Gilbert Kwok LLB (English Law), LLB (PRC Law), FHKIS, FRICS Partner, Construction & Engineering Group, Li & Partners

Size: px
Start display at page:

Download "Gilbert Kwok LLB (English Law), LLB (PRC Law), FHKIS, FRICS Partner, Construction & Engineering Group, Li & Partners"

Transcription

1 Li & Partners 1 NEC Contract Gilbert Kwok LLB (English Law), LLB (PRC Law), FHKIS, FRICS Partner, Construction & Engineering Group, Li & Partners and Justin Yuen / Stephanie Lau / Christy Yiu / Edmund Chau Members of the Construction & Engineering Group of Li & Partners Li & Partners

2 Introduction Outline of Seminar Part 1 - Standard Form Construction Contracts by Gilbert Kwok and Stephanie Lau Part 2 - New Engineering Contract (NEC) by Justin Yuen, Christy Yiu and Edmund Chau Li Li & Partners 2 2

3 Part 1: Standard Form Construction Contracts Li Li & Partners 3 3

4 Introduction I. Procurement Methods (by Gilbert Kwok) II. Some Types of Contracts (by Gilbert Kwok) III. Forms of Contracts Commonly Used (by Stephanie Lau) IV. Why Getting the Right Form is Important? (by Stephanie Lau) Li Li & Partners 4 4

5 I. Procurement Methods Traditional Design and Build Management Contracting Construction Management Li Li & Partners 5 5

6 Traditional Employer Consultants Main Contractor Sub-contractors Li Li & Partners 6 6

7 Features Traditional 2 sets of contractual relationships Consultant s s role Main Contractor s s responsibility Advantages Criticism Li Li & Partners 7 7

8 Design and Build Employer Design and Build Contractor Sub-contractors Li Li & Partners 8 8

9 Design and Build Advantages Simple contractual relationship Single point responsibility Overlap of design and construction Criticism Quality of works Tendering Tamar Development Project Li Li & Partners 9 9

10 Management Contracting Employer Consultants Management Contractor Work Package Sub-contractors Li Li & Partners 10 10

11 Management Contract Contractual relationship Features The project team Remuneration of the Management Contractor Management Contractor s s roles and duties Advantages Criticism Li Li & Partners 11 11

12 Construction Management Construction Manager Employer Consultants Work Package Contractors Li Li & Partners 12 12

13 Construction Management Contractual relationship Distinguishing CM from MC Features Advantages Criticism Li Li & Partners 13 13

14 II. Some Types of Contracts Lump Sum Fixed Price Contract Based on BQ Based on Drawings and Specifications Measurement Contract Schedule of Rates Bills of Approximate Quantities Reimbursement Contract Option: Guaranteed Maximum Price (GMP) Area of dispute Li Li & Partners 14 14

15 III. Forms of Contracts Commonly Used Hong Kong Private Sector Hong Kong Public Sector International Li Li & Partners 15 15

16 Hong Kong Private Sector Standard Form of Building Contracts (1986( Edition & 2005 Edition) Published by HKIA / HKIS / HKICM 2005 Edition More detailed description of rights/obligations Lengthy references: procedures/management requirements More notice requirements Others Standard Form of Contract for Minor Works Standard Form of Domestic Sub-contract ( published by the Hong Kong Construction Association) Li Li & Partners 16 16

17 Hong Kong Public Sector - HK Govt / Public works a) General Conditions of Contract for:- Building Works, 1999 Edition Civil Engineering Works, 1993 & 1999 Edition Design and Build Contract, 1999 Edition E&M Engineering Works, 1999 Edition Term Contracts for Building Works, 2004 Edition Term Contracts for Civil Engineering Works, 2002 Edition Term Contracts for E&M Works, 1994 Edition b) Sub-Contract for Building Works, 2000 Edition - Government Forms Li Li & Partners 17 17

18 International a) JCT b) FIDIC c) ICE d) NEC Li Li & Partners 18 18

19 a) JCT Background Joint Contracts Tribunal Representative bodies of construction industry History 19 th Century Latest Edition Criticism: lengthy / complex Li Li & Partners 19 19

20 b) FIDIC The International Federation of Consulting Engineers International context Widely used building / engineering work Main types of Conditions of Contracts (99 Ed) Red Book Construction (for Building and Engineering Works) Yellow Book Plant & Design-Build Silver Book EPC / Turnkey Short Form of Contract Li Li & Partners 20 20

21 c) ICE Background The Institution of Civil Engineers ICE / Association of Consulting Engineers / Civil Engineering Contractors Association 1st ed 1945 UK Major engineering projects Main types of contracts and features ICE Conditions of Contract: Measurement Version (7th edition 1999) ICE Design & Construct Conditions of Contract (2nd edition 2001) Other forms Hong Kong Government Form Li Li & Partners 21 21

22 d) NEC Background New Engineering Contract 1980s - Debates within ICE Focus: Obligations / Responsibilities of parties vs Project Management / Promote Cooperation / Reduction of Confrontation Main types of contracts NEC Engineering & Construction Contract NEC Engineering & Construction Sub-Contract Endorsed in the UK UK Office of Government Commerce London Olympic Delivery Authority Promoted by HK Govt Li Li & Partners 22 22

23 IV. Why Getting the Right Form is Important? Contracts govern: time, cost & quality Impact of the right contract Risk exposure and allocation Site / Market conditions Responsibilities of the parties E.g. time limits for written notices Governing law and dispute resolution Li Li & Partners 23 23

24 Why Getting the Right Form is Important? An example from the employer s s perspective If he assumes design responsibility Engage Engineer / Architect Pricing: Lump-sum / Remeasurement / Reimbursement Lump-Sum eg.. HKIS/HKIA Standard Form Reimbursement eg.nec Costs Reimbursable Contract If he does not assume design responsibility Eg.. FIDIC Yellow Book Eg.. FIDIC Silver Book Li Li & Partners 24 24

25 Part 2: New Engineering Contract (NEC) (now Engineering and Construction Contract (ECC)) Li Li & Partners 25 25

26 New Engineering Contract (NEC) I. Introduction (by Christy Yiu) II. Typical Contracts within the NEC ECC family (by Christy Yiu) III. Structure of a Typical NEC Contract (by Christy Yiu) IV. Other Features of NEC (by Edmund Chau) V. Compensation Events (by Edmund Chau) VI. VII. VIII. IX. Delay Damages (by Justin Yuen) Criticisms (by Justin Yuen) Benefits (by Justin Yuen) Conclusion (by Justin Yuen) Li Li & Partners 26 26

27 I. Introduction What is NEC ECC? Entirely new approach Focuses on cooperation and project management Objectives Flexibility Good project management Simplicity and clarity Li Li & Partners 27 27

28 II. Typical Contracts within the NEC ECC Family Priced Contract with Activity Schedule or BQ Target Cost Contract with Activity Schedule or BQ Cost Reimbursable Contract Management Contract Short Contract Framework Contract Sub Contract Professional Services Contract Adjudicator Contract Li Li & Partners 28 28

