BELT FILTER PRESS PRODUCES SIMILAR PERFORMANCE TO CENTRIFUGATION: SIDE-BY-SIDE DEWATERING RESULTS FROM THREE ANAEROBIC DIGESTED BIOSOLIDS
|
|
- Stewart Hamilton
- 7 years ago
- Views:
Transcription
1 BELT FILTER PRESS PRODUCES SIMILAR PERFORMANCE TO CENTRIFUGATION: SIDE-BY-SIDE DEWATERING RESULTS FROM THREE ANAEROBIC DIGESTED BIOSOLIDS Mohammad Abu-Orf 1, Peter Nese 2, William Suchodolski 3 1 Biosolids Technology Leader, Metcalf and Eddy/AECOM, 1700 Market Street, Suite 1700, Philadelphia, PA ( mohammad.abu-orf@m-e.aecom.com) 2 CH2MHILL, at the time of conducting this project, Mr. Nese was the Project Manager for OCUA 3 Engineering Manager, Ocean County Utilities Authority, Bayville, NJ ABSTRACT The recent Biosolids Management Plant conducted by the Ocean County Utilities Authority (OCUA) recommended side-by-side pilot testing of belt filter press and centrifuge technology to select the best technology to dewater their anaerobically digested biosolids from the authority three plants. Initially, screening of available vendors for providing dewatering technologies and conducting the side-by-side piloting were conducted and two vendors were selected: 0.6 meter Wiklepress of Ashbrook and skid mounted ALDEC 406 centrifuge of Alfa Laval. A detailed pilot testing protocol for both technologies and guidance support documents including all necessary support from both vendors and the OCUA staff to achieve successful testing were finalized prior to conducting the testing. The testing protocol called for one week testing at each plant. The testing protocol was consistent for all plants. Side-by-side testing commenced on May 7 th and ended on May 25 th, The performance of each technology was measured through achieving consistent cake solids at the end of testing at each facility with a certain polymer dose and percent solids recovery higher than 95%. Based on the obtained cake solids with the used polymer dose, and the electricity consumed for dewatering during the consistent performance testing, the operating costs for each technology were estimated. The testing showed that the belt filter press technology produced similar performance to the centrifuge at all three plants and in some cases using lower polymer doses to achieve the same cake dryness. Based on estimated operating costs, BFP technology was recommended to dewatering biosolids at all three facilities. KEYWORDS Dewatering, pilot testing, Belt filter press, high solids, centrifuge 527
2 INTRODUCTION The Ocean County Utilities Authority (OCUA) operates three different wastewater treatment facilities ranging in size from 20 million gallons a day (MGD) to 32 MGD: The Northern, Central, and Southern Water Pollution Control Facilities (WPCF). The three plants combined produce approximately 9,000 dry tons per year of biosolids. The biosolids at Northern and Southern facilities are anaerobically digested, thickened and hauled to the Central WPCF where it is blended with their thickened anaerobically digested biosolids, dewatered and dried using Andritz rotary drum dryers to produce a pellet known as OCEANGRO. Dewatering the blended thickened biosolids at the CWPCF is done via three, 2-m Andritz belt filter presses with one press as a stand-by and achieves an average of 16% cake solids. The OCUA conducted biosolids master planning to evaluate the long term viability of the existing solids handling processes at the three treatment plants and evaluate future alternative for biosolids management. Results from the master planning indicate that modifications to the existing solids handling practices will be required to accommodate future growth. The Authority decided on a phased approach for implementing required expansions and upgrades in order to reduce capital and operating costs. The OCUA realizes the benefits form improved dewatering at the CWPCF and implementation of dewatering at the NWPCF and SWPCF to decrease operating cost and increase drying capacity. Based on the existing drying system capacity, it was determined that an averaged 21% cake solids must be achieved in order to avoid constructing a third dryer train. Details regarding this study are available in Laustsen et al. (2007). OCUA decided to conduct side-by-side pilot testing of both belt filter presses and centrifuge dewatering at all three plants. Based on the results of the pilot testing, the authority would select the dewatering technology to achieve cake solids grater than 21%, and determine the corresponding operating costs. Metcalf and Eddy, Inc/AECOM was selected for conducting the side-by-side pilot dewatering studies. In this study, the performance and operating costs of belt filter press and centrifuge technology was evaluated at the three treatment plants. This paper presents tasks conducted to successfully complete the side-by-side pilot dewatering including equipment selection, testing protocol, site visits and support needed from the vendor, and the authority personnel. This paper also presents the performance of BFP and centrifuge technology in terms of cake solids and solids recovery with polymer consumption. The operating costs for each technology, including polymer usage, estimated costs from producing cake solids, and energy usage at the three treatment plant are also presented in this paper. Finally, based on these results, a recommendation as to the type of technology to be implemented at each site is presented. EVALUATION OF DEWATERING TECHNOLOGY After review of available providers for centrifuges and BFP, three BFPs and three of centrifuge manufacturers were selected for detailed evaluation. The criteria for evaluation was agreed upon with OCUA before conducting the evaluation, and included: Existing installations for each dewatering equipment 528
3 Market reputability and quality of equipment Ability to provide equipment for piloting, piloting experience, and anticipated cost of piloting Equipment and support provided during piloting Amenability to conduct side-by-side testing within the established timeframe for project completion For BFP equipment, amenability to pilot test enzyme pretreatment The three centrifuge manufacturers evaluated include Andritz, Alfa Laval, and Westfalia. The three BFP manufacturer evaluated include Andritz, Siemens, and Ashbrook. Based on the evaluation criteria and availability of vendors for piloting, Alfa Laval skid mounted ALDEC 406 was selected for centrifuge piloting and the trailer mounted 0.6 m Winklepress of Ashbrook was selected for BFP piloting. DESCRIPTION OF THE PILOT TESTING PROTOCOL A well designed protocol is vital to obtaining information necessary for the equipment selection process and for future design of the selected dewatering equipment for each facility. This task was closely coordinated with the appointed personnel from each of the three WPCFs. Site visitations and meeting with appropriate persons from each site to establish the protocol were conducted. Since conditions and option may be unique to each facility, a separate testing protocol for each facility was provided. Separate protocols for BFP and centrifuge testing due to differences in operation parameters were also provided. Each vendor provided their own operating personnel and operations were monitored and supervised order to adhere to the agreed upon testing protocol. The sections below describe the main elements of the testing protocol. Side-by-side testing was performed at the three plants of OCUA over three consecutive weeks (one week per plant). The testing protocol called for one week testing at each plant starting from the Southern WPCF, moving to the Central WPCF and ending with the Northern WPCF. The testing protocol was consistent for all plants. All samples during testing were collected by the consultant staff, and laboratory analyses were conducted by OCUA internal laboratory personnel. Testing commenced on May 7 th and ended on May 25 th, Performance of both technologies was measured as the % solids cake produced from the plant s anaerobically digested biosolids. Percent cake solids content was measured against operating factors, including: Specific loading rate (lb solids per hour) and in the BFP case lbs per hour per meter width of the belt. Usually cake solids increase with lower loading rates, however, this requires higher capital investment for purchasing more equipment. Percent solids recovery (%TSS), which should be greater than 95%, it is well documented that solids recovery can be sacrificed to obtain higher cake solids. Polymer dose in lb active content/dry ton (DT). 529
