1 California Independent System Operator Memo To: ISO Board of Governors From: Greg Cook, Senior Policy Analyst/Market Surveillance Committee Liaison CC: ISO Officers Date: September 28, 2000 Re: Management Response to MSC June Price Spikes Opinion INTRODUCTION At the September 8, 2000 board meeting, Frank Wolak, Chair of the Market Surveillance Committee (MSC), presented the findings of MSC s analysis of the June 2000 Price Spikes experienced in the California energy and ancillary services markets. The MSC identified market design flaws that they believe have significantly hindered market performance. The first design flaw outlined by the MSC in their report is that regulatory constraints on forward contracting for energy and ancillary services by utility distribution companies (UDCs), along with the failure of the UDCs to fully utilize the limited authority they had to enter into forward contracts has significantly hindered market performance. The MSC also contends that the lack of a price-responsive final demand and the ISO s policies with respect to the purchase of replacement reserves and the ISO s method for allocating the cost of these purchases also contributed to poor market performance. This memo responds to Chair Smutny-Jones request for a management response to the September 6, 2000 MSC report An Analysis of the June 2000 Price Spikes in the California ISO s Energy and Ancillary Services Markets. The ISO management in large part concurs with the assertions and solutions referenced in the report and has been developing recommendations to address these market issues based on the MSC s recommendations. This memo summarizes the main points of the MSC report and the management response. UNDER-SCHEDULING Since the first summer of operation of the California electricity market, during high load conditions there has been significant under-scheduling of load and generation on a day-ahead and hourahead basis relative to real-time electricity consumption and production. Under these system conditions, substantial amounts of generation and load often do not submit day-ahead or hourahead schedules and instead choose to trade in the ISO s real-time imbalance energy market. Trading a significant amount of load and generation in the real-time market can considerably reduce system reliability. As a result of this concern, in mid-august 1999 the ISO Board GCook Page 1 9/29/00

2 implemented a Replacement Reserve procurement mechanism and cost allocation scheme designed to eliminate the reliability problems caused by large quantities of generation and load showing up in real-time during high load hours. The MSC report describes the replacement reserve cost allocation scheme implemented in August of 1999 and its unintended consequences for the exercise of market power. The MSC previously commented on the proposal in a March 1999 report. The MSC s March 1999 Report noted that the implicit tax on shifting load from the ISO s real-time market to the PX markets may increase prices in both the PX and real-time market. The ISO recognized that the proposal would act as a tax on load that shifted to the real-time market and that it would provide load an incentive to purchase more energy in the PX market at a higher price. This was precisely the intent of the proposal. The ISO agrees with the MSC s most recent conclusion that the current replacement reserve procurement mechanism and cost allocation scheme has increased the expected revenues available to generation unit owners from under-scheduling. The combination of the replacement reserve cost allocation scheme and the June 2000 ISO price caps on adjustment bids and real-time energy also provides Load Serving Entities (LSEs) with an incentive to bid a zero demand into the PX at a price of $750/MWh, adding to the under-scheduling problem. Thus, the ISO agrees with the MSC that there have been possible adverse impacts of the current deviation replacement reserve cost allocation scheme and is evaluating possible alternatives, including the recent MSC recommendations. OUT-OF-MARKET PAYMENT MECHANISM The ISO Tariff permits the ISO to make Out-Of-Market (OOM) purchases when it anticipates the amount of energy available through the real-time market will be insufficient to meet system demand and when there are specific location energy requirements that cannot be met by resources having standing market bids or through the dispatch of RMR units. Prior to January 2000, in-state generators that were called Out-Of-Market were paid the ISO s hourly ex-post prices. In response to complaints from generator owners that the hourly ex-post price did not adequately compensate them for their full operating costs, the ISO developed and alternative payment option. The alternative payment option pays generators called out of market both a capacity component and an energy component as well as verifiable fuel related start-up costs and gas imbalance charges that result from the ISO OOM call. The MSC outlines in their report that the ISO s recently adopted alternative OOM payment scheme has increased the attractiveness to generators of not participating in any of the California energy and ancillary services markets. The MSC recommends that the ISO eliminate the current Out-of-Market (OOM) payment mechanism and replace it with a scheme that makes receipt of OOM calls always less attractive to suppliers than participating in the markets. The ISO would like to clarify that it offered the current alternative OOM payment to generators because there are often times when the ISO needs to call on units OOM for only a few hours of the day. Often, the energy prices during those hours cannot adequately compensate generation unit owners for their running costs. In such cases, the ISO policy has been to make generators whole with respect to their running costs. The ISO does not feel that it could justify ordering generation units to run at a loss. In addition, although the potential GCook Page 2 9/29/00

