1 THE NEW ENGINEERING CONTRACT: IMPROVED PROCUREMENT AND CONTRACTING WITH ITS SIMPLICITY, CLARITY AND GOOD PROJECT MANAGEMENT PROVISIONS ABSTRACT THURLOW, P.N. Thurlow Associates cc: Industrial Project Managers 4 Hillcrest Avenue, Craighall Park, 2196, South Africa Tel: , thurlow@mweb.co.za The international NEC suite of contracts published by the Institution of Civil Engineers in London is based on the principles of simplicity, clarity and a stimulus to good project management. The contract is widely used internationally and is now an integral part of the procurement and contracting scenario in RSA. The NEC s flexible structure is opening opportunities for new and wider project management applications not only in its priced, incentive and cost reimbursable options but in its firm foundations in competent time, cost, scope and risk management provisions. The use of the NEC is finding clients, professionals and contractors somewhat shy of its project management procedures, not because the contract is complex but merely as inexperience of the new, simple, clear ways of procuring and executing contracts. This paper analyses many of the traditional procurement and contracting philosophies and contrasts them with the improved, simple procedures under the NEC. The key elements are the competently structured, resource-driven programmes, their method statement provisions and their priced relationship with the activity schedule. Users are often confounded to find these new principles, along with time and cost risk allowances, float and health and safety provisions now being part of the management of their contracts. The management of change under the compensation event procedure rests on the contractor providing integrated time, cost and resource quotations largely in advance of the new or changed work being executed. The efficacy of these procedures in protecting both parties interests requires the construction industry players to take a bold step forward in embracing the new predictive, project management techniques and procedures. The NEC s use of adjudication as a contractually implemented decision to resolve any disputes has highlighted the need for skilled adjudicators to have honed time, cost and contractual skills within the terms of the NEC s procedures themselves. KEY WORDS: NEC Contract; Contract Procurement, Project Management; Partnering INTRODUCTION It is widely and wrongly believed that, in good project management practice, conditions of contract should remain in the bottom drawer until such time the lawyers call for them. This is due to the adversarialism built into traditional conditions of contract tainting the project manager s view of the pure mysticism of what project management is really all about. And yet despite this, large proportions of real, live project management services are provided by the hundreds of contactors controlling their own time, cost and performance deliverables who are forced to provide their best project management endeavours under the severe constraints of the many, adversarial conditions of contract used in the South African market. It thus seems as if the project management industry focuses more on the relationships between project managers and their clients, than in addressing the contractual constraints they place on the contractors and subcontractors providing their own project management services to those very same clients. Proceedings of the 2006 PMSA International Conference 30 May 1 June 2006 Growth and Collaboration for a Project Management Profession Johannesburg, South Africa Conference Organised by PMSA and PMI SA Chapter ISBN:

2 You may be surprised that I use the term project management services in the context of construction; however, this is not really surprising at all, when one considers that, in commissioning any construction work, the client buys the materials to be left behind, but only rents from the contractor the men and machines which manipulate them and the management skill to manipulate them effectively. In thinking about this, these contractor s own management skills are also what project management is all about. In South Africa our clients do not recognise that their choice of procurement system is a critically important decision determining the degree of success or the degree of failure of their projects. One only has to look around at the maze of traditional, adversarial contracts in use in South Africa and the resulting, poor track record of our construction industry in meeting our client s expectations, let alone exceeding them. The UK construction industry recognized these issues ten years ago and took the lead in providing the most comprehensive reviews of their contracting procedures; they have subsequently implemented and legislated recommendations making their industry, as a whole, more productive and internationally competitive. In 1995 Sir Michael Latham, in is his well-received Final Report of the Government / Industry review of Procurement and Contractual Arrangements in the UK Construction Industry recommended that Endlessly refining conditions of contract will not solve adversarial problems. A set of basic principles is required on which modem contracts can be based. A complete family of interlocking documents is also required. The NEC fulfils many of these principles and requirements... A target of one-third of Government-funded projects started over the next four years should use the NEC. Ten years on and, in addition to the UK Government s endorsement of the NEC3 for Britain s 40 billion public-sector construction market, Sir Michael recommended the NEC for procuring the 2.4 billion 2012 London Olympics facilities; his recommendation was recently endorsed by the Olympic Delivery Authority in London. But, where are we in all these international developments and of what concern is it for us? Well, the NEC family is being increasingly used and accepted in South Africa. Firstly, project managers need to understand the contract and its significant potential to improve project management practice. Secondly, project managers need to embrace the NEC and apply the contract - as it was intended - to improve our industry and make us more internationally competitive. In developing the NEC - the drafting Panel in London widely representative of all the industry s players set three objectives for the family of contracts. Firstly, flexibility that it should be suitable for all construction or service disciples, all or no contractor s design and for all contract types ranging from lump-sum, re-measurement, target contracts, cost reimbursable and management contracts. All the contracts in the family should be similar with consistent procedures and terminology. Secondly, clarity and simplicity that it should be written in ordinary language, organized in a structure which helps the user gain familiarity with its contents. The actions of the parties in administering the contract should be precisely defined to minimize any misunderstandings about who is to do what, when and how. Legal terminology should be minimized. Thirdly, a stimulus to good project management; every procedure is designed to ensure that it should contribute to, rather than detract from, the effectiveness of the management of the future work. However, the overriding and most important draughting principle had nothing to do with structure, words or grammar. It was that every action and every procedure should be designed to motivate the actors to collaborate. In this way, project results could be improved by applying collective foresight to all decisions about the future work. We all know that this will mitigate problems and shrinks risks; the clear function and responsibility will also promote accountability and motivate people to play their part. Many of these elementary principles are sadly lacking in our construction industry today. With this background, we can turn to the of the contracts and investigate the warranty of their good project management principles. The NEC is thus an integrated suite of contracts covering works, services, subcontracts, short contracts, term service, supply and maintenance contracts all have their associated guidance notes and flow charts. The flow charts show every action and response which the parties take in managing the contract, so users

