Ottawa s Light Rail Transit Project - The Confederation Line
|
|
- Dinah Willis
- 7 years ago
- Views:
Transcription
1 Ottawa s Light Rail Transit Project - The Confederation Line National Capital Heavy Construction Association January 30, 2013 Rail Implementation Office
2 Overview of the Presentation Project Background & Timeline Procurement and evaluation process Project Description: Stations plus the maintenance and storage facility LRT vehicle Tunnel construction HWY 417 widening Cash Allowance Projects Capital costs Construction schedule Transit detours
3 Need
4 Timeline November 2008: the previous Council approved the Transportation Master Plan update that identified Downtown Ottawa Transit Tunnel (DOTT) as its first priority project for Light Rail Transit (LRT) January 2010: the previous Council approved the DOTT Planning and Environmental Assessment Study providing authority to begin the expedited Environmental Assessment process, Preliminary Engineering and Property acquisition. September 2010: commence Preliminary Engineering activities and property acquisition for Ottawa s Light Rail Transit (OLRT) project.
5 Timeline May 2011: Council approved the OLRT Schedule Acceleration and Procurement Option Selection report that: an accelerated schedule that advanced completion from 2019 to Spring 2018 and, the use of Infrastructure Ontario s Alternative Finance Procurement (AFP) process using a Design-Build-Finance-Maintain model. July 2011: Council approved the OLRT Implementation report that: presented the new tunnel alignment on Queen Street, re-established the $2.1 billion budget, directed staff to implement the OLRT project using a Design Build Finance Maintain (DBFM) procurement model, and authorized the engagement of Infrastructure Ontario as the City s procurement agent.
6 Timeline October 2011: the Request for Qualification (RFQ) process resulted in a shortlist of three private sector teams June 2012: the planned widening of the Highway 417 project is bundled with the OLRT project to allow alternative Bus Rapid Transit system before the east end Transitway closure September/October 2012: RFP submittals Technical / Financial October/November 2012: Proposal evaluations December 2012: Council approves contract award
7 Timeline Procurement Phase Design Phase Construction Phase Highway 417 Operational LRT Operational Council Approval 19 Dec 2012
8 Alignment 12.5 Km long 13 Stations 2.5 Km Tunnel 8
9 Procurement The project was procured as a Design, Build, Finance and Maintain (DBFM) with a 30 year concession period Inclusion of Hwy 417 widening, from Nicholas to Hwy174 Split Inclusion of Cash Allowance projects
10 Procurement The RFP included set of financial incentives to encourage higher performance on key issues Operations matters: examined the number of drivers needed to operate the system and this impact on the City s operating costs Mobility matters: encouraged an approach to construction that minimized the number of lane closures on the Transitway as well as on roads Energy matters: developed a long-term affordability and efficiency plan for the system as the City pays these energy costs
11 Evaluation The evaluations took place in four distinct steps: Completeness Verification: Proposals were reviewed by a Completeness Review Team to ensure that the three submissions included all mandatory information. Compliance Review: A separate Compliance Team undertook a detailed review of each Proponent s design to ensure it complied with the requirements of the RFP and output specifications. Technical Evaluation: The Technical review team was made up of subject matter experts on project design and engineering. Financial Evaluation: The Financial review team was made up of subject matter experts on Alternative Finance and Procure (AFP) procurement and public and private financing.
12 The Recommended Team The recommended preferred proponent received the highest technical and financial score The preferred proponent also assumed the full geotechnical risk of the tunnel that the City sought. Currently working with the preferred proponent to reach Financial Close.
