Sharif MBA Project Management Session 9

Size: px
Start display at page:

Download "Sharif MBA Project Management Session 9"

Transcription

1 Sharif MBA Project Management Session 9 Resource Planning Project Accounts Earned Value Burke Ch. 13, 14, 16 1

2 Resource Table Example/ Exercise 2

3 Bar-chart & Resource Histogram 3

4 Cumulative Resource S Curve 4

5 Bar-chart & Smoothed Histogram 5

6 Resource Smoothed Bar-chart 6

7 Resource Constraints Working Overtime Working Shifts Increase Productivity Job and Knock Learning Curve Sub-contractors Scope of Work Duration Deadline 7

8 Cost Distribution 8

9 Schedule of Work 9

10 Cash-Flow Imposed on Bar-chart 10

11 Expenses Bar-chart (showing expenses per day) 11

12 S-Curve (accumulated expenses per day) 12

13 Cost Management Cost Management: processes required to ensure that the project is completed within the approved budget (PMBOK) Financial Accounting Management Accounting Project Accounting Due to limited class time, Cost Management will be discussed D at the end, as time permits. Only some concepts and Earned value are explained here. 13

14 Cash-Flow Statement 14

15 Cost Estimating Techniques & Tools Analogous estimates / top-down estimates Bottom-up estimating Parametric modeling Computerized tools, spread sheets, MS Project Useful tips for creating more precise estimates Have the person doing the work create the estimate. Use task information from another project. Use the PERT technique Be sure to estimate all tasks for all resources: people, equipment, and materials. 15

16 Influence / Cost Change of Curve 16

17 Project Control If anything seems to be going well, you obviously do not know what s going on! Murphy Law If the project is off course, then control in the form of corrective action must be applied. It is essential for effective project control that performance is measured while there is still time to take corrective action. 17

18 Project Progress Against Time Planned Progress => Project Behind schedule & Over-spent 18

19 Earned Value False assumption: Input == Output Example: Projects 99% complete for a year Expenses & Progress reported separately The Earned Value technique measures the performance of project as it is completed. It also allows to forecast future performance based on the past performance (PMBOK) 19

20 Input vs. Output vs. Plan 20

21 Project Man-hours Planned Man-hours: Estimates of how you intend to perform the work Actual Man-hours: Recorded on the clock cards Earned Man-hours: Measure of work done 21

22 Over Optimistic Reporting 22

23 Project Values 1. The planned value (PV), also the budgeted cost of work schedule (BCWS), or the budget, is portion of the approved total cost estimate planned to be spent on an activity during a given period. 2. The actual cost (AC), also the actual cost of work performed (ACWP), is the total direct and indirect costs incurred in accomplishing work on an activity during a given period. 3. The earned value (EV), also the budgeted cost of work performed (BCWP), is the percentage of work actually completed multiplied by the planned value. 23

24 Earned Value Curve BAC: Budget At Completion BCWS (budget): Budgeted Cost of Work Scheduled ACWP (actual): Actual Cost of Work Performed BCWP (earned): Budgeted Cost of Work Performed EAC: Estimate at Completion 24

25 Earned Value EV = PV * (% Complete) Expert Opinion % of Production Using WBS (Data Capture Proforma) 25

26 Data Capture Proforma Pipe Erection Activity 26

27 Cost Control Earned Value Management 27

28 Cost Control Calculations - Earned Value Management 28

29 Cost Variance Calculation CV = BCWP - ACWP A negative variance indicates a cost overrun 29

30 Schedule Variance Calculation SV = BCWP - BCWS A negative variance indicates a behind schedule condition 30

31 Variance percents SCHEDULE VARIANCE % = (SVP) SV BCWS X 100 COST VARIANCE % = (CVP) CV BCWP X

32 Estimate at completion (EAC) EAC = ACWP BCWP X Budget at completion (BAC) The estimate at completion is the best estimate of the total cost at the completion of the project. The EAC is a periodic evaluation of the status of the project - usually on a monthly basis or until a significant change has been identified. 32

