QA/QC Requirements for Opacity Monitors
|
|
|
- Blake Franklin
- 9 years ago
- Views:
Transcription
1 QA/QC Requirements for Opacity Monitors EPRI 2013 CEMS User Group Conference Raleigh, NC May 8, 2013 By Dru Sanders RMB Consulting & Research, Inc.
2 QA/QC for COMS Currently No Federal Requirement for Ongoing QA/QC Requirements for COMS Requirements Vary From State to State COMS QA/QC Originally Proposed (Method 203) 1992 EPA Decided to Completely Redraft Method 2001 Re-proposed as Procedure 3 (App. F, Part 60) 2003
3 QA/QC for COMS Procedure 3 Published In Federal Register as Direct Final Rule on 2/14/2012 Compliance Required Beginning 4/16/2012 EPA Withdraws Rule Due to Adverse Comments Anticipated That EPA Would Reissue Procedure 3 in 2013 Presentation Should Provide Overview of Requirements & Level of Effort For Compliance
4 Proposed Procedure 3 Quality Assurance Requirements for Continuous Opacity Monitoring Systems (COMS) at Stationary Sources Applies to COMS used to demonstrate continuous compliance with opacity standards in federally enforceable regulations Concern for State regulations with blanket Part 60 Appendix F references
5 Proposed Procedure 3 Performance Specification 1 (PS-1) References May Be a Concern for Pre-2001 COMS Daily, Quarterly & Annual QA Requirements Daily Zero/Upscale Drift and Status Indicator Checks Quarterly Optical Alignment Check, Zero Compensation Check, and Calibration Error Test (Filter Audit) Annual Zero Alignment Check Data Capture Requirements
6 Daily QA/QC Daily Calibration Drift Test Zero and upscale calibration Out-of-control if CE > 4.0% Daily Status Indicator Check Data invalid if indicators are illuminated Initiate corrective action
7 Quarterly QA/QC Optical Alignment Check Stack temperature ± 50% typical operating temperature Out-of-control if alignment > 3% opacity Data validation Zero Compensation Check Out-of-control if zero compensation > 4% opacity
8 Quarterly QA/QC Calibration Error Test References PS-1 procedures Three (3) nonconsecutive readings for each of the three (3) filters Filters calibrated every six (6) months Out-of-control if CE > 3% opacity May Request Semi-Annual Test Frequency For Quarterly Audits
9 Annual QA/QC Primary Zero Alignment Check Off stack or on stack On stack clear path demonstration Out-of-control if zero alignment error > 2% opacity Off stack zero alignment check required at least once every three (3) years
10 Annual QA/QC Alternate Zero Alignment Check Use external COMS specific zero-jig Record initial zero-jig response, then conduct zero alignment procedure If zero-jig is adjusted, must conduct an off stack zero alignment check
11 QA/QC Corrective Action Revise Procedures or Repair/Replace COMS, If COMS Fails: Two consecutive annual audits Two consecutive quarterly audits Five consecutive daily checks
12 Data Capture Requirements Must Capture Data For At Least 95% of the Operating Hours Per Calendar Quarter (Section 10.4(4)) Out-of-control data not used Excludes downtime associated with required QA/QC procedures 40 CFR 60.13(h)(1) 6-minute avg. calculated from 36 or more equally spaced data points
13 Temporary COMS Replacement May Use Temporary COMS Replacement COMS ASTM D 6216 certified Limited to 720 hours (30 days) per year May not install a second temporary COMS Complete full PS-1 certification after 720 hours
14 Temporary COMS Replacement Temporary COMS Test Requirements Off-stack clear path assessment Optical alignment check 7-day calibration drift test (Abbreviated) Conducted within 24-hr period & no more than one (1) calibration every three (3) hours, and Not less than one (1) calibration every 25 hours Calibration error test
15 Corrective Action Requirements Rule Identifies Five (5) Maintenance Classes Routine/Preventive Maintenance Measurement Non-Critical Repairs Primary Measurement Light Source Measurement Critical Repairs Measurement Critical Repairs (Not Optics) Part 75 Diagnostic Test Concept
16 Corrective Action Example Primary Light Source Repair Requires: Daily Calibration Drift Test Fault Indicator Check Optical Alignment Check Zero Alignment Check Calibration Error Check
