1 CRENSHAW/LAX TRANSIT CORRIDOR PROJECT A New Beginning for the Crenshaw Corridor Through Use of Innovative Procurement Strategies Robert Ball, P.E. and Kimberly Ong, P.E. Los Angeles Metropolitan Transportation Authority Los Angeles, CA
2 Project Overview 8.5 mile Light Rail Line Extends from Exposition LRT Line to Metro Green Line Stations: 6 Stations: Exposition Bl, Martin Luther King Jr., Slauson Ave, West Bl, La Brea Ave, Century Bl 2 Station Bid Options: Vernon (Leimert Park), Hindry Southwestern Yard $ Billion (Current Board approved LOP) 24,400 Project Trips (2035) Federally assisted contract
3 Measure R Rail Projects
4 Regional Transit Network
5 South Los Angeles Community Profile
6 The Crenshaw Corridor Crenshaw Corridor has a culturally rich history. From the early settlements of the Californias, in the 16th Century, the Baldwin Hills Crenshaw area has seen a significant presence of African Americans, Japanese Americans and Latino Americans. Clubhouse of Parkview Woman s Club incorporated the original buildings
7 The History of the Project The Crenshaw Light Rail Transit project is due in part to: The vision and early work of L.A. County Supervisor Yvonne Brathwaite Burke The commitment of Supervisor Mark-Ridley Thomas & Mayor Antonio Villaraigosa, to fight for the money to fund the project. Adoption of a Light Rail Transit (LRT) project instead of a Bus Rapid Transit Project (BRT) The community s drive to make the project a more robust light rail transit line. Budget: Initial BRT budget was $640 million Current LRT budget is $1.76 billion
8 Rich History View of the Yellow Car Line 5 operating in the median on Crenshaw Boulevard and Leimert Avenue in the 1950 s Heading south on Leimert Avenue towards Crenshaw Boulevard
9 Crenshaw/LAX Transit Corridor Procurement Actions The Crenshaw/LAX Transit Project includes four separate contracts: Advanced Utilities Contract C-0990 Awarded May 30, 2012 (First Metro contract with PLA) Alignment Design-Build Contract C-0988 Contract Award anticipated June 2013 Owner-furnished track materials Contract C-0992 Award anticipated September 2013 Southwestern Yard Contract C-0991 Design- Build procurement Release IFB Spring 2015
10 Crenshaw/LAX Transit Corridor Early Utility Relocation Work C0990 Lowering utilities for follow-on Cut and Cover Construction Clearing FAA/LAWA utility conflicts in LAX area in advance of construction
11 Major Milestones Main Design-Build Contract C0988 RFQ released December 23, 2011 Four of five proposers were pre-qualified RFP for Alignment Design-Build Contract released June 22, 2012 Proposals received December 6, 2012 Discussion with Proposers Jan./Feb BAFO released February 22, 2013 Final Scoring Late March 2013 D-B Contract award shifted from May to June 2013 board cycle Allowed time for action on Leimert Park Station that has nationwide attention
12 Crenshaw/LAX Transit Corridor Stipend Agreement RFP provides stipend for unsuccessful, responsive proposers in the amount of One Million Dollars ($1,000,000). Stipend Agreement must be submitted prior to proposal due date. Stipend Agreement includes LACMTA ownership of ATCs, which allows LACMTA to use the ATCs from unsuccessful bidders after contract award.
13 Southwestern Yard Contract C-0991 IFB to be released in Spring 2015
14 Future APM Connection Proposed by Los Angeles World Airports - Implementation 2025??
15 Design-Build Delivery Statutory Requirement for Transit Design-Build Contracts, California Public Contract Code (PCC) Best Value Procurement Process Prequalify design-build entities using a standard questionnaire developed by the State Director of Industrial Relations.
