1 Guidebook for General Requirements for Building in Gordon County Gordon County Building, Planning & Development P.O. Box 580 Calhoun, GA Telephone: (706) Fax: (706) This guide should answer frequently asked question for building requirements in Gordon County. Additional questions you may have which are not covered should be directed to the Building, Planning & Development Department (706) Revised

2 Land Requirements The Environmental Health Department may require additional land if the soil fails to meet State requirements for septic approval. If your property has been subdivided after 1992 it may require re-zoning prior to a building permit being issued. See page 8 for minimum lot size and set backs Sewage Systems Sewage system requirements are regulated by the Environmental Health Department. All inquiries regarding soil requirements, testing, permits, etc. should be directed to: Gordon County Environmental Health 318 North River Street, Calhoun, GA (706) A septic system permit must be obtained prior to applying for a building permit. Fire Permits All commercial/industrial and religious/institutional facilities require a fire permit from the Gordon County Fire Prevention Inspector prior to applying for a building permit. Contact (706) Permit Applications The following information must be provided at the time of application for a building permit: 1. Septic Permit (contact Environmental ) 2. Fire Permit (commercial, industrial & multifamily dwellings projects.) 3. Copy of recorded deed and plat of property. 4. One set of building plans (not required for Agricultural buildings & small storage buildings) 5. Street Address (obtained from Gordon County Emergency Management ( ) Please allow 48 hours to process applications Building Plans Building plans must be submitted for review at the time of permit application. Plans should consist of the minimum: 1. Must be a scaled drawing. (Typically ¼ =1 ft or 1/8 = 1 ft works best) 2. Must be fully dimensioned. 3. Must include an electrical plan. 4. Must include a foundation plan. Note: xerox copies from magazines and non-original copyrighted plans are not acceptable. Design professional seals are required on plans submitted for the following: 1. All Group A,E and I occupancies. 2. Buildings and structures three stories or more high. 3. Buildings and structures 5,000 sq ft or more in area. Soil Erosion and Sedimentation If you will be grading or disturbing more than 1.0 acres or within 200 ft. of state waters*, a Land Disturbance permit is required prior to beginning any work. A Land Disturbance permit requires a soil erosion drawing and a Notice of Intent (NOI) filled with Georgia EPD. A Land Disturbance Permit can be obtained from Building Planning & Development Dept. at (706) for additional information. * for determination of state water contact Gordon county Building Planning & Development Office Licenses State of Georgia requires a general contractor license for all construction with in the state of Georgia. However, Person wishing to be their own general contractor on their project should be aware that under Georgia law they are only able to permit one project within a 24 month period and are liable for all requirements set forth under the state workman s comp law whether they have workman s comp insurance or not. Electrical, Plumbing and Heat/Air contractor working in Gordon County must have a current Georgia State contractor s license and must register with the Building Inspection Department. There is no charge for this registration. Homeowner s are allowed under state law to do electrical, plumbing and heat/air work themselves on property they own. They may not however, permit the work themselves and then hire unlicensed workers to do the work. They may not permit or perform work on projects in which they intend to resale. Violators of this law may be prosecuted by both state and local authorities. OWNER/CONTRACTORS Under Georgia law, general contractors are responsible for workman s comp. whether they carry workman s comp. insurance or not. This law also applies to homeowners working as their own general contractors. If your name appears on the building permit as the general contractor you are regarded as the general contractor even if you hire someone to perform that task. As a general contractor you are responsible for workman s comp. for all subcontractors working under you should they be injured while working on your project. Be advised that this can be a serious liability. Please contact your attorney or insurance underwriter to determine how this may affect you. Placement of Homes Homes must be located on the property so that Gordon County set-back requirements are met. See page 8 or Gordon County ULDC for requirements. 2

3 Codes The following codes have been adopted by Gordon County and are on file with the Georgia Department of Community Affairs in Atlanta. The Gordon County Building Ordinance (including local amendments to the code) are available or contact this office. One and two family dwellings: International Residential Code (IRC), 2006 Edition 2008,2008 & 2009 Amendments International Plumbing Code (IPC), 2006 Edition 2007, 2008 & 2009Amendments National Electrical Code (NEC), 2008 Edition 2009 Amendments International Energy Conservation Code (IECC), 2006 Edition 2008 & 2009 Supplements and Amendments All other Structures: International Building Code (IBC), 2006 Edition 2007& 2009 Amendments International Mechanical Code (IMC), 2006 Edition 2007& 2008 Amendments Errata to 2007 Amendments International Fuel Gas Code (IFGC), 2006 Edition 2007, 2008 & 2009 Amendments International Plumbing Code (IPC), 2006 Edition 2007, 2008 & 2009 Amendments National Electrical Code (NEC), 2008 Edition 2009 Amendments International Fire Code (IFC), 2006 Edition 2007 Amendments International Energy Conservation Code (IECC), 2006 Edition 2008 & 2009 Supplements and Amendments Local Amendments to the Technical Codes A. Footing The following are additional requirements for footings: 1. Two runs of ½ -inch (#4) minimum, steel rebar. a. Rebar shall be evenly spaced horizontally and elevated off the floor of the footing a minimum of 2 ½-inches and shall meet American Concrete Institute (ACI) Standard 318. b. Rebar must run continuous through footing, Including any step-downs and corners. c. Where it is necessary to piece rebar, it shall overlap a minimum of 12 inches. d. All rebar shall be tied together using steel wire. e. Rebar shall be installed in a neat and workmanlike manner. 2. All grade stakes must be of metal material. 3. All trenches for footings must be cleared of all roots, stumps, loose dirt and other foreign matter. 4. Bottom of footings shall be a minimum of 12 inches below grade. C. Foundations The following are additional requirements for foundations: 1. Foundations with a crawl space shall be a minimum of 28 inches above grade measured from the interior of the crawl space. 3 D. Electrical The following are additional requirements for residential electrical work: 1. Smoke detectors In addition to that required in the IRC code, a smoke detector shall be installed in the same room as the electrical panelboard except where the panelboard is located in the garage. 2. Service Disconnect Switch A service disconnect switch shall be provided on the exterior of a dwelling adjacent to the utility company meter base, unless the meter base and panelboard are in a back-to- back position on the same wall and where the service conductors do not leave the confines of these two enclosures. 3. Wire Size Minimum wire size allowed for branch circuit work shall be #12 AWG. E. Plumbing The following are additional requirements for plumbing work: 1. Polybutylene piping shall not be used. F. Conventional housing moved on-site and modular houses shall be subject to meeting the technical codes and any other applicable local ordinances. Modular homes shall be defined as a structure in which the major components are manufactured in a factory, transported to the site on trucks, where final assembly takes place. Modular homes are constructed on permanent foundations as a stickbuilt home would be. G. Lumber - The minimum grade of lumber which shall be allowed is number 2 grade. H. An anti-siphon device (back-flow preventer) shall be installed on the water service pipe on the customer side of the water meter in a separate enclosure. The main service shutoff valve shall be located in this enclosure. I. All water heaters shall be provided with a thermal expansion valve or tank. This valve shall be in addition to the temperature and pressure relief valve. Permit Card State law requires that a permit card shall be visible on site at all times during construction. This means No Permit Card No Inspection. Permit shall be placed immediately adjacent to driveway in an easily accessible location at the building site and be clearly visible from the drive entrance. Building sites that are not visible from the road shall have their permit posted at the driveway. The permit shall be kept in good condition and protected from the weather. If the permit should become damaged or lost it is the contractor s responsibility to replace immediately. We suggest the following method to protect from weather (allow enough room so that the plastic envelope is accessible to leave inspection reports in).