13 Rideau Transit Group (RTG)
14 Rideau Transit Group (RTG) RTG is well positioned to deliver the Confederation Line ; its team members have previously : completed 80 large-scale transportation P3 projects, been awarded more than $13 billion in work in North America since 2009, constructed more than 1,360 km of tunnel, delivered more than 2,500 km of rail/mass transit projects worldwide Some of its well known projects include: the Canada Line (Vancouver), Seville Line 1 (Spain), Ankara Metro (Turkey) and Barcelona Metro Line 1 (Spain)
15 Our 13 Stations 15
16 The Stations Tunney s Pasture 16
17 Tunney s Pasture 17
18 Tunney s Pasture 18
19 Bayview 19
20 Bayview 20
21 Lebreton 21
22 Lebreton 22
23 Downtown West 23
24 Downtown West 24
25 Downtown West (includes integrated entrance in Place de Ville) 25
26 Downtown East (East) 26
27 Downtown East (includes integrated entrance in Sun Life) 27
28 Downtown East 28
29 Rideau (includes integrated entrance in Rideau Centre) 29
30 Rideau 30
31 Rideau 31
32 Campus 32
33 Campus 33
34 Lees 34
35 Lees 35
36 Hurdman 36
37 Hurdman 37
38 Hurdman 38
39 Train 39
40 Train 40
41 St. Laurent 41
42 St. Laurent 42
43 Cyrville 43
44 Cyrville 44
45 Blair Gloucester Mall 45
46 Blair 46
47 Blair 47
48 Maintenance & Storage Facility Train Yard Mall Area 48
49 Maintenance & Storage Facility 49
50 OLRT Vehicle - Citadis by Alstom Streetcar version of the Citadis used in Belgium Streetcar version of the Citadis used in Istanbul 50
51 Tunnel Construction Will take place at three entry points: the east portal, west portal and a central shaft site at Queen Street and Kent Street. Will minimize surface disruption by not using cut and cover construction for the stations Will not utilize a TBM and the only real evidence of its construction will be from the construction of the station entrances and ventilation shafts The downtown construction sites will be relatively modest and we do not expect requiring a full closure of the street
52 Tunnel Construction Rideau Downtown East East Portal Excavation Shaft West Portal Downtown West Bronson Avenue 52
53 Tunnel Construction Sequential Excavation Method using Roadheaders 53
54 Noise & Vibration Mitigation Resilient Fastener Devices Floating Trackbed 54
55 Highway 417 Widening Nicholas to OR 174 March Coventry Bridge Project Limits MTO Bridges City of Ottawa Bridges Rapid Bridge Replacement Sites
56 Cash Allowance Projects 1- Transitway Rock Stabilization Cash Allowance: $3M 2- Albert Street Utilities Cash Allowance: $20M 3- CSST Cash Allowance: $8.7M 4- Queen Street Original Cash Allowance: $8M 5- Coventry Bridge Cash Allowance: $8.8M 56
57 Capital Costs Cost Area Budget Property, Engineering, Property Management $275M Tunnel & Stations $681M Track Work, Systems, MSF Facility $551M Civil Works $102M Vehicles $344M Financing & SPV Costs $176M OLRT Total $2.130B HWY 417 Widening $214M HWY 417 Transit Priority $12M OLRT Transition $63M Multi Project Contingency: $100M HWY 417/Mobility Total $289M Project TOTAL $2.419B 57
58 Construction Schedule Awaiting Scott Street Widening Awaiting Tunnel Delayed as much as possible to not to interfere with Nicholas Offline - Independent Awaiting 417 widening
59 QUESTIONS? 59
4 SPADINA SUBWAY EXTENSION UPDATE
4 SPADINA SUBWAY EXTENSION UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the adoption of the recommendations contained in the following report June 13, 2006, from the
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: June 24, 2014 SUBJECT: SCARBOROUGH SUBWAY EXTENSION - UPDATE ACTION ITEM RECOMMENDATION It is recommended that the Board: i. Receive
More informationSPO Technical Capacity Review. June 24, 2015
SPO Technical Capacity Review June 24, 2015 Southwest Project Context The Southwest Light Rail Transit (LRT) project (METRO Green Line Extension) will operate from downtown Minneapolis through the communities
More informationBusiness Case. Ottawa Public Library Main Library Facility May 2015
Business Case Ottawa Public Library Main Library Facility May 2015 The information contained in this document is proprietary to the Ottawa Public Library and the City of Ottawa. Unauthorized distribution
More informationConstruction impacted by existing rock valley. Access shafts required Rideau Street, Triangle lands, North of NAC
Rideau Alignment Daly Alignment Mackenzie-King Alignment Rideau Alignment Profile Rideau Station Catchment Area Rideau Station Issues Constructed by tunnelling and mining Construction impacted by existing
More informationCRENSHAW/LAX TRANSIT CORRIDOR PROJECT
CRENSHAW/LAX TRANSIT CORRIDOR PROJECT A New Beginning for the Crenshaw Corridor Through Use of Innovative Procurement Strategies Robert Ball, P.E. and Kimberly Ong, P.E. Los Angeles Metropolitan Transportation
More informationRegion of Waterloo Finance Department Financial Services and Development Financing
Region of Waterloo Finance Department Financial Services and Development Financing To: Chair Jim Wideman and Members of the Planning and Works Committee Date: May 27, 2014 File Code: T16-01 Subject: Stage