16 Two-Step Procurement Process Step One: Request for Qualifications (RFQ) Statement of Qualifications (SOQ) Pass/Fail Evaluation Step Two: Request for Proposal (RFP) Technical and Price Proposal Evaluations Best Value Determination
17 Best Value Source Selection Best Value Award Firm-Fixed Price Contract to Design-Build Team whose Proposal provides the Best Value, considering RFP Evaluation Criteria and Tradeoffs Tradeoffs for added technical, schedule or performance benefits will be made against price May award to other than lowest price Contract options evaluated as part of total price
18 Phase 1 Acquisition Background Source Selection Process Evaluate Alternative Technical Concepts (ATCs) Definition of ATCs Allows for submittal of innovative ideas by proposers Should reduce cost or provide other efficiencies Address one or more elements of the Work Improve aesthetic and functional design of the stations and structures Provide schedule milestone and cost savings Lessen community impacts and traffic interruptions Results in improved operation, maintenance and serviceability Evaluate Technical & Price Proposals
19 Acquisition Background Source Selection Process (Cont.) Phase 2 Oral Presentations held to assist in the Determination of Best Value source An award decision was not made in Phase 2 Phase 3 Established a Competitive Range Phase 4 Requested BAFO and Determined Best Value proposals for Contract Award
20 RFP Evaluation Criteria Best Value RFP Evaluation Criteria Project Management 30% Technical Approach 25% Price Proposal 45% Price = 39% Delay Compensation = 5% Life Cycle Cost = 1%
21 Alternative Technical Concepts Design Innovations Desired by Metro ATCs were required to be equal or better than original contract requirements: Require full description of ATC Justification for use of the ATC Relation to Technical Requirements including any design deviations Examples of similar applications from other projects Cost & Schedule Impacts Operations and Maintenance Impacts Construction, Environmental, Right-of-way & Safety Impacts Risks to Agency, Third Parties or the Project
22 Alternative Technical Concepts Two Step Evaluation Initial ATCs Detailed ATCs Pass: 88 Accept: 37 Reject: 27 Reject: 8 Not an ATC: 4 Not an ATC 2 Total : 119 Total: 47 Range of Cost Savings: $50 to $90 Million
23 Examples of ATCs Ventilation Proposed innovation to meet Arson Fire Growth Rate; PE design based on Medium Fire Growth Rate. Station Kit of Parts Metro adopted a Kit of Parts halfway through procurement process to create a branding for stations systemwide. Requirements were broadened for grade separation solutions at La Brea, which also resulted in significant improvements to a station in Inglewood by raising the station out of a deep cut to adjacent street level.
24 Station Kit of Parts Portal Kit of Parts Center Platform Kit of Parts
25 Inglewood Station ATC Old and new alignments for the Grade Separation, from an underpass to an overpass, at La Brea Ave.
26 Inglewood Station ATC Grade Separation from an underpass to an overpass at La Brea Ave also allowed an Inglewood station to be raised from a deep cut to adjacent street level.
27 Examples of ATCs (Cont.) Change LRT Structure Type and Means & Methods for Construction over I-405. Creates an opportunity to consider clear span over freeway. Allows use of former railroad bridge to erect falsework and significantly reduces impacts on freeway traffic. Leaves RR bridge in place for alternative uses. Optimizing Horizontal & Vertical Alignments Provides potential cost advantage to proposers Raised inverts of underground stations as much as ten feet.
28 I-405 Freeway ATC
29 Lessons Learned Allow confidential one-on-one discussions with Proposers early in RFP phase. ATC process was the only opportunity Proposers had for technical clarification dialogue. Two-step ATC provided screening process to eliminate infeasible or unwanted concepts; allowed Proposers to concentrate resources on only viable concepts. ATC process allowed shortening of the BAFO phase. Reduce overly-prescriptive requirements, yet still adhere to Metro Rail Design Criteria.
30 BAFO Changes Reduced number of Key Personnel allowing proposers more flexibility in staffing. Allowed more flexibility in hardscape and landscape treatments in station and plaza areas. Reduced daily Liquidated Damages rate and cap on maximum exposure. Reduced cap on liability limits on Builder s Risk Insurance. Change in requirements for deflection criteria on support of excavation walls, allowing greater flexibility in means & methods. Provide staging areas and project office site for Proposer s use.
31 Will There be a Leimert Park Station? Station carried as 2 bid options Shell plus fully finished station City of LA Council Motion passes for $40M on May 22 nd Metro Board motion passed 10:1 for $80 M on May 23 rd Ratification expected at June 27 th Board Meeting to add both Leimert Park plus an atgrade station in Westchester community
32 Crenshaw/LAX Transit Corridor Project Information Please use one of the following to learn more about the project: Telephone: Web site: metro.net/crenshaw
DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE
ARIZONA DEPARTMENT OF TRANSPORTATION INTERMODAL TRANSPORTATION DIVISION DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE 3rd Edition December 2007 Published by: ADOT Construction Group 206 S. 17 th Ave.,
More informationDesign-Build Process for Project Managers
Vermont Agency of Transportation Design-Build Process for Project Managers This document provides guidance on the preliminary engineering and procurement process and roles and responsibilities of key personnel
More informationRBRC Combo Project Request for Qualifications Additional Information and Clarifications #1. RFQ No. 1708.057. Issued: March 9, 2011
REQUEST FOR QUALIFICATIONS ROBERTS BANK RAIL CORRIDOR PROGRAM 192 ND STREET, 54 TH AVE., 196 TH STREET COMBO PROJECT RFQ No. 1708.057 ADDITIONAL INFORMATION AND CLARIFICATIONS NO. 1 Issued: March 9, 2011
More informationUNDERGROUND CELL PHONE AND DATA SERVICES PROVIDER
55 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2ooo Tel metro. net EXECUTIVE MANAGEMENT COMMITTEE FEBRUARY 21, 2013 SUBJECT: ACTION: UNDERGROUND CELL PHONE AND DATA SERVICES PROVIDER APPROVE CONTRACT
More informationto imagine a transportation vision
to imagine a transportation vision Before 2007 many wondered Was collaboration and coalition building even possible in Los Angeles County? Creating the Measure R coalition sent a new message This is how
More informationWelcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU
Purpose of Tonight s Meeting Informational Open House to discuss two City projects: Fairchild Street Subway Phase I Engineering: Immediate need to replace subway Bowman Avenue Feasibility Study Future
More information5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES
5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES 5.1 FINANCIAL ANALYSIS The cost of a transportation investment falls into two categories: capital costs, and operating and maintenance (O&M) costs.
