistent, even wall. Make sure the straightest framing members are used where cabinets are placed Verify that wood panels are properly spaced to allow for structural, thermal or seasonal movement (generally 1/8 to 1/4 gap). Refer to the APA publication, Installation of Stucco Exterior Finish Over Structural Wood Panel Wall Sheathing at Make sure a proper gap in the sheathing is provided at the floor lines for crossgrain shrinkage, if required. Please reference Technical Bulletin MW# for additional considerations. At the very least, load the home or building with drywall prior to stucco application. Preferably have the drywall installed as nailing or screwing can affect the stucco. Load home or building with roofing materials prior to lath application. Have cabinets on outside walls installed prior to stucco application. Shrinkage Cracking Shrinkage Cracking Shrinkage cracks, commonly called hairline, eggshell or check cracks are usually caused when the stucco cures or dries quickly. Rapid drying under hot or windy days also contributes to the problem. 4
5 These small cracks are generally less than 1/16 wide and can be somewhat normal for stucco. The small cracks are usually covered with a Master Wall Superior Finish or Superior Elastomeric Finish, which is designed specifically for stucco hairline cracks. Obviously, hairline cracks that occur after the finish is applied will show up in the finish. Hairline cracks are rarely a major source of water entry for properly designed stucco walls. Beyond the design basics, there are several strategies to reduce the amount of hairline cracks in a wall. They can include the following: Fog the wall during hot or windy conditions. See Technical Bulletin MW# for specific recommendations. Let the stucco cure a minimum of seven days or until the stucco is clean, dry and hard. Add Master Wall Stucco Ad-Liquid to the stucco mix. This acrylic modifier forms a film that helps reduce cracking and strengthens the stucco mix. It also eliminates the need to fog the wall if the levels are high enough. Add fibers to the traditional stucco. Cemplaster and Master Wall One Coat Stucco both have fibers for better crack resistance. Add a leveling base coat and mesh to the stucco. Using either F&M, MBB or F&M Plus and Standard Mesh will not only help level the surface, but it will cover and reinforce any hairline cracks. Use Superior Elastomeric Finish over the hairline cracks. This product is designed to bridge minor hairline cracks in the stucco. 5
6 Structural Cracking Stress transferrred to the stucco often results in structural cracking. These cracks are a direct result of some external force placed on the stucco. Determining the exact cause of the cracking may require the involvement of a stucco expert or engineer and may include the following conditions: Ground or foundation movement Earthquakes Structural or frame movement Point Loads Green Lumber Wood panel expansion due to improper gapping Structural, mechanical or other movement Wind loads that exceed design Excessive deflection In summary, even the best applied stucco can crack. A thorough review of the owner s expectations tempered with good design, application and construction will minimize cracking issues. For any specific concerns please contact Master Wall Technical Services at
THIRD PARTY INSPECTION GUIDELINES FOR OWNERS AND GENERAL CONTRACTORS/CONSTRUCTION MANAGERS DS150
THIRD PARTY INSPECTION GUIDELINES FOR OWNERS AND GENERAL CONTRACTORS/CONSTRUCTION MANAGERS DS150 SECTION ONE A. Objective The objective of this guide is to provide Owners and General Contractors/Construction
More informationThe Minnesota Lath and Plaster Bureau Repairing Cracks in Stucco
The Minnesota Lath and Plaster Bureau Repairing Cracks in Stucco Disclaimer: This guide contains general information on stucco installation and related materials. It is provided as a guide only and is
More informationENERGY STAR Qualified New Homes Thermal Enclosure Checklist. Water Management Checklist. Eli Caudill
ENERGY STAR Qualified New Homes Thermal Enclosure Checklist & Water Management Checklist Eli Caudill ENERGY STAR Version 3 Tighter Standards Whole Home Approach Better, More Sustainable Construction Surpasses
More informationGigaCrete Specification PlasterMax
GigaCrete Inc. 6775 Speedway Blvd. Suite M105 Las Vegas, NV 89115 Ph (702) 643-6363 Fax (702) 643 1453 www.gigacrete.com GigaCrete Specification PlasterMax PlasterMax : Fire Rated Plaster for Direct Application
More informationLEGACY REPORT. www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council RETAINED ON U.S.
