Traffic Signal Plans. Chapter 4. Jerry Kotzenmacher MN/DOT
|
|
- Reynard Booth
- 7 years ago
- Views:
Transcription
1 Traffic Signal Plans Chapter 4 Jerry Kotzenmacher MN/DOT
2 Who Needs a Plan? 2
3 Who Needs a Plan? 3
4 Who Needs a Plan? 4
5 What is plan used for? Contractors bid Building the signal Operating/maintaining the signal Locates Tort claims/law suits 5
6 Typical Signal Plan Required Sheets Sheet Title Sheet Estimated Quantities (if not shown on the title sheet) Details Equipment Pad Layout Preformed NMC Loop Detector Detail Advance Warning Flasher Detail Signing and Pavement Markings Details Pole Mount Detail Other(s) Signal Design 6
7 Typical Signal Plan Required Sheets Sheet Intersection Layout Sheet Field Wiring Diagram Interconnect Layouts For Information Only Sheet(s) Utilities Signal Design 7
8 Title Sheet Title Sheet The title sheet is required for all traffic signal plans. It includes information such as the title block, project location, governing specifications, etc. 8
9 Title Sheet Plan Preparation Certification Note Signature Block 9
10 Title Sheet Index Map 10
11 Title Sheet Abbreviations 11
12 Title Sheet Standard Plates Filled arrows are the used plates. 12
13 Page 2 of the plan Equipment Pad Details 13
14 Page 3 of the plan Advance Warning Flasher Details 14
15 Page 4 of the plan NMC Loop Detail 15
16 Page 8 of the plan Interconnect plan sheet Interconnect sheets use 100 scale 16
17 Page 9 of the plan Utilities Plan Sheet This is a plan sheet view of the public utilities. 17
18 Page 10 of the plan Saw Cut Loop Detail 18
19 Page 11 of the plan Pole Base wire connector Detail 19
20 Page 12 of the plan Pole Mount Detail Angle & Straight 20
21 Last page of the plan Pedestrian Station Detail 21
22 Example only not in your plan Lighting Detail Shows the details of the lighting units if included in the project. Note: Shown graphic not from sample signal plan 22
23 Example only not in your plan Tabulations Earthwork summary tabulations may be included if this signal project is part of a construction project. Note: Shown graphic not from sample signal plan 23
24 24
25 Signal Face Chart Pole Notes Signal Layout-PAGE 5 Detector Chart Scale Pole numbering starts at the cabinet going clockwise. Indications read right to left. Conduit Wires 2-12/c #14 1-3/c #14 5-2/c #14 1-3/c #20 1-6/PR #19 1-1/c #6 INS. GR Road Lines Construction Notes Ped diagram and Phasing conduit Loop Detector 25
26 Controller Operations Phasing Dual-ring and Concurrent group Controllers DUAL RING STRUCTURE RING BARRIER 1 (LEFT SIDE) RING 2 BARRIER 2 (RIGHT SIDE) 26
27 Signal Layout Page 6 Match line Advance Detectors Match line Pavement Markings Detail 27
28 Signal Layout Equipment Pad Service Cabinet Controller Cabinet Equipment Pad 28
29 Signal Layout Pole Symbols & Names Pole Transformer Base Signal Pole Base Foundation 29
30 Signal Layout Signal Indication Pole Symbols Mast Arm Pole 30
31 Signal Layout Pole Symbols Emergency Vehicle Pre-emption Luminare 31
32 Signal Layout Pole #3 Notes Signal Pole Base 32
33 Signal Layout Pole Note #3 3 rd line 9 Davit (luminare arm) mounting at 350 o Pole Type PA100 Pole length (50 ) with A type bolt pattern Davit (luminare arm) mounting Height (40 ) 33
34 Signal Layout Pole #3 Notes Mast Arm at 0 degree Signal Pole Base #3 34
35 Signal Layout Indications Left Turns Protected Vehicle Signal Face Vehicle Signal Face 35
36 Signal Layout Signal Face Chart Left Turns Permissive Prot/Perm Protected 36
