Giovanni Di Folco Letters of Intent, Bonds & Guarantees, Defects Liability Periods

Size: px
Start display at page:

Download "Giovanni Di Folco Letters of Intent, Bonds & Guarantees, Defects Liability Periods"

Transcription

1 [Type here] Giovanni Di Folco Letters of Intent, Bonds & Guarantees, Defects Liability Periods

2 Other articles written by the same author: Enforcement of a DAB decision through an ICC partial award; (co-author Mark Tiggeman Partner of the international law firm Kennedys); Schedule and forensic delay analysis services; Quantum damages analysis services cost based claims; Dispute boards a Contractor s perspective; What do Contractors think of DABs 10 years after using FIDIC 1999 Contracts; Using Dispute Boards Why? Best use/wrong use of Dispute Boards; The use of the Primavera software for the Management of Infrastructure Projects in Romania; Using Dispute Boards. The Romanian experience of Dispute Boards; International Contracting A Consulting Engineer`s Perspective.

3 PREFACE Engineers, Lawyers, Contract Managers and Practitioners are required - during the performance of their professions and specialisms in Contract Management and Construction law - to deal with Letters of Intent, Bonds and Guarantees and the Defects Liability Period applicable in some form or other to the projects they will deal with during their careers. Although the above aspects of Contract and Construction law may appear as straight forward, in reality they are not and much abuse and disputes arise on projects due to misunderstanding of these aspects and lack of understanding of Contract law. This paper aims at providing some clarity to the professional that is called upon dealing with these aspects of contract within an international environment and in respect of the use of Standard Forms of Contract like FIDIC and NEC.

4 LETTERS OF INTENT What is a Letter of Intent (LOI)? Consequently, it may be construed that LOI represents a communication expressing an intention of a party to enter into a contract with another party at a future date. LOI creates no liability in regard to that future contract but it is intended to give some measure of security to the party commencing work, pending conclusion of the contract. Black s Law Dictionary provides that the letter of Intent (hereinafter referred to as LOI ) is a written statement detailing the preliminary understanding of parties who plan to enter into a contract or some other agreement; a noncommittal writing preliminary to a contract. A letter of intent is not meant to be binding and does not hinder the parties from bargaining with a third party. Business people typically mean not to be bound by a letter of intent, and courts ordinarily do not enforce one; but courts occasionally find that a commitment has been made. The phrase Letter of Intent is not a term of art, its meaning and effect depend on the circumstances of each case ERDC Group Ltd v Brunel University [2006] B.L.R 255 Judge Lloyd QC said: Letters of Intent come in all sorts of forms. Some are merely expressions of hope; others are firmer but make it clear that no legal consequences ensue; others presage a contract and may be tantamount to an agreement subject to contract ; others are in reality that contract in all but name. There can therefore be no prior assumptions, such as looking to see if words such as letters of intent have or have not been used.

5 When should one enter into a LOI? Expiry of a LOI Purpose of a LOI A Letter of Intent should only be used where there are good reasons to start work in advance of finalising the contract documents e.g. in cases of commercial urgency and never as a substitute for a building contract. In Cunningham v Collett [2006] EWHC 1771 (TCC), (2007) 113 Con LR 142 HHJ Coulson laid down situations where a careful Letter of Intent may be appropriate: the scope of work is agreed or there is a clear mechanism in place for it to be agreed; the price is either agreed or there is a clear mechanism in place for it to be agreed; the contract terms are, or likely to be, agreed in the near future; and there are good reasons to start work in advance of the finalisation of all the contract documents. A LOI would expire if it is not extended by the parties and if the Contract is not signed within the time stated in the LOI. The purpose of the LOI is to enable the Contractor to commence the Works and to secure its entitlements to receive the related payment until a binding Contract would be concluded. In order to assess the specific effects that it produces, each LOI has to be interpreted based on its express wording. However, it has been generally accepted that a LOI is a nonbinding statement of the future intention of both parties that entitles one part to start the works and to receive the related payment; otherwise it would be construed as unjust enrichment of the other part. A LOI allows the works to commence. In order to safeguard the parties entitlements, the LOI should contain a limitation of the value of the works that can

6 be executed and paid until the conclusion of a binding contract between the parties. Contents of the LOI Usually, a LOI may comprise the following: Aim of the LOI; Terms and conditions applying to the works specified within the LOI; Insurances; Risk management Procedures (internal policies); Payment provisions and caps on payments; Dispute resolution Procedures; Lockout Procedures; Ending of LOI arrangement; Governing Law. such creates obligations and leads to a sequence of events. So if for whatever reason the parties wish to sign a Letter of Intent such has to be clearly worded so that it is not confused with a Letter of Acceptance. Under NEC there are no restrictions to the use of Letters of Intent, however there is a lot of criticism from the construction industry when LOI operates for a long period of time as the LOI does not provide the required mechanism for real-time risk and change management that the NEC stands for. BONDS & GUARANTEES Generalities Conclusions The wording of a LOI should not be ambiguous in order to avoid misunderstandings and a LOI should clearly state that it is an interim agreement pending negotiation of the main contract. The Contract procedure provided by FIDIC does not envisage the use of LOI mainly because the Time for Completion is calculated from the Commencement Date. Under FIDIC there are provisions for the Employer to issue a Letter of Acceptance and Commonly, in all forms of Construction Contracts, there are three different types of guarantees/bonds that refer to the advance payment, performance of the works and

7 retention money, which are called guarantees or bonds, depending on each form of Contract. Thus, within the FIDIC Contracts, the aforementioned documents are called guarantees while the New Engineering and Construction Contract (hereinafter referred to as NEC ) refers to them as bonds. The advance payment guarantee/bond, the performance security/performance bond and the retention money guarantee/bond represent a payment mechanism and they can differ through their functions, as it will be presented below. All the guarantees/bonds have to be issued by an entity approved by the Employer (FIDIC Contracts) and the Project Manager (NEC Contract) in the form provided within the contract documents. Advance Payment Guarantee and Advance Payment Bond The advance payment is an interest free loan granted by the Employer that is usually used for the Contractor s mobilization or as otherwise provided for in the contract. The value of the advance payment (i.e. the percentage) and the method of payment (i.e. one instalment or more) are stated in the contract documents - in the Appendix to Tender (FIDIC Contracts) and within the Contract Data (NEC). The advance payment shall be paid by the Employer only upon receiving of the Advance Payment guarantee/bond covering the advance payment. However, under NEC, there may be cases when a bond is not required. There is no specific term for the advance payment guarantee to be provided by the Contractor under FIDIC Contracts and the sanction for the Contractor will be the late payment of the advance. In any case no advance payment can be paid by the Employer until the performance security is provided to this. Under NEC, if the advance bond is required and such is not provided within four weeks of the time agreed for its provision and the related notification of the Project Manager, this represents a severe default and even ground for termination. The value of the Advance Payment guarantee/bond may be gradually reduced with the amount repaid to the Employer; however the Contractor must ensure that the

