The Critical Path. Practical Management of Construction Delay & Disruption The Belfrey, June 14 th & 15 th 2011

Size: px
Start display at page:

Download "The Critical Path. Practical Management of Construction Delay & Disruption The Belfrey, June 14 th & 15 th 2011"

Transcription

1 The Critical Path Practical Management of Construction Delay & Disruption The Belfrey, June 14 th & 15 th 2011 David Tyerman, Athena Project Services

2 Module Overview: The critical path Schedule integrity The baseline, as-planned or contract programme

3 The Critical Path

4 The Critical Path a schematic and written description of the sequence of work that a contractor plans to use to complete the project within the contractually prescribed time. It is based upon a network, which is a graphic diagram displaying all of the activities that must be accomplished to construct the project, as well as their mutual time dependencies and durations. Work activities are linked together to show their interdependency or logic. Network logic is the planned sequence in which activities are to be performed, with the start if some activities logically dependant, or restrained, by the completion of other activities, and some activities dependant of others and hence capable of being performed concurrently. A series of activities that precede and follow each other constitute a path. The critical path is the longest path from notice to proceed to project completion, or the path with the least amount of slack or float (Galaxy Builders inc. ASBCA Nos and 50136, para 6)

5 The Critical Path

6 The Critical Path the sequence of events through a project network from start to finish, the sum of whose duration determines the overall project duration BS6079-2:2000 pt2, 2.41

7 The Critical Path Task A Task B Start Finish Task C Task D

8 The Critical Path deterministic duration

9 The Critical Path O M P

10 The Critical Path

11 The Critical Path Any extension to time must prove that a delaying event has had an effect on the project critical path and has therefore extended the overall project duration Any delay on a non-critical path activity (or activities) must therefore consume the amount of float available to the work-stream Simples!

12 Schedule Integrity

13 Schedule Integrity Are the logical interdependencies applied between project events correct? Do they contain an overuse of activity lags? Are there any open-ended ended activities, that is, activities without any predecessors or successors (other than the start and finish milestones, all project activities should have at least one predecessor and successor). Are activities unduly constrained? Are the project calendars correct i.e. have they assumed the correct period of available working time? Are any resources applied to activities correct? Are the progress values assigned to project activities correct? Can they be corroborated with supporting contemporary data? Do the remaining activity durations reflect the known work content and resource productivity achieved? Can a report of assumptions be readily found and audited?

14 Useful Case Law ''The respondent was entitled to respond to the claim both by arguing that the variations, late information and so on relied on by the claimant did not cause any delay because they were not on the critical path and positively by arguing g that the true cause of delay was other matters''. Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd

15 Useful Case Law ''Crucial questions are (a) is the delay in the critical path and, if so, (b) is it caused by MBST? If the answer to the first question if 'Yes' and the second question is 'No' then I must assess how many additional working days should be included.'' Motherwell Bridge Construction Ltd v Micafil Vakuumtechnik

16 Useful Case Law Balfour Beatty Construction Ltd v The Mayor and Burgess of the London Borough of Lambeth '''Despite the fact that the dispute concerned a multi-million pound refurbishment contract, no attempt was made to provide any critical path. The work itself was no more complex than many other projects where a CPN [critical path network] is routinely established and maintained. It seems that BB had not prepared or maintained a proper programme during the execution of the works. By now, one would have thought that it was well understood that, on a contract of this kind, in order to attack, on the facts, a clause 24 certificate for non-completion (or an extension of time determined under clause 25), the foundation must be the original programme (if capable of justification and substantiation to show its validity and reliability as a contractual starting point) and its success will similarly depend on the soundness of its revisions on the occurrence of every event, so as to be able to provide a satisfactory and convincing demonstration of cause and effect. A valid critical path (or paths) has to be established both initially and at every later material point since it (or they) will almost certainly change. Some means has also to be established for demonstrating the effect of concurrent or parallel delays or other matters for which h the employer will not be responsible under the contract.'' t

