December 30, Request for Approval to Use the Pre-Filing Process NEXUS Gas Transmission, LLC NEXUS Gas Transmission Project Docket No.

Size: px
Start display at page:

Download "December 30, Request for Approval to Use the Pre-Filing Process NEXUS Gas Transmission, LLC NEXUS Gas Transmission Project Docket No."

Transcription

1 NEXUS GAS TRANSMISSION, LLC 5400 Westheimer Ct. Houston, TX Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First, N.E. Washington, D.C December 30, 2014 Re: Request for Approval to Use the Pre-Filing Process NEXUS Gas Transmission, LLC NEXUS Gas Transmission Project Docket No. PF Dear Ms. Bose: Pursuant to Section (b) of the regulations of the Federal Energy Regulatory Commission ( FERC or Commission ), 1 NEXUS Gas Transmission, LLC ( NEXUS or Applicant ) hereby requests that the Commission initiate a National Environmental Policy Act ( NEPA ) environmental review under the Commission s Pre-Filing Process for a proposed greenfield natural gas pipeline and related facilities, herein referred to as the NEXUS Gas Transmission Project or Project. The NEXUS Gas Transmission Project is designed to deliver incremental production from the Utica Shale and Marcellus Shale plays to growing demand for natural gas by gas distribution and end use markets in the Upper Midwest and Canada. The scheduled in-service date of the Project is November 1, Representatives of NEXUS met with Commission Staff on December 17, 2014 to discuss the Project and NEXUS s use of the Pre-Filing Process. NEXUS plans to file a certificate application with the Commission for authorization of the Project under Section 7(c) of the Natural Gas Act ( NGA ) following completion of the Pre-Filing Process. Project Overview DTE Energy Company and Spectra Energy Partners, LP are lead developers of the proposed Project, a project designed to transport growing supplies of Appalachian Basin gas to customers in the U.S. Midwest and Ontario. The Project will create, through the use of greenfield pipeline and capacity on existing systems, a new path to deliver gas from the prolific Marcellus and Utica shale plays to markets in the Upper Midwest and Ontario, Canada, specifically delivering gas into existing infrastructure in Michigan and in Ontario. NEXUS held an open season for the Project from October 15, 2012 to November 30, 2012 and a supplemental open season from July 23, 2014 to August 21, NEXUS has signed precedent agreements for the majority of the capacity to be created by the Project C.F.R (b) (2014).

2 Ms. Kimberly D. Bose Page 2 Placing the Project facilities in service by the scheduled in-service date of November 1, 2017 is required to meet the firm transportation service requirements of the Project shippers. As proposed, the Project includes both new pipeline construction ( Greenfield construction, as described more fully in Section 3, below) and, to minimize environmental disruption and optimize project efficiencies, contracting for existing and expanded capacity on existing pipeline systems. The Greenfield pipeline will create a new pipeline system necessary to transport 1.5 billion cubic feet ( bcf ) of natural gas per day. It will be constructed, owned and operated by NEXUS and will extend from Kensington, Ohio to the DTE Gas transportation system west of Detroit, Michigan. The Project will also comprise contracted firm capacity existing on, and created by the expansion of, (1) the Texas Eastern Transmission, LP ( Texas Eastern ) system in Ohio and Pennsylvania to allow shippers to access gas supplies south of the Kensington, Ohio point where the NEXUS Greenfield system commences, (2) the DTE Gas Transportation ( DTE ) system in eastern Michigan and extending to the U.S. / Canada border, and (3) the Vector Pipeline ( Vector ) system in southern and eastern Michigan, northern Indiana, and eastern Illinois, and then across the U.S./Canada border into western Ontario. In this way, the Project will provide a connection between Appalachian shale gas supplies and markets in the US Midwest, including Ohio, Michigan, Chicago, and Dawn Ontario in Canada. Please see Attachment 1 for a Project Overview map of the route depicting the Project location. NEXUS understands that Texas Eastern will be separately submitting a Pre-Filing request for its expansion project in the near future, and ultimately will file its own certificate application with the Commission for approval of its expansion project. NEXUS further understands that Vector, if required, will be separately submitting a Pre-Filing request for its expansion project in the near future, and ultimately will file its own certificate application with the Commission for approval of its expansion project. The DTE expansion project will be subject to the jurisdiction of the Michigan Public Service Commission, as DTE is a state-regulated gas utility, and the service that DTE will provide to NEXUS by contractual arrangement will be pursuant to DTE s limited authority to provide service in interstate commerce. While each project would have separate applications, NEXUS understands that the Commission may prepare a single environmental impact statement to review the environmental impacts associated with all of the projects. As demonstrated herein, NEXUS has engaged in extensive efforts in anticipation of filing its certificate application to meet the Project s timeline and the November 1, 2017 in-service date. To further support the request, NEXUS submits the following in compliance with Section (d) of FERC s regulations and FERC Staff s guidance for initiating pre-filing review. 1. A description of the schedule desired for the project including the expected application filing date and the desired date for Commission approval. To meet the target in-service date for the Project of November 1, 2017, NEXUS requests that the Director of the Office of Energy Projects issue a notice approving use of the Pre-Filing Process by January 9, 2015.

3 Ms. Kimberly D. Bose Page 3 NEXUS intends to submit an initial draft of Environmental Resource Report No. 1 and a draft alternatives analysis within 30 days after issuance of the Pre-Filing docket number, a first draft of all Environmental Resource Reports by June 2015 and, if required, a second draft by September NEXUS commits to working with FERC Staff to provide Environmental Resource Reports earlier than June 2015, if possible, with all environmental reports to be provided by June Filing of the certificate application is anticipated in November NEXUS is committed to addressing environmental and landowner concerns throughout the Pre- Filing Process and requests issuance of a certificate order by November Meeting this timeline will allow for receipt of any remaining applicable permits and authorizations necessary for NEXUS to begin pre-construction activities, including the orderly mobilization of contractors and materials and the resolution of any outstanding landowner issues, and allow for commencement of construction in the first quarter of Timely commencement of these activities is critical to meet the Project s in-service date of November 1, 2017, which, as noted earlier, is needed to meet the firm transportation service requirements of the Project shippers. 2. Explain why the project applicant is requesting to use the pre-filing process. NEXUS is seeking authorization to use the Pre-Filing Process to provide the necessary environmental information to FERC Staff for review at the earliest practicable time to expedite the processing of its certificate application. In addition, use of the Pre-Filing Process will provide interested stakeholders with an opportunity to review and comment on environmental issues at the beginning of the environmental review process, facilitate timely resolution of any issues and develop a complete record. To meet the requirements of NEPA within the proposed timeline, NEXUS recognizes the need for close coordination among all interested federal, state, and local agencies, elected officials and other stakeholders. Early review of the environmental documentation required to comply with the NEPA Process and implementation of the Public and Agency Participation Plan prepared by NEXUS will facilitate the development of a complete public record, support the conclusion that the Project is in the public interest and allow the Project to receive all approvals necessary to implement the requested service by November 1, Use of the Pre-Filing Process will benefit NEXUS, interested federal, state, and local agencies, elected officials and other stakeholders by: Assisting in the development of initial information about the Project and identifying affected parties; Facilitating issue identification and resolution; Providing a process that accommodates site visits, meetings with federal, state, and local agencies, elected officials and other stakeholders, participation in public information meetings (e.g., open houses), and the examination of alternatives; Providing interested federal, state, and local agencies, elected officials and other stakeholders with access to draft Environmental Resource Reports and other Project-

4 Ms. Kimberly D. Bose Page 4 related information; Minimizing the number of Commission Staff environmental data requests and subsequent filings; Maintaining a coordinated schedule for a thorough environmental impact review; and Facilitating the preparation of high-quality Environmental Resource Reports and other related documents. Further, NEXUS believes that using the Pre-Filing Process will allow NEXUS to meet the energy needs of consumers throughout the US Midwest states such as Ohio, Michigan and Illinois and beyond through the interconnected interstate gas pipeline grid and in eastern Canada through the Dawn Hub in Dawn, Ontario with minimal impacts to the environment and stakeholders. 3. Provide a detailed description of the project, including location maps and plot plans to scale showing all major plant components. The NEXUS Gas Transmission Project will consist of the following: Greenfield Route: (i) (ii) The construction of approximately 250 miles of up to 42-inch-diameter natural gas pipeline comprised of: a. approximately 200 miles of new pipeline in Columbiana, Stark, Summit, Wayne, Medina, Lorain, Erie, Sandusky, Wood, Lucas, and Fulton Counties, Ohio b. approximately 50 miles of new pipeline in Lenawee, Monroe, and Washtenaw Counties, Michigan c. approximately 1,500 feet of lateral pipeline connecting the existing Kensington Processing Plant to the Texas Eastern mainline extension Booster Station in Columbiana County d. approximately 1.2 miles of lateral pipeline connecting the Kensington Processing Plant to the Tennessee Gas Pipeline ( TGP ) mainline in Columbiana County Installation of up to four new gas turbine compressor stations at the following locations: a. Columbiana County, Ohio b. Medina County, Ohio c. Erie County, Ohio d. Lucas County, Ohio Pending the completion of final engineering, compression strength is currently planned to be up to 52,000 horsepower (HP) 2 at the Columbiana station, up to 26,000 HP at the Medina station, up to 26,000 HP at the Erie station and up to 26,000 HP at the Lucas station. 2 The horsepower ratings provided are NEMA ratings.

5 Ms. Kimberly D. Bose Page 5 (iii) (iv) Installation of four new metering and regulating ( M&R ) stations: a. NEXUS/Kensington M&R Station located at the Kensington Processing Plant in Columbiana County, Ohio b. NEXUS/Texas Eastern M&R Station located at the tie-in from a lateral line connection with the Texas Eastern mainline extension in Columbiana County, Ohio c. NEXUS/TGP M&R Station located at the tie-in from a lateral line connection with the TGP mainline in Columbiana County, Ohio d. NEXUS/Willow Run delivery M&R Station located at the project terminus in Washtenaw County, Michigan Installation of new launcher and receiver facilities: a. launcher facility for the mainline located at the Kensington Processing Plant b. launcher and receiver facilities located at the new compressor stations located in Medina County, Ohio and Lucas County, Ohio c. receiver facility at the terminus of the pipeline within the NEXUS/Willow Run M&R Station d. launcher at TGP Lateral tie-in to the TGP mainline and a receiver at Kensington Processing Plant Texas Eastern Capacity. Capacity on Texas Eastern from certain receipt points located between Berne, Ohio and Braden Run, PA to a delivery point at a new interconnection between Texas Eastern and NEXUS at Kensington, Ohio. DTE Gas Capacity. Capacity on the DTE Gas system from Willow Run to the Vector- Highland junction interconnect (Milford Meter Station) between DTE Gas and Vector, as well as capacity on DTE Gas system to the U.S. / Canada border. Vector Capacity. Capacity on Vector extending from Vector s Milford Meter Station, Michigan to the Union Gas Limited Dawn Hub in Ontario, Canada. Note that final arrangements for transportation beyond the U.S./Canada border to Dawn, Ontario will depend on final commercial arrangements. Please see Attachment 1 for a Project Overview map of the route depicting the Project location. The attached map identifies the currently preferred route, which incorporates information gathered during document reviews, field work, and consultation and early feedback from landowners, agencies, government officials and other interested stakeholders. These outreach efforts are documented in Attachment 3 as part of the Public and Agency Participation Plan. As part of the Pre-Filing Process, NEXUS is committed to continuing to review the route alignment with stakeholders and address their concerns. As NEXUS continues its efforts to refine the route alignment, updates to the maps will be submitted to Commission Staff.

6 Ms. Kimberly D. Bose Page 6 4. Provide a list of the relevant federal and state agencies in the project area with permitting requirements. The filing shall include a statement indicating: (i) that those agencies are aware of the prospective applicant s intention to use the pre-filing process; (ii) whether the agencies have agreed to participate in the process; (iii) how the applicant has accounted for agency schedules for issuance of federal authorizations; and (iv) when the applicant proposes to file with these agencies for their respective permits or other authorizations. NEXUS began contacting federal and state regulatory agencies in Ohio and Michigan in September 2014 to discuss the relevant permitting requirements for the Project. NEXUS provided preliminary information regarding the Project, including a project description and maps, and followed up initial contact letters, in most cases, with in-person meetings. NEXUS advised these agencies of its intent to use the Pre-Filing Process. A listing of the federal and state agencies that NEXUS has contacted to date is included as Appendix C of the Public and Agency Participation Plan. A listing of anticipated environmental permits, reviews, and consultations is included as Appendix D of the Public and Agency Participation Plan. Additionally, NEXUS is in the process of determining which federal and state agencies will agree to participate in the Pre-Filing Process for the NEXUS Project. The following agencies have been made aware of NEXUS s intent to use the Pre-Filing Process and have indicated their intent to respond directly to an inquiry by FERC Staff regarding their participation in the Pre-Filing Process: U.S. Fish & Wildlife Service (Columbus, Ohio Field Office) NEXUS is in the process of coordinating with the following agencies on meeting dates to be finalized: United States (US) Army Corps of Engineers Buffalo, Huntington, and Pittsburg District Offices Ohio Environmental Protection Agency Michigan Department of Environmental Quality NEXUS expects to file for required federal authorizations at the same time as or prior to submitting its certificate application to the Commission, consistent with Order No NEXUS will work with Commission Staff and the affected federal and state agencies to develop a schedule for issuance of applicable environmental clearances and approvals. NEXUS will continue its efforts to identify and contact federal and state agency representatives during the Pre-Filing Process and will submit updates to Appendices C and D of the Public and Agency Participation Plan to Commission Staff, accordingly. 5. A list and description of other interested persons and organizations that have been contacted about the project. 3 Regulations Implementing the Energy Policy Act of 2005; Coordinating the Processing of Federal Authorizations for Applications under Sections 3 and 7 of the Natural Gas Act and Maintaining a Complete Consolidated Record, 117 FERC 61,076 (2006) ( Order No. 687 ).

7 Ms. Kimberly D. Bose Page 7 NEXUS began advising potential stakeholders, government officials, and other interested persons in September 2014 about the Project through letters and individual meetings. NEXUS has contacted officials at the federal, state, and local governments, including congressional delegations, state legislators, county commissioners, and local elected officials. As further described in section 6 below, NEXUS has also met with members of the public through voluntary public outreach efforts. A list of the other potential stakeholders that NEXUS has identified and a list of government officials is included as Appendix E of the Public and Agency Participation Plan. NEXUS will continue its ongoing efforts to identify and contact other potential stakeholders and interested persons, and updates to Appendix E will be submitted to Commission Staff, accordingly. 6. A description of what work has already been done, i.e. contacting stakeholders, agency consultations, project engineering, route planning, environmental and engineering contractor engagement, environmental surveys/studies, and open houses. Public Officials contacts: NEXUS representatives initially contacted federal, state and local public officials in September 2014 regarding the proposed Project. Additionally, NEXUS has held face to face meetings with public officials along the route and attended various county commission meetings to provide updates. Landowner contacts: Proposed new Project facilities will affect portions of 11 counties in Ohio and three counties in Michigan. The proposed Project s 600-foot survey study corridor will affect approximately 3,479 tracts along the pipeline portion. To date, these landowners have been contacted, or multiple attempts have been made at such contacts by NEXUS. These communications have included a Project introduction letter, a letter requesting survey permission, individual discussions with NEXUS s representatives, and site visits. NEXUS began communicating with landowners within the 600-foot study corridor in August 2014, and landowner notification letters and survey permission letters were ed to all identified affected landowners. To date, NEXUS has been granted survey permission on 2,505 tracts, which constitute 72 percent of the proposed Project right-of-way required to be surveyed. Multiple locations for each of NEXUS s four new Compressor Stations are currently being vetted. Once preferred sites have been identified, affected landowners at these locations will be contacted about the proposed facilities. NEXUS hosted a total of seven voluntary informational meetings for stakeholders in the vicinity of the proposed Project in Ohio in October Two additional voluntary informational meetings were held in the vicinity of the proposed Project in Michigan in November Landowners affected by the survey study corridor were sent invitations to attend the respective meetings. The voluntary informational meetings were set up similar to open house meetings, with subject matter experts available in the areas of surveying, construction, environmental impacts, regulatory affairs, state and federal relations, and right-ofway activities. Aerial imagery mapping identifying impacted tracts by landowner were available to allow for site specific discussion between the project team and interested stakeholders.

8 Ms. Kimberly D. Bose Page 8 Attendees were encouraged to ask general questions about the Project scope, schedule, noise levels, and safety and tract-specific questions around Project impacts. All questions were addressed during the informational meetings to the extent possible and any follow-up actions were tracked. A list of the landowners that NEXUS has identified is included as Appendix B of the Public and Agency Participation Plan. As such, Appendix B has been marked CONTAINS PRIVILEGED INFORMATION DO NOT RELEASE. 4 Privileged information should be treated as confidential and is for use by Commission Staff only and not to be released to the public. Questions pertaining to privileged information may be submitted to: Steven E. Hellman NEXUS Gas Transmission, LLC 5400 Westheimer Court Houston, TX E: sehellman@spectraenergy.com Tel Agency consultations: NEXUS has initiated consultation with applicable review agencies. Included in the outreach efforts to date are: the U.S. Army Corps of Engineers ( ACOE ), Pittsburgh, Buffalo, Huntington, and Detroit Districts; the U.S. Fish and Wildlife Service ( USFWS ), Ohio and Michigan Field Offices; the U.S. Environmental Protection Agency ( USEPA ); the National Park Service ( NPS ); the Ohio Historic Preservation Office ( OHPO ); the Ohio Department of Natural Resources ( ODNR ); the Ohio Environmental Protection Agency ( OEPA ); the Michigan Department of Natural Resources ( MDNR ); the Michigan Natural Features Inventory ( MNRI ); the Michigan Department of Environmental Quality ( MDEQ ); the Michigan State Historic Preservation Office ( MSHO ) and several Native American tribes with potential interest in the Project area (see Appendix C of the Public and Agency Participation Plan). NEXUS representatives conducted introductory meetings with the following agencies: USFWS, Columbus Ohio Field Office, October 7, 2014 MSHO, October 8, 2014 ODNR, October 14, 2014 OHPO, October 16, 2014 USFWS, East Lansing Michigan Field Office, November 12, 2014 NEXUS anticipates conducting the following additional meetings with regulatory agencies: ACOE, Buffalo District ACOE, Pittsburgh District ACOE, Huntington District USEPA 4 18 C.F.R , (2014).