29 III. Structure of a Typical NEC Contract Li Li & Partners 29 29

30 a) Options, Core Clauses and Secondary Option Clauses Departure from traditional approach System of options and clauses Options Select for a particular project Core Clauses Basis for a range of construction contracts Secondary Option Clauses Li Li & Partners 30 30

31 b) What needs to be done by the Employer? To create a set of NEC 3 Conditions: Select one of the 6 Main Options Include the 9 Core Clauses Specify Dispute Resolution Option Select Secondary Option Clauses Include Secondary Option Z Additional clauses drafted specially for a particular contract Li Li & Partners 31 31

32 c) 6 Main Options One of which must be included Purpose A. Priced Contract with Activity Schedule B. Priced Contract with BQ C. Target Contract with Activity Schedule D. Target Contract with BQ E. Cost Reimbursable contract F. Management Contract Li Li & Partners 32 32

33 d) 9 Core Clauses 1. General General introductory matters Early warning procedure 2. The Contractor s s Main Responsibilities Design Equipment Personnel Sub-contracting Li Li & Partners 33 33

34 d) 9 Core Clauses 3. Time Key dates To meet specification or condition 4. Testing and Defects Basic regime Rectification and acceptance 5. Payment PM to assess Assessment dates in Contract Data Certify within 1 week Pay within 3 weeks or the period stated in Contract Data Interest on late payments Li Li & Partners 34 34

35 d) 9 Core Clauses 6. Compensation Events Time and money in each event 7. Title Plant and materials 8. Risks and Insurance Employer s s risks Contractor s s risks Insurance table Li Li & Partners 35 35

36 d) 9 Core Clauses 9. Termination Reasons and procedures Situations under which either party may terminate In the event of insolvency Situations under which the Contractor may terminate Not paid within 13 weeks Situations under which the Employer may terminate Substantially failed to comply with obligations Not provided a bond or guarantee Substantially hindered the Employer or others Substantially broken a health or safety regulation Li Li & Partners 36 36

37 e) Dispute Resolution Clause Options W1 and W2 W2 is used when UK Housing Grants, Construction and Regeneration Act 1996 applies. f) Secondary Options May be included Retention Delay damages for late completion Performance bonds Advanced payment Sectional completion Li Li & Partners 37 37

38 IV. Other Features Li & Partners 38

39 IV. Other Features a) Project Manager and Supervisor b) Site Management c) Early Completion d) Contractor s s Risk for Physical Conditions e) Terms used in NEC Li Li & Partners 39 39

40 a) Project Manager and Supervisor No the Engineer or the Architect Project Manager Instruction, payment and compensation events Supervisor standards and quality of work Legal Duty of PM NEC: spirit of mutual trust and cooperation To act impartially between Employer & Contractor Costain v Bechtel [2005] EWHC 1018 Li Li & Partners 40 40

41 b) Site Management Good site management is achieved by: Rapid communication Many notice requirements Regular meetings Risk reduction meeting Up-to to-date programmes Not only Start date, access date, key dates and completion dates But also Planned completion, order & timing of each operation PM to accept/ reject in 2 weeks Li Li & Partners 41 41

42 c) Early Completion Clause 36.1 of core clauses The project manager may request Quotation for accelerating the works Option X6 of secondary options Bonus for early completion Li Li & Partners 42 42

43 d) Contractor s s Risk for Physical Conditions Contractor shall allow for it Physical condition not a compensation event, unless, (clause 60.1(12))..an experienced contractor would have judged at the Contract Date to have such a small chance of occurring that it would have been unreasonable for him to have allowed for it. Li Li & Partners 43 43

44 e) Terms used in the NEC Different from other forms Examples: Usual terms NEC terms Variation Instruction Changing the works information Suspension Order Extension of Time Liquidated Damages An instruction to stop or not to start work Assessment of a delay to the completion date Delay Damages Problem for interpretation Li Li & Partners 44 44

45 Li & Partners 45 V) Compensation Events

46 a) Introduction Core Clause 6 Deal with at the same clause EOT, Loss and Expense and V.O. A comprehensive list (clause 60.1) 2 Stages Stage 1: Notification Stage 2: Quotation & Assessment Li Li & Partners 46 46

47 Stage 1: Notification Who and When to notify? Depends on the nature of the Events (i) Arise from P.M. s instruction PM at the time of instruction (ii) Others Contractor to notify a compensation event if fails to notify within 8 weeks Not entitled to change in Prices, Completion Date or a Key Date (clause 61.3) Reply to notification P.M. to reply his decision if fails to reply within 2 weeks Treated as acceptance and instruction to give quotation (clause 61.4) Li Li & Partners 47 47

48 Stage 2: Quotation & Assessment P.M. may request Contractor to submit Time and money implications Contractor to submit within 3 weeks P.M. to reply within 2 weeks Accept or request for revised quotation if P.M. fails to assess within time limit The Contractor may notify P.M. this failure If P.M. still fails to reply within another 2 weeks Treated as accepted by P.M. (clause 62.6) Li Li & Partners 48 48

49 VI) Delay Damages (a) (b) (c) (d) (e) Introduction Option Clause X7 Repayment of Delay Damages Proportioning Down Delay Damages Employer s s Benefit Li Li & Partners 49 49

50 a) Introduction Only a Secondary Option (Option X7) If not chosen If chosen No Certificate of Non-Completion The Rate of Delay Damages Change of Completion Date Interest Li Li & Partners 50 50

51 b) Option Clause X7 Intended to operate as LD Rate conforms with rules for LD Li Li & Partners 51 51

52 c) Repayment of Delay Damages Option Clause X7.2 deals with Change of Completion Date Interest Rate not stated Contract Data Clause 51.4 Li Li & Partners 52 52

53 d) Proportioning Down Delay Damages Deficiency of Option R of NEC2 The need and importance for proportioning down Clause X7.3 of NEC 3: If the Employer takes over a part of the works before Completion, the delay damages are reduced from the date on which the part is taken over. The rationale Clause X7.3: The Project Manager assesses the benefit to the Employer of taking over the part of the works as a proportion of the benefit to the Employer of taking over the whole of the works not previously taken over. The delay damages are reduced in this proportion. Li Li & Partners 53 53

54 d) Proportioning Down Delay Damages P.M. assesses the Employer s s Benefit The Usual Rule in other Contracts The benefit rule in Option Clause X7.3 of NEC Guidance Notes to NEC3 - benefits at the time of calculation Stipulated LD rates: genuine pre-estimates estimates of loss Circumstances anticipated at the time of Contract Advisable to amend the Option Clause Li Li & Partners 54 54

55 VII) Criticism a) NEC Appropriate for All Projects? b) What are the Contract Documents? c) Practical Problems d) Language problem - the use of present tense Li Li & Partners 55 55

56 a) NEC Appropriate for All Projects? Different procurement approaches Lack of differentiation Mechanical and Electrical Engineering projects Li Li & Partners 56 56

57 b) What are the Contract Documents? Contract documents not specifically stated Discrepancies between various documents Li Li & Partners 57 57

58 c) Practical Problems Programmes Compliance with all the requirements Sub-contractors Increase the staffing requirements Tight timescales Quoting for future effects Dealing with contentious matters 2 Functions of the construction team Li Li & Partners 58 58