3 for withholding exists under the current structure, there is no strong evidence that the current OOM mechanism was problematic during the summer of However, the ISO believes that there is merit in discussing the new MSC recommendation further with the MSC to find a solution that would be acceptable to the FERC and would not provide the withholding incentives referenced by the MSC in their report. 10-MINUTE SETTLEMENTS The MSC indicates in their report that there are two potential market power problems associated with the ISO s ten-minute settlement scheme. The first relates to what the ISO calls residual imbalance energy. Under this scheme, the ISO attempts to make the distinction between generators who deviate from their schedules because they responded to the ISO s dispatch instructions in a previous settlement period and those who deviate from their schedules without instructions from the ISO. The MSC indicates that attempts to distinguish between different types of energy supplied within the same time period creates incentives for generation unit owners to have their energy classified as the one that is paid the higher price, often with detrimental impacts on system reliability and spot price volatility. Specifically, under this scheme it is possible for two generators with the same forward schedules and real-time production to be paid differently by the ISO for imbalance energy they supply. The MSC notes that the other problem associated with the ten-minute settlement is the creation of potentially two prices within each ten-minute interval in order for the ISO operator to have the tools to provide the necessary signals to generators to meet the ISO s frequency control requirements. The MSC contends that the reliability problem that led to the creation of two prices within a ten-minute interval can be overcome by setting a single price at a five-minute interval. The ISO agrees with the MSC that attempts to distinguish between different types of energy supplied within the same period creates incentives for generation unit owners to have their energy classified as the one that is paid the higher price. Ten-minute settlements do create incentives for generation unit owners to have their real-time energy receive the highest price. However, the mechanism is designed such that the highest price will always be for instructed energy rather than uninstructed energy. The ISO believes that creating incentives for generators to follow dispatch instructions rather than operate uninstructed improves reliability. The ISO will further analyze the MSC s recommendations regarding 10-minute settlements including looking at a five-minute settlement alternative which the MSC indicates would create stronger incentives for maintaining system reliability. PG&E HYDRO DIVESTITURE In August of this year, the ISO and PG&E entered a market power mitigation agreement regarding the divestiture of PG&E s hydro generation portfolio. The MSC s report indicates that the proposed agreement between the ISO and PG&E does not sufficiently take into account the potentially serious market power implications of the agreement. The MSC contends that the agreement GCook Page 3 9/29/00

