Value Adding Through Appropriate Integrated Risk Insight : Transforming Development Opportunities Into Projects.
|
|
- Adam Potter
- 8 years ago
- Views:
Transcription
1 Value Adding Through Appropriate Integrated Risk Insight : Transforming Development Opportunities Into Projects. G. J. Hawkins LRMC PTY Ltd, 96 Stanley Street, Nedlands, Western Australia 6009 Tel: Fax: llanwern@iprimus.com.au 1.0 Abstract Front End Loading is described as taking sufficient time to properly assess an opportunity, identify value drivers, identify uncertainty to achieve a quality project solution prior to committing to major expenditure (Woodside Energy Ltd 2000). Opportunity and risk factors vary throughout the project lifecycle and Front End Loading (FEL) is used to influence the business and project success whilst the expenditure is relatively low. A mandatory and consistent implementation of a Risk Management System at the onset of development appraisal has the potential to improve project success. Reflecting best strategic industry practices to support decision-making, an overview is provided of the value adding process framework, methodology, tools, constraints and significant benefits for a company wide consistent approach to opportunity and risk analysis conducted during the early project phases by an independent review team. 2.0 Introduction Woodside Energy Ltd is a leading Australian resource company with substantial assets and a growing international reputation as a successful oil and gas explorer, developer and producer. In 1999, Woodside introduced the Opportunity and Project Realisation Process (OPREP) for a structured and systematic approach to improved management of capital projects through enhanced decision and execution quality. The OPREP methodology covers the project lifecycle phases and a decision milestone check point punctuates each project phase. Assurance Checks support the decision points to move to the next phase (refer Figure 1). They provide the decision makers assurance that the recommendations are sound and will deliver maximum value. Page 1 of 10
2 AC1 Is there a real understanding of what is being initiated and of the commitments being made? Do we have a meeting of minds with JV partners on objectives and expectations? AC2 Should we enter, can we make it work? Has the venture/project been effectively framed and is there sufficient knowledge to start the process of selecting the concept and defining the plan? Are there any showstoppers, have we identified all risks and opportunities? AC3 AC4 Assurance Checks AC5 Have we selected the Are all plans, strategies, Are the HSER manage- right alternatives? organisations, resources ment systems in place Has the optimum plan been selected and defined? Have we now fully defined what we are going to do? and systems in place to commence execution in an optimum manner? Have we set-up to successfully implement and effective? Have the staff been adequately trained on the operation, inspection and maintenance of the our plan, should funds be facilities? released? Are the start-up procedures sufficiently complete? Is the start-up organisation in place? AC6 Did we achieve the predicted performance? What can be learned from the project and what further opportunities are there? Value Identification Value Realisation OPERATE & ASSESS SELECT DEVELOP EXECUTE EVALUATE MANDATORY ASSURANCE CHECKS Project Initiation Feasibility Development Plan Final Investment Decision Pre Start Up Post Investment (Concept Selection) Benchmarking Benchmarking 7 7 (FEL Assessment) (FEL Assessment) 12 Cost Estimate 12 Cost Estimate 12 Cost Estimate 7 Benchmarking (Merit/Pacesetter) RECOMMENDED ASSURANCE CHECKS 9 Reserve Certification 8 HSER 8 HSER 8 HSER 8 HSER 9 Reserve Certification 9 Reserve Certification 10 Technical Integrity (Sub-surface) 10 Technical Integrity (Sub-surface) 11 Commercial 11 Commercial 11 Commercial 11 Commercial PEER ASSISTS 13 Peer Assists 13 Peer Assists 13 Peer Assists 13 Peer Assists 13 Peer Assists Figure 1: OPREP Assurance Checks AC2 Feasibility To confirm that resolution of uncertainties supports continuation of definition and moving to concept selection. AC3 Field Development Plan (Concept Selection) To gain confidence in support of the Field Development Plan and concept selection. Commit to resources where scope is fully defined and final business proposal is prepared. AC4 Final Investment Decision To provide support for the Final Business Proposal and provide confidence to stakeholders that decision to proceed with project execution is sound. Risk Management supports