4 Structure Numbering It will be necessary for permit applicants to obtain a structure address form Gordon County Emergency Management (706) prior to applying for a building Permit. Prior to calling the Emergency Management the applicant shall mark the centerline of their driveway near the roadway with a wooden stake as illustrated below. The stake shall contain the applicants name written with a permanent black marker pen and preferably topped with an orange flagging tape or ribbon such that it is easily distinguished at the site. Failure to properly mark your driveway may result in a delay in obtaining your address. Structures shall have its address posted in compliance with the following: before a certificate of occupancy will be issued. (1) If the mailbox is located on the same side of the street and adjacent to the driveway or curb cut, the number shall be affixed to the mailbox in letters two (2) inches in height or larger and of a color contrasting with the color of the mailbox. This section does not preclude an individual from also numbering the front entrance of the structure if so desired. (2) If the mailbox is not on the same side of the street and adjacent to the driveway or curb cut, the number shall be posted at two (2) locations: a. On the mailbox as prescribed by U.S. Postal Service regulations; and b. Either on the structure front if visible from the street or on an aboveground sign attached to a post or other object at the driveway or curb cut. The numbers shall be two (2) inches in height or larger and of a color contrasting with the color of the background. This section does not preclude an individual from also numbering the front entrance of his structure if so desired. (3) In the case that a building is served by two (2) or more driveways or curb cuts, the number shall be assigned and posted to the front entrance or driveway Driveways All new driveways and or modified driveways, must be inspected by the public works department. (706) Inspections Inspections will not be made unless necessary permits have been obtained and applicable licenses are currently active. You must call 24 hours in advance for inspections. Have your building permit number when you call. The Structure shall be accessible (Gates unlocked and entrances accessible i.e. do not pour concrete at driveways or entrances on the same day as you schedule inspection) and the structure shall be open. If the door and/or gate will be locked, provide scheduler with the location of the key (or combination) at the time of scheduling inspection. The following are required inspections: 1 st Footing (before pouring foundation) 2 nd Foundation (after blocks are laid or poured wall are in place and before beginning framing) Note: piers must be capped or top course filled with concrete grout. 3 rd Rough-in (after framing is complete & plumbing, electrical, heat/air and gas lines are roughed-in) Note: Do Not hang drywall or install exterior wall coverings prior to rough-in inspection. 4 th Final (when all work is complete and building is ready to be occupied) * Temporary power pole inspections should be combined with footing or foundation inspections. All work shall be ready for inspection by 8:00 a.m. on the morning that the inspection is scheduled. Requirement for Electrical Service Connection (Permanent Power) The following requirements shall be met when requesting electrical service to be connected to structures. 1. Interior wall coverings ( i.e. sheetrock, paneling, etc.) shall be in place. 2. The cover(s) shall be off of electrical devices (i.e. electrical panel(s) and service disconnect(s) switches). 3. The electrical panel shall be completely made up. All Main and branch circuit over-current devices (breakers) shall be installed. All feeder and branch circuit conductors shall be terminated on the proper over-current device and neutral and/or ground bar. 4. Electrical system shall be grounded and required bonding in place as required by code. 5. All branch circuit devices (i.e. switches, receptacles, light fixtures, etc.) shall be installed or conductors shall be terminated with wire nuts and stuffed back inside junction boxes in such a manner as to prevent injury to personal and damage to the conductors. 6. Structure must be secured (lockable), if breaker panel is in garage than garage door must be installed or door boarded-up. When inspection is preformed and the items listed above are not in compliance a re-inspection fee shall be accessed. 4