37 Signal Layout Signal Face Chart Left Turns Flashing Yellow Arrow 37
38 Signal Layout Phasing & Pedestrian Chart Numbering APS Address 38
39 Signal Layout - Peds Pedestrian Symbols Pedestrian Countdown Signal Face Pedestrian Pedestal Pedestrian Push Button (APS) 39
40 Signal Layout - Peds Pedestrian Push Button Station & APS Pedestrian Push Button Station 40
41 Signal Layout Hand Hole Handhole 16 Handhole 1 Handhole 15 41
42 Signal Layout Detection Detector Detector 42
43 Signal Layout Detector Chart 43
44 Signal Layout Advanced Warning Flasher Advance Warning Flasher Note: Above graphic not from sample signal plan 44
45 Wiring Diagram Field Wiring - Page 7 of 12 Controller Cabinet 12 Conductor Wire Hand Hole Insulated ground Wire #11 Pole Number Ground Rod Wire #11 Loop Detectors Notes Service Cabinet 45
46 Wiring Diagram Layout/Wire Diagram Cross Reference 46
47 Wiring Diagram Field Wiring Controller Cabinet Signal Service 47
48 Wiring Diagram Field Wiring 48
49 Wiring Diagram Field Wiring 49
50 Wiring Diagram Field Wiring Handhole Graphic New Existing Loop Detector Graphic New Existing HH 19 HH 20 Splice D2-1 D6-1 Splice 50
51 Mn/DOT - Signal Courses Training Schedule Traffic Signal Design April th, 2010 Roadway Lighting..May th
52 It worked when I left! Questions? 52
ITE/IMSA 2014 Spring Meeting March 6, 2014 Signal Maintenance Practices. Bruce E. Littleton, PE, PTOE Traffic Engineering Supervisor
ITE/IMSA 2014 Spring Meeting March 6, 2014 Signal Maintenance Practices Bruce E. Littleton, PE, PTOE Traffic Engineering Supervisor Traffic Signal Shop Mission Statement Construct, modify and maintain
More informationSafety Engineering Policy Memorandum
Safety Engineering Policy Memorandum SAFETY 2-13 Automated Traffic Law Enforcement Systems: Red Light Running (RLR) Camera Enforcement Systems and Automated Railroad Grade Crossing (RGC) Enforcement Systems
More informationTraffic Signal Asset Management System (TSAMS)
BUREAU OF MAINTENANCE & OPERATIONS Traffic Signal Asset Management System (TSAMS) DATA COLLECTION PROJECT April 18, 2016 Why TSAMS? How many traffic signals exist in Pennsylvania? I don t know! How many
More informationCHAPTER 1 TRAFFIC SIGNAL DESIGN STANDARDS AND GUIDELINES
CHAPTER 1 TRAFFIC SIGNAL DESIGN STANDARDS AND GUIDELINES SECTION 1: INTRODUCTION... 1 ACKNOWLEDGMENTS... 1 SECTION 2: TRAFFIC SIGNAL PLAN REQUIREMENTS... 2 SECTION 3: VDOT Project Development Process...
More informationSECTION 611 ACCEPTANCE PROCEDURES FOR TRAFFIC CONTROL SIGNALS AND DEVICES
SECTION 611 ACCEPTANCE PROCEDURES FOR TRAFFIC CONTROL SIGNALS AND DEVICES 611-1 Description. This Section sets forth Contract acceptance procedures for installations of traffic control signals and devices
More informationLine Loss WSDOT Winter 2008 BZA
Electrical Design Training Class Line Loss WSDOT Winter 2008 BZA Presented by: Keith Calais 1 OHM S LAW P = Watts (Power) I = CURRENT (AMPERES) R = RESISTANCE (OHMS) E = ELECTROMOTIVE FORCE (VOLTS) P =
More informationKane County Division of Transportation Policy for Red Light Running (RLR) Photo Enforcement Systems
Kane County Division of Transportation Policy for Red Light Running (RLR) Photo Enforcement Systems Effective: APRIL 1, 2008 Revised October 12, 2010 Executive Summary Red Light Running (RLR) is one of
More informationDisputed Red Light Accidents: A Primer on Signal Control. Jon B. Landerville, MSME, PE Edward C. Fatzinger, MSME, PE Philip S.