ICC-ES Legacy Report ER-5043* Reissued March 2004 www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council Legacy report on the 1997 Uniform Building Code DIVISION: 09
More informationINSTALLATION INSPECTION GUIDE FOR 3RD PARTY INSPECTORS FOR PAREX USA EXTERIOR INSULATION AND FINISH SYSTEMS
INSTALLATION INSPECTION GUIDE FOR 3RD PARTY INSPECTORS FOR PAREX USA EXTERIOR INSULATION AND FINISH SYSTEMS Introduction This inspection guide is organized to follow the EIF System's Installation Guide.
More informationNCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)
NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:
More informationAsphalt Shingle Application Requirements
Alberta Allied Roofing Association Asphalt Shingle Application Requirements Section 1 Roof Decks 1.1 General Asphalt Shingles are not permitted to be installed directly over rigid insulation. When Asphalt
More information2.18 INTERIOR & EXTERIOR FINISHES 2.18.1 VAPOR & AIR BARRIERS
2.18 INTERIOR & EXTERIOR FINISHES 2.18.1 VAPOR & AIR BARRIERS The LOGIX wall assembly has no need for an additional vapor barrier, the solid concrete core covered with the low permeance EPS (Type II) foam
More informationGreenGuard Housewrap Installation Guide
000768PACBPHW_Flashing Bro 5/23/03 2:52 PM Page 1 For the most current product information, go to www.green-guard.com. Pactiv Building Products believes the information and recommendations herein to be
More informationGYPSUM BOARD, GYPSUM PANEL PRODUCTS AND PLASTER
CHAPTER 25 GYPSUM BOARD, GYPSUM PANEL PRODUCTS AND PLASTER User note: Code change proposals to this chapter will be considered by the IBC Structural Code Development Committee during the 2016 (Group B)
More informationThird Party Inspection Guidelines For Inspectors As Part of the dryvitcare EIFS Repair/Restoration
Third Party Inspection Guidelines For Inspectors As Part of the dryvitcare EIFS Repair/Restoration DS497 SECTION ONE A. Objective The objective of this guide is to provide owners and general contractors/construction
More informationSECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront
PART 1 GENERAL 1.01 Work Included SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS System 402 Flush-Glazed Screw Spline Storefront A. Furnish and install aluminum architectural storefront system
More informationLAYING BLOCK AND BRICK
LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct
More informationFOUNDATION INSULATING SYSTEM, INCLUDING WATERPROOFING AND DAMP PROOFING
FOUNDATION INSULATING SYSTEM, INCLUDING WATERPROOFING AND DAMP PROOFING insulation installed on foundation walls must be separated from the building interior with a code approved thermal barrier. Foam
More informationSuperform Products Ltd.
TYPICAL CORNER REINFORCING NOTE : SEE ENGINEERED REBAR SCHEDULES SUPPLIED BY THE MANUFACTURER STEEL REINFORCEMENT WALL CORNER 90 Copyright 2012 Sept. 2012 5.1.1 Rebar Spacing 6" 12" Max. Load LB./FT. 2000
More informationSun Windows General Information Sun New Construction Window Installation Instructions
Sun Windows General Information Section 1 G F H H H A. Apply Weather Resistive Barrier B. Apply Sill Flashing Tape C. Place Waterproof Sill Shims D. Caulk Back of Nail Fin Sides & Top, Set Window, Fasten
More informationapplication instructions
application instructions ARCHITECTURAL COLLECTION PRIMED BOLD PROFILE 120 SERIES LAP SIDING (D5, T4, D8, T5, Q4) General At the time of manufacture, siding meets or exceeds the performance standards set
More informationGYPSUM BOARD AND PLASTER
CHAPTER 25 GYPSUM BOARD AND PLASTER SECTION 2501 GENERAL 2501.1 Scope. 2501.1.1 General. Provisions of this chapter shall govern the materials, design, construction and quality of gypsum board, lath, gypsum
More informationEnvelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit
R-H-DI1 INSULATION BATT NR-E-IB1 Avoid Using Batt Insulation With Metal Framing Batt insulation should not be used with metal framing systems. Although it is common to see fiberglass batt insulation installed
More informationAvoiding Air Barrier Pitfalls
Avoiding Air Barrier Pitfalls Design & Durability November 2013 Air barriers, when correctly installed, help buildings achieve high levels of energy efficiency by decreasing heat loss. For example, great
More informationChapter 36 - STRAW BALE CONSTRUCTION SECTION 3601 - PURPOSE. SECTION 3602 - SCOPE. SECTION 3603 - DEFINITIONS.