8 guarantee/bond is valid and enforceable until the full repayment of the advance payment. Performance Security and Performance Bond to provide a Performance Security. The situation is similar on NEC when the Parties decide not to apply Option X13. Under both FIDIC and NEC Contracts, failure to provide the performance security/performance bond within the time specified in the contract represents a severe breach and may be used as ground for termination. The value of the performance security/bond can be reduced once the Works are taken over by the Employer, upon agreement of the parties and also depending on the governing legislation. However, the performance security/bond has to remain valid and enforceable until the Performance Certificate is issued (FIDIC), or the Defects Certificate under NEC. The performance security/bond has to be issued in a value (percentage) stated in the contract documents - in the Appendix to Tender (FIDIC Contracts), within the Contract Data (NEC), guarantees the quality, quantity and timely fulfilment of the Contract, and of the Contractor s obligations assumed under the Contract, including the remedy of defects. It is to be noted that within the FIDIC Contracts if no amount is stated in the Appendix to Tender, than there is no requirement for the Contractor Types of performance bonds/guarantees There are two different types of performance bonds/guarantees: Conditional a bond/guarantee that is conditional upon the occurrence of a particular event; the beneficiary may called upon the bond/guarantee only after proving a breach and only for the amount that covers the damage that had been proved;

9 Unconditional or on demand the beneficiary may call upon the guarantee/bond only in the manner prescribed therein and without proving any breach /damage for the entire amount of the bond/guarantee. Retention Money Guarantee and Retention Money Bond (FIDIC Contracts) or within the Contract Data (NEC) and this amount shall be halved upon the Employer s taking over of the works. However, such guarantee bond has to be valid until the end of the Defects Notification Period (FIDIC) or until the issuance of the Defects Certificate (NEC). DEFECTS LIABILITY PERIODS The purpose of the retention money guarantee/bond is to assure the Employer that there are sufficient funds for the remedy of the defects and to determine the Contractor to pay attention to the quality of the works performed so as to avoid or even eliminate the defects. FIDIC Contracts define the Defects Notification Period as being the period for notifying defects in the Works or a Section (as the case may be) under Sub-Clause 11.1 [Completion of Outstanding Work and Remedying Defects], as stated in the Appendix to Tender (with any extension under Sub-Clause 11.3 [Extension of the Defects Notification Period]), calculated from the date on which the Works or Section is completed as certified under Sub-Clause 10.1 [Taking Over of the Works and Sections]. Under the FIDIC Contracts, during the Defects Notification Periods, the Contractor has an obligation to remedy the defects notified after the completion of the Works. Distinction should be made either yes or not the defects had been assigned to the Contractor or to the Employer s use of the Works. The maximum amount of the retention money shall be stated in the Appendix to Tender

10 Thus, if the defects are assigned to the Contractor, it shall rectify the defects at its own expenses. However, if the defects are assigned to the Employer s use of the Works, upon receipt of the Engineer s instruction, the Contractor shall rectify such defects and shall receive the relevant payment. If the Contractor fails to remedy a defect, the Employer may instruct others or it can carry out the necessary works by itself in order to remedy the defect at the Contractor s cost or can even accept the work including defects and request the Engineer to determine a reduction of the Contract Price. Further, if the Contractor fails to remedy defects which prevent the Employer to use the Works or a Section for their intended purpose, the Employer shall be able to extend the Defects Notification Period. The Contractor s obligation to remedy the defects shall cease upon the Final Taking Over of the Works and the issuance of the Performance Certificate. The NEC defects correction period is a period of time specified within the Contract Data and pursuant to these Contracts A Defect is a part of the works which is not in accordance with the Works information or a part of the works designed by the Contractor which is not in accordance with the applicable law or the Contractor s design which the Project Manager has accepted. Under NEC, both the Contractor and the Supervisor have a common obligation to notify the other of all of the defects found before or after the completion of the Works. Furthermore, the Contractor is under an obligation to remedy/correct all the defects, either yes or not notified by the Supervisor. Similar to FIDIC Contracts, under the NEC form of Contract if the Contractor fails to remedy the defect, the Project Manager may instruct others or it can carry out the necessary works by itself in order to remedy the defect at the Contractor s cost, or can even accept the work including defects and reduce the contract Price accordingly.

11 About the author Giovanni Di Folco is the Senior Partner and President of Techno Engineering & Associates. He is a highly motivated expatriate multidiscipline professional Civil Engineer with 30 years of experience in the construction and consulting industry (transportation and heavy civil works). Experienced as Projects/Contracts Manager and Claims Expert with extensive international experience gained in multi-disciplinary Civil Engineering Projects in Italy, Iran, Libya, South Africa, Kingdom of Lesotho, Sultanate of Oman, United Arab Emirates, Greece and Romania, who attained professional recognition. Demonstrated acumen for construction and design engineering and management at all levels, acute awareness of cost control and project planning, ability to provide an immediate and calculated response to situations in the financial, contractual, legal and technical sectors of the profession, proven ability to sustain responsibilities from high level management through to operational level. He possesses acute awareness of specific Countries and International Law, the importance of quality, safety, the moral and legal responsibilities that they impose. Trained and operating to the most current standards of ISO 9000, ICE, NEC, JCT and FIDIC Conditions of Contract and the strict and controlled safety regimes in force and recognized internationally. Although specialized as a Pavement Engineer by profession, the international experience gained has enabled development of a wide diversity of his skills within the Civil Engineering Industry. During his career he has held positions of high responsibility such as Counsel, Engineer in the sense of FIDIC, Project Manager, Country Manager, Claim Expert and Adjudicator on major construction projects. He is a FIDIC expert in his own right. He possesses a vast experience in adjudication using the DAB procedure and ICC arbitration either as Expert of opinion, Attorney, Counsel for Claimant, Respondent.