9 Ms. Kimberly D. Bose Page 9 OEPA MDEQ Project Engineering and Route Planning: NEXUS has identified the facilities required to provide the transportation services associated with the Project shippers commitments. The facilities involve mainline pipeline, compression stations, metering facilities, lines to metering facilities and related appurtenances. Civil surveys commenced in September 2014 and will extend into the first quarter of The right-of-way workspace configurations will be further refined, as necessary, based on input from landowners, agencies, officials and other stakeholders, as well as information obtained from field surveys. These activities will continue throughout the Pre-Filing Process. Contractor Engagement: NEXUS has been working with the following contractors to perform various engineering and project studies: Fluor Enterprises Inc.: Geotechnical services TRC Companies, Inc.: Preparation of the Environmental Reports and acquisition of environmental permits, approvals and clearances (except air permits) Trinity Consultants, Inc.: Acquisition of air permits Hoover & Keith Inc.: Acoustic analyses for aboveground facilities and other applicable locations Universal Ensco Inc.: Civil survey and electronic mapping Environmental Surveys: The biological, aquatic, and cultural resources field surveys for the Project commenced in September 2014 and are ongoing. NEXUS anticipates completion of the majority of initial field surveys during the spring of 2015 with rare species and additional cultural resource surveys continuing through the 2015 and 2016 field seasons. NEXUS will provide additional information to the Commission regarding the status of the biological and cultural resource field surveys during the Pre-Filing Process. Based on the initial feedback from the USFWS the MNRI and ODNR, certain federal and state-listed species have been identified as potentially occurring in the vicinity of the Project facilities. The most notable of the federally-listed species identified include the following: Indiana bat (Endangered) Kirtland s warbler (Endangered) Rayed bean (Endangered) Karner blue butterfly (Endangered) Northern riffleshell (Endangered) Snuffbox (Endangered) Northern long-eared bat (Proposed Endangered) Eastern massasauga (Candidate) Eastern prairie fringe orchid (Threatened)

10 Ms. Kimberly D. Bose Page 10 Preliminary cultural resources background research and literature file reviews have been conducted at the OHPO and MSHPO ( SHPOs ) and resulted in the identification of several previously-recorded archaeological sites and historic architectural properties within or near the Project area. Phase I cultural resource surveys are currently being conducted to confirm these resources and identify additional cultural resource sites that may be present within the Project s Area of Potential Effect. Phase I survey reports on the results of archeological investigations will be submitted to the SHPOs for review in September Next Steps: Upon approval from the Commission to use the Pre-Filing Process, NEXUS will distribute letters to stakeholders that will include information about the Pre-Filing Process as well as a detailed Project description and maps, similar to the information provided to the government agencies described in the response to Item 4 above. NEXUS will continue to update stakeholders with ers and will post information on its website 7. Proposals from at least three prospective third-party contractors from which the Commission Staff may make a selection to assist in the preparation of the requisite NEPA document, or a proposal for the submission of an applicant-prepared draft Environmental Assessment as determined during the initial consultation with the Director. NEXUS prepared an RFP for a third party contractor to prepare the NEPA environmental documents for the Project. The draft RFP was reviewed by FERC Staff and issued to four prospective contractors. Attachment 2 identifies the three contractor proposals that NEXUS considers the best-qualified, for the Commission s consideration. The contractor proposals contain commercially sensitive information and have been marked CONTAINS PRIVILEGED INFORMATION DO NOT RELEASE. 5 Privileged information should be treated as confidential and is for use by Commission Staff only and not to be released to the public. Questions pertaining to privileged information may be submitted to Steven Hellman, whose contact information has been provided above. 8. Acknowledgment that a complete Environmental Report and complete application are required at the time of filing. NEXUS acknowledges that a complete Environmental Report and a complete certificate application under Section 7(c) of the NGA are still required for the Project. 9. A description of a Public and Agency Participation Plan, which identifies specific tools and actions to facilitate stakeholder communications and public information, including a project website and a single point of contact. NEXUS has developed a comprehensive Public and Agency Participation Plan that outlines a commitment to actively engage with stakeholders throughout the life cycle of the 5 18 C.F.R , (2014).

11 Ms. Kimberly D. Bose Page 11 Project and provides the steps to be taken by NEXUS to ensure successful ongoing communication with stakeholders, including establishing a project website and a single point of contact. NEXUS s Public and Agency Participation Plan is provided as Attachment 3. NEXUS is committed to identifying and resolving stakeholder issues and concerns related to the proposed Project. NEXUS believes that successful resolution of stakeholder issues is best achieved by involving the appropriate federal, state, and local agencies, elected officials and other potential stakeholders at the earliest possible stage of the Project and prior to filing its certificate application with the Commission. NEXUS appreciates the assistance of Commission Staff in initiating the Pre-Filing Process and ensuring a thorough and timely review of the Project, thereby allowing NEXUS to meet the service needs and timing requirements of the Project shippers. Should you have any questions concerning this request, please contact me at (713) or Leanne Sidorkewicz at (713) /s/ Berk Donaldson Berk Donaldson General Manager, Rates and Certificates

12 Attachment 1 Project Overview Map

13 Attachment 2 Contractor Proposals CONTAINS PRIVILEGED INFORMATION DO NOT RELEASE FILED UNDER SEPARATE COVER

14 Attachment 3 Public and Agency Participation Plan LANDOWNER LIST FILED UNDER SEPARATE COVER AS PRIVILEGED

15 NEXUS Gas Transmission, LLC NEXUS Gas Transmission Project (NEXUS Project) Public and Agency Participation Plan

16 NEXUS Project Public and Agency Participation Plan Table of Contents 1. Plan Purpose Project Description Values and Principles Management Commitment Project Development NEXUS Project Team Team Training Route/Corridor Planning Map Public Participation Public Outreach Identification of Issues Resolution of Issues Response to Comments Communication Protocol Access to Land Land Agent Contacts Identification of Stakeholders Landowners Public Officials Community and Public Interest Groups and Non-governmental Organizations Media Federal, State, and Local Agencies Agency Permits/Approvals Dissemination of Information Website Development Accessibility Maintenance Interactive Capabilities Federal, State and Local Agency Communications Stakeholder Notification of FERC Pre-Filing Participation Letters Voluntary Landowner Informational Meetings Landowner Invitations to Voluntary Landowner Informational Meetings Public Libraries for Filings Updates of Information Filings with FERC NEXUS Project Schedule Reporting... 11

17 NEXUS Project Public and Agency Participation Plan APPENDICES Appendix A: Appendix B: Appendix C: Appendix D: Appendix E: Appendix F: Appendix G: Appendix H: Project Overview Map Stakeholder List -- Landowners Stakeholder List -- Non-Landowners - Federal, State and Local Agencies Agency Permits and Approvals Stakeholder List -- Non-Landowners - Public Officials, Community and Public Interest Groups and Nongovernmental Organizations Examples of Home Pages for Websites Sample Letters List of Voluntary Landowner Informational Meetings Note: Spectra Energy Partners, LP and DTE Energy are lead developers of the NEXUS Gas Transmission Project

18 NEXUS Project Public and Agency Participation Plan 1. Plan Purpose The purpose of this Public and Agency Participation Plan is to identify stakeholders and potential issues related to the proposed NEXUS Gas Transmission Project (NEXUS Project or Project) early in the development process; determine appropriate and effective methods of communication with stakeholders; identify responsible parties and adhere to communication protocols, and document the public consultation process. NEXUS Gas Transmission, LLC (NEXUS) is dedicated to seeking greater involvement from affected stakeholder groups early in the planning process so those who are interested may participate in the decision making process throughout development of the Project. Our goal is to achieve consensus and agreements among the stakeholders reaching mutually acceptable project designs. We believe early and collaborative stakeholder involvement leads to project designs that minimize impacts to landowners, communities and the environment while enabling us to develop more comprehensive and complete applications submitted to regulatory agencies and the Federal Energy Regulatory Commission (FERC) Project Description The NEXUS Project will create, through the use of greenfield pipeline and capacity on existing systems, a new path to deliver gas from the prolific Marcellus and Utica shale plays to markets in the upper Midwest and Ontario, Canada, specifically delivering gas into existing infrastructure in Michigan and in Ontario. The NEXUS Project will create a new pipeline system and additional firm pipeline capacity necessary to transport 1.5 billion cubic feet ( bcf ) of natural gas per day. The NEXUS Project will provide the U.S. Midwest and eastern Canadian regions with a unique opportunity to secure a cost effective, domestically produced source of energy to support both current demand and future growth, for clean burning natural gas. It will allow abundant regional natural gas supplies from the Appalachian basin to flow reliably into Ohio, Michigan, Chicago and the Dawn Ontario markets, helping to meet the increasing demand while lowering energy costs. The NEXUS Project's proposed facilities consist of construction of approximately 250 miles of up to 42-inch diameter natural gas pipeline; installation of up to four new compressor units; construction of four new meter stations; and installation of new launcher and receiver facilities. 1

19 1.2. Values and Principles NEXUS Project Public and Agency Participation Plan Our core values guide our stakeholder outreach programs and activities as well as the work of our employees and contractors. In conducting our business, we value our stakeholders by: Stewardship - Demonstrating a commitment to environmental responsibility and vibrant communities. Respect for the Individual - Embracing diversity and inclusion, enhanced by openness, sharing, trust, leadership, teamwork and involvement. Integrity - Ethically and honestly doing what we say we will do. Win-Win Relationships - Having relationships that focus on the creation of value for all parties. Initiative - Having the courage, creativity and discipline to lead change and shape the future. While these values guide our stakeholder outreach approach, we tailor our activities for each project, ensuring that our dialogue with stakeholders is open, transparent and meaningful. Our Stakeholder Engagement Principles, developed to guide our interactions, are as follows: We will be respectful of and considerate to all stakeholders. We will engage with those affected by our business. We will consider stakeholder-identified issues in our decision-making process. We will provide timely and accurate communications using accessible information and language. We will be transparent in our processes and communications. Having established principles and knowing where, when and how to engage with external stakeholders is critical to our business success Management Commitment Overview Our stakeholder outreach activities are endorsed by our executive management team. We have communication plans that provide our employees the who, what, where and when protocols when conducting business. To ensure effective dialogue with our stakeholders, we rely on one-on-one discussions, face-to-face meetings, open houses, websites, legal notices, media outreach and individual letters sent via. 2

20 Project Development Stakeholder Outreach NEXUS Project Public and Agency Participation Plan During project development, stakeholder consultation is critical because many people along the proposed and existing pipeline route may not be familiar with natural gas pipelines or our company. The key criteria inherent in implementing a successful stakeholder consultation plan are the ability and knowledge to explain a project s benefits and its potential impacts; to respond to questions, concerns and issues; and, whenever possible, to mitigate potential impacts. In order to sustain a successful program, we seek, involve, inform and respond to stakeholders by implementing the planning process early, with open and collaborative activities. We execute our plans by engaging in and sustaining understandable, accurate and timely dialogue with our stakeholders. This process guides us toward building and maintaining winwin relationships. The NEXUS Project has evolved as market demands and our customers needs change and will require Federal, state, and local regulatory reviews and will be subject to government approvals. Our mission is to work with Project stakeholders to define an acceptable project design. Our vision is to involve affected landowners, other interested citizens, public officials and government agencies early in the Project planning process to determine the proposed route. It is imperative to us that our employees and Project team understand the importance of public participation. The underpinnings of this plan are to inform, listen to, and record stakeholders ideas and knowledge of the area and environment. Our values and principles include a commitment to being honest and open and following through with stakeholders concerns and issues. We manage all projects and operations in a manner that protects the environment and the health and safety of employees, customers, contractors and the public. Protection of human life is of highest priority, and actions undertaken to protect the environment or our assets must reflect this philosophy. We rely on each employee and contractor to support and actively participate in our environmental, health and safety program. 2. Project Development The NEXUS Project team has been discussing the purpose and need for the Project with landowners, agencies, public officials and other stakeholders. We explain supply and demand, energy reliability, pipeline construction, operations and safety, and the need for the Project during opportunities such as voluntary landowner informational meetings, public open houses and other meetings that include all stakeholders (e.g., county commission meetings, home owner association meetings, etc.). In identifying issues important to landowners and other stakeholders, we seek assistance from federal and state agencies, commissions, the Energy 3

21 NEXUS Project Public and Agency Participation Plan Information Administration and regional and local entities. In addition to sharing information about the benefits of the NEXUS Project, we seek to understand stakeholder issues and concerns, such as, Project construction activity alignment with landowners', community and business activities, environmental needs, right-of-way requirements, etc. As part of determining potential stakeholders for the NEXUS Project s preliminary and proposed routes, we identified and are continually communicating with the following: Ohio and Michigan Governors; federal, state, county and local public officials Federal, state and local permitting agencies and groups Energy agencies FERC staff Landowners Federal and state land managers Non-governmental organizations Community and public interest groups We continue to identify other stakeholders interested in the Project. Proper documentation is made with regard to conversations, meetings, and phone/visitor logs so that tracking of calls, visits, es and/or letters received as well as issue(s)/concern(s) raised from initial contacts are addressed and resolved. Our goal is to be responsive to all participating agencies, landowners and stakeholders NEXUS Project Team The NEXUS Project Team includes representatives from engineering, right-of-way, legal, environmental, stakeholder outreach, public relations, government relations, operations, regulatory affairs, and business development Team Training All facets of the NEXUS public outreach and consultation process are discussed with and supported by the NEXUS Project Team. Our land agents and survey crews participate in Public Consultation Training. The training includes appropriate communication, participation and documentation practices with stakeholders. All land agents are trained in project-appropriate research methods with regard to determining property ownership and legal descriptions. All have received training on negotiating skills that include effective listening. Effective listening skills are a vital part of the stakeholder/agent communication process. In addition, all land agents have extensive training in contracting and documentation, including fact checking and quality control. 4

22 NEXUS Project Public and Agency Participation Plan 2.3. Route/Corridor Planning The proposed pipeline route/corridor is selected based upon engineering, construction, environmental and stakeholder considerations that include: Maximizing use of existing corridors Utilizing streets, industrial/commercial parking lots, edges of properties Minimizing residential and business impacts Minimizing interference with future development Minimizing disruptions during construction Avoiding environmental impacts where possible Minimizing unavoidable environmental impacts The pipeline facilities will be installed is in accordance with U.S. Department of Transportation classifications and regulations Map A Project Overview Map is included in Appendix A. 3. Public Participation We believe public participation strengthens our connection with people living and working near the pipeline and is critical to the successful completion of the Project. During the early development stages of the Project we involve many landowners located within an initial 600-foot-wide study corridor comprising the preliminary and alternate routes. We landowners Project description letters and request survey permission; telephone landowners and follow up with face-to-face meetings. We hold voluntary landowner informational meetings; host public open houses and meetings with community and civic organizations; and will participate in FERC s National Environmental Policy Act (NEPA) Scoping Meetings. We also contact and meet with local and state public officials. During these meetings, we respond to stakeholders questions and for those questions that require research, we commit to responding in a timely fashion. We are taking care to respond in easy to understand terms and to provide stakeholders with comprehensive answers to their questions. We provide a toll free number and invite stakeholders to call at any time throughout the development process if new questions arise. We also invite them to visit both the Spectra Energy and NEXUS Project websites for the duration of the Project: NEXUS Project website: 5

23 NEXUS Project Public and Agency Participation Plan Spectra Energy website: US/NEXUS-Gas-Transmission 3.1. Public Outreach NEXUS will be implementing and coordinating public outreach activities during the FERC Pre-Filing Process as well as following the filing of the Certificate application. There are a number of separate components to our stakeholder outreach efforts, including the following: Developing our philosophy of outreach and stating our commitment Ensuring landowner, government and agency participation Training company representatives and land agents Providing a toll free number and website for easy access Developing and implementing a Public and Agency Participation Plan Collecting data and responding to stakeholders Having a plan for potential mitigation and compensation Identification of Issues Landowner Throughout the development, construction and operation of the NEXUS Project, we emphasize the importance of landowner and community communications. We sent letters to landowners providing them with information on the Project and requesting permission to survey. We will also send letters to stakeholders informing them of the FERC Pre-Filing Process, including the assigned Project docket number, FERC Scoping Meetings and information on the Resource Reports, as well as the locations of libraries where the Resource Reports will be made available for viewing. This communication with affected stakeholders will continue once we submit our certificate application to FERC. Further, we held 9 voluntary Landowner Informational Meetings in October and November 2014 in communities with proposed facilities. To announce the Landowner Informational Meetings, we ed letters to landowners and public officials. Additionally, the Project has received coverage from local media outlets interested in the scope, schedule, permitting, potential stakeholder impacts and opportunities for engagement. Sample letters are included in Appendix G. 6

