Ottawa s Light Rail Transit Project - The Confederation Line

Size: px
Start display at page:

Download "Ottawa s Light Rail Transit Project - The Confederation Line"

Transcription

1 Ottawa s Light Rail Transit Project - The Confederation Line National Capital Heavy Construction Association January 30, 2013 Rail Implementation Office

2 Overview of the Presentation Project Background & Timeline Procurement and evaluation process Project Description: Stations plus the maintenance and storage facility LRT vehicle Tunnel construction HWY 417 widening Cash Allowance Projects Capital costs Construction schedule Transit detours

3 Need

4 Timeline November 2008: the previous Council approved the Transportation Master Plan update that identified Downtown Ottawa Transit Tunnel (DOTT) as its first priority project for Light Rail Transit (LRT) January 2010: the previous Council approved the DOTT Planning and Environmental Assessment Study providing authority to begin the expedited Environmental Assessment process, Preliminary Engineering and Property acquisition. September 2010: commence Preliminary Engineering activities and property acquisition for Ottawa s Light Rail Transit (OLRT) project.

5 Timeline May 2011: Council approved the OLRT Schedule Acceleration and Procurement Option Selection report that: an accelerated schedule that advanced completion from 2019 to Spring 2018 and, the use of Infrastructure Ontario s Alternative Finance Procurement (AFP) process using a Design-Build-Finance-Maintain model. July 2011: Council approved the OLRT Implementation report that: presented the new tunnel alignment on Queen Street, re-established the $2.1 billion budget, directed staff to implement the OLRT project using a Design Build Finance Maintain (DBFM) procurement model, and authorized the engagement of Infrastructure Ontario as the City s procurement agent.

6 Timeline October 2011: the Request for Qualification (RFQ) process resulted in a shortlist of three private sector teams June 2012: the planned widening of the Highway 417 project is bundled with the OLRT project to allow alternative Bus Rapid Transit system before the east end Transitway closure September/October 2012: RFP submittals Technical / Financial October/November 2012: Proposal evaluations December 2012: Council approves contract award

7 Timeline Procurement Phase Design Phase Construction Phase Highway 417 Operational LRT Operational Council Approval 19 Dec 2012

8 Alignment 12.5 Km long 13 Stations 2.5 Km Tunnel 8

9 Procurement The project was procured as a Design, Build, Finance and Maintain (DBFM) with a 30 year concession period Inclusion of Hwy 417 widening, from Nicholas to Hwy174 Split Inclusion of Cash Allowance projects

10 Procurement The RFP included set of financial incentives to encourage higher performance on key issues Operations matters: examined the number of drivers needed to operate the system and this impact on the City s operating costs Mobility matters: encouraged an approach to construction that minimized the number of lane closures on the Transitway as well as on roads Energy matters: developed a long-term affordability and efficiency plan for the system as the City pays these energy costs

11 Evaluation The evaluations took place in four distinct steps: Completeness Verification: Proposals were reviewed by a Completeness Review Team to ensure that the three submissions included all mandatory information. Compliance Review: A separate Compliance Team undertook a detailed review of each Proponent s design to ensure it complied with the requirements of the RFP and output specifications. Technical Evaluation: The Technical review team was made up of subject matter experts on project design and engineering. Financial Evaluation: The Financial review team was made up of subject matter experts on Alternative Finance and Procure (AFP) procurement and public and private financing.

12 The Recommended Team The recommended preferred proponent received the highest technical and financial score The preferred proponent also assumed the full geotechnical risk of the tunnel that the City sought. Currently working with the preferred proponent to reach Financial Close.

13 Rideau Transit Group (RTG)

14 Rideau Transit Group (RTG) RTG is well positioned to deliver the Confederation Line ; its team members have previously : completed 80 large-scale transportation P3 projects, been awarded more than $13 billion in work in North America since 2009, constructed more than 1,360 km of tunnel, delivered more than 2,500 km of rail/mass transit projects worldwide Some of its well known projects include: the Canada Line (Vancouver), Seville Line 1 (Spain), Ankara Metro (Turkey) and Barcelona Metro Line 1 (Spain)

15 Our 13 Stations 15

16 The Stations Tunney s Pasture 16

17 Tunney s Pasture 17

18 Tunney s Pasture 18

19 Bayview 19

20 Bayview 20

21 Lebreton 21

22 Lebreton 22

23 Downtown West 23

24 Downtown West 24

25 Downtown West (includes integrated entrance in Place de Ville) 25

26 Downtown East (East) 26

27 Downtown East (includes integrated entrance in Sun Life) 27

28 Downtown East 28

29 Rideau (includes integrated entrance in Rideau Centre) 29

30 Rideau 30

31 Rideau 31

32 Campus 32

33 Campus 33

34 Lees 34

35 Lees 35

36 Hurdman 36

37 Hurdman 37

38 Hurdman 38

39 Train 39

40 Train 40

41 St. Laurent 41

42 St. Laurent 42

43 Cyrville 43

44 Cyrville 44

45 Blair Gloucester Mall 45

46 Blair 46

47 Blair 47

48 Maintenance & Storage Facility Train Yard Mall Area 48

49 Maintenance & Storage Facility 49

50 OLRT Vehicle - Citadis by Alstom Streetcar version of the Citadis used in Belgium Streetcar version of the Citadis used in Istanbul 50