33 Exercise Template 33

34 Solution to Number 4 34

35 Solution to Number 7 35

36 Solution to Number 13 36

37 Project Variance Analysis VARIANCE UPPER BOUNDARY PROJECTED COST $ ACTUAL COST VARIANCE VARIANCE LOWER BOUNDARY R&D QUALIFICATION DEVELOPMENT PHASE I PHASE II PHASE III TIME 37

38 Management Reserve CONTRACTED COST ACTUAL COST MANAGEMENT RESERVE $ RELEASED BUDGET TIME 38

39 Variance Analysis Questions What is the problem causing the variance? What is the impact on time, cost, and performance? What is the impact on other efforts, if any? What corrective action is planned or under way? What are the expected results of the corrective action? 39

40 Variance Reporting Variance reporting is accomplished at each reporting interval. However, the variance threshold reports are exception reports and occur only when the variances exceed the upper and lower boundaries of the project variances envelope. Reporting Intervals Depends on the type of organization and characteristics of the projects. Project-driven organization - weekly. Non-project-driven organization - monthly 40

41 Cost Account Variance Analysis Report Cost account no/cam WBS/Description Cost performance data Month to date ($) Contract to date ($k) Problem cause and impact Variance BCWS BCWP ACWP SCHED COST Reporting level As of At completion Budget EAC Var. Corrective action (including expected recovery date) Cost account Date Cost center Date WBS element Date Mgr. Mgr. Mgr. Date 41

42 The 50/50 rule Half of the budget for each element is recorded at the time that the work is scheduled to begin and the other half at the time the work is scheduled to be completed. For a project with a large number of elements the amount of distortion from such a procedure is minimal. 42

43 Analysis Budgeted cost for work Scheduled (BCWS) Performed (BCWP) Budget Cost account budget = 100 (thousands) Work packages BCWS = 38 BCWP = 49 SCHED. VARIANCE = rule used for work in process 8 43 J F M A M J J A S O N D

44 Using The Rule 4,000 10,000 TIME LINE 12,000 4,000 LEGEND COMPLETED NOT COMPLETED BCWS = 34,000 BCWP = 33,000 BAC = 52,000 TIME 6,000 6,000 10,000 44

45 Earned Value Status Reporting TIME LINE CUMMULATIVE COST, $ ACWP BCWS CV BCWP SV TIME 45

46 Monthly Project Report 1. VARIANCE ANALYSIS (Cost in Thousands) 1 June 1997 Budgeted Budgeted Cost Milestone Cost Work Work Actual Variance, % Subtask Status Scheduled Performed Cost Schedule Cost 1 Completed Completed Completed Not Started Completed Not started Started Not started Total ESTIMATE AT COMPLETION (EAC) EAC = (360/340) X 579,000 = $613,059 Overrun = 613, ,000 = $34,059 46

47 3. COST SUMMARY Costs are running approximately 5.9% over budget due to higher salaried labor. 4. SCHEDULE SUMMARY The 24.4% behind schedule condition is due to subtasks 4 and 6 which have not yet begun due to lack of raw materials and the 50/50 method for booking costs. Overtime will get us back on schedule but at an additional cost of 2.5% of direct labor costs. 5. MILESTONE REPORT Milestone/ Scheduled Projected Actual Subtask Completion Completion Completion 1 4/1/97 4/1/97 2 5/1/97 5/1/97 3 5/1/97 4/23/97 4 7/1/97 7/1/97 5 6/1/97 6/1/97 6 8/1/97 8/1/97 7 9/1/97 9/1/ /1/97 10/1/97 47

48 6. ACTIVITY REPORT Current Potential Corrective Problem Impact Action (a) Lack of raw Cost overruns and Overtime is scheduled. materials. behind schedule We will try to use lower condition. salaried staff. Raw materials are expected to be on dock next week. (b) Customer un- May need add- Customer will provide happy with test itional planning. us with revised statement results. of work on 6/15/97. 48

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description

More information

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints

More information

Project Cost Management

Project Cost Management Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please

More information

Brainstorm. What is Cost and Project Cost Management?

