1 Division i i of Capital Asset Management David B. Perini, Commissioner Susan Goldfischer, Deputy General Counsel The Construction Institute August 6, 2009 Bidding on Vertical Construction Public Projects in Massachusetts Contractor Certification and Prequalification John Adams Courthouse, Boston Massachusetts Vertical Construction Procurement Focus on Contractor Certification and Prequalification Mass Information Technology Center, Chelsea Overview and Applicable Laws Critical Resource: Inspector General s Handbook Designing and Constructing Public Facilities available on IG s website under Publications. Construction, Renovation & Repair M.G.L. c. 149, 44A-J Public Buildings estimated construction cost (ECC) > $100,000. M.G.L. c. 149 A 1-8 (Optional CM at Risk ECC > $5, ) 000) M.G.L. c. 30, 39M Public Buildings ECC > $25,000 < $100,000. Public Works Horizontal/Site only. Materials Only Purchases (no labor.) M.G.L. c.149, 44A Public Buildings estimated construction cost < $25,00 expedited process. Design & Study Contracts M.G.L. c. 7, 38A1/2 O. 1
2 Major Differences Between MGL c. 149, 149A and c.30, 39M Bids MUST BE DCAM CERTIFIED TO BID ON LARGER BUILDING PROJECTS Building Projects, M.G.L. c. 149, 44 A-J and c. 149A CM at Risk projects with Estimated Construction Cost ( ECC ) over $100,000 Must have DCAM Prime Bidder Certification to Bid Over 26 different categories, e.g., General Building Construction, HVAC, must be identified in ad and in bid documents Must have DCAM Filed-Sub-bidder Certification to Bid Filed Sub-Bid Work /CM at Risk Trade if ECC for Trade $20,000 or more 17 Categories of Filed Sub-bid Work in c. 149, 44F DCAM Contractor Certification not required for horizontal work under c. 30, 39M or for building projects with ECC under $100,000 Filed Sub-bidding not required under c. 30, 39M or for projects under $100,000 Construction Project Opportunities & Bids Projects over $25,000 Advertised on Comm-Pass ( in Local Newspaper, Central Register, trade sources such as Dodge. Bids Must be Submitted Before the Filed Sub-bid and General Bid Deadlines-these deadlines are firm, even a bid submitted one minute late can not be accepted. Bids must be complete, signed, acknowledge all addenda, and be accompanied by: 1) Bid Deposit of 5% 2) Current and Valid Certificate of Eligibility 3) Completed Update Statement OR THE BID WILL BE REJECTED! Contractor Certification Campus Center, UMASS Boston 2
3 Construction Reform Review of Key Changes DCAM Certification of filed sub-bid subcontractors Must be certified as a filed sub-bidder if subcontract is over $20K on a Ch. 149 job (building project valued over $100K). Filed Sub-Bid Categories Enumerated under Ch. 149, 44F. Must have separate Sub-Bidder Certificate for these categories. Prime Certificate not Acceptable on Filed Sub-Bid. New thresholds governing general and sub-bids. Must be certified as a Prime/General Contractor if you are the prime/general contractor on a Chapter 149 building project and estimated value is over $100K. Requirements for General/Prime Certification 5 Completed Projects Over $80K in any one Category of Work performed within the past 5 years Bonding letter from licensed Surety Reviewed or Audited CPA Financial Statement for most recent year-end Secretary of State paperwork, if Incorporated (Annual Report/Articles of Organization) Requisite Licenses mandated by state law Changes to General Contractor Certification Goal to make GC/Prime Certification more user-friendly; New factors incorporated into Overall Numerical Rating system including criteria such as: termination, amount of litigation, direct payment claims history, OSHA penalties, workers comp history (EMR ratings); Single Project Limit (highest amount you can bid on per-project) now based on average of largest 2 projects, rather than on just the single largest project; and Single and Aggregate limits reduced to 130% of the average of the 2 largest projects - 180% if the contractor has demonstrated the capacity in the opinion of the Commissioner (if contractor achieves an Overall Rating of 85% or over) 3
4 Evaluations of Prime/General Contractors Awarding Authorities have 70 days from completion to Evaluate the Prime/General Contractor. If Awarding Authorities Fail to Evaluate Contractor, they shall risk being ineligible for the receipt of public funds for future public projects. Awarding Authorities must evaluate Contractor at 50% stage of contract Interim Evaluation Must Be Submitted to the Contractor being Evaluated. Subcontractor Certification Effective January 1, 2006 Filed Sub-bidders must be certified by DCAM All Filed Sub-bids > $20K for projects with total estimated cost of construction >$100,000 shall be accompanied by: - a DCAM Filed Sub-Bidder Certificate of Eligibility; and - a Sub-Bidder Update Statement The Update Statement provides space for updated information regarding all projects which the sub-bidder currently has under contract (submitted with every bid). Subcontractor Certification Effective January 1, 2006 Sub-contractor certification is essentially the same as prime contractor certification except: Projects evaluated over past 3 years compared to 5 years for prime contractors; Certificate of Eligibility does not show single project and aggregate limits like the certificate for prime contractors; and Certificate of Eligibility will show the number of prior construction projects evaluated by DCAM, the average numerical value on those projects, and the number of projects given scores below the passing score established by DCAM (80%) over last 3 years 4