3 are always aware of exactly what has to be done, by whom and in what time period. This certainly promotes cooperation, teamwork and early resolution of changes, difficulties and, of course, the old unforeseen situations. On first reading, the impact is that it is written in ordinary language designed for use by people whose first language is not English. The sentences are short, in the present tense and make maximum use of bullet points and an open layout. In as much as the PMBOK defines the broad areas of project management as integration, scope, time, cost, quality, human resources, communications, etc. so the NEC, in its turn, defines the detailed procedures within each PMBOK area which the parties take in managing the contract. The NEC thus amplifies the general provisions of PMBOK into a detailed set of project management procedures whilst, at the same time, providing thoroughly competent conditions of contract. The NEC principles are also based on modern principles of risk allocation. Consequently, its use reduces the risk of cost and time overruns for clients and of operating losses for contractors, sub-contractors and suppliers. Starting with the simple issues; the means by which, and the time periods within which, the parties communicate are clearly defined. A welcome provision is that each communication is to be communicated separately; this stimulates timeous communications and compensates the contractor for late responses. Proactive, predictive project management is required from the early warning actions which mandate the parties to notify the other as soon as either becomes aware of any which could affect the time, cost or quality of the work or services. This is, in fact, the project manager s ideal tool enabling him to pre-plan, manage and optimize the future work; there is thus no need for all the traditional wrangling after the fact - of how and why it all went horribly wrong. The contract defines the Works Information as the scope and constraints within which the contractor is to work; departures from these definitions are Defects which the contractor corrects. A welcome change is that information about the Site is separately defined. NEC users will understand the programme requirements and the actions which the project manager takes in accepting this programme, as key procedures underlying the management of time, cost and change. These are areas where the NEC is most pragmatic and where even the most stringent project management purest, will find favour. The programme also requires the contractor to provide details of the equipment and other resources which he plans to use for each operation, the full details of his time risk allowances and his float. These contractual (and good project management) requirements move the programme away from a pretty picture into a carefully assessed, resource-driven document showing the time risks and how the contractor plans to provide the future work. The programme is contractual in its defining the timing of the work of the employer and others and, by forming the basis of compensation for any actions which are out of time. The contract also settles the old arguments about the ownership of float the terminal float belongs to the contractor. Experienced employers are using the programme information to evaluate the competency and realism of tenders instead of the normal, lowest price approach and the substance of contractor s often, well-sung assurances that of course, we will finish on time! The management of change - under the compensation event procedures - rests on the contractor providing integrated time, cost and resource-driven quotations largely in advance of the new or changed work being done. The efficacy of these procedures, in protecting both parties interests, requires the construction players to take bold steps forward in embracing the new predictive methods of control. Indeed, this is not an easy step for an industry steeped in historic re-measurement and claim evaluation procedures long after the work has been completed. One reason why clients use the NEC is the change management procedure allows them facilities to price changes in different ways; the project manager may, for example, require alternative quotations; one with an extension of time and another to hold the programme in its last accepted state. Some commentators were initially horrified that NEC variations did not automatically entitle the contractor extension of time!

4 Thus the contract does not rely on the traditional we ll sort it out at the end approach, leaving the final account and its claims to be settled sometimes years after completion of the work; defined time bars stimulate the parties to deal with the changes in advance of the work being done. The Panel addressed the well-understood difficulties of valuing changes using the rates or sums in the contract; such procedures have and, always will, lead to argument about the applicability of rates to the new of changed work and the manipulation of P&G in one or other parties interests. As a default in pricing change, the contract uses defined Actual Cost (Defined Cost) where the amounts to be included in the assessment are at open market or competitively tendered prices; the effect is to end (once and for all) the one-sided unjust enrichment difficulties arising out of changes, the loading of rates or of ordering increased quantities of work at known, low bill rates. With these strong project management backgrounds, the NEC develops and promotes skilled, proactive project managers on both sides of the fence who understand how construction costs arise and how they will be affected by changes to plan; a knowledge of construction planning and of how plans will be affected by changes; the ability to obtain up-to-date information about construction costs and, an appreciation of construction risks and how allowances for them should be assessed. For our industry to develop, we need to grasp the extent of these NEC changes away from the traditional procedures which pays the contractor according to the measured quantities of permanent work left behind, using rates which hide the contractor s true costs relating to the methods and timing of the construction itself. Project managers will find a range of contract options to deal with the risks in their contracts in open and proactive ways. Where the scope of work is clearly defined at the time of tender, they would let the contracts on one of the priced contract options either with an activity schedule or a bill of quantities. Where the scope is less defined and risks are greater, he would tend towards the target (or incentivised) options where the parties share savings and overruns assessed against a managed target. Where speed of appointment is imperative or poorly defined scope, a fact, the project manager would be comfortable using the cost reimbursable option. It is important to realize that this NEC option does not expose the employer to paying for the contractor s inefficiency. The growth of the NEC worldwide is in the target contracts where the parties share the risks on the understanding that cooperation in mitigating the risks will optimise the outcomes for both parties. The UK s Channel tunnel rail link [CTRL] and Heathrow terminal five projects (the biggest construction projects in Europe) are both essentially incentivised NEC contracts. Such incentivised provisions underlie many of the alliancing and partnering contracts now in use. But what happens when the parties find there are differences of opinion about time or cost assessments or where one of the parties has not played his part in managing the contract? Traditionally, the parties proceed into arbitration, litigation or other ADR routes which, when seen in the project management context, are not a route willingly accepted by the project management fraternity. Following the NEC s lead with third party, independent adjudication, it is a welcome change to see locally used forms of contract also adopting adjudication and the considerable stimulus which the CIDB have provided in this direction as well. Adjudication is a set of simple steps where an independent, third party - named in the contract - makes a decision in a short period of time resolving any dispute referred to him. The parties implement his decision; it is final and binding unless a dissatisfied party wishes to refer the matter to one or other of the legal processes. There have been about 130 adjudications in South Africa since early 1990 s. Our information is that none of these Adjudicator s decisions has actually proceeded into the legal processes. This is not because all the decisions were necessarily technically and commercially correct; it is more likely that a disgruntled party, having reviewed the decision and the reasons for it, considered the decision a better done deal than reopening it under the legal scrutiny of the lawyers. Any of you here today could be potential adjudicators; in fact, the contract promotes using experienced industry practitioners who have a good knowledge of the contract and, time cost resource interactions, as adjudicators. The important issue underlying adjudication is its function where the parties can, at any time, agree-to-differ about an issue without allowing such a difference of opinion to affect their cooperative, working relationship.