4 Energy consumption (kw-h/dt solids) was measured for cost comparison. Other comparative information such as the ease of bringing up the equipment to a steady state after an operational parameter change or equipment upset, and required operator s attention was also recorded. Polymer Selection Polymer selection for each plant was the responsibility of the vendor. The vendor was responsible for providing the entire polymer required for the duration of the testing. Cost alone was not the determining factor for polymer selection. Alfa Laval opted to use a representative of PolyDyne for on-site jar testing for polymer selection for each plant s biosolids. At Ashbrook s request, OCUA sampled biosolids from each plant as it leaves the secondary digester to be tested for polymer selection at Ashbrook s laboratory for polymer selection during pilot testing. Sampling Protocol Sampling protocol required sample collection throughout the testing. All samples were tested using the OCUA facilities laboratory utilizing OCUA personnel. Table 1 shows the analysis conducted by the plant and the frequency of testing for cake, biosolids, polymer, filtrate and centrate. The vendors used their own testing equipment for establishing guidelines of performance, however only laboratory data was used testing and reporting purposes. These results were entered in the corresponding data sheets. Results that have been found to be in obvious mistake, were disregarded from the testing data, and adjusted accordingly if required. The OCUA laboratory provided plastic containers for sampling and a mechanism for pick-up of the collected sample containers. Laboratory persons pick up the sample containers twice a day, one half-way through the testing day and the second at the end of the day. Empty, cleaned and labeled bottles were returned to the testing site during the first sample pick up event. Table 1. Frequency and Analysis Performed by OCUA Laboratory for Each Set of Sample SAMPLE SAMPLING ANALYSES Feed* Every parameter change and following min of steady run depending on unit TS Cake Every parameter change and following min of steady run depending on unit TS Filtrate/ Every parameter change and following centrate min of steady run depending on unit TSS Polymer Every new batch of polymer only TS *TVS will be measured once a day Day One of the Pilot Testing The vendors were requested to arrive with their equipment at the Southern WPCF either Sunday afternoon between 2-5pm or Monday morning the week of testing. Each vendor operated their own equipment under the consultant supervision. An average period of three (3) hours was allowed to install the mobile unit on site. The services of an electrician and other maintenance 530
5 persons from OCUA were provided to provide the electrical, sludge and water connections required. Connections requirements for pilot testing were finalized at earlier stages between the authority and the vendor. OCUA provided dewatered cake conveyance system and dumpster(s) for the produced cake, and was responsible for emptying and disposing the cake solids. OCUA provided water, electricity, biosolids and access to drains for wash water and centrate/filtrate. The remainder of Day One was considered a pre-testing period where the dewatering equipment operator was optimizing the equipment setup and getting familiar with the biosolids and dewatering parameters. The centrifuge operator adjusted parameters such as pond dept, differential speed, torque, sludge flow, polymer feed rate and polymer concentration in order to obtain the range of proper dewatering through observation of the centrate quality. Following this testing the pond depth will be established, the range of differential speed, polymer dose and sludge flow will be verified. The BFP s operator adjusted parameters such as belt speed, sludge flow, polymer feed and concentration, belt pressure in order to obtain proper dewatering. Some sampling will be taken this day for confirmation of visual observation of dewatering. Sampling during Day One was conducted for confirmation of visual observation of dewatering performed. Days Two and Three of the Pilot Testing During these testings, operational parameters were tested and changed systemically allowing one parameter to be changed at a time. Between each adjustment of any operating parameter, a delay of minutes was used to assure the stability of the equipment prior to collecting samples. This constant pattern of operational and sampling procedures allowed maintaining a high level of precision in the results and laboratory data. Three types of testing were conducted during these days and discussed below. 1. Effect of Polymer Dose on Cake Solids and Determining Optimum Polymer Feed Range Four to five different polymer feeds (and thus doses) were tested at a constant, optimized biosolids flow rate and pond depth in the case of centrifuge and belt speed, belt pressure, and wash water (as determined from pre-testing). Based on Day One pre-testing observations, the polymer dosage was expanded beyond what is considered optimum, allowing lower and higher dosages to be practiced if required. Usually, testing start from the higher polymer feed rate and decrease in a stepwise manner. With each polymer dosage, the unit was allowed at least minutes of stabilization time and samples of unconditioned sludge and cake were collected for total solids measurements (%TS). Centrate/filtrate was collected for total solids and suspended solids measurements (%TS and %TSS). 2. Effect of Hydraulic and Solids Loading on Cake Solids At the optimum polymer dose determined earlier, and keeping other parameters constant, five different sludge flow rates were tested, two high and two low flow rates were used in addition to the near optimum flow rate. The objective of this testing is to test the performance of the dewatering device under higher loading conditions. In the case of the centrifuge, the differential speed and torque were adjusted based on the clarity of the centrate, and in the BFP case, the belt speed was adjusted to accommodate the biosolids flow rate. As before, with each flow rate, the 531
