UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Size: px
Start display at page:

Download "UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION"

Transcription

1 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Commissioner Philip D. Moeller s Inquiry ) Into the Trading of Natural Gas, and the ) Docket No. AD Proposal to Establish an Electronic ) Information and Trading Platform ) POST-CONFERENCE COMMENTS OF THE ELECTRIC POWER SUPPLY ASSOCIATION The Electric Power Supply Association ( EPSA ) 1 respectfully submits these comments in response to the Federal Energy Regulatory Commission s ( FERC or Commission ) September 19, 2014 notice establishing a date for submittal of post-conference comments following the September 18, 2014 conference convened by Commissioner Philip D. Moeller in the above-captioned proceeding. 2 The purpose of the September 18 Conference was to explore the concept of an electronic information and trading platform for natural gas, and discuss the relationship between available gas capacity on pipelines and deliverability to electric generators. EPSA members operate a diverse fleet of power plants and recognize the importance of natural gas as a fuel for electric generation. Electric and gas coordination is essential to many EPSA members as large consumers of natural gas who therefore have a significant interest in robust natural gas supplies and a reliable pipeline delivery network. This is of particular concern for electricity suppliers that operate in competitive wholesale markets. In those markets, power plants do not earn their primary source of revenue unless their plants run, which in part requires that gas-fired plants have reliable access to competitively priced natural gas. Moreover, many EPSA members have significant market positions in both the natural gas 1 EPSA is the national trade association representing leading competitive power suppliers, including generators and marketers. Competitive suppliers, which collectively account for 40 percent of the installed generating capacity in the United States, provide reliable and competitively priced electricity from environmentally responsible facilities. EPSA seeks to bring the benefits of competition to all power customers. The comments contained in this filing represent the position of EPSA as an organization, but not necessarily the views of any particular member with respect to any issue. 2 Post-Meeting Notice, Commissioner Philip D. Moeller s Inquiry into the Trading of Natural Gas, and the Proposal to Establish an Electronic Information and Trading Platform, Docket No. AD , (issued August 19, 2014) ( August 19 Notice ). 1

2 and electric markets, as both buyers and sellers for each, and thereby are well acquainted with the current regional challenges that both industries face. Commissioner Moeller s conference underscored that certain critical market design elements, tariff rules and operator practices may be creating distortions that affect the efficiency of market operations and reliability. Therefore, the conference raised further awareness of critical matters that need to be addressed by the Commission broadly and by individual ISOs/RTOs under the Commission s oversight in order to facilitate better price formation and settlement in electric markets. To that end, with respect to gas markets, EPSA has been participating in forums supporting the Commission s March 20, 2014 Notice of Proposed Rulemaking ( NOPR or Scheduling NOPR ) 3 to establish the gas day start time and intraday nomination cycles which can be coordinated with improved ISOs/RTOs scheduling. Concurrently, the Commission has opened a proceeding to examine electricity price formation issues, which is critical to ensure that competitive power suppliers are assured of sufficient revenue recovery to make reasonable decisions and obligations that support the reliable production of power. I. COMMENTS On a broad level, the Commission is correctly looking at electricity price formation in the energy markets. By addressing issues such as the creation of and overreliance on uplift; ensuring that offer price caps allow for the purchase of fuel at all times and that those fuel prices be reflected in energy prices; and showing how shortage or scarcity pricing mechanisms are utilized in the market, the appropriate attention is being paid to sending the right signals through the right energy prices. This is important to all generators, but particularly critical for gas-fired generation as they continue to make arrangements for reliable operation and market participation. 3 Coordination of the Scheduling Processes of Interstate Natural Gas Pipelines and Public Utilities, 146 FERC 61,201, Docket No. RM , at PP 52-53, (issued March 20, 2014) ( Scheduling NOPR ). ( Under our proposal, gas-fired generators would have the option of arranging natural gas supply and transportation at the Timely Nomination Cycle knowing the results of the day-ahead electric market. In particular, this would forward the objective of minimizing situations in which gas-fired generators, particularly those that opt to procure natural gas supply and transportation after the day-ahead electric market results are posted, are unable to procure sufficient resources to fulfill their electric market commitments and to contribute to reliable system operation. Furthermore, as discussed above, a gas-fired generator s inability to know whether its bid in the day-ahead market has been selected prior to the deadline for the Timely Nomination Cycle may lead to instances in which gas-fired generators must sell off excess natural gas supply, procure more expensive natural gas supply, de-rate, or burn more expensive fuels. We are concerned that any of these scenarios could result in increased electricity costs and a shift away from the least-cost mix of supply resources as determined by the ISO or RTO s day-ahead dispatch and unit commitment. These circumstances could lead to higher costs being passed on to wholesale customers... ) 2

