STOCHASTIC SCHEDULING

Size: px
Start display at page:

Download "STOCHASTIC SCHEDULING"

Transcription

1 STOCHSTIC SCHEDULING Scheduling with Uncertain Durations Some scheduling procedures explicitly consider the uncertainty in activity duration estimates by using the probabilistic distribution of activity durations. That is, the duration of a particular activity is assumed to be a random variable that is distributed in a particular fashion. For example, an activity duration might be assumed to be distributed as a normal or a beta distributed random variable as illustrated in Figure 1. This figure shows the probability or chance of experiencing a particular activity duration based on a probabilistic distribution. The beta distribution is often used to characterize activity durations, since it can have an absolute minimum and an absolute maximum of possible duration times. The normal distribution is a good approximation to the beta distribution in the center of the distribution and is easy to work with, so it is often used as an approximation. Figure 1: Beta and Normally Distributed ctivity Durations If a standard random variable is used to characterize the distribution of activity durations, then only a few parameters are required to calculate the probability of any particular duration. Still, the estimation problem is increased considerably since more than one parameter is required to characterize most of the probabilistic distribution used to represent activity durations. For the beta distribution, three or four parameters are required depending on its generality, whereas the normal distribution requires two parameters. The most common formal approach to incorporate uncertainty in the scheduling process is to apply the critical path scheduling process and then analyze the results from a probabilistic perspective. 1

2 This process is usually referred to as the Program Evaluation and Review Technique (PERT) method. s noted earlier, the duration of the critical path represents the minimum time required to complete the project. Using expected activity durations and critical path scheduling, a critical path of activities can be identified. This critical path is then used to analyze the duration of the project incorporating the uncertainty of the activity durations along the critical path. The expected project duration is equal to the sum of the expected durations of the activities along the critical path. ssuming that activity durations are independent random variables, the variance or variation in the duration of this critical path is calculated as the sum of the variances along the critical path. With the mean and variance of the identified critical path known, the distribution of activity durations can also be computed. Program Evaluation and Review Technique Both CPM and PERT were introduced at approximately the same time and, despite their separate origins, they were very similar. The PERT method shares many similarities with CPM. Both require that a project be broken down into activities that could be presented in the form of a network diagram showing their sequential relationships to one another. Both require time estimates for each activity, which are used in routine calculations to determine project duration and scheduling data for each activity. CPM requires a reasonably accurate knowledge of time and cost for each activity. In many situations, however, the duration of an activity can not be accurately forecasted, and a degree of uncertainty exists. Contrary to CPM, PERT introduces uncertainty into the estimates for activity and project durations. It is well suited for those situations where there is either insufficient background information to specify accurately time and cost or where project activities require research and development. In the original development of PERT approach, O notations are used. However, ON diagramming can be easily used alternatively. The method is based on the well-known central limit theorem. The theorem states that: Where a series of sequential independent activities lie on the critical path of a network, the sum of the individual activity durations will be distributed in approximately normal fashion, regardless of the distribution of the individual activities themselves. The mean of the distribution of the sum of the activity durations will be the sum of the means of the individual activities and its variance will be the sum of the activities variances. The primary assumptions of PERT can be summarized as follows: 1. ny PERT path must have enough activities to make central limit theorem valid.. The mean of the distribution of the path with the greatest duration, from the initial node to a given node, is given by the maximum mean of the duration distribution of the paths entering the node.. PERT critical path is longer enough than any other path in the network. PERT, unlike CPM, uses three time estimates for each activity. These estimates of the activity duration enable the expected mean time, as well as the standard deviation and variance, to be derived mathematically. These duration estimates are: - Optimistic duration (a); an estimate of the minimum time required for an activity if exceptionally good luck is experienced.