17 Recertification Requirements Rebuild or Substantially Refurbish COMS Replace major sub-assembly or lesser subassemblies with different revision levels Change To, or Addition of COMS Components Which May Affect MCOC Performance Parameters Complete PS-1 Certification
18 General Requirements Develop Written QA Plan Written Procedures Available for Inspection Quarterly Data Assessment Report (DAR) References DAR in Procedure 1 Monitor availability QA/QC test results Corrective actions taken
19 Procedure 3 Issues 720 Operating Hours (30 Days) Clarify to 720 Unit Operating Hours Monitor Availability Requirements Disconnect Between Hourly Availability & 6-minute Average Requirements No Conditionally Valid Data Procedures PS-1 References
Quality Assurance Program Quality Assurance Plan Periodic Audits Standard Operating Procedures Preventive Maintenance Outline Quality Assurance Plan (QAP) What is a QAP Why is a QAP required? What does
Continuous Monitoring Manual
January, 1992 Revisions: April, 2015 Operations Division 811 SW 6 th Avenue Portland, OR 97204 Phone: 503-229-5696 800-452-4011 Fax: 503-229-5850 Contact: Jill Inahara www.oregon.gov/deq DEQ is a leader
PROCEDURE 1. QUALITY ASSURANCE REQUIREMENTS FOR GAS CONTINUOUS EMISSION MONITORING SYSTEMS USED FOR COMPLIANCE DETERMINATION
While we have taken steps to ensure the accuracy of this Internet version of the document, it is not the official version. Please refer to the official version in the FR publication, which appears on the
Chapter 2 Compliance Branch CEMS Guidance Manual Table of Contents. Applicability... 1.0
Chapter 2 Compliance Branch CEMS Guidance Manual Table of Contents Page No. Applicability... 1.0 1.0 Continuous Emissions Monitor Operating Principles... 3.0 1.1 Introduction... 3.0 1.2 Definitions...
INDUSTRIAL BOILER MACT FACTSHEET
INDUSTRIAL BOILER MACT FACTSHEET The National Emission Standards for Hazardous Air Pollutants (NESHAP) for Industrial/Commercial/Institutional Boilers and Process Heaters (40 CFR Part 63, Subpart DDDDD),
CONTINUOUS MONITORING MANUAL. DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION 811 SW SIXTH AVENUE Portland, Oregon 97204
CONTINUOUS MONITORING MANUAL DEPARTMENT OF ENVIRONMENTAL QUALITY AIR QUALITY DIVISION 811 SW SIXTH AVENUE Portland, Oregon 97204 January 23, 1992 Table of Contents 1.0 INTRODUCTION... 1 2.0 DEFINITIONS...
VISIBLE EMISSIONS TRAINING AND CERTIFICATION PROGRAM EVALUATION FORM
VISIBLE EMISSIONS TRAINING AND CERTIFICATION PROGRAM EVALUATION FORM Good management practice requires that every visible emission training (VETC) program activity be periodically reviewed and evaluated
Control Device Requirements Charts For Oil and Gas Handling and Production Facilities
Device Charts For Oil and Gas Handling and Production Facilities Purpose/Scope: The purpose of this document is to provide standardized guidance for use by the regulated community and air permit reviewers,
By Robert Bivens. RMB Consulting & Research, Inc. Raleigh, NC www.rmb-consulting.com (919) 791-3133 @RMBConsulting
CEMS Certification and Compliance Testing Lessons Learned on Turbines By Robert Bivens RMB Consulting & Research, Inc. Raleigh, NC www.rmb-consulting.com (919) 791-3133 @RMBConsulting Background While
Texas Commission on Environmental Quality Page 1 Chapter 117 - Control of Air Pollution from Nitrogen Compounds
Texas Commission on Environmental Quality Page 1 SUBCHAPTER G: GENERAL MONITORING AND TESTING REQUIREMENTS DIVISION 1: COMPLIANCE STACK TESTING AND REPORT REQUIREMENTS 117.8000, 117.8010 Effective June
Rob Barton RMB Consulting & Research, Inc. EPRI CEM User Group Conference May 8, 2013
Rob Barton EPRI CEM User Group Conference May 8, 2013 Unique Reporting Challenges Compilation of various reporting requirements Electronic submittal of most data/records Adapting existing tools to new
CONTINUOUS EMISSION MONITORING SYSTEM (CEMS) CODE
CONTINUOUS EMISSION MONITORING SYSTEM (CEMS) CODE 1998 Alberta Environmental Protection Environmental Service Ref:STA:CEMSCODE CONTINUOUS EMISSION MONITORING SYSTEM (CEMS) CODE MAY 1998 Pub. No.: Ref.