6 units were allowed ~ minutes of stabilization time and the different samples as discussed before were collected and analyzed. Day Four of the Pilot Testing Day Four was allocated for testing consistency of delivering cake solids and solids recovery for extended periods using operational parameters such as polymer dose, biosolids flow rate and other equipment setting parameters unchanged. Same samples as before will be collected every hour. This testing is considered performance testing using previously recognized operational parameters for the biosolids being testing. The testing results from this day were used in comparing the centrifuge and the BFP performance for the plant being tested, and was communicated with the vendors. Day Five of the Pilot Testing In this day, the vendor disassembled the pilot unit and transported to the next testing plant with the help of OCUA personnel, to be assembled the following Monday. PILOT TESTING REQUIREMENTS AND COORDINATION Requirements for the side-by-side pilot testing at each site were communicate, discussed and finalized with the dewatering vendors and OCUA appropriate staff from each treatment plant. Site visitations to each plant from Ashbrook persons for the BFP and Alfa Laval persons for the centrifuge were conducted in order to communicate and finalize testing requirements and support needed for successful pilot testing of the equipment. These requirements (staff, electricity, water, dumpsters, connection of dewatering trailer to the plant, filtrate/centrate drainage, etc,) were communicated to each plant through pilot testing guidance memorandum. Table 2 shows connection requirements for each pilot unit. Table 3 shows the division of responsibilities among the vendors, OCUA and the consultant during the pilot testing period. A point of contact person from each of the three facilities was responsible for all communications and pilot testing logistics. Table 2. Connection requirements for each pilot unit Requirements BFP/Ashbrook (1) Centrifuge/Alfa Laval (2) Equipment Size Trailer: 48 long, 8.6 wide, 13.3 high Skid: Length: 11.3 long, 6 wide, 8 high Power 480 volts at 100 Amps, 60 cycle/3 phase plus ground 400V. MIN/ at 100 Amps, 60 cycle/3 phase plus ground Water (potable or plant effluent if <30mg/LSS) 1 1/2" quick disconnect fitting, min 60psi 1 1/2" quick disconnect fitting, min 60psi Sludge Filtrate/Centrate 4" quick disconnect fittings 4" quick disconnect fittings 4" camlock connection 4" camlock connection Cake Container A 20 or 30 cubic yard dumpster for one day. No more 4.6 high A 20 or 30 cubic yard dumpster for one day 532
7 Sludge Conveyor Specs Discharge Height: 5 ft Discharge Height: 5 ft Distance from Skid: 12 ft (1) Trailer has sufficient hose and electrical cable to make connections within 50 ft only. Discharge filtrate and sludge feed connection will be made from the back of the trailer within 50 ft range (2) Skid has 50 foot electrical cable, and 50 Feet Suction/Discharge Hosing Table 3. Division of Responsibilities for Pilot Testing During Setup, testing and dismantling OCUA Consultant Vendor Setup and Connections Provide personnel for electrical, sludge and water connection Provide water, sludge and electricity Provide dumpster(s) for the sludge cake Provide access to drains for wash water, filtrate/centrate Oversee set-up and coordinate with OCUA Execute actual setup of the equipment Provide all needed polymer amount for the duration of the testing Testing Provide containers for sample collection on a continuous basis Provide containers labels Conduct total solids analysis on collected samples and provide tabulated results Empty dumpster and disposing the cake solids Disconnect Provide personnel to assist in disconnecting electricity, sludge and water Observe and assure that the testing adheres to the established protocol Complete daily data sheets during testing Collect samples and deliver labeled containers to OCUA labs for analysis Execute the testing and operate the pilot unit Test operating parameters based on established protocol Disconnect the pilot unit Transport unit to next site or departure 533
8 DEWATERING EQUIPMENT SETUP The first day of testing at each facility focused on proper setting of the equipment for delivery of biosolids to the dewatering devices and conveying the dewatered cake to the dumpster. Set up of the skid mounted Alfa Laval ALDEC 406 centrifuge and the polymer make-up and feeding system are shown in Figure 1. For this system, neat polymer solution as received from vendor was poured into a five-gallon container and allowed to flow by gravity to the polymer make up system. Dilution water, mainly tap water, is mixed with the polymer prior to conditioning the biosolids. The marked graduated cylinder shown in the figure was used to measure the polymer flow using a stop watch each time the polymer feed is changed. Figure 1. Skid Mounted Alfa Laval ALDEC 406 Centrifuge and Its Polymer Makeup System Figure 2 shows Ashbrook s trailer mounted Winklepress and the polymer makeup system. For the polymer system, either one gallon or two gallons (depending on the polymer needed to condition the sludge) of neat polymer was added to a 600 gallon mixing tank. Two tanks were available allowing continuous feed of polymer to the belt press. Regardless of the amount of polymer added, for every new batch made, a polymer sample was taken for total solids analysis and the measured TS was used in polymer feed calculations. The amount of polymer delivered in gallons per minute to dewatering was determined by using a stop watch to measure the time required to withdraw a certain volume of polymer from the tank. 534
9 Figure 2. Ashbrook s 0.6 m Trailer Mounted Winklepress and Its Polymer Makeup System OCUA s 6,000 gallon smooth-bore tank trailer shown in Figure 3 was used as an equalization tank for feeding both dewatering devices with biosolids. The biosolids from the secondary digester were pumped to the tank trailer slightly higher than the amount dewatered by both dewatering devices, thus allowing no stratification of the biosolids and delivering the same biosolids to both dewatering system. Figure 3. Tank Trailer and Hose for Delivering Biosolids to Both Dewatering Devices The dewatered biosolids from the BFP and centrifuge were conveyed to a container fabricated by the authority and then conveyed to the dumpster via a conveyor belt rented by the Authority. The container and conveyor belt to the dumpster was located between the BFP and Centrifuge. This setup is shown in Figure 4 below. 535
10 Figure 4. Cake Conveyance System from BFP and Centrifuge to the Dumpster EXAMPLE TESTING PROTOCOL RESULTS A large sum of data was collected during this side-by-side testing to be presented in this paper. The following sections represent examples of results only. Example Polymer Selection Results Four different polymers were screened for biosolids conditioning at the NWPCF prior to BFP dewatering at a constant biosolids feed and belt speed of 1.07 m/min with different polymer doses. The cake solids and percent solids recovery were measured for each polymer used. Based on the results presented in Table 4, the BFP operator selected polymer C-9555 due to the lower dose needed to obtain good dewatering as indicated by the cake solids and solids recovery. Polymer NE-1316 shows similar results at lower polymer doses and Polymer 7878FS40 appears to give the highest cake solids, but only at a very high dosage. Note that the solids content in the feed was consistent throughout the afternoon. Table 4. Polymer Selection Results from the NWPCF Polymer Type C FS40 NE-1316 C-9555 Solids Loading (lb/hr-m) Active Polymer Dose (lb/dt) % Cake Solids % Solids Recovery Example Polymer Dose Response Results Different polymer (7878FS40) feed rates were tested a constant biosolids flow rate of 47 gpm at the SWPCF with at a constant belt pressure of 260 psig and a constant belt speed of 1.26 m/min. The testing started from lower polymer feed and increasing gradually. The results are shown in Figure 5. Increasing the polymer dose from 21.6 to 41.7 lb/dt resulted in higher cake solids. However, higher polymer doses beyond 25 lb/dt resulted in only a slight increase in the cake 536