4 places too much focus on enhancing system reliability and fails to adequately address market power concerns. The MSC recommends in their report to delay the divestiture of PG&E s hydro generation units and for the ISO to reconsider its proposed hydro market power mitigation agreement with PG&E. The MSC contends that the proposed agreement does not appear to offer any guarantee that wholesale prices will not be adversely impacted by the transfer of PG&E s hydro portfolio from a market participant with an incentive to keep wholesale prices low to a market participant with an incentive to achieve high wholesale prices. The ISO agrees with the MSC that the divestiture of PG&E s hydro portfolio will have a large impact on the energy and ancillary service markets. This is precisely why the ISO developed the market power mitigation agreement with PG&E. The ISO acknowledges that no market power mitigation measure is perfect. Instead, the ISO believes that it is important to balance the need to effectively mitigate market power with the objective of allowing the markets to operate without undue regulatory intervention. Moreover, since the market power mitigation agreement is the product of a negotiation, the agreement reflects and balances the concerns of the parties to the negotiation. Nonetheless, the ISO believes that the ISO-PG&E agreement would reduce the ability of PG&E CalHydro to exert market power while minimizing any reduction in the value of the hydro portfolio. Moreover, the agreement allows the ISO to seek additional protections if circumstances change or if it becomes evident that the agreement is insufficient to address market power. Finally, the ISO has not taken a position on whether or when divestiture should occur; instead the ISO has focussed on ensuring that whatever approach the California Public Utilities Commission adopts for disposing of the hydro units, the approach includes mechanisms to minimize the potential for the exercise of market power. This remains a very high priority for the ISO. FORWARD CONTRACTING The MSC report focuses significant attention on insufficient forward market hedging in California s energy and ancillary services markets. The MSC notes that had California s three UDCs signed forward financial contracts equal to their expected net demand for energy and ancillary services during each hour of the months of May and June of 2000, average prices in the PX and ISO markets during these months would have been significantly lower. Even if the June 2000 price spikes had still occurred, the UDCs would have been largely insulated from this spot market price volatility with forward hedges. The MSC outlined the significant benefits to load serving entities from purchasing forward financial contracts. First, the MSC notes that forward market purchases limit the spot price exposure faced by a load serving entity in that it is subject to spot price risk on its real-time energy requirements only to the extent that they differ from its forward market purchases. The second source of benefits noted by the MSC is that forward market purchases from a generation unit owner limits the incentives the supplier has to exercise market power in the spot market. In addition, forward purchases of energy and capacity would have induced the market participants who sold these contracts to bid more aggressively into the ISO s energy and ancillary services market, thereby reducing their incentive to exercise market power during high load conditions. GCook Page 4 9/29/00

5 The ISO agrees strongly with the MSC that forward contracting by market participants will reduce the risk of price spikes and is an important element of a competitive electric market. The ISO supports the MSC recommendation to eliminate restrictions on how, with whom, and how much forward contracting UDCs can engage in energy and ancillary services. Place Greater Emphasis on Market Power Implications of Reliability Proposals The MSC recommends that the ISO Board and Staff place a greater emphasis on the market power implications of proposals designed to improve reliability. The ISO management agrees that it is very important to consider the market power implications of any proposed market rule changes. Moreover, the ISO has implemented a number of market reforms based on recommendations from the MSC including: - The ISO spent over a year renegotiating its Reliability Must-Run Contracts to address market power concerns raised by the MSC and Department of Market Analysis, - Most of the reforms to the ISO s ancillary service market were based on recommendations from the MSC, and - The MSC has been actively involved in reviewing the ongoing effort to redesign the ISO s Congestion Management Market and has provided significant input on design elements that mitigate market power in the procurement of local reliability services. Staff will continue to strive to consider the market power implications of any proposal designed to improve system reliability. The ISO Staff will continue to work with the MSC to carefully evaluate each of the recommendations in the report and to implement market designs that will not only improve the reliability of the system, but provide the proper incentives to facilitate workably competitive energy and ancillary services markets. GCook Page 5 9/29/00

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market CALIFORNIA ISO Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market Prepared by the Department of Market Analysis California Independent System Operator September 1999 Table of Contents Executive

More information

Measurement and Mitigation of Market Power in Wholesale Electricity Markets

Measurement and Mitigation of Market Power in Wholesale Electricity Markets Measurement and Mitigation of Market Power in Wholesale Electricity Markets Frank A. Wolak Department of Economics Stanford University Stanford, CA 94305-6072 [email protected] http://www.stanford.edu/~wolak