Disputed Red Light Accidents: A Primer on Signal Control Jon B. Landerville, MSME, PE Edward C. Fatzinger, MSME, PE Philip S. Wang, MSME Intersection Accident Statistics Intersection accidents occur on
More informationSpecial Specification 6033 Computerized Transportation Management System
6033 Special Specification 6033 Computerized Transportation Management System 1. DESCRIPTION Relocate computerized transportation management system (CTMS) equipment as shown on the plans and as described
More informationRoad Signs Recognition Quiz
Road Signs Recognition Quiz Place your answer for each of the signs/pavement markings on the answer sheet. Ready to Roll? Here Comes Sign # 1... #1 A No right turn B Right turn only C Warning, no turn
More informationAppendix A - Cost Estimate Spreadsheet
CCTV Camera, PTZ Per Each $18,500 $1,250 12 $33,500 Closed circuit television (CCTV) camera with pan, tilt, zoom (PTZ) functionality in a dome enclosure. CCTV Camera, Fixed Per Each $14,000 $1,250 12 $29,000
More informationAPPENDIX A. Asset Management Inventory
APPENDIX A Asset Management Inventory Traffic Engineering Asset Management Database Intersection ID# Sort E/W Sort N/S ACE Overhead Database Intersection Built or TS1 - C TS1 - B TS1 - A Other M52 M40
More informationRequirements for the Attachment of Communication Cable Facilities on PPL Poles
Page 99 of 137 Requirements for the Attachment of Communication Cable Facilities on Replaces: URS-3002 URS-3004 URS-101C-304 A-157649 Page 100 of 137 Reference Notes for Drawings: General 1. The term communication
More informationTS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING
TORONTO TRANSPORTATION January 2012 TS 813 GROUNDING AND BONDING TABLE OF CONTENTS 1. DRAWINGS TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET
More informationGUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables
Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,
More informationBUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE
BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE Toll Free Telephone Numbers Residential Services 800.454.3853 Commercial Services 800.653.5307 Utility Locating Company N.C. 800.632.4949 S.C. 888.721.7877
More informationSPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT
SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT The purpose of these specifications is to insure that there are minimum
More informationTable of Contents. Inductive Loop Vehicle Detector Applications
Table of Contents Introduction Design Essentials Loop Installation Techniques Determining Loop Phasing Equipment Installation 1 020907 Inductive Loop Vehicle Detector Applications Parking Revenue Control
More information2301.1 Scope: Communications and Electronic Systems addressed in this section include:
Chapter 23 COMMUNICATIONS / ELECTRONIC SYSTEMS SECTION 2301 - GENERAL 2301.1 Scope: Communications and Electronic Systems addressed in this section include: 1. Fire Alarm System 2. Telecommunication and
More informationC. Conform to requirements of Americans with Disabilities Act (ADA).
SECTION 28 31 00 - FIRE ALARM AND DETECTION SYSTEMS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Fire alarm and detection systems 1.2 REFERENCES A. NFPA 70 - National Electrical Code B. NFPA 72 - National
More informationModem. Backplane For Lanes 1 To 4 *
Speed/Classification Unit And Modem Furnished Separately 3.0 Note: Bracket shall be fabricated of.090-0.125 inch thick aluminum. Dimensions may vary depending on the manufacturer of the J1 receptacle being
More informationPS 29M DUAL CHANNEL BELTPACK IN METAL CASE
PS 29M DUAL CHANNEL BELTPACK IN METAL CASE USER MANUAL October 2013 This product is designed and manufactured by: ASL Intercom BV Zonnebaan 42 3542 EG Utrecht The Netherlands Phone: +31 (0)30 2411901 Fax:
More informationNORTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT SECTION 27 05 26 GROUNDING AND BONDING FOR COMMUNICATION SYSTEMS
SECTION GROUNDING AND BONDING FOR COMMUNICATION SYSTEMS RELATED SECTIONS: Section 27 00 00 General Requirements Section 27 02 00 Communication General Requirements Section 27 05 28 Pathways for Communications
