PREPARING DETAILED BREAKDOWNS FOR CHANGE ORDER PROPOSALS
|
|
|
- Allyson King
- 9 years ago
- Views:
Transcription
1 PREPARING DETAILED BREAKDOWNS FOR CHANGE ORDER PROPOSALS I. GENERAL A. All work to be performed under the change order must be itemized, including the work of all subcontractors. B. Items must be relevant to the scope of work of the change order. Each change order is reviewed as unique; therefore, a lump sum approach to quoting prices is not acceptable. Submit all information necessary to support the proposal including an explanation of unusual job conditions affecting the proposal. C. Itemize the work in sufficient detail so that quoted quantity and price can be verified. Each work item must be listed with its respective unit price and labor unit rate. Failure to itemize is the most common reason for delay or rejection of change orders. D. The use of values or unit prices from the CSV in the proposal may not be acceptable. CDB may require additional documentation where CSV unit prices are requested on the change order proposal. II. ALLOWABLE ITEMS. Listed below are major items that may be included in change order quotations. The list is not all inclusive. A. Basic Materials. Defined as items that can be purchased at local supply houses and are not uniquely specified. Examples include pipe, fittings, conduit, lumber, concrete and drywall. This material is to be priced at the contractor s cost, not the manufacturer s suggested list price. The timing of the change order and its size are used to determine if bulk price or over-the-counter prices are acceptable. Where a supplier s price is excessive, other local suppliers prices may be used to determine allowable costs. Material backup quote must be on supplier s letterhead. 1
2 When the material cost in question is small relative to the total change order, the estimator may verify the cost by referencing previous change orders or nationally recognized construction data manuals. B. Equipment. Defined as those components of the work which are uniquely specified for the project or are built or manufactured on special order and are not stock items. Examples include boilers, chillers, switch gear, transformers and special general finishes. Equipment costs must be supported by quotations on the supplier s letterhead with descriptions of the pertinent characteristics of the equipment listed such as size and manufacturer. Quotations that have been altered in any way are not acceptable. Some minor equipment costs, such as dumpsters, may be verified by referencing previous change orders or nationally recognized construction data manuals. C. Labor Costs. 1. Labor Unit Rates. CDB will check the contractor s estimated labor unit rates in the quotation against CDB s historical rates from other projects and published sources. Major deviations will cause rejection of the change order. Difficulty or job factors applied to rates must be noted with an explanation. 2. Working foreman hours (only) may be included. 3. Labor wage rates may include the following: a. Taxable wages to the employees (the trade base wage rate). CDB may request a copy of any worker s pay stub or certified payroll to verify the base wage rate. b. Fringe Benefits (1) When labor to be performed is covered by IDOL prevailing wage, the fringe benefits shall be in accordance with IDOL or the local union agreement. (2) When trade labor to be performed is not covered by an IDOL listed prevailing wage, the fringe benefits shall include employer s costs (subject to verification) for the following items only: (a) Medical/dental/life insurance (b) Pension (c) Vacation (d) Sick/Personal (e) Holidays 2
3 (3) The maximum allowance for fringe benefits for each trade shall be no higher than shown on the IDOL web site unless verified by union contract or other documentation acceptable to CDB. c. Employment costs mandated by the government: (1) FICA (2) FUTA (actual cost up to Federal maximum) (3) SUTA (actual cost up to State maximum) (4) Worker s compensation insurance (actual cost subject to verification) (5) Training required for State license or certification (subject to verification) d. Labor rates not conforming to IDOL published prevailing wage rates must be backed up with a copy of the union agreement or other verification. e. No other costs may be included in the hourly wage rate. 4. Overtime Hours. All overtime hours are to be itemized separately at the exact overtime rate. Worker s compensation and fringe benefits do not apply to overtime. The use of overtime in performing change order work must be approved by CDB prior to submittal of RFP. 5. Travel Costs. Travel expenses are allowed only under the following conditions and may not exceed the rates published in the State of Illinois Travel Policy (CMS publication available at: a. When travel expenses are required by the local union agreement, a copy of the union agreement which describes travel costs to be submitted with wage rates on every change order. b. When there are no workers available from the respective locals, a letter from the local hall stating such must be provided. c. When the work is very specialized and/or non-union labor is to be used, CDB will reimburse for no more than the maximum State per diem and mileage. d. If a subcontractor must return to the site after they have completed their work on site, or when a change order is initiated after substantial completion and the contractor is no longer performing work on site, or in conjunction with a time extension change order, if the delay is not due to the 3
