WYANDOTTE SITE SAFETY AND HEALTH STANDARDS PREVENTATIVE MAINTENANCE - PRESSURE SAFETY RELIEVING DEVICES

Size: px
Start display at page:

Download "WYANDOTTE SITE SAFETY AND HEALTH STANDARDS PREVENTATIVE MAINTENANCE - PRESSURE SAFETY RELIEVING DEVICES"

Transcription

1 Issued by: Site Engineering I. PURPOSE A. To provide a preventative maintenance program for "Pressure Relieving Safety Devices": Safety Valves, Rupture Disks, Conservation Vents, and Flame Arrestors. B. To reduce the possibility of injury to personnel or damage to equipment caused by the failure of pressure relieving devices. II SCOPE This standard applies to all units or departments on the Wyandotte Site. III. DESIGN AND DOCUMENTATION A. Design of pressure relieving devices shall follow all applicable codes and standards. For calculation direction, reference Site Engineering Standard Procedure 25, and Corporate Pressure Relief Design Guidelines. B. Documentation requirements shall be as specified under each unit s preventative maintenance (PM) procedure. In general, these requirements are that each unit maintains a list of all devices in use, as well as manufacturers installation, operation, and maintenance manuals for all devices installed in that unit. Each application will have its own PM file, with technical information (sizing criteria, calculations, setpoint, device specification, etc.) contained or referenced (ie, to on-line documentation system) therein. Typical system for the site uses a two folder system: 1. PM folder for technical and maintenance records on point of service or application; 2. Valve or device folder (also known as an F-15 folder), for individual device history. C. For valves in dedicated service (no spares requiring device history), or for low cost, disposable device applications, operations and maintenance may decide to combine PM and device folders. This is an acceptable practice if the required information is maintained, if the system is documented as procedure, and the procedure is reviewed by operations and maintenance. RDM = WYS&H W-9 Page 1 of 19

2 IV. ACQUISITION A. New devices shall be purchased after sizing and specification is completed following the Engineering Standard Procedure Safety Relief Valve Sizing Guidelines. B. Replacement devices (same manufacturer, make and model number) shall be purchased by providing the vendor with the specification of the existing device. Any other replacement requires review by engineering, and must follow local Management of Change procedures. V. PUTTING DEVICES INTO SERVICE A. Before putting new device into service, PM folder must be established. 1. Replacement device installation requires updating PM folder. 2. Rupture disks require individual folders when installed alone; installations in series with a PSV may be documented via the PSV folders. If documented separately, the rupture disk file should cross-reference the PSV number, to locate the calculations. B. Maintenance representative will inspect, tag, and color code device before installation, per local plant or lab practice (see section IX, Numbering and color convention ). VI PREVENTATIVE MAINTENANCE PROCEDURES A. General PM notes: 1. All devices will have their own PM sheets, reflecting individual applications and manufacturer s recommendations (PSV/Rupture disk combined installations may have one PM sheet). RDM = WYS&H W-9 Page 2 of 19

3 2. Condition of vent piping is as critical as the individual device, and as such, should be inspected at the time of device inspections. 3. Each lab or plant area should clearly designate who is responsible for reviewing and resolving PMs that result in a condition 4 or 5. B. Power boiler valves 1. This class of valves requires inspection, repair and setting by a licensed shop. These valves will be sent to a licensed shop by the Maintenance Shop. The purchase order shall state the following: a) Disassemble, clean valve parts, check measurements, recondition and replace parts as required, reassemble, adjust opening and closing (or reseating) pressures. Steam valves will be checked with steam, not air or water. b) Perform the seat tightness test (ANSI B147.1/API RP527), reseal the blow down ring pin and the top lever pin (per ASME Power Boiler Code) color code the valve, install a metal data plate which shall include capacity, set pressure, date and the National Board VR stamp. Capacity of ASME Code Section I steam valves will be given in lbs. of saturated steam per hour at 3% accumulation. The inlet and outlet connections shall be sealed for return shipment to prevent the entry of dirt and other foreign material. 2. A written service report shall be returned with the valve by the service shop and shall include: a) Describe visual inspection. State one of the following regarding internals: clean, a slight film or coating, or had heavy deposits. State condition of flanges and springs. Comment on corrosion. b) Describe reconditioning and repairs - lapping or machining required, parts replaced, etc. c) Spring number and pressure range, and orifice size. d) Seat tightness leakage rate in bubble per minute. RDM = WYS&H W-9 Page 3 of 19

4 e) A copy of this report will be sent to the Plant Maintenance Shop. The responsible technician in the shop will transfer the information from the report to Form F-15. C. Safety valves (in-house inspection & repair by qualified technicians) 1. Write-up a) Verify PSV folder calculation & specifications information agrees with the device in service and initiate the F-15 form. b) Report to process owner, and correct any discrepancies prior to proceeding. 2. Visual inspection / cleaning a) Perform visual inspection and document findings b) Safety devices which involve hazardous materials must be handled in accordance with W-8 (Contaminated Equipment) and cleaned prior to testing. 3. Testing of As found pressure setting a) The testing apparatus must have sufficient capacity to provide a clean lift (no chatter). b) ASME Section VIII valves (those on vessels rated at >15 psig) in vapor/steam service will be tested with air, and valves in liquid service will be tested with air or water. c) Document the As found setting on the F-15 in accordance with the F-15 rating system (see Appendix A), and on the PM. d) For As found conditions of 4 or 5, see 6. below. RDM = WYS&H W-9 Page 4 of 19

5 4. Disassembly and inspection a) Perform disassembly/inspection per the manufacturer s procedures. b) Note: All critical dimensions must be verified and corrected if necessary, (for example, after lapping or machining, or if excessive wear or other abnormality is observed). Polishing with a 1200 grit (or higher) compound does not require critical dimension check. c) Document findings on the F-15 and on the PM. 5. Re-assembly and testing a) Reassemble & color code per section IX. b) Perform testing to verify set pressure a minimum of three (3) full cycles. Document on the F-15 and PM. c) Note: Valve must lift and not chatter. d) Valve must reseat tightly, and should not leak below 91% to 94% of set pressure, depending on manufacturer s recommendations. A leak test will be conducted to verify seat tightness. e) Set point range vs. Popping Point Tolerance (per ASME Section VIII) 0 to 70 psig 2 psi 71 to 300 psig 3% of set pressure 301 to 1000 psig 10 psi 6. When the equipment owner s representative reviews one of these PM's which shows a "4" or "5" "as found" condition, PM files will be checked to determine if this type has previously failed in the same service. If an assignable cause has been determined, an appropriate note will be made on the PM and F-15, and the PM signed and routed by the equipment owner s rep. If an assignable cause has not been determined, the Daily Support Team (DST) (or designees, or equivalent) should meet to determine corrective action. The results of the meeting will be noted on the PM and F-15. RDM = WYS&H W-9 Page 5 of 19

6 D. Safety valves (in-house inspection, and repair by licensed shop) 1. Perform procedures in section VI.C.1 to VI.C.3, above. 2. Refer to section VI.B (Power Boilers) for instructions to outside shop. E. Each plant or lab will determine those devices that are less expensive to replace than repair. For these designated low cost valves, 1. Perform procedures in section VI.C.1 to VI.C.3, above. 2. Return valve to service, or replace it, disposing of it appropriately, depending on test results. F. Safety relief valves on hot water heaters are designed per industry standards. Visual inspection and replacement on a specified schedule is an acceptable practice. In this application, a PM folder is required, but a valve folder is not, because no valve history is required. G. Pressure relieving devices in non-safety, non-code applications. Local plant or lab will determine appropriate PMs for these devices, with maintenance and engineering support.(these devices may be recognized by designations of PRD or PRV. ) H. Conservation vents, Low Pressure Relief Valves, Emergency Vents, Vacuum Relief Valves, etc. 1. Write-up a) Verify device folder calculation & specifications information agrees with the device in service and initiate the F-15 form. b) Report to process owner, and correct any discrepancies prior to proceeding. 2. Visual inspection / cleaning a) Perform visual inspection and document findings RDM = WYS&H W-9 Page 6 of 19