More informationThe Basics of Loop Vehicle Detection
The Basics of Loop Vehicle Detection There are a number of ways to detect vehicles, ranging from hose style detection to ultra-sonic, to inductive loop. For traffic control or drive-thru, inductive loop
More informationMAST ARMS & POLES. Ornamental Pole Top & Bases
Ornamental Pole Top & Bases Pelco s decorative pole top and bases help make the traffic signal aesthetically pleasing to the eye. Available for various pole diameters and multiple finish options. Ornamental
More informationELECTRONICS G H I J K L M
ELECTRONICS TM LASER INSTALLATION INSTRUCTIONS PARTS KIT Parts Kit includes the following: A- (1) Universal Mounting Bracket A B- (1) Red L.E.D. Laser Alert Light C- (1) Piezo Beeper w/ O Ring Tape D-
More informationOEM Manual MODEL 2350 ELECTRONIC DUAL CYLINDER SCALE
OEM Manual MODEL 2350 ELECTRONIC DUAL CYLINDER SCALE Scaletron Industries, Ltd. Bedminster Industrial Park 53 Apple Tree Lane P.O. Box 365 Plumsteadville, PA 18949 USA Toll Free: 1-800-257-5911 (USA &
More informationCalifornia Manual on Uniform Traffic Control Devices. FHWA s MUTCD 2009 Edition as amended for use in California
California Manual on Uniform Traffic Control Devices FHWA s MUTCD 2009 Edition as amended for use in California Federal Highway Administration California Division 650 Capitol Mall, Suite 4-100 Sacramento
More informationPIGGY BACK Delivery System. EASY HITCH Truck/Trailer 3-Position Mounting Installation Instruction Manual
PIGGY BACK Delivery System EASY HITCH Truck/Trailer 3-Position Mounting Installation Instruction Manual PIGGY BACK Delivery System EASY HITCH Truck/Trailer 3-Position Mounting Installation Instruction
More informationDEHN + SÖHNE. DEHNconductor System No Problems with Proximities
DEHN + SÖHNE DEHNconductor System No Problems with Proximities DEHNconductor System - New Possibilities for controling Proximities. For preventing dangerous flashovers among parts of external lightning
More informationProcedure for testing the integrity of the Festo and Numatics valve stacks:
Procedure for testing the integrity of the Festo and Numatics valve stacks: 1. Disconnect the Injection Cylinder Clevis from the Injection Lever; let the Injection Cylinder lean back clear of the Injection
More informationGuidelines for Fiber Optic Cable Permits
Guidelines for Fiber Optic Cable Permits NOVA District (Fairfax/Arlington) Permits www.virginiadot.org/business/fairfax-permits-main.asp Email: NOVAFairfaxPermits@VDOT.Virginia.gov 14685 Avion Parkway
More informationpennsylvania DEPARTMENT OF TRANSPORTATION
05-299 (7-08) TRANSMITTAL LETTER PUBLICATION: 191 pennsylvania DEPARTMENT OF TRANSPORTATION DATE: 10/28/2010 SUBJECT: Guidelines for the Maintenance an~ Operation of Traffic Signals INFORMATION AND SPECIAL
More informationExhibit A Scope of Work
Exhibit A Scope of Work The agreement for S.P. 3116-142 (T.H. 169-Cross Range Expressway) includes final design plans for a 1.55 mile length of a 2 lane to 4 lane expansion project located 0.66 miles SW
More informationSECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary to perform and complete such
More informationHow To Design An Outside Plant (Osp) Network Design
Chapter 1 Introduction to Outside Plant Chapter 1 offers an overview of outside plant (OSP) fundamentals. An introduction to standardization and valuable resources for the OSP designer are also included
More informationMODELS 7007 Gorilla Cycle Alarm 7017 Gorilla Cycle Alarm with 2-way pager system 1017 2-way pager system
MODELS 7007 Gorilla Cycle Alarm 7017 Gorilla Cycle Alarm with 2-way pager system 1017 2-way pager system Remote Control Motorcycle Alarm System Installation & Operation Instructions Sistema de Alarma de
More informationSTREETLIGHT SYSTEM GROUNDING AND BONDING
Page: 1 of 8 STREETLIGHT SYSTEM GROUNDING AND BONDING 1. Scope This Construction Standard covers the grounding and bonding requirements for single phase streetlight systems served by the Looped Radial
More informationToll Zones And T geotchnical Network Infrastructure
TEXAS EPARTMENT OF TRANSPORTATION FOR SH 99 GRAN PARKWAY SEGMENTS H, I-1 AN I-2 ATTAHMENT 21-1 TOLL SYSTEMS RESPONSIILITY MATRIX APRIL 30, 2015 LEGEN Toll s Responsibility Matrix Work escription oordination