5 In fact, this is exactly how the procedure is designed to work; the parties accept their disagreement in the full knowledge that they have a procedure that will shortly provide a decision which they can implement under the contract. So, with all this background, there is no need to place the NEC contract in the bottom drawer until things go wrong. In fact, the NEC should be seen as a set of live project management procedures which the parties use on a daily if not, an hourly basis as they follow the actions and responses they take in the daily management of the contract; in fact, the contract should be open on the top of the project manager s cluttered desk! As with introducing any new technology, there are always too few appropriately trained practitioners who can firstly understand good project management procedures in the contact and secondly, who can correctly manage NEC contracts. The problem is certainly not one solely in the domain of the NEC when it comes to effectively managing contracts it is a common concern for the whole industry. From the project management perspective and, in selecting a form of contract suited to good project management applications, progressive project manager s need to challenge the traditional procedures and start using the NEC to its fullest potential. It is interesting to see NEC project management moving into web-based communication and control systems where all the actions and responses which the parties take are centrally produced, issued, controlled and stored. These systems track and record all the communications and actions of what, when and how and provide regular prompts for the parties about the responses they need to take; users screen view all the contract documentation and the providers store and backup all the data a totally paper free office. The growth of these systems will dramatically improve project management productivity. The changes needed by the NEC means that first-time users of the NEC must expect to make behavioral shifts if they are to reap the benefits of the new contract. Evidence from NEC projects is that people who are prepared to bring an open mind into the reality of the NEC, bring out the best in the new system, in the organizations for whom they work and in themselves. I hope my attempts to rationalize the important project management developments around the NEC have been helpful. You will note I have concluded my presentation on time. I had to finish on time as nothing has fairly delayed me which would have entitled me to keep you any longer. REFERENCES The NEC family of contracts published by Thomas Telford Limited on behalf of the Institution of Civil Engineers in London Refer to the web page on

Appendix 17 Options for the Form of Contract

Appendix 17 Options for the Form of Contract Appendix 17 Options for the Form of Contract December 2007 Page 444 Appendix 17 Options for the Form of Contract The main forms of contract which are available are: NEC3 HA Design and Build ICE7 ICE Target

More information

Introduction to NEC3. Course agenda. Course objectives. Session 1 Background and underlying principles the concept

Introduction to NEC3. Course agenda. Course objectives. Session 1 Background and underlying principles the concept Introduction to NEC3 Course agenda Session 1 Background and underlying principles the concept NEC characteristics NEC family including typical NEC arrangements Key NEC3 Engineering and Construction Contract

More information

NEC3: Early Warning and Compensation Events

NEC3: Early Warning and Compensation Events NEC3: Early Warning and Compensation Events Nicholas Gould January 2007 The NEC is a major attempt to draft a simple and direct standard form contract from first principles without attempting to build

More information

Appendix 18 NEC3 Options

Appendix 18 NEC3 Options Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and

More information

NEC3 Engineering & Construction Contract An Overview

NEC3 Engineering & Construction Contract An Overview NEC3 Engineering & Construction Contract An Overview Delivering Professional Solutions to the Property Industry Michael Dunn FRICS FCIArb LLB LLM Director of Contract Services T: 01274 693 622 E: m.dunn@rpp.co.uk

More information

inform practice note SUBCONTRACTING ARRANGEMENTS Content Synopsis: Practice Note # 7 May 2007 (Version 1 - May 2007) construction industry development

inform practice note SUBCONTRACTING ARRANGEMENTS Content Synopsis: Practice Note # 7 May 2007 (Version 1 - May 2007) construction industry development construction industry development inform practice note Issued by the Construction Industry Development Board Development through partnership construction procurement and delivery SUBCONTRACTING ARRANGEMENTS