Austin City Code - Volume II TITLE 25 LAND DEVELOPMENT\CHAPTER 25-12 TECHNICAL CODES\ARTICLE 1: UNIFORM BUILDING CODE\25-12-3 LOCAL AMENDMENTS TO THE BUILDING CODE Chapter 36 - STRAW BALE CONSTRUCTION
More informationMarch 14, 2007. Installation of Bay, Bow and Garden Windows
March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed
More informationThe better way to build TM. Installation Manual. EXTERIOR WALL SIPs
The better way to build TM Installation Manual EXTERIOR WALL SIPs July 2015 EXTERIOR WALL SIPs Installation Manual Table of Contents Topics General Requirements................................... 3 Materials..............................................
More informationClad Direct Glaze Window Installation Instructions
Clad Direct Glaze Window Installation Instructions Sill flashing and sealing: 2. An overview of the proper flashing sequence is shown in figure 1. Please read entire installation instructions carefully
More informationRESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000
RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings
More informationVer. 2. Guide to. Inspecting Residential Brick Veneer
Ver. 2 Guide to Inspecting Residential Brick Veneer 1. A guide created by industry professionals. The knowledgeable staff at MASONPRO together with technical support from the Masonry Institute of Michigan
More informationMark Cramer Inspection Services, Inc.
Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction
More informationCity of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures
City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures SECTION 7201 - PURPOSE The purpose of this appendix chapter is to establish minimum prescriptive standards
More informationInternational Greenhouse Company
Greenhouse Foundation Design As with any building, a good solid foundation is crucial for the long term durability and functionality of your greenhouse. A weak foundation will cause your greenhouse to
More informationWATER MANAGEMENT PRODUCTS
WATER MANAGEMENT PRODUCTS ALSO AVAILABLE IN G D E A I B H F C A #15 Solid Leg* F #9 Transition Control Joint* B M-Slide Expansion Joint * G #6 Drip Head C J-Series Casing Bead H #17 Base Flashing* D #3
More informationPART 1 GENERAL 1.1 SECTION INCLUDES
J-1 Section 09110 Long Form Specification INTERIOR METAL STUD FRAMING This section includes lightweight, usually 0.036 inch (0.9 mm) thick or lighter, non-axial load bearing metal stud framing including
More informationVA25014B0516 VA CINCINNATI PROJECT NO. 539-328 INPATIENT BED TOWER ADDITION (4 TH AND 5 TH FLOORS) SECTION 09 29 00 GYPSUM BOARD
SECTION 09 29 00 GYPSUM BOARD PART 1 - GENERAL 1.1 DESCRIPTION This section specifies installation and finishing of gypsum board, vapor retarder and air and moisture barrrier. 1.2 RELATED WORK A. Installation
More information2014 British Columbia Building Code Changes
District of Houston 250-845-2238 2014 British Columbia Building Code Changes A District of Houston interpretation of the 2014 Building Code Changes for 9.36 & 9.32 The following changes reflect the most
More informationRenovating Your Basement
building science.com 2006 Building Science Press All rights of reproduction in any form reserved. Renovating Your Building America Report - 0309 2003 (revised 2007) Building Science Corporation Abstract:
More informationComment Form on Proposed Gut Rehabilitation Alternatives
Comment Form on Gut Rehabilitation Alternatives Name: Organization: Email: Instructions Submission: Please submit this form to energystarhomes@energystar.gov by October 10 th, 2012 with the subject line
More informationCHAPTER 7: Building Systems ROOFING SYSTEMS
ROOFING SYSTEMS Purpose Examples 1. Shingle roof system 2. Metal roof with blanket insulation 3. Metal roof with rigid insulation 4. Built-up asphalt roof system 5. Single-ply roof system 6. Modified Bitumen