5 Requirements for Subcontractor Certification 3 Projects over $20K in any one Category of Work performed within the past 3 years Filed Sub-bid Categories listed in M.G.L. C F No Bonding Letter requirement Compiled CPA Financial Statement is acceptable Secretary of State Paperwork Requisite Contractor Licenses mandated by state law Filed Sub-Bid Categories Acoustical Tile Electrical Work Elevators Fire Protection Sprinkler Systems Glass and Glazing HVAC Lathing & Plastering Marble Masonry Work Metal Windows Miscellaneous and Ornamental Irons Painting Plumbing Resilient Floors Roofing & Flashing Terrazzo Tile Waterproofing, Damping, and Caulking Subcontractor Certification Effective January 1, 2006 Awarding Authorities must submit Contractor Evaluations within 90 days of project completion (or Certificate of Use/Occupancy, whichever is earlier) or risk state funding for future projects. Awarding Authority evaluations and subcontractor responses considered public records (applied to general and prime contractor evaluations as well). To encourage honest evaluations, indemnification for awarding authorities submitting evaluations (not to exceed $1M). 5
6 Key Updates & Advisory Worcester Trial Court Updates to Certification Prime Application (revised 6/08) and Sub Application (revised 6/08) & Guidelines and Procedures available at under Related Links - Contractor Certification. DCAM Regulations Promulgated May CMR 4.00; 810 CMR 8.00, also found on DCAM web site. Prevailing Wage M.G.L. c. 149, 26-27D Project Specific Wage Rates Set by Division Of Occupational Safety on a Project by Project Basis. Included in Bid and Contract Documents by Awarding Authority. Required to be paid on all construction projects of any dollar value. All Contractors and Subcontractors Required to Prepare, Retain and Submit to Awarding Authority Weekly Payroll Reports on Form Required by Awarding Authority Evidencing that All Workers Were Paid the Prevailing Wage or More for Work on the Project. 6
7 MBE/WBE Participation-Affirmative Marketing Program (M.G.L. c. 7, 40N and c. 23A, 44) MBE/WBE goals set by DCAM and SOMWBA for Construction/Design Published in Central Register and in Project documents, currently Design - 8% MBE, 4% WBE Construction 7.4% MBE, 4% WBE Apply to all DCAM Projects and state assisted building projects includes projects by municipalities i and political l subdivisions i i when costs paid in whole or in part by Commonwealth. DCAM and SOMWBA develop procedures for adjustment of goals by awarding authority on individual projects. Advisory Massachusetts Independent Contractor/Misclassification Law, M.G.L. c. 149, 148B Classification of workers as employees vs. independent contractors Substantial civil and criminal penalties, and in certain circumstances debar violators from public works contracts. Creates liability for business entities and corporate officers, and those with management authority over affected workers. Joint Task Force on the Underground Economy E.O. #499 3 The underground d economy are those that t willfully avoid compliance with labor, licensing and tax laws by misclassifying employees, or deal in cash and other "off-the-books " schemes to conceal their activities, and true tax liability from licensing, regulatory and tax agencies. The Task Force coordinates joint efforts to combat the underground economy and employee misclassification, including efforts to: (a) foster compliance with the law by educating business owners and employees about applicable requirements. (b) conduct joint, targeted investigations and enforcement actions against violators. PREQUALIFICATION OVERVIEW 7
8 Prequalification Overview Prequalification - part of a two-phased procurement process intended to limit the bidding pool to general contractors/ subcontractors qualified to do the work: RFQ Phase the awarding authority issues an RFQ and reviews information submitted to determine qualified bidders Bidding Phase only prequalified bidders are invited to bid Use of Prequalification: Mandatory - estimated construction costs > $10 million Discretionary - estimated construction costs $100K to $10 million Discretionary for exempt agencies (DCAM, MassPort, MWRA, MSCBA, UMBA). Application of Prequalification to CM At-Risk Prequalification of Construction Manager - M.G.L. c. 149A, 5 - detailed process separate and distinct from prequalification of general contractors under M.G.L. c. 149, 44D½ Prequalification of Trade Contractors - M.G.L. c. 149A 8 - separate and distinct but similar to prequalification of filed subbidders under M.G.L. c. 149, 44D¾ Prequalification of Non-Filed Sub-bid bid Trade Contractors - pursuant to M.G.L. c. 149A(8)(j) (CM to submit list of qualifications and list of at least 3 firms that meet qualifications for approval by Awarding Authority and approved firms shall be invited to submit bid). Prequalification Overview Summary of Steps for Prequalification: Prequalification Committee established Prepare prequalification forms (RFQ and SOQ) Public notice of RFQ Statements of Qualifications submitted by GC/CM and filed subs/trade contractors Evaluation of Statements of Qualifications Selection of prequalified bidders RFB issued to prequalified bidders (RFP for Construction Managers) 8
9 How to find opportunities? - Public Notice Requirements for RFQ M.G.L. c. 149, 44D½(f) and 44D¾(f) require public notice of the RFQ not less than 2 weeks before deadline to submit responsive SOQ. Public Notice must be advertised in: a newspaper of general circulation (in geographic area where building project is located); AND the Central Register (published by the Secretary of the Commonwealth); AND COMM-PASS (Commonwealth Procurement Access and Solicitation System) Other potential opportunities related to Federal Stimulus Is the Information in SOQ Public? Opening of SOQs by Awarding Authority NOT public. BUT - Awarding Authority must prepare a Register of Responders at the opening of SOQs which is a public record. SOQs become public records once evaluation completed (excluding update statements, financial statements and revenue information submitted with SOQs which are not public records). Upon inquiry, general contractors and filed sub-bidders are entitled to know their score. Standard RFQ/SOQ Forms DCAM Standard Forms located on DCAM website ( Standard RFQ Form (RFQ) - customize w/ project specific instructions/information (description, address, deadlines, etc) Standard Statement of Interest Form - customize w/project specific instructions/information (include fax number for submission) Standard Statement of Qualifications Response Form (SOQ) - customize SOQ and required schedules w/project specific instructions/information 9