More information

Producing a programme under the NEC form of contract

Producing a programme under the NEC form of contract Proceedings of the Institution of Civil Engineers Management, Procurement and Law 163 May 2010 Issue MP2 Pages 59 64 doi: 10.1680/mpal.2010.163.2.59 Paper 900033 Received 02/05/09 Accepted 19/08/09 Keywords:

More information

The New Standard Construction Contracts: NZS3910, 3916 and 3917

The New Standard Construction Contracts: NZS3910, 3916 and 3917 The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of

More information

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004) Basic Guide General Conditions of Contract for Construction Works (GCC 2004) February 2008 Preface The Construction Industry Development Board (CIDB) is a national body established by an Act of Parliament

More information

NEC ECC Option F ERF 2066 Duynefontein building refurbishment

NEC ECC Option F ERF 2066 Duynefontein building refurbishment NEC ECC Option F ERF 2066 Duynefontein building refurbishment Bok Breedt ECC Main Options There are six types of payment mechanism available in the main Options: Option A Priced contract with activity

More information

Guidance Notes for the NEC Engineering and Construction Contract

Guidance Notes for the NEC Engineering and Construction Contract The first objective of the Risk Register is to identify the risks inherent in a project. Some of these risks are generic, and will apply to whatever work is carried out. An example is the risk of errors

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

ANNEX 8 Contract Management Strategy

ANNEX 8 Contract Management Strategy ANNEX 8 Contract Management Strategy Bath & North East Somerset, Bristol, North Somerset and South Gloucestershire Councils working together to improve your local transport Contract Management Strategy

More information

Procurement Strategy and Contract Selection

Procurement Strategy and Contract Selection GUIDELINE Capital Works Management Framework Procurement Strategy and Contract Selection The suite of Capital Works Management Framework documents is available online www.hpw.qld.gov.au: The Capital Works

More information

The South African Council for the Project and Construction Management Professions (SACPCMP)

The South African Council for the Project and Construction Management Professions (SACPCMP) The South African Council for the Project and Construction Management Professions (SACPCMP) Registration Rules for Professional Construction Mentors in terms of Section 18(1) (c) of the Act, 2000 (Act

More information

How To Write A Contract

How To Write A Contract Commercial Management the NEC Way Hong Kong Institute of Surveyors Ian.Heaphy@turntown.com Mark.Lyddon@turntown.com, July 2014 Turner & Townsend plc July 14 making the difference Health, safety & wellbeing

More information

DENTISTRY, A SUITABLE CASE STUDY FOR ADR CONTENTS

DENTISTRY, A SUITABLE CASE STUDY FOR ADR CONTENTS By Gareth R Thomas & Corbett Haselgrove- Spurin CONTENTS Page Topic 1 Aims and Objects Introduction What is ADR? Mediation 2 Ground rules for mediation 3 Steps in a mediation Advantages of mediation Why

More information

Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014

Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014 Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts 5 vember 2014 Table of Contents Part 1 Introduction Part 2 Why new contracts? The reason for the publication

More information

Guidance on the template contract for social impact bonds and payment by results

Guidance on the template contract for social impact bonds and payment by results Guidance on the template contract for social impact bonds and payment by results Introduction These guidance notes have been prepared to assist users of the Cabinet Office template contract. The guidance

More information

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact info@whe.wales.nhs.uk or telephone 029 2031 5512

More information

Part E: Contract management

Part E: Contract management Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

NEC3: The Engineering and Construction Contract An overview

NEC3: The Engineering and Construction Contract An overview NEC3: The Engineering and Construction Contract An overview Michael Dunn FRICS FCIArb LLB LLM T: 02079 976 520 and 01274 693 622 E: m.dunn@rpp.co.uk www.rpp.co.uk Delivering Professional Solutions to the

More information

What's Wrong with Project Management? Introduction. Welcome to the November 2009 INSIGHTS published by acumen7.

What's Wrong with Project Management? Introduction. Welcome to the November 2009 INSIGHTS published by acumen7. Welcome to the November 2009 INSIGHTS published by acumen7. The purpose of this newsletter is to bring you new perspectives on key subjects to stimulate your own thoughts and ideas. In each edition (which

More information

How To Manage A Contract

How To Manage A Contract Contract Management Checklist Preparation This section deals with laying good foundations before a contract is let. The contract should be actively managed. You should have a plan for doing this, which

More information

Standard forms: JCT 2005, NEC3 and the Virtual Contract

Standard forms: JCT 2005, NEC3 and the Virtual Contract by Nicholas Gould, Partner Introduction This paper reviews some of the standard forms and considers some of the basic principles relating to their use in the construction industry. Basic concepts A review

More information

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the

More information

Network Rail Infrastructure Projects Joint Relationship Management Plan

Network Rail Infrastructure Projects Joint Relationship Management Plan Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf

More information

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011 BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under

More information

CLIENT / PROJECT MANAGER AGREEMENT

CLIENT / PROJECT MANAGER AGREEMENT Authorship of this work is claimed by The Association of Construction Project Managers and any unauthorised reproduction constitutes an infringement in terms of the Copyright Act No 98 of 1978. CLIENT

More information

Guide to Reviewing Contract Documentation

Guide to Reviewing Contract Documentation Guide to Reviewing Contract Documentation Introduction In order to help members address the issues associated with the review of contracts The Royal Institute of British Architects (RIBA), in association