Brainstorm. What is Cost and Project Cost Management? Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,

More information

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Unit 5: Cost Management (PMBOK Guide, Chapter 7) (PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost

More information

AACE International Recommended Practice No. 86R 14

AACE International Recommended Practice No. 86R 14 AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment

More information

A Gentle Introduction to Earned Value Management Systems

A Gentle Introduction to Earned Value Management Systems A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com

More information

Chapter 7. (PMBOK Guide)

Chapter 7. (PMBOK Guide) Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Applying Earned Value Analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

COINS EVA Earned Value Analysis

COINS EVA Earned Value Analysis COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

An introduction to Earned Value Analysis

An introduction to Earned Value Analysis An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many

More information

700 Analysis and Reporting

700 Analysis and Reporting Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how

More information

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional Selftestengine..PMI-SP.270 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 5.1 PMI-SP PMI Scheduling Professional This study guides are so comprehensible that anyone can understand

More information

Estimating Cost at Completion - Judgment & EV Information

Estimating Cost at Completion - Judgment & EV Information Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number

More information

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com Chapter 7: Project Cost Management Munawar moenawar@gmail.com Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.

More information

Module 5 Cost Management PMP Exam Questions

Module 5 Cost Management PMP Exam Questions Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Earned Value Analysis Overview Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects

More information

Project Cost Management

Project Cost Management Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,

More information

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management

More information

Introduction to earn value management in Civil Engineering

Introduction to earn value management in Civil Engineering 3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.

More information

IST 302 : Project Cost Management

IST 302 : Project Cost Management IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of

More information

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Rules on using templates 1) Must reference the template used 2) Use

More information

Earned Value and Agile Reporting

Earned Value and Agile Reporting Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,

More information

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference

More information

Chapter 3: Project Cost Management

Chapter 3: Project Cost Management Chapter 3: Project Cost Management Learning Objectives o Understand the importance of project cost management. o Explain basic project cost management principles, concepts, and terms. o Discuss different

More information

Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01

Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01 PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.

More information

plans based on actual cost, schedule and technical progress of work [1, 9].

plans based on actual cost, schedule and technical progress of work [1, 9]. An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan

More information

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu

More information

Basic Concepts of Earned Value Management (EVM)

Basic Concepts of Earned Value Management (EVM) Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data

More information

Earned Value Probabilistic Forecasting Using Monte Carlo Simulation

Earned Value Probabilistic Forecasting Using Monte Carlo Simulation Earned Value Probabilistic Forecasting Using Monte Carlo Simulation Ricardo Viana Vargas, MSc, PMP Professor Getulio Vargas Foundation - Brazil Chair - Grupo A&C Brasil ricardo.vargas@uol.com.br ou rvargas@aec.com.br

More information

Project Cost Management. Richard Boser

Project Cost Management. Richard Boser Project Cost Management Richard Boser Project Cost Management Introduction Course Objectives Upon completing today s activities you will be knowledgeable of tools and techniques to: Allocate overall costs

More information

Chapter 5: Project Cost Management

Chapter 5: Project Cost Management Chapter 5: Project Cost Management 1 Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource

More information

Project Management: Tracking Progress and Earned Value with MS Project 2003

Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain

More information

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s

More information

FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011

FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight Outline EVMS History at the Lab FRA EVMS Documents

More information

EVA (C/SCSC) and Basics of Project Control. Nathaniel Osgood 4/7/2004

EVA (C/SCSC) and Basics of Project Control. Nathaniel Osgood 4/7/2004 EVA (C/SCSC) and Basics of Project Control Nathaniel Osgood 4/7/2004 Topics Monitoring cont d EVA (C/SCSC) Definitions and examples Forecasting Project Control General Performance-adjustments adjustments

More information

Tracking Budgets and Schedules

Tracking Budgets and Schedules Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is