11 solids, but caused the percent solids recovery to fall below 95%. Thus from these results a polymer dose of about lb/dt is considered optimum, achieving cake solids of 25.1% and solids recovery of 98.3%. As testing progress, it was observed that the biosolids concentration started to become low leading to lower loading rate. Average loading rate during this polymer testing was about 770 lb/hr per meter of belt width. Note that a wide range of polymer dose (21-42 lb/dt) was tested with this biosolids ( ) 99 Cake %TS % Recovery Cake %TS % Recovery Poly Dose (lb/dt) Figure 5. Polymer Dose Response Testing Results at the SWPCF showing percent cake solids and solids recovery as a function of active polymer dose used. Example of Throughput Testing Table 5 shows results from testing the performance of the BFP at the CWPCF when increasing solids loading and using polymer 7878FS40 at a constant average active dose of about 30.2 lb/dt and with belt pressure of 160 psig. It can be observed that slightly higher than 20% cake solids can be achieved under these conditions with acceptable solids recovery. Increasing the solids loading rate from 368 to 1,180 lb/hr-m resulted in slight decrease in the cake solids. However, when increasing the polymer dose at the highest solids loading rate at 2:00 PM, the cake solids obtained were lower. Table 5. Belt Filter Press Throughput at the CWPCF, May Active Feed Feed TS Loading Cake Recovery Time Poly Dose (gpm) (%) (lb/hr-m) TS (%) (%) (lb/dt) Belt Speed (m/min) 09: : : : : : , : ,
12 Example of Performance Testing Under Consistent Operating Conditions Table 6 below shows the centrifuge performance testing under no changes in operation parameters. Average results from this testing as shown in the table were used in cost analysis for the centrifuge dewatering at the NWPCF. It is worthy to note during this day that the centrifuge operator appeared to be operating the centrifuge at a low polymer dose and at the edge of proper operation, which resulted in centrifuge washout at 9am, thus testing started mid-morning. Table 6. Centrifuge Consistent Operation Testing Results at the NWPCF, May Time Polymer Type Feed (gpm) Feed TS (%) Loading (lb/hr) Poly Dose (lb/dt) Cake TS (%) Recovery (%) 10:15 Mix :00 Mix :30 Mix :15 Mix :00 Mix :45 Mix :15 Mix Ave EXAMPLE COST ANALYSIS AT THE SWPCF Table 7 below summarizes the average performance results under consistent operating conditions from both dewatering devices at the SWPCF. These results were used to estimate operating costs for both dewatering device. Table 7. Average BFP and Centrifuge Performance Testing Results at the SWPCF Poly (lb/dt) Cake TS (%) Loading (lb/hr) Amps Measured Recovery (%) BFP Centrifuge The operating costs in terms of transportation and drying costs using either dewatering device while achieving the measured cake solids were estimated first from the previously published biosolids management plan report. These costs were then added to the estimated polymer and electricity costs for each dewatering device. The following sections describe the approach taken in estimating the cost from the drier cake and the costs due to polymer use and electricity consumption. 538
13 Operating Costs with Dewatering The Biosolids Master Plan report estimated operating costs when achieving dryer cakes at each of the three treatment facilities. However, these costs were estimated up to achieving 23% only and the results from pilot testing as shown in Table 6-7 indicated that dewatering devices can achieve higher cake solids. A curve fit of the projected operating costs including: 1) diesel cost during transportation, 2) natural gas and electricity costs during drying, and excluding electricity and polymer and labor costs incurred through dewatering at the SWPCF indicated that the data fits well a linear regression as shown from the equation below Operating Cost in $/Yr = 3,625, x Cake Solids in % R 2 = Accordingly, these operating costs when achieving ~23.8% using BFP dewatering can be estimated to be $121,390 per year, and operating costs when achieving 26.09% using centrifuge dewatering can be estimated to be $98,280 per year. Polymer Cost Assuming a polymer cost of about $2.0 per active pound and using the polymer doses in Table 6-7, the polymer cost is $33,870/year for the BFP and $57,240/year for the centrifuge for the current SWPCF biosolids production rate of 2.94 DT/day (value obtained from the Biosolids Master Plan report). Electricity Cost The amp draw during operation was measured for the BFP and centrifuge throughout the week. Table 8 below presents the average measured amps. In the absence of conceptual design to determine the number of required dewatering devices and the operating time to process the biosolids, the calculated loading rate for the BFP and centrifuge was used to estimate the electricity cost on a yearly basis as shown in Table 8. Table 8. Electricity Cost for the BFP and Centrifuge at the SWPCF Item BFP Centrifuge Amps, measured Volts kw Electricity Cost, $/kw-hr Consumption, $/hr Loading, dry lb/hr Unit Electrical Cost, $/dry lb processed Biosolids to be processed, DT/day Electricity cost, $/year 3,250 11,
14 Overall Cost Estimated operating costs from using the BFP and centrifuge without considering labor costs are shown in Table 9 below. The results showed that using BFP dewatering would result in a nominally lower total operating cost ($~9,000/Yr) despite the fact that drier cake solids was obtained with centrifugation. This is mainly due to polymer cost and electricity usage. It is noteworthy that during the dose response testing results previously shown in Figure 5, a higher cake solids of about 25% (closer to centrifuge results) could be achieved with the BFP when using a polymer dose of about 25 lb/dt or greater (similar to what was used with the centrifuge), which if used in the cost analysis will greatly favor the use of BFP technology at this facility. Table 9. Estimated Cost Comparison between BFP and Centrifuge Dewatering at SWPCF Dryer and Diesel Estimated Cake Polymer Electricity Operating Cost Operating TS (%) Cost ($/Yr) Cost ($/Yr) ($/Yr) Cost* ($/Yr) BFP ,390 33,870 3, ,510 Centrifuge ,280 57,240 11, ,395 * Excluding labor costs SUMMARY AND RECOMMENDATIONS Table 10 below summarizes the pilot testing results at each plant. As the table shows the BFP produced comparable performance to the centrifuge in terms of cake solids and recovery at the CWPCF and NWPCF with slightly less polymer dose. At the SWPCF the centrifuge outperformed the BFP in terms of cake solids, but with near doubling the required polymer dose. The reason for this performance difference at the SWPCF can be attributed to using low polymer dose during the performance testing of the BFP. Table 10. Side-By-Side Performance Results of BFP and Centrifuge at the Three Facilities under Consistent Operating Conditions. SWPCF CWPCF NWPCF Parameter BFP Centrifuge BFP Centrifuge BFP Centrifug e % Cake TS Poly Dose (lb active/ds) % Solids Recovery Amp Draw Throughput (lb/hr)* *Throughput in the BFP case is per meter of belt width Table 11 presents the estimated operation cost comparison summary for each technology at the three plants. The operation cost analysis used operating costs when dewatering at each facility per the biosolids management plan report (excluding the labor costs, and dewatering electricity and polymer costs); polymer cost to achieve the reported cake solids from the pilot testing; and electricity cost to process the desired biosolids from the pilot testing. Operator s attention to the technology during dewatering was not considered in the cost analysis at this point. It was 540