3 More specific to the coordination of the electric and natural gas systems, FERC has issued the Scheduling NOPR in order to ensure that requirements and obligations for the day ahead electric market are known in time for generators to then make gas supply and transportation arrangements while the natural gas markets are liquid such that generators have options to meet their needs. FERC initiated a NAESB process associated with the Scheduling NOPR, which has been completed with a submission of NAESB standards on September EPSA participated in that process and appreciates that the Commission allowed time for industry dialogue while being clear that action must be forthcoming either through industry consensus at NAESB, or barring that consensus, through potential Commission action as outlined in the Scheduling NOPR proposals. Once the gas day timing issues have been settled, the ISOs/RTOs are directed to develop conforming changes to their Day Ahead scheduling processes as set out in the NOPR. Currently, each ISO/RTO utilizes its own timeline which vary by market and EPSA will work with the ISOs/RTOs and market participants on the complementary changes needed on the power side to ensure there is a process in place so that gas-fired generators gas purchases can be scheduled in the Timely Nomination Cycle so that firm transportation can be utilized. This will require adjustments from each industry. Therefore, EPSA urges each ISO/RTO to work expeditiously on power market timeline changes that will best conform to any changes on the natural gas side in order to address the current inefficiencies of the two markets (natural gas and power). Importantly, and consistent with previous conferences addressing electric and gas coordination and the polar vortex events over the winter of , the September 18 conference reasserted that while the system was stressed this past winter, the electricity and gas supply and delivery system met reliability needs under those extreme conditions. That noted, there are market design and operational issues which require revision in order to ensure system reliability going forward as the nation s resource mix changes. Broadly, for instance, all power markets should have in place intraday scheduling opportunities to allow generators to refresh their supply offers to reflect changing market conditions including as to real-time gas costs. Reflecting actual market conditions, including unexpected fuel price volatility or system 4 The Scheduling NOPR provides time for the natural gas and electric industries to reach consensus that might differ from the NOPR s proposed revisions through the NAESB process. That process must conclude by September 29, 2014 and the NAESB committee established for this effort is the NAESB Gas-Electric Harmonization Forum ( NAESB GEH Forum ). Additional information is available here 3

4 constraints, is necessary to reduce sellers uncertainty regarding adequate compensation when they run and to support ongoing operational and capital investment decisions. Additionally, this intraday or hourly flexibility will benefit the interaction of the gas and electric markets by allowing power offers to accommodate gas price variation between day-ahead and real-time scheduling and delivery times, as well as oil price variation for dual fuel units which were relied upon heavily in several markets this winter. Consistent with a recommendation from Jim Ginnetti, Senior Vice President of EquiPower Resources, Corp., EPSA urges that all ISO/RTOs be required to provide offer flexibility optimally hourly reoffer opportunities -- in order to address short run operational issues, as well as ensuring that market participants have confidence in their ability to recover costs and make investment decisions supporting their generation resources. Additional scheduling flexibility on the gas pipelines may be needed to allow generators to respond to the intraday dispatch instructions from the ISO/RTOs as they are required to do under their tariffs. While natural gas prices across the country remain historically low, this past winter reflected how market prices for gas can escalate when high electric and gas demand coincide. While the electricity energy offer cap issue emerged only this past winter when it became binding, EPSA has serious concerns that certain clear flaws in energy market price formation under current rules and practices are not being addressed expeditiously by ISO/RTO markets, even when market problems experienced this winter highlighted those flaws or where internal or external market monitors have identified such flaws for years. Several of the September 18 conference panelists noted that unnecessary artificial constraints on wholesale electricity markets have serious adverse consequences when flexibility is needed most. As the Commission is well aware, several ISO/RTOs were forced to make emergency waiver filings, seeking waiver of the offer cap contained in their tariffs in order to allow generators to reflect the cost of gas in their bids. To date, none of the ISO/RTOs have submitted filings to the Commission to increase the offer caps going into this winter. If we experience another abnormally cold winter, generators could again face the untenable position of having to purchase gas at prices that exceed the ISO/RTO s bid cap. The Commission should require each ISO/RTO to address this issue prior to the start of the winter season. Another issue of concern experienced this past winter and raised at the September 18 conference is generators having to procure natural gas priced as a package on Friday for the coming three days over the weekend which includes Monday, and sometimes for four days over a holiday weekend. EPSA was encouraged by the comments from panelists representing two exchanges, the CME Group and Intercontinental Exchange (ICE). ICE is, in fact, actively 4

5 working with industry to develop market solutions for weekend gas procurement. ICE is looking at products that would separate Saturday/Sunday from Monday in order to reflect the differences between weekend and weekday demand and price conditions. While EPSA supports retention of the current ICE products, it has also been working with ICE on the development of alternative products in order to overcome impediments and facilitate greater flexibility for gas procurement for weekend days. As to the discussion regarding the trading platform proposed by Don Sipe, that conversation raised more questions than it answered. While the concept was discussed, the need for the trading platform and how it would work with existing structures is not sufficiently developed in order to allow gas and electric market participants to evaluate the need and implementation of such a concept. Consequently, at this point EPSA believes the concept needs better definition and a demonstration that the concept will, in fact, benefit both the gas and electric industries before it can be further discussed by those who might consider its use as a customer or a seller. As such, we look forward to working with FERC on its continuing efforts in the above-referenced proceedings to develop solutions to the market inefficiencies discussed during the September 18 Conference. II. CONCLUSION WHEREFORE, EPSA submits these comments regarding the September 18 Conference for the Commission s consideration. Respectfully submitted, Nancy E. Bagot, Vice President, Regulatory Affairs Jack Cashin, Director, Regulatory Affairs Electric Power Supply Association 1401 New York Avenue, NW, 12 th Floor Washington, DC (202) NancyB@epsa.org 5