59 d) Language problem - the use of present tense In Easily Comprehensible Language Present tense = Present tense Clause 11.2(16): Site Information is information which describes the Site. Statement imposing legal obligation e.g. Clause 30.3: The Contractor does the work so that the Condition stated for each Key Date is met by the Key Date. Clause 33.1: The Employer allows access to and use of the Site to the Contractor which is necessary for the work included in this Contract. Li Li & Partners 59 59

60 d) Language problem - the use of present tense Statement not imposing legal obligation Clause 61.3: The Contractor notifies the Project Manager of an event which has happened or which he expects to happen as a compensation event if (a) the Contractor believes that the event is a compensation event and (b) the Project Manager has not notified the event to the Contractor. Li Li & Partners 60 60

61 VIII. Benefits NEC is a modern day family of contracts that facilitates the implementation of sound project management principles and practices as well as defining legal relationships. Key to the successful use of NEC is users adopting the desired cultural transition. The main aspect of this transition is moving away from a reactive and hindsight-based decision-making and management approach to one that is foresight based, encouraging a creative environment with pro-active and collaborative relationships. Flexibility Clarity and Simplicity Stimulus to Good Management Li Li & Partners 61 61

62 a) Flexibility An all purpose contract Non-technical language Choices of pricing mechanisms A range of secondary options Li Li & Partners 62 62

63 b) Clarity and Simplicity Different style and structure Simple and non-legalistic language Avoid specific terminology Li Li & Partners 63 63

64 c) Stimulus to Good Management Proactive Project Management Early Warning Risk Register Co-operation operation Clause Li Li & Partners 64 64

65 Proactive Project Management Partnering approach Communications and co-operation operation Up-to to-date agreed Programme Managed Project Environment Improvement and job satisfaction Li Li & Partners 65 65

66 Early Warning Clause 16.1 The mechanism Purpose Cooperate and Discuss Partnering-based approach Li Li & Partners 66 66

67 Risk Register The mechanism Risk reduction meeting Purpose Proactive risk management Express purpose Discuss Co-operate operate Encourage proactive risk management 3 main objectives Identify risks Manage risks Identify time and cost The overall effect Li Li & Partners 67 67

68 Co-operation operation Clause Clause 10.1: The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of mutual trust and co-operation. operation. Improved attitude Li Li & Partners 68 68

69 VI. Conclusion Drawbacks Onerous requirements Benefits A framework for forward planning Li Li & Partners 69 69

70 END of PART 2 Li & Partners 70

71 NEC Contract Gilbert Kwok LLB (English Law), LLB (PRC Law), FHKIS, FRICS Partner, Construction & Engineering Group, Li & Partners and Justin Yuen / Stephanie Lau / Christy Yiu / Edmund Chau Members of the Construction & Engineering Group of Li & Partners Li & Partners Li Li & Partners 71 71

72 Li & Partners 72 NEC 3 The perfect contract? Matthew Needham-Laing BA Hons, Dip Arch, MSc, LLB, ARB registered, R.I.B.A Stevens and Bolton LLP

73 Li & Partners 73 Introduction This presentation is intended to provide a brief summary of the theoretical concepts behind NEC 3, and identify some of the limitations of using this form of contract. The presentation has been prepared from the perspective of the law within the United Kingdom.

74 Li & Partners 74 Classical contract theory: Parties have freedom of contract; Parties negotiating to maximise self interest; Parties negotiations are influenced by competitive market; and Allocation of all risks between parties at the time of contracting.

75 Li & Partners 75 Relational contract theory Parties accept that economic benefit is a result of their interdependence; Parties obligations toward each other are determined more by their relationship rather then their respective contractual promises; Parties negotiate on how to handle events in the future rather than allocate risk at the time of contracting.

76 Li & Partners 76 Classical Contracts tend to arise where the contract is: Short in duration or single project; Limited interaction between parties; Measurable outcomes or performance; and Minimal future co-operation.

77 Li & Partners 77 Relational Contracts tend to arise where contract: Is of long duration or multiple projects Requires the preservation of the relationship between parties; Has unknown or immeasurable outcomes or performance; and Requires ongoing or future co-operation.

78 Li & Partners 78 NEC 3 has been developed out of and with the intention of addressing the circumstances identified in the relational contract theory. The relational contract theory relies on the parties cooperating as it is in their commercial interest to do so and the NEC expressly requires both the parties to the contract and the parties administering the NEC contract to deal with each other in a spirit of mutual trust and co-operation [Clause 10.1].

79 Li & Partners 79 The duty to co-operate. In English law the duty to co-operate is regarded as both a positive and a negative obligation. The NEC is an international contract and therefore the duty to co-operate will be influenced by the law of the contract chosen by the parties.

80 Li & Partners 80 The positive obligation has been defined by Lord Blackburn in Mackay v Dick (1881) as: where in a written contract it appears that both parties have agreed that something shall be done, which cannot effectually be done unless both concur in doing it, the construction of the contract is that each agrees to do all that is necessary to be done on his part for the carrying out of that thing

81 The negative obligation is that party should not interfere with the performance of contract or prevent a person performing his/her duties under the contract. It has most frequently manifested itself in case law in relation the duties of certifiers under contracts, for example it is a breach of contract if the employer interferes with the architect/engineer in the performance of those functions where the architect/engineer is required to act fairly between the employer and the contractor. Sutcliffe v Thackrah Li & Partners 81

82 Li & Partners 82 His Honour Humphrey Lloyd Q.C. has suggested that: The phrase mutual trust and co-operation imports not only honesty and reasonableness but may also oblige someone to do more than the contract calls for if the contract is truly to be performed co-operatively.

83 The guidance notes to the NEC state: the two principles on which the [NEC] is based and which impact upon the objective of stimulating good management are: Foresight applied collaboratively mitigates problems and shrinks risk, and Clear division of function and responsibility helps accountability and motivates people to play their part. A secondary but important theme is that people will be motivated to play their part in collaborative management if it is in their commercial and professional interest to do so. [emphasis added] Li & Partners 83

84 The NEC has, until recently enjoyed a benign economic climate and has been used satisfactorily: By employers either under framework agreements which last 3-4 years e.g.:- British Airports Authority BAA who have until recently used the NEC on all their projects with values ranging from 60,000 to 50 million; or Anglia Water on projects with values ranging from 500,000 to 2 million On large projects where a series of contracts are to be let, e.g.:- Heathrow Express Tunnel project value 60 million Channel Tunnel Rail Link, project value 30 billion The 2012 Olympics. Li & Partners 84

85 Li & Partners 85 Economic circumstances have changed dramatically in the last 18 months: The downturn in the construction industry has resulted in a more aggressive and competitive market which has engendered a belief that the best deals are derived from competitive tendering. This has resulted in an increase in open market competition and major construction clients renegotiating or retendering their established frameworks.» UK Market Intelligence Autumn 2009 The current economic climate means that the NEC is more likely to be used on short duration or single projects where there is limited interaction between the parties and little or no prospect of future collaboration.