More informationWhat s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM
What s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM Progressive design-build: A better way? Discussion topics: What is progressive design-build?
More informationLessons Learned/Best Practices: Case Study- Design-Build at SFO
Lessons Learned/Best Practices: Case Study- Design-Build at SFO Speaker(s): Clay Paslay Moderator Ivar Satero, SFO Steven Rule, Turner Bill Hooper, Jr., Gensler SFO s Delivery Options SELECTION TYPES Price
More informationCHAPTER 8 CIVIL DESIGN
CHAPTER 8 CIVIL DESIGN A. GENERAL This Chapter includes standards and design considerations for other civil engineering design in structural, drainage and utilities. Design considerations for electrical
More informationCITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR
CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA RSTP Funds Joint Application FOR Tinker Creek Pedestrian Bridge: Tinker Creek and Glade Creek Greenways Connection Date: September 15, 2014 RSTP Project Profile
More informationExperts in Rail Maintenance and Infrastructure
Experts in Rail Maintenance and Infrastructure It is with great people and pride, rooted in a culture of safety, D that Transdev delivers systems, technologies, and business processes to strengthen rail
More information2015 Ed u cation a l S e r i e s. Contracting & Purchasing
2015 Ed u cation a l S e r i e s Contracting & Purchasing TxDOT Contracting and Purchasing INTRODUCTION Texas Department of Transportation (TxDOT) contracting activities are established and controlled
More informationGetting Connected with the Colorado Department of Transportation (CDOT)
Getting Connected with the Colorado Department of Transportation (CDOT) INTRODUCTION Who is CDOT? CDOT is responsible for 9,146 miles of highway including 3,447 bridges State government agency with funding
More informationTransit, Rail, Program, Project & Construction Management Experience
Point of Contact Peter M. Cipolla Vice President, Rail & Transit Mobile: 925.219.5235 Email: peter.cipolla@hatchmott.com Project Management Oversight Services Introduction & Background Hatch Mott MacDonald
More informationEffect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain
Effect on structures Uniform settlement - no concerns Angular distortion - causes damage due to tensile strain 1/500 - safe limit for no cracking of buildings 1/150 - potential structural damage 36 37
More informationEXECUTIVE MANAGEMENT COMMITTEE JUNE 20, 2013 OFF-SITE STORAGE & MAINTENANCE OF INACTIVE RECORDS APPROVE CONTRACT AWARD ACTION: RECOMMENDATION ISSUE
66 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net EXECUTIVE MANAGEMENT COMMITTEE JUNE 20, 2013 SUBJECT: ACTION: OFF-SITE STORAGE & MAINTENANCE OF INACTIVE RECORDS APPROVE CONTRACT
More informationCorrected Form: Revised Attachment 7B Cost Proposal Distribution Exhibits A1 and A2 Attached
ADDENDUM #1 RFP: 500 16 Design Build Maintenance & Operations Complex The following changes to the Request for Proposal and clarifications are provided based on questions received and must be added/considered
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS Engineering Design Services for the Preliminary (Design) Engineering 1. Imlay City Road Imlay City Road at Wilder Road (signal modernization), Lapeer Township 2. Imlay City Road Imlay
More informationCRENSHAW/LAX TRANSIT CORRIDOR PROJECT Page 4-219
Final Environmental Impact Statement/Final Environment Impact Report 4.0 - Affected Environment/Environmental Consequences of the Table 4-38. Other Community Facilities within 0.25-mile of the Project
More informationProject Status Update Open House West End Corridor
Project Status Update Open House West End Corridor The Exposition Construction Authority cordially invites you to a Project Status Update Open House for the Exposition Light Rail Line At this meeting we
More informationDesign-Build Projects and Right-of Way Acquisition: Benefits, Challenges and Pitfalls
Design-Build Projects and Right-of Way Acquisition: Benefits, Challenges and Pitfalls Presented by: Mark Lancaster, Riverside Co. Transportation Comm. Joey Mendoza, Overland, Pacific & Cutler, Inc. Artin
More informationARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT DESIGN-BUILD GUIDELINES AND PROCEDURES
ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT DESIGN-BUILD GUIDELINES AND PROCEDURES Revision 1 September 2015 TABLE OF CONTENTS Section I. Introduction 6 PURPOSE 6 AUTHORITY 6 DEFINITIONS AND ACRONYMS
More informationProgram Management. APWA North Carolina Chapter. Design-Build: Will it Work for You? William Palmieri, P.E.
