1 1 July 6, 2012 PSC Supplemental Comments on USAID draft IDIQ template There are three principal areas of concern in the draft IDIQ template: (1) the cost evaluation matrix; (2) the use of a single ceiling for unburdened daily rates; and (3) the way fixed fee ceilings are treated. Each of these is addressed separately below. 1. Cost Evaluation Matrix The evaluation approach falls short of the standard to consider the price the USG will pay. Section L.5 requires offerors to complete a Cost Evaluation Matrix, proposing single unburdened ceiling daily rates for each labor category (per Section B.7), ceiling indirect cost rates and a fixed fee percentage ceiling, and using LOE plug figures. We do not believe that this is an appropriate methodology for cost evaluation at the prime award stage because it would impede the government s ability to fairly compare prices across offerors and would fail to consider the the overall price the government will actually pay, as required by FAR (b) Price negotiation. Furthermore, the use of single ceiling prices in an IDIQ competition rather than analysis of the actual cost that the government can reasonably be expected to pay would create the risk of a misleading result, which appears to be inconsistent with FAR (d)(2) Proposal analysis techniques, which states that while it is up to the agency to decide upon some appropriate and reasonable method for the evaluation of offerors prices, an agency may not use an evaluation method that produces a misleading result. Requiring offerors to use the plug figures for LOE, absent an actual or illustrative scope of work, precludes offerors from budgeting LOE based on their customary accounting practices or cost accounting standards. It therefore does not reflect the considerable disparities in the indirect cost rate structures and methods used to bill labor by different offerors. This could artificially cause offerors who bill certain types of labor indirectly to appear more expensive in this type of plug figure-based IDIQ evaluation method when in fact they may cost the government the same or less on actual Task Orders. For example, some organizations bill certain types of labor directly, such as home-office backstopping, that other organizations include in their indirect rates. Offerors that bill home-office backstopping directly would require more level of effort to provide the same package of technical assistance as an offeror that bills indirectly, and may have lower indirect rates as a result of the direct billing. The use of LOE plug figures, unburdened ceiling daily rates for direct labor and ceiling indirect cost rates will lead to a price evaluation by USAID, at the prime award stage, largely amounting to a comparison of labor rates and indirect rates at the rate level, which is inherently misleading for the reasons that OAA describes in USAID s Best Practices Guide for Indirect Costing: It is generally not possible to compare indirect costs between organizations at the rate level, whether they are a for-profit or non-profit firm. Indirect costs must be compared at the cost level. An indirect cost rate by itself has very little meaning. Given these facts, the evaluation method set forth in the template impairs the Contracting Officer s ability to evaluate proposals based on the price the government will actually pay.

2 2 Proposed Solution: Proposal budgets could be prepared according to an actual or notional scope of work incorporated in the RFP. This will help remedy the above situation, and provide an essential element for addressing the FAR (b) requirements. By providing a scope against which to budget level of effort for prime and subcontractors, with indirect rates applied according to each organization s cost structure, USAID can establish a realistic representation of cost to the government. AAPD is silent on the question of how to include a notional scope of work, but USAID has successfully conducted numerous effective IDIQ procurements based on such scopes of work. The scope can be simple, thus minimizing the effort required on the part of the Contracting Officer or Technical Evaluation Committee. USAID could opt to require a brief technical approach for the sample task order or could simply evaluate the resulting price offers for cost realism. Following this approach at the prime award stage is consistent with the objective of understanding and increasing competition at the task order level, which provides the greatest opportunity for USAID to achieve better development outcomes at lower costs. 2. Unburdened Ceiling Daily Rates The requirement for single unburdened daily rate ceilings undermines the principles of CPFF contracting and transfers risks to contractors that are inappropriate to the contract type. Section B.7(a) requires offerors to propose and accept a single unburdened ceiling daily rate for each labor category. While we appreciate the objective of providing more standardization under task orders, we believe that this approach would limit contractors flexibility at the task order stage by requiring inappropriate risk tradeoffs. This requirement appears to be inconsistent with AIDAR Personnel Compensation, incorporated in the contract under Section B.7(a), which stipulates that personnel compensation be in accordance with the contractor s established policies, procedures, and practices, with reimbursement subject only to the USAID Contractor Salary Threshold. Requiring offerors to accept unburdened ceiling daily rates may preclude contractors from following their established policies, procedures, and practices, as required by AIDAR The negotiation of a fee (within the statutory limit of 10% fee on CPFF contracts) is reasonable because such contracts reimburse all reasonable, allocable, and allowable costs incurred by the contractor, and places responsibility on the contractor for payment (from the negotiated fee) of unallowable costs, including the cost of funds. The current draft template s requirement for unburdened ceiling daily rates requires offerors to choose between: a. Proposing high ceilings to be able to manage the contract in accordance with a risk profile consistent with the CPFF format, which means the proposal may be rejected based on what is perceived to be an uncompetitive price (but in fact may not be uncompetitive at the TO stage, as discussed above); or b. Accepting the extraordinary risk that it may face the choice of proposing staff that are less technically competitive but who will accept compensation within the predetermined unburdened ceiling, or proposing technically qualified staff to offer best value to USAID but whose compensation is above the ceiling rates (requiring the contractor to pay for the unallowable portion of the compensation from its negotiated fee.) Either option distorts the risk profile inherent in cost reimbursement contracts, skewing the contract form more toward fixed-rate (e.g., time-and-materials) mechanisms, without allowing for pricing considerations available to T&M contractors to adjust for uncertain labor requirements. For example, in