51 Tunnel Construction Will take place at three entry points: the east portal, west portal and a central shaft site at Queen Street and Kent Street. Will minimize surface disruption by not using cut and cover construction for the stations Will not utilize a TBM and the only real evidence of its construction will be from the construction of the station entrances and ventilation shafts The downtown construction sites will be relatively modest and we do not expect requiring a full closure of the street

52 Tunnel Construction Rideau Downtown East East Portal Excavation Shaft West Portal Downtown West Bronson Avenue 52

53 Tunnel Construction Sequential Excavation Method using Roadheaders 53

54 Noise & Vibration Mitigation Resilient Fastener Devices Floating Trackbed 54

55 Highway 417 Widening Nicholas to OR 174 March Coventry Bridge Project Limits MTO Bridges City of Ottawa Bridges Rapid Bridge Replacement Sites

56 Cash Allowance Projects 1- Transitway Rock Stabilization Cash Allowance: $3M 2- Albert Street Utilities Cash Allowance: $20M 3- CSST Cash Allowance: $8.7M 4- Queen Street Original Cash Allowance: $8M 5- Coventry Bridge Cash Allowance: $8.8M 56

57 Capital Costs Cost Area Budget Property, Engineering, Property Management $275M Tunnel & Stations $681M Track Work, Systems, MSF Facility $551M Civil Works $102M Vehicles $344M Financing & SPV Costs $176M OLRT Total $2.130B HWY 417 Widening $214M HWY 417 Transit Priority $12M OLRT Transition $63M Multi Project Contingency: $100M HWY 417/Mobility Total $289M Project TOTAL $2.419B 57

58 Construction Schedule Awaiting Scott Street Widening Awaiting Tunnel Delayed as much as possible to not to interfere with Nicholas Offline - Independent Awaiting 417 widening

59 QUESTIONS? 59

4 SPADINA SUBWAY EXTENSION UPDATE

4 SPADINA SUBWAY EXTENSION UPDATE 4 SPADINA SUBWAY EXTENSION UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the adoption of the recommendations contained in the following report June 13, 2006, from the

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: June 24, 2014 SUBJECT: SCARBOROUGH SUBWAY EXTENSION - UPDATE ACTION ITEM RECOMMENDATION It is recommended that the Board: i. Receive

More information

SPO Technical Capacity Review. June 24, 2015

SPO Technical Capacity Review. June 24, 2015 SPO Technical Capacity Review June 24, 2015 Southwest Project Context The Southwest Light Rail Transit (LRT) project (METRO Green Line Extension) will operate from downtown Minneapolis through the communities

More information

Business Case. Ottawa Public Library Main Library Facility May 2015

Business Case. Ottawa Public Library Main Library Facility May 2015 Business Case Ottawa Public Library Main Library Facility May 2015 The information contained in this document is proprietary to the Ottawa Public Library and the City of Ottawa. Unauthorized distribution

More information

Construction impacted by existing rock valley. Access shafts required Rideau Street, Triangle lands, North of NAC

Construction impacted by existing rock valley. Access shafts required Rideau Street, Triangle lands, North of NAC Rideau Alignment Daly Alignment Mackenzie-King Alignment Rideau Alignment Profile Rideau Station Catchment Area Rideau Station Issues Constructed by tunnelling and mining Construction impacted by existing

More information

CRENSHAW/LAX TRANSIT CORRIDOR PROJECT

CRENSHAW/LAX TRANSIT CORRIDOR PROJECT CRENSHAW/LAX TRANSIT CORRIDOR PROJECT A New Beginning for the Crenshaw Corridor Through Use of Innovative Procurement Strategies Robert Ball, P.E. and Kimberly Ong, P.E. Los Angeles Metropolitan Transportation

More information

Region of Waterloo Finance Department Financial Services and Development Financing

Region of Waterloo Finance Department Financial Services and Development Financing Region of Waterloo Finance Department Financial Services and Development Financing To: Chair Jim Wideman and Members of the Planning and Works Committee Date: May 27, 2014 File Code: T16-01 Subject: Stage

More information

1. RECOMMENDATIONS. It is recommended that:

1. RECOMMENDATIONS. It is recommended that: Clause No. 7 in Report No. 3 of was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on February 20, 2014. (Mayor Hackson declared an interest in this

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED STAFF REPORT ACTION REQUIRED Procurement Authorization Scarborough Subway Extension Project Management Services Contract FE85-3 Date: February 25, 2015 To: From: TTC Board Chief Executive Officer Summary

More information

Infrastructure Ontario Borrowing Today for the City of Tomorrow Session #1 Steve Rohacek, Vice President, Municipal Business Development & Lending

Infrastructure Ontario Borrowing Today for the City of Tomorrow Session #1 Steve Rohacek, Vice President, Municipal Business Development & Lending Click to edit Master title style Infrastructure Ontario Borrowing Today for the City of Tomorrow Session #1 Steve Rohacek, Vice President, Municipal Business Development & Lending www.infrastructureontario.ca