3 - Most likely or modal time (m); the time required if the activity is repeated a number of times under essentially the same conditions. - Pessimistic duration (b); an estimate of the maximum time required if unusually bad luck is experienced. These three time estimates become the framework on which the probability distribution curve for the activity is erected. Many authors argue that beta distribution is mostly fit construction activities. The use of these optimistic, most likely, and pessimistic estimates stems from the fact that these are thought to be easier for managers to estimate subjectively. The formulas for calculating the mean and variance are derived by assuming that the activity durations follow a probabilistic beta distribution under a restrictive condition. The probability density function of a beta distributions for a random variable x is given by: α β f(x) = k(x - a) (x -b), a x b, α, β > 1 (1) where k is a constant which can be expressed in terms of α and β. Several beta distributions for different sets of values of α and β are shown in Figure. Figure : Illustration of Several Beta Distributions Using beta distribution, simple approximations are made for the activities mean time and its standard deviation. Using the three times estimates, the expected mean time (t e ) is derived using Eq.. Then, t e is used as the best available time approximation for the activity in question. The standard deviation is given by Eq., and hence the variance (ν) can be determined as ν = σ.

4 a + m + b t e = () b a σ = () By adopting activity expected mean time, the critical path calculations proceed as CPM. ssociated with each duration in PERT, however, is its standard deviation or its variance. The project duration is determined by summing up the activity expected mean time along the critical path and thus will be an expected mean duration. Since the activities on the critical path are independent of each other, central limit theory gives the variance of the project duration as the sum of the individual variances of these critical path activities. Once the expected mean time for project duration (T X ) and its standard deviation (σ X ) are determined, it is possible to calculate the chance of meeting a specific project duration (T S ). Then normal probability tables are used to determine such chance using Equation. T T S T Z = X () σ S TX + Z * X = σ is an equivalent form of Equation.1, which enables the scheduled time for an X event to be determined based on a given risk level. The procedure for hand probability computations using PERT can be summarized in the following steps: 1. Make the usual forward and backward pass computations based on a single estimate (mean) for each activity.. Obtain estimates for a, m, and b for only critical activities. If necessary, adjust the length of the critical path as dictated by the new t e values based on a, m, and b.. Compute the variance for event x (ν X ) by summing the variances for the critical activities leading to event x.. Compute Z using Equation and find the corresponding normal probability. Consider the nine activity example project shown in Table 1. Suppose that the project have very uncertain activity time durations. s a result, project scheduling considering this uncertainty is desired. Table 1: Precedence Relations and Durations for a 9-ctivity Project Example ctivity Description Predecessors Duration B C D E F G H I Site clearing Removal of trees General excavation Grading general area Excavation for trenches Placing formwork and RFT for concrete Installing sewer lines Installing other utilities Pouring concrete B, C B, C D, E D, E F, G 9 1

5 Table shows the estimated optimistic, most likely and pessimistic durations for the nine activities. From these estimates, the mean, variance and standard deviation are calculated. In Figure, PERT calculations are performed very similar to that of CPM, considering the mean duration of each activity. Table : ctivity Duration Estimates for the 9-ctivity Project ctivity Duration Standard Mean a m b Deviation B C D E F G H I D H C E G..0 I B. 1.0 F Figure : PERT Calculations for 9-ctivity Example The critical path for this project ignoring uncertainty in activity durations consists of activities, C, F and I. pplying the PERT analysis procedure suggests that the duration of the project would be approximately normally distributed. The sum of the means for the critical activities is = 0.0 days, and the sum of the variances is (0.) + (0.) + (0.) + (0.) = 1. leading to a standard deviation of 1. days. With a normally distributed project duration, the probability of meeting a project deadline can be computed using Equation (). For example, the probability of project completion within days is: 0 Z = =.1 1.

6 where z is the standard normal distribution tabulated value of the cumulative standard distribution, which can be determined form standard tables of normal distribution. From Table, the probability of completing the project in days is 100%. -σ -σ -σ 0 -σ -σ -σ Figure : Normal Distribution Curve Table : rea under the Normal Curve Measured from the Center SD rea % from the center SD rea % from the center 0.1σ Example: Suppose that a network has been developed for a particular project with non-deterministic durations for the activities and the completion time for that network is 0 days and the sum of the standard deviation for the activities on the critical path is 10. Find the probability that the project will be completed in 00 days. Solution:

7 First, convert the normal random variable to the standard normal random variable. T S T Z = X = (00 0) /. = - 0. σ X From Table, the corresponding probability = 1.% Then, the probability to complete the project in 00 days = 0 1. =.%. Example: Given the information from the previous example, what is the duration that you can give with 90 percent assurance? Solution: From tables find the value of z corresponding to probability of 0%, thud yields z = 1. the, apply z into equation : 1. = (t 0) /. or t =. x = 0 days..10 Criticisms to Program Evaluation and Review Technique While the PERT method has been made widely available, it suffers from three major problems. First, the procedure focuses upon a single critical path, when many paths might become critical due to random fluctuations. For example, suppose that the critical path with longest expected time happened to be completed early. Unfortunately, this does not necessarily mean that the project is completed early since another path or sequence of activities might take longer. Similarly, a longer than expected duration for an activity not on the critical path might result in that activity suddenly becoming critical. s a result of the focus on only a single path, the PERT method typically underestimates the actual project duration. s a second problem with the PERT procedure, it is incorrect to assume that most construction activity durations are independent random variables. In practice, durations are correlated with one another. For example, if problems are encountered in the delivery of concrete for a project, this problem is likely to influence the expected duration of numerous activities involving concrete pours on a project. Positive correlations of this type between activity durations imply that the PERT method underestimates the variance of the critical path and thereby produces over-optimistic expectations of the probability of meeting a particular project completion deadline. Finally, the PERT method requires three duration estimates for each activity rather than the single estimate developed for critical path scheduling. Thus, the difficulty and labor of estimating activity characteristics is multiplied threefold.

8 MONTE CRLO SIMULTION Monte Carlo Simulation Characteristics: - Replaces analytic solution with raw computing power. - voids need to simplify to get analytic solution - No need to assume functional form of activity/project distributions. - Used by Van Slyke (19). - llows determining the criticality index of an activity (Proportion of runs in which the activity was in the critical path). - Hundreds to thousands of simulations needed. Monte Carlo Simulation Process: - Set the duration distribution for each activity. - No functional form of distribution assumed. - Could be joint distribution for multiple activities. - Iterate: for each trial ( realization ) - Sample random duration from each distributions - Find critical path & durations with standard CPM; Record these results - Report recorded results Report recorded results. - Duration distribution - Per--node criticality index (% runs where critical) Network Example ctivity Optimistic time, a Most likely time, m Pessimistic time, b Expected value, d Standard deviation, s B C D E F G

9 Summary of Simulation Runs for Example Project Run ctivity Duration Number B C D E F G Project Duration Distribution Critical Path -D-F-G -D-F-G Completion Time Then the probability that a project ends in a specific time (t) equals number of times the project finished in less than or Equal to t divided by the total number of replications. For example, the probability that the project ends in 0 weeks or less is: P( 0 ) = 1 / 0 = %. Criticality Index Criticality index is defined as the proportion of runs in which the activity was in the critical path. PERT assumes binary (either 100% or 0%). 9

A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com

A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com 2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com

More information

Project Scheduling: PERT/CPM

Project Scheduling: PERT/CPM Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times (as in exercises 1, 2, 3 and 5 in the handout) and considering Time-Cost Trade-Offs (as in exercises 4 and 6 in the handout). This

More information

Project Scheduling: PERT/CPM

Project Scheduling: PERT/CPM Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project

More information

Project Planning and Scheduling

Project Planning and Scheduling Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination

More information

Operational Research. Project Menagement Method by CPM/ PERT

Operational Research. Project Menagement Method by CPM/ PERT Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your

More information

Chapter 11 Monte Carlo Simulation

Chapter 11 Monte Carlo Simulation Chapter 11 Monte Carlo Simulation 11.1 Introduction The basic idea of simulation is to build an experimental device, or simulator, that will act like (simulate) the system of interest in certain important

More information

CRASHING-RISK-MODELING SOFTWARE (CRMS)

CRASHING-RISK-MODELING SOFTWARE (CRMS) International Journal of Science, Environment and Technology, Vol. 4, No 2, 2015, 501 508 ISSN 2278-3687 (O) 2277-663X (P) CRASHING-RISK-MODELING SOFTWARE (CRMS) Nabil Semaan 1, Najib Georges 2 and Joe

More information

A Robustness Simulation Method of Project Schedule based on the Monte Carlo Method

A Robustness Simulation Method of Project Schedule based on the Monte Carlo Method Send Orders for Reprints to reprints@benthamscience.ae 254 The Open Cybernetics & Systemics Journal, 2014, 8, 254-258 Open Access A Robustness Simulation Method of Project Schedule based on the Monte Carlo

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

Scheduling. Anne Banks Pidduck Adapted from John Musser

Scheduling. Anne Banks Pidduck Adapted from John Musser Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart

More information

Amajor benefit of Monte-Carlo schedule analysis is to

Amajor benefit of Monte-Carlo schedule analysis is to 2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to

More information

Quantitative Risk Analysis with Microsoft Project

Quantitative Risk Analysis with Microsoft Project Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials

More information

8. Project Time Management

8. Project Time Management 8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT 11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and

More information

PERT/CPM. Network Representation:

PERT/CPM. Network Representation: - 1 - PERT/CPM PERT Program Evaluation & Review Technique It is generally used for those projects where time required to complete various activities are not known as a priori. It is probabilistic model

More information

Schedule Risk Analysis Simulator using Beta Distribution

Schedule Risk Analysis Simulator using Beta Distribution Schedule Risk Analysis Simulator using Beta Distribution Isha Sharma Department of Computer Science and Applications, Kurukshetra University, Kurukshetra, Haryana (INDIA) ishasharma211@yahoo.com Dr. P.K.

More information

Profit Forecast Model Using Monte Carlo Simulation in Excel

Profit Forecast Model Using Monte Carlo Simulation in Excel Profit Forecast Model Using Monte Carlo Simulation in Excel Petru BALOGH Pompiliu GOLEA Valentin INCEU Dimitrie Cantemir Christian University Abstract Profit forecast is very important for any company.

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Using simulation to calculate the NPV of a project

Using simulation to calculate the NPV of a project Using simulation to calculate the NPV of a project Marius Holtan Onward Inc. 5/31/2002 Monte Carlo simulation is fast becoming the technology of choice for evaluating and analyzing assets, be it pure financial

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT 6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity

More information

EXAM EXEMPLAR QUESTIONS

EXAM EXEMPLAR QUESTIONS Level 6 Professional Diploma in Procurement and Supply PD5 - Programme and project management EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 10 QUALIFICATIONS 2013 QUESTIONS

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

Application Survey Paper

Application Survey Paper Application Survey Paper Project Planning with PERT/CPM LINDO Systems 2003 Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) are two closely related techniques for monitoring

More information

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking

More information

B. 2-4-6 D. 3-4-5 E. 3-5-7 F. 5-7-9

B. 2-4-6 D. 3-4-5 E. 3-5-7 F. 5-7-9 Lesson 01 Project Management Solutions #1: The network diagram for a project is shown below, with three time estimates (optimistic, most likely, and pessimistic) for each activity. Activity times are in

More information

SENSITIVITY ANALYSIS AND INFERENCE. Lecture 12

SENSITIVITY ANALYSIS AND INFERENCE. Lecture 12 This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike License. Your use of this material constitutes acceptance of that license and the conditions of use of materials on this

More information

Project Scheduling. Introduction

Project Scheduling. Introduction Project Scheduling Introduction In chapter, the O and ON networks were presented, also the time and cost of individual activities based were calculated. Yet, however, we do not know how long is the total

More information

CHAPTER 1. Basic Concepts on Planning and Scheduling

CHAPTER 1. Basic Concepts on Planning and Scheduling CHAPTER 1 Basic Concepts on Planning and Scheduling Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the selection and ordering of activities as well as

More information

CHAPTER 8 PROJECT TIME-COST TRADE-OFF

CHAPTER 8 PROJECT TIME-COST TRADE-OFF CHAPTER 8 PROJECT TIME-COST TRADE-OFF In the previous chapters, duration of activities discussed as either fixed or random numbers with known characteristics. However, activity durations can often vary

More information

Network Calculations

Network Calculations Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks

More information

Cambridge International AS and A Level Computer Science

Cambridge International AS and A Level Computer Science Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains

More information

10 Project Management with PERT/CPM

10 Project Management with PERT/CPM 10 Project Management with PERT/CPM 468 One of the most challenging jobs that any manager can take on is the management of a large-scale project that requires coordinating numerous activities throughout

More information

Scheduling Resources and Costs

Scheduling Resources and Costs Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used

More information

Econ 132 C. Health Insurance: U.S., Risk Pooling, Risk Aversion, Moral Hazard, Rand Study 7

Econ 132 C. Health Insurance: U.S., Risk Pooling, Risk Aversion, Moral Hazard, Rand Study 7 Econ 132 C. Health Insurance: U.S., Risk Pooling, Risk Aversion, Moral Hazard, Rand Study 7 C2. Health Insurance: Risk Pooling Health insurance works by pooling individuals together to reduce the variability