3 3 a fixed daily rate or fixed multiplier structure, contractors can manage their risks by offsetting any greater-than-anticipated labor costs with greater-than-anticipated recovery on other personnel. Pressuring contractors to set rate ceilings rather than fixed rates, and allowing only for subsequent reimbursement of actual costs incurred, creates the cost risks of fixed-rate mechanisms without the corresponding ability to offset those risks. The problems associated with requiring an unburdened ceiling daily rate are exacerbated by Section B.7 (a), which states that the ceiling rates proposed will remain operative for the entire life of the IDIQ contract period, which could be up to seven years (a five year ordering period plus the additional two years covered under Note 1 on page 9). Offerors cannot reasonably be expected to predict salaries for a diverse group of personnel seven years in advance, based on no actionable scope of work and an indeterminate volume of work. This fact is acknowledged by USAID in ADS , Standardization of Indefinite Quantity Contracts (IQCs), and AAPD incorporated by reference therein, which states that CPFF IQCs are chosen when The pricing uncertainties in these contracts and their orders make it difficult, if not impossible, for offerors to estimate fixed rates or multipliers with any degree of confidence or realism. If offerors cannot estimate fixed rates with confidence, they cannot be expected to estimate even riskier rate ceilings with confidence. Proposed Solution: Follow standard cost reimbursement principles rather than attempt unburdened salary ceilings. Evaluate cost at the prime award stage by means of a sample TO. Evaluate CPFF TOs following best value principles. 3. Indirect Cost Ceiling Section L.5(b)1(b), page 68, states that the prime offeror and each major subcontractor must propose ceiling indirect cost rates. Further instructions are provided on page 69 and a similar clause is included on page 71. While we understand that it is common for USAID contractors to offer ceilings on some indirect cost rates to enhance their competitiveness, our understanding is that the government may only require indirect cost rate ceilings when the conditions of FAR (b) Cost-sharing rates and limitations on indirect cost rates are met, referenced below: (b)(1) Other situations may make it prudent to provide a final indirect cost rate ceiling in a contract. Examples of such circumstances are when the proposed contractor (i) Is a new or recently reorganized company, and there is no past or recent record of incurred indirect costs; (ii) Has a recent record of a rapidly increasing indirect cost rate due to a declining volume of sales without a commensurate decline in indirect expenses; or (iii) Seeks to enhance its competitive position in a particular circumstance by basing its proposal on indirect cost rates lower than those that may reasonably be expected to occur during contract performance, thereby causing a cost overrun. (2) In such cases, an equitable ceiling covering the final indirect cost rates may be negotiated and specified in the contract.

4 4 Proposed Solution: We believe that most established USAID contractors will not meet these regulatory conditions for government-mandated indirect rate ceilings. Accordingly, we recommend that USAID remove the requirement for offerors to accept indirect cost rate ceilings, allowing offerors to propose indirect cost rate ceilings that take into consideration their accounting practices and methods for determining indirect cost rates. Fixed Fee Percentage Ceiling Section L.5(b)(2) (page 71) states: The proposal for fixed fee shall be provided in accordance with Section B.X Ceilings on Fixed Fee/Profit. The proposal shall include: An explanation of the method used to establish the fixed fee/profit rate and how it is applied to all costs. The requirement for offerors to provide an explanation of the method used to establish the fixed fee/profit rate appears inconsistent with FAR (c)(5) Profit, which states The contracting officer shall not require any prospective contractor to submit breakouts or supporting rationale for its profit or fee objective but may consider it, if it is submitted voluntarily. Furthermore, our understanding from FAR (a)(3) Proposal analysis techniques is that analysis of fee as a separate cost element is not required due to the presence of adequate price competition. Proposed Solution: Delete the general requirement noted above and include guidance as to the circumstances under which it may be required. Fixed Fee Percentage Ceiling/Firm Fixed Price TOs Section B.5 (page 5) states: NOTE: For Firm-Fixed-Price (FFP) Task Orders, the ceiling percentage above serves as a basis for negotiation only. We believe that this statement is potentially misleading and should be revised and be supported by guidance that discusses the risks assumed by a contractor performing a FFP contract and the impact on the profit element of its proposed price. We do not believe that the FAR permits or expects a contracting officer, in every instance, to require a contractor to provide details of its estimated profit in connection with a FFP offer. Rather, there are limited instances in which a decision on an offeror s proposal does require cost analysis (for instance when there has been limited competition). Also, in saying that the ceiling percentage applicable to CPFF proposals serves as a basis for negotiation in connection with FFP orders, given the reallocation of risk to the contractor under a FFP order, this language should not be interpreted to mean that the ceiling percentage that has been negotiated for CPFF order is the contracting officer s negotiation goal. Proposed Solution: Revise to read: NOTE: The ceiling percentage above only applies to cost reimbursement type contracts. For Firm Fixed Price (FFP) Task Orders, the contractor assumes greater performance and financial risk, and is not subject to the limitations of FAR

5 5 Additional Comments Completion vs. Term. In the guidance for Section B.5 on the bottom of page 6, the comments should be clarified to note that for completion type contracts, payment of the fee is tied to the schedule of deliverables. For term type contracts, the fee is invoiced on a percentage basis each month. Local Compensation Plan. In Section B.7(c), the template states: Unless otherwise authorized by the Mission Director, the compensation for CCN and TCN labor shall not exceed the Mission s Local Compensation Plan and shall be paid in the currency of the cooperating country. This constitutes a deviation from AIDAR , which recognizes the limit as prevailing compensation paid to personnel performing similar work in the cooperating country, as determined by the USAID Mission. The Local Compensation Plan does not necessarily reflect the labor market for high-level expertise, sourced competitively from the private sector for limited periods of time without a USG benefits package. We recommend that the AIDAR language be used here instead. IDIQ COR Review. Section F.8(a), page 29, new guidance at top of the page, gives the USAID/W COR the option to review a mission s TO SOW for task orders at or above a threshold. However, Section F.8(d)(5), page 32, requires review and clearance of TO SOWs by the IDIQ COR. Requirement to Propose. Section F.8(a), page 29, states that contractors are not required to submit proposal for every TO. However, Section F.8(e)(3), page 35, under the performancebased contracting section, states that the Government expects full participation of all contractors or that Contractors must file no bid justification to any proposal request that they wish not to bid on. We recommend that F.8(a) be used in the template, since there is no consideration for submitting a proposal. Threshold. Section F.8(d)(1), page 32, states a $500,000 threshold for streamlined procedures vs. the same text with a $100,000 threshold is included on page 33. What is the threshold? Key Personnel. Section F.11, top of page 42, the guidance comment on key personnel states that the greater of 5 individuals or five percent of contractor staff under a TO may be designated as key personnel. Care must be taken in mandating a particular universe. For larger Task Orders, where there may be many local staff, the burden of contract administration for USAID and the contractor could be very large if the five percent requirement were imposed. Salary Increases. In Section H.2(1)(d), the RFP states: Annual salary increase (of any kind, cost of living and merit increases, or other) of percent cumulatively may be granted within twelve month period of satisfactory services under the contract. Annual salary increases of any kind exceeding these limitations or exceeding the maximum salary in Section H.3 may be granted only with the advance written approval of the Contracting Officer. The reference to H.3 should be to H.2. We recommend that the above-mentioned restriction on a to-be-determined percent for salary increases, cost of living adjustments and merit increases be removed from the template because it appears to be inconsistent with AIDAR Personnel Compensation, incorporated in the