More information

REQUEST FOR PROPOSAL SPECTATOR FACILITY FEASIBILITY STUDY ADDENDUM NO. 1

REQUEST FOR PROPOSAL SPECTATOR FACILITY FEASIBILITY STUDY ADDENDUM NO. 1 Financial Management Services Purchasing Division Request for Proposal Spectator Facility Feasibility Study REQUEST FOR PROPOSAL FOR A SPECTATOR FACILITY FEASIBILITY STUDY ADDENDUM NO. 1 This addendum

More information

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain Effect on structures Uniform settlement - no concerns Angular distortion - causes damage due to tensile strain 1/500 - safe limit for no cracking of buildings 1/150 - potential structural damage 36 37

More information

Alstom Transport supplier of Tram Systems in PPP schemes

Alstom Transport supplier of Tram Systems in PPP schemes Alstom Transport supplier of Tram Systems in PPP schemes Arnaud de Monts 04/04/2014 Various procurement schemes A tramway system can be procured in various schemes, each of them have been experimented

More information

B1 Project Management 100

B1 Project Management 100 Assignment of points B1 Project Management 100 Requirements for Design Presentation Meetings and Proposal Submissions for Key to Project Management Design Presentation Meeting and Proposal Submissions

More information

Appendix D. Public Information Centre Summary Report

Appendix D. Public Information Centre Summary Report Appendix D Public Information Centre Summary Report HIGHWAY 417 EXPANSION, OPERATIONAL IMPROVEMENTS AND INFRASTRUCTURE REHABILITATION From Nicholas Street to Ottawa Road 174 Detail Design G.W.P. 4091 07

More information

GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES

GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES REQUEST FOR QUALIFICATIONS GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES NEW DINING HALL MONTANA STATE UNIVERSITY Bozeman, Montana PPA NO. 15-0103 Campus Planning, Design & Construction Plew Building

More information

Design-Build Process for Project Managers

Design-Build Process for Project Managers Vermont Agency of Transportation Design-Build Process for Project Managers This document provides guidance on the preliminary engineering and procurement process and roles and responsibilities of key personnel

More information

Public Health Services - The Cost of Doing Data Centre Project in Ontario, Canada

Public Health Services - The Cost of Doing Data Centre Project in Ontario, Canada VALUE FOR MONEY ASSESSMENT MINISTRY OF GOVERNMENT SERVICES NEW DATA CENTRE - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - Table of Contents Summary...6 Project description...8 Competitive selection process

More information

Need for the scheme. The project will bring a number of benefits to road users including:

Need for the scheme. The project will bring a number of benefits to road users including: Introduction Welcome to our Project Bank Account (PBA) industry briefing event for the A96 Inveramsay Bridge Improvement Project, which is the first Scottish road infrastructure project to use a PBA. The

More information

COWI s Role in the Copenhagen Metro Project

COWI s Role in the Copenhagen Metro Project COWI s Role in the Copenhagen Metro Project On the occasion of the award by the Copenhagen Cultural Foundation for COWI A/S part in the implementation of Phase 1 of the Copenhagen Metro 2 COWI s Role in

More information

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement

More information

Transit, Rail, Program, Project & Construction Management Experience

Transit, Rail, Program, Project & Construction Management Experience Point of Contact Peter M. Cipolla Vice President, Rail & Transit Mobile: 925.219.5235 Email: peter.cipolla@hatchmott.com Project Management Oversight Services Introduction & Background Hatch Mott MacDonald

More information

Executive Director, Engineering & Construction Services Director, Purchasing & Materials Management Division

Executive Director, Engineering & Construction Services Director, Purchasing & Materials Management Division PW8.5 STAFF REPORT ACTION REQUIRED Contract Award Request for Proposal No. 9117-15-7122 Engineering Services for the Detailed Design, Services During Construction, and Post-Construction Services for an

More information

RFP 43-14: STREETCAR OPERATIONS & MAINTENANCE SERVICE CONTRACT. Cincinnati Streetcar Project June 2015

RFP 43-14: STREETCAR OPERATIONS & MAINTENANCE SERVICE CONTRACT. Cincinnati Streetcar Project June 2015 RFP 43-14: STREETCAR OPERATIONS & MAINTENANCE SERVICE CONTRACT Cincinnati Streetcar Project June 2015 O&M timeline March 2015 - O&M RFP proposals due April-May 2015 Proposal evaluation and negotiations

More information

Coordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit

Coordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit Coordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit Public Information Session May 31, 2016 Transportation

More information

Prepared by David Willson, OCIO in consultation with Marc Buchalter, Procurement Please send comments to David Willson at dwillson@berkeley.