More information1. RECOMMENDATIONS. It is recommended that:
Clause No. 7 in Report No. 3 of was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on February 20, 2014. (Mayor Hackson declared an interest in this
More informationSTAFF REPORT ACTION REQUIRED
STAFF REPORT ACTION REQUIRED Procurement Authorization Scarborough Subway Extension Project Management Services Contract FE85-3 Date: February 25, 2015 To: From: TTC Board Chief Executive Officer Summary
More informationInfrastructure Ontario Borrowing Today for the City of Tomorrow Session #1 Steve Rohacek, Vice President, Municipal Business Development & Lending
Click to edit Master title style Infrastructure Ontario Borrowing Today for the City of Tomorrow Session #1 Steve Rohacek, Vice President, Municipal Business Development & Lending www.infrastructureontario.ca
More informationREQUEST FOR PROPOSAL SPECTATOR FACILITY FEASIBILITY STUDY ADDENDUM NO. 1
Financial Management Services Purchasing Division Request for Proposal Spectator Facility Feasibility Study REQUEST FOR PROPOSAL FOR A SPECTATOR FACILITY FEASIBILITY STUDY ADDENDUM NO. 1 This addendum
More informationEffect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain
Effect on structures Uniform settlement - no concerns Angular distortion - causes damage due to tensile strain 1/500 - safe limit for no cracking of buildings 1/150 - potential structural damage 36 37
More informationAlstom Transport supplier of Tram Systems in PPP schemes
Alstom Transport supplier of Tram Systems in PPP schemes Arnaud de Monts 04/04/2014 Various procurement schemes A tramway system can be procured in various schemes, each of them have been experimented
More informationB1 Project Management 100
Assignment of points B1 Project Management 100 Requirements for Design Presentation Meetings and Proposal Submissions for Key to Project Management Design Presentation Meeting and Proposal Submissions
More informationAppendix D. Public Information Centre Summary Report
Appendix D Public Information Centre Summary Report HIGHWAY 417 EXPANSION, OPERATIONAL IMPROVEMENTS AND INFRASTRUCTURE REHABILITATION From Nicholas Street to Ottawa Road 174 Detail Design G.W.P. 4091 07
More informationGENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES
REQUEST FOR QUALIFICATIONS GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES NEW DINING HALL MONTANA STATE UNIVERSITY Bozeman, Montana PPA NO. 15-0103 Campus Planning, Design & Construction Plew Building
More informationDesign-Build Process for Project Managers
Vermont Agency of Transportation Design-Build Process for Project Managers This document provides guidance on the preliminary engineering and procurement process and roles and responsibilities of key personnel
More informationPublic Health Services - The Cost of Doing Data Centre Project in Ontario, Canada
VALUE FOR MONEY ASSESSMENT MINISTRY OF GOVERNMENT SERVICES NEW DATA CENTRE - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - Table of Contents Summary...6 Project description...8 Competitive selection process
More informationNeed for the scheme. The project will bring a number of benefits to road users including:
Introduction Welcome to our Project Bank Account (PBA) industry briefing event for the A96 Inveramsay Bridge Improvement Project, which is the first Scottish road infrastructure project to use a PBA. The
More informationCOWI s Role in the Copenhagen Metro Project
COWI s Role in the Copenhagen Metro Project On the occasion of the award by the Copenhagen Cultural Foundation for COWI A/S part in the implementation of Phase 1 of the Copenhagen Metro 2 COWI s Role in
More informationAppendix A Alternative Contracting General Engineering Consultant RFP. Appendix A
Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement
More informationTransit, Rail, Program, Project & Construction Management Experience
Point of Contact Peter M. Cipolla Vice President, Rail & Transit Mobile: 925.219.5235 Email: peter.cipolla@hatchmott.com Project Management Oversight Services Introduction & Background Hatch Mott MacDonald
More informationExecutive Director, Engineering & Construction Services Director, Purchasing & Materials Management Division
PW8.5 STAFF REPORT ACTION REQUIRED Contract Award Request for Proposal No. 9117-15-7122 Engineering Services for the Detailed Design, Services During Construction, and Post-Construction Services for an
More informationRFP 43-14: STREETCAR OPERATIONS & MAINTENANCE SERVICE CONTRACT. Cincinnati Streetcar Project June 2015
RFP 43-14: STREETCAR OPERATIONS & MAINTENANCE SERVICE CONTRACT Cincinnati Streetcar Project June 2015 O&M timeline March 2015 - O&M RFP proposals due April-May 2015 Proposal evaluation and negotiations
More informationCoordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit
Coordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit Public Information Session May 31, 2016 Transportation
More informationPrepared by David Willson, OCIO in consultation with Marc Buchalter, Procurement Please send comments to David Willson at dwillson@berkeley.