6 6 contract under Section H.2 (page 46), which stipulates that personnel compensation be in accordance with the contractor s established policies, procedures, and practices, with reimbursement subject only to the USAID Contractor Salary Threshold (CST). The abovementioned restriction may preclude contractors from following their established policies, procedures, and practices, as required by AIDAR The CST is an effective upper limit, and each Task Order contracting officer (TOCO) will have full authority to negotiate salary increases that would be reasonable at the time of any TO competition, subject to U.S. and local market rates. Technical Evaluation Criteria. The draft template discusses the relative importance of evaluation criteria differently, at different points. Compare Section L.4 (page 60), Section L.4(b) (page 61) and Section M.2 (page 77). Cost Evaluation Matrix. If the template continues to include a matrix, some clarification would be helpful. The following types of labor are included under the labor categories as examples in the Cost Evaluation Matrix (page 84): o Long-Term US-based o Long-Term Field-based o Consultant o Local-Hire Different offerors can interpret these types of labor differently. For example, it is not clear whether long-term US-based should be considered home-office staff or a non home-office hired long-term expatriate person. The same applies to Consultant, which can be interpreted as a short-term expatriate or short-term home-office person. Accordingly, offerors will not understand how to apply their indirect rates applicable to labor, which vary based on labor type. Furthermore, it is unclear whether the plug figures for level of effort are inclusive or exclusive of home-office backstopping. -0-

SOL-514-15-000003 - Rural Financial Services (RFS) QUESTIONS & ANSWERS DOCUMENT January 26, 2015

SOL-514-15-000003 - Rural Financial Services (RFS) QUESTIONS & ANSWERS DOCUMENT January 26, 2015 SOL-514-15-000003 - Rural Financial Services (RFS) QUESTIONS & ANSWERS DOCUMENT January 26, 2015 TECHNICAL 1. Are there any data available on the rates of loan repayments of financial intermediaries operating

More information

Strategy and Planning Activities Implementation Planning

Strategy and Planning Activities Implementation Planning Strategy and Planning Activities Implementation Planning Presented by Kate Taylor, PMP 2-1 Strategy & Planning Activities Strategy & Planning Analysis & Design Development Deployment Operations & Maintenance

More information

Contract Compliance and the Federal Acquisition Regulation (FAR)

Contract Compliance and the Federal Acquisition Regulation (FAR) Contract Compliance and the Federal Acquisition Regulation (FAR) ORA CERTIFICATE PROGRAM (MODULE 11) 27 MAY 2015 Learning Objectives Participants will learn about the history of the Federal Acquisition

More information

Acquisition Guide Chapter 16.1 (March 2008) General Guide To Contract Types For Requirements Officials

Acquisition Guide Chapter 16.1 (March 2008) General Guide To Contract Types For Requirements Officials General Guide To Contract Types For Requirements Officials TABLE OF CONTENTS I. Introduction... 3 II. The Selection of Contract Type... 3 III. Contracting Officer Responsibility for Selecting the Type

More information

Time-and-Materials and Labor-Hour Contracts The New Policies

Time-and-Materials and Labor-Hour Contracts The New Policies Time-and-Materials and Labor-Hour Contracts The New Policies Overview: Time-and-materials and labor-hour (T&M/LH) contracts are the least preferred contract types, but they may play an important role in

More information

Risk Mitigation and Subcontract Management

Risk Mitigation and Subcontract Management Risk Mitigation and Subcontract Management Breakout Session # C13 Danielle Carr, MSM Program Acquisitions, HMS Technologies Stacey B. Dey-Foy Director Suspension & Debarment, EPA July 28, 2014 @ 4:00pm

More information

10 Steps for Managing Sub-Grants

10 Steps for Managing Sub-Grants New Partners Initiative 10 Steps for Managing Sub-Grants DRAFT Table of Contents ACRONYMS AED PEPFAR NPI USG Introduction T he Academy for Educational Development (AED) provides technical support for grantees

More information

Cost Analysis Key Components Guidance and Checklist

Cost Analysis Key Components Guidance and Checklist Cost Analysis Key Components Guidance and Checklist A Mandatory Reference for ADS Chapter 300 New Edition Date: 04/02/2013 Responsible Office: M File Name: 300mad_040213 COST ANALYSIS KEY COMPONENTS GUIDANCE

More information

Selection of Contract Type for Launch Services

Selection of Contract Type for Launch Services Selection of Contract Type for Launch Services The Right Tool for the Right Job Joe Boyle Consultant Outline Selection Criteria / Factors Contract Type Descriptions Launch Service Requirements Applied

More information

CHAPTER 3.0: PROCUREMENT AND CONTRACTING

CHAPTER 3.0: PROCUREMENT AND CONTRACTING CHAPTER 3.0: PROCUREMENT AND CONTRACTING This chapter outlines the requirements for using Federal funds to purchase materials, products, or services under the CDBG Entitlement program. Whether you are

More information

CHAPTER 23. Contract Management and Administration

CHAPTER 23. Contract Management and Administration Date Issued: June 12, 2009 Date Last Revised: September 28, 2015 CHAPTER 23. Contract Management and Administration Table of Contents CHAPTER 23. Contract Management and Administration... 23-1 23.1 Policy...

More information

This document has been archived. The Why and When list at the AAPD Archive identifies why the document has been archived and where current guidance

This document has been archived. The Why and When list at the AAPD Archive identifies why the document has been archived and where current guidance This document has been archived. The Why and When list at the AAPD Archive identifies why the document has been archived and where current guidance may be found. Internal users may also access the OAA

More information

MANAGEMENT 3 PROCUREMENT AND CONTRACTOR. Purpose

MANAGEMENT 3 PROCUREMENT AND CONTRACTOR. Purpose 3 PROCUREMENT AND CONTRACTOR MANAGEMENT Purpose The purpose of Procurement and Contractor Management is to provide basic information and direction regarding procuring commodities or services within New

More information

Source Selection Plan Guidance and Template

Source Selection Plan Guidance and Template Source Selection Plan Guidance and Template A Mandatory Reference for ADS Chapter 300 New Edition Date: 04/02/2013 Responsible Office: M File Name: 300mae_040213 SOURCE SELECTION PLAN GUIDANCE AND TEMPLATE

More information

Government Contracting 101 PART 2. Text File. Welcome to SBA s training program, Government Contracting 101, Part 2.

