PBGC - Risk Management Early Warning / Legal Matter

Size: px
Start display at page:

Download "PBGC - Risk Management Early Warning / Legal Matter"

Transcription

1 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter PBGC - Risk Early Warning / Legal Matter [redacted] Agency: 12 Exhibit 3: Capital Asset Plan Case Summary Part I: Summary Information And Justification Section A: Overview 1. Date submission: Dec 28, Agency: Bureau: Name this Capital Asset: PBGC - Risk Early Warning / Legal Matter 5. Unique Project (Investment) Identifier: What kind investment will this be in FY29? Mixed Life Cycle 7. What was the first budget year this investment was submitted to OMB? FY26 8. Provide a brief summary justification for this investment, including a brief description how this closes in part or in whole an identified agency performance gap: Two departments within PBGC support the strategic corporate goal safeguarding the system through 1) early identification risks 2) proper mitigation those risks through legal action, settlement, or termination. The Department Insurance Supervision Compliance (DISC) the Office Chief Counsel (OCC). The departments suffered from a performance gap due to years uncoordinated management the use separate management information systems containing redundant inconsistent information. DISC uses a Lotus Notes application named CHAMPS OCC uses a matter management system named LEGAL EDGE (LEW). Neither system complies with enterprise architecture guidelines or is properly maintained. In 24 a steering committee was established to address the performance gap. The committee identified the need for an integrated system to manage case information, documents, work flow that complies with PBGC s enterprise architecture uses a commercial f-the-shelf (COTS) product. The system will comply with all information security privacy act requirements will facilitate information flow between PBGC, the Department Labor (DOL), the Internal Revenue (IRS), the Employee Benefits Administration (EBSA), as DISC needs to coordinate frequently with those agencies on open, active cases. The system, once implemented, used as a pilot program for use in other departments within PBGC such as the Multi-employer Program Division the Stard Termination Compliance Division. Funds for this effort ($4.9 million) were allocated in 26. Planning efforts were completed in 26 to support the executive steering committee decision to pursue a single solution. In 27, efforts to finalize the process reengineering effort as well as the functional technical system requirements completed. Because the time required to engage in a fully competitive acquisition process, the request for proposal for the COTS stware integrator issued in 27 but may t be successfully awarded until FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page 1 26 Pages

2 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter 28. At that time, DISC OCC will spend the remainder the budgeted funds to employ the COTS integrator to configure, test, document, deploy the system in 28. By budget year 29, the project in operations maintenance. The system is fully on track within budget as the end Did the Agency's Executive/Investment Committee approve this request? a. If "," what was the date this approval? Jun 29, Did the Project Manager review this Exhibit? 11. Contact information Project Manager? Name Jennifer Messina Phone Number [redacted] messina.jennifer@pbgc.gov a. What is the current FAC-P/PM certification level the project/program manager? TBD 12. Has the agency developed /or promoted cost effective, energyefficient environmentally sustainable techniques or practices for this project. a. Will this investment include electronic assets (including computers)? b. Is this investment for new construction or major retrit a Federal building or facility? (answer applicable to n-it assets only) 1. If "," is an ESPC or UESC being used to help fund this investment? 2. If "," will this investment meet sustainable design principles? 3. If "," is it designed to be 3% more energy efficient than relevant code? 13. Does this investment directly support one the PMA initiatives? Budget Performance Integration a. Briefly specifically describe for each selected how this asset directly supports the identified initiative(s)? This asset supports Budget Performance Integration by solving a performance gap in strategic goal #1. By more quickly identifying sponsor corporate transactions that increase PBGC s exposure to financial loss, PBGC improves its ability to negotiate for protection reduces the risk loss. Streamlining communication modernizing case files eliminates the need for manual processes frees up more resources to monitor companies that sponsor large s. 14. Does this investment support a program assessed using the Program Assessment Rating Tool (PART)? (For more information about the PART, visit a. If "," does this investment address a weakness found during a PART review? b. If "," what is the name the PARTed program? Pension Benefit Guaranty Corporation c. If "," what rating did the PART receive? Moderately Effective 15. Is this investment for information techlogy? For information techlogy investments only: 16. What is the level the IT Project? (per CIO Council PM Guidance) Level 2 FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page 2 26 Pages

3 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter 17. What project management qualifications does the Project Manager have? (per CIO Council PM Guidance) (1) Project manager has been validated as qualified for this investment 18. Is this investment or any project(s) within this investment identified as "high risk" on the Q4-FY 27 agency high risk report (per OMB Memorum M-5-23)? 19. Is this a financial management system? a. If "," does this investment address a FFMIA compliance area? 1. If "," which compliance area: 2. If "," what does it address? b. If "," please identify the system name(s) system acronym(s) as reported in the most recent financial systems inventory update required by Circular A-11 section What is the percentage breakout for the total FY29 funding request for the following? Hardware 5 Stware 25 s 7 Other 21. If this project produces information dissemination products for the public, are these products published to the Internet in conformance with OMB Memorum 5-4 included in your agency inventory, schedules priorities? n/a 22. Contact information individual responsible for privacy related questions: Name Philip Hertz Phone Number [redacted] Title Deputy General Counsel/Chief Privacy Officer hertz.philip@pbgc.gov 23. Are the records produced by this investment appropriately scheduled with the National Archives Records Administration's approval? 24. Does this investment directly support one the GAO High Risk Areas? Section B: Summary Spending 1. Table 1: SUMMARY OF SPENDING FOR PROJECT PHASES (REPORTED IN MILLIONS) (Estimates for BY+1 beyond are for ning purposes only do t represent budget decisions) PY-1 earlier PY 27 CY 28 BY 29 BY+1 21 BY BY BY+4 beyond Total Planning: Acquisition: Subtotal Planning FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page 3 26 Pages

4 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Table 1: SUMMARY OF SPENDING FOR PROJECT PHASES (REPORTED IN MILLIONS) (Estimates for BY+1 beyond are for ning purposes only do t represent budget decisions) & Acquisition: Operations & Maintenance: PY-1 earlier PY 27 CY 28 BY 29 BY+1 21 BY BY BY+4 beyond Total TOTAL: Government FTE Costs should t be included in the amounts provided above. Government FTE Costs Number FTE represented by Costs: Will this project require the agency to hire additional FTE's? a. If "", How many in what year? 3. If the summary spending has changed from the FY28 President's budget request, briefly explain those changes: In the FY 28 request, two projects/systems were proposed to address the same performance gap, a Risk Early Warning System as well as a separate Legal Matter System. As a result the executive steering committee decision regarding the best way to address the performance gap, the projects/systems were combined into one project/system, as indicated in the project background justification. The only way the project was affected was through schedule, t cost. The efficiencies gained by consolidated projects enabled the teams to conduct an assessment rework the baseline schedule without adding cost. The project is still on target for completion by 29 within budget. Section C: Acquisition/Contract Strategy 1. Contract or Task Order Number Type Contract/Task Order Has the contract been awarded If so what is the date the award? If t, what is the ned award date? Contracts/Task Orders Table: PBGC-1-CT Time & Materials Oct 15, 25 Start date Contract/Task Order Oct 15, 25 End date Contract/Task Order Jun 29 Total Value Contract/ Task Order ($M) Is this an Interagency Acquisition? Is it performance based? Competitively awarded? 1.4 FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page 4 26 Pages

5 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter What, if any, alternative financing option is being used? Is EVM in the contract? Does the contract include the required security & privacy clauses? Name CO CO Contact information Contracts/Task Orders Table: NA Michele Gray gray.michele@pbgc.gov Contracting Officer Certification Level 3 If N/A, has the agency determined the CO assigned has the competencies skills necessary to support this acquisition? Contract or Task Order Number Type Contract/Task Order Has the contract been awarded If so what is the date the award? If t, what is the ned award date? PBGC-1-DO-6 Time & Materials Jul 23, 26 Start date Contract/Task Order Jul 23, 26 End date Contract/Task Order 28 Total Value Contract/ Task Order ($M) Is this an Interagency Acquisition? Is it performance based? Competitively awarded? What, if any, alternative financing option is being used? Is EVM in the contract? Does the contract include the required security & privacy clauses? Name CO CO Contact information 1.2 NA Michele Gray gray.michele@pbgc.gov Contracting Officer Certification Level 3 If N/A, has the agency determined the CO assigned has the competencies skills necessary to support this acquisition? Contract or Task Order Number Type Contract/Task Order Has the contract been awarded If so what is the date the award? If t, what is the ned award date? PBGC Fixed Price Oct 28 Start date Contract/Task Order Oct 28 End date Contract/Task Order 29 Total Value Contract/ Task Order ($M) Is this an Interagency Acquisition? Is it performance based? Competitively awarded? What, if any, alternative financing [redacted] NA FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page 5 26 Pages