Technology RFX Customer Guide Introduction This guide is intended for those that have identified a need to solicit bids from suppliers but may unclear on the different types of documents, the roles various
More informationRapid Transit Backgrounder
Rapid Transit Backgrounder Moving Forward On Rapid Transit The concept of a Rapid Transit System for Winnipeg has been debated for over 30 years. City Council and the Province of Manitoba have demonstrated
More information6.0 Procurement procedure 1 Infrastructure
Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement
More informationWelcome to the LRT Overview Open House
Welcome to the LRT Overview Open House Please sign-in so that we may provide you with updates on future events. TORONTO LRT OVERVIEW Importance of Transit to Cities Increase City s competitiveness (World
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF JULY 31, 2015 SEPTEMBER 2015 Phase 2 Cost Summary July Expenditures $ 19.2 Million Total Expenditures $ 508.7 Million
More informationTAPPAN ZEE HUDSON RIVER CROSSING PROJECT
New York State Department of Transportation New York State Thruway Authority TAPPAN ZEE HUDSON RIVER CROSSING PROJECT DESIGN-BUILD PROJECT RESPONSES TO PROPOSERS S REFERENCE NUMBER: This page is intentionally
More informationRisk Management in the Development of a Penta-P Project
Risk Management in the Development of a Penta-P Project Bill Van Meter Regional Transportation District Denver, CO Julie Skeen Jacobs Engineering Denver, CO Damian Carey Jacobs Engineering Denver, CO Don
More informationARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT DESIGN-BUILD GUIDELINES AND PROCEDURES
ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT DESIGN-BUILD GUIDELINES AND PROCEDURES Revision 1 September 2015 TABLE OF CONTENTS Section I. Introduction 6 PURPOSE 6 AUTHORITY 6 DEFINITIONS AND ACRONYMS
More informationDecember 2015. Project Report. Stanton Territorial Hospital 20567651.3
Project Report Stanton Territorial Hospital December 2015 1 Purpose of this project report The purpose of this project report ( Project Report ) is to provide key information to the public about the Stanton
More informationPurple Line Implementation Advisory Group Business Continuity During Construction July 30, 2014
Purple Line Implementation Advisory Group Business Continuity During Construction July 30, 2014 Economic Empowerment Program Scope of Work Providing advocacy for small and disadvantaged business capacity,
More informationMOTION NO. M2015-63 WSDOT Task Order for Final Design Services PROPOSED ACTION
MOTION NO. M2015-63 WSDOT Task Order for Final Design Services MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee 07/09/15 Final Action Ahmad Fazel, DECM Executive Director Ron Lewis, East
More informationGTA Cordon Count Program
Transportation Trends 2001-2011 Executive Summary Project No. TR12 0722 September 2013 1.0 Introduction The Cordon Count program was established to collect traffic data as a tool for measuring travel trends
More informationEvergreen Line Rapid Transit Project Business Case Executive Summary. February 2008. Reviewed by
Evergreen Line Rapid Transit Project Business Case Executive Summary February 2008 Reviewed by Recommendation and Executive Summary The business case for the Evergreen Line Rapid Transit Project (the Project)
More informationItem No. 10.1.1 Halifax Regional Council September 28, 2010
PO Box 1749 Halifax, Nova Scotia B3J 3A5, Canada Item No. 10.1.1 Halifax Regional Council September 28, 2010 TO: Mayor Kelly and Members of Halifax Regional Council SUBMITTED BY: Mike Labrecque, Acting
More informationWhat is Alternate Delivery?