Government Contracting 101 PART 2. Text File. Welcome to SBA s training program, Government Contracting 101, Part 2. Slide 1 Government Contracting 101 Part 2 How the Government Buys SBA U.S. Small Business Administration November 2011 Government Contracting 101 PART 2 Text File Welcome to SBA s training program, Government

More information

Are You Looking to Sell Your Products & Services to the US Government? Overview

Are You Looking to Sell Your Products & Services to the US Government? Overview Are You Looking to Sell Your Products & Services to the US Government? What You Need to Know About Accounting, Compliance, and Reporting! 1 FICPA Overview The US Government is the largest consumer of goods

More information

AGENDA FOR LUNCH SEMINAR WITH FMI AUGUST 28, 2008 12:30 PM INTRODUCTION TO GOVERNMENT CONTRACTING

AGENDA FOR LUNCH SEMINAR WITH FMI AUGUST 28, 2008 12:30 PM INTRODUCTION TO GOVERNMENT CONTRACTING AGENDA FOR LUNCH SEMINAR WITH FMI AUGUST 28, 2008 12:30 PM INTRODUCTION TO GOVERNMENT CONTRACTING 1. NICRA - What is a NICRA? - Who has a NICRA? - Do I need a NICRA? - How do I get a NICRA? 2. INDIRECT

More information

Presented by: Laura Davis, President Strategic Consulting Solutions, Inc. PDS Consulting Solutions, LLC November 12, 2015

Presented by: Laura Davis, President Strategic Consulting Solutions, Inc. PDS Consulting Solutions, LLC November 12, 2015 Presented by: Laura Davis, President Strategic Consulting Solutions, Inc. PDS Consulting Solutions, LLC November 12, 2015 Agenda Introductions RFP Process Types of Costs Pricing of Direct Costs Pricing

More information

FAR UPDATE 52.216-7, Allowable Cost and Payment (Jun 2013)

FAR UPDATE 52.216-7, Allowable Cost and Payment (Jun 2013) FAR UPDATE 52.216-7, Allowable Cost and Payment (Jun 2013) "It's never too early to prepare for your incurred cost submission (A webinar sponsored by Pleasant Valley Business Solutions) 1 Objective Know

More information

Acquisition & Assistance Policy Directive (AAPD)

Acquisition & Assistance Policy Directive (AAPD) Acquisition & Assistance Policy Directive (AAPD) From the Director, Office of Acquisition & Assistance Issued: MAY 19, 2006 AAPD 06-07 AIDAR, APPENDIX D: CONTRACT BUDGET, SALARY DETERMINATION AND SALARY

More information

Cost Accounting Standards: An M&O s Problematic Five

Cost Accounting Standards: An M&O s Problematic Five Cost Accounting Standards: An M&O s Problematic Five Wayne Moosman, CPA, CIA, CMA, CISA, CFE Los Alamos National Laboratory 2015 CIAD Conference July 23, 2015 1 Famous Quote In today s regulatory environment,

More information

U.S. Department of Energy Office of Inspector General Office of Audits and Inspections. Inspection Report

U.S. Department of Energy Office of Inspector General Office of Audits and Inspections. Inspection Report U.S. Department of Energy Office of Inspector General Office of Audits and Inspections Inspection Report Approval of Contractor Executive Salaries by Department of Energy Personnel DOE/IG-0882 March 2013

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Total Quality Project Management Lecture 9 Project Procurement Management Procurement means acquiring goods and/or services from an outside source Other terms include purchasing and outsourcing Offshoring

More information

REQUEST FOR PROPOSALS. March 4, 2016, 17:00 pm Central European Time Closing Deadline:

REQUEST FOR PROPOSALS. March 4, 2016, 17:00 pm Central European Time Closing Deadline: REQUEST FOR PROPOSALS International Republican Institute 1225 Eye St. NW, Suite 700 Washington, DC 20005 (202) 408-9450 (202) 408-9462 fax www.iri.org @IRIGlobal Procurement Number: MENA2016T06o Open Date:

More information

Chapter 15. Competitive Negotiation: Evaluating Proposals

Chapter 15. Competitive Negotiation: Evaluating Proposals Chapter 15. Competitive Negotiation: Evaluating Proposals Summary This chapter describes the steps to be taken in order to properly evaluate each proposal received in response to an RFP. Essential Information

More information

PROCUREMENT PRACTICES AT PUBLIC HOUSING AGENCIES

PROCUREMENT PRACTICES AT PUBLIC HOUSING AGENCIES PROCUREMENT PRACTICES AT PUBLIC HOUSING AGENCIES Table of Contents Procurement Regulations and Agency 3 Procurement Policies and Procedures 3 Roles and Responsibilities 4 Board of Commissioners 4 Sample

More information

NASA PROCUREMENT TENETS

NASA PROCUREMENT TENETS NASA PROCUREMENT TENETS Introduction: The goal of procurement is to ensure the Agency executes its mission successfully by effectively and efficiently managing the acquisition process. NASA spends approximately

More information

Types of Contracts. A quick walk through FAR Part 16

Types of Contracts. A quick walk through FAR Part 16 Types of Contracts A quick walk through FAR Part 16 Contract Types Contract types vary according to -- (1) The degree and timing of the responsibility assumed by the contractor for the costs of performance;

More information

Acquisition & Assistance Policy Directive (AAPD)

Acquisition & Assistance Policy Directive (AAPD) Acquisition & Assistance Policy Directive (AAPD) From the Director, Office of Acquisition & Assistance Issued: January 08, 2010 AAPD 10-01 PERSONAL SERVICES CONTRACTS -- CHANGES IN USG REIMBURSEMENT AMOUNTS

More information

Federal Regulatory Compliance Best Practices Washington Technology Webcast. September 27, 2012

Federal Regulatory Compliance Best Practices Washington Technology Webcast. September 27, 2012 Federal Regulatory Compliance Best Practices Washington Technology Webcast September 27, 2012 Agenda Topic Minutes Regulatory compliance overview 5 Major areas of financial compliance risk 15 Best practices

More information

OFFICE OF INSPECTOR GENERAL

OFFICE OF INSPECTOR GENERAL OFFICE OF INSPECTOR GENERAL AUDIT OF THE PROCUREMENT PROCESS FOR A NATIONAL IDENTIFICATION CARD AND PASSPORT SYSTEM FINANCED BY THE MILLENNIUM CHALLENGE CORPORATION AND MONITORED BY USAID/PARAGUAY AUDIT