More information

BUSINESS RULES GOVERNING CONTINGENCY RESERVE PROVIDED BY BATCH-LOAD DEMAND RESPONSE

BUSINESS RULES GOVERNING CONTINGENCY RESERVE PROVIDED BY BATCH-LOAD DEMAND RESPONSE BUSINESS RULES GOVERNING CONTINGENCY RESERVE PROVIDED BY BATCH-LOAD DEMAND RESPONSE This paper describes the issues associated with using Batch-Load Demand Response i resources to provide Contingency Reserve

More information

Table of Contents. Real-Time Reliability Must Run Unit Commitment and Dispatch (Formerly G-203) Operating Procedure

Table of Contents. Real-Time Reliability Must Run Unit Commitment and Dispatch (Formerly G-203) Operating Procedure No. 2310 Table of Contents Purpose... 2 1. Responsibilities... 2 2. Scope/Applicability... 2 2.1 Background... 2 2.2 Scope / Applicability... 2 3. Detail... 3 3.1 Energy Dispatching... 3 3.1.2 Real-Time

More information

Ten Myths About Competitive Electricity Markets: Lessons for Designing Congestion Management Protocols

Ten Myths About Competitive Electricity Markets: Lessons for Designing Congestion Management Protocols Ten Myths About Competitive Electricity Markets: Lessons for Designing Congestion Management Protocols Frank A. Wolak Department of Economics Stanford University Stanford, CA 94305-6072 [email protected]

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Price Formation in Energy and ) Docket No. AD14-14-000 Ancillary Services Markets Operated ) By Regional Transmission Organizations

More information

Real-Time Pricing and Demand Side Participation in Restructured Electricity Markets

Real-Time Pricing and Demand Side Participation in Restructured Electricity Markets Real-Time Pricing and Demand Side Participation in Restructured Electricity Markets Robert H. Patrick Frank A. Wolak Graduate School of Management Department of Economics Rutgers University Stanford University

More information

Comments on ISO s Third Revised Straw Proposal for Settlement of Interties in Real-Time

Comments on ISO s Third Revised Straw Proposal for Settlement of Interties in Real-Time Comments on ISO s Third Revised Straw Proposal for Settlement of Interties in Real-Time Department of Market Monitoring July 26, 2012 Summary The Department of Market Monitoring (DMM) appreciates the opportunity

More information

Generator Optional. Timeline including the next steps. A practical example. Potential benefits of OFA? Key implications. How might OFA work?

Generator Optional. Timeline including the next steps. A practical example. Potential benefits of OFA? Key implications. How might OFA work? Generator Optional Firm Access Rights Australian Energy Market Commission announces terms of reference for detailed design work On the 6 March 2014, the Australian Energy Market Commission (AEMC) released

More information

Comments on the California ISO MRTU LMP Market Design

Comments on the California ISO MRTU LMP Market Design Comments on the California ISO MRTU LMP Market Design SCOTT M. HARVEY, SUSAN L. POPE LECG, LLC Cambridge, Massachusetts 02138 WILLIAM W. HOGAN Center for Business and Government John F. Kennedy School

More information

June 2015. Position Paper Contribution to the debate on electricity market design and capacity markets

June 2015. Position Paper Contribution to the debate on electricity market design and capacity markets June 2015 Position Paper Contribution to the debate on electricity market design and capacity markets Eurogas is the association representing the European gas wholesale, retail and distribution sectors.

More information

2010 STATE OF THE MARKET REPORT

2010 STATE OF THE MARKET REPORT 2010 STATE OF THE MARKET REPORT FOR THE ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market August 2011 TABLE OF CONTENTS Executive Summary...

More information

PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations

PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations PJM Overview and Wholesale Power Markets John Gdowik PJM Member Relations PJM s Role Ensures the reliability of the high-voltage electric power system Coordinates and directs the operation of the region

More information

The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D.