6 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter option is being used? Is EVM in the contract? Does the contract include the required security & privacy clauses? Name CO CO Contact information Contracts/Task Orders Table: Kay Rison Rison.kay@pbgc.gov Contracting Officer Certification Level 3 If N/A, has the agency determined the CO assigned has the competencies skills necessary to support this acquisition? Contract or Task Order Number Type Contract/Task Order Has the contract been awarded If so what is the date the award? If t, what is the ned award date? PBGC Fixed Price Oct 1, 29 Start date Contract/Task Order Oct 1, 29 End date Contract/Task Order 213 Total Value Contract/ Task Order ($M) Is this an Interagency Acquisition? Is it performance based? Competitively awarded? What, if any, alternative financing option is being used? Is EVM in the contract? Does the contract include the required security & privacy clauses? Name CO CO Contact information [redacted] NA Kay Rison Rison.kay@pbgc.gov Contracting Officer Certification Level 3 If N/A, has the agency determined the CO assigned has the competencies skills necessary to support this acquisition? 2. If earned value is t required or will t be a contract requirement for any the contracts or task orders above, explain why: EVM was t required for Contract #1 or 2 but the contractors were required to create project s weekly status reports to communicate cost, schedule, performance outcomes to the project manager. The project manager then reviewed the actual cost, schedule performance against the project issued guidance to the contractors as needed to keep the efforts deliverables on schedule. 3. Do the contracts ensure Section 58 compliance? a. Explain why: Section 58 compliance is a matory requirement for the procurement this COTS-based system. The technical requirements require the stware vendor to provide evidence that the stware complies with Section 58 the Rehabilitation Act, as detailed in 36 CFR 1194, Subpart B as well as a requirement that the FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page 6 26 Pages

7 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter contractor test s include testing assurance for Section 58 compliance. Failure to meet this requirement grounds for invalidating the proposal. 4. Is there an acquisition which has been approved in accordance with agency requirements? a. If "," what is the date? Oct 15, 26 b. If "," will an acquisition be developed? 1. If "," briefly explain why: Section D: Performance Information Fiscal Year Strategic Goal(s) Supported Area Mission Mission Customer Performance Information Table Grouping Timeliness Indicator Number settlements reached to mitigate risk increased under funding Days between lien arising perfection shortening indicates is secured ultimate recovery is maximized Days to respond to minimum funding waiver applications for IRS Baseline 3 settlement agreements 6 days 12 days Target Actual +2 settlement agreements (as a result the 32 (as business 8/1/7) process reengineering effort completed in 27) -5 days (as a result the business process 55 (as reengineering 8/1/7) effort completed in 27) -1 days (as a result the business 11 (as process reengineering 8/1/7) effort completed in 27) 27 Processes Cycle Time Days to 9 days -3 days (as 6 (as FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page 7 26 Pages

8 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Fiscal Year Strategic Goal(s) Supported Area Activities Techlogy Mission Mission Customer Performance Information Table Grouping Reliability Timeliness Indicator engage sponsor after a transaction reduction improves negotiating power to secure additional funding for the Number errors found in financial statement audit Number settlements reached to mitigate risk increased under funding Days between lien arising perfection shortening indicates is secured ultimate recovery is maximized Days to respond to minimum funding waiver applications for IRS Baseline 1 error end FY27 end FY27 end FY27 Target Actual a result 8/1/7) the business process reengineering effort completed in 27) -1 errors (as a result the business process (as reengineering 8/1/7) effort completed in 27) +5 settlement agreements (as a result the business process 9/3/8 reengineering effort the system deployment) -5 days (as a result the business process reengineering effort the 9/3/8 system deployment) -2 days (as a result the business process reengineering 9/3/8 effort the FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page 8 26 Pages

9 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Fiscal Year Strategic Goal(s) Supported Area Processes Activities Techlogy Mission Mission Performance Information Table Grouping Cycle Time Reliability Indicator Days to engage sponsor after a transaction reduction improves negotiating power to secure additional funding for the Number errors found in financial statement audit maintaining a zero is the optimal goal Number settlements reached to mitigate risk increased under funding Days between lien arising perfection shortening indicates is secured ultimate recovery is maximized Baseline end FY27 end FY27 TBD a the end FY28 TBD a the end FY28 Target system deployment) Actual -5 days (as a result the business process reengineering effort the 9/3/8 system deployment) errors (as a result the business process reengineering effort the 9/3/8 system deployment) +15 settlement agreements (as a result the business process 9/3/9 reengineering effort the system deployment) -15 days (as a result the business process reengineering effort the 9/3/9 system deployment) FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page 9 26 Pages

10 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Fiscal Year Strategic Goal(s) Supported Area Customer Processes Activities Techlogy Mission Mission Performance Information Table Grouping Timeliness Cycle Time Reliability Indicator Days to respond to minimum funding waiver applications for IRS Days to engage sponsor after a transaction reduction improves negotiating power to secure additional funding for the Number errors found in financial statement audit maintaining a zero is the optimal goal Number settlements reached to mitigate risk increased under funding Days between lien arising perfection Baseline TBD a the end FY28 TBD a the end FY28 TBD a the end FY28 end FY29 end FY29 Target Actual -15 days (as a result the business process reengineering effort the 9/3/9 system deployment) -15 days (as a result the business process reengineering effort the 9/3/9 system deployment) errors (as a result the business process reengineering effort the 9/3/9 system deployment) +5 settlement agreements -5 days 9/3/1 FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page 1 26 Pages

11 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Fiscal Year Strategic Goal(s) Supported Area Customer Processes Activities Techlogy Mission Performance Information Table Grouping Timeliness Cycle Time Reliability Indicator shortening indicates is secured ultimate recovery is maximized Days to respond to minimum funding waiver applications for IRS Days to engage sponsor after a transaction reduction improves negotiating power to secure additional funding for the Number errors found in financial statement audit maintaining a zero is the optimal goal Number settlements reached to mitigate risk increased under funding Baseline end FY29 end FY29 end FY29 end FY21 Target -15 days -5 days errors +5 settlement agreements Actual 9/3/1 9/3/1 9/3/1 9/3/1 9/3/11 FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

12 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Fiscal Year Strategic Goal(s) Supported Area Mission Customer Processes Activities Techlogy Performance Information Table Grouping Timeliness Cycle Time Reliability Indicator Days between lien arising perfection Days to respond to minimum funding waiver applications for IRS Days to engage sponsor after a transaction reduction improves negotiating power to secure additional funding for the Number errors found in financial statement audit maintaining a zero is the optimal goal Baseline end FY21 end FY21 end FY21 end FY21 Target -5 days days -5 days errors Actual 9/3/11 9/3/11 9/3/11 9/3/11 FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

13 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Fiscal Year Strategic Goal(s) Supported Area Mission Mission Customer Processes Activities Techlogy Performance Information Table Grouping Timeliness Cycle Time Reliability Indicator Number settlements reached to mitigate risk increased under funding Days between lien arising perfection shortening indicates is secured ultimate recovery is maximized Days to respond to minimum funding waiver applications for IRS Days to engage sponsor after a transaction reduction improves negotiating power to secure additional funding for the Number errors found in financial statement audit Baseline TBD a the end FY211 TBD a the end FY211 TBD a the end FY211 TBD a the end FY211 TBD a the end FY211 Target +5 settlement agreements -5 days days days errors Actual 9/3/12 9/3/12 9/3/12 9/3/12 9/3/12 FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

14 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Fiscal Year Strategic Goal(s) Supported Area Mission Mission Customer Processes Activities Performance Information Table Grouping Timeliness Cycle Time Indicator maintaining a zero is the optimal goal Number settlements reached to mitigate risk increased under funding Days between lien arising perfection shortening indicates is secured ultimate recovery is maximized Days to respond to minimum funding waiver applications for IRS Days to engage sponsor after a transaction reduction improves negotiating power to secure additional Baseline end FY212 end FY212 end FY212 end FY212 Target settlement agreements -5 days days days Actual 9/3/13 9/3/13 9/3/13 9/3/13 FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

15 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Fiscal Year 213 Strategic Goal(s) Supported Area Techlogy Performance Information Table Grouping Reliability Indicator funding for the Number errors found in financial statement audit maintaining a zero is the optimal goal Baseline end FY212 Target errors Actual 9/3/13 Section E: Security Privacy 1. Have the IT security costs for the system(s) been identified integrated into the overall costs the investment: a. If "," provide the "Percentage IT Security" for the budget year: 7 2. Is identifying assessing security privacy risks a part the overall risk management effort for each system supporting or part this investment. 3. Systems in Planning Undergoing Enhancement(s), Development, /or Modernization - Security Table(s): Name System Risk Early Warning / Legal Matter System Agency/ or Contractor Operated System? Planned Operational Date Date Planned C&A update (for existing mixed life cycle systems) or Planned Completion Date (for new systems) Government Only Name System Legal Edge for Windows Agency/ or Contractor Operated System? Government Only Champs Government Only NIST FIPS 199 Risk Impact level Moderate Moderate 4. Operational Systems - Security Table: Has C&A been Completed, using NIST 8-37? Date Completed: C&A Dec 15, 23 Nov 27 What stards were used for the Security Controls tests? FIPS 2 / NIST 8-53 FIPS 2 / NIST 8-53 Date Completed: Security Control Testing Date the contingency tested Jul 5, 27 Aug 11, 27 Jul 5, 27 Aug 11, 27 FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