7 b) Safety devices which involve hazardous materials must be handled in accordance with W-8 (Contaminated Equipment) and cleaned prior to testing. 3. In-place Inspection - In-place inspections of weight-loaded devices are permitted if the following procedure is followed: a) Vessel pressure equalized with atmosphere. b) If vessel contains hazardous material or is blanketed with an inert gas such as nitrogen, a standby person must be present with the appropriate respiratory equipment in accordance with Safety Standard W-14 "Respiratory Protection Policy". All inlet connections must be isolated per Safety Standard W-10, "Lock, Tag, and Try". c) There shall be no materials pumped into or pumped out of vessel during inspection. d) Disassemble valve to expose seating surfaces and weights. Thoroughly inspect valve and document on F-15 and PM "as found" condition in accordance with the definitions in Appendix A, F-15 Practices, section IV. e) Depending on as found results, take the following actions: 1. If the "as found" condition is "1" or "2" the device may be wiped clean, color coded in accordance with the color for the current year (See Section IX) and returned to service. 2. If the "as found" condition is "3" and the device can be cleaned in place, it is permitted to do so. The device may then be reassembled, checked for proper operation, color coded and returned to service. RDM = WYS&H W-9 Page 7 of 19

8 3. If the "as found" condition is "4" or "5", the device must be removed and taken to the Maintenance Shop for cleaning and repair. (Proceed to section VI.H.4.c.3.) 4. Shop Inspection and Repair - If the device is spring loaded or the In-place Inspection "as found" condition of a weight loaded device is a "4" or "5", the device must be removed and serviced in the Maintenance Shop as follows: a) Safety devices which involve hazardous materials must be handled in accordance with W-8 (Contaminated Equipment) and cleaned prior to testing. b) Disassemble valve to expose seating surfaces and weights/springs. Vent springs should be inspected to verify that the set point pressure is within their rated range. A qualified engineer will be consulted whenever the set point is outside the rated range of the spring. Thoroughly inspect the valve and document on F-15 and PM "as found" condition in accordance with the definitions in Appendix A, F-15 Practices, section IV. c) Depending on as found results, take the following actions: 1. If the "as found" condition is "1" or "2" the device may be wiped clean, color coded in accordance with the color for the current year, and returned to service. 2. If the "as found" condition is "3" the device must be cleaned. The device may then be reassembled, checked for proper operation, color coded, and returned to service. 3. The technician must contact the appropriate equipment owner s representative with a report of any vent found in condition 4 or 5 so immediate corrective action can be taken for the vent being installed. 4. The vent will then be overhauled, making any repairs necessary and recording them on the PM and F-15. RDM = WYS&H W-9 Page 8 of 19

9 d) New vents and vents found in condition "5" will be tested to determine that it opens at a specified pressure and vacuum. The vent will be tested a minimum of three (3) full cycles. A vent must open fully, without chattering, at a pressure no greater than the sum of the setpoint plus the tolerance specified by the manufacturer. I. Rupture disks 1. Write-up 1. The vent must reseat tightly in the range specified by the manufacturer. Vents which do not meet these criteria shall not be returned to service. 2. Once the vent PM has been completed, the top bonnet will be color coded. 3. When the equipment owner s representative reviews one of these PM's which shows a "4" or "5" "as found" condition, PM files will be checked to determine if this type has previously failed in the same service. If an assignable cause has been determined, an appropriate note will be made on the PM and F-15, and the PM signed and routed by the equipment owner s rep. If an assignable cause has not been determined, the Daily Support Team (DST) (or designees, or equivalent) should meet to determine corrective action. The results of the meeting will be noted on the PM and F-15. a) Verify rupture disk folder calculation & specifications information agrees with the device in service and initiate the F-15 form. b) Report to process owner, and correct any discrepancies prior to proceeding. RDM = WYS&H W-9 Page 9 of 19

10 2. Both sides of every rupture disk must be visually inspected by a qualified technician in accordance with the procedure and frequency shown on the rupture disk PM sheet. This inspection may be done in place; however, the use of borescopes or similar devices does not permit adequate visual inspection. Therefore, they will not be utilized to perform the visual inspection. a) In-place inspections require compliance with W-18 "Vessel Entry Procedures". b) Installations involving hazardous materials must be handled in accordance with W-8 (Contaminated Equipment). 3. Rupture disks are also used to protect other pressure-relieving devices from corrosion. Inspection of the rupture disk should be part of the routine developed for inspection of the pressure relief valve. 4. Any extraordinary problems discovered during inspection must be reported to the appropriate equipment owner s representative immediately for corrective action. Damaged rupture disks must be discarded rather than repaired. "As found" conditions will be recorded on the PM by the Technician. 5. When the equipment owner s representative reviews the rupture disk PM which shows a failed disk or other problem, PM files will be checked to determine if a previous problem was noted for the same service. If an assignable cause has been determined, an appropriate note will be made on the PM and the PM signed and routed by the equipment owner s rep. If an assignable cause has not been determined, the DST (or designees, or equivalent) should meet to determine corrective action. The results of the meeting will be noted on the PM. 6. Regardless of the results of visual inspection, rupture disks require scheduled replacement, based on specifying engineer s and manufacturer s recommendations, and local experience. The replacement schedule should be documented on the PM. 7. Disks will be stored in such a manner as not to jeopardize the integrity of the disk. RDM = WYS&H W-9 Page 10 of 19

11 J. Flame arrestors 1. Every flame arrestor must be inspected/repaired by a qualified Technician in accordance with the procedure and frequency shown on the PM sheet. This inspection may be made in place. Any evidence of mechanical damage or the presence of more than surface coating, necessitates removal of the arrestor for Maintenance Shop inspection and overhaul. Arrestors which are removed and overhauled will have all repairs recorded on the PM. Any extraordinary problems discovered must be reported to the appropriate equipment owner s representative immediately for corrective action. 2. When the arrestor has been found to be serviceable the top bonnet will be color coded in accordance with the color for the current year 3. When the equipment owner s representative reviews an arrestor PM which required overhaul, PM files will be checked to determine if a previous problem was noted for the same service. If an assignable cause has been determined, an appropriate note will be made on the PM and the PM signed and routed by the equipment owner s rep. If an assignable cause has not been determined, the DST (or designees, or equivalent) should meet to determine corrective action. The results of the meeting will be noted on the PM. K. Internal reliefs (pump, compressor, etc.), or those integral to the design of the equipment. These devices do not require their own PMs or documentation, because they will be maintained with the primary equipment, per manufacturer s recommendations. (These devices should not have an individual tag number on P&IDs). RDM = WYS&H W-9 Page 11 of 19

12 VII. RESPONSIBILITIES RESPONSIBILITIES GRID (L = lead role S = support role) Scenario setting, system design and calculations S L Ensuring vendor provided devices meet site and L S corporate requirements Documentation (See III.B) L S Testing (performing PMs, managing outside L S services, pre-installation testing) Resolution of non-routine test results (including 4 L S S and 5 As Found results) Training S S S L Establish and enforce PM schedule L S S RDM = WYS&H W-9 Page 12 of 19