The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D. The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D. Why not use the Web to buy and sell transmission rights at prices derived from bids

More information

Measuring Unilateral Market Power in Wholesale Electricity Markets: The California Market, 1998 2000

Measuring Unilateral Market Power in Wholesale Electricity Markets: The California Market, 1998 2000 Measuring Unilateral Market Power in Wholesale Electricity Markets: The California Market, 1998 2000 By FRANK A. WOLAK* * Department of Economics, Stanford University, Stanford, CA 94305-6072, and NBER

More information

Introduction to Ontario's Physical Markets

Introduction to Ontario's Physical Markets Introduction to Ontario's Physical Markets Introduction to Ontario s Physical Markets AN IESO MARKETPLACE TRAINING PUBLICATION This document has been prepared to assist in the IESO training of market

More information

A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM)

A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) Non-technical summary High level design Draft Decision Paper SEM -14-047 June 2014 1 INTRODUCTION

More information

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Ross Baldick Copyright c 2015 Ross Baldick www.ece.utexas.edu/ baldick/classes/394v/ee394v.html Title Page 1 of 29

More information

Overview of Reliability Demand Response Resource

Overview of Reliability Demand Response Resource Overview of Reliability Demand Response Resource Radha Madrigal Customer Service Department May 8, 2014 Agenda Product overview and purpose Define Reliability Demand Response Resource Agreements & registration

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. ER15-1783-000 Operator Corporation ) ANSWER OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR

More information

Ancillary Services and Flexible Generation

Ancillary Services and Flexible Generation Ancillary Services and Flexible Generation Contents Ancillary Services Overview Types of Ancillary Services Market Impact Benefits of Medium Speed Solution Contact Information What are Ancillary Services?

More information

Aliso Canyon Gas-Electric Coordination. Straw Proposal

Aliso Canyon Gas-Electric Coordination. Straw Proposal Aliso Canyon Gas-Electric Coordination Straw Proposal April 15, 2016 Table of Contents 1. Executive Summary... 3 2. Plan for Stakeholder Engagement... 4 3. Background... 5 3.1. Aliso Canyon Impact... 5

More information

6. It lengthened its payables period, thereby shortening its cash cycle.

6. It lengthened its payables period, thereby shortening its cash cycle. Answers to Concepts Review and Critical Thinking Questions 1. These are firms with relatively long inventory periods and/or relatively long receivables periods. Thus, such firms tend to keep inventory

More information

Electricity Market Management: The Nordic and California Experiences

Electricity Market Management: The Nordic and California Experiences Electricity Market Management: The Nordic and California Experiences Thomas F. Rutherford Energy Economics and Policy Lecture 11 May 2011 This talk is based in part on material pepared by Einar Hope, Norwegian

More information

Computing the Electricity Market Equilibrium: Uses of market equilibrium models

Computing the Electricity Market Equilibrium: Uses of market equilibrium models Computing the Electricity Market Equilibrium: Uses of market equilibrium models Ross Baldick Department of Electrical and Computer Engineering The University of Texas at Austin April 2007 Abstract We discuss

More information

Energy in the Wholesale Market December 5, 2012 1:30 p.m. to 3:30 p.m. Irving, Texas Robert Burke, Principal Analyst ISO New England

Energy in the Wholesale Market December 5, 2012 1:30 p.m. to 3:30 p.m. Irving, Texas Robert Burke, Principal Analyst ISO New England Business Models for Transactive Energy in the Wholesale Market December 5, 2012 1:30 p.m. to 3:30 p.m. Irving, Texas Robert Burke, Principal Analyst ISO New England About ISO New England (ISO) Not-for-profit

More information

FERC Workshop on Price Formation: Scarcity and Shortage Pricing, Offer Mitigation, and Offer Caps in RTO and ISO Markets (Docket. No.