4 contractor, travel will be allowed for one lead person for each trade, providing the home base for the (sub)contractor is outside the local area. e. Vehicle mileage for only one vehicle will be allowed. D. Bonds. The increase or decrease in the cost of the performance bond as a result of the change order shall be included. E. Builders Risk Insurance. Builders Risk insurance is allowed for prime contractors only. No General Liability or other insurance cost is allowed. F. Tool Allowance. An allowance for employer provided tools and related consumables will be allowed when pertinent to the change order work. Consumables may include saw blades, drill bits, etc. Tool allowance will not be permitted on change orders that do not require allowable tools or consumables. Maximum allowance is 2% of journeyman wages only. G. Rental Equipment. Equipment such as concrete saws, pipe threaders, compressors, backhoes, etc. necessary to complete the change order work is allowed. Quotations or invoices from rental companies must be included even if equipment is owner owned. H. Additional Warranty Costs. Usually these costs will only apply when a piece of equipment is added to the project. The cost of this item must reflect the appropriate risk of a warranty call-back and should be for labor only. Replacement parts are considered to be part of the manufacturer s quotation. I. Testing, Balancing and Start-Up Costs. These costs are allowable if the scope of work for the proposed change order modifies the levels of testing, balancing or start-up costs of the original project. J. Long Term Storage. The storage costs of purchased material and equipment are allowed only under unusual situations. Where storage is chargeable, it must be shown that either a rented warehouse or the contractor s warehouse was required for extended storage of the materials required for the change order. III. UNALLOWABLE ITEMS. The following cost items are not acceptable on change order proposals. The list is not all inclusive. A. Engineering Fees. CDB requires the A/E to provide all design services. If the contractor feels that engineering or design is required to clarify the work, then the CDB project manager should be notified. B. Job Site Facilities such as trailers and phones. 4
5 C. Short Term Storage. D. Cost of Estimating and Preparation. This is an overhead cost. E. Costs of Clerical and Support Staff. This is an overhead cost. F. Supervision. This is an overhead cost, except when a foreman is also directly performing the work. Labor costs for supervisors, general foremen, foremen not allowed to work with tools by union agreement, etc, are not allowed. An exception may be made when the change order is initiated after substantial completion and the contractor no longer has supervision on site or in conjunction with a time extension change order, if the delay is not due to the contractor. G. Liability Insurance. This is an overhead cost. H. Safety. Safety materials and labor are not allowed, it is in the overhead, unless it is required by union contract. Copy of contract will be required. IV. SPECIAL SITUATIONS A. Shop Drawings. A change order may require the contractor to prepare additional or revised drawings to install the work. The cost of such drawings may be included in the change order if requested by the A/E. The contractor may be required to submit these drawings to verify the inclusion of this cost. B. Duct Work. Low and medium pressure duct work may be quoted dollar per pound delivered to the job site. The net weight should be shown as the quantity sold. The price per pound should include waste allowance, bracing and reinforcing, shop labor, material, and equipment. The intent is to treat duct work as a manufactured product. For duct work purchased from another firm an itemized and unit price quotation from the supplier is to be furnished with the contractor s proposal. C. Sheet Metal Specialties. These specialties include splitter dampers, fire dampers and flexible connections. These are to be itemized as equipment with unit prices shown. These materials may not be shown with a total lump sum. 5
Pricing of Construction Contract Change Order Documentation
The contract language contained in this Exhibit will supplement and take precedence over all other change order pricing contract provisions in the Contract Documents provided by the Owner, Design-Builder
REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office
REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield
RFQ 00318348 NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 REF. LOCATION DESCRIPTION OF CHANGE. Revised Scope of Work. Work tasks have been revised.