More informationWeather Resistive Barriers: Building Science Makes a Case for Two Layers by Dave Olson Technical Services Manager, Fortifiber Building Systems Group
Weather Resistive Barriers: Building Science Makes a Case for Two Layers by Dave Olson Technical Services Manager, Fortifiber Building Systems Group Since water intrusion is among the most damaging problems
More informationDIVISION: 07 00 00 THERMAL AND MOISTURE PROTECTION SECTION: 07 41 13 METAL ROOF PANELS REPORT HOLDER: FIRESTONE BUILDING PRODUCTS COMPANY, LLC
0 ICC ES Report ICC ES (800) 423 687 (62) 699 043 www.icc es.org 000 Most Widely Accepted and Trusted ESR 3422 Reissued 09/201 This report is subject to renewal 09/2016. DIVISION: 07 00 00 THERMAL AND
More informationWindow Installation Instructions
Caution The correct installation methods of windows in full frame or insert applications is critical towards achieving the tested performance of the window and longterm enjoyment and energy savings for
More informationWater Damage & Repair
Water Damage & Repair Chinatown Preservation Talks 2015 James Engler, P.A Glenn Mason, AIA Mason Architects Program Outline Terminology & Waterproofing Basics Discussion of why this is important Below
More informationPhoto courtesy of Delta Stone, Heber City, UT. Installation Solutions for: Manufactured Stone, Natural Thin Veneer, and Thin Brick
Photo courtesy of Delta Stone, Heber City, UT Installation Solutions for: Manufactured Stone, Natural Thin Veneer, and Thin Brick THIN VENEER INSTALLATION SYSTEMS PREMIUM BONDING MORTARS Premium PCL Stone
More informationROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS
ROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS 1. 2. 3. 3.0 Scope 1.1 This application standard shall be used where the authority having jurisdiction has adopted its use, and
More informationRECOATING AND RENEWING SPF ROOFING SYSTEMS
RECOATING AND RENEWING SPF ROOFING SYSTEMS Procedures, Regional Differences and type of coating systems Bruce Schenke Premium Spray Products REASONS TO RECOAT/RENEW Add a new coating layer to renew the
More information2015 DuROCK Alfacing International Limited
SEPTEMBER 2015 DuROCK DEFS Direct-Applied Exterior Finish System MANUFACTURER S IFICATION 09 25 15 Part 1 GENERAL 1.1 RELATED SECTIONS.1 Specification 03 30 00 Cast-in-Place Concrete.2 Specification 04
More informationCOMMERCIAL BUILDING APPLICATIONS
EXPANDED POLYSTYRENE FOR COMMERCIAL BUILDING APPLICATIONS www.falconfoam.com Commercial Building Ap Expanded Polystyrene Insulation Falcon Foam leads the commercial building industry with products that
More informationCONDENSATION IN REFRIDGERATED BUILDINGS
CONDENSATION IN REFRIDGERATED BUILDINGS By: Steve Salisbury Nov. 10, 2010 (revised Nov. 14, 2013) Introduction The following discussion reviews the basic causes of condensation in refrigerated buildings
More informationTundra Series Windows January 2016
Tundra Series Windows January 2016 New Construction Installation Instructions Nail Fin, J-Fin and Brickmold Aplications product. ATTENTION! Read and understand all installation instructions before installing
More informationINSTALLATION OF A BAY WINDOW
INSTALLATION OF A BAY WINDOW Installation of a Bay Window These instructions relate to the replacement of an existing bay window or replacement of a straight window with a new bay window, in an opening
More informationBasements are Changing. Basements Part of the Enclosure. Basements. Energy Efficient, Durable, Healthy. Below grade enclosure
Basements are Changing John Straube, Ph.D., P.Eng Basements: New & Retrofit Energy Efficient, Durable, Healthy Increasingly used as living space Not a root /coal cellar anymore! High quality space expected
More informationIntroduction...COMB-2 Design Considerations and Examples...COMB-3
SECTION DIRECTORY General Information Introduction...COMB-2 Design Considerations and Examples...COMB-3 Combination Assembly Recommendations and Limitations Composite Configurations...COMB-4 Typical Sealant