16 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter 5. Have any weaknesses, t yet remediated, related to any the systems part or supporting this investment been identified by the agency or IG? a. If "," have those weaknesses been incorporated into the agency's action milestone process? 6. Indicate whether an increase in IT security funding is requested to remediate IT security weaknesses? a. If "," specify the amount, provide a general description the weakness, explain how the funding request will remediate the weakness. Note: PBGC is t requesting additional funding. PBGC implemented new NIST compliant security policies procedures June 1, 27 that are based upon the Department Labor s, modified slightly to meet PBGC s operating environment. The new policies procedures include those for conducting a FIPS 199 inventory assessment performing NIST 8-37 certification accreditation (C&A). Following publication, PBGC developed a FIPS 199 inventory systems, completed June 27. As a result, CHAMPS was elevated to moderate from low, w requires an independent C&A. The previous C&A for Legal Edge for Windows was rejected by PBGC s independent auditors as n NIST 8-37 compliant. Legal Edge for Windows is scheduled to undergo a compliant C&A starting October 1, 27 to be completed January 31, 28. CHAMPS is scheduled to undergo C&A starting tember 1, 27 to be completed November 27. PBGC completed testing security controls July 7, 27. Deficiencies identified have been incorporated into the comprehensive POA&M for addressing the security deficiencies. PBGC is funding improvement actions to correct the weaknesses through existing budgets. This business case requests seven percent for security. With the implementation new functionality, additional security controls required. The funding request for security used to conduct annual risk assessments, update system security s, perform C&As, establish continuous monitoring perform the function continuous monitoring associated with the new functionality. 7. How are contractor security procedures monitored, verified, validated by the agency for the contractor systems above? All PBGC systems are jointly run managed by federal employees contractor teams reporting to PBGC federal employees. PBGC contracts include language to ensure the suitability contractors employees, inspection all new or revated contractor hosting sites. PBGC federal employees contractors are subject to suitability background investigations. New federal employees contractors are issued roles conduct, required to take computer security awareness orientation, provided instruction on incident reporting procedures. Annually, federal employees contractors are required to take refresher security awareness training. Role-based training is conducted during employee position training. For positions related to the Designated Approving Authority, Information System Owner, System Administrators Project Managers, role-based training is conducted by PBGC s Enterprise Security Team following orientation, annually thereafter. Electronic security compliance is monitored by the OIT security team through routine checking user ID account activity for suspicious or highrisk behavior. If such behavior is identified, the contracting ficer is FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

17 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter tified immediately to begin remediation procedures. PBGC also conducts user account recertification annually. Name System Risk Early Warning / Legal Matter System 8. Planning & Operational Systems - Privacy Table: Is this a new system? Is there a Privacy Impact Assessment (PIA) that covers this system? Champs Legal Edge for Windows (LEW) Internet Link or Exation The system does t contain, process, or transmit personal identifying information The system does t contain, process, or transmit personal identifying information The system does t contain, process, or transmit personal identifying information Is a System Records Notice (SORN) required for this system? Internet Link or Exation The system is t a Privacy Act System Records The system is t a Privacy Act System Records The system is t a Privacy Act System Records Section F: Enterprise Architecture (EA) 1. Is this investment included in your agency's target enterprise architecture? a. If "," please explain why? 2. Is this investment included in the agency's EA Transition Strategy? a. If "," provide the investment name as identified in the Transition Strategy provided in the agency's most recent annual EA Assessment. Risk Early Warning / Legal Matter System b. If "," please explain why? 3. Is this investment identified in a completed (contains a target architecture) approved segmennt architecture? a. If "," provide the name the segment architecture as provided in the agency's most recent annual EA Assessment. Plan Agency Component Name RISK AND LEGAL MATTER MANAGEMENT (CHAMPS/RMEWS- 4. Component Reference Model (SRM) Table : Agency Component Description Financial actuarial management FEA SRM Type Component Reused FEA SRM Component Component Name Investment Performance UPI Internal or External Reuse? No Reuse BY Funding Percentage 1 FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

18 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Agency Component Name LMMS) RISK AND LEGAL MATTER MANAGEMENT (CHAMPS/RMEWS- LMMS) RISK AND LEGAL MATTER MANAGEMENT (CHAMPS/RMEWS- LMMS) PARTICIPANT SERVICES (FILENET/CMS) CONSOLIDATED FINANCIAL SERVICES 4. Component Reference Model (SRM) Table : Agency Component Description risk identification valuation Financial actuarial management risk identification valuation Imaging Processing System for document storage retrieval Case Administration for terminations Premium payer tracking insured inventory management FEA SRM Type Tracking Workflow Component Reused FEA SRM Component Component Name Case Document Document Imaging OCR Tracking Workflow Tracking Workflow Case Portfolio Data Exchange Data Exchange UPI Internal or External Reuse? No Reuse No Reuse BY Funding Percentage 4 4 Internal 5 Internal 5 FEA SRM Component Performance Performance Performance Performance Performance FEA TRM Area Access Delivery Access Delivery Access Delivery Access Delivery Platform Infrastructure 5. Technical Reference Model (TRM) Table: FEA TRM Category Access Channels Delivery Channels Requirements Requirements Support Platforms FEA TRM Stard Web Browser Intranet Legislative / Compliance Authentication / Single Sign-on Platform Independent Specification COTS to be procured (RMEW- LMMS) will support PBGC browser stards (IE) COTS to be procured (RMEW- LMMS) will support PBGC EA stards from the Blueprint All PBGC privacy security web stards, in the case this web based stware this includes 58, Records P3P PBGC CSS/GSS stards COTS to be procured (RMEW- LMMS) will support PBGC EA stards from the Blueprint ex. J2EE, Linux Oracle Performance Platform Delivery Application COTS to be procured (RMEW- FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

19 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter FEA SRM Component Performance Performance Case Case Case Case Case Case Case Case Document Imaging OCR Document Imaging OCR Document Imaging OCR Document Imaging OCR FEA TRM Area Infrastructure Platform Infrastructure Interface Integration Access Delivery Access Delivery Access Delivery Access Delivery Platform Infrastructure Platform Infrastructure Platform Infrastructure Interface Integration Access Delivery Access Delivery Access Delivery Access Delivery 5. Technical Reference Model (TRM) Table: FEA TRM Category FEA TRM Stard Specification Servers Servers LMMS) will support PBGC EA stards from the Blueprint ex Oracle Application Server (OC4J) Database / Storage Interface Access Channels Delivery Channels Requirements Requirements Support Platforms Delivery Servers Database / Storage Interface Access Channels Delivery Channels Requirements Requirements Database Description / Interface Web Browser Intranet Legislative / Compliance Authentication / Single Sign-on Platform Independent Application Servers Database Description / Interface Web Browser Intranet Legislative / Compliance Authentication / Single Sign-on Oracle RDMS (current PBGC supported versions) EA Blueprint stards concerning Oriented Architecture COTS to be procured (RMEW- LMMS) will support PBGC browser stards (IE) COTS to be procured (RMEW- LMMS) will support PBGC EA stards from the Blueprint. All PBGC privacy security web stards, in the case this web based stware this includes 58, Records P3P PBGC CSS/GSS stards COTS to be procured (RMEW- LMMS) will support PBGC EA stards from the Blueprint ex. J2EE, Linux Oracle COTS to be procured (RMEW- LMMS) will support PBGC EA stards from the Blueprint ex Oracle Application Server (OC4J) Oracle RDMS (current PBGC supported versions) EA Blueprint stards concerning Oriented Architecture COTS to be procured (RMEW- LMMS) will support PBGC browser stards (IE) COTS to be procured (RMEW- LMMS) will support PBGC EA stards from the Blueprint. All PBGC privacy security web stards, in the case this web based stware this includes 58, Records P3P PBGC CSS/GSS stards FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