10 Some Recurring Issues/Problems Confusion regarding awarding authority discretion on review of evaluation criteria. Insufficient number of prequalified general contractors and subcontractors. Good general contractors and subcontractors eliminated because mandatory requirements not being met through their administrative errors. General contractors and subcontractors fail to respond fully and accurately. Once prequalified, confusion remains on requirement for subcontractors to carry cost of bonds in bid pursuant M.G.L. c. 149, 44F(D). Failure of prequalified bidders to submit bids due to insufficient project info in the RFQ or to lag time between prequal & bid. important to keep process moving! Statute does not allow rebidding without prequalification. Where is more info available? Prequalification Statutes M.G.L. c. 149, 44D½ and 44D¾ DCAM Regulations for Prequalification 810 CMR 9.00 and 810 CMR DCAM Guidelines for Prequalification - Office of Inspector General s Designing and Constructing Public Facilities manual Browsing Comm-PASS for Open Solicitations page 1 of 3 1. Open internet browser and go to 2. The homepage for Comm-PASS will show (below) 3. Any projects currently being advertised would be under the Solicitations tab. 4. Click on Solicitations and the following screen appears 5. From here, we would Browse All Open Solicitations 10
11 Browsing Comm-PASS for Open Solicitations page 2 of 3 NOTE: If you need to go back to the previous screen, do not use the Back Button on your internet browser. Use the headings at the top of the screen to go to previous screen. 6. Choose to Browse Entity / Department 7. Scroll down to find Division of Capital Asset Management 8. Click on the Check Box to select DCAM 9. Click on the Check Box to select Construction Browsing Comm-PASS for Open Solicitations page 3 of 3 In this example, there are only two open solicitations. To view a solicitation, click on the glasses icon The Summary tab gives you a description and brief overview of the document. The Rules tab states the applicable laws Under the Issuer tab, you will find contact information. The Forms and Terms provides the standard information for the solicitation. The Specifications tab provides the detailed information regarding the project (RFQ, RFP, etc.) Click on the Glasses icon on the right to view these documents or follow stated directions to view multiple documents. If you would like to go back to view another solicitation, do not hit the back button. Click on the List link at the top of the screen. QUESTIONS & ANSWERS 11
T34 - PUBLIC WORK IN MASSACHUSETTS, UNDERSTANDING CHAPTER 149 AND CHAPTER 149A
T34 - PUBLIC WORK IN MASSACHUSETTS, UNDERSTANDING CHAPTER 149 AND CHAPTER 149A PANELISTS: Deborah Anderson, Esq. Office of the Attorney General Laura Wernick, FAIA, REFP, LEED AP HMFH Architects, Inc.
More informationOffice of the Inspector General
Office of the Inspector General Commonwealth of Massachusetts Gregory W. Sullivan Inspector General Experience of Massachusetts Public Agencies with Construction Management at Risk Under M.G.L. c. 149A
More informationEXHIBITS TO GUIDELINES FOR PREQUALIFICATION GENERAL CONTRACTORS AND SUBCONTRACTORS TO WORK ON PUBLIC BUILDING CONSTRUCTION PROJECTS
EXHIBITS TO GUIDELINES FOR PREQUALIFICATION OF GENERAL CONTRACTORS AND SUBCONTRACTORS TO WORK ON PUBLIC BUILDING CONSTRUCTION PROJECTS Table of Exhibits Exhibit Exhibit A Exhibit B Exhibit C Exhibit D
More informationExecutive Office for Administration & Finance. Request for Qualifications For Construction Management Services
Executive Office for Administration & Finance Request for Qualifications For Construction Management Services Massachusetts State Project (Project Number) (Full Project Name and Location), Massachusetts
More informationOffice of the Inspector General
Office of the Inspector General Commonwealth of Massachusetts Gregory W. Sullivan Inspector General Guide to Bonding Requirements Under Construction Reform April 2005 April 2005 Dear Public Official: Contractors
More informationATTENTION APPLICANTS
ATTENTION APPLICANTS PLEASE READ THIS PAGE BEFORE COMPLETING THE ATTACHED APPLICATION FOR CERTIFICATE OF ELIGIBILITY AND CONTRACTOR QUALIFICATION STATEMENT. PLEASE NOTE: Asset Management certification
More informationPASADENA AREA COMMUNITY COLLEGE DISTRICT (PACCD) 2015 California Uniform Public Construction Cost Accounting Act (CUPCCAA) Informal Bid List
PASADENA AREA COMMUNITY COLLEGE DISTRICT (PACCD) 2015 California Uniform Public Construction Cost Accounting Act (CUPCCAA) Informal Bid List At their Board meeting of August 21, 2013, the Trustees of the
More informationProcurement of Energy Management Services
Helping Massachusetts Municipalities Create a Cleaner Energy Future COMMONWEALTH OF MASSACHUSETTS Charles D. Baker, Governor Matthew Beaton, Secretary Judith Judson, Commission Procurement of Energy Management
More informationTel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2
The Commonwealth of Massachusetts Executive Office for Administration and Finance Division of Capital Asset Management One Ashburton Place Boston, Massachusetts 02108 Tel: (617) 727-4050 Fax: (617) 727-5363