More informationInsulating Basements: Part 3 Basement Wall Systems
The Pennsylvania Housing Research Center Insulating Basements: Part 3 Basement Wall Systems Builder Brief: BB0710 Brian Wolfgang, PHRC Fellow INTRODUCTION The perception of a basement has changed significantly
More informationRESIDENTIAL MASONRY A BEST PRACTICES GUIDE
RESIDENTIAL MASONRY A BEST PRACTICES GUIDE Build With Brick Build With Boral CONTENTS BRICK :01 MASONRY CEMENT :03 MASONRY SAND :04 WALL TIES :05 STEEL LINTELS :07 DRAINAGE WALL SYSTEM :09 FLASHING :11
More informationK2 STONE NATURAL VENEER
INTRODUCTION WHAT IS K2 NATURAL THINSTONE VENEER? Natural K2 Stone veneer is real stone, cut 1 inch thick, making it light enough to be installed as a veneer. Sometimes referred to as thin veneer, thin
More informationPERFORMANCE GUIDELINES
1. Foundation/Basement 17 PERFORMANCE GUIDELINES 1. FOUNDATION/BASEMENT 1.1 Efflorescence on concrete or masonry surfaces Efflorescence is the formation of a white crystalline or powdery deposit on the
More informationAcrylic Coatings: The Perfect Stucco Finish
Acrylic Coatings: The Perfect Stucco Finish By Larry Miller and Joe Miller Whether a stucco surface is new or old, there are many different finish coatings in today s marketplace that are supposedly right
More informationFrequently Asked Questions LP SmartSide Siding, Trim, and Soffit
Frequently Asked Questions LP SmartSide Siding, Trim, and Soffit 1. Can soffit be used for siding? a. No. The soffit is designed specifically for a protected soffit application whereas siding is designed
More informationFinal inspections are completed by site visit only. Access to fenced yards shall be planned.
ROOFING RESIDENTIAL BUILDING INSPECTIONS DEPARTMENT www.ci.blaine.mn.us This handout is intended only as a guide and is based in part on the 2015 Minnesota State Building Code, Blaine City ordinances,
More informationFinegan Inspection Services, Inc.
Finegan Inspection Services, Inc. Report Prepared For: Phone 513-683-0733 Fa 513-697-0163 Owners Property Address City, State, ZIP Phone FAX Owners Realtor Realty Company Phone FAX OWNER INFORMATION PROPERTY
More informationOLD BRICK ORIGINALS KILN-FIRED THIN BRICK VENEER Installation Guide. GeneralShale.com
OLD BRICK ORIGINALS KILN-FIRED THIN BRICK VENEER Installation Guide GeneralShale.com OLD BRICK ORIGINALS THIN BRICK VENEER Page 2 INTRODUCTION Check local building codes for proper installation guidelines
More informationUPDATE October 8, 2012 Chicago Roofing Contractors Association CHICAGOLAND S ROOFING, INSULATION, AIR-BARRIER REQUIREMENTS
UPDATE October 8, 2012 Chicago Roofing Contractors Association CHICAGOLAND S ROOFING, INSULATION, AIR-BARRIER REQUIREMENTS Executive Summary: There is a proposal at the Joint Committee on Administrative
More information201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE
STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,
More informationWhat you need to know about concrete block basement construction.
Designing and planning your new residence is a vitally important process, which will have a great influence on the future enjoyment of your home. A successful process will ensure all areas of the home
More informationInstallation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows
Installation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows americancraftsmanwindows.com Project Requirements: Read
More informationCertification: Building Plans Examiner. Exam ID: B3
Certification: Building Plans Examiner Exam ID: B3 Scope: A Building Plans Examiner will be responsible for reviewing submitted plans to determine if they meet the requirements of the various Building
More informationThe better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs
The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs February 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements...................................