More information

The FIDIC Suite of Contracts

The FIDIC Suite of Contracts Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October

More information

Invitation to Tender

Invitation to Tender Invitation to Tender Provision of Training in Technology Transfer and Related Areas for The Southern Africa Innovation Support Programme 1. Drawing up the tender The tender must be submitted in writing

More information

Project Bank Account Awareness

Project Bank Account Awareness Project Bank Account Awareness Background of Fair Payment and PBAs PBAs explained Business Case Perceptions v reality HA forecast take up Impact on HA & the extended the supply chain Responsibilities KPIs

More information

The following amendments have been made to the June 2005 edition. 10 32.1 4 deleted: and of notified early warning matters

The following amendments have been made to the June 2005 edition. 10 32.1 4 deleted: and of notified early warning matters AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 43 Contract Data Part one, 1. 3 added: (with

More information

Holman Fenwick Willan CONSTRUCTION CAPABILITY

Holman Fenwick Willan CONSTRUCTION CAPABILITY Holman Fenwick Willan CONSTRUCTION CAPABILITY WHY CHOOSE HFW FOR YOUR NEEDS IN CONSTRUCTION? HFW s construction law team is one of the largest specialist international groups in the market. The partners

More information

AN OVERVIEW OF THE CONTRACT SURETY BOND CLAIMS PROCESS

AN OVERVIEW OF THE CONTRACT SURETY BOND CLAIMS PROCESS The Associated General Contractors of America 333 John Carlyle Street Suite 200 Alexandria, VA 22314 AN OVERVIEW OF THE CONTRACT SURETY BOND CLAIMS PROCESS Developed by the Associated General Contractors

More information

Activity Schedules in the NEC3 Engineering and Construction Contract

Activity Schedules in the NEC3 Engineering and Construction Contract Activity Schedules in the NEC3 Engineering and Construction Contract Prepared by Dr Ron Watermeyer Briefing Note NEC3#2 March 2013 Overview This briefing note outlines the NEC3 provisions for a Activity

More information

Bills of Quantity. D. Atkinson December 2000. Nature of Bills

Bills of Quantity. D. Atkinson December 2000. Nature of Bills Bills of Quantity D. Atkinson December 2000 Nature of Bills Bills of Quantities comprise a list of items of work which are briefly described. The Bills also provide a measure of the extent of work and

More information

Quality Management Subcontractor QM Guide-Section Two

Quality Management Subcontractor QM Guide-Section Two SECTION TWO QUALITY MANAGEMENT SYSTEMS Version No 1. PREFACE This document has been developed to assist subcontractors to meet Monaco Hickeys (MHPL) Quality Management (QM) requirements whilst working

More information

Verification of need. Assessment of options. Develop Procurement Strategy. Implement Procurement Strategy. Project Delivery. Post Project Review

Verification of need. Assessment of options. Develop Procurement Strategy. Implement Procurement Strategy. Project Delivery. Post Project Review Who should read this fact sheet? Many construction clients are not regular purchasers of construction work. This fact sheet is an introduction to construction procurement for occasional clients with a

More information

GETTING STARTED WITH THE NEC3

GETTING STARTED WITH THE NEC3 GETTING STARTED WITH THE NEC3 NEC3 TERM SERVICE CONTRACT (TSC) AND NEC3 TERM SERVICES SHORT CONTRACT (TSSC) Supported by: Published by the British Institute of Facilities Management April 2015 Introduction

More information

Nominated Subcontractors on International Projects: Approaches to Risk Allocation

Nominated Subcontractors on International Projects: Approaches to Risk Allocation Nominated Subcontractors on International Projects: Approaches to Risk Allocation September 5, 2005 (he following outline was used in a presentation to the Overseas Construction Association of Japan, Inc.

More information

The business case for lowest price tendering?

The business case for lowest price tendering? The business case for lowest price tendering? Health Warning. The use of lowest price tendering may seriously damage your financial health and reputation and may have undesirable and unexpected side effects.

More information

Click to edit Master title style

Click to edit Master title style Click to edit Master title style Presentation September 2013 Disallowance Under the NEC ICES Seminar Pioneering Bahrain Construction Public sector Energy Real estate London Tax IT Dubai Manchester Infra

More information

DENTAL ACCESS PROGRAMME INSURANCE GUIDANCE

DENTAL ACCESS PROGRAMME INSURANCE GUIDANCE DENTAL ACCESS PROGRAMME INSURANCE GUIDANCE Beachcroft LLP 7 Park Square East Leeds LS1 2LW UK tel: +44 (0) 113 251 4700 fax: +44 (0) 113 251 4900 DX 14099 Leeds Park Square 25 February 2010 DENTAL ACCESS

More information

Government of the Kingdom of Lesotho. Ministry of Public Works and Transport. Principal Building Agreement

Government of the Kingdom of Lesotho. Ministry of Public Works and Transport. Principal Building Agreement Government of the Kingdom of Lesotho Ministry of Public Works and Transport Project Employer Contractor Contract Date Contract No Principal Building Agreement MINISTRY OF PUBLIC WORKS & TRANSPORT BUILDING

More information

Thames Water Utilities Limited. Settlement deed

Thames Water Utilities Limited. Settlement deed Thames Water Utilities Limited Settlement deed DATED [ ] THAMES WATER UTILITIES LIMITED the Undertaker [ ] the Owner DEED relating to the mitigation of the effects of settlement arising from the construction