15 observed during piloting that more operator attention is needed for centrifuge operation compared to BFP operation. As can be seen from the table, using BFP technology would result in nominally lower operating costs at the SWPCF and much lower operating costs for the CWPCF and NWPCF as compared to centrifuge technology. Table 11. Estimated Operating Cost Comparison between BFP and Centrifuge at the Three Treatment Facilities. SWPCF CWPCF NWPCF Parameter BFP Centrifuge BFP Centrifuge BFP Centrifug e Diesel and Drying 121,390 98, , , , ,125 Costs* ($/Yr) Polymer Cost ($/Yr) 33,870 57, , , , ,575 Electricity Cost ($/Yr) 3,250 11,875 14,630 60,930 13,390 40,910 Total Operating Cost ($/Yr) 158, ,395 1,113,570 1,175, , ,610 * Biosolids Management Plan report Based on the results of side-by-side pilot testing of BFP and centrifuge equipment and the operating costs associated with each technology, it was recommended that OCUA use BFP technology for dewatering biosolids at all three facilities. It was also recommended that OCUA conduct an investigative study to examine the reasons behind the relatively poor dewaterability exhibited by digested biosolids at the CWPCF (using both technologies) compared to the dewaterability of digested biosolids at the NWPCF and SWPCF. Also, practicing polymer optimization methods are recommended when implementing BFP dewatering due to the high polymer dosage obtained from the pilot testing in both the CWPCF and the NWPCF. REFERENCES Laustsen, et al. Do Not Stop When You Are Ahead Ocean County Utilities Authority Critical Review of Current Biosolids Operation. WEF/AWWA Joint Residuals and Biosolids Management Conference
CHAPTER 1 - EXECUTIVE SUMMARY
Chapter Page CHAPTER 1 - EXECUTIVE SUMMARY 1.1 Background 1-1 1.2 Purpose/ Objectives 1-1 1.3 Flow, Condition and Operation Assessment 1-3 1.4 Class A Biosolids 1-4 1.5 Summary of Recommendations 1-4 CHAPTER
More informationIllinois Environmental Protection Agency Division of Water Pollution Control Class K Study Guide Industrial Wastewater Operator Certification
Illinois Environmental Protection Agency Division of Water Pollution Control Class K Study Guide Industrial Wastewater Operator Certification Revised March 2003 The purpose of this study guide is to help
More informationWilliam E. Dunn Water Reclamation Facility. Facility Overview & Information
William E. Dunn Water Reclamation Facility Facility Overview & Information General Area Served: Plant History Facility Highlights Northern Pinellas County St. Joseph Sound to East Lake Road (E/W) Tampa
More informationDescription of the Water Conserv II Facility
Description of the Water Conserv II Facility Introduction The Water Conserv II (WCII) Water Reclamation Facility provides service to a majority of the southwest section of Orlando. The WCII facility has
More informationCambridge Wastewater Treatment Facility
Cambridge Wastewater Treatment Facility Emergency Situations If you have a water or sewer emergency that relates to the City s utility system call the Public Works office at 763-689-1800 on normal working
More informationABC & C 2 EP Formula/Conversion Table for Water Treatment, Distribution, & Laboratory Exams
ABC & C EP Formula/Conversion Table for Water Treatment, Distribution, & Laboratory Exams Alkalinity, as mg CaCO 3 /L = (Titrant, ml) (Acid Normality)(50,000) Sample, ml Volts Amps = Ohms * of Circle =
More informationBASIC MATH FORMULAS - CLASS I. A. Rectangle [clarifiers, ponds] I = length; w = width; A = area; area in square ft [sq ft]
WASTEWATER MATH CONVERSION FACTORS 1. 1 acre =43,560 sq ft 2. 1 acre =2.47 hectares 3. 1 cu ft [of water] = 7.48 gallons 4. 1 cu ft [of water] = 62.4 Ibs/ft 3 5. Diameter =radius plus radius, D =r + r
More informationSt. Petersburg, FL: Vehicle Use of Recycled Natural Gas Derived from Wastewater Biosolids
U.S Department of Energy - Biomass 2014 St. Petersburg, FL: Vehicle Use of Recycled Natural Gas Derived from Wastewater Biosolids William Eleazer, PE Project Design Manager John Willis, PE, BCEE Project
More informationPractice Tests Answer Keys
Practice Tests Answer Keys COURSE OUTLINE: Module # Name Practice Test included Module 1: Basic Math Refresher Module 2: Fractions, Decimals and Percents Module 3: Measurement Conversions Module 4: Linear,
More informationThis example of a completed sampling plan worksheet has been included to illustrate the information
APPENDIX B EXAMPLE OF A COMPLETED SAMPLING PLAN WORKSHEET This example of a completed sampling plan worksheet has been included to illustrate the information necessary to document a sampling program for
More informationThe City of Boulder 75 th Street Wastewater Treatment Facility
The City of Boulder 75 th Street Wastewater Treatment Facility Wastewater Collection and Treatment The Foundation of Public Health Wastewater Collection Boulder s wastewater collection system, also known
More informationTemporary Batch Plants
Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category
More informationCWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM
CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM OTCO Water Workshop March, 2011 Frank Woyma Plant Manager Nick Pizzi Vice-President EE&T ENVIRONMENTAL ENGINEERING & TECHNOLOGY, INC. Objectives Review the
More informationPathogen Indicator (Fecal Coliform) Regrowth In Biosolids Cake Update
Pathogen Indicator (Fecal Coliform) Regrowth In Biosolids Cake Update by Todd O. Williams, BCEE, P.E. CH2M HILL Richmond, Virginia Presented at the 33 rd Annual Spring Biosolids Symposium Central States
More informationLaundry Hot Water Systems
TECHNICAL BULLETIN HE-2020 Laundry Hot Water Systems Commercial/Institutional Applications using Helitherm Heat Exchangers AERCO INTERNATIONAL, INC. 159 PARIS AVE., NORTHVALE, NJ 07647 (201) 768-2400 FAX
More informationEl Paso Water Utilities Public Service Board. Application for Renewal Industrial Wastewater Discharge Permit
El Paso Water Utilities Public Service Board Application for Renewal Industrial Wastewater Discharge Permit Application for Renewal for Industrial Wastewater Discharge Permit must be completed and submitted
More informationWell Water Iron Removal Using Quantum DMI-65 Granular Filter Media
Well Water Iron Removal Using Quantum DMI-65 Granular Filter Media ASME Research Committee Power Plant and Environmental Chemistry Overland Park, Kansas April 2-4, 2007 Prepared by: W. H. Stroman Primary
More informationChapter 5 Solids Thickening and Dewatering Systems
Chapter 5 Solids Thickening and Dewatering Systems Thickening and dewatering are important components of biosolids management programs. The proper solids concentration is critical in stabilization processes
More informationNine Industrial Scale V SEPs. Feed Tank V SEP. Feed Pumps (Three) Concentrate. Tank. V SEP Treatment System
River Treatment for Ultrapure Production A cost-effective and environmentally-sound solution Abstract New Logic International installed its Vibratory Shear Enhanced Processing (VSEP) Phase I system in
More informationEXISTING WASTEWATER TREATMENT FACILITIES
Chapter 5 EXISTING WASTEWATER TREATMENT FACILITIES 5.1 THERESA STREET WWTF 5.1.1 Overview The Theresa Street WWTF is the larger of the two wastewater treatment facilities owned and operated by the City
More informationCity of Richmond Department of Public Utilities
City of Richmond Department of Public Utilities Wastewater Treatment Plant EMS Case Study Profile City of Richmond (COR), home to the James River, is in the heart of Virginia and known for its pleasant
More informationATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING
ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,
More informationOutline. Background. NFPA 820 Applicability to Wastewater Treatment Facilities. Hazardous Area Classifications. Treatment Plant Area Classifications
Outline Background NFPA 820 Applicability to Wastewater Treatment Facilities Hazardous Area Classifications Treatment Plant Area Classifications Locations of Concern Background NFPA 820 Standard for fire
More informationHOW DOES THIS SERVICE CONTRIBUTE TO THE QUALITY OF LIFE IN THE CITY OF LONDON?
Service: Program: 3.4. Wastewater Removal & Storm Water Management Environmental Services HOW DOES THIS SERVICE CONTRIBUTE TO THE QUALITY OF LIFE IN THE CITY OF LONDON? The desired population results in
More informationThere are two sheets, Diesel and Electric, identified by tabs at the bottom of the sheet.