More information

Project Control. 1. Schedule Updating

Project Control. 1. Schedule Updating Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management

More information

Project Control with ProTrack

Project Control with ProTrack Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue

More information

Simple Earned Value (Using MS Project 2010)

Simple Earned Value (Using MS Project 2010) Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained

More information

Appendix D Glossary Of Terms

Appendix D Glossary Of Terms Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used

More information

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10. PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition

More information

PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating:

PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating: , Fourth Edition Parallels between Cost and Time estimating: There are strong parallels between cost estimating and time estimating so you should have experienced some déjà vu when you first read it. In

More information

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP PMP Formulae & Tips Cheat Sheet P a g e Integration Management Develop Project Charter process Project Selection Methods (>> Benefit Measurement Methods >> Economic Models -7) Present Value (PV) FV The

More information

PMP Exam Preparation Answer Key

PMP Exam Preparation Answer Key Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.

More information

PROJECTS SCHEDULING AND COST CONTROLS

PROJECTS SCHEDULING AND COST CONTROLS Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT 7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major

More information

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Earned Value Management Tutorial Module 8: Reporting. Prepared by: Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.

More information

Project Management for Scientists

Project Management for Scientists Project Management for Scientists Cost & Schedule Estimates Christoph U. Keller, c.u.keller@uu.nl Sterrekundig Instituut Utrecht Utrecht University www.astro.uu.nl/~keller Outline Resource Assignments

More information

Project Execution - PM Elements

Project Execution - PM Elements Performance Initial Release 1. Introduction to Project Tracking and Reviewing Once a project has advanced to the phase of performance, the consistent and constant flow of information on the true status

More information

Using Earned Value Management for Improving Processes. By Cynthia K. West

Using Earned Value Management for Improving Processes. By Cynthia K. West Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.

More information

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761 Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity

More information

Planning and Scheduling Your Project Using Microsoft Project 2003

Planning and Scheduling Your Project Using Microsoft Project 2003 Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering sridhar@sastratechnologies.in Meeting Protocol Agenda Project File Project Calendar Creating

More information

Project Cost Management

Project Cost Management Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-982-9 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-982-9 The material contained within

More information

PM in construction industry

PM in construction industry PM in construction industry Construction 2. Lepel BME Department of Construction Technology and Management 19-03-2014 PM in general Project integration Project plan development Project plan execution Integrated

More information

Analysis and Application of Earned Value Management in Software Development

Analysis and Application of Earned Value Management in Software Development Analysis and Application of Earned Value Management in Software Development Frank Tsui School of Computing and Software Engineering Southern Polytechnic State University, Marietta, Georgia, USA 30060 Abstract

More information

PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP

PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP Frequently Asked Questions What is the PMP credential? The PMP (Project Management Professional) credential is a globally recognized certification for

More information

PROJECT SCHEDULING AND TRACKING

PROJECT SCHEDULING AND TRACKING PROJECT SCHEDULING AND TRACKING PROJECT SCHEDULING AND TRACKING Software project scheduling is an activity that distributes estimated effort across the planned project duration by allocating the effort

More information

EVM.01. Earned Value Analysis Why it Doesn't Work

EVM.01. Earned Value Analysis Why it Doesn't Work EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects

More information

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2

More information

Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2

Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2 Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2 P.G. Student, Department of Civil & Environmental Engineering, NITTTR, Bhopal,

More information

PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Technical Baseline Development and Control Examples

PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Technical Baseline Development and Control Examples PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Technical Baseline Development and Control Examples Example 40 5.0 PROJECT MANAGEMENT AND CONTROL The Project Management

More information

Project Cost Management

Project Cost Management Project Cost Management Martin Pazderka martin.pazderka@inso.tuwien.ac.at INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda

More information

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor

More information

How To Manage A Project

How To Manage A Project Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management

More information

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4 MACIASZEK, L.A. and LIONG, B.L. (2005): Practical Software Engineering. A Case Study Approach Addison Wesley, Harlow England, 864p. ISBN: 0 321 20465 4 Chapter 4 Software Project Planning and Tracking

More information

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS 14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya

More information

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by: Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective

More information

Predicting progress on your project

Predicting progress on your project www.nonsuch.co info@nonsuch.co Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant

More information

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management.