the practice of understanding uncertainty during the production of deliverables in each project phase. Implementation of a project risk analysis process as a mandatory Assurance Check prior to committing to major project expenditure is a focus area to reduce project failure rates in terms of capital cost and project schedule. The Project Integrated Risk Insight (PIRI) process, models and tools are implemented during the Select (pre AC2 / 3) and Develop (pre AC4) phases using a fit for purpose approach dependent of the level of definition. Opportunity and risk that can be quantified in terms of schedule and capital cost are modelled and the results are presented to the Assurance Teams and the Decision Board via the Opportunity / Development / Project Manager(s). Note: Schedule risk analysis is well documented and external to the doctoral project. Page 2 of 10
3 The Project Integrated Risk Insight (PIRI) process described extends the boundaries of conventional thinking by including strategic thinking underpinned by a rigorous data gathering and analysis process that adds value, permits innovation, supports business proposals and Senior Management in the decision-making process leading up to a Final Investment Decision (FID). Dependent on the level of project definition, the process uses a fit for purpose selection from three Navigators (Opportunity and Risk Breakdown Structure ORBS, Simplified Functional Analysis Systems Technique Diagram SimFAST and Key Assumptions Analysis and Testing KAAT), two qualitative models (Project Contingency Assessment Model - ProCAM and a Forensic Investigation Risk Model FIRM), a Project Relationships and Influence Map (ProRIM) and a quantitative (probabilistic) Integrated Risk Insight Model (i-rim). Comparing the outcomes of Woodside offshore projects (post 1999) with the PIRI reviews conducted prior to the Final Investment Decision (FID) indicates delivery of complex offshore oil and gas projects within the predicted capital cost accuracy range, a notable improvement on past performance. 3.0 Project Failure Industry benchmarking and historical data indicates a very high failure rate for oil and gas projects internationally and within Woodside. The hot spots 1 identified as increasing the potential for project failure are: Technical definition has not been adequately completed for the decisions being taken, too little attention has been made to the upside and downside cases Too little attention in looking for innovative or aggressive angles and strategies Insufficient number of staff and competencies to deliver project Organisation structure and interfaces are unrealistic for the project complexity Non-alignment of stakeholders Project objectives poorly communicated to project team and stakeholders Quality of opportunity and risk management systems is variable and / or poorly structured Plans are incomplete and / or not fully integrated s have been too late teams were not independent 4.0 Project Opportunity and Risk Categories There is a hierarchy of opportunity and risk pertaining to a project. It ranges from that which is managed at the project level and may be internal or external, through those managed at the Joint Venture level, to a corporate level. PIRI is designed to accommodate the project level. Opportunities and risks are grouped according to categories to assist in the identification, quantification, response development and control. The risk areas have been consolidated into TECOP (Woodside Energy Ltd 1999) technical, economic, commercial, organisational and political. 1 Excerpt from WEL OPREP / Shell E&P Learning s Jan 2002 Page 3 of 10
4 Date Stop,Hold,Recycle Framing Facilitator:Graham Hawkins Date Date Date Date TeamLeader: Stop, Hold, Recycle AC2 Feasibility Team Leader: Stop, Hold, Recycle AC3 FDP Team Leader: Stop,Hold,Recycle AC4 FID TeamLeader: Stop, Hold, Recycle Date Production Acceptance Team Leader: Stop, Hold, Recycle Date AIPM National Conference 2003 Alice Springs Value, Opportunity and Risk Workshops are facilitated with a requisite variety group and underpin the concept of risk management in capturing the knowledge, perception and appetite of the multidisciplined team and supporting participants. An opportunity and risk register is prepared and a rapid ranking technique is used to prioritise focus areas. 