12 Bucharest, ROMANIA 22 Muzelor Street, Sector 4 Tel: /77 Fax: Sofia, BULGARIA 1517, Haji Dimitar Residential Area 2j Vitinya Street BENI Building, entrance C Tel: (3) Fax: Doha, QATAR Al Muthanna Complex, Salwa Road PO BOX Tel: Fax:

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004) Basic Guide General Conditions of Contract for Construction Works (GCC 2004) February 2008 Preface The Construction Industry Development Board (CIDB) is a national body established by an Act of Parliament

More information

LECTURE NO.8 THE ROLE OF GUARANTEES AND BONDS IN INTERNATIONAL TRADE

LECTURE NO.8 THE ROLE OF GUARANTEES AND BONDS IN INTERNATIONAL TRADE LECTURE NO.8 THE ROLE OF GUARANTEES AND BONDS IN INTERNATIONAL TRADE A guarantor issues a guarantee or bond, usually a bank or an insurance company, on behalf of an exporter. It is a guarantee to the buyer

More information

Home Building Amendment Act 2011 No 52

Home Building Amendment Act 2011 No 52 New South Wales Home Building Amendment Act 2011 No 52 Contents Page 1 Name of Act 2 2 Commencement 2 Schedule 1 Amendment of Home Building Act 1989 No 147 3 Schedule 2 Amendment of Civil Liability Act

More information

Government of the Kingdom of Lesotho. Ministry of Public Works and Transport. Principal Building Agreement

Government of the Kingdom of Lesotho. Ministry of Public Works and Transport. Principal Building Agreement Government of the Kingdom of Lesotho Ministry of Public Works and Transport Project Employer Contractor Contract Date Contract No Principal Building Agreement MINISTRY OF PUBLIC WORKS & TRANSPORT BUILDING

More information

Section IX. Annex to the Particular Conditions - Contract Forms

Section IX. Annex to the Particular Conditions - Contract Forms Section IX. Annex to the Particular Conditions - Contract Forms Table of Forms Notification of Award Contract Agreement Performance Security Advance Payment Security Retention Money Security - 2 - Notification

More information

PERFORMANCE BONDS AND LABOUR AND MATERIAL PAYMENT BONDS: WHAT THE CONSTRUCTION INDUSTRY SHOULD KNOW

PERFORMANCE BONDS AND LABOUR AND MATERIAL PAYMENT BONDS: WHAT THE CONSTRUCTION INDUSTRY SHOULD KNOW PERFORMANCE BONDS AND LABOUR AND MATERIAL PAYMENT BONDS: WHAT THE CONSTRUCTION INDUSTRY SHOULD KNOW Deborah E. Palter, B.A., LL.B., J.D. What is a Bond? A bond is a three party written agreement. The three

More information

DASHBOARD CONFIGURATION SOFTWARE

DASHBOARD CONFIGURATION SOFTWARE DASHBOARD CONFIGURATION SOFTWARE RECITALS: The Contractor has designed and a web site for Client, and has agreed to maintain the said web site upon the terms and conditions hereinafter contained.] NOW

More information

PERFORMANCE BOND INSTRUCTIONS (FEB 2015)

PERFORMANCE BOND INSTRUCTIONS (FEB 2015) PERFORMANCE BOND INSTRUCTIONS (FEB 2015) 1. Introduction a. Procurement Services Division has posted two distinct performance bond forms. One is an indemnity bond. The other is a completion bond. The nature

More information

Appendix 18 NEC3 Options

Appendix 18 NEC3 Options Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and

More information

The New Standard Construction Contracts: NZS3910, 3916 and 3917

The New Standard Construction Contracts: NZS3910, 3916 and 3917 The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of

More information

ICC UNIFORM RULES FOR CONTRACT BONDS

ICC UNIFORM RULES FOR CONTRACT BONDS ICC UNIFORM RULES FOR CONTRACT BONDS issued as ICC publication No. 524, adopted by the ICC Executive Board on 23 April 1993, come into effect on 1 January 1994 Copyright 1993 International Chamber of Commerce.

More information

Defects liability period an introduction

Defects liability period an introduction Investing in Infrastructure International Best Legal Practice in Project and Construction Agreements January 2016 Damian McNair Partner, Legal M: +61 421 899 231 E: damian.mcnair@au.pwc.com Defects liability

More information

Decision of the Dispute Resolution Chamber

Decision of the Dispute Resolution Chamber Decision of the Dispute Resolution Chamber passed in Zurich, Switzerland, on 8 June 2007, in the following composition: Slim Aloulou (Tunisia), Chairman Philippe Diallo (France), member Zola Malvern Percival

More information

Performance bonds and bank guarantees

Performance bonds and bank guarantees Investing in Infrastructure International Best Legal Practice in Project and Construction Agreements January 2016 Damian McNair Partner, Legal M: +61 421 899 231 E: damian.mcnair@au.pwc.com Performance

More information

Security for payment: bonds and guarantees five pitfalls and protection

Security for payment: bonds and guarantees five pitfalls and protection Article This article first appeared in a slightly different form in Civil Engineering Surveyor, July 2010 Security for payment: bonds and guarantees five By Jonathan Hosie In the current economic climate,

More information

Open, Calderbank and Part 36 offers considerations and tactics

Open, Calderbank and Part 36 offers considerations and tactics Open, Calderbank and Part 36 offers considerations and tactics PJ Kirby QC 1. Introduction 1.1 In detailed assessment proceedings there will, as in all disputes, be advantages in settling the matter in

More information

How To Write A Contract In The European

How To Write A Contract In The European (Form-9) Agreement with Contractor for THIS AGREEMENT (hereinafter, together with the appendices and all the documents annexed hereto and forming an integral part hereof, referred to as the Contract )

More information

Fiskars is one of SEB:s customers. The photo shows some of Fiskars range. Bank Guarantees

Fiskars is one of SEB:s customers. The photo shows some of Fiskars range. Bank Guarantees Fiskars is one of SEB:s customers. The photo shows some of Fiskars range. Bank Guarantees Bank guarantees On the following pages we shall go into more detail presenting the various parties in a guarantee

More information

SB 588. Employment: nonpayment of wages: Labor Commissioner: judgment enforcement.