17 Useful Case Law Balfour Beatty Construction Ltd v The Mayor and Burgess of the London Borough of Lambeth '''Despite the fact that the dispute concerned a multi-million pound refurbishment contract, no attempt was made to provide any critical path. The work itself was no more complex than many other projects where a CPN [critical path network] is routinely established and maintained. It seems that BB had not prepared or maintained a proper programme during the execution of the works. By now, one would have thought that it was well understood that, on a contract of this kind, in order to attack, on the facts, a clause 24 certificate for non-completion (or an extension of time determined under clause 25), the foundation must be the original programme (if capable of justification and substantiation to show its validity and reliability as a contractual starting point) and its success will similarly depend on the soundness of its revisions on the occurrence of every event, so as to be able to provide a satisfactory and convincing demonstration of cause and effect. A valid critical path (or paths) has to be established both initially and at every later material point since it (or they) will almost certainly change. Some means has also to be established for demonstrating the effect of concurrent or parallel delays or other matters for which h the employer will not be responsible under the contract.'' t

18 Useful Case Law Balfour Beatty Construction Ltd v The Mayor and Burgess of the London Borough of Lambeth '''Despite the fact that the dispute concerned a multi-million pound refurbishment contract, no attempt was made to provide any critical path. The work itself was no more complex than many other projects where a CPN [critical path network] is routinely established and maintained. It seems that BB had not prepared or maintained a proper programme during the execution of the works. By now, one would have thought that it was well understood that, on a contract of this kind, in order to attack, on the facts, a clause 24 certificate for non-completion (or an extension of time determined under clause 25), the foundation must be the original programme (if capable of justification and substantiation to show its validity and reliability as a contractual starting point) and its success will similarly depend on the soundness of its revisions on the occurrence of every event, so as to be able to provide a satisfactory and convincing demonstration of cause and effect. A valid critical path (or paths) has to be established both initially and at every later material point since it (or they) will almost certainly change. Some means has also to be established for demonstrating the effect of concurrent or parallel delays or other matters for which h the employer will not be responsible under the contract.'' t

19 Useful Case Law Balfour Beatty Construction Ltd v The Mayor and Burgess of the London Borough of Lambeth '''Despite the fact that the dispute concerned a multi-million pound refurbishment contract, no attempt was made to provide any critical path. The work itself was no more complex than many other projects where a CPN [critical path network] is routinely established and maintained. It seems that BB had not prepared or maintained a proper programme during the execution of the works. By now, one would have thought that it was well understood that, on a contract of this kind, in order to attack, on the facts, a clause 24 certificate for non-completion (or an extension of time determined under clause 25), the foundation must be the original programme (if capable of justification and substantiation to show its validity and reliability as a contractual starting point) and its success will similarly depend on the soundness of its revisions on the occurrence of every event, so as to be able to provide a satisfactory and convincing demonstration of cause and effect. A valid critical path (or paths) has to be established both initially and at every later material point since it (or they) will almost certainly change. Some means has also to be established for demonstrating the effect of concurrent or parallel delays or other matters for which h the employer will not be responsible under the contract.'' t

20 Useful Case Law Balfour Beatty Construction Ltd v The Mayor and Burgess of the London Borough of Lambeth '''Despite the fact that the dispute concerned a multi-million pound refurbishment contract, no attempt was made to provide any critical path. The work itself was no more complex than many other projects where a CPN [critical path network] is routinely established and maintained. It seems that BB had not prepared or maintained a proper programme during the execution of the works. By now, one would have thought that it was well understood that, on a contract of this kind, in order to attack, on the facts, a clause 24 certificate for non-completion (or an extension of time determined under clause 25), the foundation must be the original programme (if capable of justification and substantiation to show its validity and reliability as a contractual starting point) and its success will similarly depend on the soundness of its revisions on the occurrence of every event, so as to be able to provide a satisfactory and convincing demonstration of cause and effect. A valid critical path (or paths) has to be established both initially and at every later material point since it (or they) will almost certainly change. Some means has also to be established for demonstrating the effect of concurrent or parallel delays or other matters for which h the employer will not be responsible under the contract.'' t