24 NEXUS Project Public and Agency Participation Plan See Appendix H for a list of voluntary landowner informational meetings. We will continue to provide updates to the meeting information as necessary. Environmental Pipeline projects and its operations typically involve working with the U.S. Fish and Wildlife Service, U.S. Army Corps of Engineers, state departments of environmental protection, state departments of natural resources and the State Historic Preservation Offices. Knowing that developing the NEXUS Project may result in impacts to resources, we engaged these and other federal, state and regional agencies seeking guidance on specific issues early in the development process. Appendix C provides a list of Federal, state, and local agencies contacted on the NEXUS project to date Resolution of Issues To date, stakeholder meetings and communications, which were designed to inform, communicate and listen to feedback, have resulted in several modifications to the proposed route. Resolutions of issues are documented in our database and updated on an ongoing basis Response to Comments Project Team representatives are documenting all comments and responding as appropriate Communication Protocol Pre-Filing and post-certificate application activities are part of a coordinated plan involving many facets of the Project and team. Stakeholder communication is coordinated on a weekly basis, or more frequently, as needed Access to Land Initial notifications to affected landowners were ed in August 2014, and were followed by subsequent letters requesting survey permission. Sample letters are included in Appendix G Land Agent Contacts Contacts have been made with more than 2,700 landowners living along the 600-foot wide study corridor of the preliminary route. This number is expected to be greatly reduced through the survey and route selection process. 7

25 NEXUS Project Public and Agency Participation Plan 3.3. Identification of Stakeholders Landowners See Appendix B for a list of landowners and Appendix G for sample letters Public Officials Contacts have been made and/or briefings have been held with affected public officials beginning in September See Appendix E for a list of public officials Community and Public Interest Groups and Non-governmental Organizations Contacts have been made and/or briefings have been held with community and public interest groups and non-governmental organizations. See Appendix E for a list of community and public interest groups and non-governmental organizations Media Information has been and will be provided to media outlets upon request Federal, State, and Local Agencies Initial contacts and meetings with affected government officials and agencies were conducted in fall A Project overview was provided at the meetings. Since that time, we have kept and will remain in contact with these officials and agencies. See Appendix C for a list of federal, state and local agencies and Appendix G for sample letters Agency Permits/Approvals A table listing the required permits and approvals and their estimated regulatory timeframes may be found in Appendix D. 4. Dissemination of Information 4.1. Website Development A targeted Project page on the Spectra Energy website was launched in June 2013, and a standalone website for the NEXUS Project was launched in July The websites provide visitors with a toll free telephone number to obtain information and/or ask questions about the Project. This website was designed to be more interactive and to provide easy to understand and frequent updates. Appendix F provides a sample of the NEXUS Project pages. 8

26 NEXUS Project Public and Agency Participation Plan Accessibility The NEXUS Project websites provide stakeholders with information about the company, as well as facts about the Project, regulatory process, virtues of natural gas, pipeline operations, safety and maintenance, and Frequently Asked Questions. A toll free telephone contact number was established to assist stakeholders with their questions and comments. In addition, we ensure information is disseminated, as requested by stakeholders, since not all stakeholders have access to the Internet Maintenance The webmaster maintains the website and manages web-based stakeholder inquiries Interactive Capabilities The website houses a "Contact Us" section, which includes a web/e form. This allows stakeholders to request information about the Project, and we will respond within three (3) business days Federal, State and Local Agency Communications Consultation letters were ed to the identified federal, state and local permitting agencies with jurisdiction over the Project. We maintain contact with the permitting agencies and respond to all requests for information we receive from them. See Appendix C for a list of agencies and Appendix G for sample letters Stakeholder Notification of FERC Pre-Filing Participation All stakeholders will be notified by letter in the event that FERC approves the NEXUS Project to participate in the Pre-Filing process. These letters will be signed by the NEXUS Project s team members accountable for specific stakeholder groups Voluntary Landowner Informational Meetings In October and November 2014, NEXUS conducted 9 voluntary Landowner Informational Meetings in convenient locations for affected landowners. NEXUS subject matter experts hosted meetings in Ohio and Michigan. At the voluntary landowner informational meetings and public open house meetings, information was available regarding all aspects of the Project, pipeline operations, safety and our company. Sign-in sheets documented the names and contact information for participants in order to allow for follow-up, as appropriate, with affected landowners. See Appendix H for a list of voluntary Landowner Informational Meetings. 9

27 NEXUS Project Public and Agency Participation Plan 4.5. Landowner Invitations to Voluntary Landowner Informational Meetings Letters inviting landowners to voluntary Landowner Informational Meetings were distributed prior to the meetings. See Appendix G for sample letters to landowners Public Libraries for Filings To ensure filings are accessible and convenient, we will place draft environmental resource reports in the public libraries of each community where proposed facilities are located. Routine checks of the libraries will be conducted to ensure the information remains available. The FERC certificate application along with final resource reports will also be filed in these public libraries Updates of Information Updates will be approved by our Project Manager and disseminated to stakeholders in a timely manner. Methods of dissemination of information to stakeholders include U.S., hand-delivery, e, Project website and/or telephone calls Filings with FERC The NEXUS Project Application will meet all FERC requirements. 5. NEXUS Project Schedule Conduct Landowner Informational Meetings October - November 2014 Request Pre-Filing initiation Submit Draft Resource Reports 1 & 10 (Description & Alternatives) January 2015 Conduct Open Houses / FERC Scoping Meetings January - April 2015 Submit Draft Resource Reports June 2015 File FERC Certificate Application November 2015 Submit Federal and State Permit Applications October - December 2015 FERC issues Certificate November 2016 Submit Implementation Plan December 2016 Receive Final Agency Clearances December 2016 Start Major Construction January 2017 Place Project into Service November

28 6. Reporting NEXUS Project Public and Agency Participation Plan All FERC, federal, state and local government reporting will be timely and respectful of requirements. An official list of contacts within each stakeholder group has been developed to effectively and efficiently provide copies of reports and updates, as warranted. 11

29 NEXUS Project Public and Agency Participation Plan Appendix A: Project Overview Map

30 NEXUS Project Public and Agency Participation Plan Appendix B: Stakeholder List Landowners CONTAINS PRIVILEGED INFORMATION DO NOT RELEASE FILED UNDER SEPARATE COVER

31 Appendix C: Stakeholder List -- Non-Landowners Federal, State and Local Agencies NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address FEDERAL FERC USACE Office of Energy Projects Division of Gas- Environment and Engineering USACE Pittsburgh District (Northern Pittsburgh District) TBD, FERC Project Manager Matt Mason, Regulatory Branch TBD (412) TBD Matthew.R.Mason@usace.a rmy.mil FERC Office of Energy Projects Division of Gas- Environment and Engineering 888 First, NE Washington, D.C office 6J-06 Pittsburgh District Corps of Engineers William S. Moorhead Federal Building 1000 Liberty Avenue Regulatory Branch, Suite 2200 Pittsburgh, PA Initial Contact Date 10/31/14 Date Sent 10/31/14 via FedEx Response Date/Type USACE Huntington District Mark Taylor, Chief, Energy Resources (304) MARK.A.TAYLOR@usace.ar my.mil Huntington District Regulatory Division 502 8th Huntington, WV /31/14 10/31/14 via FedEx USACE Buffalo District Office Mark Scalabrino Ohio Regulatory Chief (800) TBD Buffalo District Office 1776 Niagara St. Buffalo, NY /31/14 10/31/14 via FedEx 14

32 NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address USACE USFWS USFWS USFWS Detroit District East Lansing Michigan Field Office Michigan Field Office Ohio Field Office Stanley F. Cowton, Jr., Regulatory Project Manager Chris Mensing, Fish and Wildlife Biologist Burr Fisher, Wildlife Biologist Angela Boyer, Endangered Species Coordinator (313) (517) (517) (614) x22 stanley.f.cowton@usace.ar my.mil chris_mensing@fws.gov Burr_fisher@fws.com angela_boyer@fws.gov USACE, Regulatory Office 477 Michigan Avenue, 6th Floor Detroit, Michigan East Lansing Field Office 2651 Coolidge Road East Lansing, MI East Lansing Field Office 2651 Coolidge Road East Lansing, MI U.S. Fish and Wildlife Service Ohio Field Office 4625 Morse Rd Suite 104 Columbus, OH, Initial Contact Date 10/31/14 10/14/14 via phone 09/22/14 via e 09/18/14 via e Date Sent 10/31/14 via FedEx 10/14/14 via e 09/22/14 via e 09/18/14 via e Response Date/Type 11/03/14 via e 10/23/14 via e 9/25/14 via e 09/18/14 via e NPS Midwest Region Mr. Mark Weekly Deputy Regional Director (402) Mark_Weekley@nps.gov National Park Service 601 Riverfront Drive Omaha, NE /31/14 10/31/14 via FedEx USEPA NEPA Implementation Section Kenneth A. Westlake, Chief (312) westlake.kenneth@epa.gov U.S. Environmental Protection Agency, Region 5 77 West Jackson Boulevard Chicago, Illinois /31/14 10/31/14 via FedEx 11/06/14 via phone NMFS Office of Protected Resources Donna Wieting Director, Office of Protected Resources (301) NA National Marine Fisheries Service 1315 East-West Highway Silver Spring, MD /31/14 10/31/14 via FedEx 15

33 NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address STATE OHIO OEPA Central Mike Mansour OEPA Central Dave Morehart OEPA Northeast District Ed Fasko OEPA Northeast District Jana Gannon OEPA OEPA OEPA OEPA OEPA ODNR Northeast District Akron Regional Air Quality Management District Akron Regional Air Quality Management District Akron Regional Air Quality Management District Toledo Division of Environmental Services Office of Real Estate Kevin Fortune Sean Vadas Kelly Kanoza Duane LaClair Matt Stanfield John Kessler, P.E. Assistant Chief (614) (614) (330) (330) (330) (330) (330) (330) (419) (614) mike.mansour@epa.ohio.g ov dave.morehart@epa.ohio.g ov ed.fasko@epa.ohio.gov jana.gannon@epa.ohio.gov kevin.fortune@epa.ohio.go v svadas@schd.org kkanoza@schd.org dlaclair@schd.org matthew.stanfield@toledo. oh.gov john.kessler@dnr.state.oh. us Ohio EPA Central Office Ohio EPA Central Office Ohio EPA Northeast District Office Ohio EPA Northeast District Office Ohio EPA Northeast District Office Akron Regional Air Quality Management District Akron Regional Air Quality Management District Akron Regional Air Quality Management District Toledo Division of Environmental Services Ohio Department of Natural Resources, Office of Real Estate 2045 Morse Rd., Columbus, OH Initial Contact Date 12/09/14 meeting 12/09/14 meeting 12/10/14 meeting 12/10/14 meeting 12/10/14 meeting 12/10/14 meeting 12/10/14 meeting 12/10/14 meeting 12/17/14 meeting 09/18/14 Date Sent 12/09/14 meeting 12/09/14 meeting 12/10/14 meeting 12/10/14 meeting 12/10/14 meeting 12/10/14 meeting 12/10/14 meeting 12/10/14 meeting 12/17/14 meeting 09/18/14 via e Response Date/Type 09/19/14 via e 16

34 NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address ODNR SHPO STATE - MICHIGAN Ohio Coastal Management Program ODNR Office of Coastal Management Ohio Office of Historic Preservation Steve Holland, MPA Federal Consistency Administrator Mark Epstein Department Head, Resource Protection and Review MDNR Wildlife Division Lori Sargent MNFI Natural Features Inventory Michael A. Sanders Rare Species Review Specialist (419) (614) (517) (517) steven.holland@dnr.state.o h.us mepstein@ohiohistory.org sargentl@michigan.gov sander75@msu.edu ODNR Office of Coastal Management 105 West Shoreline Drive Sandusky, Ohio Ohio Historic Preservation Office 800 E. 17th Avenue Columbus, Ohio Michigan Department of Natural Resources P.O. Box Lansing, MI Michigan State University Extension 3rd Floor Constitution Hall 525 W. Allegan St. Lansing, MI Initial Contact Date 12/02/14 via e and phone 11/5/14 via letter 09/22/14 via e 09/23/14 via e Date Sent 12/02/14 via e 11/5/14 via letter 09/22/14 via e 09/23/14 via e Response Date/Type 12/02/14 via e and phone 09/23/14 via e 10/09/14 via letter MDEQ Jackson District Office Ms. Katherine David (517) DAVIDK@michigan.gov 301 E. Louis Glick Highway Jackson, Michigan /18/14 12/18/14 via FedEx SHPO Michigan Office of Historic Preservation Martha MacFarlane- Faes Deputy State Historic Preservation Officer (517) FaesM@michigan.gov Michigan State Housing Development Authority 702 W. Kalamazoo St. P.O. Box Lansing, Michigan /4/14 via letter 12/4/14 via letter 17

35 NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address SHPO TRIBES Michigan Office of Historic Preservation Absentee-Shawnee of Indians of Oklahoma Bad River Band of the Lake Superior of Chippewa Indians of the Bad River Reservation Bad River Band of the Lake Superior of Chippewa Indians of the Bad River Reservation Bay Mills Indian Community Bay Mills Indian Community Brian D. Conway State Historic Preservation Officer Joseph Blanchard Cultural Preservation Director Tribal Historic Preservation Officer Michael Wiggins Chairman Edith Leoso Tribal Historic Preservation Officer Levi Carrick, Sr. Chairman Paula Carrick Tribal Historic Preservation Officer (517) (405) , ext 203 (715) (715) (906) (906) Conwayb1@michigan.gov joseph.blanchard@astribe. com hrmanager@badrivernsn.gov paulacarrick@baymills.org Michigan State Housing Development Authority 702 W. Kalamazoo St. P.O. Box Lansing, Michigan Absentee-Shawnee of Indians of Oklahoma 2025 S. Gordon Cooper Drive Shawnee, OK Bad River Band of the Lake Superior of Chippewa Indians of the Bad River Reservation P.O. Box 39 Odanah, WI Bad River Band of the Lake Superior of Chippewa Indians of the Bad River Reservation P.O. Box 39 Odanah, WI Bay Mills Indian Community W. Lakeshore Drive Brimley, MI Bay Mills Indian Community W. Lakeshore Drive Brimley, MI Initial Contact Date 12/4/14 via letter Date Sent 12/4/14 via letter Response Date/Type 18

36 NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address Bois Forte Band (Nett Lake) of the Minnesota Chippewa Bois Forte Band (Nett Lake) of the Minnesota Chippewa Chippewa-Cree Indians of the Rocky Boy's Reservation Chippewa-Cree Indians of the Rocky Boy's Reservation Citizen Potawatomi Nation Citizen Potawatomi Nation Delaware Nation Delaware Nation Kevin Leecy Chairman Rosemary Berens Tribal Historic Preservation Officer Bruce Sunchild Chairman Alvin Windy Boy Tribal Historic Preservation Officer John Barrett Chairman Kelli Mosteller Tribal Historic Preservation Officer C.J. Watkins Vice President Tamara Francis- Fourkiller Cultural Preservation Director (218) (218) (406) (406) (405) (405) (405) (405) , ext 1180 kevin.leecy@boisfortensn.gov rozeberens@yahoo.com bsunchild@yahoo.com alvin@nei-yahw.com rbarrett@potawatomi.org kelli.mosteller@potawato mi.org tfrancis@delawarenation.c om Bois Forte Band (Nett Lake) of the Minnesota Chippewa P.O. Box 16 Nett Lake, MN Bois Forte Band (Nett Lake) of the Minnesota Chippewa P.O. Box 16 Nett Lake, MN Chippewa-Cree Indians of the Rocky Boy's Reservation 31 Agency Square Box Elder, MT Chippewa-Cree Indians of the Rocky Boy's Reservation P.O. Box 230 Box Elder, MT Citizen Potawatomi Nation 1601 S. Gordon Cooper Drive Shawnee, OK Citizen Potawatomi Nation 1601 S. Gordon Cooper Drive Shawnee, OK Delaware Nation P.O. Box 825 Anadarko, OK Delaware Nation P.O. Box 825 Anadarko, OK Initial Contact Date Date Sent Response Date/Type 19

37 NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address Delaware of Indians Delaware of Indians Eastern Shawnee of Oklahoma Eastern Shawnee of Oklahoma Fond du Lac Band of the Minnesota Chippewa Fond du Lac Band of the Minnesota Chippewa Forest County Potawatomi Forest County Potawatomi Paula Pechonick Chief Dr. Brice Obermeyer Director, Tribal Historic Preservation Office Glenna J. Wallace Chief Robin Dushane Tribal Historic Preservation Officer Karen Driver Chairwoman LeRoy Defoe Tribal Historic Preservation Officer Harold Frank Chairman Melissa Cook Tribal Historic Preservation Officer (918) (620) (918) (918) ext 247 (218) (218) (715) (800) ext 7248 bobermeyer@delawaretrib e.org gjwallace@estoo.net r.dushane@estoo.net karendriver@fdlrez.com leroydefoe@fdlrez.com melissa.cook@fcpotawato mi-nsn.gov Delaware of Indians 170 N Barbara Ave Bartlesville, OK Delaware of Indians Roosevelt Hall, Room Commercial Emporia, KS Eastern Shawnee of Oklahoma P.O. Box 350 Seneca, MO Eastern Shawnee of Oklahoma South 705 Road Wyandotte, OK Fond du Lac Band of the Minnesota Chippewa 1720 Big Lake Road Cloquet, MN Fond du Lac Band of the Minnesota Chippewa 1720 Big Lake Road Cloquet, MN Forest County Potawatomi 5416 Everybody's Rd Crandon, WI Forest County Potawatomi Cultural Center, Library & Museum 8130 Mishkoswen Drive PO Box 340 Crandon, WI Initial Contact Date Date Sent Response Date/Type 11/17/14 via letter 20