APWA North Carolina Chapter Design-Build: Will it Work for You? Program Management William Palmieri, P.E. HDR Engineering, Inc. 695 Atlantic Avenue Boston, MA. 02111 (512) 627-6300 (m) August 6, 2015 William
More informationSYSTEMWIDE REQUIREMENTS
SYSTEMWIDE REQUIREMENTS for the Peninsula Rail Program San Francisco to San Jose on the Caltrain Corridor Description of the Systemwide Context for the High Speed Train Project This document provides a
More informationRisk Management in the Development of a Penta-P Project
Risk Management in the Development of a Penta-P Project Bill Van Meter Regional Transportation District Denver, CO Julie Skeen Jacobs Engineering Denver, CO Damian Carey Jacobs Engineering Denver, CO Don
More informationAppendix A Alternative Contracting General Engineering Consultant RFP. Appendix A
Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement
More informationDesign-Build Project for A Soccer Complex in Creve Coeur Park Industry Information Meeting. Monday June 6, 2016 St Louis County Council Chambers
Design-Build Project for A Soccer Complex in Creve Coeur Park Industry Information Meeting Monday June 6, 2016 St Louis County Council Chambers Welcome Sign in sheet / handouts - Introductions - Project
More informationDELAWARE COUNTY DIVISION OF ENVIRONMENTAL SERVICES PREQUALIFICATION AND QUALIFICATIONS-BASED SELECTION PROCEDURE FOR PROFESSIONAL DESIGN SERVICES
DELAWARE COUNTY DIVISION OF ENVIRONMENTAL SERVICES PREQUALIFICATION AND QUALIFICATIONS-BASED SELECTION PROCEDURE FOR PROFESSIONAL DESIGN SERVICES Rev. Date 4/14/2014 TABLE OF CONTENTS: Article 1: Introduction
More informationTHE COMMUNITY REDEVELOPMENT AGENCY OF THE CITY OF LOS ANGELES, CA M E M O R A N D U M DATE: AUGUST 21, 2008 CR6990
THE COMMUNITY REDEVELOPMENT AGENCY OF THE CITY OF LOS ANGELES, CA M E M O R A N D U M 5 DATE: AUGUST 21, 2008 CR6990 TO: FROM: RESPONSIBLE PARTIES SUBJECT: CRA/LA BOARD OF COMMISSIONERS CECILIA V. ESTOLANO,
More informationMetro. Board Report. File #:2015-1088, File Type:Informational Report
Metro Board Report Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room Los Angeles, CA File #:2015-1088, File Type:Informational Report SUBJECT: EXECUTIVE MANAGEMENT
More informationMetro. Board Report. C. Authorize the Chief Executive Officer, or his designee, to negotiate and execute all agreements necessary for this action.
Metro Metro Board Report Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room Los Angeles, CA 23 File #: 2015-0269, Version: 1 Planning and Programming May 20,2015
More informationSYSTEM SAFETY AND OPERATIONS COMMITTEE OCTOBER 17, 2013 GLASS ANTI-GRAFFITI FILM MAINTENANCE AND REPLACEMENT SERVICES AND ETCHED GLASS REPAIR SERVICES
40 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net SYSTEM SAFETY AND OPERATIONS COMMITTEE OCTOBER 17, 2013 SUBJECT: ACTION: GLASS ANTI-GRAFFITI FILM MAINTENANCE AND REPLACEMENT
More informationAssociated Students of the University of California, Merced 2014-2015. Resolution #14. Resolution in Support of the California High-Speed Rail Project
Introduced By: Isaias Rumayor III, ASUCM Senator At-Large Authored By: Michael Lomio, ASUCM Senator At-Large Isaias Rumayor III, ASUCM Senator At-Large Sponsored By: Background: The California High-Speed
More informationRequest for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Campus Elevator Upgrades Response Deadline 9/03/13
More information4.5 TRANSPORTATION - YEAR 2025 TRAFFIC CONDITIONS WITH PROPOSED TIMP 4.5-1 ESTIMATION OF TRIP REDUCTIONS WITH TIMP TRANSIT AND TDM PROGRAMS
Draft Environmental Impact Report State Clearinghouse No. 2002061090 City of LA EIR No. 2003-1922-EIR CPC No. 98-0010 (CPU) 4.5 TRANSPORTATION - YEAR 2025 TRAFFIC CONDITIONS WITH PROPOSED TIMP This chapter
More informationDenver Union Station. Regional Transportation District Denver, Colorado
Denver Union Station Regional Transportation District Denver, Colorado Regional Transportation District Created in 1969 Eight-county service area Service area: 2,340 sq. miles 2.8 million population 15
More informationFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874
ADVERTISEMENT FOR LETTERS OF INTEREST FOR A DESIGN BUILD PROJECT (PROCUREMENT METHOD SHORTLISTING OF PROPOSERS WITH TECHNICAL AND PRICE EVALUATION BY ADJUSTED SCORE) PROCUREMENT NUMBER: E2N44 Financial
More information--Participates in program reviews and pre-negotiation conferences with technical and management personnel on proposed procurement programs.