More information

COALITION PROVISIONAL AUTHORITY ORDER NUMBER 87 PUBLIC CONTRACTS

COALITION PROVISIONAL AUTHORITY ORDER NUMBER 87 PUBLIC CONTRACTS COALITION PROVISIONAL AUTHORITY ORDER NUMBER 87 PUBLIC CONTRACTS Pursuant to my authority as Administrator of the Coalition Provisional Authority (CPA), and under the laws and usages of war, and consistent

More information

COST PLUS AWARD FEE CONTRACT ADMINISTRATION DESKGUIDE

COST PLUS AWARD FEE CONTRACT ADMINISTRATION DESKGUIDE COST PLUS AWARD FEE CONTRACT ADMINISTRATION DESKGUIDE 1. Introduction. This Guide does not cover all aspects of administering a cost plus award fee (CPAF) contract. As all of the Directorates of Contracting

More information

Procurement Standards. Procurement. 200.317 Procurements by states. (a) States. 200.318 General procurement standards. (b) Procurement standards.

Procurement Standards. Procurement. 200.317 Procurements by states. (a) States. 200.318 General procurement standards. (b) Procurement standards. 24 CFR PART 85. Administrative Requirements for Grants and Cooperative Agreements to State, Local and Federally Recognized Indian Tribal Governments - Subpart 36 - Procurement Procurement. (a) States.

More information

Overview 1) Grantee s procurement requirements must be in conformance with the appropriate applicable Federal, State, and local laws.

Overview 1) Grantee s procurement requirements must be in conformance with the appropriate applicable Federal, State, and local laws. The award of Federal funds does not exempt the Grantee organization from compliance with State, and local requirements. When similar requirements exist at all levels, the rule of thumb is that the most

More information

Module 10 Procurement Management PMP Exam Questions

Module 10 Procurement Management PMP Exam Questions Module 10 Procurement Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company needs some work

More information

Data Communications Company (DCC) price control guidance: process and procedures

Data Communications Company (DCC) price control guidance: process and procedures Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: tricia.quinn@ofgem.gov.uk Overview: The Data and Communications Company (DCC) is required

More information

Chapter 16. Competitive Negotiation: Negotiations

Chapter 16. Competitive Negotiation: Negotiations Chapter 16. Competitive Negotiation: Negotiations Summary This chapter establishes the procedure for conducting negotiations with vendors selected by the selection committee following evaluation of the

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane samlane@aol.com Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,

More information

Consulting Services for CORPORATE SPONSORSHIP ASSET INVENTORY & VALUATION

Consulting Services for CORPORATE SPONSORSHIP ASSET INVENTORY & VALUATION REQUEST FOR PROPOSALS RFP No. 14-01-11 Consulting Services for CORPORATE SPONSORSHIP ASSET INVENTORY & VALUATION Proposals will be received on or before 2:00 pm local time Wednesday, February 19, 2014

More information

C-14: Guidance Note and Checklist for Assessing Level of Effort and Budgets for USAID Performance Evaluations

C-14: Guidance Note and Checklist for Assessing Level of Effort and Budgets for USAID Performance Evaluations C-14: Guidance Note and Checklist for Assessing Level of Effort and Budgets for USAID Performance Evaluations This tool is designed to assist USAID program managers and evaluation specialists to develop

More information

Contract Cost Principles and Guidelines

Contract Cost Principles and Guidelines Contract Cost Principles and Guidelines Introduction The City of Philadelphia Contract Cost Principles and Guidelines is designed to serve as a manual for City departments entering into professional service

More information

Procurement Standards 2 CFR 200.317-326

Procurement Standards 2 CFR 200.317-326 2 CFR 200 Uniform Guidance Procurement Standards Kris Rhodes, Director Sponsored Project Services 1 Procurement Standards 2 CFR 200.317-326 200.317 Procurement by states 200.318 General procurement standards

More information

INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006

INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006 INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006 1. MANAGEMENT REVIEWS The contractor should have policies and procedures for periodic monitoring of the billing

More information

Request for Proposal (RFP) No. SOL-OAA-15-000037. Questions and Answers

Request for Proposal (RFP) No. SOL-OAA-15-000037. Questions and Answers Request for Proposal (RFP) No. SOL-OAA-15-000037 Questions and Answers Q1. Is CUBRC (the incumbent) eligible to prime a bid? A: No, CUBRC is not eligible to propose as a prime contractor on this procurement.

More information

Request for Proposals. Security Advisory Services for the International Executive Service Corps

Request for Proposals. Security Advisory Services for the International Executive Service Corps Request for Proposals Proposal Title: Bid Reference Number: Security Advisory Services for the International Executive Service Corps IESC Security Advisory Services Issue Date: January 21, 2015 Closing

More information

AIDAR USAID Acquisition Regulation

AIDAR USAID Acquisition Regulation AIDAR USAID Acquisition Regulation STRUCTURE OF THE AIDAR TO THE SUBPART LEVEL 48 CFR CHAPTER 7 A Mandatory Reference for ADS Chapter 302 Partial Revision Date: 03/16/2015 Responsible Office: M/OAA/P File

More information

MODEL REQUEST FOR PROPOSALS (RFP) TEMPLATE Generalized for professional services. www.cdrfg.com

MODEL REQUEST FOR PROPOSALS (RFP) TEMPLATE Generalized for professional services. www.cdrfg.com MODEL REQUEST FOR PROPOSALS (RFP) TEMPLATE Generalized for professional services www.cdrfg.com CDR Fundraising Group 2015 This sample RFP is made available by the CDR Fundraising Group as a public service.