5 Connection of power does not authorize occupancy (occupancy consists of living, sleeping or moving of any personal property into the structure). Occupancy prior to passing a final inspection will result in immediate termination of power and the owner being issued a citation in the Magistrate Court of Gordon County. Re-Inspections Please be advised that the fee for re-inspections will be as follows: 1 st Re-inspection...$ nd Re-inspection...$50.00 Each additional re-inspection...$ Fees must be paid prior to re-inspection Scheduling for Inspection The following are procedures for scheduling your project for an inspection: 1. Inspections must be called into our office a minimum of one (1) day in advance. 2. You must have permit number and the name of the person or company to witch the permit was issued. Indicate the type of inspection you are requesting (example: footing, rough-in, etc.). Note anyone who answers your call in the building department can schedule your inspection. 3. Before beginning any work, permits must be purchased for the work involved. (Example: work for a concrete slab would typically require a building and plumbing permit before beginning work.) Requested inspections which do not have the proper permits will not be inspected until such time as proper permits have been obtained and a penalty will be assessed which will double the original permit fee. 4. Permit cards must be displayed at the front of the building site before an inspection will be preformed. Difficult to find sites such as those located well off the road should have permit cards displayed so that they are visible from the road. 5. It is necessary for us to emphasize quality over quantity of inspections which we perform. Therefore, we can not guarantee the time of day an inspection will be done nor can we guarantee that we can perform the inspection the day it is scheduled for. Please be patient. We will get to you as soon as we possibly can. It is important that your work be ready for inspection at any time on the day you have requested. Failure in this will result in the work being rejected. 6. When an inspection has been performed the pink copy of the inspection report will be left in the front of the permit card envelope at your site. The sheet will indicate the status of the inspection and any corrections to be made. You may call our office after 4:00 p.m. to determine the status of your inspection. Please do not call before this time because on one in the office will have that information. 7. It will be necessary for work which has been rejected to be rescheduled for re-inspection. Please make sure this work has been completed before calling for reinspection. Gas permit A separate gas permit is required if any appliances in the structure require gas (natural or LP) including Gas logs. Gas line have to be tested with pressurized air at the time of rough-in inspection. Footing Requirements for Gordon County This list is not exhaustive but contains general item that may cause a footing to be rejected. Refer to the International Building Code for all requirements. 1. Bottom of all footings must be 12 Minimum below grade level. 2. Two (2) runs of ½ (#4) rebar on metal chairs continuous at all bends, intersections and step downs are required. Joints in rebar shall be over-lapped a minimum of 12 and tied twice. A minimum of 3 of separation shall be provided between rebar & bottom of footing or bulkhead. 3. Concrete in footings shall be: Single-story dwelling: a min. of 6 deep and 16 wide Two-story dwelling: a min. of 8 deep and 18 wide Three-story dwelling a min. of 10 deep and 24 wide 4. All grade stakes shall be of metal material and in place. 5. All trenches for footings shall be clear of all roots, stumps, loose dirt and foreign debris. 6. All trenches for footings shall be clear of water and mud. When mud has been removed, bottom of footing shall be compacted. 7. All wood bulkheads, etc. shall be removed before foundation inspection. 8. If you anticipate rain, cover footings with plastic. This can greatly reduce damage caused by rain and may help eliminate a lot of reworking of footing. Concrete Slab Site Preparation 1. Remove all foreign Materials such as lumber form work, stakes. Tree stumps and other vegetation. This will limit the attraction of termites, insects and vermin. 2. Vegetation and top soil should be removed since such top soil is generally relatively loosely compacted or full of vegetation to such an extent as to allow soil settlement upon decay of the vegetation. 3. Concrete slabs placed on uncompacted fill or large quantities of foreign material can result in cracking of the floor slab. Fill 1. The fill beneath a concrete slab is required to be compacted. Fill depths shall not exceed 24 inches for clean sand or gravel and 8 inches for earth. 2. Clay and sand should be compacted to 95% of the maximum density. 3. All other fine grain, nonexpansive fills to 90% of the maximum density. 4. Compaction requirements for expanding soils must be determined from an engineering analysis. 5

6 5. Compaction may be performed using suitable hand or power equipment through the placement of fill material in 4 inch to 12 inch layers. In general, the compaction of fill is better regardless of the type of soil being compacted when the thickness of the layers in thinner. Base 1. Slabs need to be protected form the penetration of water and water vapor in order to prevent damage to interior finish materials and effectiveness of thermal insulation at the slab. 2. To provide a capillary stop for water rising through the soil and into the slab, a base course is placed over the fill for undisturbed soil. A base course is especially necessary when the site soil is other than gravel or clean sand. 3. A 4 inch base course shall be placed on the prepared sub grade when the slab is below grade. The base course shall consist of clean graded sand, gravel crushed stone or crushed blast-furnace slag passing a 3 inch sieve and retained on a ¼ inch sieve. 4. When required, vapor barriers of either singlemembranes or multi-layer membranes are acceptable, provided the vapor barrier is properly installed with 6 inch lapped joints and the barrier is not punctured during construction. Metal 1. When structural elements in floors are to be constructed of metal, details and specifications are considered to be beyond the scope of the code. The use of metal for structural elements in floors is permitted provided the adequacy of such materials is demonstrated by documentation by a professional engineer and presented to the building inspector. 6

7 IMPORTANT TELEPHONE NUMBERS WHILE BUILDING Building Department Building, Electrical, Plumbing, & Heating/Air permits Mobile home permits Soil & Erosion Land disturbing activities Planning & Development Zoning & Development City of Calhoun Utilities Water Meters Sewer Georgia Department of Transportation Driveways on a state route Electric Companies North Georgia Electric Membership Corp Georgia Power-Dalton Georgia Power-Cartersville Georgia Power-Rome Amicalola Emergency Management Agency Addresses Environmental Health Septic Systems Fire Prevention Fire Permits Public Works Driveway Inspections Driveway Tiles Utilities Protection Center 811 Under Ground Utilities Locations or

8 8

9 $6!31 4$6!31! $45 45#2 %31 6$536 #3# $6 ' $% & ' )*+, )*+, & ( &! " #" -.! & * *'*++*+ */ * *++*+ *0+*+* *+ **+*++ 9

10 1 '+B0: *+8 %9 ':;0+46?+ 36= *+ 6 *+ /+ 3 1 *: 3 " *+8 )>, 5" '+;7 /+; *7 *+ ; $ % &1A '+'+ A #A "5& 6 1 '+B0: *+8 %9 ':;0+46 <+3 7= *+ 6 1 *+ 3 " / */+ '+;7 /+;*7 0+;7 *+8)>, 5" '+;7 /+;* 7 *+ ; 7 10

11 11

12 12

13 13

Building Code Inspections and Fees

Building Code Inspections and Fees St. Mary s County Department of Land Use & Growth Management Customer Assistance Guide 22 Building Code Inspections and Fees May 10, 2014 This guide is intended to assist in the proper construction sequence

More information

Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements

Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements Charles County Government Planning and Growth Management P.O. Box 2150, La Plata, MD 20646 (301) 645-0692 Schedule

More information

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage: Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial

More information

RESIDENTIAL/COMMERCIAL

RESIDENTIAL/COMMERCIAL RESIDENTIAL/COMMERCIAL CONTRACTOR S INFORMATION MANUAL FOR City of Senatobia Disclaimer The residents or contractors using this information are responsible for complying with the applicable ICC Residential,