More informationSITE SAFETY LOGISTIC PLAN
SITE SAFETY LOGISTIC PLAN SHEET #1 Title Sheet Site Safety Logistic Plan For Project name & Address as it appears on the NB permit Or as it appears in the BIS system, with Borough Also include the following;
More informationENGINEERING COMMITTEE Construction and Maintenance Subcommittee
z ENGINEERING COMMITTEE Construction and Maintenance Subcommittee AMERICAN NATIONAL STANDARD ANSI/SCTE 87-1 2003 (formerly CMS WG6-0001) Graphic Symbols For Cable Telecommunications Part 1: HFC Symbols
More informationPLAN REVIEW GUIDE FOR FIRE ALARM
PLAN REVIEW GUIDE FOR FIRE ALARM PROJECT NAME: PERMIT # PROJECT ADDRESS: CONTACT PERSON: PHONE Fire alarm system installation information shall be provided on the appropriate architectural and electrical
More informationProduct Specification instalert Rapid Messenger Variable Message Sign
instalert 2 units to cover any application instalert 18 (ia18): 18 x 28 full matrix instalert 24: (ia24): 24 x 60 full matrix Size, Weight without battery ia18: 30 x 20 x 2.74, 29 lbs ia24: Folds to fits
More informationApproved Meter Sockets and Cabinets
Single Unit Residential Guide 1 PHASE, 120/240 VOLT S METERING (Metering sockets and cabinets are supplied by Customer). Outdoor meter mounting height is 1730 mm ( 5 8 ) to center of meter ± 100 mm ( 4
More informationRemote Access System Installation
2011-2013 Explorer Remote Access Remote Access System Installation CONTENTS VEHICLE PREPARATION Hood Switch Wire Harness Installation Hood Switch Installation RMST Module Installation RMU Module Installation
More informationStop Alert Flasher with G-Force sensor
Stop Alert Flasher with G-Force sensor Stop Alert module creates brake light flashing effect to catch attention of the drivers behind to avoid dangerous rear end collision. The flasher module is a state
More informationR E C I T A L S RD:GDS:LCP 5-18-16 T-24509.002/ 1319641
CONTINUATION TO THE AGREEMENT FOR FINAL DESIGN SERVICES BETWEEN CITY OF SAN JOSE AND SANTA CLARA VALLEY TRANSPORTATION AUTHORITY FOR THE SANTA CLARA/ALUM ROCK BUS RAPID TRANSIT PROJECT THIS SECOND AMENDMENT
More informationCollision Diagrams Last Updated: 1/18/2013
Collision Diagrams Last Updated: 1/18/2013 Contents Introduction How to Load and Use the Collision Diagram Program Other Notes on Collision Diagrams Appendix Example collision diagrams Installation Instructions
More informationSECTION 16721 FIRE ALARM AND DETECTION SYSTEM
1. GENERAL 1.1. Related Documents: 1.2. Scope: 1.1.1. The general provisions of the Contract, including General and Supplementary Conditions and General Requirements apply to the work specified in this
More informationINSTRUCTIONS FOR THE INSTALLATION AND OPERATION OF ACTIVATOR II
INSTRUCTIONS FOR THE INSTALLATION AND OPERATION OF ACTIVATOR II ELECTRONIC TRAILER BRAKE CONTROL 5500 FOR 2, 4, 6 & 8 BRAKE SYSTEMS IMPORTANT: READ AND FOLLOW THESE INSTRUCTIONS CAREFULLY. KEEP THESE INSTRUCTIONS
More informationCalMod Design-Build Electrification Services
SECTION 28 16 00 INTRUSION DETECTION SYSTEM PART 1 - GENERAL 1.1 DESCRIPTION A. This section describes the detailed technical requirements for the Intrusion Detection System (IDS), where the Contractor
More informationThis equipment has been tested and found to comply with the limits for a Class B digital device, pursuant to part 15 of the FCC Rules.
Power Max Level 2 Charging Station en Installation and Operating Instructions This equipment has been tested and found to comply with the limits for a Class B digital device, pursuant to part 15 of the
More informationMODELS 8007 Gorilla Cycle Alarm 8017 Gorilla Cycle Alarm with 2-way pager system 1018 2-way pager system
MODELS 8007 Gorilla Cycle Alarm 8017 Gorilla Cycle Alarm with 2-way pager system 1018 2-way pager system Remote Control Motorcycle Alarm System Installation & Operation Instructions Sistema de Alarma de
More informationOperating Instructions
VMD202 Vehicle Motion Detector Operating Instructions CAUTIONS AND WARNINGS Never use the VMD202 as a safety reversing or presence detection system. The VMD202 requires that a vehicle be moving for detection.