More information

Schedule 11. The Transfer of Undertakings (Protection of Employment) Regulations 2006

Schedule 11. The Transfer of Undertakings (Protection of Employment) Regulations 2006 Schedule 11 The Transfer of Undertakings (Protection of Employment) Regulations 2006 1 Definitions 1.1 In this Schedule 11 the following definitions apply: Contractor Personnel means any employee, worker,

More information

Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman of FIDIC Contracts Committee

Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman of FIDIC Contracts Committee FIDIC Conditions of Contract IBC Conference 2003 Presentation Notes on: OVERVIEW OF THE NEW MAJOR CONTRACTS Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman

More information

B R e s t o R i n g C o n f i d e n C e

B R e s t o R i n g C o n f i d e n C e B u i l d i n g B C Options for Resolving Residential Construction Disputes R e s t o r i n g C o n f i d e n c e Canadian Cataloguing in Publication Data Main entry under title: Options for resolving

More information

Outsourcing. Knowledge Summary

Outsourcing. Knowledge Summary Knowledge Summary Outsourcing P&SM professionals should have the knowledge and skills required to manage the outsourcing process and to advise colleagues of the most appropriate solution to obtain best

More information

P&SM: Writing Contracts

P&SM: Writing Contracts CIPS Position on Practice P&SM: Writing Contracts A contract is a legally binding agreement between two parties. This can take the form of a written document, a verbal agreement or implied by conduct.

More information

Construction Cost Management

Construction Cost Management Construction Cost Management In the last decade, following the Latham and Egan reports, there have been many significant changes in the role of the construction cost manager. Keith Potts examines the key

More information

A Guidance Note to. Conditions of Contract for Consultancy Services (2005)

A Guidance Note to. Conditions of Contract for Consultancy Services (2005) A Guidance Note to Conditions of Contract for Consultancy Services (2005) This Guidance Note is based on a document prepared by the Auckland Region Contract Group, and verified by ACENZ, in February 2005.

More information

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CIC/AppInsp The Construction Industry Council - Association of Consultant Approved Inspectors contract for the appointment of an approved inspector

More information

Contracting for International Outsourcing

Contracting for International Outsourcing Legal Voice: Contracting for International Outsourcing by Brad Peterson and Mark Prinsley; Mayer, Brown, Rowe & Maw International outsourcing occurs where a customer turns over responsibility for a function

More information

PLANNING & FORENSIC DELAY ANALYSIS

PLANNING & FORENSIC DELAY ANALYSIS PLANNING & FORENSIC DELAY ANALYSIS Experts in international construction & engineering disputes 01 www.gtfairway.com Fairway Fairway is an internationally recognised company that provides expert analysis

More information

PREFACE. The Contract for the Supply and Delivery of Goods has been prepared for use in supplies contracts which have the following characteristics:

PREFACE. The Contract for the Supply and Delivery of Goods has been prepared for use in supplies contracts which have the following characteristics: Supply Chain Management Document Number: SCM006 Document Title: Supply Contract Version: 01 Purpose: Standard contract for all supplies of goods PREFACE The Contract for the Supply and Delivery of Goods

More information

IMIA Short Paper (Provided by Michael Spencer, Zurich London - June 2008) The Tunnel Code of Practice for Risk Management 5 Years On

IMIA Short Paper (Provided by Michael Spencer, Zurich London - June 2008) The Tunnel Code of Practice for Risk Management 5 Years On IMIA Short Paper (Provided by Michael Spencer, Zurich London - June 2008) The Tunnel Code of Practice for Risk Management 5 Years On The Code of Practice for the Risk Management of Tunnel Works has been

More information

Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program

Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program 458 برنامج إدارة العقود الھندسية وعقود التشييد المتكامل معتمد عالميا 10 October

More information

CONTRACT MANAGEMENT COURSES

CONTRACT MANAGEMENT COURSES CONTRACT MANAGEMENT COURSES Principles and Practices Administration of Commercial Contracts Commercial Applications Risk Management in the Sourcing Environment TM Principles and Practices Identify contract

More information

Congratulations... ...and thank you for buying a Motoring First policy.

Congratulations... ...and thank you for buying a Motoring First policy. 2 Congratulations......and thank you for buying a Motoring First policy. This document explains exactly what is covered by Licence Shield, how to make a claim, important contact details and much more.

More information

SourceIT User Notes. Specific Clauses. Licence and Support Contract Commercial off-the-shelf Software RELEASE VERSION 2.

SourceIT User Notes. Specific Clauses. Licence and Support Contract Commercial off-the-shelf Software RELEASE VERSION 2. SourceIT User Notes Specific Clauses Licence and Support Contract Commercial off-the-shelf Software RELEASE VERSION 2.3 DECEMBER 2012 AGIMO is part of the Department of Finance and Deregulation SourceIT

More information

Guide to Procuring Construction Projects

Guide to Procuring Construction Projects Guide to Procuring Construction Projects Contents 1. Introduction... 3 2. The Construction Project... 4 Who s who? - The Client s Team... 4 Who s who? - Externals... 5 The Design Team... 6 The Suppliers...

More information

Project Procurement Management

Project Procurement Management Project Procurement Management 1 2 Procurement Planning Procurement Planning is the process of identifying which project needs can be best met by procuring products or services outside the project organization

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

Contents. 2. Why use a Project Management methodology?