21 Useful Case Law Balfour Beatty Construction Ltd v The Mayor and Burgess of the London Borough of Lambeth '''Despite the fact that the dispute concerned a multi-million pound refurbishment contract, no attempt was made to provide any critical path. The work itself was no more complex than many other projects where a CPN [critical path network] is routinely established and maintained. It seems that BB had not prepared or maintained a proper programme during the execution of the works. By now, one would have thought that it was well understood that, on a contract of this kind, in order to attack, on the facts, a clause 24 certificate for non-completion (or an extension of time determined under clause 25), the foundation must be the original programme (if capable of justification and substantiation to show its validity and reliability as a contractual starting point) and its success will similarly depend on the soundness of its revisions on the occurrence of every event, so as to be able to provide a satisfactory and convincing demonstration of cause and effect. A valid critical path (or paths) has to be established both initially and at every later material point since it (or they) will almost certainly change. Some means has also to be established for demonstrating the effect of concurrent or parallel delays or other matters for which h the employer will not be responsible under the contract.'' t

22 Useful Case Law Balfour Beatty Construction Ltd v The Mayor and Burgess of the London Borough of Lambeth '''Despite the fact that the dispute concerned a multi-million pound refurbishment contract, no attempt was made to provide any critical path. The work itself was no more complex than many other projects where a CPN [critical path network] is routinely established and maintained. It seems that BB had not prepared or maintained a proper programme during the execution of the works. By now, one would have thought that it was well understood that, on a contract of this kind, in order to attack, on the facts, a clause 24 certificate for non-completion (or an extension of time determined under clause 25), the foundation must be the original programme (if capable of justification and substantiation to show its validity and reliability as a contractual starting point) and its success will similarly depend on the soundness of its revisions on the occurrence of every event, so as to be able to provide a satisfactory and convincing demonstration of cause and effect. A valid critical path (or paths) has to be established both initially and at every later material point since it (or they) will almost certainly change. Some means has also to be established for demonstrating the effect of concurrent or parallel delays or other matters for which h the employer will not be responsible under the contract.'' t

23 Useful Case Law The Royal Brompton Hospital NHS Trust v Lambeth On the evidence of [the experts] the establishment of the critical path of a particular construction project can itself be a difficult task if one does not know how the contractor planned the job. Not only that, but the critical path may well change during the course of the works, and almost certainly will do if the progress of the works is affected by some unforeseen event. [The expert] frankly accepted that the various different methods of making an assessment of the impact of unforeseen occurrences upon the progress of construction works are likely to produce different results, perhaps dramatically different results. He also accepted that the accuracy of any of the methods in common use critically depends upon the quality of the information upon which the assessment exercise was based. All of this does, of course, emphasise the vital point that the duty of a professional man, generally stated, is not to be right, but to be careful.... His conduct has to be judged having regard to the information available to him, or which ought to have been available to him, at the time he gave his advice or made his decision or did whatever else it is that he did.''

24 Useful Case Law The Royal Brompton Hospital NHS Trust v Lambeth On the evidence of [the experts] the establishment of the critical path of a particular construction project can itself be a difficult task if one does not know how the contractor planned the job. Not only that, but the critical path may well change during the course of the works, and almost certainly will do if the progress of the works is affected by some unforeseen event. [The expert] frankly accepted that the various different methods of making an assessment of the impact of unforeseen occurrences upon the progress of construction works are likely to produce different results, perhaps dramatically different results. He also accepted that the accuracy of any of the methods in common use critically depends upon the quality of the information upon which the assessment exercise was based. All of this does, of course, emphasise the vital point that the duty of a professional man, generally stated, is not to be right, but to be careful.... His conduct has to be judged having regard to the information available to him, or which ought to have been available to him, at the time he gave his advice or made his decision or did whatever else it is that he did.''