RFQ 00318348 NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 DATE PUBLISHED: MAY 18, 2016 TO ALL PROSPECTIVE SUBMITTERS: THE FOLLOWING CHANGES ARE MADE: REF. LOCATION DESCRIPTION OF CHANGE Attachment A Attachment
OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS
OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS SPECIFIC AUTHORITY Sections 240.209(3)(p), 1001.74, 1013.46, F. S. OBJECTIVE To establish procedures for the administration of construction
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
Reasons for Change Orders
T E X A S D E PA R T M E N T O F T R A N S P O R TAT I O N A change order is defined in the 2004 Standard Specification Book as a written order to the Contractor detailing changes to the specified work,
TEXAS DEPARTMENT OF TRANSPORTATION. Fourth Quarter 2007
TEXAS DEPARTMENT OF TRANSPORTATION Introduction This article is a supplement to the Guide to Contract Change Orders or CO Guide (published as a Tips article, 4th Qtr., 2006). Use this article along with
A contractor s chart of accounts is the heart of the accounting system. Of particular importance is the cost of sales section (beginning in the 41000
CHART OF ACCOUNTS A contractor s chart of accounts is the heart of the accounting system. Of particular importance is the cost of sales section (beginning in the 41000 series and ending in 43000). This
Construction auditing: Continuous monitoring of active construction projects
Construction auditing: Continuous monitoring of active construction projects Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International.
a. Proposals shall be submitted in a sealed envelope and addressed as follows:
1 CITY OF ATCHISON REQUEST FOR QUALIFICATIONS & PROPOSAL HVAC SERVICES JANUARY 1, 2014 THROUGH DECEMBER 31, 2014 DUE: DECEMBER 10, 2013 10:00 A.M. The City of Atchison (City) invites interested and qualified
OBJECTIVE To establish procedures for administration of construction manager agreements, including negotiation, contracting and payments.
OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS SPECIFIC AUTHORITY Sections 240.209(3)(p), 1001.74, 1013.46, F. S. OBJECTIVE To establish procedures for administration of construction manager
CONNECTICUT DEPARTMENT OF TRANSPORTATION
EXTERNAL AUDIT CIRCULAR No. 1 CONNECTICUT DEPARTMENT OF TRANSPORTATION 2800 BERLIN TURNPIKE, PO BOX 317546, NEWINGTON, CT 06131-7546 SUBJECT: Definitions, Audit Authority, and Guidance for Computing Indirect
Auditing construction contract change orders
Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. Auditing construction contract change orders Presenter Tony Ollmann, CPA,
Product Overview. Features: Toolbox. Ease of Use of Features
Product Overview Improve job profi tability Manage cash fl ow Control costs during the job Produce more accurate estimates Control vendor and subcontractor costs Why purchase Hardhat? Since 1983, we have
CONSTRUCTION ACCOUNTING SYSTEMS
In following you will be introduced to the structure of construction financial statements,including the different ledgers used by construction accounting systems. You will also learn the difference between
Add one or multiple jobs to your field logs with the ability to assign job-specific properties, such as unique labor and equipment rates.