Continuous Emissions Monitoring - Program 77
Program Description Program Overview Coal-fired power plants are in increased need of robust, accurate, and certifiable continuous emissions monitors (CEMs) for mercury, particulate matter (PM), acid gases,
Emission monitoring, reporting, and verification (MRV) for U.S. cap and trade programs. Jeremy Schreifels US EPA
Emission monitoring, reporting, and verification (MRV) for U.S. cap and trade programs Jeremy Schreifels US EPA Principles of MRV for cap and trade programs Cap & trade requires a complete record of total
Guidance and Reporting Instructions on Temporary E-reporting for the MATS Rule
Guidance and Reporting Instructions on Temporary E-reporting for the MATS Rule As explained in the interim MATS e-reporting rule, which was signed by the Administrator on March 9, 2015, the EPA plans to
Continuous Emission Monitoring Guide
Continuous Emission Monitoring Guide Course No: C08-015 Credit: 8 PDH Harlan H. Bengtson, PhD, P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800
1.0 What Are the Purpose and Applicability of Performance Specification 11?
While we have taken steps to ensure the accuracy of this Internet version of the document, it is not the official version. Please refer to the official version in the FR publication, which appears on the
DEPARTMENT ADMINISTRATIVE ORDER No. 2016-
DEPARTMENT ADMINISTRATIVE ORDER No. 2016- SUBJECT : ACCREDITATION OF THIRD PARTY CONTINUOUS EMISSION MONITORING SYSTEMS (CEMS) AND CONTINUOUS OPACITY MONITORING SYSTEMS (COMS) TEST AUDIT FIRMS PURSUANT
Part 75 Emissions Monitoring Policy Manual. U.S. Environmental Protection Agency Clean Air Markets Division Washington, D.C.
Part 75 Emissions Monitoring Policy Manual U.S. Environmental Protection Agency Clean Air Markets Division Washington, D.C. 2013 TABLE OF CONTENTS Page Introduction... iii Section 1 -- General... 1-i Section
Continuous Emission Monitoring System (CEMS) Code
GUIDELINE PAPER Continuous Emission Monitoring System (CEMS) Code for Stationary Source Air Emissions Version: Final March 2016 DER2016/000490 1 Produced and published by Department of Environment Regulation
Keywords: PEMS, CEMS, turbine
SYMPOSIUM OF THE INDUSTRIAL APPLICATION OF GAS TURBINES COMMITTEE BANFF, ALBERTA, CANADA OCTOBER 2015 CERTIFICATION OF A STATISTICAL HYBRID PREDICTIVE EMISSION MONITORING SYSTEM IN THE U.S.A. AND DEVELOPMENT
11.0 Instrument Equipment Testing, Inspection and Maintenance
Page 1 of 6 11.0 Instrument Equipment Testing, Inspection and Maintenance Implementing an ambient air monitoring network, with the various types of equipment needed, is no easy task. Through appropriate
(a) Method 1 Sample and Velocity Traverses for Stationary Sources.