More information

10/30/2015. Procurement Under the New Requirements. Why This Session Is Needed. Lesson Overview & Module Objectives. Changes to conflict of interest

10/30/2015. Procurement Under the New Requirements. Why This Session Is Needed. Lesson Overview & Module Objectives. Changes to conflict of interest Requirements Procurement under the New Requirements 1 1 Why This Session Is Needed New provisions in Uniform Guidance Changes to conflict of interest requirements in Uniform Guidance Distinctions between

More information

PREPARING DETAILED BREAKDOWNS FOR CHANGE ORDER PROPOSALS

PREPARING DETAILED BREAKDOWNS FOR CHANGE ORDER PROPOSALS PREPARING DETAILED BREAKDOWNS FOR CHANGE ORDER PROPOSALS I. GENERAL A. All work to be performed under the change order must be itemized, including the work of all subcontractors. B. Items must be relevant

More information

SIGAR. USAID s Health Care Improvement Project: Audit of Costs Incurred by the University Research Company, LLC APRIL

SIGAR. USAID s Health Care Improvement Project: Audit of Costs Incurred by the University Research Company, LLC APRIL SIGAR Special Inspector General for Afghanistan Reconstruction SIGAR 16-31 Financial Audit USAID s Health Care Improvement Project: Audit of Costs Incurred by the University Research Company, LLC In accordance

More information

Comments of Lawyers Alliance for New York on Executive Compensation Regulations

Comments of Lawyers Alliance for New York on Executive Compensation Regulations Comments of Lawyers Alliance for New York on Executive Compensation Regulations July 16, 2012 Lawyers Alliance for New York ( Lawyers Alliance ) respectfully submits these comments on the proposed executive

More information

REQUEST FOR PROPOSAL (RFP) FORM. Enter title here. Invitation to Bid. Utica College invites you to submit a proposal to brief description.

REQUEST FOR PROPOSAL (RFP) FORM. Enter title here. Invitation to Bid. Utica College invites you to submit a proposal to brief description. REQUEST FOR PROPOSAL (RFP) FORM TITLE: Enter title here I. GENERAL INFORMATION Invitation to Bid. Utica College invites you to submit a proposal to brief description. If a contract results from this RFP,

More information

Current as of 4/1/16

Current as of 4/1/16 Checklist for Reviewing Procurements Under Grants by Non-Federal Entities (States, local and tribal governments, Institutions of Higher Education, Hospitals, and private non-profit organizations) 2 CFR

More information

Managing Cost Reimbursable Contracts

Managing Cost Reimbursable Contracts Managing Cost Reimbursable Contracts Providing Guidance in Difficult Waters Management Guide & Desk Reference Compiled and Written by: Don Philpott Scott P Cook 233 Pages ISBN: 978-0-9844038-6-8 Published

More information

ABI Position paper. Supplement to ED/2009/12 Financial Instruments: Amortised Cost and Impairment

ABI Position paper. Supplement to ED/2009/12 Financial Instruments: Amortised Cost and Impairment ABI Position paper Supplement to ED/2009/12 Financial Instruments: Amortised Cost and Impairment March 2011 Page 1 of 17 Dear Sir/Madam, The Italian Banking Association welcomes the publication of the

More information

SECTION 85 ESTIMATING EMPLOYMENT LEVELS AND THE EMPLOYMENT SUMMARY (SCHEDULE Q) Table of Contents

SECTION 85 ESTIMATING EMPLOYMENT LEVELS AND THE EMPLOYMENT SUMMARY (SCHEDULE Q) Table of Contents SECTION 85 ESTIMATING EMPLOYMENT LEVELS AND THE EMPLOYMENT SUMMARY (SCHEDULE Q) Table of Contents 85.1 How should my agency's budget address workforce planning and restructuring? 85.2 What terms do I need

More information

Objectives. Single Audit: Recent Changes and Preparation Tips. Overview. Overview 1/20/2016

Objectives. Single Audit: Recent Changes and Preparation Tips. Overview. Overview 1/20/2016 Objectives Single Audit: Recent Changes and Preparation Tips January 21, 2016 Discuss and review recently issued Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal

More information

STOC II Draft RFP (W900KK-08-R-0001) Questions & Answers

STOC II Draft RFP (W900KK-08-R-0001) Questions & Answers STOC II Draft RFP (W900KK-08-R-0001) Questions & Answers Answers to questions submitted, but not included in this set of Q&As,will be provided in a subsequent posting of Q&As in the near future. As the

More information

DEFENSE CONTRACT AUDIT AGENCY GUIDE FOR DETERMINING ADEQUACY OF CONTRACTOR INCURRED COST PROPOSAL

DEFENSE CONTRACT AUDIT AGENCY GUIDE FOR DETERMINING ADEQUACY OF CONTRACTOR INCURRED COST PROPOSAL Instructions: This form should be completed for each proposal submission and maintained in the permanent file. Adequacy reviews of contractor incurred cost proposals include verification for completeness

More information

November 1, 2013. To Whom It May Concern:

November 1, 2013. To Whom It May Concern: November 1, 2013 Re: Request for a Proposal for an Accounting Firm to Audit an Electric Supplier s Financial Statements and Connecticut Intrastate Gross Revenues To Whom It May Concern: The Public Utilities

More information

SMALL BUSINESS JOBS ACT AND NATIONAL DEFENSE AUTHORIZATION ACT FOR FISCAL YEAR 2013 F O R P U B L I C R E L E A S E 1

SMALL BUSINESS JOBS ACT AND NATIONAL DEFENSE AUTHORIZATION ACT FOR FISCAL YEAR 2013 F O R P U B L I C R E L E A S E 1 SMALL BUSINESS JOBS ACT AND NATIONAL DEFENSE AUTHORIZATION ACT FOR FISCAL YEAR 2013 F O R P U B L I C R E L E A S E 1 Overview Small Business Jobs Act of 2010 Pending Regulations Accelerated Payments to

More information

Checklist for Reviewing Procurements by Federal Grant Recipients and Subrecipients

Checklist for Reviewing Procurements by Federal Grant Recipients and Subrecipients Checklist for Reviewing Procurements by Federal Grant Recipients and Subrecipients This checklist was created to assist FEMA recipients and subrecipients in complying with the federal requirements that

More information

TOPIC 12 CONTRACT COST AND PRICE ANALYSIS

TOPIC 12 CONTRACT COST AND PRICE ANALYSIS CONTRACT AUDIT GUIDE FRAMEWORK TOPIC 12 CONTRACT COST AND PRICE ANALYSIS Objective To determine whether the agency effectively conducts cost or price analysis to arrive at fair and reasonable prices for

More information

General Terms and Conditions of Purchase

General Terms and Conditions of Purchase General Terms and Conditions of Purchase Supplement 1 Federal Acquisition Regulation (FAR) Government Contract Provisions 1. When the materials or products furnished are for use in connection with a U.S.