86 Options available to the Employer when it is no longer in its interest to collaborate: Renegotiate framework agreements to reflect the current economic climate. The contractors have little choice but to agree. Apply the contract terms strictly and disallow costs where contractually entitled to do so. The Employer however has the problem of Costain Ltd v Bechtel Ltd and Mr. Fady Bassily. How does applying the contract terms strictly comply with HHJ Humphrey Lloyd s view of clause 10.1? Li & Partners 86

87 Options available to the Contractor when it is no longer in its interest to collaborate: Renegotiate if it can rely upon the obligations in clause 10.1 Apply the terms of the contract strictly, in particular : operate the early warning procedure in clause 16.1 to the fullest extent; operate the notification of compensation events procedure in clause 61.3 to the fullest extent; and assume that all decisions of the Project Manager will be the subject of an adjudication. Li & Partners 87

88 Is the NEC robust enough to control the parties relationship when it is not in their commercial interests to collaborate? Li & Partners 88

89 The Accepted Programme Invariably the programme is prepared for tender purposes and becomes the accepted programme, consequently the contents of the programme are inadequate due to lack of information at tender stage; contractor has not dedicated sufficient programme resources at tender stage; the programme has been prepared to win the tender rather than build the project; and further information and detail are identified as being required from the Employer. Result: Project is difficult to manage without an adequate programme; The Employer fails to provide information in accordance with the programme and these are compensation events. Li & Partners 89

90 Early Warning Notices The Contract obliges the contractor to give early warning notices and penalises the contractor if it fails to do so, consequently the: Contractor issues an early warning notice in relation to any matter which potentially affects the project; and Early warning notices become treated as a notice of claim. Result: Too many early warning notices for risk reduction meetings to be held or be effective; If risk reduction meetings are held then there is insufficient time/information to manage the risk effectively; The Risk Register ceases to be a management tool. Li & Partners 90

91 Compensation Events The Contractor is required to notify the project manager of an event which has happened or is expected to happen within 8 weeks of becoming aware of the event, consequently: The contractor treats all early warnings as notification of a compensation event. Result: Risk reduction meetings cease to be collaborative; The Project Manager is unable or has insufficient time/resource to identify true compensation events; The Project Manager fails to request quotations; The Contractor fails to submit quotations in time or at all; The Project Manager does not assess, or fails to assess the compensation events correctly. Li & Partners 91

92 The Project Manager has no power to review any of his/her decisions, with the benefit of hindsight, at the conclusion of the contract, consequently: The parties must go to adjudication in relation to any disagreement with the Project Manager s decision. The result if Option W1 is used: The time periods for referring disputes to adjudication mean that resources require to manage the project are diverted to deal with disputes, or more resources are required. The result if Option W2 is used: The disputes are referred to adjudication at the end. Problems of interpreting the contract terms. Li & Partners 92

93 Summary The NEC relies upon: the parties co-operating because it is in both their economic interests to do so; and sufficient project management resources being provided by both the Employer and Contractor to operate the contract procedures and manage risk. If the parties fail to co-operate or insufficient project management resources are allocated to the project then: the Project Manager is unable to manage the contract effectively outturn cost and completion date cease to be predictable; disputes arise which must be referred to adjudication. Li & Partners 93

94 Li & Partners 94 Is the NEC the perfect contract? The NEC has been used predominantly by Employers with considerable influence on the procurement of construction projects at a time of economic prosperity. At the same time it has benefited from a general willingness within the construction industry to embrace more collaborative methods of working.

95 Is the NEC the perfect contract? Changed economic circumstances and the promotion of the NEC form of contract as suitable for a wide variety of contracts has led to its use on projects where it is not necessarily in the interests of one or both parties to co-operate. Where parties fail to co-operate, indications are that the contract may be no better at preventing disputes than other established forms of contract and may, by virtue of the detailed management procedures, encourage the use of formal dispute resolution procedures. Li & Partners 95

96 Bibliography C.J Goetz & R.E. Scott, The Mitigation Principle: Toward a General Theory of Contractual Obligation (1983) 69 Virginia Law Review I.R Mac Neil the New Social Contract (New Haven : Yale University Press 1980) G. Barrie Private firms embrace NEC for construction Building, December 1995 D.M. Giles The New Engineering Contract, a new Family of Contracts for the new millennium National Contracts Management Association Newsletter, June 1996 S. Furst & V. Ramsey Keating on Construction Contracts Eighth Edition (Thomson Sweet & Maxwell 2006) A. McInnis The New Engineering Contract: Relational Contracting, Good Faith and Cooperation Part 1 & Part 2 ( The International Construction Law Review 2003) HHJ Lloyd Some thoughts on NEC 3 (NEC Users Group 2009) NEC 3 Engineering and Construction Contract Guidance Notes (Thomas Telford Ltd) Turner & Townsend UK Market Intelligence Autumn 2009 Cases: Mackay V Dick (1881) 6 App Cas 251 Sutcliffe v Thackrah [1974] A.C (1) Costain Limited (2) O Rouke Civil Engineering Limited (3) Bachy Soletanche Limited (4) Emcor Drake & Scull Group Plc V (1) Bechtel Limited (2) Mr Fady Bassily [2005] EWHC Li & Partners 96

Appendix 18 NEC3 Options

Appendix 18 NEC3 Options Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and

More information

How To Write A Contract

How To Write A Contract Commercial Management the NEC Way Hong Kong Institute of Surveyors Ian.Heaphy@turntown.com Mark.Lyddon@turntown.com, July 2014 Turner & Townsend plc July 14 making the difference Health, safety & wellbeing

More information

NEC3: The Engineering and Construction Contract An overview

NEC3: The Engineering and Construction Contract An overview NEC3: The Engineering and Construction Contract An overview Michael Dunn FRICS FCIArb LLB LLM T: 02079 976 520 and 01274 693 622 E: m.dunn@rpp.co.uk www.rpp.co.uk Delivering Professional Solutions to the

More information

NEC Users Group Workshop Defined Cost

NEC Users Group Workshop Defined Cost NEC Users Group Workshop Defined Cost Ian.Heaphy@turntown.com; July 2014 Turner & Townsend plc July 14 making the difference Introduction Practicalities in assessing of Defined Cost & Disallowed Cost Assumption

More information

NEC3 Engineering & Construction Contract An Overview

NEC3 Engineering & Construction Contract An Overview NEC3 Engineering & Construction Contract An Overview Delivering Professional Solutions to the Property Industry Michael Dunn FRICS FCIArb LLB LLM Director of Contract Services T: 01274 693 622 E: m.dunn@rpp.co.uk

More information

NEC3: THE CONSTRUCTION CONTRACT OF THE FUTURE? Nicholas Gould. 8 February 2007 SINGAPORE SOCIETY OF CONSTRUCTION LAW

NEC3: THE CONSTRUCTION CONTRACT OF THE FUTURE? Nicholas Gould. 8 February 2007 SINGAPORE SOCIETY OF CONSTRUCTION LAW NEC3: THE CONSTRUCTION CONTRACT OF THE FUTURE? Nicholas Gould 8 February 2007 SINGAPORE SOCIETY OF CONSTRUCTION LAW Introduction The first edition of the New Engineering Contract (NEC) was published in

More information

Introduction to NEC3. Course agenda. Course objectives. Session 1 Background and underlying principles the concept