Prepared by David Willson, OCIO in consultation with Marc Buchalter, Procurement Please send comments to David Willson at dwillson@berkeley. Technology RFX Customer Guide Introduction This guide is intended for those that have identified a need to solicit bids from suppliers but may unclear on the different types of documents, the roles various

More information

Rapid Transit Backgrounder

Rapid Transit Backgrounder Rapid Transit Backgrounder Moving Forward On Rapid Transit The concept of a Rapid Transit System for Winnipeg has been debated for over 30 years. City Council and the Province of Manitoba have demonstrated

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

Welcome to the LRT Overview Open House

Welcome to the LRT Overview Open House Welcome to the LRT Overview Open House Please sign-in so that we may provide you with updates on future events. TORONTO LRT OVERVIEW Importance of Transit to Cities Increase City s competitiveness (World

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF JULY 31, 2015 SEPTEMBER 2015 Phase 2 Cost Summary July Expenditures $ 19.2 Million Total Expenditures $ 508.7 Million

More information

TAPPAN ZEE HUDSON RIVER CROSSING PROJECT

TAPPAN ZEE HUDSON RIVER CROSSING PROJECT New York State Department of Transportation New York State Thruway Authority TAPPAN ZEE HUDSON RIVER CROSSING PROJECT DESIGN-BUILD PROJECT RESPONSES TO PROPOSERS S REFERENCE NUMBER: This page is intentionally

More information

Risk Management in the Development of a Penta-P Project

Risk Management in the Development of a Penta-P Project Risk Management in the Development of a Penta-P Project Bill Van Meter Regional Transportation District Denver, CO Julie Skeen Jacobs Engineering Denver, CO Damian Carey Jacobs Engineering Denver, CO Don

More information

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT DESIGN-BUILD GUIDELINES AND PROCEDURES

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT DESIGN-BUILD GUIDELINES AND PROCEDURES ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT DESIGN-BUILD GUIDELINES AND PROCEDURES Revision 1 September 2015 TABLE OF CONTENTS Section I. Introduction 6 PURPOSE 6 AUTHORITY 6 DEFINITIONS AND ACRONYMS

More information

December 2015. Project Report. Stanton Territorial Hospital 20567651.3

December 2015. Project Report. Stanton Territorial Hospital 20567651.3 Project Report Stanton Territorial Hospital December 2015 1 Purpose of this project report The purpose of this project report ( Project Report ) is to provide key information to the public about the Stanton

More information

Purple Line Implementation Advisory Group Business Continuity During Construction July 30, 2014

Purple Line Implementation Advisory Group Business Continuity During Construction July 30, 2014 Purple Line Implementation Advisory Group Business Continuity During Construction July 30, 2014 Economic Empowerment Program Scope of Work Providing advocacy for small and disadvantaged business capacity,

More information

MOTION NO. M2015-63 WSDOT Task Order for Final Design Services PROPOSED ACTION

MOTION NO. M2015-63 WSDOT Task Order for Final Design Services PROPOSED ACTION MOTION NO. M2015-63 WSDOT Task Order for Final Design Services MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee 07/09/15 Final Action Ahmad Fazel, DECM Executive Director Ron Lewis, East

More information

GTA Cordon Count Program

GTA Cordon Count Program Transportation Trends 2001-2011 Executive Summary Project No. TR12 0722 September 2013 1.0 Introduction The Cordon Count program was established to collect traffic data as a tool for measuring travel trends

More information

Evergreen Line Rapid Transit Project Business Case Executive Summary. February 2008. Reviewed by

Evergreen Line Rapid Transit Project Business Case Executive Summary. February 2008. Reviewed by Evergreen Line Rapid Transit Project Business Case Executive Summary February 2008 Reviewed by Recommendation and Executive Summary The business case for the Evergreen Line Rapid Transit Project (the Project)

More information

Item No. 10.1.1 Halifax Regional Council September 28, 2010

Item No. 10.1.1 Halifax Regional Council September 28, 2010 PO Box 1749 Halifax, Nova Scotia B3J 3A5, Canada Item No. 10.1.1 Halifax Regional Council September 28, 2010 TO: Mayor Kelly and Members of Halifax Regional Council SUBMITTED BY: Mike Labrecque, Acting

More information

What is Alternate Delivery?

What is Alternate Delivery? What is Alternate Delivery? Hans VanPoorten, MBA, P.Eng. Vice President Advisory Services CSVA Conference, 2011 Presentation Contents P3 History, Market and MMM Credentials Process Typical P3 Infrastructure

More information

Consolidated I&T Data Centre - P3 Canada Fund

Consolidated I&T Data Centre - P3 Canada Fund STAFF REPORT ACTION REQUIRED Consolidated I&T Data Centre - P3 Canada Fund Date: January 16, 2012 To: From: Wards: Reference Number: Government Management Committee Deputy City Manager & Chief Financial

More information

Managed Services Consulting. Europe, Asia, Africa, Middle East, Latin America, North America

Managed Services Consulting. Europe, Asia, Africa, Middle East, Latin America, North America Managed Services Consulting Europe, Asia, Africa, Middle East, Latin America, North America New Vibrations Consulting Services Contents New Vibrations Consulting Managed Services Consulting Feasibility

More information

RBRC Combo Project Request for Qualifications Additional Information and Clarifications #1. RFQ No. 1708.057. Issued: March 9, 2011

RBRC Combo Project Request for Qualifications Additional Information and Clarifications #1. RFQ No. 1708.057. Issued: March 9, 2011 REQUEST FOR QUALIFICATIONS ROBERTS BANK RAIL CORRIDOR PROGRAM 192 ND STREET, 54 TH AVE., 196 TH STREET COMBO PROJECT RFQ No. 1708.057 ADDITIONAL INFORMATION AND CLARIFICATIONS NO. 1 Issued: March 9, 2011

More information

Evergreen Line Rapid Transit Project

Evergreen Line Rapid Transit Project Evergreen Line Rapid Transit Project Preliminary Design November 2009 www.evergreenline.gov.bc.ca Evergreen Line Connecting Coquitlam, Port Moody, Burnaby and Vancouver What is the Evergreen Line Project?