S43601D, page 1 Nothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time. DUTIES Serves as Contracting Officer (CO) in the
More informationNashville Area MPO Regional Freight Study fast action projects
Project #1 Beechcroft road (sr 247) at csx crossing Motor carrier survey location Maury County (Spring Hill, Tn) / City of Spring Hill Current at-grade railway crossing causes traffic delays as a result
More informationDesign Build Procurement Guide
Massachusetts Bay Transportation Authority CONTRACT ADMINISTRATION POLICIES & PROCEDURES Design/Build Procurement Guidelines May 17, 2011 Design Build Procurement Guide Rev May 17, 2011 1 TABLE OF CONTENTS
More informationNEW BLUE LINE CONNECTIONS
Washington Metropolitan Area Transit Authority NEW BLUE LINE CONNECTIONS 3/31/2014 A Major Capital Project of Momentum s Metro 2025 Program In support of its new strategic plan, Metro has considered the
More informationWhen is BRT the Best Option? 1:30 2:40 p.m.
TRB/APTA 2004 Bus Rapid Transit Conference When is BRT the Best Option? 1:30 2:40 p.m. Paul Larrousse Director, National Transit Institute (NTI) (Moderator) TRB/APTA 2004 Bus Rapid Transit Conference Session
More informationSOUTH CAROLINA DEPARTMENT OF TRANSPORTATION. Request for Qualifications
SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION Request for Qualifications Federal Aid Project No. IM23(009) A Design-Build Project Greenville County Revised July 30, 2013 Page 1 of 22 TABLE OF CONTENTS I.
More informationLos Angeles Department of Water and Power
Los Angeles Department of Water and Power now accepting applications for General Manager THE CITY OF LOS ANGELES The City of Los Angeles is the second largest City in the United States and has a multiethnic
More informationPROPRIETARY MEETINGS. Are they legal in Washington? Robynne Thaxton Parkinson, J.D, DBIA www.rtp-law.com
PROPRIETARY MEETINGS Are they legal in Washington? Robynne Thaxton Parkinson, J.D, DBIA www.rtp-law.com Purpose of Procurement Laws Protection of general public prevent fraud, collusion, favoritism, and
More informationprocedures, disputes, etc. Signs Notice to Proceed, and COTR letters, and other types as applicable. Notifies unsuccessful firms of award decisions.
S12101, Page 1 Nothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time. FUNCTIONAL DUTIES Serves as Contracts Manager, Phase
More informationBackground and Goals for the Project
City of Asheville, NC REQUEST FOR PROPOSALS Wilma Dykeman Riverway Environmental Analysis, Project Development, and Preliminary Design Submittal Address: Dan Baechtold, AICP City of Asheville Engineering
More informationBay. Region Design- US-10. June 13, 2014
REQUEST FOR QUALIFICATIONS MICHIGAN DEPARTMENT OF TRANSPORTATION Bay Region Design- Build Project US-10 over I-75 Job Numbers: 122868 Control Section: 09034 Original Issue June 13, 2014 TABLE OF CONTENTS
More informationA Review of Transit Technology Specifications
. Transit Technologies Worksheet A Review of Transit Technology Specifications 1 2 3 4 5 6 1. Heavy Rail Transit 2. Commuter Rail Transit 3. Light Rail Transit 4. Modern Streetcar 5. Heritage Trolley 6.