More information

CPM-200: Principles of Schedule Management

CPM-200: Principles of Schedule Management CPM-: Principles of Schedule Management Lesson B: Critical Path Scheduling Techniques Instructor Jim Wrisley IPM Fall Conference PMI-College of Performance Management Professional Education Program Copyright

More information

SYSM 6304: Risk and Decision Analysis Lecture 5: Methods of Risk Analysis

SYSM 6304: Risk and Decision Analysis Lecture 5: Methods of Risk Analysis SYSM 6304: Risk and Decision Analysis Lecture 5: Methods of Risk Analysis M. Vidyasagar Cecil & Ida Green Chair The University of Texas at Dallas Email: M.Vidyasagar@utdallas.edu October 17, 2015 Outline

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides

More information

Project management: a simulation-based optimization method for dynamic time-cost tradeoff decisions

Project management: a simulation-based optimization method for dynamic time-cost tradeoff decisions Rochester Institute of Technology RIT Scholar Works Theses Thesis/Dissertation Collections 2009 Project management: a simulation-based optimization method for dynamic time-cost tradeoff decisions Radhamés

More information

PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT)

PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT) PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT) ABSTRACT Category: Planning/ Monitoring - Control KEYWORDS Program (Project) Evaluation and Review Technique (PERT) (G) is a project management tool used

More information

22 Project Management with PERT/CPM

22 Project Management with PERT/CPM hil61217_ch22.qxd /29/0 05:58 PM Page 22-1 22 C H A P T E R Project Management with PERT/CPM One of the most challenging jobs that any manager can take on is the management of a large-scale project that

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

The Binomial Probability Distribution

The Binomial Probability Distribution The Binomial Probability Distribution MATH 130, Elements of Statistics I J. Robert Buchanan Department of Mathematics Fall 2015 Objectives After this lesson we will be able to: determine whether a probability

More information

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define

More information

Journal of Financial and Economic Practice

Journal of Financial and Economic Practice Analyzing Investment Data Using Conditional Probabilities: The Implications for Investment Forecasts, Stock Option Pricing, Risk Premia, and CAPM Beta Calculations By Richard R. Joss, Ph.D. Resource Actuary,

More information

The work breakdown structure can be illustrated in a block diagram:

The work breakdown structure can be illustrated in a block diagram: 1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as

More information

State-Based Probabilistic Scheduling Using STROBOSCOPE s CPM Add-On

State-Based Probabilistic Scheduling Using STROBOSCOPE s CPM Add-On Proceedings, Construction Congress V, ASCE Stuart D. Anderson,ed State-Based Probabilistic Scheduling Using STROBOSCOPE s CPM Add-On by Julio C. Martinez 1 and Photios G. Ioannou 2 Abstract Critical path

More information

Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition:

Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition: Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition: 1. Activity : It is a particular work of a project which consumes some resources (in ) & time. It is shown as & represented

More information

CRASHING PERT NETWORKS: A SIMULATION APPROACH

CRASHING PERT NETWORKS: A SIMULATION APPROACH CRASHING PERT NETWORKS: A SIMULATION APPROACH Wayne A. Haga Assistant Professor of Computer Information Systems Metropolitan State College of Denver P.O. Box 173362, Campus Box 45 Denver, CO 80217-3362

More information

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) are scheduling techniques used to plan, schedule, budget

More information

ANALYSIS OF PROJECT PLANNING USING CPM AND PERT

ANALYSIS OF PROJECT PLANNING USING CPM AND PERT ANALYSIS OF PROJECT PLANNING USING CPM AND PERT Rogelio Acuña Spring 2010 In Partial Fulfillment of Math 4395-Senior Project Department of Computer and Mathematical Sciences Faculty Advisor: Dr. Timothy

More information

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST Priti Singh Astt. Prof.-MCA Department OCM, Bhopal preitisingh@rediffmail.com Florentin Smarandache Chair of Department of Mathematics

More information

COMPUTING DURATION, SLACK TIME, AND CRITICALITY UNCERTAINTIES IN PATH-INDEPENDENT PROJECT NETWORKS

COMPUTING DURATION, SLACK TIME, AND CRITICALITY UNCERTAINTIES IN PATH-INDEPENDENT PROJECT NETWORKS Proceedings from the 2004 ASEM National Conference pp. 453-460, Alexandria, VA (October 20-23, 2004 COMPUTING DURATION, SLACK TIME, AND CRITICALITY UNCERTAINTIES IN PATH-INDEPENDENT PROJECT NETWORKS Ryan

More information

Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D.

Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D. Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D. Critical Path Method Scheduling - Some Important Reservations The critical path method (CPM) of scheduling a project is a key tool for project

More information

Measurement with Ratios

Measurement with Ratios Grade 6 Mathematics, Quarter 2, Unit 2.1 Measurement with Ratios Overview Number of instructional days: 15 (1 day = 45 minutes) Content to be learned Use ratio reasoning to solve real-world and mathematical

More information

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities

More information

Software Project Scheduling under Uncertainties

Software Project Scheduling under Uncertainties Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials

More information

PROGRAMMING TECHNIQUES. Chapter 5(Part 2)

PROGRAMMING TECHNIQUES. Chapter 5(Part 2) PROGRAMMING TECHNIQUES Chapter 5(Part 2) LEARNING OUTCOME At the end of this lesson, students will be able to: Understand the different types of planning techniques. Understand the network analysis. Formulate

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project

More information

Introduction to. Hypothesis Testing CHAPTER LEARNING OBJECTIVES. 1 Identify the four steps of hypothesis testing.

Introduction to. Hypothesis Testing CHAPTER LEARNING OBJECTIVES. 1 Identify the four steps of hypothesis testing. Introduction to Hypothesis Testing CHAPTER 8 LEARNING OBJECTIVES After reading this chapter, you should be able to: 1 Identify the four steps of hypothesis testing. 2 Define null hypothesis, alternative

More information

CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan

CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan CISC 322 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan Project A project is a temporary endeavour undertaken to create a "unique" product or service A project is composed of a number

More information

A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry

A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry Pranam B 1, Madhusudan G Kalibhat 2, Sudharshan KR 3 1 Student, Master of Technology (Construction

More information

INT 3 Schedule Risk Analysis

INT 3 Schedule Risk Analysis INT 3 Schedule Risk Analysis David T. Hulett, Ph.D. Hulett & Associates, LLC ICEAA Professional Development and Training Workshop San Diego, CA June 9-12, 2015 1 Agenda Add uncertainty to the schedule,

More information

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical

More information

Prof. Olivier de Weck

Prof. Olivier de Weck ESD.36 System Project Management + Lecture 9 Probabilistic Scheduling Instructor(s) Prof. Olivier de Weck Dr. James Lyneis October 4, 2012 Today s Agenda Probabilistic Task Times PERT (Program Evaluation

More information

SE351a: Software Project & Process Management

SE351a: Software Project & Process Management SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management

More information

An introduction to Value-at-Risk Learning Curve September 2003

An introduction to Value-at-Risk Learning Curve September 2003 An introduction to Value-at-Risk Learning Curve September 2003 Value-at-Risk The introduction of Value-at-Risk (VaR) as an accepted methodology for quantifying market risk is part of the evolution of risk

More information

Analyzing Portfolio Expected Loss

Analyzing Portfolio Expected Loss Analyzing Portfolio Expected Loss In this white paper we discuss the methodologies that Visible Equity employs in the calculation of portfolio expected loss. Portfolio expected loss calculations combine

More information

CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL

CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL Jan, Shu-Hui Ph.D. Student Construction Engineering & Management Program Department of Civil Engineering National Taiwan University

More information

Scheduling: Program Evaluation and Review Technique Networks and Linear Operations

Scheduling: Program Evaluation and Review Technique Networks and Linear Operations Chapter 9 Scheduling: Program Evaluation and Review Technique Networks and Linear Operations CONTENTS Lean Construction 9. Introduction 9. An Example Program Evaluation and Review Technique Network 6 9.