25 Useful Case Law The Royal Brompton Hospital NHS Trust v Lambeth On the evidence of [the experts] the establishment of the critical path of a particular construction project can itself be a difficult task if one does not know how the contractor planned the job. Not only that, but the critical path may well change during the course of the works, and almost certainly will do if the progress of the works is affected by some unforeseen event. [The expert] frankly accepted that the various different methods of making an assessment of the impact of unforeseen occurrences upon the progress of construction works are likely to produce different results, perhaps dramatically different results. He also accepted that the accuracy of any of the methods in common use critically depends upon the quality of the information upon which the assessment exercise was based. All of this does, of course, emphasise the vital point that the duty of a professional man, generally stated, is not to be right, but to be careful.... His conduct has to be judged having regard to the information available to him, or which ought to have been available to him, at the time he gave his advice or made his decision or did whatever else it is that he did.''

26 Useful Case Law The Royal Brompton Hospital NHS Trust v Lambeth On the evidence of [the experts] the establishment of the critical path of a particular construction project can itself be a difficult task if one does not know how the contractor planned the job. Not only that, but the critical path may well change during the course of the works, and almost certainly will do if the progress of the works is affected by some unforeseen event. [The expert] frankly accepted that the various different methods of making an assessment of the impact of unforeseen occurrences upon the progress of construction works are likely to produce different results, perhaps dramatically different results. He also accepted that the accuracy of any of the methods in common use critically depends upon the quality of the information upon which the assessment exercise was based. All of this does, of course, emphasise the vital point that the duty of a professional man, generally stated, is not to be right, but to be careful.... His conduct has to be judged having regard to the information available to him, or which ought to have been available to him, at the time he gave his advice or made his decision or did whatever else it is that he did.''

27 Useful Case Law The Royal Brompton Hospital NHS Trust v Lambeth On the evidence of [the experts] the establishment of the critical path of a particular construction project can itself be a difficult task if one does not know how the contractor planned the job. Not only that, but the critical path may well change during the course of the works, and almost certainly will do if the progress of the works is affected by some unforeseen event. [The expert] frankly accepted that the various different methods of making an assessment of the impact of unforeseen occurrences upon the progress of construction works are likely to produce different results, perhaps dramatically different results. He also accepted that the accuracy of any of the methods in common use critically depends upon the quality of the information upon which the assessment exercise was based. All of this does, of course, emphasise the vital point that the duty of a professional man, generally stated, is not to be right, but to be careful.... His conduct has to be judged having regard to the information available to him, or which ought to have been available to him, at the time he gave his advice or made his decision or did whatever else it is that he did.''

28 Useful Case Law The Royal Brompton Hospital NHS Trust v Lambeth On the evidence of [the experts] the establishment of the critical path of a particular construction project can itself be a difficult task if one does not know how the contractor planned the job. Not only that, but the critical path may well change during the course of the works, and almost certainly will do if the progress of the works is affected by some unforeseen event. [The expert] frankly accepted that the various different methods of making an assessment of the impact of unforeseen occurrences upon the progress of construction works are likely to produce different results, perhaps dramatically different results. He also accepted that the accuracy of any of the methods in common use critically depends upon the quality of the information upon which the assessment exercise was based. All of this does, of course, emphasise the vital point that the duty of a professional man, generally stated, is not to be right, but to be careful...hisconduct has to be judged having regard to the information available to him, or which ought to have been available to him, at the time he gave his advice or made his decision or did whatever else it is that he did.''

29 The baseline, as-planned or contract programme

30 Baseline, As-planned or Contract Programme City Inn v Shepherd highlights situation where the as-planned programme may be found wanting Shepherd expert did not rely on the as-planned programme and instead used as-planned v as-built analysis, this based on his assertion that he could not be confident as to the integrity of the as-planned programme Position supported by Judge (Lord Drummond Young) Skanska Construction UK v Egger (Barony) expert criticised for having reconstructed the as-planned programme for use within his time impact analysis

31 Baseline, As-planned or Contract Programme The as-planned programme (and associated critical path) must be: a solid foundation upon which there is no doubt as to its basis between the parties no doubt as to the activities contained within it and their respective interdependencies no doubt as to any changes that may be necessary for it to be used within subsequent delay analysis exercises

32 Summary Establish an agreed contract programme as soon as possible Record your assumptions in deriving the contract programme and any revisions to it (schedule integrity) Establish systems that promote accuracy of progress updates Agree the contract critical path and any subsequent revisions to it between een the parties (as single version of the truth the critical path will change during the project) Record and impact change events e contemporaneously eous (and agree or agree to disagree contemporaneously) Be careful, not necessarily right! Records, records, records!