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management. SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management. Fatima Boumahdi, Rachid Chalal Abstract This paper presents an architecture for the Project Management,

More information

Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.

Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11. Project Management ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.2003 1 Project Management - Training Program - Project Scope Management

More information

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

The Two Most Useful Earned Value Metrics: the CPI and the TCPI PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was

More information

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and their

More information

Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes

Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes Lecture Slides for Managing and Leading Software Projects Chapter 8: Measuring and Controlling Work Processes developed by Richard E. (Dick) Fairley, Ph.D. to accompany the tet Managing and Leading Software

More information

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet Project Integration Management Processes required to ensure that the various elements of the project are properly coordinated to meet / exceed stakeholder expectations. Project Plan Development Other ning

More information

Project Cost Management through Earned Value Performance Management - EVPM

Project Cost Management through Earned Value Performance Management - EVPM Project Cost Management through Earned Value Performance Management - EVPM Author: Dr. Raf M. Dua This paper was originally presented by Dr. Raf M. Dua to the Australian Institute of Project Management

More information

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin

More information

Project Cost Control: The Way it Works By R. Max Wideman

Project Cost Control: The Way it Works By R. Max Wideman Project Cost Control: The Way it Works By R. Max Wideman 12/21/05 In a recent consulting assignment we realized that there was some lack of understanding of the whole system of project cost control, how

More information

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of

More information

Contract Cash Flow & Performance Analysis. PERCEPTION Helping The Shipyard Stay On Budget

Contract Cash Flow & Performance Analysis. PERCEPTION Helping The Shipyard Stay On Budget Contract Cash Flow & Performance Analysis PERCEPTION Helping The Shipyard Stay On Budget 1 Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge

More information

Project Management Glossary

Project Management Glossary Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project

More information

CLARITY PPM TIPS, TRICKS, and TERMINOLOGY

CLARITY PPM TIPS, TRICKS, and TERMINOLOGY CLARITY PPM TIPS, TRICKS, and TERMINOLOGY Clarity PPM Knowledge Sharing Series Helping the Clarity PPM Community Members Benefit from Best Practice TABLE OF CONTENTS 1 OVERVIEW... 3 2 OVERVIEW PAGE...

More information

Certification Exam Objectives: PK0-003

Certification Exam Objectives: PK0-003 Certification Exam Objectives: PK0-003 INTRODUCTION The CompTIA Project + examination is designed for business professionals involved with projects. This exam will certify that the successful candidate

More information

Tracking Software Development Progress with Earned Value and Use Case Point

Tracking Software Development Progress with Earned Value and Use Case Point ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with

More information

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office

More information

Chapter 6. (PMBOK Guide)

Chapter 6. (PMBOK Guide) Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

5.2. 5.2 Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name]

5.2. 5.2 Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name] 231 5.2 Template for IT Project Plan Name of the Tool: Source: Usage: Description: Template for IT Project Plan GIZ This template has been designed as a tool to support the planning of IT projects for

More information

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 Kym.Henderson@froggy.com.au

More information

CHAPTER 8 Planning and Budgeting

CHAPTER 8 Planning and Budgeting Copyright 2008 by the Foundation of the American College of Healthcare Executives 6/8/07 Version 8-1 CHAPTER 8 Planning and Budgeting The planning process Budget types Statistics budget Revenue budget

More information

What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate

What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate The outcome of any venture is most often affected by the ready availability of useful information on which timely decisions can be taken. For project success, the need is therefore to know where you re

More information

MTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II)

MTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II) MTAT.03.244 Software Economics Lecture 6: Software Cost Estimation (part II) Marlon Dumas marlon.dumas ät ut. ee Outline Review of Effort Estimation Homework Discussion on book chapter by Caper Jones Earned

More information