Aliso Canyon Gas-Electric Coordination. Issue Paper

Aliso Canyon Gas-Electric Coordination. Issue Paper Aliso Canyon Gas-Electric Coordination March 17, 2016 Table of Contents 1. Executive Summary... 3 2. Plan for Stakeholder Engagement... 4 3. Background... 5 3.1. Aliso Canyon Impact... 5 3.2. FERC Order

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southwest Power Pool, Inc. ) ) Docket No. ER12-1179-000 MOTION FOR LEAVE TO INTERVENE AND PROTEST OF THE ELECTRIC POWER SUPPLY ASSOCIATION

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Coordination of the Scheduling Processes of ) Interstate Natural Gas Pipelines and Public ) Docket No. RM14-2-000 Utilities ) COMMENTS

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Capacity Deliverability Across the ) Midwest Independent Transmission System ) Docket No. AD12-16-000 Operator, Inc./PJM Interconnection,

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Electric Creditworthiness Standards ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Electric Creditworthiness Standards ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Electric Creditworthiness Standards ) Docket No. AD04-8-000 Comments of the California Independent System Operator Corporation I.

More information

Electric Power Supply Association. April 16, 2014.

Electric Power Supply Association. April 16, 2014. Electric Power Supply Association April 16, 2014. 1401 New York Avenue, NW 12th Floor Washington, DC 20005 202-628-8200 202-628-8260 fax www.epsa.org [VIA E-Mail]. Robert dev. Frierson Secretary Board

More information

Natural Gas Pipeline Penalty Recovery Issue Paper

Natural Gas Pipeline Penalty Recovery Issue Paper Natural Gas Pipeline Penalty Recovery Issue Paper September 16, 2014 Table of Contents I. Introduction and Background... 3 II. Scope of Initiative and Plan for Stakeholder Engagement... 4 III. The Approved

More information

August 4, 2014. Position Limits for Derivatives and Aggregation of Positions, 79 Fed. Reg. 30,762 (May 29, 2014).

August 4, 2014. Position Limits for Derivatives and Aggregation of Positions, 79 Fed. Reg. 30,762 (May 29, 2014). August 4, 2014 Via Electronic Submission Melissa Jurgens, Secretary Commodity Futures Trading Commission Three Lafayette Centre 1155 21st Street, N.W. Washington, D.C. 20581 Re: Position Limits for Derivatives

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Coordination Between Natural Gas ) Docket No. AD12-12-000 And Electricity Markets ) ) COMMENTS OF DOMINION RESOURCES SERVICES,

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) ) Reliability Technical Conference ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) ) Reliability Technical Conference ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Reliability Technical Conference Docket No. AD14-9-000 REMARKS OF BRAD ALBERT GENERAL MANAGER, RESOURCE MANAGEMENT ARIZONA PUBLIC

More information

Memo INTRODUCTION UNDER-SCHEDULING

Memo INTRODUCTION UNDER-SCHEDULING California Independent System Operator Memo To: ISO Board of Governors From: Greg Cook, Senior Policy Analyst/Market Surveillance Committee Liaison CC: ISO Officers Date: September 28, 2000 Re: Management

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Commissioner Philip D. Moeller s Inquiry into ) The Trading of Natural Gas, and the Proposal ) Docket No. AD14-19-000 To Establish

More information

Aliso Canyon Gas-Electric Coordination. Straw Proposal

Aliso Canyon Gas-Electric Coordination. Straw Proposal Aliso Canyon Gas-Electric Coordination Straw Proposal April 15, 2016 Table of Contents 1. Executive Summary... 3 2. Plan for Stakeholder Engagement... 4 3. Background... 5 3.1. Aliso Canyon Impact... 5

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Coordination between Natural Gas and Electricity Markets Docket No. AD12-12-000 Prepared Statement of Brad Bouillon on behalf of

More information

135 FERC 61,197 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER GRANTING AUTHORIZATION TO MAKE AFFILIATE SALES

135 FERC 61,197 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER GRANTING AUTHORIZATION TO MAKE AFFILIATE SALES 135 FERC 61,197 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, John R. Norris, and Cheryl A. LaFleur. Black

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Independent Market Monitor for PJM v. PJM Interconnection, L.L.C. ) ) ) ) ) ) Docket No. EL14- -000 COMPLAINT AND MOTION TO CONSOLIDATE

More information

FERC Workshop on Price Formation: Scarcity and Shortage Pricing, Offer Mitigation, and Offer Caps in RTO and ISO Markets (Docket. No.

FERC Workshop on Price Formation: Scarcity and Shortage Pricing, Offer Mitigation, and Offer Caps in RTO and ISO Markets (Docket. No. FERC Workshop on Price Formation: Scarcity and Shortage Pricing, Offer Mitigation, and Offer Caps in RTO and ISO Markets (Docket. No. AD14-14-000) October 28, 2014 Market Presentation Design Title & Analysis

More information

151 FERC 61,046 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

151 FERC 61,046 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 151 FERC 61,046 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Philip D. Moeller, Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable.