20 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter FEA SRM Component Document Imaging OCR Document Imaging OCR Document Imaging OCR Document Imaging OCR Case Case Portfolio Portfolio FEA TRM Area Platform Infrastructure Platform Infrastructure Platform Infrastructure Interface Integration Component Framework Component Framework Component Framework Component Framework 5. Technical Reference Model (TRM) Table: FEA TRM Category Support Platforms Delivery Servers Database / Storage Interface Data Interchange Data Data Interchange Data FEA TRM Stard Platform Independent Application Servers Database Description / Interface Data Exchange Database Connectivity Data Exchange Database Connectivity Specification COTS to be procured (RMEW- LMMS) will support PBGC EA stards from the Blueprint ex. J2EE, Linux Oracle COTS to be procured (RMEW- LMMS) will support PBGC EA stards from the Blueprint ex Oracle Application Server (OC4J) Oracle RDMS (current PBGC supported versions) EA Blueprint stards concerning Oriented Architecture XML/SOAP JDBC/ADO.NET XML/SOAP JDBC/ADO.NET 6. Will the application leverage existing components /or applications across the Government (i.e., FirstGov, Pay.Gov, etc)? a. If "," please describe. Part II: Planning, Acquisition And Performance Information Section A: Alternatives Analysis 1. Did you conduct an alternatives analysis for this project? a. If "," provide the date the analysis was completed? Apr 22, 25 b. If "," what is the anticipated date this analysis completed? c. If analysis is ned, please briefly explain why: Alternative Analyzed Status Quo 2. Alternatives Analysis : Description Alternative Use Champs for DISC LEW for OCC. The use current systems is fragmented does t enable the participants in the case team to share the same Risk Adjusted Lifecycle Costs estimate Risk Adjusted Lifecycle Benefits estimate 7 1 FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page 2 26 Pages

21 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Alternative Analyzed Alternative #1 (COTS) Alternative #2 (Custom Build) Alternative #3 (Modified Legacy) 2. Alternatives Analysis : Description Alternative information in an electronic matter or establish track due dates work flow tasks. Use COTS to create an integrated case management, document management workflow management tool to integrate DISC OCC operations information. The primary benefit this investment is a net improvement in the total dollars negotiated in settlements risk mitigation which represents a real increase in the funds to PBGC to pay benefits. The net present value this alternative is $38.5 million. Custom build an integrated case management, document management workflow management tool to integrate DISC OCC operations information. Effort includes developing, testing, deploying the new system. The primary benefit this investment is a net improvement in the total dollars negotiated in settlements, which represents a real increase in the funds to PBGC to pay benefits. The net present value this alternative is $24. million. Conversion all OCC users to CHAMPS (from LEW). The primary benefit this investment is a net improvement in the total dollars negotiated in settlements, which represents a real increase in the funds to PBGC to pay benefits. The net present value this alternative is $5.2 million. Risk Adjusted Lifecycle Costs estimate Risk Adjusted Lifecycle Benefits estimate Which alternative was selected by the Agency's Executive/Investment Committee why was it chosen? Alternative #1 was chosen, both for its lower estimated cost its highest net present value. DISC OCC also place great value on the use COTS because it enables the agency to implement the necessary functions much sooner, thereby speeding up benefit realization. COTS can also be more easily reused by other departments within PBGC or similar functions at other agencies like DOL or EBSA. The COTS-based solution involves a business process reengineering effort to integrate streamline the processes both DISC OCC. Rather than having to create detailed requirements as would be required for a custombuilt system, functional requirements can be used because much the functionality required is already in the COTS product, it just needs to be configured to meet the specific needs DISC OCC. This investment is envisioned to be reused as the workflow management, tracking, document management component in at least 3 other departments within PBGC, the Stard Termination Compliance Division, the Multi-employer Program Division the Office General Counsel. 4. What specific qualitative benefits realized? As w envisioned for the near-term, this investment will significantly improve communication workflow between the business units that are engaged in safeguarding the system. Because the system can be deployed faster by FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

22 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter using COTS than a custom-built solution, it will enable the two departments to realize benefits sooner. This is critical because the ecomic environment has required over the last two years continues to require rapid responses to corporate transactions in order to protect the assets from exposure to risk. This system will enable DISC OCC to share information, use a common data model to describe track the work that they do, give the managers in each business unit a much better organizational view priorities, allow more effective team assignments to be made by each. By increasing organizational capacity through workflow streamlining the reduction manual processes, DISC OCC able to more closely monitor a larger portion the entire insured inventory. By improving communication across DISC OCC analysts, attorneys managers by increasing the availability case histories analytical information, DISC OCC able to respond more quickly to high-risk transactions thereby increasing the amount protection that can be obtained for the, either through settlement agreement, 412(n) lien perfection, or letter credit. 5. Will the selected alternative replace a legacy system in-part or in-whole? a. If "," are the migration costs associated with the migration to the selected alternative included in this investment, the legacy investment, or in a separate migration investment? This Investment b. If "," please provide the following information: List Legacy Investment or Systems Name the Legacy Investment or Systems UPI if Date the System Retirement Champs 28 Legal Edge for Windows (LEW) 28 Section B: Risk 1. Does the investment have a Risk Plan? a. If "," what is the date the? Apr 27 b. Has the Risk Plan been significantly changed since last year's submission to OMB? c. If "," describe any significant changes: It s a new. The focuses on risks to cost, schedule, resources. The main risks identified in 27 are related to the unpredictability the procurement schedule, the quality the COTS integrator, the ability to negotiate price with the integrator. While this is a low probability risk because it was mitigated in advance by conducting thorough market research allocating budget appropriately, it is still a fundamental risk. [redacted] 2. If there currently is, will a be developed? a. If "," what is the ned completion date? b. If "," what is the strategy for managing the risks? 3. Briefly describe how investment risks are reflected in the life cycle cost estimate investment schedule: The largest risks to the investment typically impact either the schedule or executive approval (at many levels) thereby impact the cost the investment. The most apparent schedule risks are related to obtaining all the appropriate required sign fs (usually from outside department resources) on critical path deliverables, as FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

23 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter required by the IT solution life cycle methodology. Because these departments do t have an incentive to sign f according to our investment schedule, these signfs require significant advanced ning, communication management in order to ensure that sign fs happen on time with the proper review consideration. To mitigate this risk, we have included in the project, a key milestone for each deliverable the preparatory steps required to effectively communicate manage the signf each critical path deliverable. This additional project management component adds FTE costs to the schedule about 2% the overall contractor services costs. The value it provides by effectively mitigating much larger risks to the investment cost makes the additional steps cost a necessary element the budget schedule. Additionally, the investment's scope, schedule, cost are reviewed through the initiative's oversight governance procedures. In addition, the milestones reported to OMB through the OMB Dashboard Milestone reporting process. The tasks' scope completion are validated, the cost schedule are tracked using earned value management. Section B this Exhibit 3 included in the enterprise s actions milestones (POA&M). Section C: Cost Schedule Performance 1. Does the earned value management system meet the criteria in ANSI/EIA Stard - 748? 2. Is the CV% or SV% greater than ± 1%? (CV%= CV/EV x 1; SV%= SV/PV x 1) a. If "," was it the? b. If "," explain the causes the variance: c. If "," describe the corrective actions 3. Has the investment re-baselined during the past fiscal year? a. If "," when was it approved by the agency head? Description Milestone 1.1 RMEW-LMMS Market Research 1.2 As Is Process Model Defined 1.3 To Be Process Model Defined 4. Comparison Initial Baseline Current Approved Baseline: Initial Baseline Planned Completion Date Dec 25 Apr 27 May 27 Total Cost ($M) Estimated Current Baseline Completion Date Planned:Actual Nov 26 Apr 27 May 27 Nov 26 Apr 27 May 27 Total Cost ($M) Planned:Actual Current Baseline Variance Schedule:Cost (# days/$m) Percent Complete FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

24 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Description Milestone 1.4 Functional Technical Design Requirements Complete 1.5 Integrated Project Team Planning 2.1 Purchase Stware 2.2 Purchase Hardware 2.3 Design complete 2.4 Configure COTS 2.5 Testing Complete 2.6 Implement in Production 3.1 FY6 Steady State 3.2 FY7 Steady State 3.3 FY8 Steady State 3.4 FY9 Steady State 3.5 FY1 Steady State 3.6 FY11 Steady State 3.7 FY12 Steady State 4. Comparison Initial Baseline Current Approved Baseline: Initial Baseline Planned Completion Date Jun 27 Dec 31, 27 Oct 27 Oct 27 Feb 29, 28 Jun 28 Aug Total Cost ($M) Estimated Current Baseline Completion Date Planned:Actual Jun 27 Dec 31, 27 Oct 27 Oct 27 Feb 29, 28 Jun 28 Aug Jun Total Cost ($M) Planned:Actual Current Baseline Variance Schedule:Cost (# days/$m) Percent Complete FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

25 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Description Milestone 3.8 FY13 Steady State 4.1 FY6 Project 4.2 FY7 Project 4.3 FY8 Project 4.4 FY9 Project 4.5 FY1 Project 4.6 FY11 Project 4.7 FY12 Project 4.8 FY13 Project 5.1 FY8 C&A for RMEWS/LMMS LEW address security findings (CHAMPS is decommissioned) 5.2 FY9 Address security findings 5.3 FY1 Address security findings 5.4 FY11 Address security findings 5.5 FY12 Address security findings 4. Comparison Initial Baseline Current Approved Baseline: Initial Baseline Planned Completion Date Total Cost ($M) Estimated Current Baseline Completion Date Planned:Actual Total Cost ($M) Planned:Actual Current Baseline Variance Schedule:Cost (# days/$m) Percent Complete FY13 Address.1.1 FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