Willard Says Absolutely fascinating information about practical hydraulic dredging. How To Use the Dredge Production Cost Spreadsheet This program guide describes the various dredge operating cost parameters
More informationWISCONSIN WASTEWATER OPERATORS ASSOCIATION
Integrity. People. Knowledge. WISCONSIN WASTEWATER OPERATORS ASSOCIATION ANNUAL CONFERENCE GREEN BAY Resources. MEETING LOW LEVEL PHOSPHORUS LIMITS BY CHEMICAL ADDITION WHAT IS PHOSPHORUS Atomic # 15 Electron
More information5. Environmental Analysis
5.11 The potential for adverse impacts on utilities and service systems was evaluated based on information concerning current service levels and the ability of the service providers to accommodate the
More information( ) ABC Formula/Conversion Table for Wastewater Treatment, Industrial, Collection and Laboratory Exams. Alkalinity, as mg CaCO 3 /L =
ABC Formula/Conversion Table for Wastewater Treatment, Industrial, Collection and Laboratory Exams Alkalinity, as mg CaCO 3 /L = (Titrant Volume, ml) (Acid Normality)(50,000) Volts Amps = Ohms Area of
More informationPursuant to Department of Environmental Protection Rules Chapter 555, effective March 9, 2009
APPLICATION FOR ADDITION OF TRANSPORTED WASTES IN WASTEWATER TREATMENT FACILITIES Pursuant to Department of Environmental Protection Rules Chapter 555, effective March 9, 2009 This application is to be
More informationMATHEMATICS FOR WATER OPERATORS
MATHEMATICS FOR WATER OPERATORS Chapter 16: Mathematics The understanding of the mathematics of water hydraulics (flows, pressures, volumes, horsepower, velocities) and water treatment (detention time,
More informationBay Park Sewage Treatment Plant Super Storm Sandy Recovery
County of Nassau Department of Public Works Bay Park Sewage Treatment Plant Super Storm Sandy Recovery Edward P. Mangano County Executive Shila Shah-Gavnoudias, P.E. Commissioner of Public Works Bay Park
More informationBackground. 179 million gallons saved for make-up water
Essential Expertise for Water, Energy and Air Gallatin Steel Achieves Significant eroi Savings Through the Use of Nalco Innovative Technologies Background Gallatin Steel is a mini-mill that produces steel
More informationAMERICAN BOTTOMS REGIONAL WASTWATER TREATMENT FACILITY BID AB 31-15 SLUDGE LOADING, HAULING & DISPOSAL TECHNICAL SPECIFICATIONS
AMERICAN BOTTOMS REGIONAL WASTWATER TREATMENT FACILITY BID AB 31-15 SLUDGE LOADING, HAULING & DISPOSAL TECHNICAL SPECIFICATIONS 1. General Description The contractor shall provide all labor, equipment,
More informationDesign Criteria & Service Goals
4.1 Design Life of Improvements The design life of a water system component is sometimes referred to as its useful life or service life. The selection of a design life is a matter of judgment based on
More informationTexas Commission on Environmental Quality Page 1 Chapter 217 - Design Criteria for Domestic Wastewater Systems
Texas Commission on Environmental Quality Page 1 217.31. Applicability. SUBCHAPTER B: TREATMENT FACILITY DESIGN REQUIREMENTS 217.31-217.39 Effective August 28, 2008 This subchapter details the design values
More informationBHS CANDLE FILTER APPLICATIONS FOR CLARIFICATION / RECOVERY OF SOLIDS FROM CHEMICAL SLURRIES
FOR CLARIFICATION / RECOVERY OF SOLIDS FROM CHEMICAL SLURRIES TABLE OF CONTENTS 1. FINE CATALYST RECOVERY AT A REFINERY Pages 2 4 2. FINE SOLIDS REMOVAL & CLARIFICATION OF A SPECIALIZED ACIDIC SOLVENT
More informationMANURE COLLECTION AND TRANSFER SYSTEMS IN LIVESTOCK OPERATIONS WITH DIGESTERS. A. C. Lenkaitis GEA Farm Technologies Inc. (Houle USA), Naperville, IL
MANURE COLLECTION AND TRANSFER SYSTEMS IN LIVESTOCK OPERATIONS WITH DIGESTERS A. C. Lenkaitis GEA Farm Technologies Inc. (Houle USA), Naperville, IL INTRODUCTION Manure collection systems are influenced
More informationCooling Tower Sidestream Filtration A Green, Proven Cost Reduction Technology
Cooling Tower Sidestream Filtration A Green, Proven Cost Reduction Technology TAB0411 Typical crossflow cooling tower installation Due to the large air-water interface needed to obtain good evaporative
More informationWASTEWATER TREATMENT OBJECTIVES
WASTEWATER TREATMENT OBJECTIVES The student will do the following: 1. Define wastewater and list components of wastewater. 2. Describe the function of a wastewater treatment plant. 3. Create a wastewater
More informationWEFTEC.06 IMPLICATIONS OF ASSET MANAGEMENT ON CAPITAL AND O&M FINANCING
IMPLICATIONS OF ASSET MANAGEMENT ON CAPITAL AND O&M FINANCING Cara Wilson, Priscilla Bloomfield, Steve McDonald *Carollo Engineers, P.C. 4380 Southwest Macadam Avenue, Suite 300 Portland, OR 97239 ABSTRACT
More informationSan Luis Obispo County Los Osos Wastewater Project Development TECHNICAL MEMORANDUM SEPTAGE RECEIVING STATION OPTION TABLE OF CONTENTS
San Luis Obispo County Los Osos Wastewater Project Development TECHNICAL MEMORANDUM SEPTAGE RECEIVING STATION OPTION TABLE OF CONTENTS Page No. 1.0 BACKGROUND...1 2.0 INTRODUCTION - SEPTAGE RECEIVING STATION...1
More informationNEW JERSEY CENTER OF EXCELLENCE
Overview NEW JERSEY Page 1 The Plant (CUP) provides electricity via a cogeneration system, chilled water for environmental cooling, steam for heating, and compressed air primarily for HVAC control Serves
More informationCHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES
CHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES 8-1. General. Upgrading of wastewater treatment plants may be required to handle increased hydraulic and organic loadings to meet existing effluent quality
More informationCentrifugal Fans and Pumps are sized to meet the maximum
Fans and Pumps are sized to meet the maximum flow rate required by the system. System conditions frequently require reducing the flow rate. Throttling and bypass devices dampers and valves are installed
More informationREPORT ON FINANCIAL PLAN, COST OF SERVICE AND RATES WATER AND SEWER OPERATING FUND
REPORT ON FINANCIAL PLAN, COST OF SERVICE AND RATES WATER AND SEWER OPERATING FUND Harford County, Maryland APRIL 2016 Black & Veatch Holding Company 2011. All rights reserved. Harford County Report on
More informationABC & C 2 EP Formula/Conversion Table for Wastewater Treatment, Industrial, Collection, & Laboratory Exams
ABC & C EP Formula/Conversion Table for Wastewater Treatment, Industrial, Collection, & Laboratory Exams Alkalinity, as mg CaCO /L (Titrant, ml) (Acid Normality)(50,000) Sample, ml Volts Amps Ohms * of
More informationWastewater(Solids(Management(( 2(Atlantic(Canada(Perspective( Dwayne(Doucette,(MASc.(P.Eng.((( June(19,(2013(
Wastewater(Solids(Management(( 2(Atlantic(Canada(Perspective( Dwayne(Doucette,(MASc.(P.Eng.((( June(19,(2013( Wastewater(Treatment(in( Atlantic(Canada( Dramatic improvement in this Region over the Past
More informationEnvironmental Technology March/April 1998
Treating Metal Finishing Wastewater Sultan I. Amer, Ph.D. AQUACHEM INC. Environmental Technology March/April 1998 Wastewater from metal finishing industries contains high concentrations of contaminants
More informationCREATING A GREEN FUTURE THROUGH WATER REMEDIATION
CREATING A GREEN FUTURE THROUGH WATER REMEDIATION Cornerstone Principles for Conducting Business Active Treatment Systems, Inc. goes to great lengths to instill in every employee the importance of ethical
More informationStandard Operating Procedure for the Determination of Total and Total Dissolved Solids CCAL 13A.2
Standard Operating Procedure for the Determination of Total and Total Dissolved Solids CCAL 13A.2 Cooperative Chemical Analytical Laboratory College of Forestry Oregon State University 321 Richardson Hall
More informationSewerage Management System for Reduction of River Pollution
Sewerage Management System for Reduction of River Pollution Peter Hartwig Germany Content page: 1 Introduction 1 2 Total emissions 3 3 Discharge from the wastewater treatment plants 4 4 Discharge from
More informationCost Savings Gained through Rotary Impingement Tank Cleaning
Gamajet Cleaning Systems, Inc. Exton, Pennsylvania August 2012 Cost Savings Gained through Rotary Impingement Tank Cleaning Abstract: Specific case studies on the benefits of rotary impingement and CIP
More informationCase Study: Treatment of alluvial sand, treatment of washing water and sludge.
