A. General Provisions of the Contract and applicable requirements of Division 1 and this Section apply to the work specified in this section.

Size: px
Start display at page:

Download "A. General Provisions of the Contract and applicable requirements of Division 1 and this Section apply to the work specified in this section."

Transcription

1 PART 1 GENERAL 1.1 SCOPE A. Provide and adjust all vibration isolation components and materials required to isolate the building structure and occupied spaces from vibrating equipment as specified by this section. 1.2 RELATED DOCUMENTS A. General Provisions of the Contract and applicable requirements of Division 1 and this Section apply to the work specified in this section. 1.3 SUBMITTALS A. Submit complete product data to the architect in accordance with the General Provisions of the Specifications before any materials are delivered to the job site. B. Submit to the Acoustical Engineer shop drawings showing the following information so that isolation system can be checked for compliance with the specifications: 1. Sizes, placement and type of isolators, seismic snubbers, and total base mass (weight) if it is a concrete inertia base. 2. Weight distribution on isolators. 3. Isolator schedule to show size, type, load, and static deflection of each isolator. 4. Number and color-code of each isolator to show its location. 5. Isolator adjustment procedures for setting and adjusting the isolation devices so that the isolator mount selections can be checked for compliance with the specification. C. When manufacturers provide equipment bases, submit calculations verifying factory base stiffness is equal or equivalent to stiffness of base specified in the Vibration Isolation Schedule. 1.4 EQUIPMENT VIBRATION ISOLATION A. The installing contractor to furnish a balanced set of vibration isolators for each piece of equipment listed herein. B. Isolation work to include, but not necessarily be limited to, the following: 1. Inertia base frames in conjunction with isolation. 2. Penetration isolation of conduit, wiring, and cable trays through walls, floors or ceilings. 3. Flexible connections to equipment. C. Installing contractor to provide any components or materials not specifically mentioned herein, but necessary to the proper vibration isolation of the equipment. 1.5 ACCEPTABLE MANUFACTURERS A. Amber Booth B. Mason Industries, Inc. C. Kinetics Corporation D. Approved equal, meeting all of the conditions and requirements specified herein. 1.6 CONTRACTOR RESPONSIBILITY A. All vibration isolation devices, including auxiliary steel bases and pouring forms, shall be designed and furnished by a single manufacturer or supplier. B. Installing contractor to furnish a balanced set of vibration isolators for each piece of equipment listed in the Vibration Isolation Schedule MAHLUM PERMIT SET Issue Date: 11 SEPTEMBER 2015 PAGE 1 OF 6

2 C. Installing contractor to procure from the vibration isolation manufacturer instructions and procedures on how to install and adjust vibration isolators. D. Adequately restrain all equipment to resist seismic forces. Design and select restraint devices to meet seismic requirements as defined in the latest issue of the Uniform Building Code and applicable state and local codes in accordance with project area Seismic Zone with a minimum restraint capability of 1.0 g. E. Coordinate with the structural engineer to ensure mounting attachment points for seismic restrained springs and seismic snubbers will withstand forces generated from the maximum acceleration rating of the restrained springs and snubbers. F. In addition, the contractor shall have the following responsibilities: 1. Select, install, adjust, and verify the performance of vibration isolators that will meet the requirements given on the plans or in the specifications. 2. Bring to the Acoustical Engineer s attention any equipment specified for the project that is not covered in the Vibration Isolation Schedule herein. 3. Provide whatever assistance necessary to ensure correct installation and adjustment of the isolators. G. Changes or additions necessary to meet the requirements given on the plans or in the specifications are to be made without any expense to the owner. 1.7 QUALITY ASSURANCE A. Isolators shall operate in the linear portion of their load-versus-deflection curve. B. The ratio of lateral to vertical isolator stiffness to be not less than 0.9 nor greater than 1.5. C. Bring to the attention of the Acoustical Engineer any discrepancies between this Section and other related documents. PART 2 PRODUCTS 2.1 MATERIALS A. Where exposed to the atmosphere, all steel to be finished with dry powder coating for corrosion protection; hardware (bolts and capscrews) to be Zinc electroplated; springs to be dry powder coated. 2.2 ISOLATORS A. Type N-2: Neoprene Seismic Mount 1. Captive neoprene mounting shall consist of a steel housing with a captive steel insert embedded in neoprene to prevent contact between the housing and the central threaded insert. 2. Isolator shall contain a cast-in tapped steel load plate to permit bolting to the supported equipment. 3. Snubbing to limit deflection in upward, downward, and horizontal directions. Capacity to withstand not less than 1.0 g without noticeable deformation. 4. Isolators shall be selected to provide the minimum operating static deflection tabulated in the Vibration Isolation Schedule, while not exceeding the published load capacity for the isolator used. 5. Isolator shall have a minimum deflection of 0.15 inch. 6. Each isolator shall be color-coded to identify the load capacity. 7. Acceptable Products: a. Model RCA, RBA by Mason b. Model RQ by Kinetics B. Type N-4: Neoprene Pad 2015 MAHLUM PERMIT SET Issue Date: 11 SEPTEMBER 2015 PAGE 2 OF 6