More information

152 FERC 61,218 DEPARTMENT OF ENERGY FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 35. [Docket No. RM15-24-000]

152 FERC 61,218 DEPARTMENT OF ENERGY FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 35. [Docket No. RM15-24-000] 152 FERC 61,218 DEPARTMENT OF ENERGY FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Part 35 [Docket No. RM15-24-000] Settlement Intervals and Shortage Pricing in Markets Operated by Regional Transmission

More information

Evaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042. Market Subcommittee (MSC) May 3, 2016

Evaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042. Market Subcommittee (MSC) May 3, 2016 Evaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042 Market Subcommittee (MSC) May 3, 2016 Purpose Purpose and Key Takeaways Review proposed FERC Energy Offer Cap rules, and potential

More information

July 1, 2005. Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426. Magalie R. Salas, Secretary

July 1, 2005. Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426. Magalie R. Salas, Secretary 2800 Post Oak Boulevard (77056) P.O. Box 1396 Houston, Texas 77251-1396 713/215-3380 July 1, 2005 Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Attention: Re: Magalie

More information

Gas-Electric Harmonization

Gas-Electric Harmonization Gas-electric harmonization is a suite of challenges facing the nation as we move toward a much higher natural gas fuel portfolio for electric generation. Although that move is being accelerated due to

More information

Statement for the Record

Statement for the Record Statement for the Record Kevin R. Hennessy Director Federal, State and Local Affairs New England Dominion Resources, Inc. Infrastructure Needs for Heat and Power Quadrennial Energy Review Task Force April

More information

California Independent System Operator Corporation - A Case Study

California Independent System Operator Corporation - A Case Study UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Joseph T. Kelliher, Chairman; Nora Mead Brownell, and Suedeen G. Kelly. California Independent System Operator Corporation

More information

124 FERC 61,317 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Communication Protocols for Public Utilities ORDER NO.

124 FERC 61,317 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Communication Protocols for Public Utilities ORDER NO. 124 FERC 61,317 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Joseph T. Kelliher, Chairman; Suedeen G. Kelly, Marc Spitzer, Philip D. Moeller, and Jon Wellinghoff.

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Reliability Technical Conference Docket No. AD16-15-000 Prepared Statement of Mark Rothleder on behalf of the California Independent System

More information

Implementation Challenges of Incorporating Greenhouse Gas Compliance Costs

Implementation Challenges of Incorporating Greenhouse Gas Compliance Costs www.caiso.com 250 Outcropping Way, Folsom, CA 95630 916.351.4400 Revision History Date Version Description Author 2013-07-12 1.0 Xu, Lin Note: Consistent with Attachment G to the Business Practice Manual

More information

Re: Docket No. RM 10-11-000, Comments on Proposed Rule on Integration of Variable Energy Resources

Re: Docket No. RM 10-11-000, Comments on Proposed Rule on Integration of Variable Energy Resources 750 1 st St, NE Suite 1100 Washington, DC 20002 202.682.6294 Main 202.682.3050 Fax www.cleanskies.org March 2, 2011 Via Electronic Docket Hon. Kimberly D. Bose Secretary Federal Energy Regulatory Commission

More information

Informational Report of the California Independent System Operator Corporation

Informational Report of the California Independent System Operator Corporation California Independent System Operator Corporation June 30, 2016 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: Informational

More information

San Diego Gas & Electric Company ) Docket No. ER98-4498- 000 MOTION TO INTERVENE AND PROTEST OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

San Diego Gas & Electric Company ) Docket No. ER98-4498- 000 MOTION TO INTERVENE AND PROTEST OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION San Diego Gas & Electric Company ) Docket No. ER98-4498- 000 MOTION TO INTERVENE AND PROTEST OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR

More information

141 FERC 61,117 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

141 FERC 61,117 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 141 FERC 61,117 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Philip D. Moeller, John R. Norris, Cheryl A. LaFleur, and Tony T. Clark. Wyoming

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Demand Response Compensation in ) Docket No. RM10-17-000 Organized Wholesale Energy Markets ) Background and Summary COMMENT OF

More information

Natural Gas 101. MISO ENGCTF February 14, 2013

Natural Gas 101. MISO ENGCTF February 14, 2013 Natural Gas 101 MISO ENGCTF February 14, 2013 AGENDA Natural Gas 101 Topic List 1. Overview of U.S Natural Gas Regulation; Regulatory Comparison 2. How pipeline builds are developed; the internal and jurisdictional

More information

Business Requirements Specification

Business Requirements Specification Business s Specification Capacity Procurement Mechanism Replacement Doc ID: GNFDMDEHU6BB-46-53 Page 1 of 18 Disclaimer All information contained in this draft Business s Specification (BRS) as provided

More information

Securities and Exchange Commission 100 F Street, NE Washington, DC 20219 Release No. 34-65545; File No. S7-41-11; RIN 3235-AL07

Securities and Exchange Commission 100 F Street, NE Washington, DC 20219 Release No. 34-65545; File No. S7-41-11; RIN 3235-AL07 Federal Deposit Insurance Corporation 550 17 th Street, NW Washington, DC 20551 RIN No. 3064-AD85 Board of Governors of the Federal Reserve System 20 th Street & Constitution Avenue, NW Washington, DC

More information

103 FERC 61, 044 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

103 FERC 61, 044 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 103 FERC 61, 044 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; William L. Massey, and Nora Mead Brownell. Ontario Energy Trading International

More information

Response by NIE Energy (PPB)

Response by NIE Energy (PPB) NIE Energy Limited Power Procurement Business (PPB) Review of K factors & Supply Margins and Tariff Structure Review Consultation Paper CER-09-093 Response by NIE Energy (PPB) 11 September 2009. Introduction

More information

The remainder of this memo provides a summary of market performance and trends in 2014 through November.