More informationCollege of the Siskiyous Insurance Requirements
College of the Siskiyous Insurance Requirements Minimum Insurance Coverages for 2016 Pre-Qualification Contractor Insurance. The Contractor shall obtain and maintain the following insurance coverages with
More informationCONTRACTOR PREQUALIFICATION REQUIREMENTS GENERAL CONTRACTORS, MECHANICAL/PLUMBING SUBCONTRACTORS & ELECTRICAL SUBCONTRACTORS FOR THE
CONTRACTOR PREQUALIFICATION REQUIREMENTS GENERAL CONTRACTORS, MECHANICAL/PLUMBING SUBCONTRACTORS & ELECTRICAL SUBCONTRACTORS FOR THE SANTEE SCHOOL DISTRICT 1 .......... 2 1. Effective January 1 st, 2014,
More informationNOTICE TO CONTRACTORS
NOTICE TO CONTRACTORS Notice is hereby given that San Luis Obispo County Community College District, ( District ) is accepting sealed Informal Bidding Prequalification Applications and Formal Bidding Prequalification
More informationADVISORY 2004/3. An Advisory from the Attorney General's Fair Labor Division on an Act Protecting the Wages and Tips of Certain Employees
ADVISORY 2004/3 An Advisory from the Attorney General's Fair Labor Division on an Act Protecting the Wages and Tips of Certain Employees Pursuant to M.G.L. c. 23, s. 1(b), the Office of the Attorney General
More informationCarmel Unified School District. Prequalification Application For Bleacher and Pressbox Replacement Project at Carmel High School
Carmel Unified School District Prequalification Application For Bleacher and Pressbox Replacement Project at Carmel High School January 4, 2016 1 NOTICE REGARDING PREQUALIFICATION FOR BLEACHER AND PRESSBOX
More informationChapter 2 - The Process Of Construction Contract Procurement. For Facilities Projects
Pennsylvania State System of Higher Education Facilities Manual - Volume 30 Engineering / Architectural Instructions Manual Chapter 2 The Process Of Construction Contract Procurement For Facilities Projects
More informationDesigning and Constructing Public Facilities
Designing and Constructing Public Facilities Legal Requirements Recommended Practices Sources of Assistance Commonwealth of Massachusetts Office of the Inspector General Gregory W. Sullivan Inspector General
More informationGetting Connected with the Colorado Department of Transportation (CDOT)
Getting Connected with the Colorado Department of Transportation (CDOT) INTRODUCTION Who is CDOT? CDOT is responsible for 9,146 miles of highway including 3,447 bridges State government agency with funding
More informationThe Commonwealth of Massachusetts Division of Capital Asset Management
The Commonwealth of Massachusetts Division of Capital Asset Management CERTIFICATION GUIDELINES AND PROCEDURES FOR PRIME CONTRACTORS AND AWARDING AUTHORITIES I. PREFACE p. 2 Categories of Work p. II. INFORMATION
More informationIntroduction/Background. Competitive Bidding- Statutory Requirements. Competitive Bidding- Charter/Code Requirements
Public Works Contracts in Missouri Presented September 8, 2008 by Joe Lauber 2008 Missouri Municipal League Annual Conference Introduction/Background Bidding the project New construction safety training
More informationHoneywell Energy Services Group
Honeywell Energy Services Group Minnesota State Colleges and Universities Riverland Community College Guaranteed Energy Savings Program (GESP) Project Request for Qualifications (RFQ) Phase 3 Lighting
More informationUNIVERSITY OF MASSACHUSETTS BUILDING AUTHORITY
UNIVERSITY OF MASSACHUSETTS BUILDING AUTHORITY PROJECT MANUAL AND NOTICE TO CONTRACTORS BAYSIDE PARKING LOT REDEVELOPMENT BUILDING DEMOLITION PHASE AT THE UNIVERSITY OF MASSACHUSETTS BOSTON PROJECT NO.:
More informationVDOT Prequalification. Suzanne Lucas Construction Division
VDOT Prequalification Suzanne Lucas Construction Division VDOT Prequalification for Highway Contractors in the Commonwealth of Virginia 2 What is Prequalification? AASHTO defines a prequalification system
More informationGUIDELINES FOR SMALL BUSINESS CONSTRUCTION CONTRACTS
GUIDELINES FOR SMALL BUSINESS CONSTRUCTION CONTRACTS HARRISBURG, PENNSYLVANIA MAY 2014 EDITION Guidelines for the DGS Small Business Reserve Program For Construction Contracts 1 General a.) Pursuant to
More informationINFORMAL BIDDING APPLICATION FOR REGISTRATION November 2015 October 2016
INFORMAL BIDDING APPLICATION FOR REGISTRATION General Instructions: Bidders must complete the entire Application. If the requested information does not apply please indicate by N/A. If there is not enough
More informationFrequently Asked Questions Concerning the Public Bidding and Prevailing Wage Requirements of New Jersey Charter Schools
Frequently Asked Questions Concerning the Public Bidding and Prevailing Wage Requirements of New Jersey Charter Schools 1. Are charter schools required to comply with New Jersey public bidding requirements
More informationesi ning and Constructing ublic acilities
esi ning and Constructing ublic acilities.. Legal Requirements.. Recommended Practices.. Sources of Assistance Commonwealth of Massachusetts Office of the Inspector General Glenn A. Cunha Inspector General
More informationPITTSBURG UNIFIED SCHOOL DISTRICT
PITTSBURG UNIFIED SCHOOL DISTRICT New Construction and Modernization Projects PRE-QUALIFICATION PROGRAM QUESTIONNAIRE FOR PROJECTS $20 MILLION AND OVER TABLE OF CONTENTS PAGE NO. GENERAL INFORMATION.......i
More informationMINNESOTA STATE COLLEGES AND UNIVERSITIES
Projects with an estimated construction cost of $50,000 or less may be bid without advertising. Funding: The College/University must take appropriate action to confirm that funds are available in an active
More informationFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874
ADVERTISEMENT FOR LETTERS OF INTEREST FOR A DESIGN BUILD PROJECT (PROCUREMENT METHOD SHORTLISTING OF PROPOSERS WITH TECHNICAL AND PRICE EVALUATION BY ADJUSTED SCORE) PROCUREMENT NUMBER: E2N44 Financial