38 NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address Grand Portage Band of the Minnesota Chippewa Grand Portage Band of the Minnesota Chippewa Grand Traverse Band of Ottawa and Chippewa Indians Hannahville Indian Community Keweenaw Bay Indian Community Keweenaw Bay Indian Community Lac Courte Oreilles Band of Lake Superior Chippewa Indians of Wisconsin Norman Deschampe Chairman Mary Ann Gagnon Tribal Historic Preservation Officer Derek J. Bailey Chairperson Kenneth Meshigaud Chairperson Donald Shalifoe, Sr. Ogimaa Chris Chosa Tribal Historic Preservation Officer Michael Isham, Jr. Chairman (218) (218) (231) (906) (906) (906) (715) norman@grandportage.co m maryanng@grandportage.c om derek.bailey@gtindians.co m tcchris@kbic-nsn.gov terrikay@cheqnet.net Grand Portage Band of the Minnesota Chippewa P.O. Box 428 Grand Portage, MN Grand Portage Band of the Minnesota Chippewa P.O. Box 428 Grand Portage, MN Grand Traverse Band of Ottawa and Chippewa Indians 2605 North West Bayshore Drive Suttons Bay, MI Hannahville Indian Community N14911 Hannahville B1 Rd Wilson, MI Keweenaw Bay Indian Community Beartown Road Baraga, MI Keweenaw Bay Indian Community Beartown Road Baraga, MI Lac Courte Oreilles Band of Lake Superior Chippewa Indians of Wisconsin West Trapania Road, Building No. 1 Hayward, WI Initial Contact Date Date Sent Response Date/Type 21

39 NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address Lac Courte Oreilles Band of Lake Superior Chippewa Indians of Wisconsin Lac du Flambeau Band of Lake Superior Chippewa Indians of the Lac du Flambeau Reservation of Wisconsin Lac du Flambeau Band of Lake Superior Chippewa Indians of the Lac du Flambeau Reservation of Wisconsin Lac Vieux Desert Band of Lake Superior Chippewa Indians Lac Vieux Desert Band of Lake Superior Chippewa Indians Leech Lake Band of the Minnesota Chippewa Jerry Smith Tribal Historic Preservation Officer Tom Maulson President Melinda Young Tribal Historic Preservation Officer Alan Shively Chairman Giiwegiizhigoo kway Martin Tribal Historic Preservation Officer Carrie Jones Chairwoman (715) (715) (715) (906) (906) (218) jim.williams@lvdtribal.com gmartin@lvdtribal.com Lac Courte Oreilles Band of Lake Superior Chippewa Indians of Wisconsin West Trapania Road, Building No. 1 Hayward, WI Lac du Flambeau Band of Lake Superior Chippewa Indians of the Lac du Flambeau Reservation of Wisconsin P.O. Box 67 Lac du Flambeau, WI Lac du Flambeau Band of Lake Superior Chippewa Indians of the Lac du Flambeau Reservation of Wisconsin P.O. Box 67 Lac du Flambeau, WI Lac Vieux Desert Band of Lake Superior Chippewa Indians P.O. Box 249 Watersmeet, MI Lac Vieux Desert Band of Lake Superior Chippewa Indians P.O. Box 249 Watersmeet, MI Leech Lake Band of the Minnesota Chippewa 115 6th NW Suite E Cass Lake, MN Initial Contact Date Date Sent Response Date/Type 22

40 NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address Leech Lake Band of the Minnesota Chippewa Match-e-be-nashshe-wish Band of Potawatomi Indians of Michigan Miami of Oklahoma Mille Lacs Band of the Minnesota Chippewa Mille Lacs Band of the Minnesota Chippewa Minnesota Chippewa Miami of Oklahoma Nottawaseppi Huron Band of the Potawatomi Gina Lemon Tribal Historic Preservation Officer David Sprague Chairman George Strack Tribal Historic Preservation Officer Melanie Benjamin Chief Executive Natalie Weyaus Tribal Historic Preservation Officer Norman Deschampe President Douglas Lankford Chief Homer Mandoka Chairman (616) (918) (320) (320) (218) (918) (269) dsprague@mbpi.org gstrack@miamination.com info@miamination.com hmandoka@nhbpi.com Leech Lake Band of the Minnesota Chippewa 115 6th NW Suite E Cass Lake, MN Match-e-be-nash-she-wish Band of Potawatomi Indians of Michigan P.O. Box 218 Dorr, MI Miami of Oklahoma P.O. Box 1326 Miami, OK Mille Lacs Band of the Minnesota Chippewa Oodena Drive Onamia, MN Mille Lacs Band of the Minnesota Chippewa Oodena Drive Onamia, MN Minnesota Chippewa P.O. Box 217 Cass Lake, MN Miami of Oklahoma P.O. Box 1326 Miami, OK Nottawaseppi Huron Band of the Potawatomi /2 Mile Road Fulton, MI Initial Contact Date Date Sent Response Date/Type 23

41 NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address Nottawaseppi Huron Band of the Potawatomi Ottawa of Oklahoma Ottawa of Oklahoma Peoria of Indians of Oklahoma Pokagon Band of Potawatomi Indians Pokagon Band of Potawatomi Indians Prairie Band of Potawatomi Nation Quechan of the Fort Yuma Indian Reservation Jeff Chivis Tribal Historic Preservation Officer Ethel Cook Chief Rhonda Dixon Tribal Historic Preservation Officer John P. Froman Chief Matthew J. Wesaw Chairman Mike Zimmerman Tribal Historic Preservation Officer Steve Ortiz Chairman Mike Jackson President (269) (918) (918) (918) (517) (269) (785) (760) jchivis@nhbpi.com adawetribe@sbcglobal.net dixon_rhonda@sbcglobal.n et jfroman@peoriatribe.com matthew.wesaw@pokagon band-nsn.gov michael.zimmerman@poka gonband-nsn.gov Nottawaseppi Huron Band of the Potawatomi 1485 Mno-Bmadzewen Way Fulton, MI Ottawa of Oklahoma P.O. Box 110 Miami, OK Ottawa of Oklahoma P.O. Box 110 Miami, OK Peoria of Indians of Oklahoma P.O. Box 1527 Miami, OK Pokagon Band of Potawatomi Indians P.O. Box 110 Dowagiac, MI Pokagon Band of Potawatomi Indians P.O. Box 110 Dowagiac, MI Prairie Band of Potawatomi Nation Q Road Mayetta, KS Quechan of the Fort Yuma Indian Reservation P.O. Box 1899 Yuma, AZ Initial Contact Date 12/16/14 Date Sent 12/16/14 Response Date/Type 12/4/14 via e and letter 11/7/14 via letter 24

42 NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address Red Cliff Band of Lake Superior Chippewa Indians of Wisconsin Red Cliff Band of Lake Superior Chippewa Indians of Wisconsin Red Lake Band of Chippewa Indians Saginaw Chippewa Indian of Michigan Saginaw Chippewa Indian of Michigan Sault Ste. Marie of Chippewa Indians of Michigan Seneca-Cayuga of Oklahoma Seneca-Cayuga of Oklahoma Rose Gurnoe- Soulier Chairperson Larry Balber Tribal Historic Preservation Officer Floyd Jourdain Chairperson Dennis V. Kequom Chief William Johnson Curator Aaron Payment, Chairperson LeRoy Howard Chief Paul Barton Tribal Historic Preservation Officer (715) (715) (218) (989) (989) (906) (918) , ext 19 (918) webmaster@redcliffnsn.gov dkequom@sagchip.org wjohnson@sagchip.org aaronpayment@saulttribe. net pbarton@sctribe.com Red Cliff Band of Lake Superior Chippewa Indians of Wisconsin Pike Road, Hwy 13 Bayfield, WI Red Cliff Band of Lake Superior Chippewa Indians of Wisconsin Pike Road, Hwy 13 Bayfield, WI Red Lake Band of Chippewa Indians P.O. Box 550 Redlake, MN Saginaw Chippewa Indian of Michigan 7070 East Broadway Road Mt. Pleasant, MI Ziibwing Center of Anishinabe Culture and Lifeways 6650 East Broadway Road Mt. Pleasant, MI Sault Ste. Marie of Chippewa Indians of Michigan 523 Ashmun Sault Ste. Marie, MI Seneca-Cayuga of Oklahoma South 655 Road Grove, OK Seneca-Cayuga of Oklahoma South 655 Road Grove, OK Initial Contact Date Date Sent Response Date/Type 25

43 NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address Seneca Nation of Indians Seneca Nation of Indians Shawnee Shawnee Sokaogon Chippewa Community St. Croix Chippewa Indians of Wisconsin Tonawanda Band of Seneca Indians of New York Turtle Mountain Band of Chippewa Indians of North Dakota Beverly Cook President Melissa Bach Tribal Historic Preservation Officer Ron Sparkman Chairperson Kim Jumpers Tribal Historic Preservation Officer Garland McGeshick Chairman Stuart Bearheart Chairman Darwin Hill Chief Richard McCloud Chairman (716) , ext 3580 (918) (918) (715) (715) (716) (701) melissa.bach@sni.org ronded@g.com kim.jumper@shawneetribe.com gaye.graham@scc-nsn.gov annb@stcroixtribalcenter.c om tonseneca@aol.com Seneca Nation of Indians 90 O:hi yoh Way Salamanca, NY Seneca Nation of Indians 90 O:hi yoh Way Salamanca, NY Shawnee P.O. Box 189 South Highway 69A, Miami, OK Shawnee P.O. Box 189 South Highway 69A, Miami, OK Sokaogon Chippewa Community 3051 Sand Lake Road Crandon, WI St. Croix Chippewa Indians of Wisconsin Angeline Avenue Webster, WI Tonawanda Band of Seneca Indians of New York P.O. Box Meadville Road Basom, NY Turtle Mountain Band of Chippewa Indians of North Dakota P.O. Box 900 Belcourt, ND Initial Contact Date Date Sent Response Date/Type 26

44 NEXUS Project Public and Agency Participation Plan NEXUS Project Stakeholder List Non-Landowners Federal, State, and Local Agency Contacts Agency Office Contact Phone E Address White Earth Band of Minnesota Chippewa White Earth Band of Minnesota Chippewa Wyandotte Nation Wyandotte Nation Erma Vizenor Chairman Renee Lampi Tribal Historic Preservation Officer Billy Friend Chief Sherri Clemons Tribal Historic Preservation Officer (218) (218) (918) (918) ext 244 desiraes@whiteearth.com sclemons@wyandotte.org White Earth Band of Minnesota Chippewa P.O. Box 418 White Earth, MN White Earth Band of Minnesota Chippewa P.O. Box 418 White Earth, MN Wyandotte Nation E. Highway 60 Wyandotte, OK Wyandotte Nation E. Highway 60 Wyandotte, OK Initial Contact Date Date Sent Response Date/Type LOCAL CLG MWCD Washtenaw County Historic Preservation Muskingum Watershed Conservancy District Melissa Milton- Pung Historic Preservation Planner Boris E. Slogar, P.E., M.P.M. Chief Engineer (734) (330) (866) miltonpungm@ewashtena w.org TBD Washtenaw County Office of Community & Economic Development 110 N. Fourth Ave. Ann Arbor, MI Muskingum Watershed Conservancy District 1319 Third St. NW PO Box 349 New Philadelphia, OH /27/14 10/27/14 27

45 NEXUS Project Public and Agency Participation Plan Appendix D: Agency Permits and Approvals NEXUS Project Agency Permits and Approvals Agency Assumed Permit/Approval/ Consultation Assumed Approval Timeline Assumed Studies Needed to Support Applications FEDERAL Federal Energy Regulatory Commission (FERC) U.S. Army Corps of Engineers (USACE) (Buffalo, Pittsburgh, Huntington, & Detroit Districts) U.S. Department of Interior Fish and Certificate of Public Convenience and Necessity - Section 7(c) of the Natural Gas Act requires preparation of an ER (consisting of 12 Resource Reports) to be included with the Section 7(c) application. Spectra Energy is proposing to use FERC s Pre-filing Process which will involve conducting public open houses, preparation of responses to comments received on the Project, and preparation of draft and final Resource Reports. Following submittal of the ER, support activities include responding to FERC staff data requests, reviewing FERC s EIS and preparing the Implementation Plan. Assessment of environmental impacts under the National Environmental Policy Act (42 USC 4321 et seq., 18 CFR Part 380) Section 404 of the Clean Water Act (CWA), Section 10 of the Rivers and Harbors Act Consultation under Section 7 Endangered Species Act (ESA), Approval Process: Approximately 23 months assumes an Environmental Impact Statement (EIS) Approval Process: months Concurrent with the FERC EIS Approval Process: 23 months concurrent Pre-filing Notice Letter Pre-filing Environmental Reports Response to public comments Formal filing of Environmental Reports Data Request Response Implementation Plan Nationwide or Individual Permit applications depending on the results of agency consultations and anticipated impact thresholds. Delineate and map wetlands and waterbodies and quantify area of temporary and permanent wetland impacts. Develop procedures to avoid, minimize and mitigate impacts to wetlands and waterbodies. USACE Jurisdictional Determination (JD) data forms for wetland and waterbody crossings, if necessary Threatened and Endangered (T&E) species surveys. Specialized protected species surveys (e.g., Indiana bat; northern long- 28

46 NEXUS Project Public and Agency Participation Plan NEXUS Project Agency Permits and Approvals Agency Assumed Permit/Approval/ Consultation Assumed Approval Timeline Assumed Studies Needed to Support Applications Wildlife Service (USFWS); Midwest Region 3 (Columbus, Ohio and East Lansing, Michigan Field offices) U.S. Department of Interior National Park Service U.S. Department of Agriculture Natural Resource Conservation Service U.S. Environmental Protection Agency (USEPA) (Region 3) U.S. Department of Transportation, Federal Aviation Administration Migratory Bird Treaty Act (MBTA) with FEIS process eared bat). Prepare separate Biological Assessment (BA) evaluating impacts to T&E species and habitat, if required. Develop procedures to avoid, minimize, and mitigate impacts to T&E species and habitat. Develop T&E species protection and monitoring plans (e.g., Indiana bat; northern long-eared bat). Wabash Cannonball Trail historically significant segments Restoration Consultation and potential Agricultural Impact Mitigation Agreement. Review of USACE (CWA) applications with 404(c) authority for wetland permits issued by the USACE Review Section 10 applicability Delegated state oversight and review of NPDES permit program for discharges of hydrostatic test water in Ohio and Michigan Review of any major source air permit issued by OEPA Determination of No Hazard may be required for communication towers greater than 200 feet above ground level Approval Process: Unknown but expected to be concurrent with other processes Approval Process: 6 12 months Approval Process: Oversight of Federal and state agency review 60 to 90 days depending on complexity of identified potential hazards Consultation letter will be prepared requesting comments Coordinate with USDA on agricultural impacts and procedures. Coordinate with USEPA on review of USACE CWA applications, applicability and permit process. Coordinate with USEPA on review of DEIS, FEIS and NEPA process. Coordinate with FAA, Department of Defense, and National Telecommunications Information Administration (NTIA) to determine potential for conflicts with existing facilities. Perform required impact assessments (if required) Coordinate with agencies a file required permit applications Advisory Council on Historic Preservation and Consultation with Native American s Section 106 Consultation, NHPA consultation with Native American tribes with ties to the Project area to obtain comments or concerns regarding potential impacts to traditional Native American cultural Approval Process: 12+ months of consultation concurrent with FEIS process. Approval through the FEIS Native American tribes in the Project area will be identified and consultation letters to each tribe will be prepared, requesting comments on the Project 29

47 NEXUS Project Public and Agency Participation Plan NEXUS Project Agency Permits and Approvals Agency Assumed Permit/Approval/ Consultation Assumed Approval Timeline Assumed Studies Needed to Support Applications or historic properties. To ensure compliance, FERC will consult directly with the Advisory Council. Process. STATE Ohio Power Siting Board (OPSB) Ohio Department of Natural Resources (ODNR), Division of Wildlife ODNR, Division of Soil and Water Conservation Potential Consultation and Intervener Status in FERC Process State listed species consultation. Agricultural Impact Mitigation Agreement ( AIMA ) Potential intervener in the FERC Process Consultation: months depending on identified species and survey requirements Approval Process: TBD may or may not be required Limited consultation to ensure understanding of the Project scope and schedule. Establish a positive relationship with the OPSB to help streamline the overall process. Protected species surveys, as required after consultation with ODNR. Specialized protected species surveys (e.g., Indiana bat, northern longeared bat) Consultation regarding state listed species affected by the Project that may require consideration. Development of agreement ODNR, Office of Coastal Management Ohio Environmental Protection Agency (OEPA), Division of Surface Water Coastal Zone Consistency Determination for work within the Lake Erie Coastal Zone Management Area Section 401 Water Quality Certification NPDES General Permit for Discharge of Hydrostatic Test Water FERC regulated pipelines are exempted from the NPDES application process (but still must comply with federal construction stormwater discharge standards) Isolated Wetlands Permit, if required. Statutory review time allows ODNR 6 months for review. Consultation and Approval Process: Initial pre-filing consultation and 6 months for approval after acceptance of the application Evaluate activities proposed within the mapped Lake Erie Coastal Zone Management area boundary to confirm they will be performed in compliance with the enforceable policies of Ohio s approved coastal management program File application and certify in writing that proposed activities are in compliance with the enforceable policies of Ohio s approved coastal management program Delineation and mapping of wetlands and quantification of acreage Mitigation plans for wetland losses exceeding 1/10 acre (including temporary impacts), and also for conversion of forested wetland to scrub-shrub/emergent wetland. 30