More informationDouglas County, Nevada Request for Qualifications Douglas County Public Works Asset Management Plan
Douglas County, Nevada Request for Qualifications Douglas County Public Works Asset Management Plan Douglas County, Nevada ( County ) is soliciting Statement of Qualifications (SOQ) from qualified firms
More informationWEST MESQUITE INTERCHANGE DESIGN-BUILD PROJECT REQUEST FOR PROPOSALS INSTRUCTIONS TO PROPOSERS
WEST MESQUITE INTERCHANGE DESIGN-BUILD PROJECT REQUEST FOR PROPOSALS INSTRUCTIONS TO PROPOSERS TABLE OF CONTENTS 1.0 INTRODUCTION... 1 1.1 PROJECT GOALS... 1 1.2 THE PROPOSAL... 1 1.2.1 DOCUMENTS IN THE
More informationCost Reduction Opportunities
Cost Reduction Opportunities 9 December 2015 Presentation to MassDOT Board of Directors & MBTA Fiscal and Management Control Board Arup 2 A global, integrated, multidisciplinary firm of professionals 13,000
More informationTAPPAN ZEE HUDSON RIVER CROSSING PROJECT
New York State Department of Transportation New York State Thruway Authority TAPPAN ZEE HUDSON RIVER CROSSING PROJECT DESIGN-BUILD PROJECT RESPONSES TO PROPOSERS S REFERENCE NUMBER: This page is intentionally
More informationElectrical Contractor Pre-Qualification Packet. CHEM R/R Bus Duct & Generator (DMI) Project No. CP165716. Notice No. 13 09.
Electrical Contractor Pre-Qualification Packet CHEM R/R Bus Duct & Generator (DMI) Project No. CP165716 Notice No. 13 09 Issued by Department of Facilities Management Delivery address: Research Laboratory
More informationGENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES
REQUEST FOR QUALIFICATIONS GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES NEW DINING HALL MONTANA STATE UNIVERSITY Bozeman, Montana PPA NO. 15-0103 Campus Planning, Design & Construction Plew Building
More informationPublic-Private Partnerships Forum PPP Law, Structures and Contracting
Public-Private Partnerships Forum PPP Law, Structures and Contracting AGC California Fall Conference 2010 Hyatt Grand Champions, Indian Wells November 4, 2010 MAKING IT HAPPEN. Overview California PPP
More informationDesign-Build Manual. Office of Construction and Innovative Contracting (OCIC)
Design-Build Manual Office of Construction and Innovative Contracting (OCIC) THIS PAGE INTENTIONALLY BLANK FOR TWO-SIDED PRINTING Table of Contents List of Exhibits... 4 List of Forms... 5 Request for
More information9 One Gateway Plaza Los Angeles, CA 90012-2952
9 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2ooo Tel metro. net FINANCE, BUDGET AND AUDIT COMMITTEE SEPTEMBER 17, 2014 SUBJECT: ACTION: HEALTH BENEFITS CONSULTING SERVICES AWARD A CONTRACT FOR
More informationAppendix B Billboard Photos and Sign SUD Site View Simulation
Appendix B Billboard Photos and Sign SUD Site View Simulation City of Los Angeles, Bureau of Engineering W.O. EW40006B State Clearinghouse No. 2007051122 August 2007 Establishment of the proposed Sign
More informationCity of New Rochelle New York
City of New Rochelle New York REQUEST FOR PROPOSALS - CONSULTING SERVICES STUDY OF DEVELOPMENT IMPACTS ON THE SCHOOL DISTRICT Specification #: 5030 1) INTENT The City of New Rochelle s Department of Development
More informationREQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES ISSUED BY: INGLEWOOD UNIFIED SCHOOL DISTRICT Issued: November 20, 2015 Due: December 18, 2015 SCHEDULE OF EVENTS INGLEWOOD UNIFIED SCHOOL
More informationInformational Workshop Public Meeting Kanawha Falls Bridge Project
Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal
More informationORDINANCE NO.------- THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS:
ORDINANCE NO.------- An ordinance authorizing the award of one design-build contract for the decommissioning, disablement, demolition and removal of Scattergood Generating Station Unit 3 pursuant to a
More informationEXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT. BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309
EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309 FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT FOUR 1.0 SCOPE OF
More informationLight Rail Transit in Phoenix
4. Presentation and Discussion: Phoenix Light Rail Implementation Wulf Grote Planning and Development Director, Phoenix Valley Metro Light Rail Transit in Phoenix Broadway Citizen s Task Force February