More information

Pr(X = x) = f(x) = λe λx

Pr(X = x) = f(x) = λe λx Old Business - variance/std. dev. of binomial distribution - mid-term (day, policies) - class strategies (problems, etc.) - exponential distributions New Business - Central Limit Theorem, standard error

More information

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control Activity Definition Input Work Breakdown Structure Scope Statement Historical Information

More information

Matching Investment Strategies in General Insurance Is it Worth It? Aim of Presentation. Background 34TH ANNUAL GIRO CONVENTION

Matching Investment Strategies in General Insurance Is it Worth It? Aim of Presentation. Background 34TH ANNUAL GIRO CONVENTION Matching Investment Strategies in General Insurance Is it Worth It? 34TH ANNUAL GIRO CONVENTION CELTIC MANOR RESORT, NEWPORT, WALES Aim of Presentation To answer a key question: What are the benefit of

More information

Chapter 11: PERT for Project Planning and Scheduling

Chapter 11: PERT for Project Planning and Scheduling Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex

More information

PROJECT RISK ANALYSIS AND MANAGEMENT

PROJECT RISK ANALYSIS AND MANAGEMENT PROJECT RISK ANALYSIS AND MANAGEMENT A GUIDE BY THE ASSOCIATION FOR PROJECT MANAGEMENT (formerly The Association Of Project Managers) Compiled from information provided by members of the Special Interest

More information

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project

More information

Simulator for Optimization of Software Project Cost and Schedule

Simulator for Optimization of Software Project Cost and Schedule Journal of Computer Science 4 (12): 1030-1035, 2008 ISSN 1549-3636 2008 Science Publications Simulator for Optimization of Software Project Cost and Schedule 1 P.K. Suri and 2 Bharat Bhushan 1 Department

More information

Project Management Chapter 3

Project Management Chapter 3 Project Management Chapter 3 How Project Management fits the Operations Management Philosophy Operations As a Competitive Weapon Operations Strategy Project Management Process Strategy Process Analysis

More information

Risk Analysis and Quantification

Risk Analysis and Quantification Risk Analysis and Quantification 1 What is Risk Analysis? 2. Risk Analysis Methods 3. The Monte Carlo Method 4. Risk Model 5. What steps must be taken for the development of a Risk Model? 1.What is Risk

More information

Monte Carlo Schedule Risk Analysis

Monte Carlo Schedule Risk Analysis Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials

More information

Cumulative Diagrams: An Example

Cumulative Diagrams: An Example Cumulative Diagrams: An Example Consider Figure 1 in which the functions (t) and (t) denote, respectively, the demand rate and the service rate (or capacity ) over time at the runway system of an airport

More information

The Performance of Option Trading Software Agents: Initial Results

The Performance of Option Trading Software Agents: Initial Results The Performance of Option Trading Software Agents: Initial Results Omar Baqueiro, Wiebe van der Hoek, and Peter McBurney Department of Computer Science, University of Liverpool, Liverpool, UK {omar, wiebe,

More information

The Procedures of Monte Carlo Simulation (and Resampling)

The Procedures of Monte Carlo Simulation (and Resampling) 154 Resampling: The New Statistics CHAPTER 10 The Procedures of Monte Carlo Simulation (and Resampling) A Definition and General Procedure for Monte Carlo Simulation Summary Until now, the steps to follow

More information

Problem of the Month Through the Grapevine

Problem of the Month Through the Grapevine The Problems of the Month (POM) are used in a variety of ways to promote problem solving and to foster the first standard of mathematical practice from the Common Core State Standards: Make sense of problems

More information

Chapter 4: Project Time Management

Chapter 4: Project Time Management Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

A successful market segmentation initiative answers the following critical business questions: * How can we a. Customer Status.

A successful market segmentation initiative answers the following critical business questions: * How can we a. Customer Status. MARKET SEGMENTATION The simplest and most effective way to operate an organization is to deliver one product or service that meets the needs of one type of customer. However, to the delight of many organizations

More information

PROJECT COMPLETION PROBABILITY AFTER CRASHING PERT/CPM NETWORK

PROJECT COMPLETION PROBABILITY AFTER CRASHING PERT/CPM NETWORK PROJECT COMPLETION PROBABILITY AFTER CRASHING PERT/CPM NETWORK M Nazrul, ISLAM 1, Eugen, DRAGHICI 2 and M Sharif, UDDIN 3 1 Jahangirnagar University, Bangladesh, islam_ju@yahoo.com 2 Lucian Blaga University

More information

Overview of Violations of the Basic Assumptions in the Classical Normal Linear Regression Model