26 OMB Exhibit 3 Budget Year 29 PBGC - Risk Early Warning / Legal Matter Description Milestone 4. Comparison Initial Baseline Current Approved Baseline: Initial Baseline Planned Completion Date Total Cost ($M) Estimated security findings Current Baseline Completion Date Planned:Actual Total Cost ($M) Planned:Actual Current Baseline Variance Schedule:Cost (# days/$m) Percent Complete FY 29 Exhibit 3 PBGC - RMEWLMMS - redacted.doc Page Pages

How To Understand The System Of The Sec.Gov

How To Understand The System Of The Sec.Gov Core Financial Systems (CFS) Budget year: FY2009 Agency: 449 -------------------------------------------------------------------------------- Part I: Summary Information and Justification Section A: Overview

More information

PART ONE OVERVIEW. ESMD - Integrated Collaborative Environment

PART ONE OVERVIEW. ESMD - Integrated Collaborative Environment Exhibit 300 (BY2010) PART ONE OVERVIEW 1. Date of Submission: 2008-09-08 2. Agency: 026 3. Bureau: 00 4. Name of this Capital Asset: 5. Unique Project Identifier: ESMD - Integrated Collaborative Environment

More information

PBGC - Risk Management and Early Warning / Legal Management

PBGC - Risk Management and Early Warning / Legal Management PBGC - Risk and Early Warning / Legal Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary Information And Justification Section A: Overview 1. Date of submission: Sep 9, 2006 2. Agency:

More information

014-00-01-01-01-1146-00. Mixed Life Cycle FY2002

014-00-01-01-01-1146-00. Mixed Life Cycle FY2002 Consolidated American System (CAPPS) and Interagency e Migration Exhibit 300: Part I: Summary Information and Justification (All Capital Assets) I.A. Overview 1. Date of Submission: 2. Agency: Department

More information

Tuesday, May 12, 2009-12:05 PM Page 1 of 11

Tuesday, May 12, 2009-12:05 PM Page 1 of 11 Exhibit 300: NIST-wide Grant System (Revision 21) Exhibit 300: Capital Asset Plan Business Case Summary Part I: Summary And Justification (All Capital Assets) Section A: Overview (All Capital Assets) 1.

More information

9. Did the Agency's Executive/Investment Committee approve this request?

9. Did the Agency's Executive/Investment Committee approve this request? Electronic Medical Record (EMR) Exhibit 300: Part I: Summary and Justification (All Capital s) I.A. Overview 1. Date of Submission: 2. Agency: Department of State 3. Bureau: M/MED Medical Director 4. Name

More information

PART ONE OVERVIEW. JSC Space Shuttle Program Flight Software

PART ONE OVERVIEW. JSC Space Shuttle Program Flight Software Exhibit 300 (BY2009) PART ONE OVERVIEW 1. Date of Submission: 2007-09-07 2. Agency: 026 3. Bureau: 00 4. of this Capital Asset: 5. Unique Project Identifier: JSC Space Shuttle Program Flight Software 026-00-01-03-01-1418-00

More information

Exhibit 300: JMD Law Enforcement Wireless Communication (LEWC) (Revision 9)

Exhibit 300: JMD Law Enforcement Wireless Communication (LEWC) (Revision 9) Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary Information And Justification (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: 4/3/2009 2.

More information

Mixed Life Cycle FY2003

Mixed Life Cycle FY2003 FBI Computer Analysis Response Team Storage Area Network (CARTSAN) Exhibit 300: Part I: Summary Information and Justification (All Capital Assets) I.A. Overview 1. Date of Submission: 12/19/2006 2. Agency:

More information

MS Word Exhibit 300 for O&M (BY2008) (Form) / JSC Space Shuttle Program Flight Software (Item)

MS Word Exhibit 300 for O&M (BY2008) (Form) / JSC Space Shuttle Program Flight Software (Item) MS Word Exhibit 300 for O&M (BY2008) (Form) / JSC Space Shuttle Program Flight Software (Item) Form Report, printed by: System Administrator, Jan 31, 2007 OVERVIEW General Information 1. Date of Submission:

More information

Wednesday, May 13, 2009-3:56 PM Page 1 of 19

Wednesday, May 13, 2009-3:56 PM Page 1 of 19 Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary Information And Justification (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: 2. : Department

More information

Wednesday, April 15, 2009-8:22 AM Page 1 of 5

Wednesday, April 15, 2009-8:22 AM Page 1 of 5 I.A.: OVERVIEW BY10 Descriptive Information BY10 Template Name BY2010 Investment Name ETA - UI Database Management System (formerly UI ADP Support) Investment Revision Number 12 Is this investment a consolidated

More information

Exhibit 300: Exhibit 300 - Electronic Medical Record (EMR) (Revision 11) 4. Name of this Capital Asset: Exhibit 300 - Electronic Medical Record (EMR)

Exhibit 300: Exhibit 300 - Electronic Medical Record (EMR) (Revision 11) 4. Name of this Capital Asset: Exhibit 300 - Electronic Medical Record (EMR) Exhibit 300: Capital Asset Plan and Case Summary Part I: Summary Information And Justification (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: 4/10/2009 2. Agency:

More information

Wednesday, April 15, 2009-8:48 AM Page 1 of 5

Wednesday, April 15, 2009-8:48 AM Page 1 of 5 I.A.: OVERVIEW BY10 Descriptive Information BY10 Template Name BY2010 Investment Name ESA - OFCCP - Federal Contractor Compliance System Investment Revision Number 2 Is this investment a consolidated business

More information

ProSight Portfolios Report

ProSight Portfolios Report Page 1 of 18 VR&E Maintenance and Operations (non-bdn) - 2008 PART I - A PART I: SUMMARY INFORMATION AND JUSTIFICATION In Part I, complete Sections A. B, C, and D for all capital assets (IT and non-it).

More information

Exhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets)

Exhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets) Exhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: 09/08/2006 2.

More information

PART ONE OVERVIEW. JSC Space Shuttle Program Integration

PART ONE OVERVIEW. JSC Space Shuttle Program Integration Exhibit 300 (BY2010) PART ONE OVERVIEW 1. Date of Submission: 2008-09-08 2. Agency: 026 3. Bureau: 00 4. Name of this Capital Asset: 5. Unique Project Identifier: JSC Space Shuttle Program 026-00-01-05-01-1419-00

More information

Thursday, March 18, 2010-4:15 PM Page 1 of 9

Thursday, March 18, 2010-4:15 PM Page 1 of 9 Exhibit 300: Capital Asset Plan Business Case Summary Part I: Summary Information And Justification (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: 2. Agency: Department

More information

Tuesday, September 11, 2007-12:16 AM Page 1 of 6

Tuesday, September 11, 2007-12:16 AM Page 1 of 6 Exhibit 300: Exhibit 300 - Electronic Medical Record (EMR) (Revision 7) Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary And Justification (All Capital Assets) Section A: Overview

More information

Exhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets)

Exhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets) Exhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: 09/08/2007 2.

More information

Thursday, March 18, 2010-4:36 PM Page 1 of 16

Thursday, March 18, 2010-4:36 PM Page 1 of 16 Exhibit 300: OJP Community Partnership Grants Management System () Architecture Technology Refresh (Revision 11) Exhibit 300: Capital Asset Plan Business Case Summary Part I: Summary Inmation And Justification

More information

Tuesday, September 11, 2007-12:17 AM Page 1 of 8

Tuesday, September 11, 2007-12:17 AM Page 1 of 8 Exhibit 300: Capital Asset Plan and Case Summary Part I: Summary Information And Justification (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: 9/10/2007 2. Agency:

More information

Thursday, March 18, 2010-4:31 PM Page 1 of 10

Thursday, March 18, 2010-4:31 PM Page 1 of 10 Exhibit 300: JMD Law ment Wireless Communication (LEWC) (Revision 13) Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary Information And Justification (All Capital Assets) Section

More information

Exhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets)

Exhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets) Exhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: 09/08/2006 2.

More information

Exhibit 300: JMD Litigation Case Management System (LCMS) (Revision 3) 4. Name of this Capital Asset: JMD Litigation Case Management System (LCMS)

Exhibit 300: JMD Litigation Case Management System (LCMS) (Revision 3) 4. Name of this Capital Asset: JMD Litigation Case Management System (LCMS) Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary Information And Justification (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: 8/31/2007 2.