33 Records the Sahara Syndrome the only things that are relevant are what has been written and what has been built.what is said is blown away like sand in the desert.

34 David Tyerman Managing Director Athena Project Services athenaprojectservices.com t: m: Thank You ENTITLEMENT PLANNING RISK RESOURCING

Peter D Aeberli. Barrister - Arbitrator - Mediator Adjudicator. The Waiting Game: Extensions of Time

Peter D Aeberli. Barrister - Arbitrator - Mediator Adjudicator. The Waiting Game: Extensions of Time Peter D Aeberli Barrister - Arbitrator - Mediator Adjudicator The Waiting Game: Extensions of Time Determining extensions of time can be as sophisticated an art as designing a building in the first place.

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

PRACTICALITIES OF DELAY ANALYSIS: RETROSPECTIVE ANALYSIS

PRACTICALITIES OF DELAY ANALYSIS: RETROSPECTIVE ANALYSIS PRACTICALITIES OF DELAY ANALYSIS: RETROSPECTIVE ANALYSIS Christopher A. Gorse 1, Mike Bates 1 and Aaron Hudson-Tyreman 2 1 Scchool of the Built Environment, Leeds Metropolitan University, Queen Square

More information

Project Control. 1. Schedule Updating

Project Control. 1. Schedule Updating Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools

More information

Hong Kong Institute of Surveyors

Hong Kong Institute of Surveyors Prolongation and Loss and Expense Claims For the Hong Kong Institute of Surveyors Mike Allen BSc FRICS MHKIS MCI Arb FA Cost E FAE CEDR Accredited Mediator 13 th February 2012 Contents Introduction The

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

CALCULATION DIFFERENCES WHEN IMPORTING FROM INTO ORACLE PRIMAVERA P6 VERSION 7 PAUL E HARRIS EASTWOOD HARRIS

CALCULATION DIFFERENCES WHEN IMPORTING FROM INTO ORACLE PRIMAVERA P6 VERSION 7 PAUL E HARRIS EASTWOOD HARRIS CALCULATION DIFFERENCES WHEN IMPORTING FROM MICROSOFT PROJECT 2003-2010 INTO ORACLE PRIMAVERA P6 VERSION 7 BY PAUL E HARRIS OF EASTWOOD HARRIS TABLE OF CONTENTS 1 INTRODUCTION 3 2 AIM 3 3 SUMMARY 3 4 LEVELS

More information

Scheduling Best Practices

Scheduling Best Practices RECOVERY SCHEDULES By Mark I. Anderson, Executive Vice President and Chief Operating Officer of Warner Construction Consultants, Inc. In this article, as part of a continuing series of articles regarding

More information

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

MODEL SCHEDULING SPECIFICATION

MODEL SCHEDULING SPECIFICATION MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with

More information

Priori ty ... ... ...

Priori ty ... ... ... .Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster Andrew Avalon, P.E., PSP and Curtis W. Foster LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com

More information

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Performing critical path analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the

More information

SCT AND MCAS MIRAMAR FOTS SOUTHERN CALIFORNIA TRACON

SCT AND MCAS MIRAMAR FOTS SOUTHERN CALIFORNIA TRACON 1-5 CONSTRUCTION SCHEDULES 1-5.1 General, Network Analysis System (NAS).- 1-5.1.1 Applicable documents.- The Publication listed below forms a part of this specification and is applicable to the extent

More information

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E. Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June

More information

Use project management tools

Use project management tools Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding

More information

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,

More information

Devising new Software Project Risk Management Model: MARUNA

Devising new Software Project Risk Management Model: MARUNA Devising new Software Project Risk Management Model: MARUNA Bekim Fetaji South East European University, Computer Sciences, Ilindenska bb, 00 Tetovo, Macedonia Abstract The focus of this research is the

More information

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Lecture 26 CPM / PERT Network Diagram

Lecture 26 CPM / PERT Network Diagram Lecture 26 CPM / PERT Network Diagram 26.1 Introduction to CPM / PERT Techniques CPM (Critical Path Method) was developed by Walker to solve project scheduling problems. PERT (Project Evaluation and Review

More information

Construction Bonds. Vanessa S. Werden 604.408.2033 vsw@shk.ca

Construction Bonds. Vanessa S. Werden 604.408.2033 vsw@shk.ca Construction Bonds Vanessa S. Werden 604.408.2033 vsw@shk.ca What is a bond? A bond is a special form of contract whereby one party guarantees the performance by another party of certain obligations. A

More information

SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...

SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards... SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement

More information

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical

More information

Module 3: The Project Planning Stage

Module 3: The Project Planning Stage Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you

More information

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06 SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable

More information

Scheduling. Anne Banks Pidduck Adapted from John Musser

Scheduling. Anne Banks Pidduck Adapted from John Musser Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart

More information

Operational Research. Project Menagement Method by CPM/ PERT

Operational Research. Project Menagement Method by CPM/ PERT Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your

More information

BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses

BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses BIM.03 Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses Mr. Kevin Coyne, PE PSP T his paper explores the use of 4D models, which provide a virtual construction

More information

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Schedule and Delay Analysis Methodologies Richard J.

More information

Construction Delay Analysis Techniques A Review of Application Issues and Improvement Needs

Construction Delay Analysis Techniques A Review of Application Issues and Improvement Needs Buildings 01,, 0-1; doi:10.90/buildings000 Review OPEN ACCESS buildings ISSN 07-09 www.mdpi.com/journal/buildings/ Construction Delay Analysis Techniques A Review of Application Issues and Improvement

More information

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) 4 February 2009 Jesse Santiago & Desirae Magallon Overview Background & History CPM Defined The CPM approach Definitions Class Exercise Background & History Developed

More information

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration SECTION 01 311 NETWORK ANALYSIS SCHEDULE Part 1.1 DESCRIPTION A. Scope: Provide projected network analysis schedules for the entire Work and revise periodically. This type of schedule is acceptable for

More information

FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment

FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment AACE International Recommended Practice No. 29R-03 FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment Acknowledgments: Kenji P. Hoshino, PSP CFCC (Author) Robert B. Brown, PE

More information

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,

More information

Network Planning and Analysis

Network Planning and Analysis 46 Network Planning and Analysis 1. Objective: What can you tell me about the project? When will the project finish? How long will the project take (project total duration)? 2. Why is this topic Important

More information

Introduction to Project Management

Introduction to Project Management L E S S O N 1 Introduction to Project Management Suggested lesson time 50-60 minutes Lesson objectives To be able to identify the steps involved in project planning, you will: a b c Plan a project. You

More information

Time Management. Part 5 Schedule Development. Richard Boser

Time Management. Part 5 Schedule Development. Richard Boser Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms

More information

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method

More information

Project Management. Week 4- Project Planning and Network Diagrams 2012-13

Project Management. Week 4- Project Planning and Network Diagrams 2012-13 Project Management Week 4- Project Planning and Network Diagrams 2012-13 Last Week Project Appraisal Techniques Scoping Tools-Breakdown Structures Estimation This Week What is Planning? Purpose of Planning

More information

CRITICAL PATH METHOD (CPM) SCHEDULES

CRITICAL PATH METHOD (CPM) SCHEDULES 96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without

More information

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute

More information

Collaborative Scheduling using the CPM Method

Collaborative Scheduling using the CPM Method MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines

More information

EXHIBIT 2-2-C PROGRESS SCHEDULES

EXHIBIT 2-2-C PROGRESS SCHEDULES EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (August 2008) --------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (July 2007) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule 763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project

More information

Project Planning and Scheduling

Project Planning and Scheduling Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination

More information

Project Time Management

Project Time Management Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-981-3 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-981-3 The material contained within

More information

SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION

SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 Related Documents A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

Project Implementation Plan (PIP) User Guide

Project Implementation Plan (PIP) User Guide eea financial mechanism Project Implementation Plan (PIP) User Guide 23 November 2007 norwegian financial mechanism Page 2 of 20 1 Introduction The Project Implementation Plan (PIP) is a representation

More information

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

WORK PROGRAM GUIDELINES

WORK PROGRAM GUIDELINES Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment

More information

A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN

A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN Introduction A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN The core technique available to Project Managers for planning and controlling their projects is Network Analysis. This short guide will provide

More information

Project Management Glossary

Project Management Glossary Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project

More information

The work breakdown structure can be illustrated in a block diagram:

The work breakdown structure can be illustrated in a block diagram: 1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as

More information

The Job of the Project Manager. Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA 20816 bobyouker@worldnet.att.