FERC Workshop on Price Formation: Scarcity and Shortage Pricing, Offer Mitigation, and Offer Caps in RTO and ISO Markets (Docket. No. FERC Workshop on Price Formation: Scarcity and Shortage Pricing, Offer Mitigation, and Offer Caps in RTO and ISO Markets (Docket. No. AD14-14-000) October 28, 2014 Market Presentation Design Title & Analysis

More information

Chapter 13 Managing Demand-Side Economic and Political Constraints on Electricity Industry Restructuring Processes

Chapter 13 Managing Demand-Side Economic and Political Constraints on Electricity Industry Restructuring Processes Chapter 13 Managing Demand-Side Economic and Political Constraints on Electricity Industry Restructuring Processes Abstract Frank A. Wolak This paper identifies the major political and economic constraints

More information

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) Paul L. Joskow September 28, 2007 ALTERNATIVE SYSTEM OPERATOR MODELS System operator (SO) is vertically integrated utility (G+T) Functional

More information

The UK Electricity Market Reform and the Capacity Market

The UK Electricity Market Reform and the Capacity Market The UK Electricity Market Reform and the Capacity Market Neil Bush, Head Energy Economist University Paris-Dauphine Tuesday 16 th April, 2013 Overview 1 Rationale for Electricity Market Reform 2 Why have

More information

THE FINANCIAL AND PHYSICAL INSURANCE BENEFITS OF PRICE-RESPONSIVE DEMAND

THE FINANCIAL AND PHYSICAL INSURANCE BENEFITS OF PRICE-RESPONSIVE DEMAND THE FINANCIAL AND PHYSICAL INSURANCE BENEFITS OF PRICE-RESPONSIVE DEMAND Eric Hirst Consulting in Electric-Industry Restructuring 16 Capital Circle Oak Ridge, Tennessee 3783 January 22 1. INTRODUCTION

More information

Overview of the IESO-Administered Markets. IESO Training. Updated: January, 2014. Public

Overview of the IESO-Administered Markets. IESO Training. Updated: January, 2014. Public Overview of the IESO-Administered Markets IESO Training Updated: January, 2014 Public Overview of the IESO-Administered Markets AN IESO TRAINING PUBLICATION This guide has been prepared to assist in the

More information

Different types of electricity markets modelled using PLEXOS Integrated Energy Model The UK Balancing Market example

Different types of electricity markets modelled using PLEXOS Integrated Energy Model The UK Balancing Market example Different types of electricity markets modelled using PLEXOS Integrated Energy Model The UK Balancing Market example Peny Panagiotakopoulou, Senior Power Systems Consultant, Energy Exemplar Europe Overview

More information

2. Executive Summary. Emissions Trading Systems in Europe and Elsewhere

2. Executive Summary. Emissions Trading Systems in Europe and Elsewhere 2. Executive Summary With the introduction of CO 2 emission constraints on power generators in the European Union, climate policy is starting to have notable effects on energy markets. This paper sheds

More information

ERCOT Monthly Operational Overview (March 2014) ERCOT Public April 15, 2014

ERCOT Monthly Operational Overview (March 2014) ERCOT Public April 15, 2014 ERCOT Monthly Operational Overview (March 2014) ERCOT Public April 15, 2014 Grid Operations & Planning Summary March 2014 Operations The peak demand of 54,549 MW on March 3 rd was greater than the mid-term

More information

Workshop B. 11:15 a.m. to 12:30 p.m.

Workshop B. 11:15 a.m. to 12:30 p.m. Workshop B Advanced Energy Management Tools: Benefitting from the Competitive Electricity Marketplace Beyond the Fixed Rate & Key Issues to Understand when Comparing Electricity Quotes 11:15 a.m. to 12:30

More information

From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer

From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer Date: September

More information

PRICE FORMATION IN ISOs AND RTOs PRINCIPLES AND IMPROVEMENTS

PRICE FORMATION IN ISOs AND RTOs PRINCIPLES AND IMPROVEMENTS Economic Consulting PRICE FORMATION IN ISOs AND RTOs PRINCIPLES AND IMPROVEMENTS SUSAN L. POPE 1 October 2014 Executive Summary Assessment of concerns about price formation and prompt action to address