The Operational Networked Elements platform provides the base infrastructure and shared services for B2W Estimate and the B2W Operational Suite which includes B2W Dispatch, B2W Track, and B2W Maintain
Fundamentals of a Construction Audit. August 7, 2014
Fundamentals of a Construction Audit August 7, 2014 Agenda Definitions Risk Based Approach What Determines Risk Fraud Construction Risks What to Audit Red Flags Why Audit Prevention Wrap-up 1 Definitions
TRAVIS UNIFIED SCHOOL DISTRICT REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT SERVICES CONSTRUCTION MANAGER MULTI-PRIME
TRAVIS UNIFIED SCHOOL DISTRICT REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT SERVICES CONSTRUCTION MANAGER MULTI-PRIME QUESTIONS PAGE 11 200.325 BONDING REQUIREMENTS Please confirm that construction
Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES
SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work
TOOLING DEFINITIONS, COST AND AUDIT GUIDELINES
INTRODUCTION AND SCOPE This document sets forth the rights of Lear Corporation or its subsidiaries or affiliates (Lear) with regard to the auditing of 1) tooling paid for by Lear and used either (a) by
SUBCONTRACTOR PRE-QUALIFICATION APPLICATION
APPLICATION SUBCONTRACTOR IDENTITY Date Submitted Company Name Complete Address Phone Number Contact Name Federal Tax ID # DUNS # Fax Number Email Address NAICS Code States Registered to do Business Include
FOREMAN TRAINING. John Songer Alan Still Larry Lawrence
FOREMAN TRAINING John Songer Alan Still Larry Lawrence WANTED: FOREMAN Looking for highly motivated, well trained, responsible leaders who can look after a job as good or better than I will. Who treats
Analyzing contract terms: General requirements
Analyzing contract terms: General requirements Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. About Baker Tilly > Established
AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES. Responsibilities of Construction Manager Scope of Construction Manager s Basic Services
AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES Article I Article II Article III Article IV Article V Article VI Article VII Article VIII Article IX Responsibilities of Construction Manager Scope of Construction
Welcome to the 2015 Construction Industry Occupational Wage Survey Workshop. August 17, 2015 Jason Payton Oregon Employment Department Auditorium
Welcome to the 2015 Construction Industry Occupational Wage Survey Workshop August 17, 2015 Jason Payton Oregon Employment Department Auditorium The Bureau of Labor and Industries contracts with the Oregon
REQUEST FOR QUOTES (RFQ)
REQUEST FOR QUOTES (RFQ) Lincoln County Public Works is requesting quotes (RFQ) through its Small Works Roster Process. Quotes are being requested for a project to replace the roof on the Crew Headquarters/Truck
How to estimate the cost of installing an Electrical Distribution Center (EDC)
How to estimate the cost of installing an Electrical Distribution Center (EDC) Candidate Number 0112233 June 2012 Table of Contents 1) Introduction 3 2) Types and Methods of Measurement 3 5 3) Specific
Tecta America Roofing Redefined. Estimating is from Venus Financials are from Mars
Tecta America Roofing Redefined Estimating is from Venus Financials are from Mars Introductions Leslie Shiner Owner of The ShinerGroup Financial & management consultant for over 25 years MBA in Accounting
a. Proposals shall be submitted in a sealed envelope and addressed as follows:
1 CITY OF ATCHISON REQUEST FOR QUALIFICATIONS & PROPOSAL PLUMBING SERVICES JANUARY 1, 2014 THROUGH DECEMBER 31, 2014 DUE: DECEMBER 10, 2013 10:00 A.M. The City of Atchison (City) invites interested and
Construction Contract Fundamentals. Baker Tilly refers to Baker Tilly Virchow Krause, LLP,
Construction Contract Fundamentals Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. 2010 Baker Tilly Virchow Krause, LLP About
Request For Proposal. Furnish Schneider Business Park Signs Design Build Services. For the Cibolo Economic Development Corporation Cibolo, Texas
Request For Proposal Furnish Schneider Business Park Signs Design Build Services For the Cibolo Economic Development Corporation Cibolo, Texas The City of Cibolo, Texas Economic Development Corporation
Members, Council of Presidents. Advertisements for Architect/Engineer and Construction Manager Services and Calls for Bid
July, 2003 MEMORANDUM UCF-05.01-07/03 TO: Members, Council of Presidents FROM: SUBJECT: Advertisements for Architect/Engineer and Construction Manager Services and Calls for Bid AUTHORITY: Sections 240.209(3)(p),
SUCF PROJECT COST REPORTING GUIDE
SUCF PROJECT COST REPORTING GUIDE State University Construction Fund 353 Broadway / ALBANY, NY 12246 SUCF 900 / 11 Table of Contents Page A. Preface 1 B. Area Takeoff Methodology 1. General 2 2. Net Assignable
FAR 15.408 Table 15-2 -- Instructions for Submitting Cost/Price Proposals When Cost or Pricing Data Are Required
FAR 15.408 Table 15-2 -- Instructions for Submitting Cost/Price Proposals When Cost or Pricing Data Are Required This document provides instructions for preparing a contract pricing proposal when cost
A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.
DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) SECTION 23 08 02 PART 1 GENERAL 1.01 AUTHORITY (CxA) A. The Commissioning Authority (CxA) has been contracted or will be contracted directly
INSTRUCTIONS FOR PROVIDING PROFESSIONAL CONSULTING SERVICES
INSTRUCTIONS FOR PROVIDING PROFESSIONAL CONSULTING SERVICES Prepared by: Engineering Services and Internal Review May 2014 CONTENTS INTRODUCTION... 1 I. AUDIT EVALUATION... 2 II. PERFORMANCE AND POST-PERFORMANCE
HUMAN RESOURCE INFORMATION SYSTEM GROSS-TO-NET CALCULATOR
HUMAN RESOURCE INFORMATION SYSTEM GROSS-TO-NET CALCULATOR Revised March 2016 Table of Contents Introduction, Accessing the Payroll Calculator, and Exiting the Screen... 3 Changing Withholding Status on
ACCOUNTING TRANSACTIONS
ln following you will gain a better understanding accounting how different transactions are processed in the accounting system. There are a number of unique transactions that take place in construction
Contract Cost Principles and Guidelines
Contract Cost Principles and Guidelines Introduction The City of Philadelphia Contract Cost Principles and Guidelines is designed to serve as a manual for City departments entering into professional service
The Role of Construction Managers. FIDIC offers two contributions on the question of the role of a construction manager in a construction contract:
The Role of Construction Managers FIDIC offers two contributions on the question of the role of a construction manager in a construction contract: A. Notes on the use of FIDIC in the Middle East B. A Communication
QUESTIONS & ANSWERS LOG
QUESTIONS & ANSWERS LOG AUTHORIZATION OF EXTRA WORK (AEW) Q: Is an Authorization of Extra Work form required for all increases in quantities, even for an FCP? A: An Authorization of Extra Work (AEW) form
Compensation Methods for Architectural Services
Compensation Methods for Architectural Services Compensation Methods for Architectural Services By: Thomas R. Gossen, AIA, PE Secretary/Treasurer and Chief Operating Officer Gossen Livingston Associates,
Audits of Automobile Body and Repair Shops
Audits of Automobile Body and Repair Shops If you are in certain retail businesses, industry specific audit procedures may be performed by the IRS in addition to the standard procedures performed during
How-To-Tutorial for MoDOT s Consultant Prequalification Process. How-To-Tutorial for MoDOT s Consultant Annual Financial Prequalification Process
How-To-Tutorial for MoDOT s Consultant Prequalification Process Why has MoDOT developed the Annual Financial Prequalification Process MoDOT s has developed an Annual Financial Pre-Qualification process
The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY
The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY From Financial Management & Accounting for the Construction Industry, CFMA. 2014 Matthew Bender and Company, Inc., a member of the LexisNexis Group.