Overview of Violations of the Basic Assumptions in the Classical Normal Linear Regression Model Overview of Violations of the Basic Assumptions in the Classical Normal Linear Regression Model 1 September 004 A. Introduction and assumptions The classical normal linear regression model can be written

More information

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning

More information

Chapter 1 Introduction. 1.1 Introduction

Chapter 1 Introduction. 1.1 Introduction Chapter 1 Introduction 1.1 Introduction 1 1.2 What Is a Monte Carlo Study? 2 1.2.1 Simulating the Rolling of Two Dice 2 1.3 Why Is Monte Carlo Simulation Often Necessary? 4 1.4 What Are Some Typical Situations

More information

An Introduction to Variable-Energy-Resource Integration Analysis Energy Exemplar October 2011

An Introduction to Variable-Energy-Resource Integration Analysis Energy Exemplar October 2011 An Introduction to Variable-Energy-Resource Integration Analysis Energy Exemplar October 2011 1. Introduction Increased Renewable Portfolio Standards (RPS) are being enacted at the state, provincial, and

More information

Event Chain Methodology in Project Management

Event Chain Methodology in Project Management Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials

More information

Project Planning, Scheduling and Control: Assignment 2 D. U. Singer Hospital Products Corp.

Project Planning, Scheduling and Control: Assignment 2 D. U. Singer Hospital Products Corp. Project Planning, Scheduling and Control: Assignment 2 D. U. Singer Hospital Products Corp. Code for Course: MBL45-5 Assignment Number: 2 Student number: 75-163-3 Group Code Number: BOT1 Table of Contents

More information

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps Project Planning What are you going to do in the project? Lecture Objectives To discuss the tasks in planning a project To describe the tools that can be used for developing a project plan To illustrate

More information

CRITERIUM FOR FUNCTION DEFININING OF FINAL TIME SHARING OF THE BASIC CLARK S FLOW PRECEDENCE DIAGRAMMING (PDM) STRUCTURE

CRITERIUM FOR FUNCTION DEFININING OF FINAL TIME SHARING OF THE BASIC CLARK S FLOW PRECEDENCE DIAGRAMMING (PDM) STRUCTURE st Logistics International Conference Belgrade, Serbia 8-30 November 03 CRITERIUM FOR FUNCTION DEFININING OF FINAL TIME SHARING OF THE BASIC CLARK S FLOW PRECEDENCE DIAGRAMMING (PDM STRUCTURE Branko Davidović

More information

The Math. P (x) = 5! = 1 2 3 4 5 = 120.

The Math. P (x) = 5! = 1 2 3 4 5 = 120. The Math Suppose there are n experiments, and the probability that someone gets the right answer on any given experiment is p. So in the first example above, n = 5 and p = 0.2. Let X be the number of correct

More information

Probability and Statistics Prof. Dr. Somesh Kumar Department of Mathematics Indian Institute of Technology, Kharagpur

Probability and Statistics Prof. Dr. Somesh Kumar Department of Mathematics Indian Institute of Technology, Kharagpur Probability and Statistics Prof. Dr. Somesh Kumar Department of Mathematics Indian Institute of Technology, Kharagpur Module No. #01 Lecture No. #15 Special Distributions-VI Today, I am going to introduce

More information

1.7 Graphs of Functions

1.7 Graphs of Functions 64 Relations and Functions 1.7 Graphs of Functions In Section 1.4 we defined a function as a special type of relation; one in which each x-coordinate was matched with only one y-coordinate. We spent most

More information

BPEL disadvantage: more time to product BPEL advantage: better reusability, analysis

BPEL disadvantage: more time to product BPEL advantage: better reusability, analysis Modeling Page 1 To BPEL or not to BPEL? 5:56 PM To BPEL or not to BPEL? BPEL disadvantage: more time to product BPEL advantage: better reusability, analysis Modeling Page 2 A tale of two strategies 5:57

More information

CHAPTER 2 Estimating Probabilities

CHAPTER 2 Estimating Probabilities CHAPTER 2 Estimating Probabilities Machine Learning Copyright c 2016. Tom M. Mitchell. All rights reserved. *DRAFT OF January 24, 2016* *PLEASE DO NOT DISTRIBUTE WITHOUT AUTHOR S PERMISSION* This is a

More information