More informationCHAPTER 2 TRAFFIC SIGNS AND HIGHWAY MARKINGS
CHAPTER 2 TRAFFIC SIGNS AND HIGHWAY MARKINGS This chapter summarizes traffic signs, signals and road markings that control the flow of traffic, making streets and highways safer for motorists, bicyclists
More informationFIRE ALARM AND DETECTION SYSTEMS SECTION 16721
PART 1 - GENERAL 1.01 WORK INCLUDED FIRE ALARM AND DETECTION SYSTEMS SECTION 16721 A. Provide a complete fully addressable, power limited, fire detection and evacuation system. The system shall be connected
More informationWarning Road Signs. Road Layout (W100 Series) Direction of Movement (W200 Series) Beginning of Dual Roadway (To Left) Right)
Road Layout (W100 Series) Product Cross Road T-Junction Side-Road Junction (Left) Code W101 W104 W107 Code TW101 TW104 TW107 Product Side-Road Junction (Right) Staggered Junctions (Right-Left) Staggered
More informationCHAPTER 11: PEDESTRIAN SIGNS AND SIGNALS
CHAPTER 11: PEDESTRIAN SIGNS AND SIGNALS Traffic signs and signals should be useful for all pedestrians. It is essential to provide signals that are phased and timed to allow senior citizens, children,
More informationNEI-30 VEI-30 Dinion Infrared Imager NEI VEI Series. Quick Install Guide
NEI-30 VEI-30 Dinion Infrared Imager NEI VEI Series en Quick Install Guide NEI-30 VEI-30 Dinion Infrared Imager Table of Contents en 3 Table of Contents 1 Planning 4 1.1 Hardware Requirements 4 1.2 Pre-installation
More informationProcurement Specification for a High Security Lift Arm Barrier (HSLAB) EB950 CR Armstrong High Security Lift Arm Barrier
Procurement Specification for a High Security Lift Arm Barrier (HSLAB) EB950 CR Armstrong High Security Lift Arm Barrier A. Requirement This document is to be used to specify the physical and operational
More informationIndustrial Design And Build Plans For California State Laws
CITY OF MISSION VIEJO STANDARD SPECIFICATIONS SECTION 307 STREET LIGHTING AND TRAFFIC SIGNALS 307-1 TRAFFIC SIGNAL AND HIGHWAY LIGHTING SYSTEM The furnishing and installing of traffic signals and highway
More information* DISCLAIMER: Contents. How to Use This Guide: COMMERCIAL INSTALL GUIDE 2
COMMERCIAL INSTALL GUIDE 2 Contents How to Use This Guide: The first section of this guide is designed to assist you with the installation of your DECK Monitoring hardware. The revenue grade meter and
More informationFire Alarm System Plans Submittal Guidelines For New and Existing Systems
Fire Alarm System Plans Submittal Guidelines For New and Existing Systems SCOPE The Temecula Fire Prevention Bureau (TFPB) has established the following requirements for the submittal of all fire alarms,
More informationTraffic Signal Master Plan
Traffic Signal Master Plan DEPARTMENT OF PUBLIC WORKS Engineering Division June 2006 i TABLE OF CONTENTS Executive Summary... iii 1.0 PURPOSE...1 2.0 CITY TRAFFIC SIGNAL SYSTEM...1 2.1 Introduction 2.2
More informationOperating Instructions
D-TEK Vehicle Loop Detector Operating Instructions This product is an accessory or part of a system. Always read and follow the manufacturer s instructions for the equipment you are connecting this product
More informationSOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings
*** Provide this document to the inspector along with ALL system installation instructions *** Project Address: Scope: Standard plan for the installation of grounded microinverter solar PV systems, not
More informationTS93 EMR T/PT/TDE. Surface applied door closer
TS EMR T/PT/TDE Surface applied door closer Installation instructions: Pull side track mount door closer with smoke detector (EMR T) Push side track mount door closer with smoke detector (EMR PT) Double
More information702 TRAFFIC SIGNALS 700-2 703 DETECTION SIGNAL HEAD CONTROLLER CABINET 700-12
CITY OF THORNTON Standards and Specification Revised: October 2012 SECTION 700 - TRAFFIC TECHNICAL SPECIFICATIONS TABLE OF CONTENTS PAGE 701 GENERAL PROVISIONS 700-1 701.1 Definitions 700-1 701.2 Regulations
More informationCITY OF BOCA RATON. Special Requirements for Traffic Control Signal Devices and ITS Devices
CITY OF BOCA RATON Special Requirements for Traffic Control Signal Devices and ITS Devices January 2014 Revision 5.0 Traffic Management Center Municipal Services Department 2500 Northwest 1ST Avenue Boca