More informationSECTION 07 61 13 STANDING SEAM METAL ROOFING
SECTION 07 61 13 STANDING SEAM METAL ROOFING PART 1 GENERAL 1.01 SCOPE OF WORK A. The Work shall include all labor, materials, equipment and supervision required to complete the work of the above referenced
More informationManufactured Stone Veneer Installation Instructions
Manufactured Stone Veneer Installation Instructions Published: 8/14/2008 Revised: 6/25/2010 Table of Contents PART 1 -- INTRODUCTION PART 2 -- MATERIAL REQUIREMENTS PART 3 EXECUTION REQUIREMENTS PART 4
More informationSeptember 3, 2009. Ric Boyd, Public Works Director Ketchikan Gateway Borough 344 Front St. Ketchikan, AK 99901
September 3, 2009 Ric Boyd, Public Works Director Ketchikan Gateway Borough 344 Front St. Ketchikan, AK 99901 RE: Ketchikan Gateway Borough Gateway Recreation Center Roof Observations and Intrusive Inspections
More informationMold Preventing I nterior System
interior insulation and renovation boards A system of components that have been designed to work perfectly together to repair damage caused by mold. The system consists of boards, insulation wedges, reveal
More informationSTANDARD PROCEDURES FOR INSTALLATION OF METAL ROOF SYSTEMS
ROOFING APPLICATION STANDARD (RAS) No. 133 STANDARD PROCEDURES FOR INSTALLATION OF METAL ROOF SYSTEMS 1. Scope 1.1 This application standard has been developed to provide consistent information for the
More informationChapter 2 Basis of design and materials
Chapter 2 Basis of design and materials 2.1 Structural action It is necessary to start a design by deciding on the type and layout of structure to be used. Tentative sizes must be allocated to each structural
More informationStucco Failures and Remediation
BEST2 Case Studies Session WB4-1 Stucco Failures and Remediation Roger G. Morse AIA, and Paul E. Haas CSP, CIH ABSTRACT Stucco over a single wythe of concrete block is widely used as wall construction
More informationINSTALLATION INSTRUCTIONS for Vinyl Windows without Nailing Fin (JII011) ImPOrTANT INFOrmATION & GlOssAry. rough OPeNINGs
Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for vinyl windows without a nailing fin (including finless, flush fin and flange). Read these instructions
More informationRDH Building Sciences Inc.
MAK LTR 2007 03 26 Proposal for Building Enclosure Consulting Services RDH Building Sciences Inc. 509 FAIRVIEW AVENUE N SEATTLE WA 98109-5507 TEL 206 324 2272 FAX 206 324 6339 SEA@RDHBE.COM WWW.RDHBE.COM
More informationCOMMONLY USED RESIDENTIAL BUILDING CODES
COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section
More informationBuilding Owners Guide to a Duro-Last System!
Building Owners Guide to a Duro-Last System Table of Contents Section 1: Introduction to Duro-Last Roofing Systems Section 2: Benefits of a Duro-Last Roofing System Section 3: Comparing a Duro-Last Roof
More informationSun Vinyl New Construction Windows Homeowner's Warranty
Sun Windows Sun Vinyl New Construction Windows Homeowner's Warranty Vinyl Sun Windows, Inc. warrants for a period of 2 years that the quality of workmanship and materials of vinyl items shall be free from
More informationTable of Contents. Western States RustWall Wall and Soffit Panels Installation, Flashings & Shop Drawing Detail Guide
Western States RustWall Wall and Soffit Panels Installation, Flashings & Shop Drawing Detail Guide Table of Contents Section Page Section Page Notes to Designer /Installers.. 1 Fastener Placement and Selection.2-3
More informationThe Foundation Group SSIPS vs Concrete Block and Wood Framing
www.thefoundationgroup.us RoryHiller@gmail.com The Foundation Group SSIPS vs Concrete Block and Wood Framing The creation of concrete building systems, such as concrete block, when created was a fair choice.