13 VIII. GENERAL OPERATIONS A. Changes in service 1. All changes in service require review by a qualified engineer. Use of a Management of Change procedure is required for all PSM plants, and is strongly encouraged for other facilities as well. If the change in service requires re-calculation, or re-specification of a valve, fill out a Request for Engineering Service (RES) form, or consult with local engineering team or Technical Engineering Support (TES) manager. In operations using TINMAN, submit a Request for Change (RFC). 2. Changes in set pressure should include a review of existing spring range. Change in set pressure requires the old setpoint and capacity be lined out, and a repair tag with the new setpoint and capacity be installed on the valve. 3. Revisions to vent piping must also be made only in consultation with engineering. B. Follow-up to device relieving or vessel overflow The Process Owner or Department Manager has the responsibility to require an incident investigation when a safety device relieves. The intent of this investigation is to analyze the incident and prevent its recurrence. The incident report should include immediate corrective actions such as performing a special PM to clean the safety valve to ensure that it is still functional. Any corrective action taken as a result of this investigation must be documented in the PM folder. IX. NUMBERING AND COLOR CONVENTIONS A. Each pressure-safety relieving device must have a prefix letter, followed by a number indented into the devices metal surface. (Inlet flange or as near as possible to the inlet connection.) The letters and numerals will be 1/4" high, or as large as possible, and the letters will be assigned for identification in accordance with the Identification Prefix described in the table below. The numbers will be assigned sequentially by the plant Maintenance Shop. EVERY SAFETY RELIEVING DEVICE, EXCEPT RUPTURE DISKS, WILL BE STAMPED. RDM = WYS&H W-9 Page 13 of 19

14 B. Identification Code Identification Department or Area Recipient of F-15 second copy Prefix A Site Main Office Human Resources Manager B Plastic Materials Department Manager C Adhesives Department Manager D Engineered Plastics Compounding Department Manager E Elastocell Department Manager F Expandable Polyolefin Department Manager FB Food Blends Operations Superintendent G Polyol Department Manager H Rail Car Department Manager I Chem. Engineering Department Manager J Chem. Engineering Department Manager K Miscellaneous Department Manager (Maint. Shops, Stores, Engineering & Research) KR Kreelon Department Manager L Thermal Plastic Urethane Department Manager N NPR Operations Superintendent PA PAC Department Manager UA Urethanes Applications Department Manager VA* Vitamin A Operations Superintendent VE* Vitamin E Operations Superintendent VQ Quality Assurance Operations Superintendent Z Steam Facility Responsible Engineering Associate T Livonia Site Plant Manager *Note: Current Vitamins practice is to use P&ID device tag number, in addition to Vx code RDM = WYS&H W-9 Page 14 of 19

15 C. Inspection Color Code The top bonnet of all pressure safety relieving devices will be color coded to indicate the year in which it was newly installed or was last inspected/repaired. Last digit of Year Color 0 Black 1 Brown 2 Red 3 Orange 4 Yellow 5 Green 6 Blue 7 Violet (Purple) 8 Grey 9 White X. REFERENCES ASME Boiler Code, Section 1 ASME Boiler Code, Section VIII API 2000 API 576 Corporate Standard No. 19, Pressure Relieving Devices RDM = WYS&H W-9 Page 15 of 19

16 Appendix A, F-15 Practices I. The permanent maintenance record for pressure safety relieving devices will be maintained on Form F-15 (click here to view F-15). The top portion of Form F-15 must be filled out by the owning department. Since this portion is critical in determining the history of the device, it must be filled out completely. II. When the PM on the valve is completed, the Technician performing the work will sign Form F-15. Distribution of the F-15 form corresponds with local plant or lab needs. A typical practice follows: A. The gold copy will be placed in a plastic envelope and attached to the valve. Once the valve is mounted in service, this copy may be removed and discarded by Operations personnel upon their confirming that the valve is installed for the application stated on the tag. B. The yellow copy will be sent to the appropriate Department Manager as listed on the distribution list maintained in the Maintenance Shop. (See Paragraph IX.B). C. The white copy will be kept in the Maintenance Shop F-15 or valve or device folder. D. The pink copy will be stapled to the safety PM for further routing. III. The "as found" condition for PSVs will be classified and noted on the F-15 in accordance with the following definitions (Note: Slight leaks may be detected by a wet paper towel, or bubble test): 1 Valve is clean, lifts fully within the tolerances shown in the table below, and reseats firmly. 2 Valve is clean, lifts fully within the tolerances shown in the table below, but has a slight leak when reseated. 3 Valve has slight film or coating on interior, but lifts fully within the tolerances shown in the table below, and reseats with no more than a slight leak. RDM = WYS&H W-9 Page 16 of 19

17 4 Valve has heavy deposits on interior but flow capacity is not restricted, lifts fully within the tolerances shown in the table below, and has no more than a slight leak. 5 Valve has heavy deposits restricting relieving capacity, or will not lift fully, or does not lift within the tolerances shown in the table below, or has more than a slight leak after reseating. Table: From ASME Section VIII Set point range Popping Point Tolerance 0 to 70 psig 2 psi 71 to 300 psig 3% of set pressure 301 to 1000 psig 10 psi IV. The "as found" condition for Conservation Vents (and other low pressure or vacuum devices) will be classified and noted on the F-15 or on the PM in accordance with the following definitions 1 Vent is clean -- weights/springs are as described on the PM sheet. 2 Vent is clean on interior -- exterior has slight film or coating - weights/springs are as described on the PM sheet. 3 Vent has slight film or coating on interior -- weights/springs are as described on the PM sheet. 4 Vent has heavy deposits on interior, but flow capacity is not restricted -- weights/springs are as described on the PM sheet. 5 Vent has heavy deposits restricting relieving capacity, or will not lift fully -- weights/springs are damaged or not as described on the PM sheet. RDM = WYS&H W-9 Page 17 of 19

18 Appendix B, Definitions 1. Blowdown -- Difference between set pressure and reseating pressure of a pressure relief valve expressed as a percent of set pressure. 2. Chatter -- Extremely rapid opening and closing of a valve 3. Conservation Vents -- These Devices are all used to protect a vessel or system from damage due to over-pressure or excessive vacuum. The set-points are less than 15 psig (usually inches of water), therefore, the ASME code does not apply. These devices are specified using the guidelines of API Flame Arrestor -- A device whose primary function is to prevent the propagation of fire, by absorbing and dissipating heat, from fire on one side of the flame arrestor, to below the ignition point on the opposite side of the arrestor. 5. Lift -- The actual travel of the disk away from the closed position when the valve relieves. (Full lift typically occurs at 10% overpressure). 6. Pressure Safety Relieving Valve -- An automatic pressure relieving device which may be used as a safety or relief valve, depending upon application: a safety relief valve is used to protect personnel and equipment by preventing excessive accumulation of pressure. 7. Qualified Personnel -- Maintenance personnel required to service safety relieving devices are required to have formal training provided by a recognized professional in this field every three years minimum, and perform such work at an appropriate frequency to maintain the necessary basic skills. 8. Relief valve -- A relief valve is an automatic pressure-relieving device, actuated by inlet static pressure which opens in proportion to the increase in pressure over the opening pressure. 9. Rupture Disk -- A non-reclosing pressure relief device actuated by inlet static pressure and designed to function by the bursting or rupturing of a pressure containing disk at a predetermined pressure. 10. Safety valve -- An automatic pressure-relieving device actuated by inlet static pressure and characterized by rapid opening or pop action. RDM = WYS&H W-9 Page 18 of 19