Contents. 2. Why use a Project Management methodology? Case Study Ericsson Services Ireland The APM Group Limited 7-8 Queen Square High Wycombe Buckinghamshire HP11 2BP Tel: + 44 (0) 1494 452450 Fax + 44 (0) 1494 459559 http://www.apmgroup.co.uk/ Q:\Users\Marie

More information

April 2014 THE CONTRACT SURETY BOND CLAIMS PROCESS. Developed by the Associated General Contractors of America

April 2014 THE CONTRACT SURETY BOND CLAIMS PROCESS. Developed by the Associated General Contractors of America April 2014 THE CONTRACT SURETY BOND CLAIMS PROCESS Developed by the Associated General Contractors of America 1 THE CONTRACT SURETY BOND CLAIMS PROCESS OVERVIEW What is a surety bond? A surety bond is

More information

Project manager services

Project manager services Corporate Professional Local Project manager services For use with the RICS Standard form of consultant s appointment and RICS Short form of consultant s appointment The mark of property professionalism

More information

A Guide to Standard forms of Construction Contract Outlining Key Characteristics and Components

A Guide to Standard forms of Construction Contract Outlining Key Characteristics and Components Produced for SCALA and the Local Government Task Force by Rob Tate Dip Arch. Dip TP. Dip Arb. FCIArb. RIBA 01582 516662 rob.tate@ntlworld.com You can contact the Local Government Task Force tel 020 7837

More information

Construction Dispute Resolution Services. Bringing construction industry specialists to the heart of the dispute

Construction Dispute Resolution Services. Bringing construction industry specialists to the heart of the dispute Construction Dispute Resolution Services Bringing construction industry specialists to the heart of the dispute They delivered a team of people who could provide comprehensive support, covering all aspects

More information

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer Conditions of Offer A1 The offer documents comprise the offer form, letter of invitation to offer (if any), these Conditions of Offer and Conditions of Contract (Works & Services), the Working with Queensland

More information

Welsh School of Architecture CONSTRUCTION INDUSTRY IN THE UK

Welsh School of Architecture CONSTRUCTION INDUSTRY IN THE UK CONSTRUCTION INDUSTRY IN THE UK ART 201 CIUK Credits 20 Semester Autumn Approximate dates October to January Aims This module enables the student to develop a critical understanding of factors which control

More information

Week 4: Procurement of Highway Maintenance. Day 2 - Tuesday 18 June 2002. The Procurement Process CONTENTS

Week 4: Procurement of Highway Maintenance. Day 2 - Tuesday 18 June 2002. The Procurement Process CONTENTS Week 4: Procurement of Highway Maintenance Day 2 - Tuesday 18 June 2002 The Procurement Process CONTENTS Overview of Partnering and the Procurement Process...1 1. Overview of Partnering...1 2. Overview

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

Arthur J Gallagher, Construction - Technical Briefing. Battle of the Contracts Round Two The insurance implications of JCT & NEC forms

Arthur J Gallagher, Construction - Technical Briefing. Battle of the Contracts Round Two The insurance implications of JCT & NEC forms Arthur J Gallagher, Construction - Technical Briefing Battle of the Contracts Round Two The insurance implications of JCT & NEC forms Arthur J. Gallagher, Construction Technical Briefing 1 Introduction

More information

FP Marine Risks Limited

FP Marine Risks Limited FP Marine Risks Limited Terms of Business CONTENTS Introduction and Scope... 3 Management and Service Standards... 3 Placing Services... 4 Duty of Disclosure... 6 Solvency of Underwriters... 6 Confidentiality

More information

Technology EXPERTISE & EXPERIENCE. www.conybeare.com. a better perspective...

Technology EXPERTISE & EXPERIENCE. www.conybeare.com. a better perspective... Technology EXPERTISE & EXPERIENCE a better perspective... RECOGNITION Global Law Experts Conybeare Solicitors - Oil & Gas Law Firm of the Year in England 2014. Chambers Global 2014 Steven is recognised

More information

aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608

aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608 aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608 NCSA 01 Competency Based Assessment in Architecture THE

More information

2.1 STAGE 1 PROJECT PROCUREMENT STRATEGY

2.1 STAGE 1 PROJECT PROCUREMENT STRATEGY APM Procurement Guide : Draft7_RevA_Chapter 2.1_Project Procurement Strategy_Jan12 1 2.1 STAGE 1 PROJECT PROCUREMENT STRATEGY In this stage, the project definition is developed so that decisions can be

More information

BUSINESS CONSULTING SERVICES TERMS OF BUSINESS IBM

BUSINESS CONSULTING SERVICES TERMS OF BUSINESS IBM BUSINESS CONSULTING SERVICES TERMS OF BUSINESS IBM (China) Co., Limited( IBM ) with its registered office at 7F, Building 10, 399 Keyuan Road, Zhangjiang Hi- Tech Park, Pudong New District Shanghai, People

More information

PROJECT MANAGEMENT BASICS

PROJECT MANAGEMENT BASICS PROJECT MANAGEMENT BASICS Rick Panos AIA, CCM Director of Construction Management Totum Consulting Gary Cardamone, P.E., FCMAA Principal, G J Cardamone Consulting, LLC Program Management Is.... In the

More information

Contract Management Framework

Contract Management Framework Contract Management Framework Contents Purpose and Scope... 2 The Contract... 2 The importance of the Contract... 2 Contract Management... 3 The Toolkits... 4 Outline of establishing a Contract Management