More information

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation

More information

LBJ Freeway in Dallas

LBJ Freeway in Dallas LBJ Freeway in Dallas Texas/USA Ferrovial Agroman is redeveloping the LBJ Freeway to increase capacity and relieve severe congestion in one of the fastest growing areas in the United States. Ribera del

More information

Project and site organization of a NATM tunnel project on the example of the Koralm tunnel. Hanns Wagner OBB Austrian Federal Railways

Project and site organization of a NATM tunnel project on the example of the Koralm tunnel. Hanns Wagner OBB Austrian Federal Railways Project and site organization of a NATM tunnel project on the example of the Koralm tunnel Hanns Wagner OBB Austrian Federal Railways Requirements for a successful application of NATM Design, which considers

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF MARCH 19, 2013

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF MARCH 19, 2013 CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF MARCH 19, 2013 Item 9, Report No. 9, of the Committee of the Whole, which was adopted, as amended, by the Council of the City of Vaughan on March

More information

Engineers Australia. Delivering the North West Rail Link. Stuart Suthern-Brunt, Deputy Project Director, Operations Trains and Systems

Engineers Australia. Delivering the North West Rail Link. Stuart Suthern-Brunt, Deputy Project Director, Operations Trains and Systems Engineers Australia Delivering the North West Rail Link Stuart Suthern-Brunt, Deputy Project Director, Operations Trains and Systems The $8.3 billion Sydney Metro Northwest is Australia s largest public

More information

Transportation Asset Management Best Practices for Canada

Transportation Asset Management Best Practices for Canada Primer Transportation Asset Management Best Practices for Canada Introduction Canada ranks seventh in the world in terms of road network size, with a two-lane equivalent length of 1.04 million kilometres,

More information

Nashville Area MPO Regional Freight Study fast action projects

Nashville Area MPO Regional Freight Study fast action projects Project #1 Beechcroft road (sr 247) at csx crossing Motor carrier survey location Maury County (Spring Hill, Tn) / City of Spring Hill Current at-grade railway crossing causes traffic delays as a result

More information

Alberta Schools Alternative Procurement (ASAP) Projects. Public School Construction Program September 19, 2011 Baltimore, USA

Alberta Schools Alternative Procurement (ASAP) Projects. Public School Construction Program September 19, 2011 Baltimore, USA Alberta Schools Alternative Procurement (ASAP) Projects Public School Construction Program September 19, 2011 Baltimore, USA Presentation Outline P3 s in Alberta - An Overview Alberta Schools (ASAP) Projects

More information

What s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM

What s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM What s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM Progressive design-build: A better way? Discussion topics: What is progressive design-build?

More information

Median Bus Lane Design in Vancouver, BC: The #98 B-Line

Median Bus Lane Design in Vancouver, BC: The #98 B-Line Li 1 Median Bus Lane Design in Vancouver, BC: The #98 B-Line Simon Li, P.Eng. PTOE Acting Program Manager, Road and Bridge Projects TransLink (Greater Vancouver Transportation Authority) 1600 4720 Kingsway

More information

The AMT s Reno-Tunnel Program : Improving Safety in the Mount-Royal Tunnel Is the Result of a Partnership with the Montreal Fire Department

The AMT s Reno-Tunnel Program : Improving Safety in the Mount-Royal Tunnel Is the Result of a Partnership with the Montreal Fire Department The AMT s Reno-Tunnel Program : Improving Safety in the Mount-Royal Tunnel Is the Result of a Partnership with the Montreal Fire Department ISTSS 2016 - AMT s conference Jean-Philippe Pelletier, eng.,

More information

Looking for new opportunities of investment for the PPPs projects. The keys of the success for PPPs in railway sector

Looking for new opportunities of investment for the PPPs projects. The keys of the success for PPPs in railway sector Looking for new opportunities of investment for the PPPs projects The keys of the success for PPPs in railway sector Doris CHEVALIER Paris 14 Juin 2013 1 2 French expertise for railway PPPs French expertise

More information

AEG-ASCE SHORT COURSE

AEG-ASCE SHORT COURSE AEG-ASCE SHORT COURSE TUNNELS THROUGH FAULT ROCKS AND TECTONIC MELANGES May 31 and June 1, 2002 Gunter Riedmueller and Wulf Schubert Course Outline! Introduction! Characterization and Classification! Investigation!