More information

Overview of Local Unit Power Supply Bidding Practices

Overview of Local Unit Power Supply Bidding Practices Overview of Local Unit Power Supply Bidding Practices Once deciding to public bid power supply (as opposed to using the BGS-FP tariff) it is a major effort to design and implement a bidding process that

More information

The European Financial Reporting Advisory Group (EFRAG) and the Autorité des Normes Comptables (ANC) jointly publish on their websites for

The European Financial Reporting Advisory Group (EFRAG) and the Autorité des Normes Comptables (ANC) jointly publish on their websites for The European Financial Reporting Advisory Group (EFRAG) and the Autorité des Normes Comptables (ANC) jointly publish on their websites for information purpose a Research Paper on the proposed new Definition

More information

GUIDELINES FOR THE ENGAGEMENT OF EXTERNAL CONSULTANTS/PROFESSIONAL SERVICES AT MEMORIAL UNIVERSITY

GUIDELINES FOR THE ENGAGEMENT OF EXTERNAL CONSULTANTS/PROFESSIONAL SERVICES AT MEMORIAL UNIVERSITY GUIDELINES FOR THE ENGAGEMENT OF EXTERNAL CONSULTANTS/PROFESSIONAL SERVICES AT MEMORIAL UNIVERSITY INTENT: 1. To ensure due diligence and consistency is followed in the solicitation, selection, contract

More information

This document has been archived. The Why and When list at the AAPD Archive identifies why the document has been archived and where current guidance

This document has been archived. The Why and When list at the AAPD Archive identifies why the document has been archived and where current guidance This document has been archived. The Why and When list at the AAPD Archive identifies why the document has been archived and where current guidance may be found. Internal users may also access the OAA

More information

Sample RFP Response citing use of Corp_Pro SM

Sample RFP Response citing use of Corp_Pro SM Sample RFP Response citing use of Corp_Pro SM XYZ CORPORATION will employ its Corp_Pro SM system to facilitate contract/task order management, cost control and invoicing, security clearance tracking, and

More information

PS15-1505: Enhancing HIV Prevention Communication and Mobilization Efforts through Strategic Partnerships. Procurement and Grants Management Overview

PS15-1505: Enhancing HIV Prevention Communication and Mobilization Efforts through Strategic Partnerships. Procurement and Grants Management Overview PS15-1505: Enhancing HIV Prevention Communication and Mobilization Efforts through Strategic Partnerships Procurement and Grants Management Overview Constance Jarvis Grants Management Specialist Procurement

More information

CMS Use of GSA Schedules

CMS Use of GSA Schedules CMS Use of GSA Schedules 2013 Contracting With CMS Conference Building and Maintaining Relationships to Achieve Results Donald Knode Director, Division of Medicare & Medicaid IT Support Contracts May 13,

More information

Reasons for Change Orders

Reasons for Change Orders T E X A S D E PA R T M E N T O F T R A N S P O R TAT I O N A change order is defined in the 2004 Standard Specification Book as a written order to the Contractor detailing changes to the specified work,

More information

CHAPTER 7 COST PRINCIPLES

CHAPTER 7 COST PRINCIPLES CHAPTER 7 COST PRINCIPLES 7101. Cost Principles. (a) Definitions. (1) Actual Costs are all direct and indirect costs which have been incurred for services rendered, supplies delivered, or construction

More information

June 2008 Report No. 08-038. An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers

June 2008 Report No. 08-038. An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers John Keel, CPA State Auditor An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers Report No. 08-038 An Audit Report on The Department of Information

More information

DEFENSE CONTRACT AUDIT AGENCY CHECKLIST FOR DETERMINING ADEQUACY OF CONTRACTOR INCURRED COST PROPOSAL

DEFENSE CONTRACT AUDIT AGENCY CHECKLIST FOR DETERMINING ADEQUACY OF CONTRACTOR INCURRED COST PROPOSAL Instructions: This form should be completed for each proposal submission and maintained in the permanent file. Adequacy reviews of contractor incurred cost proposals include an assessment for completeness

More information

Compensation Methods for Architectural Services

Compensation Methods for Architectural Services Compensation Methods for Architectural Services Compensation Methods for Architectural Services By: Thomas R. Gossen, AIA, PE Secretary/Treasurer and Chief Operating Officer Gossen Livingston Associates,

More information

NOTICE TO INVESTORS: THE NOTES ARE SIGNIFICANTLY RISKIER THAN CONVENTIONAL DEBT INSTRUMENTS.

NOTICE TO INVESTORS: THE NOTES ARE SIGNIFICANTLY RISKIER THAN CONVENTIONAL DEBT INSTRUMENTS. PRICING SUPPLEMENT Filed Pursuant to Rule 424(b)(2) Registration Statement No. 333-171806 Dated May 22, 2013 Royal Bank of Canada Airbag Autocallable Yield Optimization Notes $6,732,000 Notes Linked to

More information

24 CFR PART 85 85.36 Procurement. States. Procurement standards.

24 CFR PART 85 85.36 Procurement. States. Procurement standards. 85.36 Procurement. (a) States. When procuring property and services under a grant, a State will follow the same policies and procedures it uses for procurements from its non-federal funds. The State will

More information

Request for Proposals

Request for Proposals Request for Proposals Title: RFP #: 2010-HR-001 Issue Date: January 4, 2010 Due Date/Time: January 28, 2010 2 p.m. Issuing Agency: Harnett County Human Resources Department 102 E. Front Street P.O. Box

More information

In this chapter, you will learn to use cost-volume-profit analysis.

In this chapter, you will learn to use cost-volume-profit analysis. 2.0 Chapter Introduction In this chapter, you will learn to use cost-volume-profit analysis. Assumptions. When you acquire supplies or services, you normally expect to pay a smaller price per unit as the

More information

Standard business terms

Standard business terms Standard business terms Cybertec Schönig & Schönig GmbH Gröhrmühlgasse 26 2700 Wiener Neustadt (Named Cybertec resp. contractor below) Edition 2014-01 1. General remarks 1.1 As contractor Cybertec provides

More information

Project Procurement Management

Project Procurement Management Project Procurement Management 1 2 Procurement Planning Procurement Planning is the process of identifying which project needs can be best met by procuring products or services outside the project organization

More information

Lawrence Livermore National Laboratory

Lawrence Livermore National Laboratory Lawrence Livermore National Laboratory Supply Chain Management Department Attention: To All Offerors June 16, 2016 Subject: Request for Proposal (RFP) Number B617524 Lawrence Livermore National Security,

More information

SUMMARY: This document contains final regulations relating to qualified

SUMMARY: This document contains final regulations relating to qualified [4830-01-u] DEPARTMENT OF THE TREASURY Internal Revenue Service (IRS) 26 CFR Parts 1 and 602 [TD 8933] RIN 1545-AX33 Qualified Transportation Fringe Benefits AGENCY: Internal Revenue Service (IRS), Treasury.