19 11. Safety relief valve -- An automatic pressure-relieving device characterized by rapid opening or pop action, or by opening in proportion to the increase in pressure over opening pressure, depending on the application. 12. Set Pressure -- Expressed in psig, set pressure is inlet pressure at which the device has been set to open under service conditions. In liquid service, set pressure is determined by the inlet pressure at which the valve starts to discharge a continuous stream of liquid. In gas or vapor service, the set pressure is determined by the inlet pressure at which the valve will pop under service conditions The set pressure for any device must be established by a qualified engineer who is authorized by Site Engineering. The engineer must consider the valve s relieving capacity (Pressure and flowrate), plus the system being protected. Set pressures for safety relief valves and rupture disks must be established according to ASME. Set pressures for conservation vents and other low pressure (less than 15 psig) relieving devices must be established according to API The set pressure for any pressure safety relieving device will be that value which has most recently been established by the authorized engineer and approved by the appropriate equipment owner s representative. If the set pressure must be changed (authorized via engineering) the old set pressure and capacity is to be lined out (still legible) and a repair tag with the new set pressure, capacity, and date must be installed on the valve. 13. Simmer -- Characterized by the audible or visual passage of a fluid across the seating surface of the safety or pressure relief device just prior to opening. In gas or vapor, simmer is the leakage just prior to popping (opening). For liquid service valves, simmer is the non-continuous flow (drops) just prior to becoming continuous. 14. Vacuum relief valve -- A pressure relief device designed to open to prevent an excessive internal vacuum. It is designed to reclose after normal conditions have been restored. RDM = WYS&H W-9 Page 19 of 19

Contents. LWN 750.30 edition: 24.02.10 3-0

Contents. LWN 750.30 edition: 24.02.10 3-0 Contents 3.1 Introduction...3.1-1 3.2 List of Referenced Codes and Standards...3.2-1 3.3 Overview Terms and Definitions...3.3-1 3.4 Description Terms and Definitions...3.4-1 LWN 750.30 edition: 24.02.10

More information

Select the Right Relief Valve - Part 1 Saeid Rahimi

Select the Right Relief Valve - Part 1 Saeid Rahimi Select the Right Relief Valve - Part 1 Saeid Rahimi 8-Apr-01 Introduction Selecting a proper type of relief valve is an essential part of an overpressure protection system design. The selection process

More information

Pentair Pressure Relief Valve Engineering Handbook

Pentair Pressure Relief Valve Engineering Handbook Pentair Pressure Relief Valve Engineering Handbook Anderson Greenwood, Crosby and Varec Products VALVES & CONTROLS Forward Copyright 2012 Pentair Valves & Controls. All rights reserved. No part of this

More information

Sizing, Selection, and Installation of Pressure-relieving Devices in Refineries

Sizing, Selection, and Installation of Pressure-relieving Devices in Refineries Sizing, Selection, and Installation of Pressure-relieving Devices in Refineries Part I Sizing and Selection API STANDARD 520 EIGHTH NINTH EDITION, DECEMBER 20082013 2 API STANDARD 520, PART 1 SIZING AND

More information

www.klmtechgroup.com TABLE OF CONTENT

www.klmtechgroup.com TABLE OF CONTENT Page : 1 of 51 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 3 REFERENCES

More information

OPERATING and MAINTENANCE MANUAL SERIES 2700A CONTROL VALVE CONTENTS. INTRODUCTION...1 Scope...1 Description...1 Valve Identification...

OPERATING and MAINTENANCE MANUAL SERIES 2700A CONTROL VALVE CONTENTS. INTRODUCTION...1 Scope...1 Description...1 Valve Identification... OPERATING and MAINTENANCE MANUAL SERIES 2700A CONTROL VALVE CONTENTS INTRODUCTION...1 Scope...1 Description...1 Valve Identification...2 1.0 VALVE INSTALLATION...2 2.0 VALVE MAINTENANCE...3 Actuator Disassembly...3

More information

COMPRESSED GASES. 1.2 The contents of each cylinder and container must be clearly identified (by tag or stamp) on the cylinder.

COMPRESSED GASES. 1.2 The contents of each cylinder and container must be clearly identified (by tag or stamp) on the cylinder. Page 1 of 5 COMPRESSED GASES A compressed gas is defined as any mixture of gases in a container with a pressure exceeding 40 psi. at 70 o F, or 104 psi. at 130 o F; or any flammable liquid with an absolute

More information

Float and Thermostatic Traps Series H, C and X

Float and Thermostatic Traps Series H, C and X Hoffman Specialty Installation & Maintenance Instructions HS-(E) and Thermostatic Traps Series H, C and X Series C & NPT Series C NPT Series X NPT Series C NPT Series H Ratings Maximum Max. Operating NPT

More information

KUNKLE SAFETY AND RELIEF VALVE PRODUCTS OVERVIEW

KUNKLE SAFETY AND RELIEF VALVE PRODUCTS OVERVIEW KUNKLE SAFETY AND RELIEF VALVE PRODUCTS OVERVIEW ISSUED FEBRUARY 2014 KUNKLE SAFETY AND RELIEF VALVE PRODUCTS OVERVIEW Contents Models 1 and 2 Brass Safety Valves... 4 Models 19, 19M, 20, 20M, 20P, 20MP,

More information

INSPECTION, MAINTENANCE AND RECHARGE SERVICE MANUAL P/N 16303

INSPECTION, MAINTENANCE AND RECHARGE SERVICE MANUAL P/N 16303 WATER MIST HAND PORTABLE FIRE EXTINGUISHERS Model B270 ¾ Gallon Model B272 2 ½ Gallon INSPECTION, MAINTENANCE AND RECHARGE SERVICE MANUAL P/N 6303 All fire extinguishers should be installed, inspected

More information

The First Line of Safety

The First Line of Safety Pilot Operated Pressure Relief Valves The First Line of Safety Pilot Operated Pressure Relief Valves 597C Farris Engineering Pressure Relief Valves Process Pressure Relief Valves Series 2600 ASME NB Certified:

More information

OPERATIONS & MAINTENANCE (O&M) FOR PROPANE STORAGE FACILITIES

OPERATIONS & MAINTENANCE (O&M) FOR PROPANE STORAGE FACILITIES OPERATIONS & MAINTENANCE (O&M) FOR PROPANE STORAGE FACILITIES Reference: National Fire Protection Association (NFPA) Pamphlet No. 58 Liquefied Petroleum Gas Code, 2001, Chapter 11 Type of Facility: Petroleum

More information

Boiler Preparation, Start-Up and Shutdown

Boiler Preparation, Start-Up and Shutdown Boiler Preparation, Start-Up and Shutdown Learning Outcome When you complete this module you will be able to: Describe the basic preparation of a boiler for start-up, and the start-up and shutdown procedures.

More information

BLADDER SURGE CONTROL SYSTEM

BLADDER SURGE CONTROL SYSTEM PART I GENERAL 1.01 Description BLADDER SURGE CONTROL SYSTEM This specification describes the requirements for a Bladder Surge Control System. The purpose of the system is to minimize transient pressures

More information

DARTMOUTH COLLEGE DESIGN January 3, 2012 & CONSTRUCTION GUIDELINES

DARTMOUTH COLLEGE DESIGN January 3, 2012 & CONSTRUCTION GUIDELINES SECTION 15062 STEAM AND CONDENSATE PIPING PART 1 DESIGN DIRECTIVES 1.1 QUALITY ASSURANCE A. Comply with the provisions of the following: 1.2 DESIGN CRITERIA 1. ASME B 31.9 Building Services Piping : for

More information

Boiler & Pressure Vessel Inspection discrepancies and failures

Boiler & Pressure Vessel Inspection discrepancies and failures Boiler & Pressure Vessel Inspection discrepancies and failures Water Heaters / Pressure Vessels Pressure Vessels are inspected once every three years. This requires a test of A: safety relief devices B:

More information

Facility Operations Physical Safety Guidance Document

Facility Operations Physical Safety Guidance Document Facility Operations Physical Safety Guidance Document Title: Guide on Pipe Identification Standards (ASME A13.1-1996) Original Date: December 18, 2000 Section: 4.0 Facility Operations Revised Date: Number:

More information

Product Manual. CVS Type 67AFR Filter Regulator. Introduction. Installation. Description