Introduction to NEC3. Course agenda. Course objectives. Session 1 Background and underlying principles the concept Introduction to NEC3 Course agenda Session 1 Background and underlying principles the concept NEC characteristics NEC family including typical NEC arrangements Key NEC3 Engineering and Construction Contract

More information

A Guide to Standard forms of Construction Contract Outlining Key Characteristics and Components

A Guide to Standard forms of Construction Contract Outlining Key Characteristics and Components Produced for SCALA and the Local Government Task Force by Rob Tate Dip Arch. Dip TP. Dip Arb. FCIArb. RIBA 01582 516662 rob.tate@ntlworld.com You can contact the Local Government Task Force tel 020 7837

More information

NEC3: Early Warning and Compensation Events

NEC3: Early Warning and Compensation Events NEC3: Early Warning and Compensation Events Nicholas Gould January 2007 The NEC is a major attempt to draft a simple and direct standard form contract from first principles without attempting to build

More information

The FIDIC Suite of Contracts

The FIDIC Suite of Contracts Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October

More information

Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014

Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014 Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts 5 vember 2014 Table of Contents Part 1 Introduction Part 2 Why new contracts? The reason for the publication

More information

JCT Standard Building Contract 2011 - SBC/Q

JCT Standard Building Contract 2011 - SBC/Q JCT Standard Building Contract 2011 - SBC/Q Michael Dunn FRICS FCIArb LLB LLM T: 02079 976 520 and 01274 693 622 E: m.dunn@rpp.co.uk www.rpp.co.uk Delivering Professional Solutions to the Property Industry

More information

Understanding variations a contractor's perspective Jonathan Brooks, Tim Tapper, Andrew Ash & Stuart McGee. 21 March 2011 & 23 March 2011

Understanding variations a contractor's perspective Jonathan Brooks, Tim Tapper, Andrew Ash & Stuart McGee. 21 March 2011 & 23 March 2011 Understanding variations a contractor's perspective Jonathan Brooks, Tim Tapper, Andrew Ash & Stuart McGee 21 March 2011 & 23 March 2011 Introduction Jonathan Brooks osborneclarke.com osborneclarke.com

More information

Guidance Notes for the NEC Engineering and Construction Contract

Guidance Notes for the NEC Engineering and Construction Contract The first objective of the Risk Register is to identify the risks inherent in a project. Some of these risks are generic, and will apply to whatever work is carried out. An example is the risk of errors

More information

Practice Note Deciding on the appropriate JCT contract

Practice Note Deciding on the appropriate JCT contract Practice Note Deciding on the appropriate JCT contract This Practice Note is intended to provide assistance in deciding the appropriate form of contract but it is not a substitute for professional advice.

More information

GETTING STARTED WITH THE NEC3

GETTING STARTED WITH THE NEC3 GETTING STARTED WITH THE NEC3 NEC3 TERM SERVICE CONTRACT (TSC) AND NEC3 TERM SERVICES SHORT CONTRACT (TSSC) Supported by: Published by the British Institute of Facilities Management April 2015 Introduction

More information

THE NEW ENGINEERING CONTRACT: IMPROVED PROCUREMENT AND CONTRACTING WITH ITS SIMPLICITY, CLARITY AND GOOD PROJECT MANAGEMENT PROVISIONS

THE NEW ENGINEERING CONTRACT: IMPROVED PROCUREMENT AND CONTRACTING WITH ITS SIMPLICITY, CLARITY AND GOOD PROJECT MANAGEMENT PROVISIONS THE NEW ENGINEERING CONTRACT: IMPROVED PROCUREMENT AND CONTRACTING WITH ITS SIMPLICITY, CLARITY AND GOOD PROJECT MANAGEMENT PROVISIONS ABSTRACT THURLOW, P.N. Thurlow Associates cc: Industrial Project Managers

More information

Bills of Quantity. D. Atkinson December 2000. Nature of Bills

Bills of Quantity. D. Atkinson December 2000. Nature of Bills Bills of Quantity D. Atkinson December 2000 Nature of Bills Bills of Quantities comprise a list of items of work which are briefly described. The Bills also provide a measure of the extent of work and

More information

The Commercial Agents Regulations.DOC. The Commercial Agents Regulations

The Commercial Agents Regulations.DOC. The Commercial Agents Regulations The Commercial Agents Regulations.DOC The Commercial Agents Regulations Contents 1. Introduction... 1 2. The Previous Position... 1 3. Commercial Agent... 2 4. Rights and Duties... 3 5. Remuneration...

More information

NEC ECC Option F ERF 2066 Duynefontein building refurbishment

NEC ECC Option F ERF 2066 Duynefontein building refurbishment NEC ECC Option F ERF 2066 Duynefontein building refurbishment Bok Breedt ECC Main Options There are six types of payment mechanism available in the main Options: Option A Priced contract with activity

More information

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CIC/AppInsp The Construction Industry Council - Association of Consultant Approved Inspectors contract for the appointment of an approved inspector

More information

Appendix 17 Options for the Form of Contract

Appendix 17 Options for the Form of Contract Appendix 17 Options for the Form of Contract December 2007 Page 444 Appendix 17 Options for the Form of Contract The main forms of contract which are available are: NEC3 HA Design and Build ICE7 ICE Target

More information

Nominated Subcontractors on International Projects: Approaches to Risk Allocation

Nominated Subcontractors on International Projects: Approaches to Risk Allocation Nominated Subcontractors on International Projects: Approaches to Risk Allocation September 5, 2005 (he following outline was used in a presentation to the Overseas Construction Association of Japan, Inc.

More information

Construction Cost Management

Construction Cost Management Construction Cost Management In the last decade, following the Latham and Egan reports, there have been many significant changes in the role of the construction cost manager. Keith Potts examines the key

More information

A. UK, EUROPEAN AND INTERNATIONAL CONTRACT FORMS. I. Fédération Internationale des Ingénieurs-Conseils (FIDIC)

A. UK, EUROPEAN AND INTERNATIONAL CONTRACT FORMS. I. Fédération Internationale des Ingénieurs-Conseils (FIDIC) STANDARD FORM CONSTRUCTION CONTRACTS Introduction Subcommittee TI of the International Bar Association has undertaken to compile a library of standard conditions of contract for construction in various

More information

EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC

EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC 2 June 2012 EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC Option C) Contract No. DC/2008/02 Improvement of Fuk Man Road Nullah in Sai Kung Change of Consultant s Role & Highlights

More information

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer Conditions of Offer A1 The offer documents comprise the offer form, letter of invitation to offer (if any), these Conditions of Offer and Conditions of Contract (Works & Services), the Working with Queensland

More information

inform practice note SUBCONTRACTING ARRANGEMENTS Content Synopsis: Practice Note # 7 May 2007 (Version 1 - May 2007) construction industry development

inform practice note SUBCONTRACTING ARRANGEMENTS Content Synopsis: Practice Note # 7 May 2007 (Version 1 - May 2007) construction industry development construction industry development inform practice note Issued by the Construction Industry Development Board Development through partnership construction procurement and delivery SUBCONTRACTING ARRANGEMENTS

More information

Letters, Instructions, etc.