What is Alternate Delivery? Hans VanPoorten, MBA, P.Eng. Vice President Advisory Services CSVA Conference, 2011 Presentation Contents P3 History, Market and MMM Credentials Process Typical P3 Infrastructure
More informationConsolidated I&T Data Centre - P3 Canada Fund
STAFF REPORT ACTION REQUIRED Consolidated I&T Data Centre - P3 Canada Fund Date: January 16, 2012 To: From: Wards: Reference Number: Government Management Committee Deputy City Manager & Chief Financial
More informationManaged Services Consulting. Europe, Asia, Africa, Middle East, Latin America, North America
Managed Services Consulting Europe, Asia, Africa, Middle East, Latin America, North America New Vibrations Consulting Services Contents New Vibrations Consulting Managed Services Consulting Feasibility
More informationRBRC Combo Project Request for Qualifications Additional Information and Clarifications #1. RFQ No. 1708.057. Issued: March 9, 2011
REQUEST FOR QUALIFICATIONS ROBERTS BANK RAIL CORRIDOR PROGRAM 192 ND STREET, 54 TH AVE., 196 TH STREET COMBO PROJECT RFQ No. 1708.057 ADDITIONAL INFORMATION AND CLARIFICATIONS NO. 1 Issued: March 9, 2011
More informationEvergreen Line Rapid Transit Project
Evergreen Line Rapid Transit Project Preliminary Design November 2009 www.evergreenline.gov.bc.ca Evergreen Line Connecting Coquitlam, Port Moody, Burnaby and Vancouver What is the Evergreen Line Project?
More informationAmendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling
Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation
More informationLBJ Freeway in Dallas
LBJ Freeway in Dallas Texas/USA Ferrovial Agroman is redeveloping the LBJ Freeway to increase capacity and relieve severe congestion in one of the fastest growing areas in the United States. Ribera del
More informationProject and site organization of a NATM tunnel project on the example of the Koralm tunnel. Hanns Wagner OBB Austrian Federal Railways
Project and site organization of a NATM tunnel project on the example of the Koralm tunnel Hanns Wagner OBB Austrian Federal Railways Requirements for a successful application of NATM Design, which considers
More informationCITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF MARCH 19, 2013
CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF MARCH 19, 2013 Item 9, Report No. 9, of the Committee of the Whole, which was adopted, as amended, by the Council of the City of Vaughan on March
More informationEngineers Australia. Delivering the North West Rail Link. Stuart Suthern-Brunt, Deputy Project Director, Operations Trains and Systems
Engineers Australia Delivering the North West Rail Link Stuart Suthern-Brunt, Deputy Project Director, Operations Trains and Systems The $8.3 billion Sydney Metro Northwest is Australia s largest public
More informationTransportation Asset Management Best Practices for Canada
Primer Transportation Asset Management Best Practices for Canada Introduction Canada ranks seventh in the world in terms of road network size, with a two-lane equivalent length of 1.04 million kilometres,
More informationNashville Area MPO Regional Freight Study fast action projects
Project #1 Beechcroft road (sr 247) at csx crossing Motor carrier survey location Maury County (Spring Hill, Tn) / City of Spring Hill Current at-grade railway crossing causes traffic delays as a result
More informationAlberta Schools Alternative Procurement (ASAP) Projects. Public School Construction Program September 19, 2011 Baltimore, USA
Alberta Schools Alternative Procurement (ASAP) Projects Public School Construction Program September 19, 2011 Baltimore, USA Presentation Outline P3 s in Alberta - An Overview Alberta Schools (ASAP) Projects
More informationWhat s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM
What s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM Progressive design-build: A better way? Discussion topics: What is progressive design-build?
More informationMedian Bus Lane Design in Vancouver, BC: The #98 B-Line
Li 1 Median Bus Lane Design in Vancouver, BC: The #98 B-Line Simon Li, P.Eng. PTOE Acting Program Manager, Road and Bridge Projects TransLink (Greater Vancouver Transportation Authority) 1600 4720 Kingsway
More informationThe AMT s Reno-Tunnel Program : Improving Safety in the Mount-Royal Tunnel Is the Result of a Partnership with the Montreal Fire Department
The AMT s Reno-Tunnel Program : Improving Safety in the Mount-Royal Tunnel Is the Result of a Partnership with the Montreal Fire Department ISTSS 2016 - AMT s conference Jean-Philippe Pelletier, eng.,
More informationLooking for new opportunities of investment for the PPPs projects. The keys of the success for PPPs in railway sector
Looking for new opportunities of investment for the PPPs projects The keys of the success for PPPs in railway sector Doris CHEVALIER Paris 14 Juin 2013 1 2 French expertise for railway PPPs French expertise
More informationAEG-ASCE SHORT COURSE
AEG-ASCE SHORT COURSE TUNNELS THROUGH FAULT ROCKS AND TECTONIC MELANGES May 31 and June 1, 2002 Gunter Riedmueller and Wulf Schubert Course Outline! Introduction! Characterization and Classification! Investigation!