Product Manual. CVS Type 67AFR Filter Regulator. Introduction. Installation. Description Product Manual CVS Type 67AFR Filter Regulator Introduction This CVS Controls product manual includes instructions for the installation, adjustment, maintenance and parts ordering of the CVS Type 67AFR

More information

BPW32 DN15, DN20 and DN25 Balanced Pressure Wafer Steam Trap

BPW32 DN15, DN20 and DN25 Balanced Pressure Wafer Steam Trap 1263050/6 IM-P126-07 ST Issue 6 BPW32 DN15, DN20 and DN25 Balanced Pressure Wafer Steam Trap Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation

More information

PBX Series Quick Fit Connector Bimetallic Steam Traps

PBX Series Quick Fit Connector Bimetallic Steam Traps 6262100/6 IM-P626-01 ST Issue 6 PBX Series Quick Fit Connector Bimetallic Steam Traps Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Commissioning

More information

API Flanged Safety Relief Valves Series 526 CATALOG

API Flanged Safety Relief Valves Series 526 CATALOG API Flanged Safety Relief Valves Series 26 CATALOG The-Safety-Valve.com 1 Valve finder How to find the right product group High operating to set pressure ratio, high backpressure or low total height? Yes

More information

Proportional Relief Valves

Proportional Relief Valves www.swagelok.com Proportional Relief Valves R Series Liquid or gas service Set pressures from 10 to psig (0.7 to 413 bar) 1/4 and 1/2 in. and 6 to 12 mm end connections 2 Proportional Relief Valves Spring

More information

Pressure Relief Valves. 1811 Series - Maintenance Manual. Consolidated Safety Valve

Pressure Relief Valves. 1811 Series - Maintenance Manual. Consolidated Safety Valve Pressure Relief Valves 1811 Series - Maintenance Manual Consolidated Safety Valve Table of Contents Section Subject Page No Conversion Table...3 I. Consolidated Safety Valve Type 1811...4 II. Product Safety

More information

P O B o x 3 11 5 4 S t. L o u i s, M O 6 3 1 3 1-0 1 5 4 P h o n e : ( 3 1 4 ) 9 6 6-8 9 1 9 ~ E m a i l : w m h u I t t @ a o l.

P O B o x 3 11 5 4 S t. L o u i s, M O 6 3 1 3 1-0 1 5 4 P h o n e : ( 3 1 4 ) 9 6 6-8 9 1 9 ~ E m a i l : w m h u I t t @ a o l. P O B o x 3 11 5 4 S t. L o u i s, M O 6 3 1 3 1-0 1 5 4 P h o n e : ( 3 1 4 ) 9 6 6-8 9 1 9 ~ E m a i l : w m h u I t t @ a o l. c o m Determining Code Compliance and Pipe System Leak ing by William M.

More information

www.klmtechgroup.com TABLE OF CONTENT

www.klmtechgroup.com TABLE OF CONTENT Page : 1 of 19 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 2 REFERENCES

More information

ball valves Flomite 71 Series 2-way Integral Panel Mount Ball Valves

ball valves Flomite 71 Series 2-way Integral Panel Mount Ball Valves 2-way Integral Panel Mount Ball Valves Used for quick on-off service with a visual indication of flow, HOKE s 2-way ball valves offer orifice sizes up to 0.25 (6.4mm). Flomite valves feature a floating

More information

Installation, Operation and Maintenance Manual for Pilot Operated Valves

Installation, Operation and Maintenance Manual for Pilot Operated Valves Installation, Operation and Maintenance Manual for Pilot Operated Valves Models 1400, 1420, 1430, 1460 IOM1400.0 January 2, 2014 REV A 12393 REF. ID 98136 IOM1400.0 REV. A 12541 TABLE OF CONTENTS DESCRIPTION

More information

G-704-0 SPECIFICATION: GAS METER AND REGULATOR INSTALLATION REQUIREMENTS. 3 and Gas Yellow Book. REVISIONS: (See ) 1/15/14 5 Years

G-704-0 SPECIFICATION: GAS METER AND REGULATOR INSTALLATION REQUIREMENTS. 3 and Gas Yellow Book. REVISIONS: (See ) 1/15/14 5 Years LAST REVIEW DATE: REVIEW CYCLE: 1/15/14 5 Years SPECIFICATION: TITLE: VOLUME: G-704-0 3 and Gas Yellow Book REVISIONS: (See ) 1) This specification is being issued for the first time. G-704-0 Gas Operations

More information

STORED PRESSURE STAINLESS STEEL

STORED PRESSURE STAINLESS STEEL STORED PRESSURE STAINLESS STEEL WATER FIRE EXTINGUISHERS Model 240-2-1/2 Gallon OWNER'S SERVICE MANUAL NO. 05601 INSPECTION, MAINTENANCE AND RECHARGE All fire extinguishers should be installed, inspected

More information

Flushing and Cleaning the A/C System

Flushing and Cleaning the A/C System Flushing and Cleaning the A/C System Once an AC system has been contaminated or has suffered a failure, the most important part of the AC service to restore the cooling performance to the system = FLUSHING

More information

Tankless Water Heater

Tankless Water Heater Tankless Water Heater USER S INFORMATION MANUAL Models WGRTNG199 / WGRTLP199 WGRTCNG199 / WGRTCLP199 NOTICE: Westinghouse reserves the right to make product changes or updates without notice and will not

More information

Steam System Efficiency. Bill Lumsden Leidos Engineering

Steam System Efficiency. Bill Lumsden Leidos Engineering Steam System Efficiency Bill Lumsden Leidos Engineering Steam System Efficiency Steam System Efficiency Key Take-aways: Review of the properties of ice, water, and steam Learn the basics of steam trap

More information

WHAT YOU DON T KNOW ABOUT ACCUMULATORS CAN KILL YOU!

WHAT YOU DON T KNOW ABOUT ACCUMULATORS CAN KILL YOU! WHAT YOU DON T KNOW ABOUT ACCUMULATORS CAN KILL YOU! Atlanta (Monroe) GA 770-267-3787 gpm@gpmhydraulic.com www.gpmhydraulic.com What You Don t Know About Hydraulic Accumulators Can Kill You TABLE OF CONTENTS

More information

TYPE E Main Valve Sizes 3 /8 through 12

TYPE E Main Valve Sizes 3 /8 through 12 SD 3001F PRINTED IN U.S.A. SD 3001F/0707 A B TYPE E MAIN VALVE C D E TYPE E Main Valve Sizes 3 /8 through 12 The Spence Type E Main Valve is of normally closed, single seat design featuring packless construction,

More information

5.23.22 STEAM AND CONDENSATE PIPING AND PUMPS DESIGN AND CONSTRUCTION STANDARD PART 1: GENERAL. 1.01 Purpose:

5.23.22 STEAM AND CONDENSATE PIPING AND PUMPS DESIGN AND CONSTRUCTION STANDARD PART 1: GENERAL. 1.01 Purpose: PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is

More information

Pressure Testing Procedures for Building Services Piping

Pressure Testing Procedures for Building Services Piping Pressure Testing Procedures for Building Services Piping Document Number Revision 0 Approved By Ric Morris McMurdo, Palmer, and South Pole February 25, 2005 Active Divisions/Departments FEMC Raytheon Polar

More information

INSTALLATION INSTRUCTIONS Fan Coil Replacement Coil Kit EBX & EBXX

INSTALLATION INSTRUCTIONS Fan Coil Replacement Coil Kit EBX & EBXX Fan Coil Replacement Coil Kit EBX & EBXX These instructions must be read and understood completely before attempting installation. These instructions covers the installation of replacement coil kit into