More information

MINISTRY OF EDUCATION AND SASKBUILDS SASKATCHEWAN JOINT-USE SCHOOLS PROJECT PROJECT #2

MINISTRY OF EDUCATION AND SASKBUILDS SASKATCHEWAN JOINT-USE SCHOOLS PROJECT PROJECT #2 June 5, 2015 MINISTRY OF EDUCATION AND SASKBUILDS SASKATCHEWAN JOINT-USE SCHOOLS PROJECT PROJECT #2 FINAL REPORT OF THE FAIRNESS ADVISOR ON THE PROCUREMENT PROCESS: RFP STAGE TO: STEERING COMMITTEE, SASKATCHEWAN

More information

Request for Proposals for. Dam Safety and Floodplain Management Database Services DSFPM RFP 2015-1

Request for Proposals for. Dam Safety and Floodplain Management Database Services DSFPM RFP 2015-1 Request for Proposals for Dam Safety and Floodplain Management Database Services DSFPM RFP 2015-1 Arkansas Natural Resources Commission December 2015 A. INTRODUCTION The Arkansas Natural Resources Commission

More information

Implementation of PPPs for Transit: The Request for Proposal Process ADVISORY

Implementation of PPPs for Transit: The Request for Proposal Process ADVISORY Implementation of PPPs for Transit: The Request for Proposal Process ADVISORY Agenda KPMG Introduction The Gotham BIA Connector The initial stages RFI to RFQ The final stages RFP to Evaluation 2 KPMG Infrastructure

More information

Getting Connected with the Colorado Department of Transportation (CDOT)

Getting Connected with the Colorado Department of Transportation (CDOT) Getting Connected with the Colorado Department of Transportation (CDOT) INTRODUCTION Who is CDOT? CDOT is responsible for 9,146 miles of highway including 3,447 bridges State government agency with funding

More information

Vendor Performance Evaluation

Vendor Performance Evaluation Vendor Performance Evaluation Canadian Public Procurement Council Oct. 27-29, 2014 Agenda 1) Objectives and 2) Evaluation 3) Evaluation Templates and 4) Use of Vendor Score 2 13:00 14:00 1 Objectives and

More information

REQUEST FOR PROPOSALS For. Kelowna and Vernon Hospitals Project

REQUEST FOR PROPOSALS For. Kelowna and Vernon Hospitals Project REQUEST FOR PROPOSALS For The Kelowna and Vernon Hospitals Project VOLUME 2 of 4 Instructions to Proponents Closing Time: Delivery Address: 3:00 pm (local time) Thursday, March 6,2008 Kelowna and Vernon

More information

MARKHAM STOUFFVILLE HOSPITAL EXPANSION AND REDEVELOPMENT PROJECT

MARKHAM STOUFFVILLE HOSPITAL EXPANSION AND REDEVELOPMENT PROJECT Insert VFM letter VALUE FOR MONEY ASSESSMENT MARKHAM STOUFFVILLE HOSPITAL EXPANSION AND REDEVELOPMENT PROJECT - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - Markham Stouffville Hospital Artist s Rendering

More information

The Follo Line Project

The Follo Line Project The Follo Line Project Longest. UrbAN. Complex. Faster. 2015/1 Norwegian National Rail Administration the follo line project 1 2 the follo line project The project The Follo Line Project is currently the

More information

Member Nation Report 2010 from Denmark.

Member Nation Report 2010 from Denmark. Member Nation Report 2010 from Denmark. The has during the year 2010 arranged 6 member meetings including two technical site visits. The first technical site visit covered the 5.3 km long Leipzig City

More information

EXPANDING PRESTO ON TTC: STATUS UPDATE

EXPANDING PRESTO ON TTC: STATUS UPDATE EXPANDING PRESTO ON TTC: STATUS UPDATE Robert Hollis, Executive Vice President, PRESTO Chris Upfold, Deputy CEO and Chief Customer Officer, TTC APRIL 27, 2016 WHY PRESTO Offering 1.8 million customers

More information

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26 Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain

More information

TOWN OF BERLIN REQUEST FOR QUALIFICATIONS

TOWN OF BERLIN REQUEST FOR QUALIFICATIONS TOWN OF BERLIN REQUEST FOR QUALIFICATIONS Notice is hereby given that qualifications will be received by the Town of Berlin, Maryland for: RFQ # 2015 4 Community Solar Garden: Design, Build, Finance, Operate

More information

PROPANE EDUCATION & RESEARCH COUNCIL. Request for Proposals to Develop an Aftermarket Bi-Fuel Propane Autogas Vehicle System. Posted August 15, 2011

PROPANE EDUCATION & RESEARCH COUNCIL. Request for Proposals to Develop an Aftermarket Bi-Fuel Propane Autogas Vehicle System. Posted August 15, 2011 PROPANE EDUCATION & RESEARCH COUNCIL Request for Proposals to Develop an Aftermarket Bi-Fuel Propane Autogas Vehicle System Posted August 15, 2011 General Information The Propane Education & Research Council

More information

C a b l i n g s o l u t i o n s a t t h e c o r e o f R a i l w a y N e t w o r k s

C a b l i n g s o l u t i o n s a t t h e c o r e o f R a i l w a y N e t w o r k s C a b l i n g s o l u t i o n s a t t h e c o r e o f R a i l w a y N e t w o r k s High Speed Line (HSL) Zuid The Netherlands - Siemens project Dedicated 100 km high speed rail line between Antwerp (Belgium)