While we have taken steps to ensure the accuracy of this Internet version of the document, it is not the official version. Please refer to the official version in the FR publication, which appears on the
Title V Compliance Verification Process
em case study by Sara King and Jeffrey Meyers Development and Implementation of a Title V Compliance Verification Process Sara L. King is the environmental director at the ConocoPhillips Ponca City Refinery,
EQUIPMENT CALIBRATION/MAINTENANCE
EQUIPMENT CALIBRATION/MAINTENANCE The following chart provides a guide for calibration of standard equipment used in the Fish Health Laboratory. All Intervals suggested are subject to individual manufacturer
Series of CEMS Guidelines
Series of CEMS Guidelines VERSION 6.0 Nov 2009 Volume I: GUIDELINE FOR THE INSTALLATION & MAINTENANCE OF CONTINUOUS EMISSION MONITORING SYSTEMS (CEMS) FOR INDUSTRIAL PREMISES / FACILITIES Department of
Handling Alternative Test Method and Monitoring Requests and Approvals. Robin Segall Measurement Technology Workshop January 28, 2015
Handling Alternative Test Method and Monitoring Requests and Approvals Robin Segall Measurement Technology Workshop January 28, 2015 Topics Background/Approval Authority Delegation of Authority Approval
Predictive Maintenance
PART ONE of a predictive maintenance series Predictive Maintenance Overview Predictive maintenance programs come in all shapes and sizes, depending on a facility s size, equipment, regulations, and productivity
Life & Times of a PM2.5 Filter: Quality Control in the Laboratory and Beyond
Life & Times of a PM2.5 Filter: Quality Control in the Laboratory and Beyond Brenda Saldana, Manager Inorganic Laboratory Section Monitoring and Laboratory Division Air Resources Board 1 Field Sampling
COLORADO REGULATION 7
COLORADO REGULATION 7 Author: Jay Christopher, Business Unit Manager, Air & Process Services, Trihydro Corporation Jane Steere, QAQC Coordinator, Air & Process Services, Trihydro Corporation ABSTRACT The
equivalents (CO2e) emitted by a person or business. Usually expressed in the number of CO2e tons emitted per unit of time (per year) or
Greenhouse Gas Reporting and Carbon Footprints Douglas A. McWilliams Squire, Sanders & Dempsey L.L.P. January ar 11, 2010 What is a carbon footprint? An estimate of the amount of carbon dioxide equivalents
Top Ten Mistakes In Title V Deviation and Certification Reports
Top Ten Mistakes In Title V Deviation and Certification Reports M A U R E E N N. H A R B O U R T K E A N M I L L E R L L P B A T O N R O U G E N E W O R L E A N S L A K E C H A R L E S P L A Q U E M I
High Volume PM10/TSP Calibration/Verification/Audit Guidance. Issued: 12/15/14 - FINAL
High Volume PM10/TSP Calibration/Verification/Audit Guidance Issued: 12/15/14 - FINAL Purpose: The purpose of this guidance is to assist operators of industrial particulate samplers for particulate matter
AIR EMISSION PERMIT NO. 13100005-003 IS ISSUED TO MULTEK FLEXIBLE CIRCUITS INC
AIR EMISSION PERMIT NO. 13100005-003 IS ISSUED TO MULTEK FLEXIBLE CIRCUITS INC Multek Flexible Circuits Inc.-Sheldahl Road East and West Buildings 1150 Sheldahl Road and 805 North Highway 3 Northfield,
Air Quality Performance Test Guidelines. Kansas Department of Health and Environment Bureau of Air and Radiation
Air Quality Performance Test Guidelines Kansas Department of Health and Environment Bureau of Air and Radiation December 22, 2004 TABLE OF CONTENTS 1. INTRODUCTION 2. TEST PLANNING 2.1 EPA Test Methods
STATE OF CONNECTICUT DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF AIR MANAGEMENT
Page 1 of 7 STATE OF CONNECTICUT DEPARTMENT OF ENVIRONMENTAL PROTECTION NEW SOURCE REVIEW PERMIT TO CONSTRUCT AND OPERATE A STATIONARY SOURCE Issued pursuant to Title 22a of the Connecticut General Statutes
GLOSSARY. Glossary of Terms for Capacity Based Demand Response PUBLIC. Issue 3.0 GOT-1
PUBLIC GOT-1 GLOSSARY Glossary of Terms for Capacity Based Demand Response Issue 3.0 This document provides a glossary of terms with definitions used in the Capacity Based Demand Response program. Public
Surgi Manufacturing Quality Manual
Surgi Manufacturing Page 1 of 18 Approvals: QA: Eng. Mgt. : A Date: 18Aug98 1. Introduction... 4 1.1 Scope... 4 1.2 Purpose... 4 1.3 Authority... 4 1.4 Issue of the Manual... 4 1.5 Amendments... 4 1.6
NSW Air Quality Monitoring Network: Quality Assurance Procedures
NSW Air Quality Monitoring Network: Quality Assurance Procedures Copyright State of NSW and Office of Environment and Heritage With the exception of photographs, the State of NSW and Office of Environment
BEST PRACTICES IN LEAK DETECTION AND REPAIR (LDAR) PROGRAMS. November 06, 2014 By: François Thibodeau, Eng.