SB 588. Employment: nonpayment of wages: Labor Commissioner: judgment enforcement. SB 588. Employment: nonpayment of wages: Labor Commissioner: judgment enforcement. (1) The Enforcement of Judgments Law provides for the enforcement of money judgments and other civil judgments. Under

More information

Developments and Challenges of DAB Procedures Enforcement of a DAB s Decision

Developments and Challenges of DAB Procedures Enforcement of a DAB s Decision Developments and Challenges of DAB Procedures Enforcement of a DAB s Decision By Dr. ImadAl Jamal 1. The decision of a Dispute Adjudication Board ( DAB ) becomes a contract obligation by virtue of Sub-Clause

More information

BROKERAGE ACCOUNT AGREEMENT

BROKERAGE ACCOUNT AGREEMENT www.efghermes.com BROKERAGE ACCOUNT AGREEMENT One Region. One Investment Bank Egypt Emirates Jordan Kuwait Lebanon Oman Qatar Saudi Arabia Syria Date (DD/MM/YYYY) MCD Number Client Type Individual Non-Individual

More information

Return completed applications to: APAC-Texas, Inc. P.O. Box 20779 Beaumont, TX 77720 (409) 866-1444 Phone (409) 866-5541 Fax

Return completed applications to: APAC-Texas, Inc. P.O. Box 20779 Beaumont, TX 77720 (409) 866-1444 Phone (409) 866-5541 Fax Return completed applications to: APAC-Texas, Inc. P.O. Box 20779 Beaumont, TX 77720 (409) 866-1444 Phone (409) 866-5541 Fax APPLICATION FOR BUSINESS CREDIT Date: NOTE: This application for Business Credit

More information

and the President has proclaimed the following Law:

and the President has proclaimed the following Law: Unofficial translation The Saeima 1 has adopted and the President has proclaimed the following Law: THE INSURANCE CONTRACT LAW Chapter I GENERAL PROVISIONS Article 1. Definitions 1) sum insured - the amount

More information

SCHEDULE 14. Part 1 Performance Bond PERFORMANCE BOND NO.

SCHEDULE 14. Part 1 Performance Bond PERFORMANCE BOND NO. SCHEDULE 14 BONDS Part 1 Performance Bond PERFORMANCE BOND NO. $ KNOW ALL PERSONS BY THESE PRESENTS, that Contractor s Name as Principal ( the Principal ) and Surety / Insurance Company name and address,

More information

The ICC Uniform Rules for Demand Guarantees ("URDG") in Practice: A Decade of Experience

The ICC Uniform Rules for Demand Guarantees (URDG) in Practice: A Decade of Experience The ICC Uniform Rules for Demand Guarantees ("URDG") in Practice: A Decade of Experience A Contractor's View of the URDG Christopher R. Seppala Partner,White & Case LLP, Paris and Legal Advisor, FIDIC

More information

Taking Action. Dispute resolution, legal action and claims for negligence

Taking Action. Dispute resolution, legal action and claims for negligence Taking Action Dispute resolution, legal action and claims for negligence Taking Action Part 3: Dispute Resolution, taking legal action and claims for negligence Introduction If you believe an architect

More information

Warranties, Bonds and Guarantees in the Construction World

Warranties, Bonds and Guarantees in the Construction World Warranties, Bonds and Guarantees in the Construction World Presented by Gregory Buckley Senior Associate Jonathan Robinson Senior Solicitor McGrigors Construction and Engineering Team Warranties, Bonds

More information

Software Development. Standard Terms and Conditions. V2.0 January 2013

Software Development. Standard Terms and Conditions. V2.0 January 2013 Software Development Standard Terms and Conditions V2.0 January 2013 Elysium Ltd Milton House Whitehill Road Crowborough East Sussex TN6 1LB Tel: 01892 667411 Fax: 01829667433 Email: sales@elysium.ltd.uk

More information

Bonds. Brian E. Rawling, Brian E. Rawling & Associates

Bonds. Brian E. Rawling, Brian E. Rawling & Associates Bonds Brian E. Rawling, Brian E. Rawling & Associates It is now customary, and has been for several years, for employers in Hong Kong to request bonds to be provided by their main contractors. he usual

More information

After studying this chapter you should be able to understand: 8.1 The role of guarantees and bonds in international trade

After studying this chapter you should be able to understand: 8.1 The role of guarantees and bonds in international trade GUARANTEES OR BONDS Objectives After studying this chapter you should be able to understand: 8.1 The role of guarantees and bonds in international trade 8.2 Bonds: definition, parties involved, elements,

More information

Kingdom of the Netherlands

Kingdom of the Netherlands Kingdom of the Netherlands GENERAL GOVERNMENT PURCHASING CONDITIONS 2014 (ARIV 2014) Adopted by order of the Prime Minister, Minister of General Affairs, of 26 March 2014, no. 3132081 I General Article

More information

CLAIMS ADMINISTRATION SERVICES AGREEMENT

CLAIMS ADMINISTRATION SERVICES AGREEMENT Attachment D.13 CLAIMS ADMINISTRATION SERVICES AGREEMENT This AGREEMENT is made and entered into by and between SANTA BARBARA SCHOOL DISTRICTS hereinafter referred to as "DISTRICT", and KEENAN & ASSOCIATES,

More information

SURETY. and Title: (Any additional signatures appear on the last page of this Performance Bond.)