More informationRACQUETBALL, HANDBALL OR SQUASH COURTS AND GYMNASIUM WALL SURFACES
1807 Elmwood Avenue, Suite 275 Buffalo, New York 14207 (800) 543-5155 RACQUETBALL, HANDBALL OR SQUASH COURTS AND GYMNASIUM WALL SURFACES Fiberesin Wall System Provide materials and labor to complete courts
More informationGYPSUM AREA SEPARATION FIREWALLS GA-620-2011
GYPSUM AREA SEPARATION FIREWALLS GA-620-2011 GA-620-2011 Copyright 2011 Gypsum Association All rights reserved. Printed in U.S.A. Characteristics, properties, or performance of materials or systems herein
More informationWELCOME. Recommended Window Installation. 1.5 credits Minnesota Department of Labor and Industry
WELCOME Recommended Window 1.5 credits Minnesota Department of Labor and Industry In accordance with the Department of Labor and Industry s statute 326.0981, Subd. 11, This educational offering is recognized
More informationG VYCOR DECK PROTECTOR
G VYCOR DECK PROTECTOR Self-Adhered Flashing Contractor s Guide DECKS AND DETAIL AREAS For longer lasting decks, install Grace Vycor Deck Protector. FROM THE MAKERS OF G Ice & Water Shield What Self-Adhered
More informationState of Connecticut Department of Public Health RADON PROGRAM
State of Connecticut Department of Public Health RADON PROGRAM Scope The Connecticut Department of Public Health (DPH) Radon Program is providing this information for contractors who decide to build radon
More informationINSTALLATION INSTRUCTIONS for Vinyl Windows with Integral Nailing Fin (JII001)
Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for Vinyl windows with an integral nailing fin. While the use of these installation instructions
More informationEverybody talks about the high
An Efficient Wall System Produces Energy Savings and Attractiveness Florida Man Designs Own Home Complete With Patented Air- Return System Plus Insulated Roof and Stucco Wall System Everybody talks about
More informationSTAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM
STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM Installed in Pre-engineered Steel Buildings Provides Lowest Cost Construction Method for CORROSIVE AND WET Environments PREFERRED SOLUTIONS, INC.
More informationSTANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES
ROOFING APPLICATION STANDARD (RAS) No. 117 STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES Scope 1.1.
More informationBarewood Octagon and Elongated Windows Installation Instructions
Step-by-step instructions to a beautiful window. Measuring and Installation of your new window from Century Specialty Windows couldn't be easier with our step-by-step instructions. Quality, function and
More informationWhen dealing with a potential moisture problem, time is of the essence. Taking a proactive approach will save you money and headaches down the road.
If you own a house clad in something known as exterior insulated finish systems (EIFS), also known as synthetic stucco, you are probably trying to cope with a small but growing feeling of anxiety. You
More information3.1 Water Intrusion Problems Related to Unsealed Stucco Penetrations
3.1 Water Intrusion Problems Related to Unsealed Stucco Penetrations Any penetration through the stucco that is left unsealed will allow entry of moisture. Even an average size home can have an extreme
More information10DBMC International Conference On Durability of Building Materials and Components LYON [France] 17 20 April 2005
10DBMC International Conference On Durability of Building Materials and Components Wall Cladding System Durability Lessons Learned from the Premature Deterioration of Wood-Framed Construction Clad with
More informationInvestigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps
Foundations on Expansive Clay Soil Part 3 - Investigation of Failed Foundations Presented by: Eric Green, P.E. Structural Engineer Slide 1 Copyright Eric Green 2005 Investigation of Foundation Failure
More informationGUIDELINE SPECIFICATIONS
GUIDELINE SPECIFICATIONS GORDON SOFFIT-SHIELD - An Exterior Metal Soffit System DIVISION 05 5800 or DIVISION 07 7700 Note To Specifier: SOFFIT-SHIELD should be installed by tradesmen that are experienced
More informationNRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS
NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS The (NRDCA) has prepared this document to provide customers and installers information that the industry
More informationMinor Cracks in Horizontal Surfaces
Cracks, chips and broken or flaking areas in concrete are not only unsightly, they can lead to further deterioration of the surface. The result is a costly replacement project as opposed to a simple repair.
More informationSection 4: Architectural Design
Section 4: Architectural Design 4.1 Design Flexibility and Compatibility...3 4.2 Moisture Protection...3 4.3 Surface Treatments...6 4.4 Exterior Surface Treatments...6 4.5 Interior Surface Treatments...8
More informationFigure 1 The GENERAL CONTRACTOR blames the applicator (if available) for improper installation and
BACKGROUND History The Exterior Insulation and Finish System (EIFS) was originally developed in West Germany in the 1960s. The original market for EIFS was providing an insulation layer to existing masonry