BEST PRACTICES IN LEAK DETECTION AND REPAIR (LDAR) PROGRAMS November 06, 2014 By: François Thibodeau, Eng. 2 PRESENTATION OVERVIEW 1. Essential Components of a LDAR Program 2. LDAR Best Practices a. A
NORTH CAROLINA EDUCATION LOTTERY POLICIES AND PROCEDURES MANUAL CHAPTER 2 GAME RULES 2.04B CAROLINA PICK 3 GAME RULES
Page 1 of 5 A. The purpose of Carolina Pick 3 is to generate revenue for the NCEL and ultimately, education programs in North Carolina through the operation of a specially-designed lottery game that will
1 Quality Assurance and Quality Control Project Plan
1 Quality Assurance and Quality Control Project Plan The purpose of this section is to describe the quality assurance/quality control program that will be used during the system specific field testing
Employing a Data Acquisition Handling System (DAHS) for New Source Performance Standards (NSPS) Ja Rule Reporting of Petroleum Refinery Emissions
Technical Paper BR-1923 Employing a Data Acquisition Handling System (DAHS) for New Source Performance Standards (NSPS) Ja Rule Reporting of Petroleum Refinery Emissions Authors: D.C. Pretty Babcock &
(a) Method 1 Sample and Velocity Traverses for Stationary Sources.
While we have taken steps to ensure the accuracy of this Internet version of the document, it is not the official version. Please refer to the official version in the FR publication, which appears on the
Liberty Technology & City of Hapeville IT Outsourcing Agreement
Liberty Technology & City of Hapeville IT Outsourcing Agreement 1) General Terms and Conditions (Mutual) 2) What s Included Normally Included Services: Day to Day Operations Employee Account management
NEW APC Smart-UPS. Advanced line interactive power protection for servers and network equipment. The world s most popular network and server UPS.