SURETY. and Title: (Any additional signatures appear on the last page of this Performance Bond.) Performance Bond Document A312 2010 CONTRACTOR: (Name, legal status and address) SURETY: (Name, legal status and principal place of business) OWNER: (Name, legal status and address) CONSTRUCTION CONTRACT

More information

The FIDIC Form of Contract. The Fourth Edition of the Red Book. 2nd Edition. Nael G. Bunni

The FIDIC Form of Contract. The Fourth Edition of the Red Book. 2nd Edition. Nael G. Bunni The FIDIC Form of Contract The Fourth Edition of the Red Book 2nd Edition Nael G. Bunni BSc, MSc, PhD, CEng, FIEI, FICE, FIStruct, FCIArb, FInstD, MconsEI b Blackwell Science Contents List of Figures List

More information

Workers Compensation Amendment (Miscellaneous Provisions) Regulation 2006

Workers Compensation Amendment (Miscellaneous Provisions) Regulation 2006 No 656 New South Wales Workers Compensation Amendment (Miscellaneous Provisions) Regulation under the Workers Compensation Act 1987 and Workplace Injury Management and Workers Compensation Act 1998 Her

More information

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011 BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under

More information

General Terms and Conditions of Sale and Delivery of Federatie Aandrijven en Automatiseren (Trading Companies)

General Terms and Conditions of Sale and Delivery of Federatie Aandrijven en Automatiseren (Trading Companies) General Terms and Conditions of Sale and Delivery of Federatie Aandrijven en Automatiseren (Trading Companies) Filed at the Registry of the Court of The Hague, the Netherlands, on 6 December 2011, under

More information

Construction Claims in

Construction Claims in Construction Claims in the Gulf ICES CPD Event 12/2012 ADMC Auditorium 19 December 2012 DISPUTES & INVESTIGATIONS ECONOMICS FINANCIAL ADVISORY MANAGEMENT CONSULTING Context» Aftermath of 2008 / 2009 financial

More information

Risks in International Consultancy Appointments: The FIDIC White Book

Risks in International Consultancy Appointments: The FIDIC White Book Risks in International Consultancy Appointments: The FIDIC White Book An increasing number of UK based consultants are involved in international projects. Given the forecasted growth in global construction

More information

[This translation is provided for guidance. The governing text is the Arabic text.] Form of Consultancy Engineering Services Contract (Supervision)

[This translation is provided for guidance. The governing text is the Arabic text.] Form of Consultancy Engineering Services Contract (Supervision) [This translation is provided for guidance. The governing text is the Arabic text.] Form of Consultancy Engineering Services Contract (Supervision) Section One Contract - Basic Document It has been agreed

More information

IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer

IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer THE ROLE OF THE ENGINEER IN FIDIC 99 RED BOOK COULD IT BE PERFORMED BY A SUPERVISION CONSULTANT & A CONSTRUCTION MANAGER? Dr. Munther M. Saket December 2010 The Role of the Engineer 1 The ENGINEER S ROLE

More information

Contractor s Claims Under The FIDIC Contracts For Major Works

Contractor s Claims Under The FIDIC Contracts For Major Works March 17, 2005 [This paper is to be published in the Construction Law Journal, London, in 2005]] International Construction Contracts and Dispute Resolution Co-Hosted by ICC and FIDIC In partnership with

More information

Directors Duties. Directors Duties

Directors Duties. Directors Duties Directors Duties The Companies Act 2014 (the Act ), for the first time, codifies directors duties, drawing together both existing statutory rules on transactions involving directors and also the various

More information

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES General Terms of Public Procurement in Service Contracts January 2015 Contents Introduction...3 Issues to be observed in applying...5 General Terms of Public Procurement in Service Contracts ()...9 1 Definitions...9

More information

Kentucky Department of Education Version of Document A312 2010

Kentucky Department of Education Version of Document A312 2010 Kentucky Department of Education Version of Document A312 2010 Performance Bond CONTRACTOR: (Name, legal status and address) SURETY: (Name, legal status and principal place of business) OWNER: (Name, legal

More information

A Guide to Directive 2014/17/EU on Credit Agreements for Consumers Relating to Residential Immovable Property (the Mortgage Credit Directive )

A Guide to Directive 2014/17/EU on Credit Agreements for Consumers Relating to Residential Immovable Property (the Mortgage Credit Directive ) Conseil européen des Professions immobilières European Council of Real Estate Professions A Guide to Directive 2014/17/EU on Credit Agreements for Consumers Relating to Residential Immovable Property (the

More information

Part E: Contract management

Part E: Contract management Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

General Terms of Public Procurement in Supply Contracts JYSE 2014 SUPPLIES

General Terms of Public Procurement in Supply Contracts JYSE 2014 SUPPLIES General Terms of Public Procurement in Supply Contracts January 2015 Contents Introduction...3 Issues to be observed in applying...5 General Terms of Public Procurement in Supply Contracts ()...8 1 Definitions...8

More information

AIA Document A312 - Electronic Format. Performance Bond

AIA Document A312 - Electronic Format. Performance Bond AIA Document A312 - Electronic Format Performance Bond THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES: CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS COMPLETION OR MODIFICATION. AUTHENTICATION

More information

BROKER AND CARRIER AGREEMENT

BROKER AND CARRIER AGREEMENT P.O. Box 889 394 NE Hemlock Redmond, OR 97756 BROKER AND CARRIER AGREEMENT All loads tendered by Central Oregon Truck Company ("Broker") and accepted for transportation by third party carriers ("Carrier")

More information

General Terms and Conditions of Assembly:

General Terms and Conditions of Assembly: General Terms and Conditions of Assembly: Contractor within the meaning of 67a of the Austrian Federal General Social Security Act. 1. GENERAL, SUBJECT MATTER OF THE CONTRACT 1.1 Between the Customer and

More information

Make sure your builder is registered.

Make sure your builder is registered. Marylanders purchase more than 10,000 new homes each year. The purchase of a new home is protected by Maryland law. Understanding your rights and responsibilities as a new home buyer protects your investment

More information

CONSTRUCTION DISPUTE AVOIDANCE NEWSLETTER (number 49)

CONSTRUCTION DISPUTE AVOIDANCE NEWSLETTER (number 49) CONSTRUCTION DISPUTE AVOIDANCE NEWSLETTER (number 49) BONDS AND GUARANTEES In difficult economic times, procuring security for performance of obligations will be a significant concern for many parties

More information

AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES

AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES Names of Parties 1. (Company Name) of (Company Address) ( Consultancy ). 2. Redline Group Ltd of 26-34 Liverpool Road, Luton. Beds LU1

More information

Back to Basics: Professional Indemnity Construction and Engineering

Back to Basics: Professional Indemnity Construction and Engineering Back to Basics: Professional Indemnity Construction and Engineering December 2015 Table of Contents Table of Contents... 2 Introduction... 3 Part A - Understanding the construction industry... 4 1 Construction