48 NEXUS Project Public and Agency Participation Plan NEXUS Project Agency Permits and Approvals Agency Assumed Permit/Approval/ Consultation Assumed Approval Timeline Assumed Studies Needed to Support Applications OEPA, Division of Air Pollution Control Ohio Historical Society (Ohio State Historic Preservation Office [SHPO]) Ohio Department of Transportation (ODOT) Various railroad, transmission line, and other right-of-way owners. Michigan Department of Natural Resources (MDNR), Wildlife Division MDNR Major/minor source permits to install and operate depending on compressor station horsepower requirements. Possible minor source permits to install and operate for meter station air emissions. NHPA, Section 106 Consultation State road, highway, or interstate crossing permits Railroad, transmission line, and other right-of-way crossing negotiations. State listed species consultation. Public Lands consultation Permit to Use State Lands Approval Process: 6-18 months Consultation and Approval Process which starts after surveys complete: 20 months total Approval Process: 4-6 months Approval Process: 4-12 months Consultation: months depending on identified species and survey requirements Approval Process: 3-6 months Air quality dispersion modeling may be required for compressor stations. Top down BACT analysis for any pollutants above significance thresholds. State BAT analysis required for pollutants exceeding 10 TPY. Phase I survey to identify historically or archeologically significant properties. Phase II studies to determine eligibility for inclusion of properties on the National Register of Historic (or Archeological) Places, after identification at the Phase I level. Phase III mitigation for National Register properties impacted by the Project, if required after Phase II is completed. Mitigation of sites can take 6-9 months or longer. Historic structure assessment, linear resources, viewsheds should also be included, Memorandum of Agreements and tribal consultation will typically be done by FERC, but can add considerably to the time. If there is a time constraint, then some work should be completed by the Applicant. Unanticipated Discoveries Plan Information concurrent with other applications. Information concurrent with other applications. Protected species surveys. Consultation regarding state listed species affected by the Project that may require conservation plans. Information concurrent with other applications. Michigan Department of Environmental Joint Permit consultation MDEQ/USACE Joint Permit for impacts to wetlands, inland lakes, Approval Process: 6 12 months Delineation and mapping of wetlands and waters of the state and quantification of impacts. Mapping of floodplains and quantification of impacts. 31

49 NEXUS Project Public and Agency Participation Plan NEXUS Project Agency Permits and Approvals Agency Assumed Permit/Approval/ Consultation Assumed Approval Timeline Assumed Studies Needed to Support Applications Quality (MDEQ), Water Resources Division MDEQ, Air Quality Division Michigan State Housing and Development Authority (MSHDA) State Historic and Preservation Office (SHPO) Michigan Department of Transportation (MDOT) LOCAL Various railroad, transmission line, and other right-of-way owners. General Concerns of Counties/Cities streams and floodplains NPDES Permit for Storm Water Discharge from Construction Activities Water Withdrawal Authorization Possible permit to install for facility meter station air emissions NHPA, Section 106 Consultation State road, highway, or interstate crossing permits Railroad, transmission line, and other right-of-way crossing negotiations Drain Crossing Permits and Soil Erosion & Sedimentation Control Permits Approval Process: 4-12 months Consultation and Approval Process which starts after surveys complete: 20 months total Approval Process: 4 12 months Approval Process: 4-12 months Approval Process: TBD TBD Phase I survey to identify historically or archeologically significant properties. Phase II studies to determine eligibility for inclusion of properties on the National Register of Historic (or Archeological) Places, if required. Phase III mitigation for National Register properties impacted by the Project, if required. Unanticipated Discoveries Plan Information concurrent with other applications. Information concurrent with other applications. Information concurrent with other applications. Lenawee County, Michigan Monroe County, Michigan Washtenaw County, Michigan County Drain ROW Permits Soil Erosion & Sedimentation Control Permit County Drain ROW Permits Soil Erosion & Sedimentation Control Permit County Drain ROW Permits Soil Erosion & Sedimentation Control Permit Approval Process: 1-3 months Approval Process: 1-3 months Approval Process: 1-6 months Information concurrent with other applications. Information concurrent with other applications. Information concurrent with other applications. 32

50 NEXUS Project Public and Agency Participation Plan Appendix E: Stakeholder List -- Non-Landowners - Public Officials, Community and Public Interest Groups and Non- governmental Organizations Public Officials First Name Last Name County Position Address1 Address2 City State Zip Code David Stimpson Lenawee County County Commissioner 301 North Main Adrian MI Edwin Branch Lenawee County County Commissioner 301 North Main Adrian MI Jim Driskill Lenawee County County Commissioner 301 North Main Adrian MI Cletus Smith Lenawee County County Commissioner 301 North Main Adrian MI Karol Bolton Lenawee County County Commissioner 301 North Main Adrian MI Terry Collins Lenawee County County Commissioner 301 North Main Adrian MI John Tuckerman Lenawee County County Commissioner 301 North Main Adrian MI Ralph Tillotson Lenawee County County Commissioner 301 North Main Adrian MI Chris Wittenbach Lenawee County County Commissioner 301 North Main Adrian MI Martin Marshall Lenawee County County Administrator 301 North Main Adrian MI Bruce Caswell Lenawee County State Senator P.O. Box Lansing MI Mike Shirkey Lenawee County State Representative P.O. Box Lansing MI Nancy Jenkins Lenawee County State Representative P.O. Box Lansing MI Richard Marks Lenawee County Town Supervisor Ogden Township Pence Hwy Blissfield MI Eric Martis Lenawee County Ogden Township 8612 E. Mulberry Blissfield MI Rd. Mark Vandenbusche Lenawee County Ogden Township 6672 E. Weston Rd. Blissfield MI Jim Isley Lenawee County Town Supervisor Palmyra Township 2683 Grosvenor Highway Palmyra MI

51 NEXUS Project Public and Agency Participation Plan Steve Papenhagen Lenawee County Palmyra Township 5765 Palmyra Road Palmyra MI Perry Pooley Lenawee County Palmyra Township 4594 Ogden Highway Al Navarro Lenawee County Town Supervisor Blissfield Township 120 S. Lane, P.O. Box 58 Kris Ruhl Lenawee County Blissfield Township 120 S. Lane, P.O. Box 58 Devon Gilson-Pitts Lenawee County Blissfield Township 120 S. Lane, P.O. Box 58 Ron Cosuino Lenawee County Town Supervisor Deerfield Township 392 East River Keith Kapnick Lenawee County Deerfield Township 1645 N Stearns Highway Daniel Wittenbach Lenawee County Deerfield Township 2352 Stearns Highway Lee Wagner Lenawee County Town Supervisor Macon Township 8329 Macon-Clinton Road David Wielfaert Lenawee County Macon Township 8329 Macon-Clinton Road Ed Clark Wielfaert Lenawee County Macon Township 8329 Macon-Clinton Road Robert Downing Lenawee County Town Supervisor Ridgeway Township 6666 North County Line Highway Marc Brown Lenawee County Ridgeway Township 7583 Hendershot Highway Daniel Prielipp Lenawee County Ridgeway Township 4651 Downing Highway David Hoffman Monroe County County Commissioner 125 East Second Mark Brant Monroe County County Commissioner 125 East Second Al Potratz Monroe County County Commissioner 125 East Second Robert Lambert Monroe County County Commissioner 125 East Second Jason Turner Monroe County County Commissioner 125 East Second Jerry Oley Monroe County County Commissioner 125 East Second Jon Cook Monroe County County Commissioner 125 East Second Jason Sheppard Monroe County County Commissioner 125 East Second Adrian MI Blissfield MI Blissfield MI Blissfield MI Deerfield MI Deerfield MI Deerfield MI Clinton MI Clinton MI Clinton MI Britton MI Tecumseh MI Britton MI Monroe MI Monroe MI Monroe MI Monroe MI Monroe MI Monroe MI Monroe MI Monroe MI

52 NEXUS Project Public and Agency Participation Plan Michael Bosanac Monroe County County Administrator 125 East Second Monroe MI J. Henry Lievens Monroe County County Commissioner 125 East Second Monroe MI Randy Richardville Monroe County State Senator P.O. Box Lansing MI Phil Heath Monroe County Town Supervisor Milan Township Cone Road Milan MI Olga Mancik Monroe County Milan Township Cone Road Milan MI Bob Dopkowski Monroe County Milan Township 1644 Cone Road Milan MI Kent Martinez-Kratz Washtenaw County Dan Smith Washtenaw County Alicia Ping Washtenaw County Felicia Brabec Washtenaw County Rolland Sizemore, Jr Washtenaw County Ronnie Peterson Washtenaw County Andy LaBarre Washtenaw County Yousef Rabhi Washtenaw County Conan Smith Washtenaw County Verna McDaniel Washtenaw County Adam Zemke Washtenaw County David Rutledge Washtenaw County Rebekah Warren Washtenaw County John Stanowski Washtenaw County Jill Hargrove Washtenaw County Brian Iott Washtenaw County Jane Kartje Washtenaw County County Administrator 220 North Main Ann Arbor MI County Commissioner 220 North Main Ann Arbor MI County Commissioner 220 North Main Ann Arbor MI County Commissioner 220 North Main Ann Arbor MI County Commissioner 220 North Main Ann Arbor MI County Commissioner 220 North Main Ann Arbor MI County Commissioner 220 North Main Ann Arbor MI County Commissioner 220 North Main Ann Arbor MI County Commissioner 220 North Main Ann Arbor MI County Commissioner 220 North Main Ann Arbor MI State Representative P.O. Box Lansing MI State Representative P.O. Box Lansing MI State Senator P.O. Box Lansing MI Town Supervisor York Township Stony Creek Road York Township Stony Creek Road York Township Stony Creek Road York Township Stony Creek Road Milan MI Milan MI Milan MI Milan MI

53 NEXUS Project Public and Agency Participation Plan Dan Pichla Washtenaw York Township Stony Creek Milan MI County Road Pete Hafler Washtenaw Supervisor Augusta Township P.O. Box 100 Whittaker MI County Cath Howard Washtenaw Augusta Township P.O. Box 100 Whittaker MI County Joe Keefe Washtenaw Augusta Township P.O. Box 100 Whittaker MI County Judy Thornton Washtenaw Augusta Township P.O. Box 100 Whittaker MI County Ira Todd Washtenaw Augusta Township P.O. Box 100 Whittaker MI County Larry Doe Washtenaw Treasurer Ypsilanti Township 7200 South Huron Ypsilanti MI County River Drive Brenda Stumbo Washtenaw Ypsilanti Township 7200 South Huron Ypsilanti MI County River Drive Jean Hall Currie Washtenaw Ypsilanti Township 7200 South Huron Ypsilanti MI County River Drive Mike Martin Washtenaw Ypsilanti Township 7200 South Huron Ypsilanti MI County River Drive Scott Martin Washtenaw Ypsilanti Township 7200 South Huron Ypsilanti MI County River Drive Stan Eldridge Washtenaw Ypsilanti Township 7200 South Huron Ypsilanti MI County River Drive Tim Walberg Lenweee, Monroe, US Representative 110 First, Jackson MI Washtanaw Counties Suite 2 John Dingell Washtenaw US Representative West Outer Dearborn MI County Drive, Suite 103-E Debbie Stabenow US Senator 221 West Lansing East MI Road, Suite 100 Lansing Carl Levin US Senator 477 Michigan Detroit MI Avenue, Suite 1860 Rick Snyder Governor P. O. Box Lansing MI

54 NEXUS Project Public and Agency Participation Plan First Name Last Name County Position Address1 Address2 City State Zip Code Jeffrey Ohler Carroll County Commissioner 879 Courtview Dr Carrollton OH Thomas Wheaton Carroll County Commissioner 4082 Perth Rd SE Carrollton OH Robert Wirkner Carroll County Commissioner 2072 Brenner Rd Carrollton OH NE Curtis Frase Carroll East Township 8156 Mark Rd NE Kensington OH Richard Miller Carroll East Township 5210 Meadow Rd Kensington OH NE Russell Shipley Carroll East Township 9099 Apollo Rd NE Kensington OH Andy Thompson Carroll State Representative 77 South High Columbus OH Michael Halleck Columbiana County Commissioner 2096 Country Side Salem OH Dr James Hoppel Columbiana County Commissioner Calcutta E Liverpool OH Smith Ferry Rd Timothy Weigle Columbiana County Commissioner England Dr E Palestine OH Bert Dawson Columbiana County Engineer Fisher Ave E Liverpool OH Robert Manfull Columbiana Hanover Township Manfull Lake Kensington OH Rd Mancil Ridgeway Columbiana Hanover Township Hanoverton OH Mechanicstown Rd John Zehentbauer Columbiana Hanover Township Lindesmith PO Box 304 Hanoverton OH Rd Gregory Carver Columbiana Knox Township 4038 Homeworth Homeworth OH Rd Sara Crawford Columbiana Knox Township Hartley Rd Beloit OH Benjamin Pidgeon Columbiana Knox Township SR 62 Beloit OH Nick Barborak Columbiana State Representative 77 South High Columbus OH Joe Schiavoni Columbiana State Senator 1 Captiol Square Columbus OH Dale Lowmiller Columbiana West Township SR 172 Minerva OH Richard Mcclellan Columbiana West Township Mc Daniel Rd Minerva OH

55 NEXUS Project Public and Agency Participation Plan Glenn Whiteleather Columbiana West Township 8008 Essick Rd Minerva OH Chris Redfern Erie State Representative 77 South High Columbus OH Rick Jeffrey Erie Auditor 247 Columbus Ave. Rm. 210 Sandusky OH Mathew Old Erie Berlin Township St. Rt. 61 Berlin OH Heights Tadd Smith Erie Berlin Township St. Rt. 61 Berlin OH Heights John Zarvis Erie Berlin Township PO Box 216 Berlin Hts OH John Zarvis Erie Berlin Township St. Rt. 61 Berlin OH Heights Thomas Ferrell, Jr. Erie Commissioner 2900 Columbus Ave Sandusky OH Bill Monaghan Erie Commissioner 2900 Columbus Ave Sandusky OH Patrick Shenigo Erie Commissioner 2900 Columbus Ave Sandusky OH John Farschman Erie Engineer 2700 Columbus Ave Sandusky OH Raymond Halliwell Erie Florence Township Chapel St Wakeman OH "Skip" John Krumweide Erie Florence Township Chapel St Wakeman OH Orville Sayler Erie Florence Township Chapel St Wakeman OH Ron Brown Erie Groton Township 1820 Bogart Rd. Huron OH Roger Rowland Erie Groton Township 1820 Bogart Rd. Huron OH Roger Russell Erie Groton Township 1820 Bogart Rd. Huron OH Daniel Frederick Erie Milan Township 1518 St. Rt 113 Milan OH Frank Lytle Erie Milan Township 1518 St. Rt 113 Milan OH Jim Verbridge Erie Milan Township 1518 St. Rt 113 Milan OH Sparky Weilnau Erie Milan Township 1518 St. Rt. 113 Milan OH Scott Leber Erie Oxford Township Ransom Rd Monroeville OH Michael Parker Erie Oxford Township Ransom Rd Monroeville OH

56 NEXUS Project Public and Agency Participation Plan James Stewart Erie Oxford Township Ransom Rd Monroeville OH Barbara Sessler Erie Recorder 247 Columbus Ave. Suite 225 Sandusky OH Randy Gardner Erie, Wood, Lucas, State Senator 1 Captiol Square Columbus OH Fulton Vond Hall Fulton Administrator 152 S. Fulton St. Wauseon OH #270 Thomas Herr Jr. Fulton Amboy Township 2650 Co. Rd. S Metamora OH Richard Raab Fulton Amboy Township 2650 Co. Rd. S Metamora OH Jeff Simon Fulton Amboy Township 2650 Co. Rd. S Metamora OH Brett Kolb Fulton Auditor 152 S. Fulton St. Suite 165 Wauseon OH Paul Barnaby Fulton Commissioner 152 S. Fulton St. Suite 270 Wauseon OH Bill Rufenacht Fulton Commissioner 152 S. Fulton St. Suite 270 Wauseon OH Perry Rupp Fulton Commissioner 152 S. Fulton St. Suite 270 Wauseon OH Cheryl Geer Fulton Council, Village of P.O. Box 299 Metamora OH Metamora John Hudik Fulton Council, Village of P.O. Box 299 Metamora OH Metamora Karon Lane Fulton Council, Village of P.O. Box 299 Metamora OH Metamora Ned Monroe Fulton Council, Village of P.O. Box 299 Metamora OH Metamora Suzie Stough Fulton Council, Village of P.O. Box 299 Metamora OH Metamora Ken Wysong Fulton Council, Village of P.O. Box 299 Metamora OH Metamora Frank Onweller Fulton Engineer 9120 Co. Rd. 14 Wauseon OH Scott Gillen Fulton Fulton Township 1613 Co Rd N Swanton OH Joe Gombash Fulton Fulton Township 9241 Co Rd 1 Swanton OH David Pilliod Fulton Fulton Township 125 Woodside Dr. Swanton OH Gary Loar Fulton Mayor, Village of P.O. Box 299 Metamora OH Metamora Sandra Barber Fulton Recorder 152 S. Fulton St. Suite 175 Wauseon OH