More informationTRAVIS UNIFIED SCHOOL DISTRICT REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT SERVICES CONSTRUCTION MANAGER MULTI-PRIME
TRAVIS UNIFIED SCHOOL DISTRICT REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT SERVICES CONSTRUCTION MANAGER MULTI-PRIME QUESTIONS PAGE 11 200.325 BONDING REQUIREMENTS Please confirm that construction
More informationNEW JERSEY ADMINISTRATIVE CODE Copyright 2015 by the New Jersey Office of Administrative Law
Page 1 NEW JERSEY ADMINISTRATIVE CODE Copyright 2015 by the New Jersey Office of Administrative Law *** This file includes all Regulations adopted and published through the *** *** New Jersey Register,
More informationMorgan Hill Unified SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE FOR PROSPECTIVE BIDDERS. October 19, 2015
Morgan Hill Unified SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE FOR PROSPECTIVE BIDDERS October 19, 2015 The Morgan Hill Unified School District ( District ) has determined that contractors on future
More informationOAKLAND UNIFIED SCHOOL DISTRICT FOR LOCAL FIRST TIER SUBCONTRACTORS PREQUALIFICATION QUESTIONNAIRE FOR PROSPECTIVE BIDDERS
OAKLAND UNIFIED SCHOOL DISTRICT FOR LOCAL FIRST TIER SUBCONTRACTORS PREQUALIFICATION QUESTIONNAIRE FOR PROSPECTIVE BIDDERS THIS QUESTIONNAIRE MUST BE PRINTED ON BLUE PAPER OAKLAND UNIFIED SCHOOL DISTRICT
More informationCapital Projects Construction Manager At-Risk (CMR) Guaranteed Maximum Price (GMP) Best Value Selection Procedure Manual
Page 1 of 21 Connecticut Department of Administrative Services Capital Projects Construction Manager At-Risk (CMR) Guaranteed Maximum Price (GMP) Best Value Selection Procedure Manual Prepared for Capital
More informationPREQUALIFICATION QUESTIONNAIRE
PREQUALIFICATION QUESTIONNAIRE BAW&G/WHW/JWF/172861.2 Revision Date: 01-14/14 1 Contractor Prequalification Package CONTACT INFORMATION Firm Name: Check One: Corporation (as it appears on license) Partnership
More informationBOND MEASURE E CONTRACTOR OUTREACH
FREMONT UNIFIED SCHOOL DISTRICT BOND MEASURE E CONTRACTOR OUTREACH May 4, 2015 INTRODUCTIONS Therese Gain, Director of Facilities, Fremont Unified School District Carol Lemos, Administrative Assistant
More informationPROCUREMENT POLICY CHAPTER 142.010
PROCUREMENT POLICY CHAPTER 142.010 Approved by Board of Aldermen Resolution 15-659 Revised March 25, 2015 CHAPTER 142: PROCUREMENT POLICY ARTICLE 1. GENERAL PROVISIONS SECTION 142.010 PROCUREMENT POLICY
More informationNebraska Public Schools: Statutes Related to the Construction of Improvements to Real Property
Nebraska Public Schools: Statutes Related to the Construction of Improvements to Real Property 73-101. Public lettings; how conducted. Whenever the State of Nebraska, or any department or any agency thereof,
More informationREQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES ISSUED BY: INGLEWOOD UNIFIED SCHOOL DISTRICT Issued: November 20, 2015 Due: December 18, 2015 SCHEDULE OF EVENTS INGLEWOOD UNIFIED SCHOOL
More informationHow To Help The Town Of Bloomsburg With A Flood Resilience Program
REQUEST FOR PROPOSALS FOR PROFESSIONAL HOUSING REHABILITATION PROGRAM ADMINISTRATIVE AND MANAGEMENT SERVICES TOWN OF BLOOMSBURG, COLUMBIA COUNTY, PENNSYLVANIA Requested by: Town of Bloomsburg 301 East
More informationAgenda. Graphic 1. Graphic 2. Graphic 3. Supplier Diversity Program (SDP) Webinar. How to Submit a Supplier Diversity Plan
Supplier Diversity Program (SDP) Webinar Welcome to the Operational Service Division s Supplier Diversity Program webinar. This presentation is for businesses that are interested in responding to an open
More information12-15-08 DRAFT 2009FL-0004/018
1 HEALTH REFORM - HEALTH INSURANCE 2 COVERAGE IN STATE CONTRACTS 3 2009 GENERAL SESSION 4 STATE OF UTAH 5 6 LONG TITLE 7 General Description: 8 This bill requires certain state entities to require a contractor
More informationPrequalification Supplement for First Tier Subcontractors under CM at Risk Wake Technical Community College Early Site North Campus Project
NC General Statue 143-128.1.c states, The construction manager at risk shall contract directly with the public entity for all construction; shall publically advertise as prescribed in G.S. 143-129; and
More informationPrequalification Document for Procurement of Works
STANDARD PROCUREMENT DOCUMENT Prequalification Document for Procurement of Works Caribbean Development Bank September 2007 ii Foreword This Standard Procurement Document Prequalification Document for Procurement
More informationREQUEST FOR QUALIFICATIONS PLANNING, DESIGN AND CONSTRUCTION ARCHITECTURAL SERVICES FOR THE NEW COUNTY DETENTION CENTER
REQUEST FOR QUALIFICATIONS PLANNING, DESIGN AND CONSTRUCTION ARCHITECTURAL SERVICES FOR THE NEW COUNTY DETENTION CENTER MIAMI COUNTY DETENTION CENTER 118 S. Pearl Paola, Kansas 66071 RESPONSE DEADLINE:
More informationMondays 9:00 a.m. 4:30 p.m. Tuesdays 9:00 a.m. 4:30 p.m. Wednesdays 9:00 a.m. 1:00 p.m. Thursdays 9:00 a.m. 4:30 p.m. Fridays 9:00 a.m. 4:30 p.m.
TOWN OF WEBSTER, MASSACHUSETTS REQUEST FOR QUALIFICATIONS FOR OWNER S PROJECT MANAGEMENT SERVICES FOR THE CHESTER C. CORBIN PUBLIC LIBRARY CONSTRUCTION PROJECT The Town of Webster, Massachusetts seeks
More informationRHODE ISLAND CONSTRUCTION LAW PRIMER
RHODE ISLAND CONSTRUCTION LAW PRIMER By Chad L. Hershman, Esq. chershman@haslaw.com 617-378-4192 I. Introduction: As the construction industry continues to attempt to emerge from a period of decreased
More informationGREENFIELD MIDDLE SCHOOL ROOF PROJECT
CITY OF GREENFIELD GREENFIELD, MASSACHUSETTS RFQ TITLE: GREENFIELD MIDDLE SCHOOL ROOF PROJECT RFQ #: 12-03 Date of Issuance: June 22, 2011 9:00 a.m. Deadline for Receipt Of Bids: July 8, 2011 2:00 p.m.