3 1. Isolator shall consist of 5/16-inch to 3/8-inch thick molded neoprene. 2. Pad to either be a ribbed or waffle type construction. 3. Isolator shall have a 40 to 50 durometer rating. 4. Isolator shall be loaded to limit surface pressure to a maximum of 50 psi. 5. Isolator to be equipped with a steel plate bonded to the neoprene pad if required for proper load distribution. 6. Acceptable Products: a. Model W, WM by Mason b. Model NPD, NG by Kinetics C. Type N-5: Neoprene Pad 1. Isolator shall consist of 3/4-inch thick molded neoprene. 2. Pad to either be a ribbed or waffle type construction. 3. Isolator shall have a 50-durometer rating. 4. Isolator shall be loaded to limit surface pressure to a maximum of 50 psi. 5. Isolator to be equipped with a steel plate bonded to the neoprene pad if required for proper load distribution. 6. Acceptable Products: a. Model Super W by Mason D. Type H-1: Spring Hanger 1. Hanger to consist of a combination of a steel spring and a fiberglass or neoprene isolator placed in series and encased in a welded steel bracket. 2. Isolator to have minimum operating static deflection as tabulated in the Vibration Isolation Schedule. 3. Isolator shall be designed to carry five (5) times overload without failure. 4. Spring shall have minimum additional travel to solid equal to 50% of rated deflection. 5. Isolator to be installed to allow up to fifteen (15) degrees of rod misalignment without metal-to-metal contact or other isolation short circuit. 6. Acceptable Products: a. Model 30N by Mason b. Model SRH by Kinetics c. Model BSRA by Amber Booth 2.3 MISCELLANEOUS SUPPORT A. Type WB-1: Neoprene washers and bushings 1. Washer-bushing shall be manufactured of bridge bearing neoprene. 2. Washer-bushing maximum loading not to exceed 1000 psi. 3. Washer-bushing to be used such that direct contact between bolt and equipment is eliminated. 4. Acceptable Products: a. Model HG by Mason B. Type CS-1: Cushion Sleeve 1. Fiberglass sleeve sized to fit pipe. 2. Acceptable Products: a. Owens Corning Fiberglass 25 ASJ/SSL Service Jacket, or approved equal. b. Johns Manville Micro-Lok Fiberglass Pipe Insulation, or approved equal. C. Type CVI-1: Individual conduit 1. Isolate conduit from structure using type CS-1 sleeve MAHLUM PERMIT SET Issue Date: 11 SEPTEMBER 2015 PAGE 3 OF 6

4 D. Type CVI-2: Conduit grouped on unistrut 1. Isolate unistrut from structure using type N-5 neoprene pads with WB-1 neoprene washer bushings. 2. Alternatively, the unistrut can be rigidly attached to structure if each conduit is isolated from the unistrut with type CS-1 sleeve. 2.4 MISCELLANEOUS PRODUCTS A. Acoustical Insulation 1. Fiberglass a. 1/2 to 6 thick low density unfaced fiberglass batts. b. Acceptable Products: c. Standard by Owens Corning 2. Mineral Fiber a. 2" to 3" thick mineral fiber insulation batts. b. Acceptable Products: c. "Thermafiber" by U.S. Gypsum Company, or equal - fire rated. B. Acoustical Sealant shall meet the following requirements: 1. Sealant shall be a paintable, non-hardening, non-bleeding, non-drying, resilient caulk. 2. Acceptable Products: a. Acoustical Sealant by U.S. Gypsum Company b. Acoustical Sealant BA-98 by Pecora Corporation c. Fire Barrier 2000" by 3M Vibration Control Systems - fire rated d. Non Sag Firestop Caulk (Part # AA-529) by Nelson - fire rated e. CP 606 by Hilti - fire rated f. Tremco Acoustical Sealant - LEED Approved C. Intumescent Firestop Pillow PART 3 EXECUTION 3.1 GENERAL 1. The firestop pillow shall consist of a monolithic (one piece) core that is encapsulated on all sides by a flexible intumescent coating. 2. The firestop pillow shall not contain any loose fiber fill. 3. The pillow shall be UL Classified and/or FM Systems Approved and tested to the requirements of ASTM E814 (UL1479). 4. Acceptable Products: a. SpecSeal Firestop Pillow by STI A. Isolate Electrical equipment from the building structure by means of vibration isolators as scheduled herein and on the Drawings. If there is a conflict between the drawings and the Vibration Isolation Schedule herein, bring this conflict to the Architect and/or the Acoustical Engineer s attention. B. Install isolation systems (isolators, bases, and related hardware) in accordance with the manufacturer s written Installation Instructions. C. Isolated equipment mounting systems must permit equipment motion in all directions. D. Adjust or provide additional resilient restraints to flexibly limit equipment lateral motion to 1/2 inch during startup and operation MAHLUM PERMIT SET Issue Date: 11 SEPTEMBER 2015 PAGE 4 OF 6

5 E. Prior to startup, clean out all foreign matter between base, isolator, equipment, and mounting surfaces. Verify that there are no rigid connections between equipment and building structure that degrade the vibration isolation systems specified herein. F. Align isolator rods to clear the isolator housing. G. Unless otherwise directed by this document, suspend isolators with the isolator hanger housing attached to or hung as close as possible to the structure. H. Do not use wall, floor, or ceiling penetrations to support conduit, wiring, or cable trays. Support conduit, wiring, or cable trays just prior to and just after the penetration, so that the penetrating element is centered in penetration. I. Do not allow contact between isolated conduit or cable trays and non-isolated equipment or structure. Isolated conduit or cable trays include the isolated portions of their supports or hangers. J. Bring to the Acoustical Engineer s attention prior to installation any conflicts with other trades which will result in unavoidable rigid contact with equipment or piping as described herein, due to inadequate space or other unforeseen conditions. Corrective work necessitated by conflicts after installation will be at the responsible contractor s expense. K. Size anchoring bolts to isolators or snubbers withstand seismic lateral shear and tensile failure and isolate bolts from direct contact with the structure using Type WB-1 isolator. 3.2 ISOLATION OF EQUIPMENT AND PANELS AT PARTITIONS ADJACENT TO OCCUPIED SPACES A. In all electrical rooms, isolate electrical equipment, panels, and devices mounted to partitions adjacent to offices and classrooms as follows: 1. Isolate the supports for equipment mounted to the floor with N-5/WB-1 isolators. 2. Isolate the supports for equipment mounted to the wall with N-2 isolators. 3. Isolate cable and conduit mounted to the partition with CVI-1/CVI-2 isolators. 4. Different sections of conduit or cable requiring the same type of isolator with the same minimum static deflection may be supported on a common Unistrut support that is isolated with the same type of isolator. 3.3 ELECTRICAL EQUIPMENT ISOLATION A. Conduit Isolation 1. Use flexible electrical conduit to isolate all electrical connections to vibration isolated equipment. 2. Do not use conduit clamps or hangers at the flex conduit. The first point of contact with any wall should be past the flex conduit. 3. Flex conduit shall be no shorter than 3 feet in length. 3.4 PENETRATION ISOLATION A. Scope 1. Penetration requirements identified in this section will be applied to all walls, floors, and ceilings of the following rooms: B. Method a. ELECTRICAL ROOMS CONTAINING TRANSFORMERS 1. Isolate all conduit and cable tray penetrations as follows: 2. Conduit Penetration Isolation at Fire-Rated and Non-Fire Rated Partitions For Conduit Greater Than 2 Inches in Diameter 2015 MAHLUM PERMIT SET Issue Date: 11 SEPTEMBER 2015 PAGE 5 OF 6