The remainder of this memo provides a summary of market performance and trends in 2014 through November. California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Eric Hildebrandt, Director, Market Monitoring Date: December 10, 2014 Re: Market monitoring report This memorandum

More information

COMMODITY FUTURES TRADING COMMISSION. AGENCY: Commodity Futures Trading Commission; Securities and Exchange

COMMODITY FUTURES TRADING COMMISSION. AGENCY: Commodity Futures Trading Commission; Securities and Exchange COMMODITY FUTURES TRADING COMMISSION SECURITIES AND EXCHANGE COMMISSION [Release No. 33-10062; 34-77506; File No. S7-05-16] RIN 3235- AL93 Certain Natural Gas and Electric Power Contracts AGENCY: Commodity

More information

Rules on Southern Companies Energy Auction Participation. 1.2.1 Available Capacity: See Section 1.3 of Appendix DA-1 and Section 1.3 of Appendix HA-1.

Rules on Southern Companies Energy Auction Participation. 1.2.1 Available Capacity: See Section 1.3 of Appendix DA-1 and Section 1.3 of Appendix HA-1. Rules on Southern Companies Energy Auction Participation 1.0 Participation; Definitions 1.1 Southern Companies shall participate in the Energy Auction in accordance with these Rules on Southern Companies

More information

Market Solutions to Loop Flow

Market Solutions to Loop Flow Market Solutions to Loop Flow Robert Pike Director, Market Design New York Independent System Operator Business Issues Committee September 9, 2009 1 Agenda Background Recommendation Next Steps Solution

More information

142 FERC 61,131 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 38. [Docket No. RM05-5-020; Order No.

142 FERC 61,131 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 38. [Docket No. RM05-5-020; Order No. 142 FERC 61,131 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Part 38 [Docket No. RM05-5-020; Order No. 676-G] Standards for Business Practices and Communication Protocols for Public

More information

Note No. 137 March 1998. Countries in Asia, Europe, and North and South America are introducing reforms to boost

Note No. 137 March 1998. Countries in Asia, Europe, and North and South America are introducing reforms to boost Privatesector P U B L I C P O L I C Y F O R T H E Note No. 137 March 1998 Competition in the Natural Gas Industry The emergence of spot, financial, and pipeline capacity markets Andrej Juris Countries

More information

140 FERC 61,036 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 284. [Docket No. RM96-1-037; Order No.

140 FERC 61,036 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 284. [Docket No. RM96-1-037; Order No. 140 FERC 61,036 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Part 284 [Docket No. RM96-1-037; Order No. 587-V] Standards for Business Practices of Interstate Natural Gas Pipelines

More information

151 FERC 61,049 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 284. [Docket No. RM14-2-000; Order No.

151 FERC 61,049 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 284. [Docket No. RM14-2-000; Order No. 151 FERC 61,049 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Part 284 [Docket No. RM14-2-000; Order No. 809] Coordination of the Scheduling Processes of Interstate Natural Gas Pipelines

More information

Is It Possible to Charge Market-Based Pricing for Ancillary Services in a Non-ISO Market?

Is It Possible to Charge Market-Based Pricing for Ancillary Services in a Non-ISO Market? Is It Possible to Charge Market-Based Pricing for Ancillary Services in a Non-ISO Market? Regulation and Operating Reserves 33 rd Eastern Conference Center for Research in Regulated Industry Romkaew P.

More information

Specific amendments to the Capacity Allocation and Congestion Management Network Code

Specific amendments to the Capacity Allocation and Congestion Management Network Code Annex: Specific amendments to the Capacity Allocation and Congestion Management Network Code I. Amendments with respect to entry into force and application The Network Code defines deadlines for several

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 101. (Docket No. RM04-12-000; Order No. 668)

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 101. (Docket No. RM04-12-000; Order No. 668) UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Part 101 (Docket No. RM04-12-000; Order No. 668) Accounting and Financial Reporting for Public Utilities Including RTOs (Issued December

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator ) Corporation ) Docket No. ER10-500-000 MOTION OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR

More information

The Impact of Fuel Costs on Electric Power Prices

The Impact of Fuel Costs on Electric Power Prices The Impact of Fuel Costs on Electric Power Prices by Kenneth Rose 1 June 2007 1 Kenneth Rose is an independent consultant and a Senior Fellow with the Institute of Public Utilities (IPU) at Michigan State

More information

While there has been a lot of discussion

While there has been a lot of discussion Pipelines Is North American Natural Gas Infrastructure Up to Complementing Wind, Solar? Donald F. Santa Jr. While there has been a lot of discussion within the electric power industry about integrating

More information

The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D.