57 NEXUS Project Public and Agency Participation Plan Roy Miller Fulton Sheriff 129 Courthouse Wauseon OH Plaza Lynn Wachtmann Fulton State Representative 77 South High Columbus OH Cliff Hite Fulton State Senator 1 Captiol Square Columbus OH Ron Holdeman Fulton Swancreek Township 5565 Co. Rd. D Delta OH Rick Kazmierczak Fulton Swancreek Township 5565 Co. Rd. D Delta OH Pamela Moore Fulton Swancreek Township 5565 Co. Rd. D Delta OH Charlene Lee Fulton Treasurer 152 S. Fulton St. Suite 155 Wauseon OH Jim Cordes Lorain Administrator 226 Middle Ave Elyria OH Eric Norenerg Lorain City Manager 85 S. Main Oberlin OH Ted Kalo Lorain Commissioner 226 Middle Avenue Fourth Floor Elyria OH Lori Kokoski Lorain Commissioner 226 Middle Avenue Fourth Floor Elyria OH Tom Williams Lorain Commissioner 226 Middle Avenue Fourth Floor Elyria OH Scott Broadwell Lorain Council, City of Oberlin 85 South Main Oberlin OH Bryan Burgess Lorain Council, City of Oberlin 85 South Main Oberlin OH Sharon Fairchild- Lorain Council, City of Oberlin 85 South Main Oberlin OH Soucy Elizabeth Meadows Lorain Council, City of Oberlin 85 South Main Oberlin OH Sharon Pearson Lorain Council, City of Oberlin 85 South Main Oberlin OH Kristin Peterson Lorain Council, City of Oberlin 85 South Main Oberlin OH Ron Rimbert Lorain Council, City of Oberlin 85 South Main Oberlin OH Ken Carney Lorain Engineer 247 Hadaway Elyria OH Jean Haight Lorain Grafton Township Dan Miller Lorain Grafton Township Carl Wesemeyer Lorain Grafton Township Ronald Baumann Lorain Henrietta Township Avon Belden Road Avon Belden Road Avon Belden Road Vermilion Road PO Box 100 Grafton OH PO Box 100 Grafton OH PO Box 100 Grafton OH Oberlin OH

58 NEXUS Project Public and Agency Participation Plan Howard Born III Lorain Henrietta Township Vermilion Oberlin OH Road Joseph Knoble Lorain Henrietta Township Vermilion Oberlin OH Road Gary Burnett Lorain LaGrange Township Route 303 LaGrange OH Douglas Gardner Lorain LaGrange Township Indian Grafton OH Hollow Road Rita Tompkins Lorain LaGrange Township Diagonal LaGrange OH Canfield Road Patti Brubaker Lorain New Russia Township Butternut Oberlin OH Ridge Road Jack Hoyt Lorain New Russia Township Butternut Oberlin OH Ridge Road John Piwinski Lorain New Russia Township Butternut Oberlin OH Ridge Road Mark Diedrick Lorain Pittsfield Township State Route Oberlin OH Mark McConnell Lorain Pittsfield Township State Route Oberlin OH Forrest Mohrman Lorain Pittsfield Township State Route Oberlin OH Paul Stammitti Lorain Sheriff 9896 Murray Ridge Elyria OH Rd Terry Boose Lorain State Representative 77 South High Columbus OH Dan Ramos Lorain State Representative 77 South High Columbus OH Gayle Manning Lorain State Senator 1 Captiol Square Columbus OH Jim Jordan Lorain, Erie, U.S. House of 1524 Longworth House Office Building Washington DC Sandusky Representatives Laura Lloyd- Jenkins Lucas Administrator One Government Center #870 Toledo OH Anita Lopez Lucas Auditor One Government Suite 600 Toledo OH Center Carol Contrada Lucas Commissioner One Government Suite 800 Toledo OH Center Pete Gerken Lucas Commissioner One Government Suite 800 Toledo OH Center Tina Skeldon Lucas Commissioner One Government Suite 800 Toledo OH Wozniak Center Barb Bruno Lucas Council, Village of Waterville 25 North Second St. Waterville OH

59 42 NEXUS Project Public and Agency Participation Plan Micheline Krise Lucas Council, Village of 25 North Second St. Waterville OH Waterville Charles Larkins Lucas Council, Village of 25 North Second St. Waterville OH Waterville Tim Pedro Lucas Council, Village of 25 North Second St. Waterville OH Waterville John Rozic Lucas Council, Village of 25 North Second St. Waterville OH Waterville Jim Valtin Lucas Council, Village of 25 North Second St. Waterville OH Waterville Keith Earley Lucas Engineer 1049 S. McCord Holland OH Road Keith Early Lucas Engineer One Government Toledo OH Center #870 Lori Brodie Lucas Mayor, Village of 25 North Second St. Waterville OH Waterville Lee Bialecki Lucas Providence Township Perry Road Grand OH Rapids Steve Kendall Lucas Providence Township Perry Road Grand OH Rapids Cody Mastin Lucas Providence Township Perry Road Grand OH Rapids Phil Copeland Lucas Recorder One Government Suite 700 Toledo OH Center John Tharp Lucas Sheriff 1622 Spielbusch Toledo OH Ave Wade Kapszukiewi Lucas Treasurer One Government Suite 500 Toledo OH cz Center Les Disher Lucas Waterville Township 621 Farnsworth Waterville OH Road Robert Hertzfeld Lucas Waterville Township 621 Farnsworth Waterville OH Road Timothy Pedro Lucas Waterville Township 621 Farnsworth Waterville OH Road Barbara Sears Lucas, Fulton State Representative 77 South High Columbus OH Adam Friedrick Medina Commissioner 144 North Medina OH Broadway St., #201 Patricia Geissman Medina Commissioner 144 North Medina OH Broadway St., #201 Stephen Hambley Medina Commissioner 144 North Medina OH Broadway St., #201 Mike Salay Medina Engineer 791 West Smith Road, Medina OH 44256

60 NEXUS Project Public and Agency Participation Plan Steve Fulton Medina Guilford Township 8701 Hubbard Seville OH Valley Rd Robert Rohrer Medina Guilford Township 8612 Yoder Rd Wadsworth OH Glenn Sheller Medina Guilford Township 9027 Skypark Drive Wadsworth OH Lynda Bowers Medina Lafayette Township 6776 Wedgewood Medina OH Road Michael Costello Medina Lafayette Township 6776 Wedgewood Medina OH Road Bryon Macron Medina Lafayette Township 6776 Wedgewood Medina OH Road Dennis Horvath Medina Litchfield Township 9256 Norwalk Road Litchfield OH Michael Pope Medina Litchfield Township 9256 Norwalk Road Litchfield OH Nancy Wargo Medina Litchfield Township 9256 Norwalk Road Litchfield OH Sally Albrecht Medina Montville Township 3077 Blue Heron Medina OH Trace Ronald Bischof Medina Montville Township 3227 Rustic Valley Medina OH Dr Jeff Brandon Medina Montville Township 5184 Glenmore Way Medina OH Bill Batchelder Medina State Representative 77 South High Columbus OH Dave Hall Medina State Representative 77 South High Columbus OH Larry Obhof Medina State Senator 1 Captiol Square Columbus OH Robert Engler Medina Wadsworth Township James Gardner Medina Wadsworth Township Kevin Keiper Medina Wadsworth Township Colene Conley Medina York Township Richard Monroe Medina York Township William Pavlick Medina York Township Bob Gibbs Medina, Lorain, U.S. House of Stark Representatives 263 Wall Road Doylestown OH Hartman Road Wadsworth OH Mennonite Road Wadsworth OH Norwalk Road Mallet OH Creek 6609 Norwalk Road Mallet OH Creek 6609 Norwalk Road Mallet OH Creek 329 Cannon House Washington DC Office Building 43

61 NEXUS Project Public and Agency Participation Plan Warren Brown Sandusky Administrator 622 Croghan Fremont OH William Farrell Sandusky Auditor 100 N. Park Ave. Suite 228 Fremont OH Dan Polter Sandusky Commissioner 622 Croghan St. Fremont OH Charles Schwochow Sandusky Commissioner 622 Croghan St. Fremont OH Terry Thatcher Sandusky Commissioner 622 Croghan St. Fremont OH James Moyer Sandusky Engineer 2500 West State St. Fremont OH Colleen Carmack Sandusky Recorder 100 N. Park Ave. Suite 217 Fremont OH John Antesberger Sandusky Riley Township 1062 N. CR 220 Fremont OH Gary Overmyer Sandusky Riley Township 3420 CR 231 Fremont OH David Sachs Sandusky Riley Township 997 N. CR 198 Fremont OH Paul Lotycz Sandusky Sandusky Township 710 N. Stone St Fremont OH Gilbert Overmyer Sandusky Sandusky Township 1749 CR 142 Fremont OH Michael Willis Sandusky Sandusky Township 351 W. CR 73 Fremont OH Kyle Overmyer Sandusky Sheriff 2323 Countryside Fremont OH Dr. Rex Damschrode Sandusky State Representative 77 South High Columbus OH r Jean Leber Sandusky Townsend Township 1736 N. County Rd. Clyde OH Bruce Meggitt Sandusky Townsend Township 1736 N. County Rd. Clyde OH Paul Warner Sandusky Townsend Township 1736 N. County Rd. Clyde OH Irma Celestino Sandusky Treasurer 100 N. Park Ave. Suite 227 Fremont OH Glenn Baker Sandusky Washington Township Harold Overmyer Sandusky Washington Township Robert Reed Sandusky Washington Township Kenneth Green Sandusky Woodville Township William Hammer Sandusky Woodville Township 211 Lynn St Lindsey OH W. CR 109 Fremont OH CR 92 Lindsey OH CR 44 Woodville OH Water St. Woodville OH

62 45 NEXUS Project Public and Agency Participation Plan Paul Heineman Sandusky Woodville Township 731 Fort Findlay Rd. Woodville OH John Boehner Speaker of House U.S. House of 1011 Longworth House Office Building Washington DC Representatives Brant Luther Stark Administrator 110 Central Plaza S Canton OH #240 Thomas M. Bernabei Stark County Commissioner 2745 Dunkeith Dr., Canton OH NW Janet Weir Creighton Stark County Commissioner 7711 Bucknell Cir., North OH NW Canton Richard Regula Stark County Commissioner 8020 Erie Ave Sw Navarre OH Keith Bennett Stark County Engineer 266 Creekside Cir North OH NE Canton John Arnold Stark Lake Township 2725 Aylesbury St North OH Nw Canton Ellis Erb Stark Lake Township 1477 Lake O Pines Hartville OH St NE Galen Lee Stoll Stark Lake Township 2690 Rita St NE Hartville OH Kenneth Eddleman Stark Marlboro Township Marlboro Louisville OH Ave NE John Hagan Stark Marlboro Township Marlboro Alliance OH Ave NE Wayne Schillig Stark Marlboro Township Marlboro Alliance OH Ave NE Lou Johnson Stark Nimishillen Township 9821 Louisville St Louisville OH NE Mike Lynch Stark Nimishillen Township PO Box 181 Louisville OH Lisa Shafer Stark Nimishillen Township 6590 Winter St NE Louisville OH Christina Hagan Stark State Representative 77 South High Columbus OH Scott Oelslager Stark State Senator 1 Captiol Square Columbus OH Mort Dehoff Stark Washington Township 5789 Beechwood Alliance OH Ave Paul Delpuppo Stark Washington Township 8701 Byrd Ave NE Alliance OH Randy Rodgers Stark Washington Township Bowman St. Homeworth OH NE John Kasich state Ohio Governor 77 South High Columbus OH Bill Johnson state U.S. House of 317 Cannon House Washington DC 20515

63 Representatives Office Building Sherrod Brown state U.S. Senate 713 Hart Senate Office Building Rob Portman state U.S. Senate 448 Russell Senate Office Building Christopher Humphrey Summit City Of Green Council- Green At-Large Administration Gerard Neugebauer Summit City Of Green Council- At-Large Joel Reed Summit City Of Green Council- At-Large Harold Gehm Summit City Of New Franklin Council-At-Large Judy Jones Summit City Of New Franklin Council-At-Large Andrea Norris Summit City Of New Franklin Council-At-Large Building Green Administration Building Green Administration Building New Franklin Administration Building New Franklin Administration Building New Franklin Administration Building 1755 Town Park Blvd. PO Box Town Park Blvd. PO Box Town Park Blvd. PO Box 278 NEXUS Project Public and Agency Participation Plan Washington DC Washington DC Green OH Green OH Green OH Manchester Rd. Akron OH Manchester Rd. Akron OH Manchester Rd. Akron OH Tim Crawford Summit County Council 175 South Main Akron OH Paula Prentice Summit County Council 175 South Main Akron OH Alan Brubaker Summit County Engineer 538 E South St Akron OH Russell Pry Summit County Executive 175 S. Main St. 7th Floor Akron OH Dick Norton Summit Mayor City of Green Central Administration Building Al Bollas Summit Mayor City of New Franklin NEw Franklin Administration Building 1755 Town Park Blvd. PO Box 278 Green OH Manchester Rd. Akron OH Tony DeVitis Summit State Representative 77 South High Columbus OH Marilyn Slaby Summit State Representative 77 South High Columbus OH Tom Sawyer Summit State Senator 1 Captiol Square Columbus OH Sandra Kurt Summit Summit County Council-At-Large 175 S Main St 7th Floor Akron OH

64 NEXUS Project Public and Agency Participation Plan William Roemer Summit Summit County 176 S Main St 7th Floor Akron OH Council-At-Large Ilene Shapiro Summit Summit County Council-At-Large 177 S Main St 7th Floor Akron OH Tim Ryan Summit U.S. House of 1421 Longworth House Office Building Washington DC Representatives Jim Renacci Summit, Medina, U.S. House of 130 Cannon House Washington DC Wayne, Stark Representatives Office Building Frank LaRose Summit, Wayne State Senator 1 Captiol Square Columbus OH Lenny Broome Wayne Chippewa Township Mark Path OH Doylestown Roberta Gleason Wayne Chippewa Township Galehouse Rd Doylestown OH Robert Macgregor Wayne Chippewa Township Whitman Rd. OH Doylestown Patrick Herron Wayne County Administrator 428 West Liberty St Wooster OH Jim Carmichael Wayne County Commissioner 1429 Moore Rd. Wooster OH Ann Obrecht Wayne County Commissioner 7849 Columbus Rd. Shreve OH Scott Wiggam Wayne County Commissioner 316 E. Beverly Rd. Wooster OH Roger Terrill Wayne County Engineer 3151 West Old Wooster OH Lincoln Way Terry Lindeman Wayne Mayor City of 24 S. Portage St Doylestown OH Doylestown Ron Amstutz Wayne State Representative 77 South High Columbus OH Michael Sibbersen Wood Auditor One Courthouse 5th Floor Bowling OH Square Green Lisa Heft Wood Clerk, Village of 100 N Church St. PO Box 182 Haskins OH Haskins James Carter Wood Commissioner One Courthouse 5th Floor Bowling OH Square Green Dori Herringshaw Wood Commissioner One Courthouse 5th Floor Bowling OH Square Green Joel Kuhlman Wood Commissioner One Courthouse 5th Floor Bowling OH Square Green Helen Bonnough Wood Council, Village of 100 N Church St. PO Box 182 Haskins OH Haskins Ashley Pearl Brooks Wood Council, Village of 100 N Church St. PO Box 182 Haskins OH Haskins Nancy Perry Wood Council, Village of Haskins 100 N Church St. PO Box 182 Haskins OH

65 NEXUS Project Public and Agency Participation Plan Julienne Snyder Wood Council, Village of 100 N Church St. PO Box 182 Haskins OH Haskins Phillip Tipton Wood Council, Village of 100 N Church St. PO Box 182 Haskins OH Haskins Ray Huber Wood Engineer One Courthouse Bowling OH Square Green Raymond Huber Wood Engineer One Courthouse 5th Floor Bowling OH Square Green Paul Gies Wood Mayor, Village of 100 N Church St. PO Box 182 Haskins OH Haskins Jim Bostdorff Wood Middleton Township P.O. Box 206 Haskins OH Penny Getz Wood Middleton Township PO Box 206 Haskins OH Fred Vetter Wood Middleton Township P.O. Box 206 Haskins OH Julie Baumgardne Wood Recorder One Courthouse 5th Floor Bowling OH r Square Green Mark Wasylyshyn Wood Sheriff One Courthouse 5th Floor Bowling OH Square Green Jill Engle Wood Treasurer One Courthouse 5th Floor Bowling OH Square Green Matt Brinker Wood Troy Township P.O. Box Krotzer Ave. Luckey OH Stephen Levorchick Wood Troy Township P.O. Box Krotzer Ave. Luckey OH Steven Levorchik Wood Troy Township 5735 Oak St Stony Ridge OH Ken "Skip" Recker Wood Troy Township P.O. Box Krotzer Ave. Luckey OH Isaac Bailey Wood Webster Township 8138 Middleton Bowling OH Pike Green Mark Bushman Wood Webster Township 8138 Middleton Bowling OH Pike Green Jim Cajka Wood Webster Township 8138 Middleton Bowling OH Pike Green Tim Brown Wood State Representative 77 South High Columbus OH Bob Latta Wood, Lucas, Fulton U.S. House of Representatives 2448 Rayburn House Office Building Washington DC