Letters, Instructions, etc. Letters, Instructions, etc. Michael Dunn FRICS FCIArb LLB LLM T: 02079 976 520 and 01274 693 622 E: m.dunn@rpp.co.uk www.rpp.co.uk Delivering Professional Solutions to the Property Industry Introduction

More information

An Inspector Calls-Architect s Inspection Duties

An Inspector Calls-Architect s Inspection Duties An Inspector Calls-Architect s Inspection Duties An architect acting as contract administrator under the standard forms of contract has to balance what appear to be the conflicting duties of protecting

More information

Standard forms: JCT 2005, NEC3 and the Virtual Contract

Standard forms: JCT 2005, NEC3 and the Virtual Contract by Nicholas Gould, Partner Introduction This paper reviews some of the standard forms and considers some of the basic principles relating to their use in the construction industry. Basic concepts A review

More information

ICE Legal Notes Series

ICE Legal Notes Series ICE Legal Notes Series Legal Notes Reviewing the work of another Engineer and replacing another Engineer Institution of Civil Engineers www.ice.org.uk Published by the Institution of Civil Engineers (ICE).

More information

The New Standard Construction Contracts: NZS3910, 3916 and 3917

The New Standard Construction Contracts: NZS3910, 3916 and 3917 The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of

More information

Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program

Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program 458 برنامج إدارة العقود الھندسية وعقود التشييد المتكامل معتمد عالميا 10 October

More information

Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman of FIDIC Contracts Committee

Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman of FIDIC Contracts Committee FIDIC Conditions of Contract IBC Conference 2003 Presentation Notes on: OVERVIEW OF THE NEW MAJOR CONTRACTS Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman

More information

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004) Basic Guide General Conditions of Contract for Construction Works (GCC 2004) February 2008 Preface The Construction Industry Development Board (CIDB) is a national body established by an Act of Parliament

More information

NEC3: Common Amendments and Contract Management Issues

NEC3: Common Amendments and Contract Management Issues NEC3: Common Amendments and Contract Management Issues Introduction 1 The NEC Suite of Contracts is not universally loved among lawyers. The suite has as many detractors as it has supporters within the

More information

The following amendments have been made to the June 2005 edition. 10 32.1 4 deleted: and of notified early warning matters

The following amendments have been made to the June 2005 edition. 10 32.1 4 deleted: and of notified early warning matters AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 43 Contract Data Part one, 1. 3 added: (with

More information

NEC3: ECC Project Manager Accreditation. The NEC Gold Standard

NEC3: ECC Project Manager Accreditation. The NEC Gold Standard NEC3: ECC Project Manager Accreditation The NEC Gold Standard I was very impressed with the programme and tutor, as it was completely relevant to our project and the work that I carry out on a daily basis.

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

Dated 29 February 2016. Flood Re Limited. Payments Dispute Process. Version 1.0

Dated 29 February 2016. Flood Re Limited. Payments Dispute Process. Version 1.0 Dated 29 February 2016 Flood Re Limited Payments Dispute Process Version 1.0 1. General 1.1 The following provisions will apply to all disputes referred to and conducted under this Payments Dispute Resolution

More information

The FIDIC Form of Contract. The Fourth Edition of the Red Book. 2nd Edition. Nael G. Bunni

The FIDIC Form of Contract. The Fourth Edition of the Red Book. 2nd Edition. Nael G. Bunni The FIDIC Form of Contract The Fourth Edition of the Red Book 2nd Edition Nael G. Bunni BSc, MSc, PhD, CEng, FIEI, FICE, FIStruct, FCIArb, FInstD, MconsEI b Blackwell Science Contents List of Figures List

More information

Click to edit Master title style

Click to edit Master title style Click to edit Master title style Presentation September 2013 Disallowance Under the NEC ICES Seminar Pioneering Bahrain Construction Public sector Energy Real estate London Tax IT Dubai Manchester Infra

More information

Risks in International Consultancy Appointments: The FIDIC White Book

Risks in International Consultancy Appointments: The FIDIC White Book Risks in International Consultancy Appointments: The FIDIC White Book An increasing number of UK based consultants are involved in international projects. Given the forecasted growth in global construction

More information

Customer Feedback Report

Customer Feedback Report Customer Feedback Report Registrants and Customers Analysis 2015 FTPIMPROVEMENT@GDC-UK.ORG Table of Contents I. Overview... 2 II. Results Registrants... 4 III. Key findings Registrants... 5 IV. Key themes

More information

CLIENT / PROJECT MANAGER AGREEMENT

CLIENT / PROJECT MANAGER AGREEMENT Authorship of this work is claimed by The Association of Construction Project Managers and any unauthorised reproduction constitutes an infringement in terms of the Copyright Act No 98 of 1978. CLIENT

More information

Giovanni Di Folco Letters of Intent, Bonds & Guarantees, Defects Liability Periods

Giovanni Di Folco Letters of Intent, Bonds & Guarantees, Defects Liability Periods [Type here] Giovanni Di Folco Letters of Intent, Bonds & Guarantees, Defects Liability Periods Other articles written by the same author: Enforcement of a DAB decision through an ICC partial award; (co-author

More information

The Role of Construction Managers. FIDIC offers two contributions on the question of the role of a construction manager in a construction contract:

The Role of Construction Managers. FIDIC offers two contributions on the question of the role of a construction manager in a construction contract: The Role of Construction Managers FIDIC offers two contributions on the question of the role of a construction manager in a construction contract: A. Notes on the use of FIDIC in the Middle East B. A Communication

More information

Data Centre Construction. Paul Jayson - Partner 20 March 2012

Data Centre Construction. Paul Jayson - Partner 20 March 2012 Data Centre Construction Paul Jayson - Partner 20 March 2012 Buy Benefits Control over facilities that handle and store data Bespoke rather than generic design and housing Security Disadvantages Build

More information

CONTRACTING HINTS AND TIPS

CONTRACTING HINTS AND TIPS CONTRACTING HINTS AND TIPS Contents 1. Contract formation 2. Entire agreement clauses 3. Warranties and indemnities 4. Time of the essence 5. Contract variation 6. Exclusion and limitation clauses 7. Exercising

More information

Risk in Construction

Risk in Construction Risk in Construction Market Research prepared for June 2014 In association with the Chartered Institution of Civil Engineering Surveyors, The Institution of Civil Engineers and the UK s leading Design

More information

Explaining an architect s services. General information on the usual tasks undertaken by an architect

Explaining an architect s services. General information on the usual tasks undertaken by an architect Explaining an architect s services General information on the usual tasks undertaken by an architect June 2008 What an architect may do for you Introduction The root cause of disputes and complaints against

More information

ENERGY PERFORMANCE CONTRACT

ENERGY PERFORMANCE CONTRACT DATED DAY OF ENERGY PERFORMANCE CONTRACT THE CUSTOMER SPECIFIED IN THE FORMAL INSTRUMENT OF AGREEMENT -AND- THE ESCO SPECIFIED IN THE FORMAL INSTRUMENT OF AGREEMENT [This document is a DRAFT provided only

More information

Home Warranty Insurance - Victoria Insurance Policy

Home Warranty Insurance - Victoria Insurance Policy Home Warranty Insurance - Victoria Insurance Policy CBHWA VIC 1208 Effective Date 01 December 2008 Table of Contents Calliden Home Warranty Insurance - Victoria Insurance Policy Important Information 02

More information

What's Wrong with Project Management? Introduction. Welcome to the November 2009 INSIGHTS published by acumen7.