NONPROFIT FINANCIAL MANAGEMENT SELF ASSESSMENT TOOL
NONPROFIT FINANCIAL MANAGEMENT SELF ASSESSMENT TOOL I. Financial Planning/Budget Systems 1. Organization has a comprehensive annual budget which includes all sources and uses of funds for all aspects of
What Documents are required at Pre-award Audit of an agreement or sub-agreement. How to Avoid Common Proposal Mistakes
January 29, 2015 What Documents are required at Pre-award Audit of an agreement or sub-agreement How to Avoid Common Proposal Mistakes How to Avoid Common Invoice Mistakes Pre-Award Review New Agreement/Sub-agreement:
REIMBURSEMENT PROCEDURE for FEMA PUBLIC ASSISTANCE
REIMBURSEMENT PROCEDURE for FEMA PUBLIC ASSISTANCE Financial Assistance Availability The impact of major or catastrophic emergencies can exceed local financial resources. Financial aid and assistance may
City Website Design & Replacement RFP # 15-006
Request for Proposals City Website Design & Replacement RFP # 15-006 9/29/2015 The City of Fairburn, Georgia ( City ) is now accepting proposals from qualified consultants to provide design and replacement
REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER
RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February
CONTENTS I. PREMIUM ADJUSTMENT BY AUDIT 2 II. REMUNERATION INCLUSIONS AND EXCLUSIONS 2 III. TYPE OF LABOR HIRED 3 IV. WORKERS COMPENSATION 4
CONTENTS I. PREMIUM ADJUSTMENT BY AUDIT 2 II. REMUNERATION INCLUSIONS AND EXCLUSIONS 2 III. TYPE OF LABOR HIRED 3 IV. WORKERS COMPENSATION 4 V. GENERAL LIABILITY 5 VI. TEMPORARY LABOR INFORMATION FOR GENERAL
Pool Canvas. Question 1 Multiple Choice 0 points Modify Remove. Question 2 Multiple Choice 0 points Modify Remove
Page 1 of 21 TEST BANK > CONTROL PANEL > POOL MANAGER > POOL CANVAS Pool Canvas Add, modify, and remove questions. Select a question type from the Add Question drop-down list and click Go to add questions.
PASADENA AREA COMMUNITY COLLEGE DISTRICT (PACCD) 2015 California Uniform Public Construction Cost Accounting Act (CUPCCAA) Informal Bid List
PASADENA AREA COMMUNITY COLLEGE DISTRICT (PACCD) 2015 California Uniform Public Construction Cost Accounting Act (CUPCCAA) Informal Bid List At their Board meeting of August 21, 2013, the Trustees of the
CONSTRUCTION FRAUD DETECTING CONTROLLING AUDITING
CONSTRUCTION FRAUD DETECTING CONTROLLING AUDITING Louis A. Urso, CFE, CIA L. A. Urso Consulting 8190 Natures Way Suite 12 Lakewood Ranch, FL 34202 Construction Cost Recovery Auditing Project Controls Review
CPA DUE DILIGENCE CHECKLIST FOR THE SALE AND ACQUISITION OF A BUSINESS
Law Offices of Robert A. Briskin, a Professional Corporation 1901 Avenue of the Stars, Suite 1700, Los Angeles, California 90067 Certified Specialist - Taxation Law Telephone (310) 201-0507 The State Bar
Contractor s Guide. April 2016
Contractor s Guide April 2016 The Minnesota Housing Finance Agency does not discriminate on the basis of race, color, creed, national origin, sex, religion, marital status, status with regard to public
Bond Program Standard Operating Procedures
Los Angeles Community College District Bond Program Standard Operating s Volume III Construction Version Review 3 Issuance Date LACCD Program Management Office 515 S. Flower Street, Suite 900 Los Angeles,
TOWN OF STRATFORD PURCHASING DEPARTMENT STRATFORD, CONNECTICUT REQUEST FOR PROPOSAL. Subject: Payroll Processing Services for Stratford Library
TOWN OF STRATFORD PURCHASING DEPARTMENT STRATFORD, CONNECTICUT REQUEST FOR PROPOSAL RFP No. 2014-027 Issued: March 24, 2014 Subject: Payroll Processing Services for Stratford Library The Town of Stratford
FLEET MANAGEMENT. Fleet Management s motto is If you make the time for us, We will make the time for you.
FLEET MANAGEMENT Department Mission/Purpose Statement We are dedicated to be a well managed, responsive and preferred provider of fleet services and to meet all fuel, mechanical repairs, towing and vehicle
Labor Compliance Program Guidebook For School Districts
Labor-Management-Consultants P.O. Box 24455 Oakland, CA 94623 Phone: (510) 835-7603 Fax: (510) 835-7613 www.davillier-sloan.com [email protected] Labor Compliance Program Guidebook For School Districts
MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.