More information

CONTRACT REIMBURSEMENT MANUAL

CONTRACT REIMBURSEMENT MANUAL CONTRACT REIMBURSEMENT MANUAL TABLE OF CONTENTS Section 1 Introduction 1.0 Fundamental Principles 1.1 Introduction to the Manual 1.2 Reimbursement Objectives 1.3 How the Manual is Organized Section 2 Management

More information

FAR 15.408 Table 15-2 -- Instructions for Submitting Cost/Price Proposals When Cost or Pricing Data Are Required

FAR 15.408 Table 15-2 -- Instructions for Submitting Cost/Price Proposals When Cost or Pricing Data Are Required FAR 15.408 Table 15-2 -- Instructions for Submitting Cost/Price Proposals When Cost or Pricing Data Are Required This document provides instructions for preparing a contract pricing proposal when cost

More information

Consultant Selection Policy for Building Infrastructure Consulting Services (Effective April 1, 2007)

Consultant Selection Policy for Building Infrastructure Consulting Services (Effective April 1, 2007) Consultant Selection Policy for Building Infrastructure Consulting Services (Effective April 1, 2007) 1.0 SCOPE This policy applies to the procurement of consulting services contracted directly by the

More information

U.S. Department of Energy Human Resources and Administration Home Page http://www.hr.doe.gov/ig

U.S. Department of Energy Human Resources and Administration Home Page http://www.hr.doe.gov/ig The Office of Inspector General wants to make the distribution of its reports as customer friendly and cost effective as possible. Therefore, this report will be available electronically through the Internet

More information

BEST VALUE SOURCE SELECTION TRADE OFFS. Scott Ilg Site Manager, Germany Defense Acquisition University

BEST VALUE SOURCE SELECTION TRADE OFFS. Scott Ilg Site Manager, Germany Defense Acquisition University BEST VALUE SOURCE SELECTION TRADE OFFS Scott Ilg Site Manager, Germany Defense Acquisition University PLAN Acquisition Plan captures the requirement, market research, and business arrangement in a single

More information

GUIDE TO PROCUREMENT PROCEDURES FOR RECIPIENTS OF DOJ GRANTS AND COOPERATIVE AGREEMENTS

GUIDE TO PROCUREMENT PROCEDURES FOR RECIPIENTS OF DOJ GRANTS AND COOPERATIVE AGREEMENTS U. S. Department of Justice Office of Justice Programs Office of the Chief Financial Officer GUIDE TO PROCUREMENT PROCEDURES FOR RECIPIENTS OF DOJ GRANTS AND COOPERATIVE AGREEMENTS June 2011 Table of Contents

More information

THE USAID MENTOR-PROTÉGÉ PROGRAM A GUIDE FOR MENTORS AND PROTÉGÉS

THE USAID MENTOR-PROTÉGÉ PROGRAM A GUIDE FOR MENTORS AND PROTÉGÉS THE USAID MENTOR-PROTÉGÉ PROGRAM A GUIDE FOR MENTORS AND PROTÉGÉS CONTENTS Chapter 1... 4 Getting Started...4 Purpose...4 How This Guidebook Is Organized...4 Chapter 2... 5 Overview of USAID...5 Introduction...5

More information

REQUEST FOR PROPOSAL FINANCIAL PLANNING CONSULTANT

REQUEST FOR PROPOSAL FINANCIAL PLANNING CONSULTANT REQUEST FOR PROPOSAL FINANCIAL PLANNING CONSULTANT Proposals will be received until Friday, May 22, 2015 4:00 p.m. CST General Information Questions: All inquiries for information regarding this solicitation

More information

4.06 Consulting Services

4.06 Consulting Services MANAGEMENT BOARD SECRETARIAT AND MINISTRIES OF THE ENVIRONMENT, FINANCE, HEALTH AND LONG-TERM CARE, NATURAL RESOURCES, AND COMMUNITY SAFETY AND CORRECTIONAL SERVICES 4.06 Consulting Services (Follow-up

More information

GENERAL SERVICES ADMINISTRATION. Federal Supply Service Authorized Federal Supply Schedule Price List. The Consolidated Schedule

GENERAL SERVICES ADMINISTRATION. Federal Supply Service Authorized Federal Supply Schedule Price List. The Consolidated Schedule GENERAL SERVICES ADMINISTRATION Federal Supply Service Authorized Federal Supply Schedule Price List On-line access to contract ordering information, terms and conditions, up-to-date pricing, and the option

More information

GAS INDUSTRY ACT 2001 COST RECOVERY ORDER IN COUNCIL

GAS INDUSTRY ACT 2001 COST RECOVERY ORDER IN COUNCIL GAS INDUSTRY ACT 2001 COST RECOVERY ORDER IN COUNCIL The Lieutenant-Governor as the Governor s deputy, with the advice of the Executive Council, under section 68 of the Gas Industry Act 2001 ( the Act

More information

An organization which employs, or is about to employ, any of the above, has a financial or other interest in the firm selected for award.

An organization which employs, or is about to employ, any of the above, has a financial or other interest in the firm selected for award. 85.36 Procurement (a) States. When procuring property and services under a grant, a State will follow the same policies and procedures it uses for procurements from its non-federal funds. The State will

More information

Agile Software Development Brings New Contracting Issues

Agile Software Development Brings New Contracting Issues Portfolio Media. Inc. 111 West 19 th Street, 5th Floor New York, NY 10011 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com Agile Software Development Brings New Contracting

More information

AF Life Cycle Management Center

AF Life Cycle Management Center AF Life Cycle Management Center Subcontract Pricing Shannon Prince AFLCMC/PZF Wright-Patterson AFB 24 March 2014 Overview Intro to Subcontracts Pertinent Thresholds PCO & Prime Responsibilities Prime Analysis

More information

REQUEST FOR PROPOSALS. November 13, 2015 6:00pm Eastern European Time. Time Zone. (EET) Zone

REQUEST FOR PROPOSALS. November 13, 2015 6:00pm Eastern European Time. Time Zone. (EET) Zone REQUEST FOR PROPOSALS International Republican Institute 1225 Eye St. NW, Suite 700 Washington, DC 20005 (202) 408-9450 (202) 408-9462 fax www.iri.org @IRIGlobal Procurement Number: #EURASIA2015BR07o Open

More information