Case Study: Treatment of alluvial sand, treatment of washing water and sludge. Client: FAMY & Cie SARL Site of BELLEGARDE Presentation of the project: The company Famy operates in the department of Ain,
More informationEnergy Audits Waste Water Treatment Plants
Energy Audits Waste Water Treatment Plants Ohio Water Environment Association Conference June 20, 2012 Presented by: Samuel J. Morgan, P.E., LEED AP CT Consultants, Inc. World Energy Trend US Total Energy
More informationDirector of Utilities. Manager. Distribution Supervisor. Utilities Analyst. Account Clerk. Water. Conservation Specialist.
DEPARTMENT WATER RESOURCES ORGANIZATIONAL CHART Director of Utilities Secretary Resources Manager Business Services Manager Utilities Engineer Resources Supervisor Distribution Supervisor Utilities Project
More informationMC4-50 Feeding System
MC4-50 Feeding System Dry Calcium Hypochlorite For Municipal Applications The smarter way to water quality PATENTED SPRAY TECHNOLOGY DELIVERS UNPARALLELED CONSISTENT RESULTS The Constant Chlor Plus MC4-50
More informationTOWN OF LAKESHORE CLASS ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL STUDY REPORT FOR LAKESHORE EASTERN COMMUNITIES SEWAGE WORKS
TOWN OF LAKESHORE CLASS ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL STUDY REPORT FOR LAKESHORE EASTERN COMMUNITIES SEWAGE WORKS Prepared for The Town of Lakeshore 419 Notre Dame Street, Belle River Ontario
More informationTampa Bay Seawater Desalination Plant
Tampa Bay Seawater Desalination Plant Project History How The Plant Works Desal Fun Facts 2575 Enterprise Road, Clearwater, FL 33763-1102 Phone: 727.796.2355 / Fax: 727.791.2388 www.tampabaywater.org Tampa
More informationExperts Review of Aerobic Treatment Unit Operation and Maintenance. Bruce Lesikar Texas AgriLife Extension Service
Experts Review of Aerobic Treatment Unit Operation and Maintenance Bruce Lesikar Texas AgriLife Extension Service Overview Overview of Aerobic Treatment Units Installing for accessibility to system components
More informationMEMCOR membranes for drinking water applications. Water Technologies
MEMCOR membranes for drinking water applications Water Technologies Memcor membranes Why choose membrane filtration? As ever-tightening water regulations continue to challenge the limits of conventional
More informationWater Wash Spray Booth Paint Sludge Recovery
Water Wash Paint Spray Booth Sludge Removal, Water Curtain Paint Wastewater Treatment, Paint Sludge Separation and Dewatering, Paint sludge removal centrifuge, Palin paint sludge dewatering Since 1991
More informationGodwin NC series Dri-Prime pumps
Godwin NC series Dri-Prime pumps now with Flygt N-technology INTRODUCTION 2 We combined the world s most reliable portable pumps with the world s most efficient self-cleaning hydraulics To bring you the
More information12:10 Lysotherm : 5 jaar ervaring met innovatieve slibhydrolyse. Bert Geraats (Eliquo)
LYSOTHERM A novel approach to thermal sludge hydrolysis 01.07.2015 ELIQUO WATER GROUP FACTS AND FIGURES STAFF HISTORY FIGURES >200 employees Engineers Technicians Sales, commercial staff 1986 ELIQUO WATER
More informationFilter Aid Filtration
Filter Aid Filtration Filtration is the separation of solids from liquids by forcing the liquid to flow through a porous medium and depositing the solids on the medium. A filter aid (finely divided material
More informationWater Efficiency. Water Management Options. Boilers. for Commercial, Industrial and Institutional Facilities. Boiler Water Impurities
Water Efficiency Water Management Options Boilers for Commercial, Industrial and Institutional Facilities Boiler Water Impurities All boiler make-up water contains impurities. As clean steam is released
More informationApplication Note NEW LOGIC RESEARCH. Treating Fuel Storage Tank Bottom Water With VSEP. Overview
Treating Fuel Storage Tank Bottom Water With VSEP Overview Fuel storage tank bottom water (FSTBW) is one of several types of petroleum contaminated wastewater sources that can be treated using V SEP technology.
More informationConversions between the common units of length used in the Imperial system are listed below 12 in = 1 ft 3 ft = 1 yard 1760 yards = 1 mile
THE METRIC SYSTEM The metric system or SI (International System) is the most common system of measurements in the world, and the easiest to use. The base units for the metric system are the units of: length,
More informationModule 9: Basics of Pumps and Hydraulics Instructor Guide
Module 9: Basics of Pumps and Hydraulics Instructor Guide Activities for Unit 1 Basic Hydraulics Activity 1.1: Convert 45 psi to feet of head. 45 psis x 1 ft. = 103.8 ft 0.433 psi Activity 1.2: Determine
More informationDesigning a Zero-Waste Concrete Mix Testing Lab
Designing a Zero-Waste Concrete Mix Testing Lab James A. Lee 1 Michael J. D Agostino 2 Abstract A zero waste laboratory to mix and test the engineering and performance properties of concrete was designed
More informationEXISTING WASTEWATER TREATMENT FACILITIES
Chapter 5 EXISTING WASTEWATER TREATMENT FACILITIES 5.1 THERESA STREET WWTF 5.1.1 Overview The Theresa Street WWTF is the larger of the two wastewater treatment facilities owned and operated by the City.
More informationOPTIMIZING CONDENSER WATER FLOW RATES. W. A. Liegois, P.E. Stanley Consultants, Inc. Muscatine, Iowa
OPTIMIZING CONDENSER WATER FLOW RATES W. A. Liegois, P.E. Stanley Consultants, Inc. Muscatine, Iowa T.A. Brown, P.E. Thermal Energy Corporation Houston, Texas ABSTRACT Most chillers are designed for a
More informationUDOT SPILL PREVENTION and RESPONSE PLAN for CONSTRUCTION SITES
UDOT SPILL PREVENTION and RESPONSE PLAN for CONSTRUCTION SITES February 2014 The plan contained in the following pages was developed in part from UDOT Construction Division s Safety and Health Manual,
More informationDependable dewatering. High corrosion resistance.
Dependable dewatering. High corrosion resistance. Star Filters has been manufacturing quality, dependable stainless steel plate and frame filters for liquid processing applications for over 100 years.
More informationWASTE WATER TREATMENT for surface treatment applications
WASTE WATER TREATMENT for surface treatment applications Effluent an important cost factor Effluent cannot be avoided Water and compound are essential for vibratory mass finishing. During the finishing
More informationDewatering - Time and Cost Relief by way of Trenchless Construction
North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-04 Dewatering - Time and Cost Relief by way of Trenchless Construction Jenn Stillman,
More informationFire Pump Plan Review March 2010
Fire Pump Plan Review March 2010 Date of Review: / / Permit Number: Business/Building Name: Address of Project: Designer Name: Designer s Phone: Contractor: Contractor s Phone: Occupancy Classification:
More informationCOD/BOD 5 Reduction with ROTAMAT Fine and Micro Screens
COD/BOD 5 Reduction with ROTAMAT Fine and Micro Screens Removal of particulate material from wastewater Eco-efficient use of capital Water pollution control through maximum COD/BOD 5 reduction Service
More information26th Ward Wastewater Treatment Plant Wet Weather Operating Plan
26th Ward Wastewater Treatment Plant Prepared by: New York City Department of Environmental Protection Bureau of Wastewater Treatment July 2010 TABLE OF CONTENTS Page 1.0 INTRODUCTION... 1-1 1.1 BACKGROUND...