More informationMINISTRY OF EDUCATION AND SASKBUILDS SASKATCHEWAN JOINT-USE SCHOOLS PROJECT PROJECT #2
June 5, 2015 MINISTRY OF EDUCATION AND SASKBUILDS SASKATCHEWAN JOINT-USE SCHOOLS PROJECT PROJECT #2 FINAL REPORT OF THE FAIRNESS ADVISOR ON THE PROCUREMENT PROCESS: RFP STAGE TO: STEERING COMMITTEE, SASKATCHEWAN
More informationRequest for Proposals for. Dam Safety and Floodplain Management Database Services DSFPM RFP 2015-1
Request for Proposals for Dam Safety and Floodplain Management Database Services DSFPM RFP 2015-1 Arkansas Natural Resources Commission December 2015 A. INTRODUCTION The Arkansas Natural Resources Commission
More informationImplementation of PPPs for Transit: The Request for Proposal Process ADVISORY
Implementation of PPPs for Transit: The Request for Proposal Process ADVISORY Agenda KPMG Introduction The Gotham BIA Connector The initial stages RFI to RFQ The final stages RFP to Evaluation 2 KPMG Infrastructure
More informationGetting Connected with the Colorado Department of Transportation (CDOT)
Getting Connected with the Colorado Department of Transportation (CDOT) INTRODUCTION Who is CDOT? CDOT is responsible for 9,146 miles of highway including 3,447 bridges State government agency with funding
More informationVendor Performance Evaluation
Vendor Performance Evaluation Canadian Public Procurement Council Oct. 27-29, 2014 Agenda 1) Objectives and 2) Evaluation 3) Evaluation Templates and 4) Use of Vendor Score 2 13:00 14:00 1 Objectives and
More informationREQUEST FOR PROPOSALS For. Kelowna and Vernon Hospitals Project
REQUEST FOR PROPOSALS For The Kelowna and Vernon Hospitals Project VOLUME 2 of 4 Instructions to Proponents Closing Time: Delivery Address: 3:00 pm (local time) Thursday, March 6,2008 Kelowna and Vernon
More informationMARKHAM STOUFFVILLE HOSPITAL EXPANSION AND REDEVELOPMENT PROJECT
Insert VFM letter VALUE FOR MONEY ASSESSMENT MARKHAM STOUFFVILLE HOSPITAL EXPANSION AND REDEVELOPMENT PROJECT - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - Markham Stouffville Hospital Artist s Rendering
More informationThe Follo Line Project
The Follo Line Project Longest. UrbAN. Complex. Faster. 2015/1 Norwegian National Rail Administration the follo line project 1 2 the follo line project The project The Follo Line Project is currently the
More informationMember Nation Report 2010 from Denmark.
Member Nation Report 2010 from Denmark. The has during the year 2010 arranged 6 member meetings including two technical site visits. The first technical site visit covered the 5.3 km long Leipzig City
More informationEXPANDING PRESTO ON TTC: STATUS UPDATE
EXPANDING PRESTO ON TTC: STATUS UPDATE Robert Hollis, Executive Vice President, PRESTO Chris Upfold, Deputy CEO and Chief Customer Officer, TTC APRIL 27, 2016 WHY PRESTO Offering 1.8 million customers
More informationPart 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26
Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain
More informationTOWN OF BERLIN REQUEST FOR QUALIFICATIONS
TOWN OF BERLIN REQUEST FOR QUALIFICATIONS Notice is hereby given that qualifications will be received by the Town of Berlin, Maryland for: RFQ # 2015 4 Community Solar Garden: Design, Build, Finance, Operate
More informationPROPANE EDUCATION & RESEARCH COUNCIL. Request for Proposals to Develop an Aftermarket Bi-Fuel Propane Autogas Vehicle System. Posted August 15, 2011
PROPANE EDUCATION & RESEARCH COUNCIL Request for Proposals to Develop an Aftermarket Bi-Fuel Propane Autogas Vehicle System Posted August 15, 2011 General Information The Propane Education & Research Council