More information

North-South Bypass Tunnel Project. Coordinator-General s Change Report

North-South Bypass Tunnel Project. Coordinator-General s Change Report North-South Bypass Tunnel Project Coordinator-General s Change Report July 2006 1.0 INTRODUCTION 1.1 Background 1.2 Proponent and proposed delivery mode 1.3 Council s Request for Project Change 2.0 DESCRIPTION

More information

5 ALTERNATIVE SOLUTIONS AND EVALUATION

5 ALTERNATIVE SOLUTIONS AND EVALUATION Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable

More information

3.05. Infrastructure Ontario Alternative Financing and Procurement. Chapter 3 Section. Background. Alternative Financing and Procurement

3.05. Infrastructure Ontario Alternative Financing and Procurement. Chapter 3 Section. Background. Alternative Financing and Procurement Chapter 3 Section 3.05 Infrastructure Ontario Alternative Financing and Procurement Background Alternative Financing and Procurement Alternative Financing and Procurement (AFP) is the name given to the

More information

Availability Payment Mechanisms For Transit Projects ADVISORY

Availability Payment Mechanisms For Transit Projects ADVISORY Availability Payment Mechanisms For Transit Projects ADVISORY Agenda Availability Payments Overview Structure Financial Implications Case Study Additional Considerations KPMG Infrastructure 2 What is an

More information

DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE

DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE ARIZONA DEPARTMENT OF TRANSPORTATION INTERMODAL TRANSPORTATION DIVISION DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE 3rd Edition December 2007 Published by: ADOT Construction Group 206 S. 17 th Ave.,

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of Azerbaijan, the Ministry of Transport and Baku Metro Company requested ADB to help improving its urban transport system and

More information

REQUEST FOR INFORMATION FOR #2015-12 POINT OF SALE SYSTEM. November 18, 2015

REQUEST FOR INFORMATION FOR #2015-12 POINT OF SALE SYSTEM. November 18, 2015 REQUEST FOR INFORMATION FOR #2015-12 POINT OF SALE SYSTEM November 18, 2015 Questions Due: December 9, 2015 at 12:00 p.m. SUBMISSIONS DUE: December 18, 2015 at 11:00 a.m. 2425 NE 65th Avenue ~ PO Box 2529

More information

Project Report: Evergreen Line Rapid Transit Project

Project Report: Evergreen Line Rapid Transit Project Project Report: Evergreen Line Rapid Transit Project March 2013 Purpose of this Report The purpose of this report is to provide key information to the public about the Evergreen Line Rapid Transit Project

More information

The Gateway Program and Hudson Tunnel Project

The Gateway Program and Hudson Tunnel Project The Gateway Program and Hudson Tunnel Project Presented to: NJ State Senate Oversight Committee Stephen Gardner Executive Vice President NEC Business Development August 10, 2015 1 The Need for Gateway

More information

Request for Proposal. City of Atlanta Taxicab Industry Analysis. May 30, 2012

Request for Proposal. City of Atlanta Taxicab Industry Analysis. May 30, 2012 City of Atlanta Taxicab Industry Analysis May 30, 2012 Contact: Kristi Rooks Central Atlanta Progress, Inc. 50 Hurt Plaza SE, Suite 110 Atlanta, GA 30303 (404) 658-5911 and krooks@atlantadowntown.com Page

More information

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874 ADVERTISEMENT FOR LETTERS OF INTEREST FOR A DESIGN BUILD PROJECT (PROCUREMENT METHOD SHORTLISTING OF PROPOSERS WITH TECHNICAL AND PRICE EVALUATION BY ADJUSTED SCORE) PROCUREMENT NUMBER: E2N44 Financial

More information

5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES

5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES 5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES 5.1 FINANCIAL ANALYSIS The cost of a transportation investment falls into two categories: capital costs, and operating and maintenance (O&M) costs.

More information

Procurement Management. Scott Coplan, PMP David Masuda, M.D.

Procurement Management. Scott Coplan, PMP David Masuda, M.D. Procurement Management Scott Coplan, PMP David Masuda, M.D. 1 Procurement Management Procurement management is planning, executing and controlling acquisition of goods and services necessary to support

More information

Southwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014)

Southwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014) Southwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014) Summary Description Proposed Project: Light Rail Transit 15.7 Miles, 17 Stations

More information

DATA MANAGEMENT SYSTEM FOR TUNNELLING

DATA MANAGEMENT SYSTEM FOR TUNNELLING DATA MANAGEMENT SYSTEM FOR TUNNELLING A working tool for data acquisition, visualization AND Reporting 2 IRIS Integrated Risk and Information System A single software solution for integrated data management

More information

Request for Qualifications November 2007 GIS Migration and Modeling Page 1 TABLE OF CONTENTS. 1.0 Overview. 2.0 General Information

Request for Qualifications November 2007 GIS Migration and Modeling Page 1 TABLE OF CONTENTS. 1.0 Overview. 2.0 General Information REQUEST FOR QUALIFICATIONS GIS Migration and Modeling November 2007 Closing Date: Wednesday, December 5, 2007 Closing Time: 3:00 p.m. (Local Time) Halifax Water 450 Cowie Hill Road P.O. Box 8388, Station