More information

Frequently Asked Questions

Frequently Asked Questions Warren County, Tennessee Building & Environmental Codes Department 201 Locust Street, Suite 6 McMinnville, TN, 37110 931.474.2633 Frequently Asked Questions What building codes are the Warren County Building

More information

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are: When is a Permit Required? The most common types of projects that require permits are: -New Houses or buildings -Room Additions or Expansions -Structural repairs, remodeling and alterations -Accessory

More information

Mobile Home Pre-Inspection Checklist

Mobile Home Pre-Inspection Checklist Mobile Home Pre-Inspection Checklist TWO (2) STEP INSPECTION PROCESS STEP ONE: CALL FOR THE FIRST INSPECTION WHEN THESE ITEMS ARE COMPLETE. 1. Septic tank installed and plumbing complete. (SEE PLUMBING

More information

Single Family Residential Building Permit Questions & Answers

Single Family Residential Building Permit Questions & Answers Single Family Residential Building Permit Questions & Answers Prepared by Dept. of Public Works Revised 07/01/13 200 East Park Street Edwardsville, IL 62025 (618) 692-7535 (618) 692-7505(Fax) Hours: Monday

More information

City of St. Charles Basement Finish or Remodel

City of St. Charles Basement Finish or Remodel City of St. Charles Basement Finish or Remodel Building & Code Enforcement Division 2 East Main Street St. Charles IL 60174 630.377.4406 (Office) 630.443.4638 (Fax) http://www.stcharlesil.gov Please direct

More information

The purpose of this document is to provide standards for persons requesting or subject to County building inspections.

The purpose of this document is to provide standards for persons requesting or subject to County building inspections. STANDARD OPERATING PROCEDURE BUILDING & SITE DEVELOPMENT Number: 310.1 Approval: Yves Khawam Effective Date: December 27, 2006 Subject: Requirements for County building inspections Page 1 of 7 1.0 PURPOSE:

More information

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264 BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used

More information

MULTI-FAMILY, COMMERCIAL, INDUSTRIAL, AS GOVERNED BY THE BC BUILDING CODE PART 3

MULTI-FAMILY, COMMERCIAL, INDUSTRIAL, AS GOVERNED BY THE BC BUILDING CODE PART 3 TOWN OF SIDNEY Multi-Family, Commercial, Industrial and Institutional Building Permit Guide The information provided is intended as a guide only and does not replace current bylaws and regulations. Complete

More information

BUILDING PERMIT SPECIFICATIONS

BUILDING PERMIT SPECIFICATIONS BUILDING PERMIT SPECIFICATIONS The below noted requirements are based upon La Plata County Building Code. These specifications are not intended as a complete set of requirements, but are intended to provide

More information

BUILDING SAFETY UNIT

BUILDING SAFETY UNIT POLICY Page 1 of 5 SUBMITTAL REQUIREMENTS FOR ONE AND TWO FAMILY DWELLINGS, ADDITIONS AND RENOVATIONS All submittals shall be site specific and designed to the provisions of the 2012 International Residential

More information

CITY OF SELMA, TEXAS Inspection Checklist: Commercial

CITY OF SELMA, TEXAS Inspection Checklist: Commercial Rev Y71004 The Permits and Inspections Department welcomes you to the City of Selma. The following information is provided to you as guidance through the inspection process. The City of Selma provides

More information

VILLAGE OF BETHALTO RESIDENTIAL BUILDING PERMIT APPLICATION AND INFORMATION

VILLAGE OF BETHALTO RESIDENTIAL BUILDING PERMIT APPLICATION AND INFORMATION VILLAGE OF BETHALTO RESIDENTIAL BUILDING PERMIT APPLICATION AND INFORMATION VILLAGE OF BETHALTO RESIDENTIAL BUILDING PERMIT INFORMATION / REQUIRMENTS I. APPLICATION REQUIREMENTS 1. GENERAL APPLICATION

More information

Residential Building Permits Information

Residential Building Permits Information City of Bonham Building Department 514 Chestnut St. Bonham, Texas 75418 OFFICE: (903) 583-7555 FAX: (903)583-5761 Residential Building Permits Information Application for Permits: To apply for a permit,

More information

PLEASE NOTE. For more information concerning the history of these regulations, please see the Table of Regulations.

PLEASE NOTE. For more information concerning the history of these regulations, please see the Table of Regulations. PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this regulation, current to August 1, 2013. It is intended for information and reference purposes only.

More information

VILLAGE OF BETHALTO COMMERCIAL BUILDING PERMIT APPLICATION

VILLAGE OF BETHALTO COMMERCIAL BUILDING PERMIT APPLICATION VILLAGE OF BETHALTO COMMERCIAL BUILDING PERMIT APPLICATION VILLAGE OF BETHALTO COMMERICAL BUILDING PERMIT INFORMATION / REQUIRMENTS I. APPLICATION REQUIREMENTS 1. GENERAL APPLICATION REQUIREMENTS A building

More information

The City of Basehor, Kansas

The City of Basehor, Kansas The City of Basehor, Kansas Residential and Miscellaneous Permits This list provides general information regarding permit requirements for various residential construction and maintenance activities. The

More information

Homeowner Information Guide Electrical Safety. British Columbia Safety Authority

Homeowner Information Guide Electrical Safety. British Columbia Safety Authority Homeowner Information Guide Electrical Safety British Columbia Safety Authority The following information should be carefully reviewed before performing any electrical work. The information contained in

More information

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003) NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:

More information

Vision Home Inspection

Vision Home Inspection Vision Home Inspection 324 Rams Run Shepherdsville KY 40165-7877 Inspector: James McFadden Property Inspection Report Client(s): Property address: Inspection date: View report summary This report is the

More information

2. What building projects are exempted? (permit not required)

2. What building projects are exempted? (permit not required) BUILDING AND SAFETY DEPARTMENT 1. What building projects require a permit? Following is a list of projects that require building permits based on Appendix chapter 1 of the California Building Code and

More information

Residential Foundations and Basements

Residential Foundations and Basements Residential Foundations and Basements Disclaimer All of the following information is based on the 2006 International Residential Code with Kentucky Amendments. As some information is paraphrased, article