More information

M A N U A L 13-10-05

M A N U A L 13-10-05 Documentation The following information sheets illustrate the description below: 12-WW01-4G-E Sectional view of the lance with main dimensions 12-W101-6G-E Sectional view of the head of the lance with

More information

Owner-User Pressure Equipment Integrity Management Requirements

Owner-User Pressure Equipment Integrity Management Requirements the pressure equipment safety authority Owner-User Pressure Equipment Integrity Management Requirements AB-512 Edition 2, Revision 0 Issued 2015-06-25 Owner-user Pressure Equipment Integrity Management

More information

ENVIRONMENTAL STANDARDS FOR PETROLEUM OIL REFINERIES EMISSIONS. Standards for emissions from furnaces, boilers and Power Plant

ENVIRONMENTAL STANDARDS FOR PETROLEUM OIL REFINERIES EMISSIONS. Standards for emissions from furnaces, boilers and Power Plant ENVIRONMENTAL STANDARDS FOR PETROLEUM OIL REFINERIES EMISSIONS Standards for emissions from furnaces, boilers and Power Plant S. Parameter Limiting concentration in mg/nm 3, unless stated Existing refineries

More information

Type HSR Pressure Reducing Regulator for Residential, Commercial or Industrial Applications

Type HSR Pressure Reducing Regulator for Residential, Commercial or Industrial Applications Instruction Manual Form 5753 Type HSR February 014 Type HSR Pressure Reducing Regulator for Residential, Commercial or Industrial Applications P154 TYPE HSR ANGLE BODY P175 TYPE HSR STRAIGHT Figure 1.

More information

In-Line Air Separators

In-Line Air Separators Air Elimination & Control In-Line Air Separators The AC models of air separators deliver all the quality and performance you expect from Taco products. They are built to last with shell, heads and ANSI

More information

Vehicle Maintenance Facilities Requirements for CNG and LNG Vehicles

Vehicle Maintenance Facilities Requirements for CNG and LNG Vehicles Vehicle Maintenance Facilities Requirements for CNG and LNG Vehicles Presented by: Leo Thomason Executive Director Natural Gas Vehicle Institute (NGVi) at NFPA Conference and Expo, June 11, 2014 Leo Thomason

More information

Compressed Gas Cylinder Storage and Handling Guide

Compressed Gas Cylinder Storage and Handling Guide Overview Compressed gas cylinders are used in many workplaces to store gases that vary from extremely flammable (acetylene) to extremely inert (helium). Many compressed gas cylinders are stored at extremely

More information

Types 66R and 66RR Low-Pressure Relief Valves

Types 66R and 66RR Low-Pressure Relief Valves November 2009 Types 66R and 66RR Low-Pressure Relief Valves W1953 W1908 TYPE 66R RELIEF VALVE TYPE 66RR RELIEF VALVE Figure 1. Typical Constructions Introduction Types 66R and 66RR low-pressure throttling

More information

ANNEX 17 DRAFT AMENDMENTS TO SOLAS REGULATIONS II-2/4 AND II-2/16. Part B Prevention of fire and explosion

ANNEX 17 DRAFT AMENDMENTS TO SOLAS REGULATIONS II-2/4 AND II-2/16. Part B Prevention of fire and explosion Annex 17, page 1 ANNEX 17 DRAFT AMENDMENTS TO SOLAS REGULATIONS II-2/4 AND II-2/16 Part B Prevention of fire and explosion Regulation 4 Probability of ignition 1 The existing paragraph 5.5 is replaced

More information

Flowserve - Edward Valves Quick Closing Isolation Valves -The Equiwedge Alternative

Flowserve - Edward Valves Quick Closing Isolation Valves -The Equiwedge Alternative Flowserve - Edward Valves Quick Closing Isolation Valves -The Equiwedge Alternative Problem Fast isolation of a large bore main steam or feedwater line during a pipe rupture that seals flow in both directions.

More information

Process Equipment Design Guidelines Chapter Ten PRESSURE RELIEF VALVE SELECTION AND SIZING (ENGINEERING DESIGN GUIDELINES)

Process Equipment Design Guidelines Chapter Ten PRESSURE RELIEF VALVE SELECTION AND SIZING (ENGINEERING DESIGN GUIDELINES) Guidelines for Processing Plant www.klmtechgroup.com Page : 1 of 94 Rev 01 Oct 2007 Rev 02 May 2012 Rev 03 Febuary 2014 KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200

More information

SECTION 33 12 19 FIRE HYDRANTS

SECTION 33 12 19 FIRE HYDRANTS SECTION 33 12 19 FIRE HYDRANTS PART 1: GENERAL 1.01 SCOPE A. Fire hydrants. B. Adjustment of fire hydrants and gate valves. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 - Submittals.

More information

www.klmtechgroup.com TABLE OF CONTENT

www.klmtechgroup.com TABLE OF CONTENT Page : 1 of 10 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia PIPING FLEXIBILITY ANALYSIS TABLE

More information

60 Series Pilot Regulator

60 Series Pilot Regulator 0 Series Pilot Regulator Repair Parts List www.elster-americanmeter.com Read carefully and follow all instructions shipped with this regulator. The incorrect installation of this equipment could result

More information

Ontario Fire Code SECTION 5.13 DIP TANKS. Illustrated Commentary. Office of the Ontario Fire Marshal

Ontario Fire Code SECTION 5.13 DIP TANKS. Illustrated Commentary. Office of the Ontario Fire Marshal Ontario Fire Code SECTION 5.13 DIP TANKS Illustrated Commentary Office of the Ontario Fire Marshal Dip Tanks Illustrated Commentary 1 5.13.1. Location 5.13.1.1. Dip tank operations involving flammable

More information

Specific Volume of Liquid (Column 7). The volume per unit of mass in cubic feet per pound.

Specific Volume of Liquid (Column 7). The volume per unit of mass in cubic feet per pound. Steam Tables What They Are How to Use Them The heat quantities and temperature/ pressure relationships referred to in this Handbook are taken from the Properties of Saturated Steam table. Definitions of

More information

OSHA Tank Venting DEFINITIONS

OSHA Tank Venting DEFINITIONS OSHA Tank Venting DEFINITIONS 1910.106 - Flammable and combustible liquids. 1910.106(a)(2) (a) Definitions. As used in this section: (2) Atmospheric tank shall mean a storage tank which has been designed

More information

Nitrogen Blanketing for Methanol Storage and Transportation

Nitrogen Blanketing for Methanol Storage and Transportation Nitrogen Blanketing for Methanol Storage and Transportation Overview Air is the enemy of many materials. Not only can oxygen cause safety concerns and product degradation, but moisture, dirt, hydrocarbons

More information

A Job Safety Execution Plan is required. mixtures of the above called, natural gas liquids (NGL's) refined products and their components

A Job Safety Execution Plan is required. mixtures of the above called, natural gas liquids (NGL's) refined products and their components TITLE Pipelines and Terminals Manual/Volume 3 - SECTION 02: SUBJECT 20: PURPOSE AND SCOPE During the normal lifetime of a pipeline it becomes necessary to add or remove piping, modify existing piping or

More information

Design, Inspection, Testing and Repair of ASME-Coded Pressure Systems and Safety Relief Valves

Design, Inspection, Testing and Repair of ASME-Coded Pressure Systems and Safety Relief Valves HANFORD MSSON SUPPORT CONTRACT Design, nspection, Testing and Repair of ASME-Coded Pressure Systems and Safety Relief alves MSC-RD-19440 Revision 0 Effective Date: December 10, 2009 Topic: Engineering

More information

Constantemp Double Wall Low pressure steam-water Heater F-340LDW,F-640LDW, F-940LDW and F-1240LDW

Constantemp Double Wall Low pressure steam-water Heater F-340LDW,F-640LDW, F-940LDW and F-1240LDW Installation, Operating and Maintenance Instructions 90/4.5.5 Rev. 0 Constantemp Double Wall Low pressure steam-water Heater F-340LDW,F-640LDW, F-940LDW and F-1240LDW Table of Contents SECTION I... 2 INSTALLATION...