More informationTOWN OF MILFORD REQUEST FOR QUALIFICATIONS DESIGNER SERVICES FOR LIBRARY ROOF REPLACEMENT
TOWN OF MILFORD REQUEST FOR QUALIFICATIONS DESIGNER SERVICES FOR LIBRARY ROOF REPLACEMENT The Milford Board of Library Trustees, as the Awarding Authority, invites the submission of qualifications by responsible
More informationState of North Carolina Prequalification for First Tier Subcontractors under CM at Risk
NC General Statute 143.128.1.c states, The construction manager at risk shall contract directly with the public entity for all construction; shall publicly advertise as prescribed in G.S. 143 129; and
More informationSAN BERNARDINO MOUNTAINS COMMUNITY HEALTHCARE DISTRICT
SAN BERNARDINO MOUNTAINS COMMUNITY HEALTHCARE DISTRICT CONTRACTOR PRE-QUALIFICATION QUESTIONNAIRE 1 PRE-QUALIFICATION QUESTIONNAIRE 000 CONTACT INFORMATION Firm Name: Check One: Corporation (as it appears
More informationPRE BID MEETING AGENDA
PRE BID MEETING AGENDA Project Name: UCHC Academic Bldg. Addition & Renovation Meeting Location: UCHC, Farmington, CT Campus Project #: 901729 Meeting Date: December 10, 2014 1. Team Introductions: Construction
More informationCity of Chicago - Department of Procurement Services. January 31, 2014. Addendum No. 1 TARGET MARKET REQUEST FOR QUALIFICATIONS ( RFQ ) For
City of Chicago - Department of Procurement Services January 31, 014 Addendum No. 1 TARGET MARKET REQUEST FOR QUALIFICATIONS ( RFQ ) For COURT REPORTER AND TRANSCRIPTION SERVICES Specification No. 118343
More informationADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES *RE-ADVERTISED*
ADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES *RE-ADVERTISED* BID PACKAGE DESCRIPTION REQUIRED LICENSE Bid Package No. 1 Asbestos Abatement C22 or B, with ASB & HAZ Certification Bid
More informationOcoee, FL July 01, 2016 Advertisement No. 1
BID SOLICITATION NOTICE Turnpike FLORIDA DEPARTMENT OF TRANSPORTATION CONSTRUCTION AND MAINTENANCE PROGRAMS Ocoee, FL July 01, 2016 Advertisement No. 1 All bids must be completed using Expedite Bid software
More informationSCRANTON, PA 18503 (570) 963-6800
REQUEST FOR PROPOSALS FOR GRANT WRITING SERVICES FOR ENVIRONMENTAL ASSESSMENTS OF BROWNFIELD SITES PROPOSAL FORMAT AND SCOPE OF SERVICES PROPOSALS TO BE SUBMITTED BY 10:00 AM, MONDAY, SEPTEMBER 29, 2014
More informationSECTION 00100 NOTICE TO BIDDERS IVY TECH COLLEGE OF INDIANA NMC INFRASTRUCTURE IMPROVEMENTS INDIANAPOLIS, INDIANA
Ivy Tech Community College of Indiana, hereinafter referred to as the Owner, furnishes the following information and special instructions to prospective Bidders desiring to submit Bids for the Work on
More informationREQUEST FOR QUALIFICATIONS
REQUEST FOR QUALIFICATIONS CONTRACT GE-357 RECONSTRUCTION AND REPLACEMENT OF BROKEN WATER MAINS ON AN EMERGENCY BASIS, SYSTEM WIDE I. GENERAL INFORMATION Scope of Work The Department of Design and Construction
More informationRFP-10-20 Courier and Logistics Services For the Indiana State Department of Health
RFP-10-20 Courier and Logistics Services For the Indiana State Department of Health Contacts: Shelley Harris, In Department of Administration sharris@idoa.in.gov 317.233.3105 Secretary of State Charles
More information2. Ensure that small and minority and women s businesses are solicited whenever they are potential sources of products or services to be bid;
MBE/WBE: Six (6) Affirmative Steps The Code of Federal Regulations Title 40 Part 31.36(e), Procurement, requires the Recipient and Prime Contractor to take all necessary affirmative steps to assure that
More informationB. The History of the Law
An Advisory from the Attorney General s Fair Labor Division on M.G.L. c. 149, s. 148B 2008/1 1 The Office of the Attorney General (AGO) issues the following Advisory regarding M.G.L. c. 149, s. 148B, the
More informationRequest for Proposal # CL16-HT-0006 Web-Based Bid Document Distribution, Electronic Bid Specification Tool, Bidding, Archiving (Record Retention) And
Request for Proposal # CL16-HT-0006 Web-Based Bid Document Distribution, Electronic Bid Specification Tool, Bidding, Archiving (Record Retention) And Consulting Services 1 1. Overview The University of
More informationAPPLICATION FOR PRE-QUALIFICATION OF GENERAL CONTRACTORS AND PRIME CONTRACTORS. (for construction projects valued at more than $250,000) for
Palomar Community College District Business & Contract Services, Room A-10 1140 W. Mission Rd. San Marcos, CA 92069-1487 Phone: (760) 744-1150 x 2129 FAX: (760) 761-3548 APPLICATION FOR PRE-QUALIFICATION
More informationFREQUENTLY ASKED QUESTIONS General Licensing Issues
Q: When is a license required as a Residential Builder or Maintenance & Alteration Contractor? A: In general, a person who contracts with a property owner to do residential construction or remodeling on
More informationCHAPTER 48-01.2 PUBLIC IMPROVEMENT BIDS AND CONTRACTS
CHAPTER 48-01.2 PUBLIC IMPROVEMENT BIDS AND CONTRACTS 48-01.2-01. Definitions. In this chapter, unless the context otherwise requires: 1. "Agency construction management" means a public improvement delivery
More informationContractor s Bond Questionnaire
We appreciate the opportunity to be the broker of record in providing surety bond credit to your company. The purpose of this questionnaire is to assist us, and the designated surety company, in evaluating
More informationMechanical Contractor Pre-Qualification Packet. SPSC N180 Computer Data Room Phase II. Project No. CP 159313. Notice No. Notice 13-11.