More information

Home Inspection Report

Home Inspection Report 4949 Brownsboro Rd Suite 293 Louisville, KY 40223 (502) 414-1440 tripleainspections@gmail.com Inspected By: William Carter, HI-1956 Home Inspection Report Prepared For: Edward Cullen Property Address:

More information

City of Mandeville. Guidelines for Construction and Development

City of Mandeville. Guidelines for Construction and Development City of Mandeville Guidelines for Construction and Development 1 Application for Permitting Requirements The following items must accompany any application for a permit for the construction of single family

More information

Upper Southampton Township Department of Licenses and Inspections 939 Street Rd. Southampton, Pa. 18966 Phone: 215-322-9700 Fax: 215-322-5842

Upper Southampton Township Department of Licenses and Inspections 939 Street Rd. Southampton, Pa. 18966 Phone: 215-322-9700 Fax: 215-322-5842 Upper Southampton Township Department of Licenses and Inspections 939 Street Rd. Southampton, Pa. 18966 Phone: 215-322-9700 Fax: 215-322-5842 APPLICATION for ZONING and BUILDING PERMIT APPLICATION INSTRUCTIONS:

More information

PLAN REVIEW SERVICES CONSTRUCTION DOCUMENTS NECESSARY FOR A THOROUGH PLAN REVIEW

PLAN REVIEW SERVICES CONSTRUCTION DOCUMENTS NECESSARY FOR A THOROUGH PLAN REVIEW CONSTRUCTION DOCUMENTS NECESSARY FOR A THOROUGH PLAN REVIEW PRELIMINARY BUILDING REVIEW two sets of the following: Architectural/engineering design development drawings indicating size of the building,

More information

MOBILE HOME SERVICE REQUIREMENTS GAS

MOBILE HOME SERVICE REQUIREMENTS GAS ELECTRIC AND GAS 1.0 INDEX 1.0 INDEX 2.0 PURPOSE 3.0 GENERAL 4.0 REFERENCE MATERIAL 5.0 TYPICAL UNDERGROUND UTILITY LAYOUT 6.0 METER PAD DETAILS 7.0 GENERAL INSTALLATION PROCEDURES 8.0 PEDESTAL SPECIFICATIONS

More information

Botetourt County, Virginia. Frequently Asked Questions

Botetourt County, Virginia. Frequently Asked Questions Botetourt County, Virginia Development Services Construction Compliance Frequently Asked Questions Permits... 2 When is a permit required?... 2 When is a permit NOT required?... 2 Who may apply for a permit?...

More information

www.citiesinspection.com October 5, 2015 Dear Client,

www.citiesinspection.com October 5, 2015 Dear Client, www.citiesinspection.com October 5, 2015 Dear Client, On 9/14/2015, Cities Inspection Service, Inc. completed a building inspection of the property located at 123 Oak Street, Someplace, Minnesota for you.

More information

REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION

REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION RESIDENTIAL: REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION 2 COMPLETE SETS OF PRINTS WITH ENGINEERS STAMP ON FOUNDATION PLAN INCLUDING ELECTRICAL, PLUMBING, ETC. SITE PLAN SHOWING HOUSE LOCATION

More information

BOROUGH OF NATIONAL PARK APPLICATION FOR A CERTIFICATE OF OCCUPANCY FOR CHANGE OF OCCUPANCY ADDRESS OF PROPERTY FOR INSPECTION CURRENT OWNER

BOROUGH OF NATIONAL PARK APPLICATION FOR A CERTIFICATE OF OCCUPANCY FOR CHANGE OF OCCUPANCY ADDRESS OF PROPERTY FOR INSPECTION CURRENT OWNER BOROUGH OF NATIONAL PARK APPLICATION FOR A CERTIFICATE OF OCCUPANCY FOR CHANGE OF OCCUPANCY ADDRESS OF PROPERTY FOR INSPECTION # BLOCK LOT VACANT YES NO CURRENT OWNER NAME ADDRESS TELEPHONE # PROSPECTIVE

More information

Bureau Veritas Contact Information

Bureau Veritas Contact Information Bureau Veritas Contact Information Permit Submittal The permit documents and fees will be submitted to the city. Submittal documents should be complete to expedite plan review and permit issuance. Please

More information

BUILDING DEPARTMENT 8748 W. 82 nd Place - Justice, IL 60458 Phone: (708) 458-2130 Fax: (708) 458-3207

BUILDING DEPARTMENT 8748 W. 82 nd Place - Justice, IL 60458 Phone: (708) 458-2130 Fax: (708) 458-3207 BUILDING DEPARTMENT 8748 W. 82 nd Place - Justice, IL 60458 Phone: (708) 458-2130 Fax: (708) 458-3207 SELF EVALUATION CHECKLIST FOR RESIDENTIAL AND MULTI-FAMILY DWELLING INSPECTIONS The attached checklist

More information

BUILDING PERMIT APPLICATION APPLICABLE TO CITY LIMITS AND ETJ CHAPTER 18, General

BUILDING PERMIT APPLICATION APPLICABLE TO CITY LIMITS AND ETJ CHAPTER 18, General BUILDING PERMIT APPLICATION APPLICABLE TO CITY LIMITS AND ETJ CHAPTER 18, General Property Address: Property Owner: Lot: Block: Subdivision: Lot Size: Scope of Work: Note: Please attach copies of all general

More information

STATE OF SOUTH CAROLINA RESIDENTIAL PROPERTY CONDITION DISCLOSURE STATEMENT

STATE OF SOUTH CAROLINA RESIDENTIAL PROPERTY CONDITION DISCLOSURE STATEMENT STATE OF SOUTH CAROLINA RESIDENTIAL PROPERTY CONDITION DISCLOSURE STATEMENT The South Carolina Code of Laws (Title 27, Chapter 50, Article 1) requires that an owner of residential real property (single

More information

Residential Plan Routing Information

Residential Plan Routing Information Residential Plan Routing Information BUILDING INSPECTIONS 800 4th AVENUE EAST WEST FARGO, ND 58078 PHONE: 701-433-5480 The building Inspection s Department receives and issues all applications for building

More information

PREPARED DATE: SIGNATURE AND SEAL INSPECTION REPORT PREPARED BY: PRINT NAME: REGISTRATION NUMBER: MAILING ADDRESS:

PREPARED DATE: SIGNATURE AND SEAL INSPECTION REPORT PREPARED BY: PRINT NAME: REGISTRATION NUMBER: MAILING ADDRESS: CU PROCESS NUMBER FOLIO NUMBER Financial Institution Information Local Agent: Address: Phone: Space above reserved for use of recording office INSPECTION CERTIFICATE OF USE REPORT FOR SINGLE FAMILY RESIDENCE,

More information

The Lambton County Homeowner's BUILDING PERMIT INFORMATION GUIDE

The Lambton County Homeowner's BUILDING PERMIT INFORMATION GUIDE The Lambton County Homeowner's BUILDING PERMIT INFORMATION GUIDE BUILDING SERVICES DEPARTMENT 789 Broadway Street, Box 3000 Wyoming, ON N0N 1T0 Telephone: 519 845-0801 Toll-free: 1-866-324-6912 Fax: 519

More information

MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS

MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS 01. SAFETY INSPECTION of service equipment at FPL Power Source 02. Construction GFI power outlets (Temp Pole for Construction) 03. 90 day temporary power

More information

PERMIT APPLICATION FORM SELECT ALL THAT APPLY: BUILDING DRIVEWAY ELECTRICAL PLUMBING HEATING DEMOLITION SIGN MOBILE HOME

PERMIT APPLICATION FORM SELECT ALL THAT APPLY: BUILDING DRIVEWAY ELECTRICAL PLUMBING HEATING DEMOLITION SIGN MOBILE HOME PERMIT # TOWN OF ASHLAND, NEW HAMPSHIRE 20 HIGHLAND STREET PO BOX 517 ASHLAND, NH 03217 603-968-4432 FAX 603-968-3776 www.ashland.nh.gov PERMIT APPLICATION FORM SELECT ALL THAT APPLY: BUILDING DRIVEWAY

More information

Physical Address/Intersection: Name of Project: Within a NFIP 100/500yr Floodzone:

Physical Address/Intersection: Name of Project: Within a NFIP 100/500yr Floodzone: Choctaw Date Recorded: Permit # RESIDENTIAL - BUILDING Permit APPLICATION Physical Address/Intersection: Name of Project: Within a NFIP 100/500yr Floodzone: YES NO Sec., Township, Range/Subdivision: Acres/Block:

More information

City of La Vernia 102 E. Chihuahua Street, La Vernia, Texas 78121 Phone: (830)779-4541 Fax: (830) 253-1198 cityoflavernia@lavernia-tx.

City of La Vernia 102 E. Chihuahua Street, La Vernia, Texas 78121 Phone: (830)779-4541 Fax: (830) 253-1198 cityoflavernia@lavernia-tx. cityoflavernia@lavernia-tx.gov Commercial New/Remodel Building Requirements This document is not meant to modify any Federal or State laws or City Ordinances. It is intended to be informative and to be

More information

Elevating Your House. Introduction CHAPTER 5

Elevating Your House. Introduction CHAPTER 5 CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,

More information

Uniform Construction Code (UCC) Manufactured Homes. Modular Homes. Building Permit Application Package

Uniform Construction Code (UCC) Manufactured Homes. Modular Homes. Building Permit Application Package Uniform Construction Code (UCC) Manufactured Homes (Single-Wide, Double-Wide) Modular Homes Building Permit Application Package Per the Uniform Construction Code (UCC) all structures must be built per

More information

Gas Meter Clearances and Service Installation Requirements

Gas Meter Clearances and Service Installation Requirements March 2015 Gas Meter Clearances and Service Installation Requirements Builder/Owner/Developer Requirements Call PSE s Customer Construction Services 1-888-321-7779 or visit PSE.com/CustomerConstruction

More information

CONSTRUCTION PERMITS AND CERTIFICATES A Helpful Guide

CONSTRUCTION PERMITS AND CERTIFICATES A Helpful Guide CONSTRUCTION PERMITS AND CERTIFICATES A Helpful Guide Monroe Township Municipal Government Construction Office 125 Virginia Avenue Williamstown NJ 08094 856-728-9800 x 222 856-629-2143 FAX 2 P a g e APPLYING

More information

ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS:

ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: Chapter 12 of the Burlington Code of ordinances allows owner occupants of single family homes to do their own wiring if they choose. If you choose to

More information

MOBILE HOME LAW. Revised November 2001

MOBILE HOME LAW. Revised November 2001 MOBILE HOME LAW Revised November 2001 TABLE OF CONTENTS: SECTION 1: SECTION 2: SECTION 3: SECTION 4: SECTION 5: SECTION 6: SECTION 7: SECTION 8: SECTION 9: SECTION 10: SECTION 11: SECTION 12: INTENT DEFINITIONS

More information

#506 New Multi-Family Buildings & Additions Plan Intake Submittal Checklist

#506 New Multi-Family Buildings & Additions Plan Intake Submittal Checklist #506 New Multi-Family Buildings & Additions Plan Intake Submittal Checklist Case #: Date: Project Name: Site Address: Application Submittal Building permit applications and plans can be submitted to the

More information

2010 Residential Water Heater Replacement Check List

2010 Residential Water Heater Replacement Check List 2010 Residential Water Heater Replacement Check List The intent of this check list is to provide installers a general reference for the enforcement of code requirements in the Greater San Diego Area. This

More information

Building Permit Application Packet. BUILDING CODES Adopted by La Plata County For Enforcement In The Unincorporated Areas Of La Plata County

Building Permit Application Packet. BUILDING CODES Adopted by La Plata County For Enforcement In The Unincorporated Areas Of La Plata County Building Permit Application Packet The purpose of Building Codes is to establish the minimum requirements to safe guard the public health, safety and general welfare through structural strength, means

More information

KITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS

KITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS St. Louis County Department of Public Works Division of Code Enforcement KITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS This guideline is intended to provide the homeowner/contractor with the

More information

HOMEOWNER S PERMIT GUIDE

HOMEOWNER S PERMIT GUIDE HOMEOWNER S PERMIT GUIDE WHEN IS A PERMIT REQUIRED? Department of Development and Permits 306 Cedar Road, City Hall 2 nd Floor P.O. Box 15225 Chesapeake, VA 23328 Phone: (757) 382-6018 Fax: (757) 382-8448