More information

153 FERC 61,221 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DIRECTING REPORTS. (Issued November 20, 2015) TABLE OF CONTENTS

153 FERC 61,221 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DIRECTING REPORTS. (Issued November 20, 2015) TABLE OF CONTENTS 153 FERC 61,221 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. Price Formation in

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Reliability Technical Conference Docket No. AD16-15-000 Prepared Statement of Mark Rothleder on behalf of the California Independent System

More information

Wind Power and Electricity Markets

Wind Power and Electricity Markets PO Box 2787 Reston, VA 20195 Phone: 703-860-5160 Fax: 703-860-3089 E-mail: [email protected] Web: www.uwig.org Wind Power and Electricity Markets A living summary of markets and market rules for wind energy

More information

2013 STATE OF THE MARKET REPORT ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market

2013 STATE OF THE MARKET REPORT ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market 2013 STATE OF THE MARKET REPORT FOR THE ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market September 2014 TABLE OF CONTENTS Executive

More information

Demand Response in Capacity and Electricity Markets: What Role Can and Should It Play?

Demand Response in Capacity and Electricity Markets: What Role Can and Should It Play? Demand Response in Capacity and Electricity Markets: What Role Can and Should It Play? Professor Joel B. Eisen Austin Owen Research Fellow University of Richmond School of Law Austin Electricity Conference

More information

Energy Efficiency and Demand Response Programs in the United States

Energy Efficiency and Demand Response Programs in the United States Energy Efficiency and Demand Response Programs in the United States Structure, Operations, Accomplishments, Lessons Learned Claude Godin Director Energy Data Analytics Overview Introduction - Definitions

More information

Evaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042. Market Subcommittee (MSC) May 3, 2016

Evaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042. Market Subcommittee (MSC) May 3, 2016 Evaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042 Market Subcommittee (MSC) May 3, 2016 Purpose Purpose and Key Takeaways Review proposed FERC Energy Offer Cap rules, and potential

More information

market design policy paper

market design policy paper market design policy paper 15 September 2014 1 introduction Ensuring economic growth, jobs, secure coverage of basic needs at an affordable and competitive price, and sustainable use of limited resources

More information

Operating Hydroelectric and Pumped Storage Units In A Competitive Environment

Operating Hydroelectric and Pumped Storage Units In A Competitive Environment Operating electric and Pumped Storage Units In A Competitive Environment By Rajat Deb, PhD 1 LCG Consulting In recent years as restructuring has gained momentum, both new generation investment and efficient

More information

Contracts for Difference - the new support regime for low carbon generation

Contracts for Difference - the new support regime for low carbon generation Contracts for Difference - the new support regime for low carbon generation James Taylor Raj Bavishi 11 November 2014 UK Incentive Regimes Small scale Feed in Tariffs and the Renewables Obligations have

More information

How To Settle Day Ahead Energy, Loss, And Loss For A Day Ahead Market

How To Settle Day Ahead Energy, Loss, And Loss For A Day Ahead Market Settling the Day-Ahead Market Charge Codes included in this training: 6011, 6800, 6700, 6301. EXTERNAL Customer Services Page 1 of 45 Disclaimer All information contained in this document is provided for

More information

WHITE PAPER THE NIAGARA FRAMEWORK A PLATFORM FOR DEMAND RESPONSE

WHITE PAPER THE NIAGARA FRAMEWORK A PLATFORM FOR DEMAND RESPONSE WHITE PAPER WP THE NIAGARA FRAMEWORK A PLATFORM FOR DEMAND RESPONSE The Niagara Framework A Platform for Demand Response Executive Summary A PLATFORM FOR DEMAND REPONSE The Federal Energy Regulatory Commission

More information

Presentation for The National Commission for Energy State Regulation of Ukraine

Presentation for The National Commission for Energy State Regulation of Ukraine Presentation for The National Commission for Energy State Regulation of Ukraine Todd Keech Laura Walter PJM Interconnection June 17, 2014 What is PJM? 1 What is PJM? ISO RTO Map Part of Eastern Interconnection