6 a. Provide a sheet metal (22 gauge) sleeve to cover the entire perimeter of a 1 inch to 1-1/2 inch (1/2 inch to 3/4 inch on each side) oversized penetration cut. b. If conduit or cable penetrates a double or staggered stud wall, use a separate sleeve at each side of the wall. There shall be no sleeve connection between walls. c. Plaster or caulk sleeve to the wall, ceiling, or floor, to ensure an airtight seal. d. Pack the gap between the penetrating conduit or cable and the sleeve with Acoustical Insulation and seal airtight on both sides of the wall, floor, or ceiling with an outer layer of Resilient Sealant. e. Do not use wall, floor, or ceiling penetrations to support conduit or cable. Support conduit or cable just prior to and just after the penetration so that it is centered in the penetration. 3. Conduit Penetration Isolation at Fire-Rated and Non-Fire Rated Partitions For Conduit Less Than or Equal to 2 Inches in Diameter a. Oversize penetration by 3/8 inch on each side. b. Seal gap airtight with Acoustical Sealant. c. Do not use wall, floor, or ceiling penetrations to support conduit or cable. Support conduit or cable just prior to and just after the penetration so that it is centered in the penetration. 4. Cable Tray Penetration Isolation at Non-Fire Rated and Fire-Rated partitions a. Provide a sheet metal (22 gauge) box to cover the entire perimeter of a 1 inch to 1-1/2 inch (1/2 inch to 3/4 inch on each side) oversized penetration cut. The box shall extend 2 feet from each side of the wall. b. Plaster or caulk the sheet metal box to the wall, ceiling, or floor, to ensure an airtight seal. c. If the cable tray penetrates a double or staggered stud wall, use a separate box at each side of the wall. Ensure there are no sleeve connections between the walls. d. Pack the gap between the penetrating cable tray and the box with Intumescent Firestop Pillows for the full length of the sheet metal box. C. Use the above penetration treatment regardless of the existence of external insulation. Size penetration large enough to pack additional Acoustical Insulation and apply Acoustical Sealant between the external insulation and the sheet metal sleeve. 3.5 MISCELLANEOUS A. Coordinate with other trades and structural engineer to ensure mounting attachment points for seismic restrained springs and seismic snubbers called out in this specification will withstand forces generated from the maximum acceleration rating of the restrained springs and snubbers. B. Any and all electrical equipment within mechanical or electrical rooms not listed in the schedules above, shall be separated from contact with the structure via isolator Type N-4, plus neoprene washers and bushings Type WB-1, if equipment is bolted to structure. Size pads and use metal plates or washers to limit surface pressure on neoprene to 45 psi. END OF SECTION 2015 MAHLUM PERMIT SET Issue Date: 11 SEPTEMBER 2015 PAGE 6 OF 6

SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes seismic restraints and other earthquake-damage-reduction measures for electrical

More information

PART 1 GENERAL 1.1 SECTION INCLUDES

PART 1 GENERAL 1.1 SECTION INCLUDES J-1 Section 09110 Long Form Specification INTERIOR METAL STUD FRAMING This section includes lightweight, usually 0.036 inch (0.9 mm) thick or lighter, non-axial load bearing metal stud framing including

More information

Tremco Fire Protection Systems Group Technical Bulletin

Tremco Fire Protection Systems Group Technical Bulletin Compartmentalization products and design play a key role in protecting lives and property from fire. Understanding the tools and techniques available for firestopping is of utmost importance to designers,

More information

SECTION 23 05 29 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

SECTION 23 05 29 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT SECTION 23 05 29 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Pipe hangers and supports. 2. Hanger rods. 3. Inserts. 4. Flashing. 5. Equipment

More information

Chapter 36 - STRAW BALE CONSTRUCTION SECTION 3601 - PURPOSE. SECTION 3602 - SCOPE. SECTION 3603 - DEFINITIONS.

Chapter 36 - STRAW BALE CONSTRUCTION SECTION 3601 - PURPOSE. SECTION 3602 - SCOPE. SECTION 3603 - DEFINITIONS. Austin City Code - Volume II TITLE 25 LAND DEVELOPMENT\CHAPTER 25-12 TECHNICAL CODES\ARTICLE 1: UNIFORM BUILDING CODE\25-12-3 LOCAL AMENDMENTS TO THE BUILDING CODE Chapter 36 - STRAW BALE CONSTRUCTION

More information

FIRESTOPPING & SMOKE SEALS

FIRESTOPPING & SMOKE SEALS SPECIFICATION SECTION 07 84 00 FIRESTOPPING & SMOKE SEALS 1 GENERAL 1.1 SECTION INCLUDES 1.1.1 Comply with Division 1, General Requirements and Documents referred to therein. 1.1.2 It is the intent of

More information

SECTION 15140 - PIPE HANGERS AND SUPPORTS

SECTION 15140 - PIPE HANGERS AND SUPPORTS Part I - GENERAL 1.01 SECTION INCLUDES A. The work covered under this section consists of the furnishing of all necessary labor, supervision, materials, equipment, and services to completely execute the

More information

SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary to perform and complete such

More information

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here)

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here) SECTION 08332 COILING COUNTER DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Coiling Metal Counter Doors. B. Coiling Counter Fire Doors. 1.2

More information

HOUSTON COMMUNITY COLLEGE HCC ALIEF CAMPUS MAIN BUILDING, FIRST, SECOND & FOURTH FLOORS RENOVATION ISSUE DATE: 10.17.12

HOUSTON COMMUNITY COLLEGE HCC ALIEF CAMPUS MAIN BUILDING, FIRST, SECOND & FOURTH FLOORS RENOVATION ISSUE DATE: 10.17.12 SECTION 27 05 26 - GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes grounding and bonding products, design requirements and installation for communications