The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D. The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D. Why not use the Web to buy and sell transmission rights at prices derived from bids

More information

Comments on ISO s Third Revised Straw Proposal for Settlement of Interties in Real-Time

Comments on ISO s Third Revised Straw Proposal for Settlement of Interties in Real-Time Comments on ISO s Third Revised Straw Proposal for Settlement of Interties in Real-Time Department of Market Monitoring July 26, 2012 Summary The Department of Market Monitoring (DMM) appreciates the opportunity

More information

Performance Metrics. For Independent System Operators And Regional Transmission Organizations

Performance Metrics. For Independent System Operators And Regional Transmission Organizations Performance Metrics For Independent System Operators And Regional Transmission Organizations A Report to Congress In Response to Recommendations of the United States Government Accountability Office April

More information

122 FERC 61,085 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C. 20426. February 1, 2008

122 FERC 61,085 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C. 20426. February 1, 2008 122 FERC 61,085 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C. 20426 February 1, 2008 In Reply Refer To: Insight Research, Inc. Docket No. PL03-3-007 Insight Research, Inc. 3004 SW First Avenue

More information

132 FERC 61,064 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING REQUEST FOR CLARIFICATION AND GRANTING LIMITED WAIVER

132 FERC 61,064 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING REQUEST FOR CLARIFICATION AND GRANTING LIMITED WAIVER 132 FERC 61,064 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, John R. Norris, and Cheryl A. LaFleur. Arizona

More information

Taking Advantage of Lower Electric Rates for your Government Agency

Taking Advantage of Lower Electric Rates for your Government Agency Taking Advantage of Lower Electric Rates for your Government Agency This is an expanded version of an article written by the NJ Department of Community Affairs, originally published in New Jersey Municipalities,

More information

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market CALIFORNIA ISO Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market Prepared by the Department of Market Analysis California Independent System Operator September 1999 Table of Contents Executive

More information

PRICE FORMATION IN ISOs AND RTOs PRINCIPLES AND IMPROVEMENTS

PRICE FORMATION IN ISOs AND RTOs PRINCIPLES AND IMPROVEMENTS Economic Consulting PRICE FORMATION IN ISOs AND RTOs PRINCIPLES AND IMPROVEMENTS SUSAN L. POPE 1 October 2014 Executive Summary Assessment of concerns about price formation and prompt action to address

More information

Presentation for The National Commission for Energy State Regulation of Ukraine

Presentation for The National Commission for Energy State Regulation of Ukraine Presentation for The National Commission for Energy State Regulation of Ukraine Todd Keech Laura Walter PJM Interconnection June 17, 2014 What is PJM? 1 What is PJM? ISO RTO Map Part of Eastern Interconnection

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Southwest Power Pool, Inc. ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Southwest Power Pool, Inc. ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Southwest Power Pool, Inc. ) Docket No. ER09-1050-000 ) COMMENTS OF SOUTHWEST POWER POOL, INC. Southwest Power Pool, Inc. ( SPP

More information

Rules on Southern Companies Energy Auction Participation

Rules on Southern Companies Energy Auction Participation Southern Company Services, Inc. First Revised Sheet No. 20B Superseding Original Sheet No. 20B Rules on Southern Companies Energy Auction Participation 1.0 Participation; Definitions 1.1 Southern Companies

More information

2009 Bates White, LLC. Asset Management Agreements Christopher Gulick Presentation to the 2009 Energy Management Fall Meeting November 10, 2009

2009 Bates White, LLC. Asset Management Agreements Christopher Gulick Presentation to the 2009 Energy Management Fall Meeting November 10, 2009 Asset Management Agreements Christopher Gulick Presentation to the 2009 Energy Management Fall Meeting Asset Management Agreements (AMAs) Background on AMAs FERC Order No. 712: Background FERC Order No.

More information

March 25, 2015. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426

March 25, 2015. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 March 25, 2015 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Tuscarora Gas Transmission Company 700 Louisiana Street, Suite 700 Houston,

More information

Drafting the Natural Gas Sale and Purchase Agreement

Drafting the Natural Gas Sale and Purchase Agreement Drafting the Natural Gas Sale and Purchase Agreement Glenn S. Krassen Presented at the Conference: Utica Shale: Issues in Law Practice and Policy Cleveland Marshall College of Law Cleveland, Ohio September

More information

153 FERC 61,227 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

153 FERC 61,227 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 153 FERC 61,227 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. Gulf South Pipeline

More information

Eni Gas &Power s response to ERGEG s consultation - ERGEG principles: Capacity allocation and congestion management in natural gas transmission

Eni Gas &Power s response to ERGEG s consultation - ERGEG principles: Capacity allocation and congestion management in natural gas transmission Eni Gas &Power s response to ERGEG s consultation - ERGEG principles: Capacity allocation and congestion management in natural gas transmission networks. San Donato Milanese, 27.3.2009 Introduction Eni

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Parts 35, 101, 154, 201, 346, and 352. Docket No. RM02-7-000, Order No.

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Parts 35, 101, 154, 201, 346, and 352. Docket No. RM02-7-000, Order No. UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Parts 35, 101, 154, 201, 346, and 352 Docket No. RM02-7-000, Order No. 631 Accounting, Financial Reporting, and Rate Filing Requirements

More information

Demand Response FAQs

Demand Response FAQs 1 Under the current CAISO tariff, assuming it would otherwise meet the requirements under the CAISO tariff and business practice manuals to do so, can the Load associated with a retail meter participate

More information

AGCS Gas Clearing and Settlement AG

AGCS Gas Clearing and Settlement AG Annex to the General Terms and Conditions of the Balance Group Coordinator (GTC BGC) Balancing energy management in the Eastern distribution area V 5.0 Annex Balancing energy management Version 5.0 Page