Mechanical Contractor Pre-Qualification Packet SPSC N180 Computer Data Room Phase II Project No. CP 159313 Notice No. Notice 13-11 Issued by Department of Facilities Management Delivery address: Research
More informationHunt Construction Group, Inc. LEVEL 1 DESIGN BUILD SPECIALTY CONTRACTOR PREQUALIFICATION DOCUMENTS FOR:
Hunt Construction Group, Inc. LEVEL 1 DESIGN BUILD SPECIALTY CONTRACTOR PREQUALIFICATION DOCUMENTS FOR: San Diego State University Basketball Practice Facility Project Number: 03400200 October 2013 San
More informationGENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES
REQUEST FOR QUALIFICATIONS GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES NEW DINING HALL MONTANA STATE UNIVERSITY Bozeman, Montana PPA NO. 15-0103 Campus Planning, Design & Construction Plew Building
More informationInternational Peace Support Training Centre Westwood Park P O Box 24232-00502 Karen, Kenya
International Peace Support Training Centre Westwood Park P O Box 24232-00502 Karen, Kenya PRE-QUALIFICATION TENDER NO. IPSTC/PREQ/2014/2015/043 FOR PROVISION OF PLUMBING SERVICES FOR 2014/2015 July, 2014
More informationRequest for Qualifications. Owner s Project Manager. Design and Construction of a New School Facility. K~8 Charter School
Request for Qualifications Owner s Project Manager Design and Construction of a New School Facility K~8 Charter School 26 Madeira Avenue New Bedford, MA 02746 REQUEST FOR QUALIFICATIONS (RFQ) Issued: 4/16/2014
More informationREQUEST FOR QUALIFICATIONS FOR FY 2015 MAJOR PLANT REHABILITATION PROJECT FOR ENCINA WASTEWATER AUTHORITY S ENCINA WATER POLLUTION CONTROL FACILITY
REQUEST FOR QUALIFICATIONS FOR FY 2015 MAJOR PLANT REHABILITATION PROJECT FOR ENCINA WASTEWATER AUTHORITY S ENCINA WATER POLLUTION CONTROL FACILITY Ref: Admin.15 12265a September 23, 2015 Qualifications
More informationSub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders
INTRODUCTORY INFORMATION TABLE OF CONTENTS 00 0101 PROJECT TITLE PAGE PROCUREMENT REQUIREMENTS (PROJECT MANUAL) Tab A - Invitation for Bids Tab B - Instructions to Bidders Tab C Bid Form for General Bids
More informationThe School Board of Miami-Dade County, Florida Department of Contractor Prequalification Frequently Asked Questions and Answers
The School Board of Miami-Dade County, Florida Department of Contractor Prequalification Frequently Asked Questions and Answers Question 1: How long will the prequalification process take? Answer: The
More informationA mandatory pre bid walk through will be held on May 14, 2015 at 1:30 p.m. See Invitation to Bid for pre qualifications required to bid.
REQUEST FOR PROPOSALS (RFP) for CONSTRUCTION SERVICES at Hollywood Theater: Minimum Improvements and Add Alternates 2815 Johnson Street NE Minneapolis, MN 55418 Section 1: Introduction Out of the Past
More information15-213. Procurement practices of school districts and charter schools; definitions
ARIZONA AUTHORITY 15-213. Procurement practices of school districts and charter schools; definitions A. The state board of education shall adopt rules prescribing procurement practices for all school districts
More informationSolicitation Information February 26, 2016
Solicitation Information February 26, 2016 RFP#7550347 TITLE: SEARCH FOR AFFORDABLE CARE ACT TAX REPORTING SOLUTION Submission Deadline: Monday, March 21, 2016 @ 11:30 AM (Eastern Time) Questions concerning
More informationANY INVALID WILL NOT
NOTICE!! THIS IS AN OFFICIAL DOCUMENT THAT IS USED TO DETERMINE THE QUALIFICATIONS OF CONTRACTORS TO BID WITH THE AGENCY OF TRANSPORTATION FOR THE STATE OF VERMONT. ANY ALTERATIONS OF THIS DOCUMENT WILL
More informationTown of Clinton MECHANICAL/SHEET METAL PERMIT 242 Church Street, Clinton MA. 01510 Tel: (978) 365-4128 Fax: (978) 612-0202
Town of Clinton MECHANICAL/SHEET METAL PERMIT 242 Church Street, Clinton MA. 01510 Tel: (978) 365-4128 Fax: (978) 612-0202 Building Commissioner Zoning Enforcement Officer Tony Zahariadis This Section
More informationPanel 4 Insurance, Materials. Table of Contents
Panel 4 Insurance, Materials Table of Contents Limitations on the Use of Wrap-Up Insurance when a State, a Municipality or Other Public Entity Commissions or Conducts a Construction Project New York Construction
More informationDOCUMENT 00400 BID FORM TO THE SAN FRANCISCO PORT COMMISSION, CITY AND COUNTY OF SAN FRANCISCO
Date of Bid: DOCUMENT 00400 BID FORM TO THE SAN FRANCISCO PORT COMMISSION, CITY AND COUNTY OF SAN FRANCISCO In response to the Advertisement for Bids for the following public work: PIER 26 SOUTH BULKHEAD
More informationSTATE OF MINNESOTA OFFICE OF THE STATE AUDITOR
REBECCA OTTO STATE AUDITOR STATE OF MINNESOTA OFFICE OF THE STATE AUDITOR SUITE 500 525 PARK STREET SAINT PAUL, MN 55103-2139 (651) 296-2551 (Voice) (651) 296-4755 (Fax) state.auditor@osa.state.mn.us (E-mail)
More informationAdvisory on the Massachusetts Independent Contractor/Misclassification Law
Advisory on the Massachusetts Independent Contractor/Misclassification Law http://www.mass.gov/?pageid=cagoterminal&l=2&l0=home&l1=workplace+rights&sid=cago&b=te... Page 1 of 1 9/15/2008 The Official Website
More informationATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects
Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects Pursuant to Revised Statute of Missouri Section 8.250(3), Ozarks Technical
More informationOn behalf of Governor Pat Quinn and CDB s Executive Director, Jim Underwood Welcome!