More information

City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures

City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures SECTION 7201 - PURPOSE The purpose of this appendix chapter is to establish minimum prescriptive standards

More information

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders INTRODUCTORY INFORMATION TABLE OF CONTENTS 00 0101 PROJECT TITLE PAGE PROCUREMENT REQUIREMENTS (PROJECT MANUAL) Tab A - Invitation for Bids Tab B - Instructions to Bidders Tab C Bid Form for General Bids

More information

Lightweight Partition Design for Residential and Commercial Buildings

Lightweight Partition Design for Residential and Commercial Buildings Lightweight Partition Design for Residential and Commercial Buildings Stanley D. Gatland II, CertainTeed Corporation, Valley Forge, Pennsylvania Guidelines are presented for the design and proper installation

More information

SECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT

SECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT SECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT PART 1 - GENERAL 1.1 DESCRIPTION A. The Work specified in this Section consists of designing, furnishing and installing factory-assembled

More information

Fiberglas, Exterior Wall Thermal Insulation

Fiberglas, Exterior Wall Thermal Insulation PROJECT ENGINEER RESPONSIBILITY: This is a general specification guide, intended to be used by experienced construction professionals, in conjunction with good construction practice and professional judgment.

More information

Installation Details. D1 General D2 Walls D3 Ceilings D4 Reference. D Installation Details

Installation Details. D1 General D2 Walls D3 Ceilings D4 Reference. D Installation Details D Installation Details D1 General D2 Walls D3 Ceilings D4 Reference D Installation Details D Contents D1 General Installation and Fastening Sequence for Steel Studs D1.1 Fastener Selection D1.3 D2 Walls

More information

Catalog Number Pillow Type Pillow Size

Catalog Number Pillow Type Pillow Size FSA-1 3M Fire Barrier Self-Locking Pillows Extremely easy to install - saves time and labor Easy removal and fully reusable - with no blocking or fusing of materials No cutting required, no left over debris

More information

CABLE TRENCH INSTALLATION GUIDE

CABLE TRENCH INSTALLATION GUIDE 1.0 INDEX 1.0 INDEX 2.0 PURPOSE 3.0 GENERAL INFORMATION 4.0 PLANNING INFORMATION 5.0 CREW INFORMATION 6.0 CONTRACTOR INFORMATION 7.0 PRECASTED/ POURED-IN-PLACE TRENCH DRAWINGS 2.0 PURPOSE This standard

More information

SUGGESTED SPECIFICATION EXHAUST SYSTEM SILENCER, FLEX CONNECTOR, INSULATION BLANKETS, WALL / ROOF THIMBLES

SUGGESTED SPECIFICATION EXHAUST SYSTEM SILENCER, FLEX CONNECTOR, INSULATION BLANKETS, WALL / ROOF THIMBLES SUGGESTED SPECIFICATION EXHAUST SYSTEM SILENCER, FLEX CONNECTOR, INSULATION BLANKETS, WALL / ROOF THIMBLES 4121 N.W. 37 th Street, Lincoln, NE 68524 Telephone (402) 470-2627 Fax (404) 470-2410 www.gtexhaust.com

More information

CERTIFICATE OF APPROVAL No CF 5055 ARABIAN VERMICULITE INDUSTRIES

CERTIFICATE OF APPROVAL No CF 5055 ARABIAN VERMICULITE INDUSTRIES CERTIFICATE OF APPROVAL No CF 5055 This is to certify that, in accordance with TS00 General Requirements for Certification of Fire Protection Products The undermentioned products of 1 st Industrial Area,

More information

SERIES ASM NEOPRENE/EPMD FLANGED SINGLE SPHERE CONNECTOR CONNECTORS. Pressures to 225 PSIG (15.51 barg) Temperatures to 230ºF (110ºC)

SERIES ASM NEOPRENE/EPMD FLANGED SINGLE SPHERE CONNECTOR CONNECTORS. Pressures to 225 PSIG (15.51 barg) Temperatures to 230ºF (110ºC) APPLICATIONS Process Industry Weak Acids Alkalies Compressed Air Pulp & Paper MODELS ASM - Flanged Connection OPTIONS Control Rods Oil & Gas Water & Waste Pump suction & discharge Sea water Chemical lines

More information

VA25014B0516 VA CINCINNATI PROJECT NO. 539-328 INPATIENT BED TOWER ADDITION (4 TH AND 5 TH FLOORS) SECTION 09 29 00 GYPSUM BOARD

VA25014B0516 VA CINCINNATI PROJECT NO. 539-328 INPATIENT BED TOWER ADDITION (4 TH AND 5 TH FLOORS) SECTION 09 29 00 GYPSUM BOARD SECTION 09 29 00 GYPSUM BOARD PART 1 - GENERAL 1.1 DESCRIPTION This section specifies installation and finishing of gypsum board, vapor retarder and air and moisture barrrier. 1.2 RELATED WORK A. Installation

More information

ACOUSTIC ISOLATION DETAILS

ACOUSTIC ISOLATION DETAILS ACOUSTIC ISOLATION DETAILS Icelandic National Concert and Conference Center Reykjavík, Iceland January 5, 2007 Artec Report No. 7742 Artec Project No. 3760 Distribution: Stefán Hermannsson East Harbour

More information

DIVISION 8, METAL SOUND CONTROL DOOR ASSEMBLIES PART 1 GENERAL 1.1 RELATED DOCUMENTS

DIVISION 8, METAL SOUND CONTROL DOOR ASSEMBLIES PART 1 GENERAL 1.1 RELATED DOCUMENTS DIVISION 8, METAL SOUND CONTROL DOOR ASSEMBLIES PART 1 GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the contract, including general and supplementary conditions and other Division 1

More information

RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS

RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS The following guidelines are intended to assist with the permit acquisition process with regard to Plumbing Alterations. Not all information, or additional

More information

Mark Cramer Inspection Services, Inc.