More information

Overview of Reliability Demand Response Resource

Overview of Reliability Demand Response Resource Overview of Reliability Demand Response Resource Radha Madrigal Customer Service Department May 8, 2014 Agenda Product overview and purpose Define Reliability Demand Response Resource Agreements & registration

More information

Staff Report on Gas-Electric Coordination Technical Conferences (Docket No. AD12-12-000) November 15, 2012

Staff Report on Gas-Electric Coordination Technical Conferences (Docket No. AD12-12-000) November 15, 2012 Staff Report on Gas-Electric Coordination Technical Conferences (Docket No. AD12-12-000) November 15, 2012 This report was prepared by the staff of the Federal Energy Regulatory Commission. This report

More information

Gas Electric System Interface Study. PPA Stakeholder Forum: MISO ENGCTF 6/03/2013 Eric Thoms (MISO)

Gas Electric System Interface Study. PPA Stakeholder Forum: MISO ENGCTF 6/03/2013 Eric Thoms (MISO) Gas Electric System Interface Study PPA Stakeholder Forum: MISO ENGCTF 6/03/2013 Eric Thoms (MISO) Table of Contents History Participating Planning Authorities (PPAs) / Study Region PPA Stakeholder Groups

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. PJM Interconnection, LLC ) Docket No. ER10-2280-000

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. PJM Interconnection, LLC ) Docket No. ER10-2280-000 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, LLC ) Docket No. ER10-2280-000 MOTION TO INTERVENE AND COMMENTS OF THE AMERICAN PUBLIC POWER ASSOCIATION In

More information

135 FERC 61,202 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

135 FERC 61,202 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 135 FERC 61,202 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, John R. Norris, and Cheryl A. LaFleur. Entergy

More information

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-29

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-29 SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-29 EXPERIMENTAL PRICE PLAN FOR TIME-OF-USE SERVICE WITH SUPER OFF-PEAK FOR ELECTRIC VEHICLES Effective: April 2015 Billing Cycle AVAILABILITY:

More information

Physical Natural Gas

Physical Natural Gas Risk Management 101 Physical Natural Gas Gas Measurement Mcf Thousand cubic feet Volumetric measurement MMBtu Million British Thermal Units Heating value measurement of gas based on a standard heat value

More information

131 FERC 61,157 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER GRANTING WAIVER. (Issued May 25, 2010)

131 FERC 61,157 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER GRANTING WAIVER. (Issued May 25, 2010) 131 FERC 61,157 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, and John R. Norris. Hudson Transmission Partners,

More information

Monitoring Competitive Markets

Monitoring Competitive Markets Monitoring Competitive Markets Pennsylvania Public Utility Commission John A. Levin, Assistant Counsel Statutory Authority Pennsylvania Public Utility Commission Pennsylvania Public Utility Code Business

More information

Request for Information on Evolving Treasury Market Structure (Docket No. TREAS-DO-2015-0013)

Request for Information on Evolving Treasury Market Structure (Docket No. TREAS-DO-2015-0013) , 2016 VIA ONLINE SUBMISSION (http://regulations.gov) David R. Pearl Office of the Executive Secretary U.S. Department of the Treasury 1500 Pennsylvania Avenue, NW Washington, DC 20220 Re: Request for

More information

Demand Response Management System ABB Smart Grid solution for demand response programs, distributed energy management and commercial operations

Demand Response Management System ABB Smart Grid solution for demand response programs, distributed energy management and commercial operations Demand Response Management System ABB Smart Grid solution for demand response programs, distributed energy management and commercial operations Utility Smart Grid programs seek to increase operational

More information

CABINET. 24 March 2015

CABINET. 24 March 2015 CABINET 24 March 2015 Title: Procurement of Electricity and Gas Supplies Report of the Cabinet Member for Finance Open Report with Exempt Appendix 4 Wards Affected: All Report Author: Andrew Sivess Group

More information

134 FERC 61,226 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON COMPLIANCE FILING. (Issued March 24, 2011)

134 FERC 61,226 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON COMPLIANCE FILING. (Issued March 24, 2011) 134 FERC 61,226 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, John R. Norris, and Cheryl A. LaFleur. Southern

More information

Reliability Options in Ireland and Northern Ireland Obligations and Penalties

Reliability Options in Ireland and Northern Ireland Obligations and Penalties Reliability Options in Ireland and Northern Ireland Obligations and Penalties European Commission Technical Working Group on Energy: Subgroup on generation adequacy 14 April, Brussels Background Single

More information

June 2015. Position Paper Contribution to the debate on electricity market design and capacity markets

June 2015. Position Paper Contribution to the debate on electricity market design and capacity markets June 2015 Position Paper Contribution to the debate on electricity market design and capacity markets Eurogas is the association representing the European gas wholesale, retail and distribution sectors.