More information

CAPITAL ASSET PLAN AND BUSINESS CASE SUMMARY EXHIBIT 300

CAPITAL ASSET PLAN AND BUSINESS CASE SUMMARY EXHIBIT 300 Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary Information And Justification (All Capital Assets) Section A: Overview ( All Capital Assets) 1. Date of Submission: January 26,

More information

Thursday, March 18, 2010-4:09 PM Page 1 of 8

Thursday, March 18, 2010-4:09 PM Page 1 of 8 Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary Information And Justification (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: 12/2/2009 2.

More information

ProSight Portfolios Report

ProSight Portfolios Report Page 1 of 19 Patient Financial Services System (PFSS) - 2008 PART I - A PART I: SUMMARY INFORMATION AND JUSTIFICATION In Part I, complete Sections A. B, C, and D for all capital assets (IT and non-it).

More information

Capital Programming and Project Management Under the US Budget

Capital Programming and Project Management Under the US Budget CIRCULAR NO. A 11 PART 7 PLANNING, BUDGETING, ACQUISITION, AND MANAGEMENT OF CAPITAL ASSETS Executive Office of the President Office of Management and Budget June 2008 SECTION 300 PLANNING, BUDGETING,

More information

Exhibit 300: BOP Inmate Telephone System (TRUFONE) (Revision 10) 4. Name of this Capital Asset: BOP Inmate Telephone System (TRUFONE)

Exhibit 300: BOP Inmate Telephone System (TRUFONE) (Revision 10) 4. Name of this Capital Asset: BOP Inmate Telephone System (TRUFONE) Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary Information And Justification (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: 8/17/2007 2.

More information

Business Case Study - The Financial Information System (OIS)

Business Case Study - The Financial Information System (OIS) I.A.: OVERVIEW BY09 Descriptive Information BY09 Template Name BY2010 Investment Name OSHA - Information System (OIS) Investment Revision Number 19 Is this investment a consolidated business case? No Point

More information

Saturday, April 11, 2009-3:29 PM Page 1 of 13

Saturday, April 11, 2009-3:29 PM Page 1 of 13 Exhibit 300: Exhibit 300 - Integrated Personnel System (IPMS) (Revision 12) Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary Information And Justification (All Capital Assets)

More information

Thursday, March 18, 2010-4:04 PM Page 1 of 11

Thursday, March 18, 2010-4:04 PM Page 1 of 11 Exhibit 300: BOP Inmate Telephone (TRUFONE) (Revision 14) Exhibit 300: Capital Asset Plan Case Summary Part I: Summary Information And Justification (All Capital Assets) Section A: Overview (All Capital

More information

Total Cost of Ownership

Total Cost of Ownership Protecting America's Pensions Office of Information Technology IT Investment Owner's Guide to Total Cost of Ownership Version 1.0 Last Updated Date: January 25, 2011 Revision History Document Version Release

More information

Exhibit 300: JMD Unified Financial Management System (UFMS) (Revision 9)

Exhibit 300: JMD Unified Financial Management System (UFMS) (Revision 9) Exhibit 300: Unified System (UFMS) (Revision 9) Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary Information And Justification (All Capital Assets) Section A: Overview (All Capital

More information

Exhibit 300: Capital Asset Summary

Exhibit 300: Capital Asset Summary Exhibit 300: Capital Asset Summary Part I: Summary Information And Justification (All Capital Assets) Section A: Overview & Summary Information Date Investment First Submitted: 2012-09-12 Date of Last

More information

What Does the Government Want from Project Management? DC PMI Chapter Executive Breakfast Series January 16, 2008

What Does the Government Want from Project Management? DC PMI Chapter Executive Breakfast Series January 16, 2008 What Does the Government Want from Project Management? DC PMI Chapter Executive Breakfast Series January 16, 2008 The Government Wants from Project Management A project management process and culture in

More information

Exhibit 300 (BY2010) PART ONE OVERVIEW. 1. Date of Submission: 2008-09-08. 2. Agency: 026. 3. Bureau: 00. 4. Name of this Capital Asset:

Exhibit 300 (BY2010) PART ONE OVERVIEW. 1. Date of Submission: 2008-09-08. 2. Agency: 026. 3. Bureau: 00. 4. Name of this Capital Asset: Exhibit 300 (BY2010) PART ONE OVERVIEW 1. Date of Submission: 2008-09-08 2. Agency: 026 3. Bureau: 00 4. Name of this Capital Asset: 5. Unique Project Identifier: KSC Shuttle Processing 026-00-01-05-01-1425-00

More information

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION Treasury Inspector General for Tax Administration Federal Information Security Management Act Report October 27, 2009 Reference Number: 2010-20-004 This

More information

HARPER, RAINS, KNIGHT & COMPANY, P.A. CERTIFIED PUBLIC ACCOUNTANTS RIDGELAND, MISSISSIPPI

HARPER, RAINS, KNIGHT & COMPANY, P.A. CERTIFIED PUBLIC ACCOUNTANTS RIDGELAND, MISSISSIPPI FARM CREDIT ADMINISTRATION INDEPENDENT ACCOUNTANT S REPORT ON AGREED-UPON PROCEDURES: FEDERAL INFORMATION SECURITY MANAGEMENT ACT EVALUATION For the Year Ending September 30, 2005 HARPER, RAINS, KNIGHT

More information

Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary Information And Justification (All Capital Assets)

Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary Information And Justification (All Capital Assets) Exhibit 300: Capital Asset Plan and Business Case Summary Part I: Summary Information And Justification (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: February 9,

More information

United States Department of State Global Financial Management System (GFMS) Privacy Impact Assessment

United States Department of State Global Financial Management System (GFMS) Privacy Impact Assessment United States Department of State Global Financial Management System (GFMS) Privacy Impact Assessment CGFS/DCFO/GFMS 1. Contact Information Privacy Impact Assessment (PIA) Department of State Privacy Coordinator

More information

IT Baseline Management Policy. Table of Contents

IT Baseline Management Policy. Table of Contents Table of Contents 1. INTRODUCTION... 1 1.1 Purpose... 2 1.2 Scope and Applicability... 2 1.3 Compliance, Enforcement, and Exceptions... 3 1.4 Authority... 3 2. ROLES, RESPONSIBILITIES, AND GOVERNANCE...

More information

Guide to IT Capital Planning and Investment Control (CPIC)

Guide to IT Capital Planning and Investment Control (CPIC) U.S. Department of Energy Guide to IT Capital Planning and Investment Control (CPIC) September 2010 Office of the Chief Information Officer TABLE OF CONTENTS 1.0 Preface... 1 2.0 Introduction... 2 2.1

More information

Department of the Interior Privacy Impact Assessment

Department of the Interior Privacy Impact Assessment Department of the Interior August 15, 2014 Name of Project: email Enterprise Records and Document Management System (eerdms) Bureau: Office of the Secretary Project s Unique ID: Not Applicable A. CONTACT

More information

DIRECTIVE TRANSMITTAL

DIRECTIVE TRANSMITTAL U.S. NUCLEAR REGULATORY COMMISSION DIRECTIVE TRANSMITTAL TN: DT-07-08 To: Subject: Purpose: Office and Division of Origin: NRC Management Directives Custodians Transmittal of Management Directive 2.8,

More information

SLCM Framework (Version 2003.1) Roles and Responsibilities As of January 21, 2005

SLCM Framework (Version 2003.1) Roles and Responsibilities As of January 21, 2005 SLCM Framework (Version 2003.1) Roles and Responsibilities As of January 21, 2005 ROLE RESPONSIBILITY REVIEW SIGN- OFF CTO Manage IT assets to meet corporate goals Establish and chair the Information Technology

More information

Federal Segment Architecture Methodology (FSAM): An Overview

Federal Segment Architecture Methodology (FSAM): An Overview Information Resources Management College Federal Segment Architecture Methodology (FSAM): An Overview Dr. Stan Boddie & Prof. Matt Newman 1 a global learning community for government s most promising information

More information

EVALUATION REPORT. Weaknesses Identified During the FY 2014 Federal Information Security Management Act Review. March 13, 2015 REPORT NUMBER 15-07

EVALUATION REPORT. Weaknesses Identified During the FY 2014 Federal Information Security Management Act Review. March 13, 2015 REPORT NUMBER 15-07 EVALUATION REPORT Weaknesses Identified During the FY 2014 Federal Information Security Management Act Review March 13, 2015 REPORT NUMBER 15-07 EXECUTIVE SUMMARY Weaknesses Identified During the FY 2014

More information

AUDIT REPORT. The Energy Information Administration s Information Technology Program

AUDIT REPORT. The Energy Information Administration s Information Technology Program U.S. Department of Energy Office of Inspector General Office of Audits and Inspections AUDIT REPORT The Energy Information Administration s Information Technology Program DOE-OIG-16-04 November 2015 Department