The Job of the Project Manager. Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA 20816 bobyouker@worldnet.att. The Job of the Project Manager Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA 20816 bobyouker@worldnet.att.net For any organization and for any project manager it is vitally important

More information

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead

More information

Chapter 3 Managing the Information Systems (IS) Project

Chapter 3 Managing the Information Systems (IS) Project Content Chapter 3 Managing the Information Systems (IS) Project Process of managing IS projects Skills required to be an effective project manager Skills and activities of a project manager during project

More information

ASSESSMENT TRAINING - INTERVENTION

ASSESSMENT TRAINING - INTERVENTION Project Time Management (Managing the Risk of Delayed Completion in the 21 st Century) Practical Management of Construction Delay & Disruption Melia White House Hotel, October 17 th & 18 th 2011 David

More information

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking

More information

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment // Taming an Unruly Schedule Using the 14-Point Schedule Assessment Dr. Dan Patterson, PMP CEO & President, Acumen February 2010 www.projectacumen.com Table of Contents Introduction... 3 The 14-Point Assessment...

More information

25Project management

25Project management 5Project management A Activity 5.1 (page ) 1 Verify the ESTs above by working through the diagram from left to right, taking the longest route, in days, to each node. Node 1 3 5 7 8 EST 0 0 + 8 = 8 0 +

More information

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing

More information

Chapter 2: Project Time Management

Chapter 2: Project Time Management Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.

More information

SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE

SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining an accurate cost loaded critical path schedule in

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS USACE / NAVFAC / AFCEC / NASA UFGS-01 32 16.00 20 (February 2015) Change 2-11/15 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 32 16.00 20 (November 2009) UNIFIED FACILITIES

More information

1. Interpretation of this Schedule

1. Interpretation of this Schedule Schedule 6 Programming Requirements 1. Interpretation of this Schedule 1.1 Primavera The following capitalised terms used in this Schedule 6 have the meanings given to them in the proprietary computer

More information

EdExcel Decision Mathematics 1

EdExcel Decision Mathematics 1 EdExcel Decision Mathematics 1 Notes and Examples Critical Path Analysis Section 1: Activity networks These notes contain subsections on Drawing an activity network Using dummy activities Analysing the

More information

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps Project Planning What are you going to do in the project? Lecture Objectives To discuss the tasks in planning a project To describe the tools that can be used for developing a project plan To illustrate

More information

Chapter-6. Developing a Project Plan

Chapter-6. Developing a Project Plan MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies

More information

AACE International Recommended Practices

AACE International Recommended Practices AACE International Recommended Practice No. 52R-06 TIME IMPACT ANALYSIS AS APPLIED IN CONSTRUCTION TCM Framework: 6.4 Forensic Performance Assessment, 7.2 Schedule Planning and Development, 10.2 Forecasting,

More information

Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition:

Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition: Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition: 1. Activity : It is a particular work of a project which consumes some resources (in ) & time. It is shown as & represented

More information

Alexandria National Cemetery SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULE

Alexandria National Cemetery SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULE SECTION 01 32 16.13 PART 1 - GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Microsoft Project 2003 (or latest version) Bar Chart schedule demonstrating fulfillment of the contract requirements.