More informationANTI-THEFT SYSTEM. 1995 Volvo 850 DESCRIPTION & OPERATION BASIC ALARM. 1995-96 ACCESSORIES & EQUIPMENT Volvo Anti-Theft Systems
ANTI-THEFT SYSTEM 1995 Volvo 850 1995-96 ACCESSORIES & EQUIPMENT Volvo Anti-Theft Systems 850 DESCRIPTION & OPERATION WARNING: Deactivate air bag system before performing any service operation. For 1995
More informationSTANDARDS AUSTRALIA/STANDARDS NEW ZEALAND. Committee CE-001 Parking Facilities DRAFT. Australian/New Zealand Standard
Draft For Committee Purposes Only DRAFT FOR SUBMISSION TO ABCB CE/001/09-481A (Supersedes CE/001/05-406) Issued: February 2009 Project No: 5431 STANDARDS AUSTRALIA/STANDARDS NEW ZEALAND Committee CE-001
More informationUNIT PRICE LIST (09/30/2012) DIVISION I -EARTHWORK
LIST (09/30/2012) DIVISION I -EARTHWORK 100.1 MOBILIZATION L.S. - 11% 100.2 INSURANCE & BOND L.S. - 3% 101.1 PREPARING RIGHT OF WAY L.S. - 4% 102.1 OBLITERATING ABANDONED STREET ( < 25,000 S.Y.) S.Y. 6
More informationSECTION 13850 (28 31 00) FIRE DETECTION AND ALARM SYSTEM
SECTION 13850 (28 31 00) FIRE DETECTION AND ALARM SYSTEM ENGINEERING SPECIFICATION INTELLIGENT REPORTING FIRE DETECTION SYSTEM PART 1 GENERAL 1.1 DESCRIPTION A. This specification includes the furnishing,
More informationid led 4" square housing FL44
id led 4" square housing FL44 LUMINAIRE MUST BE INSTALLED PRIOR TO DRYWALL CEILING. ALL GRID LUMINAIRES MUST BE SECURED TO STRUCTURE ABOVE. non-emergency optional - bar hangers key sold separately power
More informationSECTION 16721 FIRE ALARM AND DETECTION SYSTEMS
SECTION 16721 FIRE ALARM AND DETECTION SYSTEMS The equipment requirements of this section apply to the IUB Campus. The IUPUI Campus has a preferred vendor agreement for fire alarm systems. Contact Pat
More informationSelf-Install Security System Installation and User Guide
Self-Install Security System Installation and User Guide Contents Installation Installation guide 4 Codepad and accessories 6 Step 1 Determine security system location 8 Step 2 Mounting motion sensors
More informationJUTAI Barcode Ticket Parking System Solution
JUTAI Barcode Ticket Parking System Solution SHENZHEN JUTAI COMM CO., LTD Add: 5F, Mingjinhai Park, Shiyan Town, Bao an District Shenzhen City, China. Tel: (86)755 29573855 E-mail:info@jutairfid.com Fax:
More information8900 EMR (WITH DETECTOR)
00 EMR (WITH ) GENERAL DESCRIPTION Each 00 EMR series unit contains a door closer, hold open electromagnet and smoke detector. The unit can be used as a single installation or as a series of singles powered
More informationWYDOT Quick Facts TRAFFIC SIGNALS
TRAFFIC SIGNALS WYDOT Quick Facts 2 Advantages of traffic signals WYDOT Quick Facts Traffic signals control vehicle and pedestrian traffic by assigning priorities to various traffic movements to influence
More informationSTANDARD SPECIFICATIONS FOR SIGNAGE, STRIPING, AND LIGHTING TOWNSHIP OF STANFORD
STANDARD SPECIFICATIONS FOR SIGNAGE, STRIPING, AND LIGHTING TOWNSHIP OF STANFORD TABLE OF CONTENTS 1.00 2.00 3.00 4.00 GENERAL REQUIREMENTS MATERIALS DESIGN LAYOUT STANDARD PLATES Page No. 1 1 3 5 STANDARD
More informationSTATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 804 FIBER OPTIC CABLE FOR TRAFFIC SIGNAL INTERCONNECT JANUARY 19, 2007
804.01 Description 804.02 General 804.03 Materials 804.04 Fan-Out Kit 804.05 Drop Cable 804.06 Fiber Optic Patch Cord 804.07 Termination Panel 804.08 Fusion Splice 804.09 Fiber Optic Connector 804.10 Splice
More informationSECTION 1092 SIGNAL EQUIPMENT. 1092.1 Signal Heads. Signal heads shall meet the following requirements:
SECTION 1092 SIGNAL EQUIPMENT 1092.1 Signal Heads. Signal heads shall meet the following requirements: (a) All signal heads shall be weatherproof and black in color in accordance with Sec 1092.1.1. All
More informationCDGRD-10. Grounding. Solutions For Comm/Data Applications
CDGRD-10 Grounding Solutions For Comm/Data Applications Overview & Table of Contents Cooper B-Line s Grounding products for rack & runway provide a complete solution for grounding metal supports. The offering
More informationCOURTING YOUR BICYCLE AND PEDESTRIAN FACILITIES... FROM A FORENSIC ENGINEERING AND PLANNING PERSPECTIVE
COURTING YOUR BICYCLE AND PEDESTRIAN FACILITIES... FROM A FORENSIC ENGINEERING AND PLANNING PERSPECTIVE 1 PRESENTED BY: J.M. TEAGUE ENGINEERING, PLLC 2 OBJECTIVES 1. What is Transportation Forensic Engineering
More informationElectrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial
More informationADA POST INSPECTION CHECKLIST. Job No. Route County Location
ADA POST INSPECTION CHECKLIST Job No. Route County Location SIDEWALKS All sidewalks constructed within the project limits are ADA compliant. Sidewalks are 5 or greater in width. Exception, existing sidewalks
More informationWIND ALARM. Wind Speed Alarm. Wind Speed. Set Point 2. Set Point 1 NEW BEDFORD, MA 02745 USA
Thank you for purchasing the Maximum wind speed alarm. The Maximum wind speed alarm is a dual set point wind speed indicator with a two digit LED display. It contains a yellow light to display one set
More informationPART B: LOCATION REFERENCING P ART B: METHOD LOCATION REFERENCING METHOD
PART B: LOCATION REFERENCING P ART B: METHOD LOCATION REFERENCING METHOD Manual No. SM051 B-1 RECORDING A ROUTE POSITION Overview This chapter explains how the location referencing signs, described in
More informationINSTALLATION AND OPERATION MANUAL
ECO-WORTHY INSTALLATION AND OPERATION MANUAL INSTALLATION AND OPERATION MANUAL www.eco-worthy.com ECO-WORTHY Solar tracker ECO-WORTHY 400 Solar Tracker Owner s Manual Manual User Installation instructions
More informationSECTION 1-5 OPERATION OF INSTRUMENTS AND CONTROLS 06.0.711. Lights, Wipers and Defogger
OPERATION OF INSTRUMENTS AND CONTROLS Lights, Wipers and Defogger SECTION 1-5 Headlights and turn signals................................... 76 Emergency flashers..........................................
More informationSECTION 16720 - FIRE AND SMOKE ALARM SYSTEM. City of San Diego, CWP Guidelines
PART 1 -- GENERAL 1.1 WORK OF THIS SECTION SECTION 16720 - City of San Diego, CWP Guidelines A. The WORK of this Section includes providing manual and automatic fire alarm and smoke detection systems meeting
More informationCITY OF BOCA RATON. Special Requirements for Traffic Control Signal Devices and ITS Devices
CITY OF BOCA RATON Special Requirements for Traffic Control Signal Devices and ITS Devices January 2012 Revision 4.0 Traffic Management Center Municipal Services Department 2500 Northwest 1 st Avenue Boca
More informationSecurity Systems Intrusion Alarm
Dufferin-Peel Catholic District School Board STANDARD TEXT GUIDELINE FOR Security Systems for SECONDARY AND ELEMENTARY SCHOOLS Prepared by the Plant Department With Assistance from Vision Dynamics Formatted
More informationCLARK COUNTY FIRE DEPARTMENT Fire Hazard & Prevention Services
CLARK COUNTY FIRE DEPARTMENT Fire Hazard & Prevention Services 575 E. Flamingo Road, Las Vegas, NV 89119 (702) 455-7316 FAX (702) 455-7347 105.8a-6.1 TITLE: FIRE ALARM SYSTEM REQUIREMENTS SCOPE: This guideline
More informationHow To Improve Safety
Collision Diagrams Collision diagrams are used to display and identify similar accident patterns. They provide information on the type and number of accidents; including conditions such as time of day,
More informationFIBER-OPTIC CABLE PLAN CHECK
Engineering Division 201 North Broadway, Escondido, CA 92025 (760) 839-4651, FAX (760) 839-4597 FIBER-OPTIC CABLE PLAN CHECK To: Date: Project: Project No. Address: Check No. Attn: Via: The attached plans
More informationMulti Function, User Configurable Remote Vehicle Security System with 4 Button Replaceable Membrane Remote Transmitter
MODEL PRO-9744 INSTALLATION MANUAL Multi Function, User Configurable Remote Vehicle Security System with 4 Button Replaceable Membrane Remote Transmitter This System Allows The Transmitter Buttons To Be
More informationMAC-821SC-E. Centralized On-Off Remote Controller. English ÏÏËÓÈÎ. Русский [FOR INSTALLER] INSTALLATION MANUAL
Centralized On-Off Remote Controller MC-821SC-E [FOR INSTLLER] INSTLLTION MNUL English [ [ π À À π ] E XEIPI IO O H IøN E KT T H [ [MONTÖR Ç N] MONTJ ELK TBI ÏÏËÓÈÎ [ДЛЯ УСТАНОВИТЕЛЯ] РУКОВОДСТВО ПО УСТАНОВКЕ
More informationHyperlinks are Inactive
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
More informationSolar Panel Installations
Solar Panel Installations Page 1 of 6 SINGLE-FAMILY RESIDENTIAL CHECKLIST City of Hayward Development Services Department Revised: 7-09-15 PERMIT REQUIREMENTS Permits are required for all solar panel installations.
More information