More informationC a b l i n g s o l u t i o n s a t t h e c o r e o f R a i l w a y N e t w o r k s
C a b l i n g s o l u t i o n s a t t h e c o r e o f R a i l w a y N e t w o r k s High Speed Line (HSL) Zuid The Netherlands - Siemens project Dedicated 100 km high speed rail line between Antwerp (Belgium)
More informationNorth-South Bypass Tunnel Project. Coordinator-General s Change Report
North-South Bypass Tunnel Project Coordinator-General s Change Report July 2006 1.0 INTRODUCTION 1.1 Background 1.2 Proponent and proposed delivery mode 1.3 Council s Request for Project Change 2.0 DESCRIPTION
More information5 ALTERNATIVE SOLUTIONS AND EVALUATION
Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable
More information3.05. Infrastructure Ontario Alternative Financing and Procurement. Chapter 3 Section. Background. Alternative Financing and Procurement
Chapter 3 Section 3.05 Infrastructure Ontario Alternative Financing and Procurement Background Alternative Financing and Procurement Alternative Financing and Procurement (AFP) is the name given to the
More informationAvailability Payment Mechanisms For Transit Projects ADVISORY
Availability Payment Mechanisms For Transit Projects ADVISORY Agenda Availability Payments Overview Structure Financial Implications Case Study Additional Considerations KPMG Infrastructure 2 What is an
More informationDESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE
ARIZONA DEPARTMENT OF TRANSPORTATION INTERMODAL TRANSPORTATION DIVISION DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE 3rd Edition December 2007 Published by: ADOT Construction Group 206 S. 17 th Ave.,
More informationPROJECT PREPARATORY TECHNICAL ASSISTANCE
A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of Azerbaijan, the Ministry of Transport and Baku Metro Company requested ADB to help improving its urban transport system and
More informationREQUEST FOR INFORMATION FOR #2015-12 POINT OF SALE SYSTEM. November 18, 2015
REQUEST FOR INFORMATION FOR #2015-12 POINT OF SALE SYSTEM November 18, 2015 Questions Due: December 9, 2015 at 12:00 p.m. SUBMISSIONS DUE: December 18, 2015 at 11:00 a.m. 2425 NE 65th Avenue ~ PO Box 2529
More informationProject Report: Evergreen Line Rapid Transit Project
Project Report: Evergreen Line Rapid Transit Project March 2013 Purpose of this Report The purpose of this report is to provide key information to the public about the Evergreen Line Rapid Transit Project
More informationThe Gateway Program and Hudson Tunnel Project
The Gateway Program and Hudson Tunnel Project Presented to: NJ State Senate Oversight Committee Stephen Gardner Executive Vice President NEC Business Development August 10, 2015 1 The Need for Gateway
More informationRequest for Proposal. City of Atlanta Taxicab Industry Analysis. May 30, 2012
City of Atlanta Taxicab Industry Analysis May 30, 2012 Contact: Kristi Rooks Central Atlanta Progress, Inc. 50 Hurt Plaza SE, Suite 110 Atlanta, GA 30303 (404) 658-5911 and krooks@atlantadowntown.com Page
More informationFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874
ADVERTISEMENT FOR LETTERS OF INTEREST FOR A DESIGN BUILD PROJECT (PROCUREMENT METHOD SHORTLISTING OF PROPOSERS WITH TECHNICAL AND PRICE EVALUATION BY ADJUSTED SCORE) PROCUREMENT NUMBER: E2N44 Financial
More information5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES
5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES 5.1 FINANCIAL ANALYSIS The cost of a transportation investment falls into two categories: capital costs, and operating and maintenance (O&M) costs.
More informationProcurement Management. Scott Coplan, PMP David Masuda, M.D.