More information

Summary: Gas Balancing Study Austria

Summary: Gas Balancing Study Austria : On behalf of: Energie-Control Austria, Rudolfsplatz 13a, 1010 Wien, Austria Prepared by: KEMA Consulting GmbH, Kurt-Schumacher-Str. 8 53113 Bonn, Germany Bonn, May 2012 Copyright 2012, KEMA Consulting

More information

Multi-Faceted Solution for Managing Flexibility with High Penetration of Renewable Resources

Multi-Faceted Solution for Managing Flexibility with High Penetration of Renewable Resources Multi-Faceted Solution for Managing Flexibility with High Penetration of Renewable Resources FERC Technical Conference Increasing RT & DA Market Efficiency Through Improved Software June 24 26, 2013 Nivad

More information

U.S. DEPARTMENT OF COMMERCE NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY

U.S. DEPARTMENT OF COMMERCE NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY U.S. DEPARTMENT OF COMMERCE NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY ) Developing a Framework ) To Improve ) Docket No. 130208119-3119-01 Critical Infrastructure Cybersecurity ) ) RESPONSE OF THE

More information

The Levy Control Framework

The Levy Control Framework Report by the Comptroller and Auditor General Department of Energy & Climate Change The Levy Control Framework HC 815 SESSION 2013-14 27 NOVEMBER 2013 4 Key facts The Levy Control Framework Key facts 2bn

More information

On November 17, 2015, Chicago Board Options Exchange, Incorporated ( CBOE or

On November 17, 2015, Chicago Board Options Exchange, Incorporated ( CBOE or (SECURITIES AND EXCHANGE COMMISSION) (Release No. 34-76909; File No. SR-CBOE-2015-106) January 14, 2016 Self-Regulatory Organizations; Chicago Board Options Exchange, Incorporated; Order Approving a Proposed

More information

In the Matter of a Generic Proceeding to Establish Uniform Policies and Guidelines for a Standard Service Package

In the Matter of a Generic Proceeding to Establish Uniform Policies and Guidelines for a Standard Service Package UNITED STATES OF AMERICA FEDERAL TRADE COMMISSION WASHINGTON, D.C. 20580 Before the ARKANSAS PUBLIC SERVICE COMMISSION In the Matter of a Generic Proceeding to Establish Uniform Policies and Guidelines

More information

Note No. 141 April 1998. The United States enjoys a highly competitive natural gas market and an increasingly efficient

Note No. 141 April 1998. The United States enjoys a highly competitive natural gas market and an increasingly efficient Privatesector P U B L I C P O L I C Y F O R T H E Note No. 141 April 1998 Development of Competitive Natural Gas Markets in the United States Andrej Juris The United States enjoys a highly competitive

More information

NEW ENGLAND GAS-ELECTRIC FOCUS GROUP FINAL REPORT

NEW ENGLAND GAS-ELECTRIC FOCUS GROUP FINAL REPORT I. Introduction NEW ENGLAND GAS-ELECTRIC FOCUS GROUP FINAL REPORT March 28, 2014 New England s increasing dependence on natural gas as a generation fuel, and the implications that such dependence has for

More information

FILED IN THE MATTER OF THE P TITION OF ) ENTERGY ARKANSAS, INC. FOR AN ) ACCOUNTING ORDER AUTHORIZING ) ESTABLISHMENT OF A REGULATORY )

FILED IN THE MATTER OF THE P TITION OF ) ENTERGY ARKANSAS, INC. FOR AN ) ACCOUNTING ORDER AUTHORIZING ) ESTABLISHMENT OF A REGULATORY ) BEFORE THE r r r ARKANSAS PUBLIC SERVICE COMMI&@ FILED IN THE MATTER OF THE P TITION OF ) ENTERGY ARKANSAS, INC. FOR AN ) ACCOUNTING ORDER AUTHORIZING ) ESTABLISHMENT OF A REGULATORY ) DOCKET NO. 08 -

More information

Request for Proposals For Renewable Energy Power Purchase Agreement

Request for Proposals For Renewable Energy Power Purchase Agreement Request for Proposals For Renewable Energy Power Purchase Agreement Issued by PowerOptions, Inc. October 2, 2015 Contents 1) Introduction... 1 a) PowerOptions Program... 2 b) Contracting Parties... 3 c)

More information

Doubts About State-Mandated Power Contracts

Doubts About State-Mandated Power Contracts Portfolio Media. Inc. 860 Broadway, 6th Floor New York, NY 10003 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com Doubts About State-Mandated Power Contracts Law360,

More information

Public Roundtable on. PR 18-502, Medicare Supplement Insurance. Minimum Standards Approval Resolution of 2009".

Public Roundtable on. PR 18-502, Medicare Supplement Insurance. Minimum Standards Approval Resolution of 2009. Government of the District of Columbia Department of Insurance, Securities and Banking Testimony of Philip Barlow Associate Commissioner Public Roundtable on PR 18-502, Medicare Supplement Insurance Minimum

More information

STATEMENT OF NATURE, REASONS AND BASIS

STATEMENT OF NATURE, REASONS AND BASIS March 27, 2015 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Dear Ms. Bose: Re: Docket No. RP15- Compliance with Order No. 801 on Pipeline

More information

Energy and Consumer Impacts of EPA s Clean Power Plan. Prepared for the American Coalition for Clean Coal Electricity

Energy and Consumer Impacts of EPA s Clean Power Plan. Prepared for the American Coalition for Clean Coal Electricity Energy and Consumer Impacts of EPA s Clean Power Plan Prepared for the American Coalition for Clean Coal Electricity Contents Executive Summary Overview of the Clean Power Plan NERA Methodology Baseline

More information

131 FERC 61,148 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON COMPLIANCE FILING. (Issued May 20, 2010)

131 FERC 61,148 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON COMPLIANCE FILING. (Issued May 20, 2010) 131 FERC 61,148 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, and John R. Norris. California Independent

More information