More information

CODE OF LAW PRACTICE Royal Decree No. (M/38) 28 Rajab 1422 [ 15-October 2001] Umm al-qura No. (3867) 17- Sha ban 1422-2 November 2001

CODE OF LAW PRACTICE Royal Decree No. (M/38) 28 Rajab 1422 [ 15-October 2001] Umm al-qura No. (3867) 17- Sha ban 1422-2 November 2001 CODE OF LAW PRACTICE Royal Decree No. (M/38) 28 Rajab 1422 [ 15-October 2001] Umm al-qura No. (3867) 17- Sha ban 1422-2 November 2001 PART ONE DEFINITION OF THE PRACTICE OF LAW AND ITS REQUIREMENTS Article

More information

Terms of Use/ Disclaimers/ Contract/ Agreement

Terms of Use/ Disclaimers/ Contract/ Agreement Website Development and Ongoing Services Agreement Terms of Use/ Disclaimers/ Contract/ Agreement Between You as the client and WideNet Consulting, LLC as the service provider. By using the services of

More information

GENERAL TERMS AND CONDITIONS OF SALE AND DELIVERY SENSUS

GENERAL TERMS AND CONDITIONS OF SALE AND DELIVERY SENSUS Article 1 Applicability GENERAL TERMS AND CONDITIONS OF SALE AND DELIVERY SENSUS 1.1 These terms and conditions are used by Sensus B.V., as well as by its affiliated companies, hereinafter referred to

More information

TITLE 18 INSURANCE DELAWARE ADMINISTRATIVE CODE 1. 900 Consumer Rights. 901 Arbitration of Automobile and Homeowners' Insurance Claims

TITLE 18 INSURANCE DELAWARE ADMINISTRATIVE CODE 1. 900 Consumer Rights. 901 Arbitration of Automobile and Homeowners' Insurance Claims DELAWARE ADMINISTRATIVE CODE 1 900 Consumer Rights 901 Arbitration of Automobile and Homeowners' Insurance Claims 1.0 Purpose and Statutory Authority 1.1 The purpose of this Regulation is to implement

More information

MUSIC RESOURCES TERMS AND CONDITIONS FOR SCHOOLS ( Conditions )

MUSIC RESOURCES TERMS AND CONDITIONS FOR SCHOOLS ( Conditions ) MUSIC RESOURCES TERMS AND CONDITIONS FOR SCHOOLS ( Conditions ) Please ensure all relevant staff have read and understood these Conditions before signing. Please complete, sign and return the Music Resources

More information

BELIZE LIMITED LIABILITY PARTNERSHIP ACT CHAPTER 258 REVISED EDITION 2003 SHOWING THE SUBSTANTIVE LAWS AS AT 31ST MAY, 2003

BELIZE LIMITED LIABILITY PARTNERSHIP ACT CHAPTER 258 REVISED EDITION 2003 SHOWING THE SUBSTANTIVE LAWS AS AT 31ST MAY, 2003 BELIZE LIMITED LIABILITY PARTNERSHIP ACT CHAPTER 258 REVISED EDITION 2003 SHOWING THE SUBSTANTIVE LAWS AS AT 31ST MAY, 2003 This is a revised edition of the Substantive Laws, prepared by the Law Revision

More information

Letters of Intent: Overcoming the Pitfalls

Letters of Intent: Overcoming the Pitfalls Julie Stagg Letters of Intent: Overcoming the Pitfalls Introduction No matter how forcefully lawyers may counsel against them, letters of intent (otherwise known as letters of authority or letters of instruction)

More information

MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS

MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS International Trade Centre, August 2010 Model Contracts for Small Firms: International Commercial Sale of Goods Contents

More information

AIA Document A310 TM 2010

AIA Document A310 TM 2010 AIA Document A310 TM 2010 Bid Bond CONTRACTOR: OWNER: «Lane County» «125 East Eighth Avenue BOND AMOUNT: $ PROJECT: (Name, location or address, and Project number, if any) «Lane County Adult Corrections

More information

GENERAL TERMS AND CONDITIONS

GENERAL TERMS AND CONDITIONS GENERAL TERMS AND CONDITIONS OF: Europe Retail Packing BV ABC Westland 315 2685 DD Poeldijk hereinafter to be referred to as: ERP Article 1 Definitions 1. In the present general terms and conditions, the

More information

B. Uniform Rules for Contract Bonds (URCB): Report of the Secretary-General (A/CN.9/478) [Original: English]

B. Uniform Rules for Contract Bonds (URCB): Report of the Secretary-General (A/CN.9/478) [Original: English] 594 Yearbook of the United Nations Commission on International Trade Law, 2000, vol. XXXI B. Uniform Rules for Contract Bonds (URCB): Report of the Secretary-General (A/CN.9/478) [Original: English] 1.

More information

388 Blohm Ave. PO Box 388 Aromas CA 95004-0388 (831)726-3155 FAX (831)726-3951 email aromaswd@aol.com ADDENDUM NO. 1

388 Blohm Ave. PO Box 388 Aromas CA 95004-0388 (831)726-3155 FAX (831)726-3951 email aromaswd@aol.com ADDENDUM NO. 1 388 Blohm Ave. PO Box 388 Aromas CA 95004-0388 (831)726-3155 FAX (831)726-3951 email aromaswd@aol.com May 6, 2015 To: All Plan Holders From: Vicki Morris General Manager Subject: Water Serviceline Installation

More information

Bankruptcy of a company involved in a debt restructuring agreement The position of creditors and the steps to be taken by them

Bankruptcy of a company involved in a debt restructuring agreement The position of creditors and the steps to be taken by them Bankruptcy of a company involved in a debt restructuring agreement The position of creditors and the steps to be taken by them 1. A brief overview on debt restructuring agreements Debt restructuring agreements

More information

GENERAL LIABILITY INSURANCE

GENERAL LIABILITY INSURANCE GENERAL LIABILITY INSURANCE 1/6 TABLE OF CONTENTS CONDITIONS OF GENERAL LIABILITY INSURANCE T001/2011 1. Policyholder and insured person 4 2. Insured event 4 3. Term of insurance contract 4 4. Insurance