NEW APC Smart-UPS Advanced line interactive power protection for servers and network equipment. > The world s most popular network and server UPS. Award-winning Smart-UPS protects critical data by supplying
Continuous Monitoring Data Acquisition System
Continuous Monitoring Data Acquisition System Finally, a company that offers a cost effective solution for my data acquisition system requirements Data management is vital to your company s bottom line
MD 7.5 ETHICS COUNSELING AND TRAINING DT-10-10
U.S. NUCLEAR REGULATORY COMMISSION MANAGEMENT DIRECTIVE (MD) MD 7.5 ETHICS COUNSELING AND TRAINING DT-10-10 Volume 7 Approved By: Legal and Ethical Guidelines Gregory B. Jaczko Chairman Date Approved:
Note: This App is under development and available for testing on request. Note: This App is under development and available for testing on request. Note: This App is under development and available for
Quick Summary of Final Tangible Property Regulations
This summary is intended to provide a high-level overview only and should not be relied on for application to specific fact patterns and situations. Taxpayers should consult their tax advisors to determine
Rail Network Configuration Management
Division / Business Unit: Function: Document Type: Enterprise Services Engineering Procedure Rail Network Configuration Management Applicability ARTC Network Wide SMS Publication Requirement Internal /
Quality Control and Maintenance Programs
Quality Control and Maintenance Programs Cari Borrás, D.Sc., FACR, FAAPM Visiting Professor DOIN-DEN / UFPE Recife, Pernambuco, Brazil Co-Chair, IUPESM Health Technology Task Group 1 Medical Imaging Equipment
PARTICULATE MATTER MONITOR
Model 360 PARTICULATE MATTER MONITOR A COMPLIANCE PARTICULATE MATTER MONITOR A Complete Quality System... PARTICULATE MATTER Monitor - Model 360 The most stable (under all operating conditions), accurate
Example ESD Control Program Document Based on ANSI/ESD S20.20-2007
PROFESSIONAL STATIC CONTROL SERVICES Example ESD Control Program Document Based on ANSI/ESD S20.20-2007 The following document demonstrates the structure for an ESD control program that is compliant to
Notice of Decision: Approval Effective Immediately
INDIANA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT We Protect Hoosiers and Our Environment. 100 N. Senate Avenue Indianapolis, IN 46204 (800) 451-6027 (317) 232-8603 www.idem.in.gov Michael R. Pence Thomas
9. Quality Assurance 9.1 INTRODUCTION 9.2 FIELD SAMPLING QUALITY ASSURANCE 9.3 ANALYTICAL QUALITY ASSURANCE. 9.3.1 Internal Quality Control
9. Quality Assurance Setting The overall goal of a well-designed and well-implemented sampling and analysis program is to measure accurately what is really there. Environmental decisions are made on the
Appendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1
Appendix C Change Management Plan Communication Plan QA/QC Plan Transition and Closure Plan C-1 CHANGE MANAGEMENT PLAN Whether the effects of changes are positive or negative, managing change is an important
Meet the requirements of the New Hampshire Safe Drinking Water Act, RSA 485 (state SDWA);
#10 FP 2016-41 Fixed Text 06-09-16 1 Readopt with amendment Env-Dw 600, 3-23-08 (doc. # 9107), to read as follows: CHAPTER Env-Dw 600 CAPACITY ASSURANCE Statutory Authority: RSA 485:2, V PART Env-Dw 601
Performance Standards and Test Procedures for Automated Dust Arrestment-Plant Monitors
Performance Standards and Test Procedures for Automated Dust Arrestment-Plant Monitors Certification under MCERTS according to EN 15859 Environment Agency Version 1 August 2010 Record of amendments Version
Section 6 Fire Detection and Alarm Systems Russell Porteous Chief Executive Officer Firewize Services
Section 6 Fire Detection and Alarm Systems Russell Porteous Chief Executive Officer Firewize Services General Information Section 6 of AS1851-2012 covers: Fire Detection and Alarms Systems Electrical Detection
LAB ID and/or LABORATORY NAME: ASSESSOR NAME: CONTINUOUS RADON MONITOR (CRM) by Proportional Counting. Method Number: ELAP method code 7037
LAB ID and/or LABORATORY NAME: ASSESSOR NAME: DATE: CONTINUOUS RADON MONITOR (CRM) by Proportional Counting Method Number: ELAP method code 7037 SOP Number: Revision Number: SOP Date: Personnel / Data
AIR QUALITY SURVEILLANCE BRANCH ACCEPTANCE TEST PROCEDURE (ATP) FOR. Teledyne Advanced Pollution Instruments Model 400 E Ozone Analyzer AQSB ATP 002
AIR QUALITY SURVEILLANCE BRANCH ACCEPTANCE TEST PROCEDURE (ATP) FOR Teledyne Advanced Pollution Instruments Model 400 E Ozone Analyzer AQSB ATP 002 First Edition MONITORING AND LABORATORY DIVISION August
Corrections and Removals 21 CFR Part 806
Corrections and Removals 21 CFR Part 806 Presented by: Kimberly Lewandowski-Walker Food and Drug Administration Division of Domestic Field Investigations Office of Regulatory Affairs From the Newsroom
A.1 Sensor Calibration Considerations
Wind Speed and Direction Appendix A. Quality Assurance A major pre-requisite for establishing quality control standards for wind measurements is a strong quality assurance program. Remember the mantra
Air Monitoring Directive Summary of Feedback and Responses for Chapter 6 (Ambient Data Quality)
Air Monitoring Directive Summary of Feedback and Responses for Chapter 6 (Ambient Data Quality) Environment and Sustainable Resource Development The following feedback was received following the 60-day
NEW APC Smart-UPS. Advanced line interactive power protection for servers and network equipment. The world s most popular network and server UPS.