More information

SENTINEL AUDIT V: STATUS OF

SENTINEL AUDIT V: STATUS OF SENTINEL AUDIT V: STATUS OF THE FEDERAL BUREAU OF INVESTIGATION S CASE MANAGEMENT SYSTEM U.S. Department of Justice Office of the Inspector General Audit Division Audit Report 10-03 November 2009 Redacted

More information

FISH AND WILDLIFE SERVICE INFORMATION RESOURCES MANAGEMENT. Chapter 7 Information Technology (IT) Security Program 270 FW 7 TABLE OF CONTENTS

FISH AND WILDLIFE SERVICE INFORMATION RESOURCES MANAGEMENT. Chapter 7 Information Technology (IT) Security Program 270 FW 7 TABLE OF CONTENTS TABLE OF CONTENTS General Topics Purpose and Authorities Roles and Responsibilities Policy and Program Waiver Process Contact Abbreviated Sections/Questions 7.1 What is the purpose of this chapter? 7.2

More information

Audit of Veterans Health Administration Blood Bank Modernization Project

Audit of Veterans Health Administration Blood Bank Modernization Project Department of Veterans Affairs Office of Inspector General Audit of Veterans Health Administration Blood Bank Modernization Project Report No. 06-03424-70 February 8, 2008 VA Office of Inspector General

More information

Review of the SEC s Systems Certification and Accreditation Process

Review of the SEC s Systems Certification and Accreditation Process Review of the SEC s Systems Certification and Accreditation Process March 27, 2013 Page i Should you have any questions regarding this report, please do not hesitate to contact me. We appreciate the courtesy

More information

Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report

Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report The Enterprise Program Investment Council (EPIC) is responsible for governance

More information

Office of Inspector General Pension Benefit Guaranty Corporation

Office of Inspector General Pension Benefit Guaranty Corporation Office of Inspector General Pension Benefit Guaranty Corporation RISK ADVISORY February 19, 2016 To: From: Subject: W. Thomas Reeder, Jr. Director Robert A. Westbrooks Inspector General Monitoring and

More information

Evaluation Report. Weaknesses Identified During the FY 2013 Federal Information Security Management Act Review. April 30, 2014 Report Number 14-12

Evaluation Report. Weaknesses Identified During the FY 2013 Federal Information Security Management Act Review. April 30, 2014 Report Number 14-12 Evaluation Report Weaknesses Identified During the FY 2013 Federal Information Security Management Act Review April 30, 2014 Report Number 14-12 U.S. Small Business Administration Office of Inspector General

More information

014-00-01-02-01-1177-00. Mixed Life Cycle. FY2001 or earlier

014-00-01-02-01-1177-00. Mixed Life Cycle. FY2001 or earlier Integrated Personnel System (IPMS) Exhibit 300: Part I: Summary Information and Justification (All Capital Assets) I.A. Overview 1. Date of Submission: 9/11/2006 2. Agency: Department of State 3. Bureau:

More information

Concept of Operations for Line of Business Initiatives

Concept of Operations for Line of Business Initiatives Concept of Operations for Line of Business Initiatives Version 1.0 Office of E-Gov and IT, OMB March 2006 Table of Contents FOREWORD...2 1 OBJECTIVES OF THE LINES OF BUSINESS CONCEPT OF OPERATIONS...3

More information

CMS Policy for Information Technology (IT) Investment Management & Governance

CMS Policy for Information Technology (IT) Investment Management & Governance Chief Information Officer Office of Information Services Centers for Medicare & Medicaid Services CMS Policy for Information Technology (IT) Investment Management & Governance May 17, 2007 Document Number:

More information

STATEMENT THOMAS P. MICHELLI CHIEF INFORMATION OFFICER U.S. IMMIGRATION AND CUSTOMS ENFORCEMENT DEPARTMENT OF HOMELAND SECURITY REGARDING A HEARING ON

STATEMENT THOMAS P. MICHELLI CHIEF INFORMATION OFFICER U.S. IMMIGRATION AND CUSTOMS ENFORCEMENT DEPARTMENT OF HOMELAND SECURITY REGARDING A HEARING ON STATEMENT OF THOMAS P. MICHELLI CHIEF INFORMATION OFFICER U.S. IMMIGRATION AND CUSTOMS ENFORCEMENT DEPARTMENT OF HOMELAND SECURITY REGARDING A HEARING ON EXAMINING CHALLENGES AND WASTED TAXPAYER DOLLARS

More information

Significant Revisions to OMB Circular A-127. Section Revision to A-127 Purpose of Revision Section 1. Purpose

Significant Revisions to OMB Circular A-127. Section Revision to A-127 Purpose of Revision Section 1. Purpose Significant Revisions to OMB Circular A-127 Section Revision to A-127 Purpose of Revision Section 1. Purpose Section 5. Definitions Section 6. Policy Section 7. Service Provider Requirements Section 8.

More information

Information Technology Processes FinCEN is an agency whose mission is dependent on the effective collection,

Information Technology Processes FinCEN is an agency whose mission is dependent on the effective collection, Appendix L Project Management and Information Technology Processes FinCEN is an agency whose mission is dependent on the effective collection, dissemination, and meaningful analysis of large quantities

More information

Migration Planning Guidance (Draft)

Migration Planning Guidance (Draft) Financial Management Line of Business Migration Planning Guidance (Draft) Section 1.1 Overview The purpose of the Migration Planning Guidance document is to help agencies prepare for, and manage, a migration

More information

The Council of the Inspectors General on Integrity and Efficiency s Cloud Computing Initiative

The Council of the Inspectors General on Integrity and Efficiency s Cloud Computing Initiative The Council of the Inspectors General on Integrity and Efficiency s Cloud Computing Initiative September 2014 Council of the Inspectors General on Integrity and Efficiency Cloud Computing Initiative Executive

More information

2008 FISMA Executive Summary Report

2008 FISMA Executive Summary Report 2008 FISMA Executive Summary Report PUBLIC REDACTED VERSION September 29, 2008 4B M E M O R A N D U M September 29, 2008 To: From: Lew Walker, Acting Chief Information Officer H. David Kotz, Inspector

More information

A. SYSTEM DESCRIPTION

A. SYSTEM DESCRIPTION NOTE: The following reflects the information entered in the PIAMS Website. A. SYSTEM DESCRIPTION Authority: Office of Management Budget (OMB) Memorandum (M) 03-22, OMB Guidance for Implementing the Privacy

More information

Fiscal Year 2007 Federal Information Security Management Act Report

Fiscal Year 2007 Federal Information Security Management Act Report OFFICE OF INSPECTOR GENERAL Special Report Catalyst for Improving the Environment Fiscal Year 2007 Federal Information Security Management Act Report Status of EPA s Computer Security Program Report No.

More information

NUMBER OF MATERIAL WEAKNESSES

NUMBER OF MATERIAL WEAKNESSES APPENDIX A: PERFORMANCE AND RESOURCE TABLES MANAGEMENT DISCUSSION AND ANALYSIS MANAGEMENT CONTROLS FEDERAL MANAGER S FINANCIAL INTEGRITY ACT (FMFIA) OF 1982 D uring FY 2005, the Department reviewed its

More information

Sound Transit Internal Audit Report - No. 2014-3

Sound Transit Internal Audit Report - No. 2014-3 Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management

More information

A. SYSTEM DESCRIPTION

A. SYSTEM DESCRIPTION NOTE: The following reflects the information entered in the PIAMS website. A. SYSTEM DESCRIPTION Authority: Office of Management Budget (OMB) Memorandum (M) 03-22, OMB Guidance for Implementing the Privacy

More information

Office of Audits and Evaluations Report No. AUD-13-007. The FDIC s Controls over Business Unit- Led Application Development Activities

Office of Audits and Evaluations Report No. AUD-13-007. The FDIC s Controls over Business Unit- Led Application Development Activities Office of Audits and Evaluations Report No. AUD-13-007 The FDIC s Controls over Business Unit- Led Application Development Activities September 2013 Executive Summary The FDIC s Controls over Business

More information

5 FAM 620 INFORMATION TECHNOLOGY (IT) PROJECT MANAGEMENT

5 FAM 620 INFORMATION TECHNOLOGY (IT) PROJECT MANAGEMENT 5 FAM 620 INFORMATION TECHNOLOGY (IT) PROJECT MANAGEMENT 5 FAM 621 GENERAL (Office of Origin: IRM/BMP/SPO/PMD) a. The strategic importance of Information Technology (IT) to the mission of the State Department

More information

Portfolio Management through Capital Planning and Investment Control: Program Planning Best Practice Agency Level (for the US Department of State)

Portfolio Management through Capital Planning and Investment Control: Program Planning Best Practice Agency Level (for the US Department of State) Portfolio Management through Capital Planning and Investment Control: Program Planning Best Practice Agency Level (for the US Department of State) Robert A. Horrigan, PMP Knowledge Exchange Forum Moderator

More information

Privacy Impact Assessment (PIA)