What's Wrong with Project Management? Introduction. Welcome to the November 2009 INSIGHTS published by acumen7. Welcome to the November 2009 INSIGHTS published by acumen7. The purpose of this newsletter is to bring you new perspectives on key subjects to stimulate your own thoughts and ideas. In each edition (which

More information

Owner-Builder VIC Resıdentıal Constructıon Warranty Insurance

Owner-Builder VIC Resıdentıal Constructıon Warranty Insurance Owner-Builder VIC Resıdentıal Constructıon Warranty Insurance Important Notices The policy is made up of this policy wording, any endorsements and the certificate of insurance. You should read those documents

More information

Overview 1) Grantee s procurement requirements must be in conformance with the appropriate applicable Federal, State, and local laws.

Overview 1) Grantee s procurement requirements must be in conformance with the appropriate applicable Federal, State, and local laws. The award of Federal funds does not exempt the Grantee organization from compliance with State, and local requirements. When similar requirements exist at all levels, the rule of thumb is that the most

More information

FIDIC users guide A practical guide to the 1999 Red and Yellow Books. Brian W. Totterdill

FIDIC users guide A practical guide to the 1999 Red and Yellow Books. Brian W. Totterdill FIDIC users guide A practical guide to the 1999 Red and Yellow Books Brian W. Totterdill Published by Thomas Telford Publishing, Thomas Telford Ltd, 1 Heron Quay, London E14 4JD. URL: www.thomastelford.com

More information

PREFACE. The Contract for the Supply and Delivery of Goods has been prepared for use in supplies contracts which have the following characteristics:

PREFACE. The Contract for the Supply and Delivery of Goods has been prepared for use in supplies contracts which have the following characteristics: Supply Chain Management Document Number: SCM006 Document Title: Supply Contract Version: 01 Purpose: Standard contract for all supplies of goods PREFACE The Contract for the Supply and Delivery of Goods

More information

C1.2 CONTRACT DATA PROVIDED BY EMPLOYER (ECC3)

C1.2 CONTRACT DATA PROVIDED BY EMPLOYER (ECC3) C1.2 CONTRACT DATA PROVIDED BY EMPLOYER (ECC3) The conditions of contract are the NEC3 Engineering and Construction Contract (June 2005), copies of which may be obtained from the South African Institution

More information

Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals

Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals Journal of Construction in Developing Countries, Vol. 16(1), 41 67, 2011 Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals Visuth Chovichien

More information

GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES

GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES REQUEST FOR QUALIFICATIONS GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES NEW DINING HALL MONTANA STATE UNIVERSITY Bozeman, Montana PPA NO. 15-0103 Campus Planning, Design & Construction Plew Building

More information

Warranties, Bonds and Guarantees in the Construction World

Warranties, Bonds and Guarantees in the Construction World Warranties, Bonds and Guarantees in the Construction World Presented by Gregory Buckley Senior Associate Jonathan Robinson Senior Solicitor McGrigors Construction and Engineering Team Warranties, Bonds

More information

Dr. Simon Chee, Professor Michael Hor, Distinguished Guests, Ladies and. 2. Hong Kong has never been short of infrastructure and construction

Dr. Simon Chee, Professor Michael Hor, Distinguished Guests, Ladies and. 2. Hong Kong has never been short of infrastructure and construction Speech by the Hon Rimsky Yuen, SC, JP, Secretary for Justice Hong Kong Construction Arbitration Centre & University of Hong Kong Joint Conference on Construction Dispute Resolution 2015 Resolution of Construction

More information

Curriculum Vitae Ian Mansfield

Curriculum Vitae Ian Mansfield 18 Throstle est Way Tel: 01335 360716 Brailsford Mobile: 07925 532632 Ashbourne Email:ian.mansfield@btopenworld.com Derbyshire DE6 3DB Curriculum Vitae Ian Mansfield Personal Profile Director, General

More information

How To Write A Contract In The European

How To Write A Contract In The European (Form-9) Agreement with Contractor for THIS AGREEMENT (hereinafter, together with the appendices and all the documents annexed hereto and forming an integral part hereof, referred to as the Contract )

More information

PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS

PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS 2014 Public Sector Standard Conditions of Contract for Construction Works 2014 Building and Construction Authority First published 1995

More information

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the

More information

Sealed bids will be received by the City of Dearborn, at the Office of the Purchasing

Sealed bids will be received by the City of Dearborn, at the Office of the Purchasing CITY OF DEARBORN ADVERTISEMENT FOR NATURAL GAS PROVIDER TO THE CITY OF DEARBORN, MICHIGAN Sealed bids will be received by the City of Dearborn, at the Office of the Purchasing Agent, 2951 Greenfield, Dearborn,

More information

The role will require the management of consultancy and in-house teams in the successful execution of the estates strategy.

The role will require the management of consultancy and in-house teams in the successful execution of the estates strategy. Senior Project Manager Job Description Reference: 102014/51 Job Title: Senior Project Manager Purpose of Role: The University is committed to providing an environment conducive to high quality teaching

More information

PPC2000 Contracts RICS East of England and CIOB - Framework and Partnering Agreements CPD 21 June 2010 Richard Cooke. Contents.

PPC2000 Contracts RICS East of England and CIOB - Framework and Partnering Agreements CPD 21 June 2010 Richard Cooke. Contents. PPC2000 Contracts RICS East of England and CIOB - Framework and Agreements CPD 21 June 2010 Richard Cooke Contents Background Parties and Contracts Documents Early Involvement Pre-Construction Phase Construction

More information

PRACTICE NOTES FOR QUANTITY SURVEYORS

PRACTICE NOTES FOR QUANTITY SURVEYORS PRACTICE NOTES FOR QUANTITY SURVEYORS Preface Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant Quantity Surveyors and the Hong Kong

More information

Thames Water Utilities Limited. Settlement deed

Thames Water Utilities Limited. Settlement deed Thames Water Utilities Limited Settlement deed DATED [ ] THAMES WATER UTILITIES LIMITED the Undertaker [ ] the Owner DEED relating to the mitigation of the effects of settlement arising from the construction

More information

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011 BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under

More information

NHS Standard Contract 2015/16 General Conditions

NHS Standard Contract 2015/16 General Conditions NHS Standard Contract 2015/16 Draft for consultation December 2014 NHS Standard Contract 2015/16 Draft for consultation Version number: 1 First published: December 2014 Updated: Prepared by: NA NHS Standard

More information

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should

More information

AS 11000: General conditions of contract

AS 11000: General conditions of contract STATEMENT Embargoed until 23 January 2015 AS 11000: General conditions of contract Standards Australia (SA) Technical Committee MB-010, General Conditions of Contract, is currently revising the suite of

More information

WHAT MAKES AN INTELLIGENT CLIENT? SUMMARY

WHAT MAKES AN INTELLIGENT CLIENT? SUMMARY WHAT MAKES AN INTELLIGENT CLIENT? Report of seminar 166 held on 16th November 2011 at the Institution of Civil Engineers, 1 Great George Street, London SUMMARY v KEY CONCLUSIONS KEY CONCLUSIONS Leaders

More information

A Guidance Note to. Conditions of Contract for Consultancy Services (2005)

A Guidance Note to. Conditions of Contract for Consultancy Services (2005) A Guidance Note to Conditions of Contract for Consultancy Services (2005) This Guidance Note is based on a document prepared by the Auckland Region Contract Group, and verified by ACENZ, in February 2005.