NEW APC Smart-UPS Advanced line interactive power protection for servers and network equipment. > The world s most popular network and server UPS. Award-winning Smart-UPS protects critical data by supplying
Application Note 12: TrendView Recorders Continuous Emissions Monitoring
Application Note 12: TrendView Recorders Continuous Emissions Monitoring Continuous Emissions Monitoring (often abbreviated to CEM) is the term commonly used to describe instantaneous or real-time environmental
PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF WASTE MANAGEMENT
PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF WASTE MANAGEMENT DOCUMENT NUMBER: 250-4000-004 TITLE: Program Implementation Guidance EFFECTIVE DATE: September 17, 2005 AUTHORITY: The Solid
Unlimited Fibre Office SLA
1 SCOPE 1.1 This sets out the Service Levels provided in relation to the Unlimited Fibre Office Service and is subject to our General Terms and Conditions and Fibre Broadband Specific Terms and Conditions.
Sullivan County RFP for HVAC Maintenance Page 2 of 5 April 14, 2016
SULLIVAN COUNTY, NH REQUEST FOR PROPOSALS FOR HVAC MAINTENANCE AND MECHANICAL SERVICES PROPOSALS ARE DUE NO LATER THAN 12:00 NOON ON MONDAY, MAY 16, 2016 AND SHALL BE SEALED AND ADDRESSED TO: John Cressy
Operating Policy and Procedure. DATE: February 9, 2015
[Major revision posted 2/9/15 (replaces 9/19/12 edition)] Operating Policy and Procedure : Overtime DATE: February 9, 2015 PURPOSE: The purpose of this Operating Policy and Procedure (OP) is to establish
Distribution Restriction Statement Approved for public release; distribution is unlimited.
CEMP-CP Regulation No. 415-1-15 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 Construction CONSTRUCTION TIME EXTENSIONS FOR WEATHER ER 415-1-15 Distribution Restriction
CONSTRUCTION PERMIT OFFICE OF AIR MANAGEMENT. Lone Star Industries, Inc. 3301 South County Road 150 West Greencastle, Indiana 46135
CONSTRUCTION PERMIT OFFICE OF AIR MANAGEMENT Lone Star Industries, Inc. 3301 South County Road 150 West 46135 (herein known as the Permittee) is hereby authorized to construct the facilities listed in
Metrohm Care Contracts. Protect your investment the smart way
Metrohm Care Contracts Protect your investment the smart way Metrohm Care Contracts service, certainty and so much more 02 No matter whether you work for a private company or for a public institution,
Agreement on Quality, Occupational Health and Safety, Environmental Protection and Social Responsibility (Quality Assurance Agreement)
Agreement on Quality, Occupational Health and Safety, Environmental Protection and Social Responsibility (Quality Assurance Agreement) between Robert Bosch GmbH Robert-Bosch-Platz 1, 70839 Gerlingen, Germany
Bridging Development and Operations: The Secret of Streamlining Release Management
Bridging Development and Operations: The Secret of Streamlining Release Management Mark Levy, Product Manager Serena Software SERENA SOFTWARE INC. Release Management Goal Deploy application changes into
Monitoring the Operation of Wind Turbines Alex Robertson, Vestas Northern Europe
Monitoring the Operation of Wind Turbines Alex Robertson, Vestas Northern Europe Renewable Efficient Energy II Conference, 21.03.2012, Vaasa, Finland Modern wind power plant produce more data than ever