More informationA Guide to Hazardous Substance Storage Capacity
New Jersey Department of Environmental Protection Bureau of Release Prevention A Guide to Hazardous Substance Storage Capacity August 7, 2014 Introduction The Spill Compensation and Control Act (the Spill
More informationSeptic System Management Plan for Below Grade Systems
The goal of a septic system is to protect human health and the environment by properly treating wastewater before returning it to the environment. Your septic system is designed to kill harmful organisms
More informationTown of New Castle Utility Department Introduction
Town of New Castle Utility Department Introduction Town of New Castle Utility Department Mission Statement Our commitment is to ensure that our customers receive high quality water and wastewater treatment
More informationFLOTTWEG CENTRIFUGE TECHNOLOGY FOR OIL SLUDGE TREATMENT Open Up New and Profitable Oil Wells
FLOTTWEG CENTRIFUGE TECHNOLOGY FOR OIL SLUDGE TREATMENT Open Up New and Profitable Oil Wells FLOTTWEG TECHNOLOGY FOR OIL SLUDGE TREATMENT Efficient Centrifuge Technology for the Treatment of Oily Waste
More informationEnrichments (6-10) Grade(s) Grades 6-10. Goal(s) Practice mathematical problem solving skills
Enrichments (6-10) At a glance These materials are a sampling of quick equations that your students can complete as they tour the Zoo (Elephant Reserve, Lords of the Arctic, Children s Zoo Sea Lions, Swan
More informationRotary Tank Cleaning and Cost Savings
Rotary Tank Cleaning and Cost Savings Gamajet Cleaning Systems, Inc. Exton, Pennsylvania June 2011 Abstract: Specific case studies on the benefits of rotary impingement and CIP optimization vs. the standard
More informationDEWATERING AND WATER TREATMENT OPERATIONS OF THE OTTAWA RIVER SEDIMENT REMEDIATION PROJECT
DEWATERING AND WATER TREATMENT OPERATIONS OF THE OTTAWA RIVER SEDIMENT REMEDIATION PROJECT William J. Cretens 1 ABSTRACT The Ottawa River Sediment Remediation Project, performed in Toledo, Ohio in 2010,
More informationDirector of Utilities. Manager. Regulatory Compliance Supervisor. Distribution Supervisor. Utilities Analyst. Account Clerk. Water
DEPARTMENT ORGANIZATIONAL CHART WATER RESOURCES Director of Utilities Secretary Resources Manager Business Services Manager Utilities Engineer Resources Supervisor Distribution Supervisor Utilities Project
More informationPRODUCT SELECTOR Pollution Control, Pumping and Rainwater Harvesting Systems
PRODUCT SELECTOR Pollution Control, Pumping and Rainwater Harvesting Systems PACKAGE SEWAGE TREATMENT SYSTEM Clearwater treatment plants are ideal for single houses and employ the well proven aerobic biological
More informationSYNERGISTIC APPLICATION OF ADVANCED PRIMARY AND SECONDARY WASTEWATER TREATMENT SYSTEMS
SYNERGISTIC APPLICATION OF ADVANCED PRIMARY AND SECONDARY WASTEWATER TREATMENT SYSTEMS Published in Water and Waste Digest membrane issue, November 2008 Miroslav Colic; Chief Scientist, Clean Water Technology
More informationSMALL COMMUNITY TREATMENT PLANT EXPANSION WHILE IN OPERATION USING ADVANCED TECHNOLOGY
SMALL COMMUNITY TREATMENT PLANT EXPANSION WHILE IN OPERATION USING ADVANCED TECHNOLOGY Adel Bassyouni, HDR Engineering, Guillermo Garcia, HDR Engineering, Don Mc Dermott, Viejas Public Works Department
More informationWastewater Treatment System Rehabilitation Project
Wastewater Treatment System Rehabilitation Project An overview The City of Shelton, WA / January 2010 Before After SHELTON WASTEWATER TREATMENT IMPROVMENTS PROJECT Enabled by extensive grant-funding, loans
More informationGuidelines for Preparing for a Temporary Steam Plant
Guidelines for Preparing for a Temporary Steam Plant Trailer-Mounted Boilers Skid Mounted Boilers Mobile Boiler Rooms Mobile Feedwater Vans Mobile Steam Plants Emergency Preparedness Plan Table of Contents
More informationResiduals Management Somersworth Drinking Water Treatment Facility. Ian Rohrbacher, Treatment Operator IV
Residuals Management Somersworth Drinking Water Treatment Facility A HISTORICAL OVERVIEW OF SURFACE WATER TREATMENT RESIDUALS HANDLING Ian Rohrbacher, Treatment Operator IV Background We are a Grade III
More informationImproper storage of potential pollutants will increase the risk of water pollution that may occur because of spills.
WQ-3 Best Management Practice (BMP) Water Quality Protection Guideline Secondary Containment Design and Operation Standards Section 1. Introduction According to the EPA, the majority of water pollution
More informationA HOMEOWNERS GUIDE ON-SITE SEWAGE MANAGEMENT SYSTEMS
GEORGIA DEPARTMENT OF HUMAN RESOURCES ENVIRONMENTAL HEALTH SECTION A HOMEOWNERS GUIDE TO ON-SITE SEWAGE MANAGEMENT SYSTEMS March 12, 2002 WHAT IS AN ON-SITE SEWAGE MANAGEMENT SYSTEM An on-site sewage management
More informationAir Eliminators and Combination Air Eliminators Strainers
Description Air Eliminators and Combination Air Eliminator Strainers are designed to provide separation, elimination and prevention of air in piping systems for a variety of installations and conditions.
More informationReduced water consumption in the removal of paint from skids Compact filter MAXFLOW in the automotive production
Reduced water consumption in the removal of paint from skids Compact filter MAXFLOW in the automotive production Optimum surface coating of passenger cars: Before being provided with their customer-chosen
More information1 Quality Assurance and Quality Control Project Plan
1 Quality Assurance and Quality Control Project Plan The purpose of this section is to describe the quality assurance/quality control program that will be used during the system specific field testing
More informationIntroducing the Improved MAS DRD "Waterless" Cleaning System for Plastic Film, Flakes and Fibers
PRESS RELEASE - For Immediate Distribution Introducing the Improved MAS DRD "Waterless" Cleaning System for Plastic Film, Flakes and Fibers September 28, 2015 - The Upper Austrian plastics machinery manufacturer
More informationExecutive Summary: PA No. 12 Micro-hydro at Graham Hill Water Treatment Plant
Executive Summary: PA No. 12 Micro-hydro at Graham Hill Water Treatment Plant Description A micro-hydro project at SCWD s Graham Hill Water Treatment Plant (WTP) would replace an exisiting non-operational
More information