More information

Guideline for Construction Contractor Performance Reporting

Guideline for Construction Contractor Performance Reporting Guideline for Construction Contractor Performance Reporting Procedure Applicable to: Transport Projects Quality Management System Status: Approved Division: Transport Projects Version: 60 Date of issue:

More information

Managing construction procurement risks

Managing construction procurement risks CONSTRUCTION PROCUREMENT BEST PRACTICE GUIDELINE #A5 Construction Industry Development Board Pretoria - Head Office Tel: 012 482 7200 Fraudline: 0800 11 24 32 Call Centre: 0860 103 353 E-mail: cidb@cidb.org.za

More information

60 Day Expert Determination Structured to Meet the Commercial Expectations of Business Management

60 Day Expert Determination Structured to Meet the Commercial Expectations of Business Management 60 Day Expert Determination Structured to Meet the Commercial Expectations of Business Management By Charles O Neil FCIArb and Dr. Michael Hammes Published in Arbitration Journal April 2011 (Chartered

More information

Measured development Construction and Engineering Training Supplement Guide

Measured development Construction and Engineering Training Supplement Guide Construction and Engineering Training Supplement Guide Welcome Eversheds is the law firm behind some of the world s most ambitious construction and engineering projects. We have one of the biggest teams

More information

Note that the following document is copyright, details of which are provided on the next page.

Note that the following document is copyright, details of which are provided on the next page. Please note that the following document was created by the former Australian Council for Safety and Quality in Health Care. The former Council ceased its activities on 31 December 2005 and the Australian

More information

How To Write A Contract

How To Write A Contract Government Gazette Staatskoerant REPUBLIC OF SOUTH AFRICA REPUBLIEK VAN SUID-AFRIKA Vol. 582 Pretoria, 4 December Desember 2013 No. 37102 N.B. The Government Printing Works will not be held responsible

More information

Procurement guidance Managing and monitoring suppliers performance

Procurement guidance Managing and monitoring suppliers performance Procurement guidance Managing and monitoring suppliers performance Procurement guidance: Managing and monitoring suppliers performance Page 2 of 16 Table of contents Table of contents... 2 Purpose of the

More information

Procurement Capability Standards

Procurement Capability Standards IPAA PROFESSIONAL CAPABILITIES PROJECT Procurement Capability Standards Definition Professional Role Procurement is the process of acquiring goods and/or services. It can include: identifying a procurement

More information

The Practical Techniques on Contract Administration, Site Management, Scheduling, Budgeting, Claims & Counterclaims

The Practical Techniques on Contract Administration, Site Management, Scheduling, Budgeting, Claims & Counterclaims The Practical Techniques on Contract Administration, Site Management, Scheduling, Budgeting, 469 (ECCM Workshops 3, 4 & 5) Certified Program التقنيات العملية في إعداد الجدول الزمني والمالي اإلدارة الموقعية

More information

Giovanni Di Folco Letters of Intent, Bonds & Guarantees, Defects Liability Periods

Giovanni Di Folco Letters of Intent, Bonds & Guarantees, Defects Liability Periods [Type here] Giovanni Di Folco Letters of Intent, Bonds & Guarantees, Defects Liability Periods Other articles written by the same author: Enforcement of a DAB decision through an ICC partial award; (co-author

More information

Client Contracts: Business Risk, Professional Liability & Insurance Coverage

Client Contracts: Business Risk, Professional Liability & Insurance Coverage Hanover Architects & Engineers Advantage Client Contracts: Business Risk, Professional Liability & Insurance Coverage Many client-drafted contracts endeavor to transfer unreasonable risk to the design

More information

RECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME

RECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME National Home Builders Registration Council RECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME (14 October 2002) 1 Requirements of the Housing Consumers

More information

CHAPTER 23. Contract Management and Administration

CHAPTER 23. Contract Management and Administration Date Issued: June 12, 2009 Date Last Revised: September 28, 2015 CHAPTER 23. Contract Management and Administration Table of Contents CHAPTER 23. Contract Management and Administration... 23-1 23.1 Policy...

More information

Mediation Services, Throughout the UK Guide to Mediation

Mediation Services, Throughout the UK Guide to Mediation mediation Mediation Services, Throughout the UK Guide to Mediation let sstarthere Why Mediate? Pg 3 The Mediation Day Pg 4 Preparing for the Mediation Pg 5 Quality Assured Pg 6 Flexible Fee Policy Pg 7

More information

CONTRACT FOR CONSULTANCY SERVICES. Section 1 Form of Contract

CONTRACT FOR CONSULTANCY SERVICES. Section 1 Form of Contract CONTRACT FOR CONSULTANCY SERVICES Equatorial Fidelity Centre 2 nd Floor, Off Waiyaki Way P.O Box 313-00606 Nairobi, Kenya. Tel +254 20 423 5000 Section 1 Form of Contract CONTRACT FOR: [Insert Title here]

More information

LEGAL COSTS IN SOUTH AUSTRALIA'S WORKERS' COMPENSATION SCHEME

LEGAL COSTS IN SOUTH AUSTRALIA'S WORKERS' COMPENSATION SCHEME BLAKE DAWSON WALDRON SOLICITORS LEGAL COSTS IN SOUTH AUSTRALIA'S WORKERS' COMPENSATION SCHEME February 1997 Workcover Corporation,. Library Worl(Cove _. i00,waymouth Street toz.v.,.;4.'rk:iilatil Adelaide

More information