More information

HS-901(A) BASIC STEAM HEATING SYSTEMS

HS-901(A) BASIC STEAM HEATING SYSTEMS HS-901(A) BASIC HEATING SYSTEMS One-Pipe Two-Pipe Basic Steam Heating Systems One-pipe steam heating system EQUALIZER SAFETY FACTOR STATIC HEAD PRESSURE DROP 2" HEATING UNIT 15" DRIP CONNECTION In a one-pipe,

More information

Pressure & Flame Protection

Pressure & Flame Protection Pressure & Flame Protection Safety Relief Valves Safety Relief Valves WB SERIES SPRING LOADED SAFETY RELIEF VALVES The WB is designed safely relieve excess pressure in pumps, pipework, tanks, calorifiers,

More information

1800C and 1800C-HC Series Service Regulators. Technical Bulletin

1800C and 1800C-HC Series Service Regulators. Technical Bulletin and -H Series Service Regulators Technical Bulletin and -H Series Service Regulators 0 Elster American Meter The Series pressure regulators are designed to control natural gas, air, nitrogen, carbon dioxide,

More information

Your safety and the safety of others are very important.

Your safety and the safety of others are very important. NATURAL GAS TO PROPANE CONVERSION KIT 090 INSTALLATION INSTRUCTIONS FOR ALTITUDES 0 -,00 FT. ONLY PROPANE CONVERSION KIT SAFETY... INSTALLATION REQUIREMENTS... Tools and Parts... LP Gas Requirements...

More information

Vacuum Control. Vacuum Applications. Vacuum Regulators. Vacuum Breakers (Relief Valves) Vacuum Control Devices. Vacuum Terminology

Vacuum Control. Vacuum Applications. Vacuum Regulators. Vacuum Breakers (Relief Valves) Vacuum Control Devices. Vacuum Terminology Vacuum Applications Vacuum regulators and breakers are widely used in process plants. Conventional regulators and relief valves might be suitable for service if applied correctly. This section provides

More information

LCT 1025 (08/08) Copyright 2008 Harleysville Mutual Insurance Company Page 1 of 5 All rights reserved

LCT 1025 (08/08) Copyright 2008 Harleysville Mutual Insurance Company Page 1 of 5 All rights reserved Bonding and Grounding of Flammable Liquid Containers Provided by Harleysville s Risk Control Department 800-523-6344 ext 8100 www.harleysvillegroup.com/riskcontrol Summary The movement of volatile liquids,

More information

University of Tennessee Safety Guidelines

University of Tennessee Safety Guidelines University of Tennessee Safety Guidelines Guideline Subject: Compressed Gases and Cryogenics Safety Guidelines Approval Date: 10/1/15 (Rev. 1) Next Scheduled Review: 10/1/19 Date Effective: 1/01/09 Contact

More information

Non-Code Liquid Relief, ASME Section VIII, Air/Gas and Steam, National Board Certified, Safety and Relief Valves

Non-Code Liquid Relief, ASME Section VIII, Air/Gas and Steam, National Board Certified, Safety and Relief Valves Non-Code Liquid Relief, ASME Section VIII, Air/Gas and Steam, National Board Certified, Safety and Relief Valves Features Top guided design offers high capacity with 0.110 in 2 [0.710 cm 2 ] orifice area.

More information

Description of Thermal Oxidizers

Description of Thermal Oxidizers Description of Thermal Oxidizers NESTEC, Inc. is a full service equipment supplier specializing in solutions for plant emission problems. The benefit in working with NESTEC, Inc. is we bring 25+ years

More information

V47 Series Temperature Actuated Modulating Water Valves

V47 Series Temperature Actuated Modulating Water Valves V47 Series Temperature Actuated Modulating Water Valves Master Catalog 125 Valves, Miscellaneous (Other Than Gas) Section V Product Bulletin V47 Issue Date 0286 Application The V47 modulating valves regulate

More information

IMPORTANT SAFETY NOTICE

IMPORTANT SAFETY NOTICE IMPORTANT SAFETY NOTICE To: Our Valued Customers User safety is a major focus in the design of our products. Following the precautions outlined in this manual will minimize your risk of injury. ITT Goulds

More information

ENGINE COOLING SYSTEM

ENGINE COOLING SYSTEM ENGINE COOLING SYSTEM 1988 Toyota Celica 1987-88 TOYOTA Engine Cooling Systems Celica DESCRIPTION The basic liquid cooling system consists of a radiator, water pump, thermostat, cooling fan, pressure cap,

More information

CONTAMINANT REMOVAL FROM CENTRIFUGAL SYSTEMS

CONTAMINANT REMOVAL FROM CENTRIFUGAL SYSTEMS CONTAMINANT REMOVAL FROM CENTRIFUGAL SYSTEMS BULLETIN 240-10-3 June 2004 Supersedes June 1983 Many centrifugal systems get little maintenance. As a result they operate with the refrigerant highly contaminated

More information

Compressed Gas Cylinder Safety

Compressed Gas Cylinder Safety Compressed Gas Cylinder Safety I. Background. Due to the nature of gas cylinders, special storage and handling precautions are necessary. The hazards associated with compressed gases include oxygen displacement,

More information

Unsteady State Relief Valve Evaluation. External Pool Fire Scenario

Unsteady State Relief Valve Evaluation. External Pool Fire Scenario Unsteady State Relief Valve Evaluation External Pool Fire Scenario By Rame Sulaiman Process Engineer Process Engineering Associates, LLC Copyright 2009 Process Engineering Associates, LLC. All rights reserved.

More information

CROWN BOILER COMPANY BWF SERIES BOILER CATEGORY I VENT KIT INSTALLATION AND OPERATING INSTRUCTIONS

CROWN BOILER COMPANY BWF SERIES BOILER CATEGORY I VENT KIT INSTALLATION AND OPERATING INSTRUCTIONS CROWN BOILER COMPANY BWF SERIES BOILER CATEGORY I VENT KIT INSTALLATION AND OPERATING INSTRUCTIONS WARNING Improper installation, adjustment, alteration, service, or maintenance of this product can cause

More information

FJ2. 2 Ton Trolley Floor Jack Assembly & Operating Instructions

FJ2. 2 Ton Trolley Floor Jack Assembly & Operating Instructions FJ2 2 Ton Trolley Floor Jack Assembly & Operating Instructions READ ALL INSTRUCTIONS AND WARNINGS BEFORE USING THIS PRODUCT. This manual provides important information on proper operation & maintenance.

More information

Industrial Process Pump Safety Manual IMPORTANT SAFETY NOTICE

Industrial Process Pump Safety Manual IMPORTANT SAFETY NOTICE Industrial Process Pump Safety Manual IMPORTANT SAFETY NOTICE To: Our Valued Customers User safety is a major focus in the design of our products. Following the precautions outlined in this manual will

More information

TECHNICAL DATA. Dry 122a. November 12, 2013

TECHNICAL DATA. Dry 122a. November 12, 2013 Dry 122a 1. PRODUCT DESCRIPTION The Viking is a quick-opening device. When installed with the required external Anti-flood Device, the assembly is designed to increase the operating speed of Viking Model

More information

T&P and ASME Safety Relief Valves

T&P and ASME Safety Relief Valves T&P and ASME Safety Relief Valves w a t t s. c o m Table of Contents Temperature & Pressure Relief Valves General Information The Role of Temperature and Pressure Relief Valves in Water Heater Safety........................................4

More information

A Code of Practice for Pressure Equipment in the Department of Physics

A Code of Practice for Pressure Equipment in the Department of Physics A Code of Practice for Pressure Equipment in the Department of Physics Scope This code of practice describes the management of equipment and systems operating above atmospheric pressure in the Department.