More information

C O N T R A C T N o. F M V I D 2015/106. ACL Desktop

C O N T R A C T N o. F M V I D 2015/106. ACL Desktop Annex 4 To the Regulations of the Procurement Provision of Maintenance Service for the Computerised Accounting Audit Software ACL Desktop, procurement identification No. FM VID 2015/2016, organised by

More information

NPSA GENERAL PROVISIONS

NPSA GENERAL PROVISIONS NPSA GENERAL PROVISIONS 1. Independent Contractor. A. It is understood and agreed that CONTRACTOR (including CONTRACTOR s employees) is an independent contractor and that no relationship of employer-employee

More information

The Overview of Tanzania Legal Framework on Contract Management

The Overview of Tanzania Legal Framework on Contract Management The Overview of Tanzania Legal Framework on Contract Management OUTLINE 1. Introduction; 2. Public Procurement System; 3. Legal and Regulatory Framework; 4. Contract Formation; 5. Construction Contract

More information

TT ELECTRONICS INTEGRATED MANUFACTURING SERVICES LIMITED CONDITIONS OF PURCHASE

TT ELECTRONICS INTEGRATED MANUFACTURING SERVICES LIMITED CONDITIONS OF PURCHASE TT ELECTRONICS INTEGRATED MANUFACTURING SERVICES LIMITED CONDITIONS OF PURCHASE DEFINITIONS In these conditions of purchase: the Buyer means TT electronics integrated manufacturing services Ltd., the Supplier

More information

The Credit Information Companies (Regulation) Act, 2005 1

The Credit Information Companies (Regulation) Act, 2005 1 Disclaimer : Text of this Act/Bill/Rules is provided for information only. We undertake no responsibility for any errors/mistakes in the same. Please refer to the Gazette of India for the authentic text.

More information

General Terms of Public Procurement in service contracts JYSE 2009 SERVICES

General Terms of Public Procurement in service contracts JYSE 2009 SERVICES General Terms of Public Procurement in service contracts November 2009 Contents Introduction........................................................................................................................................3

More information

TERMS AND CONDITIONS OF PURCHASE FOR CONSTRUCTION WORKS OF SIEMENS-GROUP AUSTRIA ISSUED DECEMBER 2012

TERMS AND CONDITIONS OF PURCHASE FOR CONSTRUCTION WORKS OF SIEMENS-GROUP AUSTRIA ISSUED DECEMBER 2012 1 Scope These Terms and Conditions of Purchase for Construction Works apply to all purchase orders of SIEMENS Aktiengesellschaft Österreich and the companies affiliated to it ("SIEMENS") which, at least

More information

REQUEST FOR QUOTATIONS

REQUEST FOR QUOTATIONS ROMANIA NATIONAL AGENCY FOR FISCAL ADMINISTRATION REVENUE ADMINISTRATION MODERNIZATION PROJECT REQUEST FOR QUOTATIONS FOR PROJECT MANAGEMENT SOFTWARE RAMP/9 Country: ROMANIA Name of the Project: Revenue

More information

Terms and Conditions for Tax Services

Terms and Conditions for Tax Services Terms and Conditions for Tax Services In the course of delivering services relating to tax return preparation, tax advisory, and assistance in tax controversy matters, Brady, Martz & Associates, P.C. (we

More information

Bills of Quantity. D. Atkinson December 2000. Nature of Bills

Bills of Quantity. D. Atkinson December 2000. Nature of Bills Bills of Quantity D. Atkinson December 2000 Nature of Bills Bills of Quantities comprise a list of items of work which are briefly described. The Bills also provide a measure of the extent of work and

More information

PUBLIC Law, Chapter 394 LD 1703, item 1, 123rd Maine State Legislature An Act To Regulate Presettlement Lawsuit Funding

PUBLIC Law, Chapter 394 LD 1703, item 1, 123rd Maine State Legislature An Act To Regulate Presettlement Lawsuit Funding PLEASE NOTE: Legislative Information cannot perform research, provide legal advice, or interpret Maine law. For legal assistance, please contact a qualified attorney. Be it enacted by the People of the

More information

EXPERT RULES PROPOSAL OF EXPERTS AND NEUTRALS APPOINTMENT OF EXPERTS AND NEUTRALS ADMINISTRATION OF EXPERT PROCEEDINGS

EXPERT RULES PROPOSAL OF EXPERTS AND NEUTRALS APPOINTMENT OF EXPERTS AND NEUTRALS ADMINISTRATION OF EXPERT PROCEEDINGS EXPERT RULES PROPOSAL OF EXPERTS AND NEUTRALS APPOINTMENT OF EXPERTS AND NEUTRALS ADMINISTRATION OF EXPERT PROCEEDINGS EXPERT RULES PROPOSAL OF EXPERTS AND NEUTRALS APPOINTMENT OF EXPERTS AND NEUTRALS

More information

Personal Loan Agreement

Personal Loan Agreement March 2014 HSBC Bank Middle East Limited - PERSONAL LOAN AGREEMENT HSBC Bank Middle East Limited Personal Loan Agreement Copyright. HSBC Bank Middle East Limited 2014 ALL RIGHTS RESERVED. No part of this

More information

SUBCONTRACTOR LABOR AND MATERIAL PAYMENT BOND ("Bond") SURETY Address

SUBCONTRACTOR LABOR AND MATERIAL PAYMENT BOND (Bond) SURETY Address Bond # SUBCONTRACTOR LABOR AND MATERIAL PAYMENT BOND ("Bond") KNOW ALL PERSONS BY THESE PRESENTS; that SUBCONTRACTOR as Principal (the "Subcontractor"), and SURETY as Surety or Co-sureties (hereinafter

More information

SMALL CLAIMS RULES. (d) Record of Proceedings. A record shall be made of all small claims court proceedings.

SMALL CLAIMS RULES. (d) Record of Proceedings. A record shall be made of all small claims court proceedings. SMALL CLAIMS RULES Rule 501. Scope and Purpose (a) How Known and Cited. These rules for the small claims division for the county court are additions to C.R.C.P. and shall be known and cited as the Colorado

More information

Issued by the Association FME-CWM, P.O. Box 190, 2700 AD ZOETERMEER

Issued by the Association FME-CWM, P.O. Box 190, 2700 AD ZOETERMEER TRANSLATION of the "Algemene verkoop- en leveringsvoorwaarden voor de technologische industrie". Only the Dutch text of these conditions is authentic. In case of ambiguities or doubts as to the meaning

More information

1. Technical Offer Submission Sheet

1. Technical Offer Submission Sheet 8. Sample Forms SUMMARY Sample Form No. 1: 1. TECHNICAL OFFER SUBMISSION SHEET... 3 Sample Form No. 2: 2. PRICE OFFER SUBMISSION SHEET... 5 Sample Form No. 3: 3. BID SECURITY... 6 Sample Form No. 4: 4.