Mark Cramer Inspection Services, Inc. Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction

More information

SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront

SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront PART 1 GENERAL 1.01 Work Included SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS System 402 Flush-Glazed Screw Spline Storefront A. Furnish and install aluminum architectural storefront system

More information

Flamesafe Firestopping Products. Firestopping Products. http://flamesafe.rectorseal.com

Flamesafe Firestopping Products. Firestopping Products. http://flamesafe.rectorseal.com Flamesafe Firestopping Products Firestopping Products http://flamesafe.rectorseal.com Engineering Tested By Fire RectorSeal Firestopping Products Since the birth of the firestopping industry almost three

More information

Guide for SOLID CONCRETE BLOCK SEALS

Guide for SOLID CONCRETE BLOCK SEALS Guide for SOLID CONCRETE BLOCK SEALS July, 2006 Mine Safety and Health Administration SOLID CONCRETE BLOCK SEAL Formersection 30 CFR 75.335(a)(1) specifies requirements for seals constructed using solid

More information

Fire Barrier Duct Wrap 15A

Fire Barrier Duct Wrap 15A 3 Fire Barrier Duct Wrap 15A Commerical Kitchen Grease Duct Fire Protection System Product Data and Installation Instructions Compliance 1998 Edition Complies with International Mechanical Code Complies

More information

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS 1.0 DESIGN 1.1 Scope of Work 1.1.1 This work shall consist of furnishing Isolation Bearings and installing Isolation Bearing Assemblies at the locations

More information

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM Chapter 9 STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM 9.1 BACKGROUND Steel is widely used in the construction of multi-storey buildings. However, steel construction is seldom used and is traditionally

More information

SECTION 05 7360 ALUMINUM HANDRAIL AND RAILING SYSTEMS WITH DECORATIVE METAL PANEL INFILLS

SECTION 05 7360 ALUMINUM HANDRAIL AND RAILING SYSTEMS WITH DECORATIVE METAL PANEL INFILLS 1 SECTION 05 7360 ALUMINUM HANDRAIL AND RAILING SYSTEMS WITH DECORATIVE METAL PANEL INFILLS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and

More information

EcoTouch Insulation with PureFiber Technology

EcoTouch Insulation with PureFiber Technology PROJECT ENGINEER RESPONSIBILITY: This is a general specification guide, intended to be used by experienced construction professionals, in conjunction with good construction practice and professional judgment.

More information

ACOUSTIC ISOLATION DETAILS

ACOUSTIC ISOLATION DETAILS ACOUSTIC ISOLATION DETAILS Icelandic National Concert and Conference Center Reykjavík, Iceland January 5, 2007 Artec Report No. 7742 Artec Project No. 3760 Distribution: Stefán Hermannsson East Harbour

More information

FireWall. High performance fireresistant. FireWall. www.british-gypsum.com

FireWall. High performance fireresistant. FireWall. www.british-gypsum.com FireWall FireWall High performance fireresistant wall system FireWall is a non-loadbearing wall which provides up to 240 minutes fire resistance. It is used in certain ground floor basement situations

More information

SECTION 230529 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

SECTION 230529 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT SECTION 230529 - PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Steel pipe hangers and supports. 2. Metal framing systems. 3. Thermal-hanger shield inserts. 4. Fastener systems.

More information

INSTALLATION OF A BAY WINDOW

INSTALLATION OF A BAY WINDOW INSTALLATION OF A BAY WINDOW Installation of a Bay Window These instructions relate to the replacement of an existing bay window or replacement of a straight window with a new bay window, in an opening

More information

Preformed Metal Roofing and Siding

Preformed Metal Roofing and Siding Page -1-1. GENERAL 1.1. Description This specification along with the drawings covers the furnishing of all material, products, equipment, accessories, tools, services, transportation, labor and supervision

More information

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel

More information

GUIDELINES FOR INSTALLATION OF AIR CONDITIONING UNITS 174-180 PHILLIP STREET, SYDNEY

GUIDELINES FOR INSTALLATION OF AIR CONDITIONING UNITS 174-180 PHILLIP STREET, SYDNEY GUIDELINES FOR INSTALLATION OF AIR CONDITIONING UNITS 174-180 PHILLIP STREET, SYDNEY July 2008 1.0 SCOPE These guidelines describe the way in which air conditioning units shall be installed or replaced

More information

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona for Earthen Material and Straw Bale Structures SECTION 70 - GENERAL "APPENDIX CHAPTER 7 - EARTHEN MATERIAL STRUCTURES 70. Purpose. The purpose of this chapter is to establish minimum standards of safety

More information

Spring-Flex Hangers Series SH/RSH

Spring-Flex Hangers Series SH/RSH Bulletin No. SH/14 Spring-Flex Hangers Series SH/RSH Two Basic Designs Effective Isolation of Noise and Vibration Loads to 5,000 pounds Static Deflections to 5 inches Quickly and Easily Installed Color

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

TABLE OF CONTENTS. Roof Decks 172 B, BA, BV Deck N, NA Deck. Form Decks 174.6 FD,.6 FDV Deck 1.0 FD, 1.0 FDV Deck 1.5 FD Deck 2.0 FD Deck 3.

TABLE OF CONTENTS. Roof Decks 172 B, BA, BV Deck N, NA Deck. Form Decks 174.6 FD,.6 FDV Deck 1.0 FD, 1.0 FDV Deck 1.5 FD Deck 2.0 FD Deck 3. Pages identified with the NMBS Logo as shown above, have been produced by NMBS to assist specifiers and consumers in the application of New Millennium Building Systems Deck products. Pages identified with

More information

The National Armored Cable Manufacturers Association Presents. Installation Standard for Types AC and MC Cables

The National Armored Cable Manufacturers Association Presents. Installation Standard for Types AC and MC Cables The National Armored Cable Manufacturers Association Presents Installation Standard for Types AC and MC Cables An ANSI Standard Original document jointly produced by NECA and NACMA as Standard for Installing

More information

Vibration Isolation Products. Spring Isolators. Isolation Hangers. Thrust Restraints. Flexible Connectors. Isolation Bases. Rooftop Isolation Curbs