More information

City of West Chicago Community Development Department 475 Main Street, West Chicago, IL 60185 Phone: (630) 293-2200 x 131 / Fax: (630) 293-1257

City of West Chicago Community Development Department 475 Main Street, West Chicago, IL 60185 Phone: (630) 293-2200 x 131 / Fax: (630) 293-1257 City of West Chicago Community Development Department 475 Main Street, West Chicago, IL 60185 Phone: (630) 293-2200 x 131 / Fax: (630) 293-1257 APPLICATION FOR DEMOLITION PERMIT Permit Number: Date Received:

More information

EL LAGO BUILDING DEPARTMENT PERMIT ISSUANCE PROCEDURES As of February 20, 2013

EL LAGO BUILDING DEPARTMENT PERMIT ISSUANCE PROCEDURES As of February 20, 2013 PERMIT AUTHORIZATION EL LAGO BUILDING DEPARTMENT PERMIT ISSUANCE PROCEDURES As of February 20, 2013 El Lago ordinances require the issuance of building permits as a method of enforcing code minimums, ensuring

More information

SWIMMING POOL, SPA, & HOT TUB GUIDELINES

SWIMMING POOL, SPA, & HOT TUB GUIDELINES SWIMMING POOL, SPA, & HOT TUB GUIDELINES Pool permit cost is based on the total value of the project. See Permit Fee Schedule Table 1A. A. Adopted construction codes and installation requirements 1. 2015

More information

Arapahoe County Residential Water Heater Installation and Inspection Guide

Arapahoe County Residential Water Heater Installation and Inspection Guide Arapahoe County Residential Water Heater Installation and Inspection Guide The attached handout is designed to be a general permit submittal and inspection guide covering most installation instances, however

More information

Reference Guide for Obtaining Permits and Utility Services For New Construction

Reference Guide for Obtaining Permits and Utility Services For New Construction Reference Guide for Obtaining Permits and Utility Services For New Construction (Revised 04-2012) Table of Contents City Offices Telephone Numbers...1 Application for Utilities...2 Building Permits New

More information

RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS

RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS Johnson County Building Officials Association January 2008 Residential Foundation Guideline Foundation designs for one-and two-family dwellings may use

More information

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME 1 THE BUILDING PROCESS The focus of Woodland Homes building department is Quality, Service and Predictability. Through

More information

Plumbing Installations. A homeowner guide to the City of Winnipeg plumbing requirements for a single-family dwelling

Plumbing Installations. A homeowner guide to the City of Winnipeg plumbing requirements for a single-family dwelling Plumbing Installations A homeowner guide to the City of Winnipeg plumbing requirements for a single-family dwelling February 2001 contents General Information 3 Inspection 4 New Drain and Vent Installations

More information

City of Mt. Juliet Public Works

City of Mt. Juliet Public Works City of Mt. Juliet Public Works Building Department City of Mt. Juliet Public Works Department Building Codes REQUIREMENTS FOR PERMIT LOT & SUBDIVISION (Please provide a copy of Liability Insurance and

More information

C I T Y O F P E A R S A L L

C I T Y O F P E A R S A L L The Largest City Between San Antonio and Laredo COMMUNITY DEVELOPMENT C I T Y O F P E A R S A L L A Business-Friendly, Family-Oriented Community Building Department Application Information (Please read

More information

BUILDING/PLUMBING PERMIT APPLICATION REQUIREMENTS

BUILDING/PLUMBING PERMIT APPLICATION REQUIREMENTS BUILDING BROCHURE BUILDING/PLUMBING PERMIT APPLICATION REQUIREMENTS To ALTER, ADD TO, MOVE or CONSTRUCT a NEW HOME, CARPORT, GARAGE, SUNDECK, or other Building or Structure within the Regional District

More information

Inspection Report Atlanta Strip Mall Commercial Building Property Address:

Inspection Report Atlanta Strip Mall Commercial Building Property Address: Page 1 of 25 Inspection Report Atlanta Strip Mall Property Address: Smyrna GA 30082 Page 2 of 25 South East Building Consultants Ray Thoroman Serving the entire State of Georgia 6 678-410-3005 Page 3 of

More information

Town House 11265 Center Highway North Huntingdon, PA 15642

Town House 11265 Center Highway North Huntingdon, PA 15642 APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House

More information

Building Information Packet

Building Information Packet Code Enforcement Department 882-9225 Building Information Packet The following information has been compiled to help you as a homeowner or contractor with the various steps and requirements for a building

More information

Chapter 3 Pre-Installation, Foundations and Piers

Chapter 3 Pre-Installation, Foundations and Piers Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory

More information

Applications for building permits will not be reviewed until all of the required information has been submitted.

Applications for building permits will not be reviewed until all of the required information has been submitted. NOTICE: Applications for building permits will not be reviewed until all of the required information has been submitted. Once all items are submitted a minimum of ten (10) working days are required to

More information

Does Wall Township require an inspection by the building department on resale of a home?

Does Wall Township require an inspection by the building department on resale of a home? Selling your home Does Wall Township require an inspection by the building department on resale of a home? No. We do not require a Certificate of Continued Occupancy on the resale of home. A Smoke Detector,

More information

Single Family Residential Basement Finish

Single Family Residential Basement Finish How to Use This Guide Building Guide Pottawattamie County Planning & Development Department Building & Safety Division Single Family Residential Basement Finish Provide two (2) sets of plans and complete

More information

HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com

HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com, 2011 TO: Mr. REF: CONDITION OF PROPERTY SURVEY Dear Mr. : At your request,

More information

NAVAJO COUNTY ADDENDA & ADDITIONS TO THE INTERNATIONAL BUILDING CODES. Public Works/Planning & Zoning Building & Safety AMENDED (05-02-05)

NAVAJO COUNTY ADDENDA & ADDITIONS TO THE INTERNATIONAL BUILDING CODES. Public Works/Planning & Zoning Building & Safety AMENDED (05-02-05) NAVAJO COUNTY ADDENDA & ADDITIONS TO THE INTERNATIONAL BUILDING CODES Public Works/Planning & Zoning Building & Safety AMENDED (05-02-05) NAVAJO COUNTY GOVERNMENTAL COMPLEX P.O. BOX 668 HOLBROOK, ARIZONA

More information

INFORMATION BULLETIN NO.