More information

Project Control System Manual. Jefferson Science Associates, LLC. 600 Progress Status. Project Control System Manual Revision 7 - 44 -

Project Control System Manual. Jefferson Science Associates, LLC. 600 Progress Status. Project Control System Manual Revision 7 - 44 - Jefferson Science Associates, LLC 600 Progress Status Project Control System Manual Revision 7-44 - 600 Progress Status This chapter of the JSA Project Control System Manual explains how the status of

More information

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define

More information

Technology A Risk Prevention / Mitigation Tool

Technology A Risk Prevention / Mitigation Tool Technology A Risk Prevention / Mitigation Tool by Belden Premaraj 1 This paper highlights the possible use of various technological advancements as a tool to prevent or mitigate risk rather than merely

More information

Time bars in construction and global claims

Time bars in construction and global claims Simon Tolson and Jeremy Glover Time bars in construction and global claims Time bars in construction contracts Introduction 1. 2. There is an increasing tendency in construction contracts to include time

More information

How To Perform An As-Built But For Schedule Delay Analysis

How To Perform An As-Built But For Schedule Delay Analysis LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. Table of Contents 1. INTRODUCTION...

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT 6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity

More information

Construction Delay Analysis Techniques A Review of Application Issues and Improvement Needs

Construction Delay Analysis Techniques A Review of Application Issues and Improvement Needs Construction Delay Analysis Techniques A Review of Application Issues and Improvement Needs Nuhu Braimah, Lecturer of Construction/Infrastructure Management, Civil Engineering Department, School of Engineering

More information

THE SYSTEMS APPROACH TO CURRICULUM DEVELOPMENT

THE SYSTEMS APPROACH TO CURRICULUM DEVELOPMENT THE SYSTEMS APPROACH TO CURRICULUM DEVELOPMENT 1 Dr.S.Rajasekar, Professor, Department of Education, Annamalai University Email:sr@sekars.net Website: http://www.sekars.net Introduction The systems approach

More information

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose 1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing

More information

CRITICAL PATH ANALYSIS AND GANTT CHARTS

CRITICAL PATH ANALYSIS AND GANTT CHARTS CRITICAL PATH ANALYSIS AND GANTT CHARTS 1. An engineering project is modelled by the activity network shown in the figure above. The activities are represented by the arcs. The number in brackets on each

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

Procurement Strategy and Contract Selection

Procurement Strategy and Contract Selection GUIDELINE Capital Works Management Framework Procurement Strategy and Contract Selection The suite of Capital Works Management Framework documents is available online www.hpw.qld.gov.au: The Capital Works

More information

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Unit 4: Time Management (PMBOK Guide, Chapter 6) (PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may

More information

PLANNING & FORENSIC DELAY ANALYSIS

PLANNING & FORENSIC DELAY ANALYSIS PLANNING & FORENSIC DELAY ANALYSIS Experts in international construction & engineering disputes 01 www.gtfairway.com Fairway Fairway is an internationally recognised company that provides expert analysis

More information

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides

More information

Baseline Schedule Metrics. Donald R. McNatty, PSP FAACE November 18, 2015

Baseline Schedule Metrics. Donald R. McNatty, PSP FAACE November 18, 2015 Donald R. McNatty, PSP FAACE November 18, 2015 1 Thank you for joining today s technical webinar Mute all call in phones are automatically muted in order to preserve the quality of the audio for all attendees.

More information

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 Agenda Revision of 108.03 Schedule How CDOT Uses Construction Schedules Critical Path Method Scheduling Microsoft Project Overview 1 Revision

More information

SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS

SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS A. The term Baseline Schedule, as used throughout the contract documents, shall refer to a fixed projection of the project

More information

In initial planning phases In monitoring and execution phases

In initial planning phases In monitoring and execution phases Project management What is it? Project management is a framework for a range of tools for helping plan and implement development and change projects. A range of tools exist, including: Gantt charts (bar

More information

5. Creating a Gantt Chart

5. Creating a Gantt Chart 5. Creating a Gantt Chart Whilst the network diagram is a useful way to describe how tasks are linked to each other, the Gantt chart is used to display the schedule of a project. The Gantt chart is the

More information

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information

(Refer Slide Time: 01:52)

(Refer Slide Time: 01:52) Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This

More information

Dashboards and Reporting for Program Management

Dashboards and Reporting for Program Management MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will

More information

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for

More information