More information

Construction Breakfast Briefing: Performance Bonds

Construction Breakfast Briefing: Performance Bonds Construction Breakfast Briefing: Performance Bonds Philip Vaughan Partner Lucy Bushell Managing Associate 2 December 2014 Introduction Performance Bonds and purpose in construction On demand/conditional

More information

Client Care and Terms and Conditions

Client Care and Terms and Conditions Client Care and Terms and Conditions Introduction We set out below our standard terms and conditions which apply if we act for you. We also provide you with information relating to the Rules of Conduct

More information

ASBESTOS/LEAD SURVEY AND CONSULTING AGREEMENT BY AND BETWEEN NEW YORK UNIVERSITY / NYU HOSPITALS CENTER - OWNER - AND - CONSULTANT - --------- PROJECT

ASBESTOS/LEAD SURVEY AND CONSULTING AGREEMENT BY AND BETWEEN NEW YORK UNIVERSITY / NYU HOSPITALS CENTER - OWNER - AND - CONSULTANT - --------- PROJECT APPENDIX A ASBESTOS/LEAD SURVEY AND CONSULTING AGREEMENT BY AND BETWEEN NEW YORK UNIVERSITY / NYU HOSPITALS CENTER - OWNER - AND - CONSULTANT - --------- PROJECT DATED AS OF ASBESTOS/LEAD SURVEY AND CONSULTING

More information

This page left blank intentionally

This page left blank intentionally ATTACHMENT 13 PERFORMANCE AND PAYMENT BONDS This page left blank intentionally RFP #0606-14 Attachment 13: Payment & Performance Bonds Page 1 of 8 PAYMENT BOND (CALIFORNIA PUBLIC WORK) KNOW ALL MEN BY

More information

Trading during difficult times for SMEs. November, 2009

Trading during difficult times for SMEs. November, 2009 November, 2009 Introduction In an effort to support small and medium sized enterprises (SMEs), which constitute the main fabric of the upstream oil and gas supply chain, the Supply Chain Forum of Oil

More information

DATED 2016 [SURETY] and [CONTRACTOR] and SCHOOL OF ORIENTAL AND AFRICAN STUDIES PERFORMANCE BOND

DATED 2016 [SURETY] and [CONTRACTOR] and SCHOOL OF ORIENTAL AND AFRICAN STUDIES PERFORMANCE BOND DATED 2016 [SURETY] (1) and [CONTRACTOR] (2) and SCHOOL OF ORIENTAL AND AFRICAN STUDIES (3) PERFORMANCE BOND relating to NEC3 OPTION A TERM SERVICE CONTRACT FOR INTEGRATED FACILITIES MANAGEMENT SERVICES

More information

Managing Payment Risks on International Construction Projects

Managing Payment Risks on International Construction Projects Managing Payment Risks on International Construction Projects January 23, 2006 (The following outline was used in a presentation to the Overseas Construction Association of Japan, Inc. (OCAJI) on July

More information

This AGREEMENT is made as of the day of in the year of, by and between the following parties, for the sale of materials.

This AGREEMENT is made as of the day of in the year of, by and between the following parties, for the sale of materials. MCPU Standard Contract 101 Agreement Between Seller and Buyer For Sale on Credit This document has important legal consequences. Consultation with an attorney is recommended with respect to its completion,

More information

A Guidance Note to. Conditions of Contract for Consultancy Services (2005)

A Guidance Note to. Conditions of Contract for Consultancy Services (2005) A Guidance Note to Conditions of Contract for Consultancy Services (2005) This Guidance Note is based on a document prepared by the Auckland Region Contract Group, and verified by ACENZ, in February 2005.

More information

Voluntary Winding up of Company

Voluntary Winding up of Company Voluntary Winding up of Company Voluntary Winding up of Company Circumstances in which company may be wound up voluntarily 132. Subject to section 200(3), a company may be wound up voluntarily (a) when

More information

[This translation is provided for guidance. The governing text is the Arabic text.] Form of Consultancy Engineering Services Contract (Design)

[This translation is provided for guidance. The governing text is the Arabic text.] Form of Consultancy Engineering Services Contract (Design) [This translation is provided for guidance. The governing text is the Arabic text.] Form of Consultancy Engineering Services Contract (Design) Section One Contract - Basic Document It has been agreed in

More information

Split Dollar Life Insurance Agreement

Split Dollar Life Insurance Agreement Agreement Document 1562A Access to this document and the LeapLaw web site is provided with the understanding that neither LeapLaw Inc. nor any of the providers of information that appear on the web site

More information

QUOTATION DOCUMENTS TERMS AND CONDITIONS OF AGREEMENT

QUOTATION DOCUMENTS TERMS AND CONDITIONS OF AGREEMENT Page 1 of 5 INTERPRETATION QUOTATION DOCUMENTS TERMS AND CONDITIONS OF AGREEMENT FOR THE SUPPLY AND DELIVERY OF FOODSTUFF OR AMENITIES ITEM(S) FOR THE PERIOD SPECIFIED IN THE AWARD LETTER In these Terms

More information

MODEL TRIPARTITE AGREEMENT (FOR ROAD PROJECTS) BETWEEN PROJECT AUTHORITY, CONCESSIONAIRE AND INFRASTRUCTURE DEBT FUND

MODEL TRIPARTITE AGREEMENT (FOR ROAD PROJECTS) BETWEEN PROJECT AUTHORITY, CONCESSIONAIRE AND INFRASTRUCTURE DEBT FUND MODEL TRIPARTITE AGREEMENT (FOR ROAD PROJECTS) BETWEEN PROJECT AUTHORITY, CONCESSIONAIRE AND INFRASTRUCTURE DEBT FUND This Tripartite Agreement 1 is made at [New Delhi] on the ***** 2 day of *****, 201*

More information