Vibration Isolation Products. Spring Isolators. Isolation Hangers. Thrust Restraints. Flexible Connectors. Isolation Bases. Rooftop Isolation Curbs Spring Isolators Isolation Hangers Thrust Restraints Flexible Connectors Isolation Bases Rooftop Isolation Curbs Neoprene Isolators Fiberglass Isolators Air Mounts Seismic and Wind Restraint Isolators,

More information

SEISMIC and WIND Restraint Products. 55-years of product innovation and manufacturing excellence

SEISMIC and WIND Restraint Products. 55-years of product innovation and manufacturing excellence SEISMIC and WIND Restraint Products 55-years of product innovation and manufacturing excellence Why are Seismic and Wind Restraint Needed? For hospitals and healthcare facilities, the damaging effects

More information

MRI RF SHIELDING DESIGN

MRI RF SHIELDING DESIGN MRI RF SHIELDING DESIGN Nelco s MRI RF Shielding is specifically designed for the MRI industry. Our engineers have developed a shielded enclosure made entirely of nonmagnetic materials that is unsurpassed

More information

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION SPECIFICATION EO-5023 REVISION 3 MARCH 2003 REQUIREMENTS FOR

More information

Product Information Sheet

Product Information Sheet Distributed by Thermal Products Company, Inc. Product Information Sheet FyreWrap Elite 1.5 Duct Insulation Air Distribution System (ADS Ducts) Introduction Unifrax s FyreWrap Elite 1.5 Duct Insulation

More information

March 14, 2007. Installation of Bay, Bow and Garden Windows

March 14, 2007. Installation of Bay, Bow and Garden Windows March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed

More information

MASON JACK-UP FLOOR SLAB SYSTEM and eliminate the cost and need for:

MASON JACK-UP FLOOR SLAB SYSTEM and eliminate the cost and need for: When you need a floating floor to dramatically Increase your Sound Transmission Class and Impact Noise Rating BULLETIN ACS-102-3.1 Why not use the MASON JACK-UP FLOOR SLAB SYSTEM and eliminate the cost

More information

SECTION 16402 UNDERGROUND ELECTRIC SERVICE

SECTION 16402 UNDERGROUND ELECTRIC SERVICE SECTION 16402 UNDERGROUND ELECTRIC SERVICE PART 1 GENERAL 1.1 SUMMARY A. Description of System 1. Furnish all labor, materials, and equipment for below grade work external to buildings as required, and

More information

SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS

SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS Display hidden notes to specifier by using Tools / Options / View / Hidden Text. On newer versions of Microsoft Word

More information

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 MINORITY AND WOMEN S BUSINESS ENTERPRISE PARTICIPATION

More information

PART E SPECIFICATIONS

PART E SPECIFICATIONS PART E SPECIFICATIONS Page 1 of 5 PART E - SPECIFICATIONS GENERAL E1. APPLICABLE SPECIFICATIONS, STANDARD DETAILS AND DRAWINGS E1.1 The City of Winnipeg Works and Operations Division Standard Construction

More information

SECTION 22 LIGHTNING PROTECTION SYSTEM

SECTION 22 LIGHTNING PROTECTION SYSTEM SECTION 22 LIGHTNING PROTECTION SYSTEM 22.01 SCOPE: A. These Specifications shall form a part of the Contract Documents and shall govern construction work for all buildings to be built or modified for

More information

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations. DIVISION 16 ELECTRICAL SECTION 16100 - ELECTRICAL PART 1 - GENERAL SCOPE All electrical work as shown on the drawings and as necessary to provide a complete electrical system. Include primary service,

More information

Complete Firestop Systems Guide

Complete Firestop Systems Guide Complete Firestop Systems Guide Passive Fire Protection products are tested to various test requirements, please check with your local building code for the requirements within your municipality. Firestop

More information

ENGINEERING SPECIFICATION FIBERGRATE MOLDED GRATING. January 24, 2014 06610-1

ENGINEERING SPECIFICATION FIBERGRATE MOLDED GRATING. January 24, 2014 06610-1 ENGINEERING SPECIFICATION FIBERGRATE MOLDED GRATING January 24, 2014 06610-1 SECTION 06610 FIBERGLASS REINFORCED PLASTICS (FRP) FABRICATIONS MOLDED GRATING PART 1 - GENERAL 1.1 SCOPE OF WORK A. The CONTRACTOR

More information

Specifications. Preformed Metal Wall and Roof Panels. Alcoa Cladding Systems Manufacturing Plant 100 Industrial Boulevard Eastman, Georgia 31023

Specifications. Preformed Metal Wall and Roof Panels. Alcoa Cladding Systems Manufacturing Plant 100 Industrial Boulevard Eastman, Georgia 31023 Specifications Preformed Metal Wall and Roof Panels Alcoa Cladding Systems Manufacturing Plant 100 Industrial Boulevard Eastman, Georgia 31023 Section 07410 Preformed Metal Wall and Roof Panels Structural

More information

4 Installation Requirements

4 Installation Requirements 4 Installation Requirements 9 4.1 Code Reference The authority having jurisdiction should be referenced to determine what law, ordinance or code shall apply in the use of flexible duct. Ducts conforming

More information

ONTRAC WIRE MESH CABLE TRAY SYSTEM

ONTRAC WIRE MESH CABLE TRAY SYSTEM P R O D U C T D ATA S H E E T ONTRAC WIRE MESH CABLE TRAY SYSTEM K E Y F E AT U R E S Available in two styles: Shaped and Standard Tray Easy to use pathway solution that supports large quantities of network

More information

HVAC Air Duct Leakage. Eli P. Howard, III Group Director Technical Resources SMACNA

HVAC Air Duct Leakage. Eli P. Howard, III Group Director Technical Resources SMACNA HVAC Air Duct Leakage Eli P. Howard, III Group Director Technical Resources SMACNA Key Variables that Affect the Amount of Leakage Static Pressure Amount of Duct Openings in the Duct Surface Seams, Joints,

More information

GUIDELINE ON THROUGH-PENETRATION FIRESTOPPING

GUIDELINE ON THROUGH-PENETRATION FIRESTOPPING GUIDELINE ON THROUGH-PENETRATION FIRESTOPPING SECOND EDITION AUGUST 2007 SHEET METAL AND AIR CONDITIONING CONTRACTORS NATIONAL ASSOCIATION, INC. 4201 Lafayette Center Drive Chantilly, VA 20151-1209 www.smacna.org

More information

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage: Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial

More information

PANELIZED HOME INSTALLATION GUIDELINE

PANELIZED HOME INSTALLATION GUIDELINE PANELIZED HOME INSTALLATION GUIDELINE A typical home package will be constructed of Snap-N-Lock Insulated Panels clad with steel skins. 4" panels will be used for the walls, and 6" panels for the roof.