Privacy Impact Assessment (PIA) Privacy Impact Assessment (PIA) 1. Contact Information Department of State Privacy Coordinator Margaret P. Grafeld Bureau of Administration Global Information Services Office of Information Programs and

More information

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION Complete Actions Were Not Taken to Validate the Best Software Solution Was Chosen for the Private Debt Collection Program April 10, 2007 Reference Number:

More information

Manag. Roles. Novemb. ber 20122

Manag. Roles. Novemb. ber 20122 Information Technology Manag gement Framework Roles and Respo onsibilities Version 1.2 Novemb ber 20122 ITM Roles and Version History Version ed By Revision Date Approved By Approval Date Description of

More information

Project Type Guide. Project Planning and Management (PPM) V2.0. Custom Development Version 1.1 January 2014. PPM Project Type Custom Development

Project Type Guide. Project Planning and Management (PPM) V2.0. Custom Development Version 1.1 January 2014. PPM Project Type Custom Development Project Planning and Management (PPM) V2.0 Project Type Guide Custom Development Version 1.1 January 2014 Last Revision: 1/22/2014 Page 1 Project Type Guide Summary: Custom Development Custom software

More information

Primavera Portfolio Management

Primavera Portfolio Management Exhibit 300 BY13 (Form) / FEMA - Mapping, Assessment and Planning (RISKMAP) Program (Item) / Feb 29, 2012 (Data as of) Primavera Portfolio Management 300A - OVERVIEW Section A: Overview 1. Name of this

More information

Table of Contents. Agencies are required to provide two reports on financial management and one on grants management:

Table of Contents. Agencies are required to provide two reports on financial management and one on grants management: SECTION 52 INFORMATION ON FINANCIAL MANAGEMENT Table of Contents 52.1 What are the general reporting requirements? 52.2 What reporting requirements are addressed? 52.3 Who must report financial and grant

More information

NIST 800-53A: Guide for Assessing the Security Controls in Federal Information Systems. Samuel R. Ashmore Margarita Castillo Barry Gavrich

NIST 800-53A: Guide for Assessing the Security Controls in Federal Information Systems. Samuel R. Ashmore Margarita Castillo Barry Gavrich NIST 800-53A: Guide for Assessing the Security Controls in Federal Information Systems Samuel R. Ashmore Margarita Castillo Barry Gavrich CS589 Information & Risk Management New Mexico Tech Spring 2007

More information

SECTION 53 INFORMATION TECHNOLOGY AND E-GOVERNMENT. Table of Contents

SECTION 53 INFORMATION TECHNOLOGY AND E-GOVERNMENT. Table of Contents SECTION 53 INFORMATION TECHNOLOGY AND E-GOVERNMENT Table of Contents 53.1 Why must I report on information technology (IT) investments? 53.2 What background information must I know? 53.3 How do I ensure

More information

1. Contact Information. 2. System Information. Privacy Impact Assessment (PIA)

1. Contact Information. 2. System Information. Privacy Impact Assessment (PIA) 1. Contact Information Privacy Impact Assessment (PIA) Department of State Privacy Coordinator Margaret P. Grafeld Bureau of Administration Information Sharing Services Office of Information Programs and

More information

DEPARTMENTAL REGULATION

DEPARTMENTAL REGULATION U.S. DEPARTMENT OF AGRICULTURE WASHINGTON, D.C. 20250 DEPARTMENTAL REGULATION SUBJECT: Identity, Credential, and Access Management Number: 3640-001 DATE: December 9, 2011 OPI: Office of the Chief Information

More information

The OMB Federal IT Dashboard: Overview and Potential Application for IT Cost and Schedule Analysis

The OMB Federal IT Dashboard: Overview and Potential Application for IT Cost and Schedule Analysis The OMB Federal IT Dashboard: Overview and Potential Application for IT Cost and Schedule Analysis Daniel Harper For Internal MITRE Use Did you know. 2 that there is a public available database of over

More information

NARA s Information Security Program. OIG Audit Report No. 15-01. October 27, 2014

NARA s Information Security Program. OIG Audit Report No. 15-01. October 27, 2014 NARA s Information Security Program OIG Audit Report No. 15-01 October 27, 2014 Table of Contents Executive Summary... 3 Background... 4 Objectives, Scope, Methodology... 7 Audit Results... 8 Appendix

More information

OFFICE OF INSPECTOR GENERAL

OFFICE OF INSPECTOR GENERAL OFFICE OF INSPECTOR GENERAL Audit Report Catalyst for Improving the Environment Evaluation of U.S. Chemical Safety and Hazard Investigation Board s Compliance with the Federal Information Security Management

More information

POSTAL REGULATORY COMMISSION

POSTAL REGULATORY COMMISSION POSTAL REGULATORY COMMISSION OFFICE OF INSPECTOR GENERAL FINAL REPORT INFORMATION SECURITY MANAGEMENT AND ACCESS CONTROL POLICIES Audit Report December 17, 2010 Table of Contents INTRODUCTION... 1 Background...1

More information

Recruitment System RECRUIT

Recruitment System RECRUIT DEPARTMENT OF STATE FISCAL YEAR 2008 PRIVACY IMPACT ASSESSMENT Recruitment System RECRUIT Conducted by: Bureau of Administration Information Sharing Services Office of Information Programs and Services

More information

Office of Inspector General

Office of Inspector General DEPARTMENT OF HOMELAND SECURITY Office of Inspector General Security Weaknesses Increase Risks to Critical United States Secret Service Database (Redacted) Notice: The Department of Homeland Security,

More information

Privacy Impact Assessment (PIA) Consular Affairs Enterprise Service Bus (CAESB) 01.00.00. Last Updated: May 1, 2015

Privacy Impact Assessment (PIA) Consular Affairs Enterprise Service Bus (CAESB) 01.00.00. Last Updated: May 1, 2015 United States Department of State (PIA) Consular Affairs Enterprise Service Bus (CAESB) 01.00.00 Last Updated: May 1, 2015 Bureau of Administration 1. Contact Information A/GIS/IPS Director Bureau of Administration

More information

United States Secret Service Enterprise Architecture Review Board (EARB) Project Briefing for NAME OF PROJECT

United States Secret Service Enterprise Architecture Review Board (EARB) Project Briefing for NAME OF PROJECT United States Secret Service Enterprise Architecture Review Board (EARB) Project Briefing for NAME OF PROJECT Presenter Name(s) Date 1 Introduction: An Enterprise Architecture Review Board (EARB) review

More information

Security Controls Assessment for Federal Information Systems

Security Controls Assessment for Federal Information Systems Security Controls Assessment for Federal Information Systems Census Software Process Improvement Program September 11, 2008 Kevin Stine Computer Security Division National Institute of Standards and Technology

More information

U.S. Department of the Treasury. Treasury IT Performance Measures Guide

U.S. Department of the Treasury. Treasury IT Performance Measures Guide U.S. Department of the Treasury Treasury IT Performance Measures Guide Office of the Chief Information Officer (OCIO) Enterprise Architecture Program June 2007 Revision History June 13, 2007 (Version 1.1)

More information

Year 2000 Contingency Planning and Certification Reporting

Year 2000 Contingency Planning and Certification Reporting United States Risk Stop 0801 Department of Management 1400 Independence Avenue, SW Agriculture Agency Washington, DC 20250-0801 BULLETIN NO.: MGR-98-023 TO: FROM: SUBJECT: All Reinsured Companies Kenneth

More information

FHFA. Privacy Impact Assessment Template FM: SYSTEMS (SYSTEM NAME)

FHFA. Privacy Impact Assessment Template FM: SYSTEMS (SYSTEM NAME) FHFA Privacy Impact Assessment Template FM: SYSTEMS (SYSTEM NAME) This template is used when the Chief Privacy Officer determines that the system contains Personally Identifiable Information and a more

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

SIGNIFICANT CHANGES DOCUMENT

SIGNIFICANT CHANGES DOCUMENT SIGNIFICANT CHANGES DOCUMENT Descriptive Title Schedule 70_MassModification_Health IT SIN Significant Changes Disclaimer Language DISCLAIMER: GSA FAS is posting this notification of a planned solicitation

More information

AUDIT REPORT REPORT NUMBER 14 08. Information Technology Professional Services Oracle Software March 25, 2014

AUDIT REPORT REPORT NUMBER 14 08. Information Technology Professional Services Oracle Software March 25, 2014 AUDIT REPORT REPORT NUMBER 14 08 Information Technology Professional Services Oracle Software March 25, 2014 Date March 25, 2014 To Chief Information Officer Director, Acquisition Services From Inspector

More information

Department-wide Systems and Capital Investment Program

Department-wide Systems and Capital Investment Program Department-wide Systems and Capital Investment Program Mission Statement The Department-wide Systems and Capital Investments Program (DSCIP) is authorized to be used by or on behalf of the Treasury Department

More information