INFORMATION BULLETIN NO. Requirements for Plans Review Submittal, One- and Two-Family Dwellings INFORMATION BULLETIN NO. 100 (June 26, 1998, Revised March 26, 2009) City Planning & Development - Development Services City of Kansas

More information

EFFECTIVE FEBRUARY 2014. note: drainage permit required to call for a dampproof inspection

EFFECTIVE FEBRUARY 2014. note: drainage permit required to call for a dampproof inspection EFFECTIVE FEBRUARY 2014 note: drainage permit required to call for a dampproof inspection 1. ROOF DRAINS/DECK DRAINS (INTERIOR ) All roof and deck drains within the perimeter of the building shall be APPROVED

More information

Owner: Phone # Mailing Address: Contractor: Phone # Fax #

Owner: Phone # Mailing Address: Contractor: Phone # Fax # CITY OF EASTON BUREAU OF CODES AND INSPECTIONS 2 nd Floor, 123 South Third Street, Easton, PA 18042 phone (610) 250-6724 - fax (610) 250-6607 email codes@easton-pa.gov PERMIT APPLICATION Owner: Phone #

More information

INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1

INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 City of Cotati Building Division 201 W. Sierra Ave. Cotati, CA 94931 707 665-3637 Fax 792-4604 INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 Any PV system on a new structures should be included

More information

Commercial Construction Information Packet

Commercial Construction Information Packet Commercial Construction Information Packet Inspection Requirements, Notes and Listings 9/2009 TABLE OF CONTENTS General Requirements.............................................................1 General

More information

METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D

METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D 12 - ELECTRIC SERVICE HANDBOOK SECTION D METER REQUIREMENTS This chapter gives you information on Central Lincoln s metering requirements. It's divided into three sections: General requirements This section

More information

REHABILITATION OF MOBILE HOMES R4 34 606

REHABILITATION OF MOBILE HOMES R4 34 606 REHABILITATION OF MOBILE HOMES R4 34 606 PURPOSE The purpose of this program is to provide minimum safety standards for homes manufactured before the implementation of the HUD Manufactured Home Construction

More information

State of Connecticut Department of Public Health RADON PROGRAM

State of Connecticut Department of Public Health RADON PROGRAM State of Connecticut Department of Public Health RADON PROGRAM Scope The Connecticut Department of Public Health (DPH) Radon Program is providing this information for contractors who decide to build radon

More information

WHEN IS A PERMIT REQUIRED?

WHEN IS A PERMIT REQUIRED? WHEN IS A PERMIT REQUIRED? Any owner, builder, contractor, or other authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure,

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

Questions and Answers for Heating and A/C Contractors

Questions and Answers for Heating and A/C Contractors 1. How do we accomplish grounding of furnaces and / or water heaters on two wire circuits? 250.134 Equipment Fastened in Place or Connected by Permanent Wiring Methods (Fixed) Grounding. Unless grounded

More information

Village of Airmont APPLICATION FOR BUILDING PERMIT INSTRUCTIONS

Village of Airmont APPLICATION FOR BUILDING PERMIT INSTRUCTIONS Village of Airmont BUILDING AND ZONING DEPARTMENT 251 CHERRY LANE, AIRMONT, NEW YORK Mailing Address: P.O. BOX 578, TALLMAN, NEW YORK 10982 Telephone: 845-369-8813 Fax: 845-357-8307 Website: www.airmont.org

More information

Additions and Alterations

Additions and Alterations Additions and Alterations Addition and alteration construction is a miscellaneous grouping of home improvement and renovation projects that are generally geared toward the enhancement of an existing principal

More information

Building Construction and Development in Norristown: A User s Guide to the Land Development and Building Permit Process 1/25/11

Building Construction and Development in Norristown: A User s Guide to the Land Development and Building Permit Process 1/25/11 Building Construction and Development in Norristown: A User s Guide to the Land Development and Building Permit Process 1/25/11 Introduction Constructing new commercial or residential space can be a complicated

More information

Concord Building Department Frequently Asked Questions

Concord Building Department Frequently Asked Questions Does Concord have its own Building codes? No, we utilize the 8th Edition of the Massachusetts State Building code for one and two family dwellings, multi-family dwellings, and Commercial Buildings. When

More information

Underground Commercial Electric Service

Underground Commercial Electric Service Underground Commercial Electric Service SCANA Corporation 2013 Revised: June 2013 Table of Contents SECTION PAGE I. Specification and Requirements 2 A. General B. Definition of Terms C. Company and Developer

More information

City of Hill Country Village Residential Construction/Development Packet

City of Hill Country Village Residential Construction/Development Packet City of Hill Country Village Residential Construction/Development Packet City Hall has developed this Construction/Development Packet to consolidate instructions, the permits required, and zoning rules

More information

Residential Deck Safety, Construction, and Repair

Residential Deck Safety, Construction, and Repair Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the

More information

How To Make A House Safe

How To Make A House Safe 1 RESIDENTIAL Screen Enclosures Orange County Residential Code Compliance Alternative design method for screen enclosures R301.2.1.1.3 PLAN REVIEW Engineered plans must state that the Alternative Design

More information

Crawford Inspection Services C.C.B. # 76914 www.crawfordinspections.com

Crawford Inspection Services C.C.B. # 76914 www.crawfordinspections.com Crawford Inspection Services C.C.B. # 76914 www.crawfordinspections.com Portland Area PO Box 665 West Linn, OR 97068 Ph: (503) 650-6957 Salem Area 5434 River Rd. N; #192 Keizer, OR 97303 Ph: (503) 362-5809

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property

2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property 2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical

More information

CITY OF BERKELEY BUILDING PERMIT DETAILED CHECKLIST

CITY OF BERKELEY BUILDING PERMIT DETAILED CHECKLIST CITY OF BERKELEY DETAILED CHECKLIST This checklist will assist you in preparing plans for submittal with a building permit application. Alterations, additions and remodeling projects may not require all

More information