More information

State of Connecticut Department of Public Health RADON PROGRAM

State of Connecticut Department of Public Health RADON PROGRAM State of Connecticut Department of Public Health RADON PROGRAM Scope The Connecticut Department of Public Health (DPH) Radon Program is providing this information for contractors who decide to build radon

More information

Assessing Curtain Walls

Assessing Curtain Walls Assessing Curtain Walls Considerations and Best Practices Paul E Beers GCI Consultants, LLC pbeers@gciconsultants.com What is a Curtain Wall System? A curtain wall system is an outer covering of a building

More information

Chapter 3 Pre-Installation, Foundations and Piers

Chapter 3 Pre-Installation, Foundations and Piers Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory

More information

Packaged Terminal Air Conditioner Wall Sleeve Installation

Packaged Terminal Air Conditioner Wall Sleeve Installation Installation & Maintenance Data IM 1196 Group: PTAC Part Number: 910141799 Date: October 2013 Packaged Terminal Air Conditioner Installation x 42" PGAN with Top-Mounted Hydronic Heat Note: Installation

More information

INTER-NOISE 2006 3-6 DECEMBER 2006 HONOLULU, HAWAII, USA

INTER-NOISE 2006 3-6 DECEMBER 2006 HONOLULU, HAWAII, USA INTER-NOISE 2006 3-6 DECEMBER 2006 HONOLULU, HAWAII, USA An effective new approach to isolate plumbing stub-outs in residential construction Jeffrey P. Kwolkoski, P.E., INCE Bd. Cert. a D. L. Adams Associates,

More information

INSTALLING SEISMIC RESTRAINTS FOR MECHANICAL EQUIPMENT

INSTALLING SEISMIC RESTRAINTS FOR MECHANICAL EQUIPMENT VISCMA 412/August 2014 INSTALLING SEISMIC RESTRAINTS FOR MECHANICAL EQUIPMENT August 2014 Developed originally by the Vibration Isolation and Seismic Control Manufacturers Association under a cooperative

More information

Gypsum Board Systems Manual

Gypsum Board Systems Manual CertainTeed Gypsum Board Systems Manual Fire Resistance and Sound Control Design Manual Division 09 GYPSUM BOARD SYSTEMS MANUAL TABLE OF CONTENTS Introduction General Fire Resistance...1 Sound Control...3

More information

Rockwool Flexi Insulation Application Guide

Rockwool Flexi Insulation Application Guide Pitched roof Rafters InterMediate floors INTERNAL partitions external Framed walls separating floors Separating Walls Rockwool Flexi Insulation Application Guide Ground floor The perfect fit for any framed

More information

James M. Pleasants Company

James M. Pleasants Company James M. Pleasants Company SUBMITTAL DATA GAINESVILLE MECHANICAL DECEMBER 20, 2013 PROJECT: GSU: J-183 HUMANITIES LAW BLDG. QUOTE NO:12116 ENGINEER: STEVENS & WILKINSON GASKETED PLATE HEAT EXCHANGER Tag:

More information

This section applies to the design and installation of transformers.

This section applies to the design and installation of transformers. ELECTRICAL: TRANSFORMERS BASIS OF DESIGN This section applies to the design and installation of transformers. Design Criteria 13.8-kV equipment shall be 15-kV class. Coordinate with short-circuit studies

More information

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table

More information

STANDARD SPECIFICATIONS SECTION 05500 METAL FABRICATIONS

STANDARD SPECIFICATIONS SECTION 05500 METAL FABRICATIONS STANDARD SPECIFICATIONS SECTION 05500 METAL FABRICATIONS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for providing metal fabricated items like castings, gratings, hatchways, ladders,

More information

Cable Installation Accessories. Cable Hoisting and Attachment. Snap-In Hangers. SnapStak Hangers

Cable Installation Accessories. Cable Hoisting and Attachment. Snap-In Hangers. SnapStak Hangers SnapStak Hangers New design increases stack height SnapStak hangers have become the industry standard for maximizing space utilization on crowded towers and now that utility is further expanded with the

More information

GYPSUM AREA SEPARATION FIREWALLS GA-620-2011

GYPSUM AREA SEPARATION FIREWALLS GA-620-2011 GYPSUM AREA SEPARATION FIREWALLS GA-620-2011 GA-620-2011 Copyright 2011 Gypsum Association All rights reserved. Printed in U.S.A. Characteristics, properties, or performance of materials or systems herein

More information

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with

More information

H-Stud Area Separation Wall System

H-Stud Area Separation Wall System 12 TH EDITION 09 21 16.33/NGC H-Stud Area Separation Wall System 09 21 16.33 139 H-STUD AREA SEPARATION WALL SYSTEM The fire-protection of gypsum-based Area Separation Walls is demonstrated in dramatic

More information

WASHROOM UPGRADE SIR CHARLES TUPPER BUILDING 2250 RIVERSIDE DRIVE, OTTAWA, ON SIR CHARLES TUPPER BUILDING A0.0 COVER SHEET / DRAWING LIST

WASHROOM UPGRADE SIR CHARLES TUPPER BUILDING 2250 RIVERSIDE DRIVE, OTTAWA, ON SIR CHARLES TUPPER BUILDING A0.0 COVER SHEET / DRAWING LIST 0 RIVERSIDE DRIVE, OTTAWA, ON A0.0 COVER SHEET / DRAWING LIST A0. LEGEND AND GENERAL NOTES A0. GENERAL NOTES A0. GENERAL NOTES A0. TYPICAL WASHROOM WALL/SINK SECTION A0. DETAIL - CONTROL JOINT A0. DETAIL