66 NEXUS Project Public and Agency Participation Plan Community and Public Interest Groups and Non-governmental Organizations NEXUS Gas Transmission, LLC has identified numerous non-governmental organizations along the proposed pipeline route. We will be engaged with these groups as appropriate and will continue to supplement the list as contact is made. These groups may be associated with businesses, environmental resources or community groups and NEXUS engagement efforts will be coordinated with the Project subject matter experts. These groups include: State and local Chambers of Commerce Community members Labor associations Economic Development Authorities Educational Institutions Natures preservation organizations Local/regional environmental organizations River groups and partnerships 49

67 NEXUS Project Public and Agency Participation Plan Appendix F: Examples of Home Pages for Websites 50

68 NEXUS Project Public and Agency Participation Plan Appendix G: Sample Letters (page left intentionally blank) 51

69 NEXUS Project Public and Agency Participation Plan 52

70 NEXUS Project Public and Agency Participation Plan 53

71 NEXUS Project Public and Agency Participation Plan 54

72 NEXUS Project Public and Agency Participation Plan 55

73 NEXUS Project Public and Agency Participation Plan 56

74 NEXUS Project Public and Agency Participation Plan 57

75 NEXUS Project Public and Agency Participation Plan 58

76 NEXUS Project Public and Agency Participation Plan 59

77 NEXUS Project Public and Agency Participation Plan 60

78 NEXUS Project Public and Agency Participation Plan 61

79 NEXUS Project Public and Agency Participation Plan 62

80 NEXUS Project Public and Agency Participation Plan 63

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Elba Liquefaction Company, L.L.C. Southern LNG Company, L.L.C. Elba Express Company, L.L.C. Docket No. PF13-3-000 NOTICE OF INTENT TO PREPARE

More information

PLANNED ENHANCEMENTS, NORTHEAST NATURAL GAS PIPELINE SYSTEMS (as of 9-25-14)

PLANNED ENHANCEMENTS, NORTHEAST NATURAL GAS PIPELINE SYSTEMS (as of 9-25-14) PIPELINE SYSTEMS (as of 9-25-14) The Northeast Gas Association (NGA) has prepared this summary based on publicly-available information. NGA will strive to keep the information as updated as possible and

More information

OVERVIEW ABOUT WBI ENERGY

OVERVIEW ABOUT WBI ENERGY OVERVIEW The proposed Demicks Lake Pipeline Project involves approximately 22 miles of 24-inch diameter natural gas pipeline between a natural gas processing plant proposed by ONEOK Rockies Midstream (ONEOK)

More information

Comanche Trail Pipeline Project. September 2015

Comanche Trail Pipeline Project. September 2015 Comanche Trail Pipeline Project September 2015 2 Comanche Trail Pipeline Project The Comanche Trail Pipeline is a Texas intrastate pipeline (1) designed to transport 1.1 billion cubic feet per day of clean-burning

More information

PLANNED ENHANCEMENTS, NORTHEAST NATURAL GAS PIPELINE SYSTEMS (as of 7-24-15)

PLANNED ENHANCEMENTS, NORTHEAST NATURAL GAS PIPELINE SYSTEMS (as of 7-24-15) PIPELINE SYSTEMS (as of 7-24-15) The Northeast Gas Association (NGA) has prepared this summary based on publicly-available information. NGA will strive to keep the information as updated as possible and

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION PennEast Pipeline Company, LLC Docket No. PF15-1-000 NOTICE OF INTENT TO PREPARE AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PLANNED PENNEAST

More information

Northern Middlesex Council of Governments

Northern Middlesex Council of Governments Northern Middlesex Council of Governments The Federal Energy Commission (FERC) is the agency charged with evaluating whether the proposed route should be approved Cooperating agencies generally include

More information

Sabal Trail Transmission, LLC

Sabal Trail Transmission, LLC FGU 2014 ANNUAL MEETING JUNE 25, 2014 Sabal Trail Transmission, LLC Connecting diverse natural gas supplies to southeast markets Josh Browning Changing Natural Gas Flows Value of capacity increases with

More information

TEAM 2014 Project Texas Eastern Transmission, LP

TEAM 2014 Project Texas Eastern Transmission, LP TEAM 2014 Project Texas Eastern Transmission, LP FERC Section 7(b) and 7(c) Application and Public Exhibits, Except F-1 FERC Docket No. CP13- -000 Volume I PUBLIC February 2013 5400 Westheimer Court Houston,

More information

Effingham County Compressor Station and Meter Stations

Effingham County Compressor Station and Meter Stations FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C. 20426 OFFICE OF ENERGY PROJECTS In Reply Refer To: OEP/DG2E/Gas 2 Elba Liquefaction Company, L.L.C., Southern LNG Company, L.L.C., and Elba Express

More information

Minnesota Public Utilities Commission Staff Briefing Papers

Minnesota Public Utilities Commission Staff Briefing Papers Minnesota Public Utilities Commission Staff Briefing Papers Meeting Date: April 17, 2014...Agenda Item *3 Company: Docket No. Minnesota Power E015/GP-13-978 In the Matter of the Application of Minnesota

More information

Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426. Compliance Filing Docket No.

Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426. Compliance Filing Docket No. October 31, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 North Baja Pipeline, LLC 717 Texas Street, Suite 2400 Houston, TX 77002 John

More information

Natural Gas Summit 11/14/12

Natural Gas Summit 11/14/12 Natural Gas Summit 11/14/12 1 Natural Gas Summit 11/14/12 Maureen Ball Joined Central New York Oil and Gas (Inergy) in 1999. Participated in the development and construction of various storage, compression,

More information

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE 1 1 Welcome to The Eldorado-Ivanpah Transmission Project Open House How is the open house organized? This

More information

Access Northeast Project New England Energy Reliability Solution

Access Northeast Project New England Energy Reliability Solution Access Northeast Project New England Energy Reliability Solution Open Season Notice for Firm Service February 18, 2015 May 1, 2015 Access Northeast Project New England Energy Reliability Solution Eversource

More information

S Y S T E M M O D E R N I Z A T I O N

S Y S T E M M O D E R N I Z A T I O N S Y S T E M M O D E R N I Z A T I O N T H E L I N E M B E X T E N S I O N P R O J E C T B A L T I M O R E A N D H A R F O R D C O U N T I E S, M A R Y L A N D Project Overview Columbia Gas Transmission

More information

CHICAGO MARKET EXPANSION PROJECT PHASE 2 NOTICE OF NON-BINDING SOLICITATION OF INTEREST CMEP PHASE 1 UPDATE

CHICAGO MARKET EXPANSION PROJECT PHASE 2 NOTICE OF NON-BINDING SOLICITATION OF INTEREST CMEP PHASE 1 UPDATE CMEP PHASE 1 UPDATE Natural Gas Pipeline Company of America LLC (NGPL) is pleased to announce its acceptance of the FERC Certificate Order issued March 17, 2016 in Docket No. CP15-505-000, as filed June

More information

March 25, 2015. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426

March 25, 2015. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 March 25, 2015 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Tuscarora Gas Transmission Company 700 Louisiana Street, Suite 700 Houston,

More information

Highlights of Testimony

Highlights of Testimony The following is a summary of a written statement submitted by Alex Paris of Alex E. Paris Contracting, Inc. on behalf of the Distribution Contractors Association (DCA) before the House Committee on Energy

More information

Pipeline Engineering and Field Services

Pipeline Engineering and Field Services Pipeline Engineering and Field Services Field Services Professionals Your Reliable Partner Mustang s Pipeline Field Services Group is recognized by the industry as a reliable partner for providing a complete

More information

APPENDIX K NATURAL GAS PIPELINE STORAGE PERMITTING PROCESSES

APPENDIX K NATURAL GAS PIPELINE STORAGE PERMITTING PROCESSES APPENDIX K NATURAL GAS PIPELINE & STORAGE PERMITTING PROCESSES Natural Gas Pipeline & Storage Permitting Processes NiSource follows the Federal Energy Regulatory Commission (FERC) planning and permitting

More information

Millennium Pipeline Company, LLC Response to New York State Energy Highway RFI

Millennium Pipeline Company, LLC Response to New York State Energy Highway RFI Millennium Pipeline Company, LLC Response to New York State Energy Highway RFI www.millenniumpipeline.com One Blue Hill Plaza, 7th Floor Post Office Box 1565 Pearl River, N Y 10965 845.620.1300 Voice 845.620.1320

More information

NEW HAMPSHIRE PIPELINE INSTALLATION

NEW HAMPSHIRE PIPELINE INSTALLATION NORTHEAST ENERGY DIRECT NEW HAMPSHIRE PIPELINE INSTALLATION Benefits to New Hampshire January 2015 Overview of Proposed New Hampshire Facilities The proposed Northeast Energy Direct Pipeline (NED) routed

More information

GAO PIPELINE PERMITTING. Interstate and Intrastate Natural Gas Permitting Processes Include Multiple Steps, and Time Frames Vary

GAO PIPELINE PERMITTING. Interstate and Intrastate Natural Gas Permitting Processes Include Multiple Steps, and Time Frames Vary GAO United States Government Accountability Office Report to Congressional Committees February 2013 PIPELINE PERMITTING Interstate and Intrastate Natural Gas Permitting Processes Include Multiple Steps,

More information

Standardized Environmental Survey Protocols

Standardized Environmental Survey Protocols 14 Best Practices for Sustainable Wind Energy Development in the Great Lakes Region Great Lakes Wind Collaborative Best Practice #14 Standard environmental survey protocols should be developed by federal

More information

hereby submits for filing a report of its Operational Purchases and Sales for the thirteen-month period ending December 31, 2011.

hereby submits for filing a report of its Operational Purchases and Sales for the thirteen-month period ending December 31, 2011. April 26, 2012 Ms. Kimberly D. Bose Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Bison Pipeline LLC 717 Texas Street, Suite 2400 Houston, TX 77002 tel 832.320.5675

More information

MIAMI TOWNSHIP, MONTGOMERY COUNTY, OHIO AMENDED REQUEST FOR PROPOSALS FOR OUTSIDE LEGAL COUNSEL

MIAMI TOWNSHIP, MONTGOMERY COUNTY, OHIO AMENDED REQUEST FOR PROPOSALS FOR OUTSIDE LEGAL COUNSEL SUMMARY MIAMI TOWNSHIP, MONTGOMERY COUNTY, OHIO AMENDED REQUEST FOR PROPOSALS FOR OUTSIDE LEGAL COUNSEL The Miami Township Board of Trustees has amended their initial request for proposals from private

More information

National Standards for Disability Services. DSS 1504.02.15 Version 0.1. December 2013

National Standards for Disability Services. DSS 1504.02.15 Version 0.1. December 2013 National Standards for Disability Services DSS 1504.02.15 Version 0.1. December 2013 National Standards for Disability Services Copyright statement All material is provided under a Creative Commons Attribution-NonCommercial-

More information

Version Part Section Description 0.0.0 II 13.27 Summary of Negotiated Rate Agreement

Version Part Section Description 0.0.0 II 13.27 Summary of Negotiated Rate Agreement Transcontinental Gas Pipe Line Company, LLC 2800 Post Oak Boulevard (77056) P.O. Box 1396 Houston, Texas 77251-1396 (713) 215-2000 Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

The Suggested Best Practices for Industry Outreach Programs to Stakeholders is a staff product and does not necessarily reflect the views of the

The Suggested Best Practices for Industry Outreach Programs to Stakeholders is a staff product and does not necessarily reflect the views of the The Suggested Best Practices for Industry Outreach Programs to Stakeholders is a staff product and does not necessarily reflect the views of the Commission or any Commissioner. All images are property

More information

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PIPELINE ROUTING PERMIT For A NATURAL GAS PIPELINE IN DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PUC DOCKET No. G002/GP-05-1706 In accordance with the requirements

More information

Mailing Address: P.O. Box 1642 Houston, TX 77251-1642. July 27, 2015

Mailing Address: P.O. Box 1642 Houston, TX 77251-1642. July 27, 2015 5400 Westheimer Court Houston, TX 77056-5310 713.627.5400 main Mailing Address: P.O. Box 1642 Houston, TX 77251-1642 July 27, 2015 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888

More information

THE LOCAL ROLE IN PERMITTING INTERSTATE NATURAL GAS PIPELINES MASSACHUSETTS ASSOCIATION OF CONSERVATION COMMISSIONS

THE LOCAL ROLE IN PERMITTING INTERSTATE NATURAL GAS PIPELINES MASSACHUSETTS ASSOCIATION OF CONSERVATION COMMISSIONS THE LOCAL ROLE IN PERMITTING INTERSTATE NATURAL GAS PIPELINES PRESENTATION AT CITIZEN PLANNER TRAINING COLLABORATIVE CONFERENC E BY EUGENE B. BENSON, EXECUTIVE DIRECTOR, MACC MARCH 21, 2015 Massachusetts

More information

F i r s t N a t i o n a n d M é t i s Consultation Policy Framework. June 2010

F i r s t N a t i o n a n d M é t i s Consultation Policy Framework. June 2010 F i r s t N a t i o n a n d M é t i s Consultation Policy Framework June 2010 Table of Contents 1. Introduction.... 2 2. Duty to Consult Policy................................................. 3 1. Policy

More information

Pendleton Solar Energy Centre COMMUNITY ENGAGEMENT PLAN

Pendleton Solar Energy Centre COMMUNITY ENGAGEMENT PLAN Pendleton Solar Energy Centre COMMUNITY ENGAGEMENT PLAN Large Renewable Procurement (LRP) I PENDLETON SOLAR ENERGY CENTRE 844.553-3336 PendletonSolar@edf-en.ca www.pendletonsolar.ca Table of Contents 1.

More information

Re: Preliminary Permit Application for the Rose Creek Pumped Storage Project

Re: Preliminary Permit Application for the Rose Creek Pumped Storage Project September 12, 2013 Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Preliminary Permit Application for the Dear Ms. Bose, Please find attached

More information

Catalog of Domestic Assistance Number: 66.462 Announcement Date: February 23, 2005 Submission Date: Must be postmarked by April 20, 2005.

Catalog of Domestic Assistance Number: 66.462 Announcement Date: February 23, 2005 Submission Date: Must be postmarked by April 20, 2005. Federal Agency Name: US Environmental Protection Agency Funding Opportunity Title: National Wetland Program Development Grants Announcement Number: HQWPDGFY05 Announcement Type: Initial Request for Proposals

More information

January 14, 2011. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 14, 2011. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. January 14, 2011 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Northern Border Pipeline Company 717 Texas Street, Suite 2400 Houston,

More information

Appendix G Process For Protection of Proposal Information For

Appendix G Process For Protection of Proposal Information For Process For Protection of Proposal Information For 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Louisiana, LLC DRAFT Entergy Services, Inc. March 24June 8, 2016 APPENDIX

More information

Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way

Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way Public Works Department Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way October 2015 HillsboroughCounty.org HILLSBOROUGH COUNTY Office of the County

More information

Regional Gas Market Update

Regional Gas Market Update April 22, 2015 Milford, MA Regional Gas Market Update Presentation to: ISO-NE Planning Advisory Committee Tom Kiley Northeast Gas Association Objective NGA S ANTITRUST COMPLIANCE PROCEDURES Adopted by

More information

FERC NGA GAS TARIFF. Fifth Revised Volume No. 1. (Supersedes Fourth Revised Volume No. 1) TRANSWESTERN PIPELINE COMPANY, LLC.

FERC NGA GAS TARIFF. Fifth Revised Volume No. 1. (Supersedes Fourth Revised Volume No. 1) TRANSWESTERN PIPELINE COMPANY, LLC. FERC NGA GAS TARIFF Fifth Revised Volume No. 1 (Supersedes Fourth Revised Volume No. 1) Of TRANSWESTERN PIPELINE COMPANY, LLC Filed with the FEDERAL ENERGY REGULATORY COMMISSION Communications concerning

More information

STATEMENT OF NATURE, REASONS AND BASIS

STATEMENT OF NATURE, REASONS AND BASIS March 27, 2015 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Dear Ms. Bose: Re: Docket No. RP15- Compliance with Order No. 801 on Pipeline

More information

Airspace Change Communications and Consultation Protocol Protocol

Airspace Change Communications and Consultation Protocol Protocol Airspace Change Communications and Consultation Protocol Protocol A voluntary protocol of the aviation industry June 2015 Preface The primary duty of the aviation industry in Canada is to ensure the safety

More information

September 29, 2014. Docket No. ER14- -000 Amendment to CAISO FERC Electric Tariff to Eliminate Annual External Operations Review

September 29, 2014. Docket No. ER14- -000 Amendment to CAISO FERC Electric Tariff to Eliminate Annual External Operations Review California Independent System Operator Corporation September 29, 2014 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

Structuring Oil and Gas Pipeline Projects: Key Issues and Key Contracts Involved

Structuring Oil and Gas Pipeline Projects: Key Issues and Key Contracts Involved Structuring Oil and Gas Pipeline Projects: Key Issues and Key Contracts Involved International Law Institute International Oil & Gas Development June 11-22, 2012 June 20, 2012 Vince Murchison Partner T

More information

Self Assessment Tool for Principals and Vice-Principals

Self Assessment Tool for Principals and Vice-Principals The Institute for Education Leadership (IEL) brings together representatives from the principals' associations, the supervisory officers' associations, councils of directors of education and the Ministry

More information

The 2016 Business Plan and Budget Process

The 2016 Business Plan and Budget Process Recommendation That the Executive Committee recommend to City Council that it: 1. Reaffirm Council s four-year priorities listed in Attachment 1; 2. Approve the proposed performance measures listed in

More information

133 FERC 61,057 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER AMENDING CERTIFICATE. (Issued October 21, 2010)

133 FERC 61,057 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER AMENDING CERTIFICATE. (Issued October 21, 2010) 133 FERC 61,057 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, John R. Norris, and Cheryl A. LaFleur. Southern

More information

STRATEGIC PLAN September 2011

STRATEGIC PLAN September 2011 STRATEGIC PLAN September EXECUTIVE SUMMARY The Santa Barbara County Association of Governments (SBCAG) plays a unique role throughout the region of Santa Barbara County. It was formed to provide a forum

More information

February 23, 2015. Ms. Larine A. Moore Docket Room Manager U.S. Department of Energy FE-34 PO Box 44375 Washington, D.C.