DESCRIPTION: '108-01, Start and Progress of Work, is hereby amended to require that the Contractor furnish and participate in a computerized CPM (critical path method) network scheduling system. The purpose
CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP)
Michigan Department Of Transportation 5100B (05/13) CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Page 1 of 2 REQUISITION NUMBER DUE DATE TIME DUE MDOT PROJECT MANAGER JOB
Classification: Subject to recoupment of funds by NWICA if the standard is Not Met.
RE: Documentation of In-Kind & Cash Match Applies to: Vendors providing Older Americans Act Services Classification: Subject to recoupment of funds by NWICA if the standard is Not Met. *SUPERSEDES THE
942 Preakness Dr. email- [email protected] Eagle, ID 83616 Idaho Registered Contractor RCE-23530 208-573-1082
942 Preakness Dr. email- [email protected] Eagle, ID 83616 Idaho Registered Contractor RCE-23530 208-573-1082 TO: SAMPLE CUSTOMER Thank you for inviting us to look at your project. As per your descriptions,
Information Concerning Specifications: Contact: Torri Martin (770)-964-2244 Email: [email protected]
ISSUE DATE: November 21, 2014 Information Concerning Specifications: Contact: Torri Martin (770)-964-2244 Email: [email protected] Information Concerning HR Policies: Contact: Abril Montano (770)-964-2244
CONSULTANT SERVICES MANUAL
WEST VIRGINIA DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS CONSULTANT SERVICES MANUAL Prepared by the: Engineering Division Consultant Services Section April 2005 West Virginia Department of Transportation,
CONTRACTOR PREQUALIFICATION REQUIREMENTS GENERAL CONTRACTORS, MECHANICAL/PLUMBING SUBCONTRACTORS & ELECTRICAL SUBCONTRACTORS FOR THE
CONTRACTOR PREQUALIFICATION REQUIREMENTS GENERAL CONTRACTORS, MECHANICAL/PLUMBING SUBCONTRACTORS & ELECTRICAL SUBCONTRACTORS FOR THE SANTEE SCHOOL DISTRICT 1 .......... 2 1. Effective January 1 st, 2014,
ACG Commissioning Guideline
ACG Commissioning Guideline Appendix A Sample Commissioning Specification NOTES TO APPENDIX A This appendix contains a sample Request for Proposal (RFP) for Commissioning Services as would be issued by
1 OF 7. there will be few "surprises" as the work progresses.
1 OF 7 FP-G1.94 GUIDELINES FOR SUCCESSFUL SUPERVISION OF SCHOOL DISTRICT CAPITAL CONSTRUCTION PROJECTS There is no doubt that the successful completion of any capital construction project is the result
Certified Payrolls Certified Payrolls Submittal Requirements Notice of Delinquent Certified Payroll
Certified Payrolls Certified Payrolls Weekly certified payrolls covering the s and sub s workforce shall be submitted to the engineer on all MDOT-let contracts. Certified payrolls are required for all
FAIR LABOR STANDARDS ACT, SERVICE CONTRACT LABOR STANDARDS EO 13658 AIR FORCE PRICE ADJUSTMENT GUIDE. March 2015
FAIR LABOR STANDARDS ACT, SERVICE CONTRACT LABOR STANDARDS & EO 13658 AIR FORCE PRICE ADJUSTMENT GUIDE March 2015 The purpose of this guide is to provide assistance in calculating contract price adjustments
Norsouth Construction Company of Georgia, Inc. Bid Information and Requirements To Whom it May Concern:
Norsouth Construction Company of Georgia, Inc. Bid Information and Requirements To Whom it May Concern: Norsouth Construction Company of Georgia, Inc. is dedicated to the highest standards of integrity
THE PREMIUM AUDIT PROCESS
THE PREMIUM AUDIT PROCESS TOPICS COVERED What is a premium audit? When is an audit performed? What types of audits are conducted? How do I prepare for my audit What records will I need? Certificates of