More information

Retardants Inc. The Decision You Make May Save A Life! 123 Columbia Court North Suite 201 Chaska, MN 55318

Retardants Inc. The Decision You Make May Save A Life! 123 Columbia Court North Suite 201 Chaska, MN 55318 Fire Barrier Moldable Putty+ Pads 123 Columbia Court North Suite 201 Chaska, MN 55318 952-448-7377 FAX:952-448-2613 e-mail: info@fireretardantsinc.com Visit Our Web Site at www.fireretardantsinc.com Protecting

More information

Value Engineering Considerations for Cast Iron Soil Pipe and PVC in Commercial Sanitary and Storm Drainage Applications

Value Engineering Considerations for Cast Iron Soil Pipe and PVC in Commercial Sanitary and Storm Drainage Applications Value Engineering Considerations for Cast Iron Soil Pipe and PVC in Commercial Sanitary and Storm Drainage Applications BR-VEC (2-14-13) The Correct Material for the Correct Application Plumbing design

More information

necessary for years of satisfactory service. SmartBlock insulating form concrete walls share the

necessary for years of satisfactory service. SmartBlock insulating form concrete walls share the Chapter 7 PLUMBING AND ELECTRICAL 7.1 Introduction to Plumbing and Electrical Consideration of support services such as plumbing and electrical systems from the preliminary schematics phase through final

More information

SECTION 23 81 03 - PACKAGED ROOFTOP AIR CONDITIONING UNITS NON-CUSTOM

SECTION 23 81 03 - PACKAGED ROOFTOP AIR CONDITIONING UNITS NON-CUSTOM SECTION 23 81 03 - PACKAGED ROOFTOP AIR CONDITIONING UNITS NON-CUSTOM PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Packaged rooftop air conditioning unit (5 tons and smaller). 2. Roof curb. 1.2

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE

SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE PART 1: GENERAL 1.01 SECTION INCLUDES PVC pressure pipe and fabricated fittings in nominal sizes 4-inches through 12-inches with cast iron pipe equivalent

More information

ST. MONICA FOOD PANTRY HOUSTON, TEXAS

ST. MONICA FOOD PANTRY HOUSTON, TEXAS PROJECT MANUAL FOR ST. MONICA FOOD PANTRY HOUSTON, TEXAS OWNER: ST. MONICA CATHOLIC CHURCH 8421 W. MONTGOMERY ROAD HOUSTON, TEXAS 77088 ARCHITECT: C SIX ARCHITECTURE, LLC 4606 F.M. 1960 WEST, STE 400 HOUSTON,

More information

SECTION 17400 ACCESS CONTROL SYSTEM. CONDITIONS OF THE CONTRACT AND DIVISION 1, as applicable, apply to this Section.

SECTION 17400 ACCESS CONTROL SYSTEM. CONDITIONS OF THE CONTRACT AND DIVISION 1, as applicable, apply to this Section. SECTION 17400 ACCESS CONTROL SYSTEM CONDITIONS OF THE CONTRACT AND DIVISION 1, as applicable, apply to this Section. PART 1 - GENERAL 1.1 RELATED WORK A. 16060 Grounding and Bonding B. 16070 Electrical

More information

FEDERAL EMERGENCY MANAGEMENT AGENCY FEMA 413/January 2004 INSTALLING SEISMIC RESTRAINTS FOR ELECTRICAL EQUIPMENT

FEDERAL EMERGENCY MANAGEMENT AGENCY FEMA 413/January 2004 INSTALLING SEISMIC RESTRAINTS FOR ELECTRICAL EQUIPMENT FEDERAL EMERGENCY MANAGEMENT AGENCY FEMA 413/January 2004 INSTALLING SEISMIC RESTRAINTS FOR ELECTRICAL EQUIPMENT Notice: This guide was prepared by the Vibration Isolation and Seismic Control Manufacturers

More information

Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit

Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit R-H-DI1 INSULATION BATT NR-E-IB1 Avoid Using Batt Insulation With Metal Framing Batt insulation should not be used with metal framing systems. Although it is common to see fiberglass batt insulation installed

More information

DENVER MODEL 30 X 30 SPECIFICATIONS

DENVER MODEL 30 X 30 SPECIFICATIONS DENVER MODEL 30 X 30 SPECIFICATIONS Dimensions: Roof Dimensions 30-0 x 30-0 (4) Columns (Center to Center) 25-6½ x 25-6½ Minimum Clearance 8-0 Roof Height @ Peak Dependent on Col. Ht. Hip Roof 4:12 pitch

More information

TYPICAL WIRING OF METER SOCKET FOR SINGLE PHASE, THREE WIRE OVERHEAD SERVICE

TYPICAL WIRING OF METER SOCKET FOR SINGLE PHASE, THREE WIRE OVERHEAD SERVICE TYPICAL WIRING OF METER SOCKET FOR SINGLE PHASE, THREE WIRE OVERHEAD SERVICE A. GENERAL NOTES: Service entrance line and load conductors, conduit straps, weatherhead, lock nuts, bushings, connectors, and

More information

Design No. P736 September 26, 2003. Restrained Assembly Ratings 1, 1-1/2 or 2 Hr. (See Items 3, 7 and 8A)

Design No. P736 September 26, 2003. Restrained Assembly Ratings 1, 1-1/2 or 2 Hr. (See Items 3, 7 and 8A) Design No. P736 September 26, 2003 Restrained Ratings 1, 1-1/2 or 2 Hr (See Items 3, 7 and 8A) Ratings 1, 1-1/2 or 2 Hr (See Items 3, 7 and 8A) Beam Ratings 1, 1-1/2 or 2 Hr (See Items 7 and 8A) 1. Beam

More information

Sports and High Mast Lighting Poles Phone: (866) 474-7200 Fax: (817) 924-7049

Sports and High Mast Lighting Poles Phone: (866) 474-7200 Fax: (817) 924-7049 Sports and High Mast Lighting Poles 4 High Mast Lighting Poles General American LitePole offers a raising and lowering system that allows for ease of maintaining the lighting system at ground level. Ideal

More information