More informationThe State of Maryland s Coverage and Data Collection for the Nationwide Public Safety Broadband Network
The State of Maryland s Coverage and Data Collection for the Nationwide Public Safety Broadband Network Objective: The Nationwide Public Safety Broadband Network (NPSBN) promises to provide critical broadband
More informationPeekskill City School District. Westchester County, New York REQUEST FOR PROPOSALS FOR A STUDENT MANAGEMENT SYSTEM
Peekskill City School District Westchester County, New York REQUEST FOR PROPOSALS FOR A STUDENT MANAGEMENT SYSTEM October 18, 2006 Gregory J. Sullivan Assistant Superintendent for Business & Administrative
More informationOwner s Procurement Forum
Washington Metropolitan Area Transit Authority Construction Management Association of America National Capitol Chapter Owner s Committee Owner s Procurement Forum February 24, 2015 OVERVIEW of WMATA INFRASTRUCTURE:
More informationDallas-Fort Worth Area Major Transportation Projects
Dallas-Fort Worth Area Major Transportation Projects Presented by: Jeffrey C. Neal Program Manager Transportation North Central Texas Council of Governments (NCTCOG) August 14, 2014 Texas Society of Professional
More informationRecommendation. Final Action
MOTION NO. M2015-90 Amend Contract for Construction Management Services for the Sounder Point Defiance Bypass, Tacoma Trestle Track and Signal, and Sounder Yard Expansion Projects MEETING: DATE: TYPE OF
More informationREQUEST FOR QUALIFICATIONS ROBERTS BANK RAIL CORRIDOR PROGRAM 192 ND STREET, 54 TH AVE., 196 TH STREET COMBO PROJECT CITY OF SURREY
REQUEST FOR QUALIFICATIONS ROBERTS BANK RAIL CORRIDOR PROGRAM 192 ND STREET, 54 TH AVE., 196 TH STREET COMBO PROJECT Issued: February 16, 2011 This project is being undertaken by: CITY OF SURREY ON BEHALF
More informationBASSETT CREEK VALLEY MASTER PLAN OPEN HOUSE
BASSETT CREEK VALLEY MASTER PLAN OPEN HOUSE February 23, 2006 PROJECT INTRODUCTION Project Area 230 acres $50 million estimated market value (approximately) 50 acres parkland 100 residences (estimated)
More informationA Guide to All Locations
A Guide to All Locations Nov 2009 Includes: Canoga Park Wholesale Electric Company Wholesale Electric Company Guide to All Walters Locations Page ANAHEIM Page 1050 N. Kraemer Place Anaheim, CA 92806 (714)
More informationTown of Paradise Valley 6401 East Lincoln Drive Paradise Valley, Arizona 85253-4328 www.paradisevalleyaz.gov. GIS Consulting Services
6401 East Lincoln Drive Paradise Valley, Arizona 85253-4328 www.paradisevalleyaz.gov Request for Qualifications (RFQ) for GIS Consulting Services RFQ Issued: July 16, 2015 Deadline for Submittal of Qualifications:
More informationSPO Technical Capacity Review. June 24, 2015
SPO Technical Capacity Review June 24, 2015 Southwest Project Context The Southwest Light Rail Transit (LRT) project (METRO Green Line Extension) will operate from downtown Minneapolis through the communities
More information05-15-98 CIVIL ENGINEERING ASSOCIATE, 7246
CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION POSTED JUNE 1999 05-15-98 CIVIL ENGINEERING ASSOCIATE, 7246 Summary of Duties: Performs professional civil engineering work in researching,
More informationImpact Analysis: The Atlanta Braves new Stadium Project. March 2014. A Cushman & Wakefield Research Publication
Impact : The new Stadium Project A Cushman & Wakefield Research Publication March 2014 1 Executive Summary The new baseball stadium project will dramatically transform the Cumberland/Galleria area of Northwest
More informationMid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014)
Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014) Summary Description Proposed Project: Light Rail Transit 10.9 Miles, 9 Stations Total
More informationBest Practices and Trends in Design-Build and Construction Management at-risk from The Municipal Water and Wastewater Design-Build Handbook
Best Practices and Trends in Design-Build and Construction Management at-risk from The Municipal Water and Wastewater Design-Build Handbook Water Design-Build Council March 31, 2011 Kansas City, MO Presentation
More informationMechanical Contractor Pre-Qualification Packet. SPSC N180 Computer Data Room Phase II. Project No. CP 159313. Notice No. Notice 13-11.