Schedule to Regulation PR No. 30/53
Schedule to Regulation PR No. 30/53 Rules for the Determination of Cost Prices Contents Page I. General 5 1. Scope 5 2. Contractor's Accounting System 5 3. Declaration by the Contractor 5 II. Determination
CHAPTER 4 TYPES OF COST ESTIMATES
CHAPTER 4 TYPES OF COST ESTIMATES 1. INTRODUCTION All projects, both construction and environmental restoration, require cost estimates to plan and budget the project efficiently. Numerous estimates are
SALES AND USE TAX TECHNICAL BULLETINS SECTION 17
SECTION 17 - NONPROFIT ENTITIES - HOSPITALS, EDUCATIONAL INSTITUTIONS, CHURCHES, ORPHANAGES AND OTHER CHARITABLE OR RELIGIOUS INSTITUTIONS AND ORGANIZATIONS AND QUALIFIED RETIREMENT FACILITIES WHOSE PROPERTY
Construction Contract Audit Fundamentals
Construction Contract Audit Fundamentals Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. 2010 Baker Tilly Virchow Krause,
Presenting the Numbers: Accounting Systems for Government Contractors
Presenting the Numbers: Accounting Systems for Government Contractors William D. Craven, CPA Senior Cost/Price Analyst CH2M HILL Plateau Remediation Company William D. Craven, CPA, CMA, CIA Cost/Price
Request for Quote Number: 2015-06-PRC Baseball Diamond Backstop Re-Fence
Request for Quote Number: 2015-06-PRC Baseball Diamond Backstop Re-Fence Sealed request for quotes will be received by Brian Tocheri, CAO/Clerk at 341 10 th St. Hanover, Ontario, N4N 1P5 until 2:00 pm,
BASE CONSTRUCTION INC
BASE CONSTRUCTION INC 14252 CULVER DRIVE A-630 IRVINE,CA 92604-0326 OFFICE:949 387-3471 Shop 714 994 9563 CELL:949 735-5292 FAX:949 786-8753 QUALITY ASSURANCE and QUALITY CONTROL MANUAL 1 TABLE OF CONTENTS
Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.
Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Contractor City, Zip Work Phone Number: Cell Phone Number: Fax Number: Email
PAYCHEX. Mastering Payroll Compliance. 10 Missteps to Avoid
PAYCHEX Mastering Payroll Compliance 10 Missteps to Avoid Executive Summary. Businesses pay government agencies millions of dollars each year in labor and tax compliance penalties. And, in this economy
Eanes Independent School District
EANES INDEPENDENT SCHOOL DISTRICT 601 Camp Craft Road Austin, Texas 78746 Request for Qualifications Construction Manager at Risk Services Eanes Independent School District Construct a District Operations
PLUMBING, HEATING & AIR CONDITIONING, REFRIGERATION & BOILER INSTALLATION CONTRACTORS QUESTIONNAIRE
PLUMBING, HEATING & AIR CONDITIONING, REFRIGERATION & BOILER INSTALLATION CONTRACTORS QUESTIONNAIRE 1. General Information Name of Applicant: Website Address: Annual Receipts: 2. Indicate the percentage
CHAPTER 15 DISASTER COST RECOVERY PROCEDURES
Kern County Policy and Administrative Procedures Manual CHAPTER 15 DISASTER COST RECOVERY PROCEDURES 1501. General Statement... 1 1502. Disaster Relief Claim Procedures... 1 1503. Responsibilities... 2
Example Accounting/Financial Policies
Example Accounting/Financial Policies TABLE OF CONTENTS INTERNAL CONTROLS... 2 ACCESS TO RECORDS BY MEMBERS... 3 ACCOUNTING COMPUTER FILE BACK-UP PROCEDURE... 3 ACCOUNTING METHOD... 3 AUDIT COMMITTEE...
Payroll Inclusions & Exclusions
Payroll Inclusions & Exclusions All information provided in this report and any documents ancillary thereto ("Report") are provided for information purposes only. Although the information found in this