February 23, 2015. Ms. Larine A. Moore Docket Room Manager U.S. Department of Energy FE-34 PO Box 44375 Washington, D.C. February 23, 2015 By Email and Federal Express fergas@hq.doe.gov Ms. Larine A. Moore Docket Room Manager U.S. Department of Energy FE-34 PO Box 44375 Washington, D.C. 20026-4375 Re: Application of Floridian

More information

BPA Policy 482-1 Contract Lifecycle Management

BPA Policy 482-1 Contract Lifecycle Management B O N N E V I L L E P O W E R A D M I N I S T R A T I O N -1 Contract Lifecycle Management Customer Contracting Table of Contents 482-1.1 Purpose & Background... 2 482-1.2 Policy Owner... 2 482-1.3 Applicability...

More information

Multiple Species Conservation Program County of San Diego. A Case Study in Environmental Planning & The Economic Value of Open Space

Multiple Species Conservation Program County of San Diego. A Case Study in Environmental Planning & The Economic Value of Open Space Multiple Species Conservation Program County of San Diego A Case Study in Environmental Planning & The Economic Value of Open Space Amy M. Fox Land Use Law Case Study Autumn Semester, 1999 Multiple Species

More information

Frequently Asked Questions About PennEast Pipeline Project

Frequently Asked Questions About PennEast Pipeline Project Frequently Asked Questions About PennEast Pipeline Project Who is PennEast Pipeline Company, LLC? AGL Resources, NJR Pipeline Company, South Jersey Industries, PSEG Power LLC and UGI Energy Services (UGIES)

More information

154 FERC 61,032 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ISSUING CERTIFICATE. (Issued January 21, 2016)

154 FERC 61,032 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ISSUING CERTIFICATE. (Issued January 21, 2016) 154 FERC 61,032 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. Texas Gas Transmission,

More information

IT Standards & Contract Management

IT Standards & Contract Management Appendix F IT Standards & Table of Contents Vision of Action... 2 Background... 3 Goals and Objectives... 4 Projects... 5 Metrics and Measures... 6 F IT Standards & Carol Steffanni Director, MDIT Bureau

More information

"Project" Permitting Specialist III Location Hadley Road - South Plainfield NJ (0010) Job Function Project Management.

Project Permitting Specialist III Location Hadley Road - South Plainfield NJ (0010) Job Function Project Management. Req# 16715BR Title "Project" Permitting Specialist III Location Hadley Road - South Plainfield NJ (0010) Job Function Project Management Job Description This is a Project Position This is a "Project" function

More information

PUBLIC NOTICE Application for Permit

PUBLIC NOTICE Application for Permit PUBLIC NOTICE Application for Permit 30-Day Notice Issue Date: June 20, 2016 Expiration Date: July 20, 2016 US Army Corps of Engineers No: NWP-2010-535 Oregon Department of State Lands No: 58311-RF Interested

More information

CHAPTER 8. FEDERALLY-LISTED ENDANGERED OR THREATENED SPECIES

CHAPTER 8. FEDERALLY-LISTED ENDANGERED OR THREATENED SPECIES 1. INTRODUCTION AND DEFINITIONS. CHAPTER 8. FEDERALLY-LISTED ENDANGERED OR THREATENED SPECIES a. General. The Biotic Resources chapter in Appendix A of Order 1050.1E combines information on Federally-listed

More information

Peninsular Florida Landscape Conservation Cooperative. Charter. Background

Peninsular Florida Landscape Conservation Cooperative. Charter. Background Charter Background The Peninsular Florida Landscape Conservation Cooperative (Conservation Cooperative) is part of a national network of Landscape Conservation Cooperatives (LCCs). LCCs are applied conservation

More information

Request for Proposals For Financial Advisor Services

Request for Proposals For Financial Advisor Services Request for Proposals For Financial Advisor Services Finance Department Contents Section I Introduction 2 Section II Description of Village 2 Section III Debt Financing Plans 3 Section IV Scope of Services

More information

Arlington Storage Company, LLC, Docket No. CP13-83-000 Submission of Implementation Plan and Request for Clearance to Commence Construction

Arlington Storage Company, LLC, Docket No. CP13-83-000 Submission of Implementation Plan and Request for Clearance to Commence Construction August 12, 2014 VIA ELECTRONIC FILING Ms. Kimberly Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re:, Docket No. Submission of Implementation Plan and Request

More information

Understanding Natural Gas Pipeline Infrastructure and Impacts DAVE MESSERSMITH MARCELLUS EDUCATION TEAM

Understanding Natural Gas Pipeline Infrastructure and Impacts DAVE MESSERSMITH MARCELLUS EDUCATION TEAM Understanding Natural Gas Pipeline Infrastructure and Impacts DAVE MESSERSMITH MARCELLUS EDUCATION TEAM Pipeline Infrastructure & Impacts Pipeline Background Pipeline Construction Pipeline-Related Infrastructure

More information

State Comprehensive Wildlife Conservation Support Program Application for Funds

State Comprehensive Wildlife Conservation Support Program Application for Funds State Comprehensive Wildlife Conservation Support Program Application for Funds I. APPLICANT INFORMATION Organization (intended recipient): Northeast Association of Fish & Wildlife Agencies Street: c/o

More information

LEACH XPRESS. Leach XPress Rayne XPress. Non Binding Open Seasons

LEACH XPRESS. Leach XPress Rayne XPress. Non Binding Open Seasons LEACH XPRESS Leach XPress Rayne XPress Non Binding Open Seasons Columbia Pipeline Group is pleased to announce another innovative solution that will allow the growing Marcellus and Utica shale production

More information

145 FERC 61,172 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

145 FERC 61,172 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 145 FERC 61,172 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Cheryl A. LaFleur, Acting Chairman; Philip D. Moeller, John R. Norris, and Tony Clark. California Independent

More information

Florida Gas Transmission Company, LLC Docket No. RP14- -000

Florida Gas Transmission Company, LLC Docket No. RP14- -000 April 30, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 RE: Florida Gas Transmission Company, LLC Docket No. RP14- -000 Dear Ms.

More information

145 FERC 61,112 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

145 FERC 61,112 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 145 FERC 61,112 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Philip D. Moeller, John R. Norris, Cheryl A. LaFleur, and Tony Clark. NET

More information

Los Angeles Department of Water and Power

Los Angeles Department of Water and Power Los Angeles Department of Water and Power now accepting applications for General Manager THE CITY OF LOS ANGELES The City of Los Angeles is the second largest City in the United States and has a multiethnic

More information

Frequently Asked Transmission Pipeline Questions

Frequently Asked Transmission Pipeline Questions Frequently Asked Transmission Pipeline Questions Who is PennEast, LLC? PennEast was formed by the partnership of AGL Resources, NJR Pipeline Company, South Jersey Industries and UGI Energy Services (UGIES).

More information

REQUEST FOR PROPOSALS VOLUNTEER SECURITY VETTING SERVICES

REQUEST FOR PROPOSALS VOLUNTEER SECURITY VETTING SERVICES REQUEST FOR PROPOSALS VOLUNTEER SECURITY VETTING SERVICES 2016 Democratic National Convention Committee 430 South Capitol Street, SE Washington, DC 20003 202.863.8000 Philadelphia 2016 Host Committee 1900

More information

National Environmental Policy Act/ Clean Water Act Section 404 (NEPA/404) Merger Process and Agreement for Transportation Projects in Colorado

National Environmental Policy Act/ Clean Water Act Section 404 (NEPA/404) Merger Process and Agreement for Transportation Projects in Colorado Background In a May 12, 2003, letter from Mr. James L. Connaughton, Executive Office of the President, Council on Environmental Quality, to Mr. Norman Y. Minneta, Secretary of Transportation, Mr. Connaughton

More information

REQUEST FOR PROPOSAL GlobalPittsburgh Website February 11, 2015. 1. Summary and Background

REQUEST FOR PROPOSAL GlobalPittsburgh Website February 11, 2015. 1. Summary and Background REQUEST FOR PROPOSAL GlobalPittsburgh Website February 11, 2015 1. Summary and Background The Pittsburgh Council for International Visitors (PCIV), a non profit organization doing business as GlobalPittsburgh,

More information

Williams is in the preliminary

Williams is in the preliminary Hillabee Expansion Project www.williams.com/hillabee Winter 2013 2014 Public Feedback Sought for Proposed Williams Pipeline Expansion Williams is in the preliminary stages of developing a multiphased pipeline

More information

Lake Charles Expansion Project

Lake Charles Expansion Project Lake Charles Expansion Project Resource Report 11 Reliability and Safety Docket No. CP14- - Public Kinder Morgan Louisiana Pipeline LLC 1001 Louisiana Street, Suite 1000 Houston, Texas 77002 June 2014

More information

Land Protection Planning for the National Wildlife Refuge System

Land Protection Planning for the National Wildlife Refuge System March 2012 Planning Information Brochure 1 Land Protection Planning for the National Wildlife Refuge System The following questions are often asked when the U.S. Fish and Wildlife Service (Service) begins

More information

ALASKA NATURAL GAS PIPELINE PROJECT

ALASKA NATURAL GAS PIPELINE PROJECT ALASKA NATURAL GAS PIPELINE PROJECT Testimony on AGIA of W. H. Sparger House Resources Committee May 11, 2007 EPC Energy Project Consultants, LLC Introduction William H. (Bill) Sparger Energy Project Consultants.

More information

Amendments to the Rules of Practice and Procedure to Allow Each Signatory Party and the

Amendments to the Rules of Practice and Procedure to Allow Each Signatory Party and the This document is scheduled to be published in the Federal Register on 02/03/2016 and available online at http://federalregister.gov/a/2016-02048, and on FDsys.gov 6301-01-P DELAWARE RIVER BASIN COMMISSION

More information

May 27, 2014. Version 12.0.0

May 27, 2014. Version 12.0.0 5151 San Felipe, Suite 2400 Houston, Texas 77056 Phone: 713-386-3759 Fax: 713-386-3755 jdowns@nisource.com Jim Downs Vice President of Rates & Regulatory Affairs May 27, 2014 Ms. Kimberly D. Bose Federal

More information

Building Interstate Natural Gas Transmission Pipelines: A Primer

Building Interstate Natural Gas Transmission Pipelines: A Primer Building Interstate Natural Gas Transmission Pipelines: A Primer INGAA FOUNDATION REPORT 2013.01 January 2013 The INGAA Foundation Inc. 20 F Street NW Suite 450 Washington, DC 20001 INGAA Foundation Ad-Hoc

More information

How To Write A Listing Policy For A Species At Risk Act

How To Write A Listing Policy For A Species At Risk Act Fisheries and Oceans Canada Species at Risk Act Listing Policy and Directive for Do Not List Advice DFO SARA Listing Policy Preamble The Fisheries and Oceans Canada (DFO) Species at Risk Act (SARA) Listing

More information

141 FERC 61,117 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

141 FERC 61,117 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 141 FERC 61,117 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Philip D. Moeller, John R. Norris, Cheryl A. LaFleur, and Tony T. Clark. Wyoming

More information

Appendix U. Environmental Compliance Monitoring Plan

Appendix U. Environmental Compliance Monitoring Plan RUBY PIPELINE PROJECT PLAN OF DEVELOPMENT Appendix U. Environmental Compliance Monitoring Plan U-1 June 2010 Environmental Compliance Monitoring Plan Ruby Pipeline Project May 2010 Table of Contents

More information

Negotiating Pipeline Easements

Negotiating Pipeline Easements FACT SHEET Ohio State University Extension, 2120 Fyffe Road, Columbus, OH 43210 Introduction Shale Oil and Gas Development Fact Sheet Series Negotiating Pipeline Easements Peggy Kirk Hall Director, OSU

More information

Risk Management in the Development of a Penta-P Project

Risk Management in the Development of a Penta-P Project Risk Management in the Development of a Penta-P Project Bill Van Meter Regional Transportation District Denver, CO Julie Skeen Jacobs Engineering Denver, CO Damian Carey Jacobs Engineering Denver, CO Don

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Rock Island Clean Line LLC ) Docket No. ER12-365-000

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Rock Island Clean Line LLC ) Docket No. ER12-365-000 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Rock Island Clean Line LLC ) Docket No. ER12-365-000 ROCK ISLAND CLEAN LINE LLC S ANSWER TO COMMENTS OF INTERSTATE POWER AND LIGHT

More information

8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP

8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP 8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP 8.1 INTRODUCTION Mitigation measures, monitoring and other follow-up actions identified in Chapter 7 (Environmental Effects Assessment and Mitigation)

More information

146 FERC 61,195 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

146 FERC 61,195 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 146 FERC 61,195 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Cheryl A. LaFleur, Acting Chairman; Philip D. Moeller, John R. Norris, and Tony Clark. Houston Pipe Line

More information

National Marine Sanctuaries Act

National Marine Sanctuaries Act Please note: This text is from the fourth edition of Federal Historic Preservation Laws, published in 2006 by the National Center for Cultural Resources, National Park Service, Department of the Interior.

More information

TENNESSEE GAS PIPELINE COMPANY 300 LINE PROJECT Vernon, West Milford Townships and Ringwood Borough, New Jersey

TENNESSEE GAS PIPELINE COMPANY 300 LINE PROJECT Vernon, West Milford Townships and Ringwood Borough, New Jersey Prepared for: Houston, TX COMPREHENSIVE MITIGATION PLAN HIGHLANDS REGION TENNESSEE GAS PIPELINE COMPANY 300 LINE PROJECT Vernon, West Milford Townships and Ringwood Borough, New Jersey AECOM, Inc. September

More information

S T A T E O F M I C H I G A N BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION * * * * *

S T A T E O F M I C H I G A N BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION * * * * * S T A T E O F M I C H I G A N BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION * * * * * In the matter of the application of ) LIBERTY POWER DELAWARE, LLC, ) Case No. for a license as an alternative electric

More information

Final NPS Alternative Transportation Program Strategic Action Plan, 2012 2016

Final NPS Alternative Transportation Program Strategic Action Plan, 2012 2016 Final NPS Alternative Transportation Program Strategic Action Plan, 2012 2016 FY 2012 Executive summary This plan is an action oriented, performance based update to the 2002 2006 Alternative Transportation

More information

CALIFORNIA OCEAN PROTECTION COUNCIL. Staff Recommendation March 11, 2011 STATEWIDE SCIENCE INTEGRATION AND MARINE PROTECTED AREA MONITORING PROGRAMS

CALIFORNIA OCEAN PROTECTION COUNCIL. Staff Recommendation March 11, 2011 STATEWIDE SCIENCE INTEGRATION AND MARINE PROTECTED AREA MONITORING PROGRAMS CALIFORNIA OCEAN PROTECTION COUNCIL Staff Recommendation March 11, 2011 STATEWIDE SCIENCE INTEGRATION AND MARINE PROTECTED AREA MONITORING PROGRAMS File No.: 08-123-02 File No.: 06-090-02 Project Managers:

More information

Transcontinental Gas Pipe Line Company, LLC Flow Through of Dominion Transmission, Inc. Penalty Sharing

Transcontinental Gas Pipe Line Company, LLC Flow Through of Dominion Transmission, Inc. Penalty Sharing Gas Pipeline Transco 2800 Post Oak Boulevard (77056) Houston, Texas 77251-1396 713/215-4060 August 7, 2014 Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Attention:

More information

Trunkline Gas Company, LLC Docket No. RP12- -000

Trunkline Gas Company, LLC Docket No. RP12- -000 October 7, 2011 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E., Room 1A Washington, D.C. 20426 Re: Trunkline Gas Company, LLC Docket No. RP12- -000 Dear Ms.

More information

PIPELINE FUNDAMENTALS. texaspipelines.com

PIPELINE FUNDAMENTALS. texaspipelines.com PIPELINE FUNDAMENTALS texaspipelines.com Texas Oil & Gas: Generating $2.6 Billion for State Revenues texaspipelines.com Texas Oil & Gas Texas produces 20% of US Domestic Oil Production 1.1 Million Barrels

More information

Office of Inspector General

Office of Inspector General United States Department of State and the Broadcasting Board of Governors Office of Inspector General Office of Inspector General Office of Audits Special Review of the Keystone XL Pipeline Permit Process

More information

APPENDIX B. Agency Correspondence

APPENDIX B. Agency Correspondence APPENDIX B Agency Correspondence Connecticut State Historic Preservation Office INTEGRATED HISTORIC PRESERVATION PLANNING June 29, 2012 Ms. Amanda Mayhew Northeast Utilities Service Company 107 Selden

More information

146 FERC 61,166 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

146 FERC 61,166 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 146 FERC 61,166 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Cheryl A. LaFleur, Acting Chairman; Philip D. Moeller, John R. Norris, and Tony Clark. Reliability Standards

More information

Flow Through of Dominion Transmission, Inc. Penalty Sharing

Flow Through of Dominion Transmission, Inc. Penalty Sharing Transcontinental Gas Pipe Line Company, LLC 2800 Post Oak Boulevard (77056) Houston, Texas 77251-1396 713/215-2000 August 3, 2015 Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information