More information

Electricity Exchanges in South Asia The Indian Energy Exchange Model

Electricity Exchanges in South Asia The Indian Energy Exchange Model Electricity Exchanges in South Asia The Indian Energy Exchange Model 18 Mar 14 Rajesh K Mediratta Director (BD) [email protected] www.iexindia.com In this presentation Overview - Indian Market

More information

Uplift in RTO and ISO Markets

Uplift in RTO and ISO Markets i Staff Analysis of Uplift in RTO and ISO Markets August 2014 For further information, please contact: William Sauer Office of Energy Policy and Innovation Federal Energy Regulatory Commission 888 First

More information

sink asset load power pool ISO pool participant bids operating constraints ancillary service declarations

sink asset load power pool ISO pool participant bids operating constraints ancillary service declarations G1 DEFINITIONS In the ISO rules: acceptable operational reason means with respect to a source asset, any one or more of the following: i) a circumstance related to the operation of the generating asset

More information

SCHEDULE 1. Scheduling, System Control and Dispatch Service

SCHEDULE 1. Scheduling, System Control and Dispatch Service Seventh Revised Volume No. 5 (MT) Original Sheet No. 71 SCHEDULE 1 Scheduling, System Control and Dispatch Service This service is required to schedule the movement of power through, out of, within, or

More information

An Overview of the Midwest ISO Market Design. Michael Robinson 31 March 2009

An Overview of the Midwest ISO Market Design. Michael Robinson 31 March 2009 An Overview of the Midwest ISO Market Design Michael Robinson 31 March 2009 The Role of RTOs Monitor flow of power over the grid Schedule transmission service Perform transmission security analysis for

More information

Enabling 24/7 Automated Demand Response and the Smart Grid using Dynamic Forward Price Offers

Enabling 24/7 Automated Demand Response and the Smart Grid using Dynamic Forward Price Offers Enabling 24/7 Automated Demand Response and the Smart Grid using Dynamic Forward Price Offers Presented to ISO/RTO Council by Edward G. Cazalet, PhD The Cazalet Group [email protected] www.cazalet.com 650-949-0560

More information

Overview and Comparison of Demand Response Programs in North American Electricity Markets

Overview and Comparison of Demand Response Programs in North American Electricity Markets , pp.22-29 http://dx.doi.org/10.14257/astl.205.97.04 Overview and Comparison of Demand Response Programs in North American Electricity Markets Pedro Faria 1, Zita Vale 1 1 GECAD Knowledge Engineering and

More information

Two Settlement - Virtual Bidding and Transactions

Two Settlement - Virtual Bidding and Transactions Two Settlement - Virtual Bidding and Transactions (Fall 2009) PJM 2009 2009 PJM 1 Agenda Two-Settlement Overview Two-Settlement Features & System Two-Settlement Business Rules Two-Settlement Data Requirements

More information

Informational Report of the California Independent System Operator Corporation

Informational Report of the California Independent System Operator Corporation California Independent System Operator Corporation June 30, 2016 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: Informational

More information

Is It Possible to Charge Market-Based Pricing for Ancillary Services in a Non-ISO Market?

Is It Possible to Charge Market-Based Pricing for Ancillary Services in a Non-ISO Market? Is It Possible to Charge Market-Based Pricing for Ancillary Services in a Non-ISO Market? Regulation and Operating Reserves 33 rd Eastern Conference Center for Research in Regulated Industry Romkaew P.

More information

Demand Response Programs: Lessons from the Northeast

Demand Response Programs: Lessons from the Northeast Demand Response Programs: Lessons from the Northeast Charles Goldman E. O. Lawrence Berkeley National Laboratory [email protected] Mid Atlantic Demand Response Initiative Meeting Baltimore MD December

More information