Mechanical Contractor Pre-Qualification Packet SPSC N180 Computer Data Room Phase II Project No. CP 159313 Notice No. Notice 13-11 Issued by Department of Facilities Management Delivery address: Research
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) Administration of Project: Local Higher Education Project Name FAES- Student Success Center Response Deadline 03/04/2013 4:30 pm local time Project Location
More informationMAXIMIZING COMPETITION & EXPANDING OPPORTUNITIES FOR SMALL BUSINESS
Los Angeles County One Gateway Plaza 213.922.2000 Tel Metropolitan Transportation Authority Los Angeles, CA 90012-2952 metro.net Metro SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE MARCH 19, 2015 SUBJECT:
More informationPART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express
PART II SCHEDULE SECTION TITLE D E Scope of Services Special Terms and Conditions 11 SECTION D SCOPE OF SERVICES D.1 OVERVIEW A. The selected firm is referred to herein as either the Consultant or the
More informationSouth LA Fast Food Health Impact Assessment
South LA Fast Food Health Impact Assessment Draft April 3, 2013 EXECUTIVE SUMMARY PURPOSE Decades of research indicate that an individual s health is not solely impacted by their biological predisposition
More informationFigure 4-21. L3: Level 2 SR 99 Elevated Light Rail Alternative Detail - 1 of 4
4-34 SEE FIGURE 4-22 N 14TH ST ROOSEVELT WAY N 130th Street N 130TH ST NE NORTHGATE WAY N 0 1/4 Miles Elevated Light Rail At-Grade Light Rail Elevated Light Rail Station At-Grade Light Rail Station Figure
More informationRequest for Proposals For Financial Advisor Services
Request for Proposals For Financial Advisor Services Finance Department Contents Section I Introduction 2 Section II Description of Village 2 Section III Debt Financing Plans 3 Section IV Scope of Services
More informationPreapplication for HSIPR Program OMB No. 2130 0583
U.S. Department of Transportation Federal Railroad Administration Preapplication for HSIPR Program OMB No. 2130 0583 Preapplication instructions: For each question, enter the appropriate information in
More informationHACC Central Pennsylvania s Community College Harrisburg, PA. Request for Proposal
HACC Central Pennsylvania s Community College Harrisburg, PA Request for Proposal RFP12-14 for EXECUTIVE SEARCH CONSULTING SERVICES Issued: February 1, 2012 Deadline for Questions: Response to Questions:
More informationPrepared by David Willson, OCIO in consultation with Marc Buchalter, Procurement Please send comments to David Willson at dwillson@berkeley.
Technology RFX Customer Guide Introduction This guide is intended for those that have identified a need to solicit bids from suppliers but may unclear on the different types of documents, the roles various
More informationRailyard Alternatives and I-280 Boulevard Feasibility Study. Planning Commission February 6, 2014
Railyard Alternatives and I-280 Boulevard Feasibility Study Planning Commission February 6, 2014 Problem Statement Major pieces of new infrastructure are planned including: Downtown Rail Extension (DTX)
More informationIntroduction to Station Area Planning The Charlotte Story
Introduction to Station Area Planning The Charlotte Story Boston 2009 Steve Hamwey - Sasaki Associates, Inc. Troy Russ - Glatting Jackson, Inc. October 31 st, 2009 Station Area Planning October 15th History
More informationRequest for Qualifications. for. Design-Build of the Proposed. Calaveras River Pump Variable Frequency Drive Upgrade Project
Request for Qualifications for Design-Build of the Proposed Calaveras River Pump Variable Frequency Drive Upgrade Project Request For Qualification No. 7000138614 Issued: June 27, 2016 Qualification Submission
More informationMetro Rail Gating Study
Executive Management & Audit Committee Item # 27 Operations Committee Item # 43 FINAL DRAFT Metro Rail Gating Study Los Angeles, California November 15, 2007 Filename/RPS Number 1 Briefing Contents Executive
More informationAWARD AND APPROVAL OF CONSTRUCTION CONTRACT CONTRACTOR: JOHNSON-PELTIER ELECTRICAL CONTRACTOR
THE PORT OF LOS ANGELES Executive Director's Report to the Board of Harbor Commissioners DATE: MAY 24, 2016 FROM: CONSTRUCTION RESOLUTION NO. AWARD AND APPROVAL OF CONSTRUCTION CONTRACT CONTRACTOR: JOHNSON-PELTIER
More informationDesign Build Procurement Guide
Design Build Procurement Guide DESIGN BUILD PROCUREMENT GUIDE Page 1 of 29 TABLE OF CONTENTS Abbreviations... 4 Chapter 1 Design Build Introduction.. 1.1 Purpose 1.2 Authority 1.3 Scope 1.4 Background
More informationTOWN OF BERLIN REQUEST FOR QUALIFICATIONS
TOWN OF BERLIN REQUEST FOR QUALIFICATIONS Notice is hereby given that qualifications will be received by the Town of Berlin, Maryland for: RFQ # 2015 4 Community Solar Garden: Design, Build, Finance, Operate
More information3 Tappan Zee Bridge Rehabilitation Options
3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:
More informationCLARK COUNTY DEPARTMENT OF ADMINISTRATIVE SERVICES PURCHASING & CONTRACTS DIVISION
CLARK COUNTY DEPARTMENT OF ADMINISTRATIVE SERVICES PURCHASING & CONTRACTS DIVISION Clark County Government Center 500 Grand Central Parkway, 4th Floor Las Vegas, NV 89106 Phone: (702) 455-2897 Fax: (702)
More informationUNO CHARTER SCHOOL NETWORK ( UNO-CSN ) Invitation for Bids ( IFB ) for ELECTRICAL UPGRADES
UNO CHARTER SCHOOL NETWORK ( UNO-CSN ) Invitation for Bids ( IFB ) for ELECTRICAL UPGRADES All Bids must be sent electronically to: ucsnbidresponse@unocharterschools.org All communications should be addressed
More information