On behalf of Governor Pat Quinn and CDB s Executive Director, Jim Underwood Welcome! 1 WHAT CDB IS DOING FOR THE STATE OF ILLINOIS 2 Capital Development Board Created in 1972 Illinois General Assembly
More informationREQUEST FOR QUALIFICATIONS
A. Instructions for the Request of Qualifications 1. Interested professional services are invited to submit one (1) comprehensive Statement of Qualifications (SOQ) by responding to the items below. Responses
More informationCLARK COUNTY DEPARTMENT OF ADMINISTRATIVE SERVICES PURCHASING & CONTRACTS DIVISION
CLARK COUNTY DEPARTMENT OF ADMINISTRATIVE SERVICES PURCHASING & CONTRACTS DIVISION Clark County Government Center 500 Grand Central Parkway, 4th Floor Las Vegas, NV 89106 Phone: (702) 455-2897 Fax: (702)
More informationCHAPTER 7 PUBLIC WORKS LAW
7-1 CHAPTER 7 PUBLIC WORKS LAW GENERAL PROVISIONS The "Public Works Law" [IC 36-1-12] applies to all public work performed or contracted by political subdivisions and their agencies. Any public work performed
More informationHUMAN RESOURCE COMPLIANCE AUDIT
REQUEST FOR PROPOSAL (RFP) TOWN OF WEST BOYLSTON MASSACHUSETTS October 24, 2011 REQUEST FOR PROPOSAL (RFP) TOWN OF WEST BOYLSTON, MA 1 GENERAL INFORMATION: The Town of West Boylston is soliciting proposals
More informationORDINANCE NO.------- THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS:
ORDINANCE NO.------- An ordinance authorizing the award of one design-build contract for the decommissioning, disablement, demolition and removal of Scattergood Generating Station Unit 3 pursuant to a
More informationHow to File a Workers Compensation Request For Proposal
REQUEST FOR PROPOSAL West Virginia Offices of the Insurance Commissioner Workers Compensation for West Virginia State Agencies INS 11015 TABLE OF CONTENTS Section 1: Section 2: Section 3: Section 4: Section
More informationDenver Water Capital Projects Contractor Prequalification REQUEST FOR QUALIFICATIONS
RFQ Term: 9/29/2015 12/1/2019 Denver Water Capital Projects Contractor Prequalification REQUEST FOR QUALIFICATIONS Denver Water (DW), in an effort to improve the administration and efficiency, has initiated
More informationHow to do Business. with Charlotte-Mecklenburg Utilities. http://cmucontracts.charmeck.org
How to do Business with Charlotte-Mecklenburg Utilities http://cmucontracts.charmeck.org How Charlotte-Mecklenburg Utilities Purchases Products and Services 2 & 3 l About Water and Sewer Projects 4 & 5
More informationREQUEST FOR QUALIFICATIONS PROPERTY APPRAISAL SERVICES. Prepared by. City of Richmond Finance Department. February 18, 2016 RESPONSES DUE:
REQUEST FOR QUALIFICATIONS PROPERTY APPRAISAL SERVICES Prepared by City of Richmond Finance Department February 18, 2016 RESPONSES DUE: 2:30 P.M., Monday, March 7, 2016 REQUEST FOR STATEMENTS OF QUALIFICATIONS
More informationVIRGINIA POLYTECHNIC INSTITUTE AND STATE UNIVERSITY (Virginia Tech) REQUEST FOR QUALIFICATIONS RFQ #CM-208-18267
VIRGINIA POLYTECHNIC INSTITUTE AND STATE UNIVERSITY (Virginia Tech) REQUEST FOR QUALIFICATIONS RFQ #CM-208-18267 Title: Prequalification of Construction Managers at Risk Virginia Tech Renovate Holden Hall
More informationCCFC 22 nd Annual Conference
CCFC 22 nd Annual Conference Public Agency Law Group Attorneys At Law Sherman Wong 222 North Sepulveda Boulevard Suite 1690 El Segundo, California 90245 Tel: (310) 640-0800 Fax: (310) 640-0818 swong@palg.net
More informationThe Commonwealth of Massachusetts AUDITOR OF THE COMMONWEALTH
The Commonwealth of Massachusetts AUDITOR OF THE COMMONWEALTH ONE ASHBURTON PLACE, ROOM 1819 BOSTON, MASSACHUSETTS 02108 A. JOSEPH DeNUCCI AUDITOR TEL. (617) 727-6200 NO. 2008-1461-3A INDEPENDENT STATE
More informationDetroit Land Bank Authority. Request for Qualifications: As Needed Legal Services
Detroit Land Bank Authority Request for Qualifications: As Needed Legal Services RFQ NUMBER: 02-09-2015 DATE ISSUED: Request for Qualifications As Needed Legal Services Page 2 REQUEST FOR QUALIFICATIONS
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Shideler Hall Renovation Response Deadline 12/20/13
More informationOP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS
OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS SPECIFIC AUTHORITY Sections 240.209(3)(p), 1001.74, 1013.46, F. S. OBJECTIVE To establish procedures for the administration of construction