More information

Guide to Reviewing Contract Documentation

Guide to Reviewing Contract Documentation Guide to Reviewing Contract Documentation Introduction In order to help members address the issues associated with the review of contracts The Royal Institute of British Architects (RIBA), in association

More information

International Accounting Standard 11 Construction Contracts

International Accounting Standard 11 Construction Contracts International Accounting Standard 11 Construction Contracts Objective The objective of this Standard is to prescribe the accounting treatment of revenue and costs associated with construction contracts.

More information

Geoff Schmitt FRICS FInstCES FCIArb. Mission Statement. Major Projects. Potential Target Locations. Paper Summary

Geoff Schmitt FRICS FInstCES FCIArb. Mission Statement. Major Projects. Potential Target Locations. Paper Summary Geoff Schmitt FRICS FInstCES FCIArb Dispute Resolution Consultant Expert Witness Overseas civil engineering projects CONTRACTING IN THE GLOBAL MARKET PLACE Geoffrey SCHMITT, United Kingdom Over 40 years

More information

TENDER DOCUMENTS PROCUREMENT OF GOODS PRICE QUOTATIONS. Public Procurement Board. Accra, Ghana

TENDER DOCUMENTS PROCUREMENT OF GOODS PRICE QUOTATIONS. Public Procurement Board. Accra, Ghana TENDER DOCUMENTS PROCUREMENT OF GOODS PRICE QUOTATIONS Public Procurement Board Accra, Ghana October 2003 i Table Contents Table Contents... i Introduction and Instructions... 1 Section I. Invitation for

More information

ANNEX 8 Contract Management Strategy

ANNEX 8 Contract Management Strategy ANNEX 8 Contract Management Strategy Bath & North East Somerset, Bristol, North Somerset and South Gloucestershire Councils working together to improve your local transport Contract Management Strategy

More information

CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO 2015-6 1

CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO 2015-6 1 CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO 2015-6 1 PART 3G Contracts Standing Orders 2015/16 Definitions Aggregation is the combining together of the total contract value from separate contracts

More information

IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer

IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer THE ROLE OF THE ENGINEER IN FIDIC 99 RED BOOK COULD IT BE PERFORMED BY A SUPERVISION CONSULTANT & A CONSTRUCTION MANAGER? Dr. Munther M. Saket December 2010 The Role of the Engineer 1 The ENGINEER S ROLE

More information

Trading during difficult times for SMEs. November, 2009

Trading during difficult times for SMEs. November, 2009 November, 2009 Introduction In an effort to support small and medium sized enterprises (SMEs), which constitute the main fabric of the upstream oil and gas supply chain, the Supply Chain Forum of Oil

More information

ICC UNIFORM RULES FOR CONTRACT BONDS

ICC UNIFORM RULES FOR CONTRACT BONDS ICC UNIFORM RULES FOR CONTRACT BONDS issued as ICC publication No. 524, adopted by the ICC Executive Board on 23 April 1993, come into effect on 1 January 1994 Copyright 1993 International Chamber of Commerce.

More information

Provision of Managed Network Services to the Transport for NSW [FIVE] ORDER FORMS

Provision of Managed Network Services to the Transport for NSW [FIVE] ORDER FORMS 1 Provision of Managed Network Services to the Transport for NSW [FIVE] S Order Form This Order is placed under this Agreement between the Contractor and the Contract Authority and includes Parts A, B

More information

Trelleborg Sealing Solutions Germany GmbH Handwerkstr. 5-7, 70565 Stuttgart. General Conditions of Purchase for Components

Trelleborg Sealing Solutions Germany GmbH Handwerkstr. 5-7, 70565 Stuttgart. General Conditions of Purchase for Components Trelleborg Sealing Solutions Germany GmbH Handwerkstr. 5-7, 70565 Stuttgart General Conditions of Purchase for Components 1. Basic Provisions 1.1 The General Conditions of Purchase of Trelleborg Sealing

More information

Construction Contracts

Construction Contracts 65 Accounting Standard (AS) 7 Construction Contracts Contents OBJECTIVE SCOPE Paragraph 1 DEFINITIONS 2-5 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 6-9 CONTRACT REVENUE 10-14 CONTRACT COSTS 15-20

More information

Smart Meters Programme Schedule 2.5. (Security Management Plan) (CSP South version)

Smart Meters Programme Schedule 2.5. (Security Management Plan) (CSP South version) Smart Meters Programme Schedule 2.5 (Security Management Plan) (CSP South version) Schedule 2.5 (Security Management Plan) (CSP South version) Amendment History Version Date Author Status v.1 Signature

More information

NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS

NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS NAS 13 NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS CONTENTS Paragraphs OBJECTIVE SCOPE 1 2 DEFINITIONS 3 6 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 7 10 CONTRACT REVENUE 11 15 CONTRACT

More information

AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder

AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder AGREEMENT made as of the day of in the year of (In words, indicate day, month and year) BETWEEN the Owner: (Name,

More information

CONSTRUCTION DISPUTE AVOIDANCE NEWSLETTER (number 49)

CONSTRUCTION DISPUTE AVOIDANCE NEWSLETTER (number 49) CONSTRUCTION DISPUTE AVOIDANCE NEWSLETTER (number 49) BONDS AND GUARANTEES In difficult economic times, procuring security for performance of obligations will be a significant concern for many parties

More information

NZS 3910:2013. Conditions of contract for building and civil engineering construction NZS 3910:2013. New Zealand Standard

NZS 3910:2013. Conditions of contract for building and civil engineering construction NZS 3910:2013. New Zealand Standard New Zealand Standard Conditions of contract for building and civil engineering construction Superseding (in part) NZS 3910:2003 NZS 3910:2013 COMMITTEE REPRESENTATION This Standard was prepared under the

More information

Statutes in translation Please note that this translations are not official translations. The translation is furnished for information purposes only

Statutes in translation Please note that this translations are not official translations. The translation is furnished for information purposes only Statutes in translation Please note that this translations are not official translations. The translation is furnished for information purposes only and the documents are not legal documents. The texts

More information

Construction Contracts

Construction Contracts STATUTORY BOARD FINANCIAL REPORTING STANDARD SB-FRS 11 Construction Contracts This version of SB-FRS 11 does not include amendments that are effective for annual periods beginning after 1 January 2015.

More information

How To Account For Construction Contracts In Hong Kong Kongsong Accounting Standard 11

How To Account For Construction Contracts In Hong Kong Kongsong Accounting Standard 11 HKAS 11 Issued October 2004Revised March 2010 Hong Kong Accounting Standard 11 Construction Contracts COPYRIGHT Copyright 2011 Hong Kong Institute of Certified Public Accountants This Hong Kong Financial

More information