More information

Port Mann/Highway 1 Project Request For Proposals Volume 1 Instructions to Proponents

Port Mann/Highway 1 Project Request For Proposals Volume 1 Instructions to Proponents Port Mann/Highway 1 Project Request For Proposals Volume 1 Instructions to Proponents August 7, 2007 PAGE 1 OF 57 Table of Contents 1. Introduction... 5 1.1 Project Scope Overview... 5 1.2 Short-listed

More information

Owner s Procurement Forum

Owner s Procurement Forum Washington Metropolitan Area Transit Authority Construction Management Association of America National Capitol Chapter Owner s Committee Owner s Procurement Forum February 24, 2015 OVERVIEW of WMATA INFRASTRUCTURE:

More information

EXECUTIVE SUMMARY. Salini Impregilo / Healy / GLF Joint Venture

EXECUTIVE SUMMARY. Salini Impregilo / Healy / GLF Joint Venture EXECUTIVE SUMMARY statement of qualifications chesapeake bay bridge and tunnel district EXECUTIVE SUMMARY With extensive international tunneling and marine design and construction experience, Salini Impregilo/Healy/GLF

More information

How to implement cycling solutions in a post-communist street system (and mentality) Marcin Hyła, VeloForum, 16 Oct.

How to implement cycling solutions in a post-communist street system (and mentality) Marcin Hyła,  VeloForum, 16 Oct. How to implement cycling solutions in a post-communist street system (and mentality) Marcin Hyła, www.miastadlarowerow.pl VeloForum, 16 Oct. 2010 th What has communism to do with cycling? No free flow

More information

Track and Track Drainage Renewals Programme

Track and Track Drainage Renewals Programme Board Date: 26 March 2015 Item 14: Track and Track Drainage Renewals Programme This paper will be considered in public 1 Summary Track and Track Drainage Renewals Programme Existing Estimated Existing

More information

NETLIPSE NETWORK MEETING 27-28.5.2013 Seppo Mäkinen Finnish Transport Agency 27.5.2013

NETLIPSE NETWORK MEETING 27-28.5.2013 Seppo Mäkinen Finnish Transport Agency 27.5.2013 NETLIPSE NETWORK MEETING 27-28.5.2013 Seppo Mäkinen Finnish Transport Agency 27.5.2013 Mainroad 4 Järvenpää Lahti PPP Project 1997 2012 FINLAND 27.5.2013 27.5.2013 Seppo Mäkinen Mainroad 4 Järvenpää -

More information

Advanced Construction Techniques

Advanced Construction Techniques Alaskan Way Viaduct Replacement Program Organization University of Washington Date October 20, 2011 Presentation Overview SR 99 south end viaduct replacement. Design-build contracting. SR 99 tunnel project.

More information

4.03. Brampton Civic Hospital Public-private Partnership Project. Chapter 4 Section. Background. Follow-up on VFM Section 3.03, 2008 Annual Report

4.03. Brampton Civic Hospital Public-private Partnership Project. Chapter 4 Section. Background. Follow-up on VFM Section 3.03, 2008 Annual Report Chapter 4 Section 4.03 Brampton Civic Hospital Public-private Partnership Project Follow-up on VFM Section 3.03, 2008 Annual Report Background In 2001, the then Minister of Finance announced that public

More information

Business Opportunities Seminar

Business Opportunities Seminar Business Opportunities Seminar In Finland, Norway, Denmark, Ireland and The Netherlands (22 29 September 2015) Presented by: Rustam Abdukayumov Senior Procurement Specialist Operations Services and Financial

More information

Program Management. APWA North Carolina Chapter. Design-Build: Will it Work for You? William Palmieri, P.E.

Program Management. APWA North Carolina Chapter. Design-Build: Will it Work for You? William Palmieri, P.E. APWA North Carolina Chapter Design-Build: Will it Work for You? Program Management William Palmieri, P.E. HDR Engineering, Inc. 695 Atlantic Avenue Boston, MA. 02111 (512) 627-6300 (m) August 6, 2015 William

More information

Atrium Skylight Repair Carleton Lodge

Atrium Skylight Repair Carleton Lodge Requirement Period of Contract The successful bidder shall complete the work no later than 27 November 2015. Closing Date Quotations must be submitted no later than close of business day (11:59 pm) on

More information

CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR

CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA RSTP Funds Joint Application FOR Tinker Creek Pedestrian Bridge: Tinker Creek and Glade Creek Greenways Connection Date: September 15, 2014 RSTP Project Profile

More information

REQUEST FOR QUALIFICATIONS for SURREY PRETRIAL SERVICES CENTRE EXPANSION PROJECT RFQ #3225 VOLUME 1 PROJECT BRIEF

REQUEST FOR QUALIFICATIONS for SURREY PRETRIAL SERVICES CENTRE EXPANSION PROJECT RFQ #3225 VOLUME 1 PROJECT BRIEF Ministry of Public Safety and Solicitor General Ministry of Citizens Services Shared Services BC REQUEST FOR QUALIFICATIONS for SURREY PRETRIAL SERVICES CENTRE EXPANSION PROJECT RFQ #3225 VOLUME 1 PROJECT

More information