Procurement Management Scott Coplan, PMP David Masuda, M.D. 1 Procurement Management Procurement management is planning, executing and controlling acquisition of goods and services necessary to support
More informationSouthwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014)
Southwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014) Summary Description Proposed Project: Light Rail Transit 15.7 Miles, 17 Stations
More informationDATA MANAGEMENT SYSTEM FOR TUNNELLING
DATA MANAGEMENT SYSTEM FOR TUNNELLING A working tool for data acquisition, visualization AND Reporting 2 IRIS Integrated Risk and Information System A single software solution for integrated data management
More informationRequest for Qualifications November 2007 GIS Migration and Modeling Page 1 TABLE OF CONTENTS. 1.0 Overview. 2.0 General Information
REQUEST FOR QUALIFICATIONS GIS Migration and Modeling November 2007 Closing Date: Wednesday, December 5, 2007 Closing Time: 3:00 p.m. (Local Time) Halifax Water 450 Cowie Hill Road P.O. Box 8388, Station
More informationPort Mann/Highway 1 Project Request For Proposals Volume 1 Instructions to Proponents
Port Mann/Highway 1 Project Request For Proposals Volume 1 Instructions to Proponents August 7, 2007 PAGE 1 OF 57 Table of Contents 1. Introduction... 5 1.1 Project Scope Overview... 5 1.2 Short-listed
More informationOwner s Procurement Forum
Washington Metropolitan Area Transit Authority Construction Management Association of America National Capitol Chapter Owner s Committee Owner s Procurement Forum February 24, 2015 OVERVIEW of WMATA INFRASTRUCTURE:
More informationEXECUTIVE SUMMARY. Salini Impregilo / Healy / GLF Joint Venture
EXECUTIVE SUMMARY statement of qualifications chesapeake bay bridge and tunnel district EXECUTIVE SUMMARY With extensive international tunneling and marine design and construction experience, Salini Impregilo/Healy/GLF
More informationHow to implement cycling solutions in a post-communist street system (and mentality) Marcin Hyła, VeloForum, 16 Oct.
How to implement cycling solutions in a post-communist street system (and mentality) Marcin Hyła, www.miastadlarowerow.pl VeloForum, 16 Oct. 2010 th What has communism to do with cycling? No free flow
More informationTrack and Track Drainage Renewals Programme
Board Date: 26 March 2015 Item 14: Track and Track Drainage Renewals Programme This paper will be considered in public 1 Summary Track and Track Drainage Renewals Programme Existing Estimated Existing
More informationNETLIPSE NETWORK MEETING 27-28.5.2013 Seppo Mäkinen Finnish Transport Agency 27.5.2013
NETLIPSE NETWORK MEETING 27-28.5.2013 Seppo Mäkinen Finnish Transport Agency 27.5.2013 Mainroad 4 Järvenpää Lahti PPP Project 1997 2012 FINLAND 27.5.2013 27.5.2013 Seppo Mäkinen Mainroad 4 Järvenpää -
More informationAdvanced Construction Techniques
Alaskan Way Viaduct Replacement Program Organization University of Washington Date October 20, 2011 Presentation Overview SR 99 south end viaduct replacement. Design-build contracting. SR 99 tunnel project.
More information4.03. Brampton Civic Hospital Public-private Partnership Project. Chapter 4 Section. Background. Follow-up on VFM Section 3.03, 2008 Annual Report
Chapter 4 Section 4.03 Brampton Civic Hospital Public-private Partnership Project Follow-up on VFM Section 3.03, 2008 Annual Report Background In 2001, the then Minister of Finance announced that public
More informationBusiness Opportunities Seminar
Business Opportunities Seminar In Finland, Norway, Denmark, Ireland and The Netherlands (22 29 September 2015) Presented by: Rustam Abdukayumov Senior Procurement Specialist Operations Services and Financial
More informationProgram Management. APWA North Carolina Chapter. Design-Build: Will it Work for You? William Palmieri, P.E.
APWA North Carolina Chapter Design-Build: Will it Work for You? Program Management William Palmieri, P.E. HDR Engineering, Inc. 695 Atlantic Avenue Boston, MA. 02111 (512) 627-6300 (m) August 6, 2015 William
More informationAtrium Skylight Repair Carleton Lodge
Requirement Period of Contract The successful bidder shall complete the work no later than 27 November 2015. Closing Date Quotations must be submitted no later than close of business day (11:59 pm) on
More informationCITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR
CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA RSTP Funds Joint Application FOR Tinker Creek Pedestrian Bridge: Tinker Creek and Glade Creek Greenways Connection Date: September 15, 2014 RSTP Project Profile
More informationREQUEST FOR QUALIFICATIONS for SURREY PRETRIAL SERVICES CENTRE EXPANSION PROJECT RFQ #3225 VOLUME 1 PROJECT BRIEF
Ministry of Public Safety and Solicitor General Ministry of Citizens Services Shared Services BC REQUEST FOR QUALIFICATIONS for SURREY PRETRIAL SERVICES CENTRE EXPANSION PROJECT RFQ #3225 VOLUME 1 PROJECT
More information