More information

James M. Pleasants Company

James M. Pleasants Company James M. Pleasants Company SUBMITTAL DATA GAINESVILLE MECHANICAL DECEMBER 20, 2013 PROJECT: GSU: J-183 HUMANITIES LAW BLDG. QUOTE NO:12116 ENGINEER: STEVENS & WILKINSON GASKETED PLATE HEAT EXCHANGER Tag:

More information

GNOME PELLET E.I. Pellet Heater Owner's Manual Installation and Operating Instructions. Please read this entire manual before installation.

GNOME PELLET E.I. Pellet Heater Owner's Manual Installation and Operating Instructions. Please read this entire manual before installation. Pellet Heater Owner's Manual Installation and Operating Instructions Please read this entire manual before installation. Save these instructions. SAFETY NOTICE HEATER MUST BE PROPERLY INSTALLED AND MAINTAINED

More information

Notes. Material 1. Appropriate Flammable Liquids

Notes. Material 1. Appropriate Flammable Liquids 29 CFR 1910.106 Flammable Materials Flammable Liquids Preparation 1. Read Applicable Background information and related Company Policy Chapter. 2. Make Copies of this Lesson Plan for Personnel 3. Make

More information

Installation, Operating and Maintenance Instructions for AEON Metal Seated Gate Valve (MSGV) Water

Installation, Operating and Maintenance Instructions for AEON Metal Seated Gate Valve (MSGV) Water 1 Foreword 1.1 Thank you for choosing one of the range of AEON's BS standard valves. For safety purposes, the user shall read this instruction to fully understand the operation of the product. 2 AEON Design

More information

Air Eliminators and Combination Air Eliminators Strainers

Air Eliminators and Combination Air Eliminators Strainers Description Air Eliminators and Combination Air Eliminator Strainers are designed to provide separation, elimination and prevention of air in piping systems for a variety of installations and conditions.

More information

Operation & Maintenance Manual

Operation & Maintenance Manual Manual # OMAV2-SUMP1 High Performance Air & Dirt Separators Manual # 9636-1230 Rev. A Operation & Maintenance Manual 340 West 8 th Street Peru, IN 46970 PH: 765 472 3351 FX: 765 472 3968 www.thrushco.com

More information

MODEL J SERIES CONVERTER

MODEL J SERIES CONVERTER 3030 S Susan Street, MODEL J SERIES CONVERTER REPAIR KIT INSTRUCTIONS Important: Any maintenance, service or repair should be performed by trained and experienced service technicians. Proper tools and

More information

1805 Series Relief Valves

1805 Series Relief Valves October 2011 1805 Series Relief Valves P1026 1805G Type 1805-2 Type 1805-4 Figure 1. Typical 1805 Relief Valves Introduction The 1805 Series relief valves are designed for use in farm tap applications

More information

pdi PLASTIC DRUM INSTITUTE Plastic Drum Paneling Issues

pdi PLASTIC DRUM INSTITUTE Plastic Drum Paneling Issues pdi PLASTIC DRUM INSTITUTE Plastic Drum Paneling Issues PANELING BACKGROUND This report will explain the causes of paneling and suggest some possible ways to eliminate or minimize the paneling of plastic

More information

Air Conditioner Water Heater - A Product of HotSpot Energy LLC

Air Conditioner Water Heater - A Product of HotSpot Energy LLC Air Conditioner Water Heater - A Product of HotSpot Energy LLC PLEASE READ THIS BEFORE YOU INSTALL THE UNIT 1. This air conditioner must be installed and/or repaired by a qualified technician. If you perform

More information

Boiler and Burner Cleaning and Servicing Specifications

Boiler and Burner Cleaning and Servicing Specifications Boiler and Burner Cleaning and Servicing Specifications The Town of Groton of Public Works Department is requesting bids to provide manufacturers recommended maintenance, repairs and emergency service

More information

STORAGE, INSTALLATION AND MAINTENANCE PROCEDURES

STORAGE, INSTALLATION AND MAINTENANCE PROCEDURES GATE VALVE O.S. & Y 1.0 Periodic Inspections 1.1 The valve stem packing should be inspected at least monthly. If the stem packing shows signs of leakage, simply tighten the adjusting nuts to compress the

More information

Factory owners must ensure the boiler is:

Factory owners must ensure the boiler is: Factory owners must ensure the boiler is: * Registered with the Boilers and Pressure Vessels Division, Labour Department * Examined by an appointed examiner and has a valid certificate of fitness * Supervised

More information

BEST PRACTICES IN LEAK DETECTION AND REPAIR (LDAR) PROGRAMS. November 06, 2014 By: François Thibodeau, Eng.

BEST PRACTICES IN LEAK DETECTION AND REPAIR (LDAR) PROGRAMS. November 06, 2014 By: François Thibodeau, Eng. BEST PRACTICES IN LEAK DETECTION AND REPAIR (LDAR) PROGRAMS November 06, 2014 By: François Thibodeau, Eng. 2 PRESENTATION OVERVIEW 1. Essential Components of a LDAR Program 2. LDAR Best Practices a. A

More information

Heating Water by Direct Steam Injection

Heating Water by Direct Steam Injection Heating Water by Direct Steam Injection Producing hot water by direct steam injection provides a solution where large volumes of hot water at precise temperatures are required, and where energy and space

More information

Standard Pneumatic Test Procedure Requirements for Piping Systems

Standard Pneumatic Test Procedure Requirements for Piping Systems the pressure equipment safety authority Standard Pneumatic Test Procedure Requirements for Piping Systems AB-522 Edition 2, Rev. 0 Issued 2012-06-28 Table of Contents FOREWORD... 3 1.0 INTRODUCTION...

More information

Recharge Procedure for Telemark TVP-2000 and TVP-3500

Recharge Procedure for Telemark TVP-2000 and TVP-3500 Recharge Procedure for Telemark TVP-2000 and TVP-3500 Required items: 1.) Refrigeration service manifold. 2.) Charge recovery system. 3.) Dry nitrogen gas. If a high pressure cylinder is used, a pressure

More information

81000 Series Aluminum Gate Valve Installation and Repair Manual

81000 Series Aluminum Gate Valve Installation and Repair Manual High Vacuum Valves Leader in Quality and Value 81000 Series Aluminum Gate Valve Installation and Repair Manual Dear Customer, Thank you for choosing HVA as your vacuum valve supplier. Your valve will give

More information

http://waterheatertimer.org/troubleshoot-rheem-tankless-water-heater.html

http://waterheatertimer.org/troubleshoot-rheem-tankless-water-heater.html http://waterheatertimer.org/troubleshoot-rheem-tankless-water-heater.html TECHNICAL SERVICE DEPARTMENT Removal, Cleaning, & Reinstallation of the Burner Assembly For models 74 & GT199 Required tools -

More information

SAFETY - LIFE SAVING RULES MECHANICAL ISOLATION CAT A-1 SOP #3

SAFETY - LIFE SAVING RULES MECHANICAL ISOLATION CAT A-1 SOP #3 SUNCOR ENERGY PRODUCTS DISTRIBUTION TERMINAL OPERATING MANUAL STANDARD OPERATING PROCEDURE SAFETY - LIFE SAVING RULES Verify isolations of hazardous energy before any work begins. Date Issued: February

More information

Diesel Fuel Systems. Injection Nozzles

Diesel Fuel Systems. Injection Nozzles Diesel Fuel Systems Injection Nozzles Unit Terms Injection nozzle Nozzle, nozzle holder, valve, spring assembly Nozzle assembly Valve, body, and spray valve Orifice Small hole Pintle Valve which the end

More information