5.0 Project Integrated Risk Insight (PIRI) Process Project Integrated Risk Insight has been developed using structured uncertainty analysis and documented (refer Figure 2) to bridge the gap between the qualitative approach to opportunity and risk identification, scoring and ranking, and the traditional desktop reviews by individuals of capital cost estimates and extend beyond the classical cost model endorsement by modelling the uncertainty inherent to the options, configurations and scenarios being considered prior to the final investment decision. The deliverable from the analysis is an opportunity and risk report describing the le vel of project definition, supported by a calculated accuracy and contingency for the capital cost estimate. PROCESS MAP Opportunity, Value & Risk Identification Opportunity, Value & Risk Quantification Project Integrated Risk Insight (PIRI) Project Opportunity, Value & Risk Management Process Opportunity & Risk Opportunity & Response Risk Control Response Development Feedback, Learning & Improvement Value Adding through appropriate Integrated Risk Insight: Transforming Oil and Gas Development Opportunities into Projects Phase 1 Phase 2A Phase 2B Phase 3 Phase4 Phase 5 ASSESS SELECT SELECT DEVELOP EXECUTE OPERATE Qualitative Assessment Quantitative Analysis Reporting AC12 AC12 AC12 Figure 2: 5.1 Qualitative Assessment Assurance Check AC12 Strategy, Economics, Forecasting & Optimisation Integrated Risk Insight (PIRI) Otway Platform Otway Subsea Angel Subsea AUD 1 Billion Angel Concrete Gravity Structure Angel Jackup Trunkline System 2 nd Trunkline Expansion Project AUD 500 Million Blacktip Platform Echo Yodel Subsea GWA Platform Low Pressure Train Laminaria Phase 2 Laminaria Phase 2 Subsea Subsea AUD 100 Million Lambert 6 Subsea Pipeline Systems Modifications Lambert 5 Subsea Project Uncertainty assessment can never be exact; as with identification, the knowledge and perception of the multi-disciplined team and supporting participants is important in assessing the likelihood and impact. The opportunity and risks are scored according to the scope, quality, schedule and cost and ranked on a project opportunity and risk register, the primary deliverable from the workshop to the Opportunity / Project Manager. 5.2 Quantitative Analysis Risk Quantification involves evaluating opportunities and risks and their interactions. It uses probabilistic theory combined with a rigorous and structured tool in determining a range of possible outcomes. Page 4 of 10
5 6.0 Project Integrated Risk Insight (PIRI) Tools If a development / project team can come up with true insights then developing a strategy to exploit them is a viable task. Insight gives meaning to tactics and allows objectives to be set with the knowledge that they have a better chance of being achieved. In addition, for the opportunity and risk that can be quantified and modelled we can have a better level of confidence when classifying an estimate by calculating the accuracy and contingency for complex projects. 6.1 Opportunity and Risk Breakdown Structure (ORBS Navigator) Hillson (2002) defines the Risk Breakdown Structure as A source-oriented grouping of project risks that organises and defines the total risk exposure of the project. Each descending level represents an increasingly detailed definition of sources of risk to the project. The ORBS Navigator builds upon generic versions and is an industry specific risk breakdown structure for oil and gas developments / projects (ref Figure 3 for sample). LEVEL 0 DEVELOPMENT / PROJECT RISK LEVEL 1 TECHNICAL ECONOMIC COMMERCIAL ORGANISATIONAL POLITICAL LEVEL 2 Scope Function Technology Health & Safety Sub-surface Surface Operational Infrastructure Environment Reserves Production Market Price Market Demand Life Cycle Cost Schedule Joint Venture Participants Contracting Legal Framework Financing Insurance Competition Economy Structure Competencies Resourcing Execution Plan Knowledge Mgt IT Systems Procedures Processes Government Regulator Reputation Industrial Relations Shareholders Other Stakeholders Community Employment Location LEVEL 3 Systems Drilling Completions Subsea Structures Facilities Pipeline LEVEL 4 Equipment Process Figure 3: Installation ORBS Navigator Page 5 of 10
6 6.2 Simplified Function Analysis Systems Technique (SimFAST Navigator) The SimFAST Navigator (refer Figure 4 for example) uses a well established technique from Value Engineering to develop the base from which to build up a picture of the scope of work and key cost areas. It is used to prioritise focus areas for assessment and analysis of opportunity, risk and value enhancing initiatives. Produce, Process and Export Oil SCOPE LINE Inspection Maintenance Repair Maintain Integrity Lay Commission Construct Flowline Hydrate Mitigation Chemicals Maintain Flow Valves Isolate Wellhead SCOPE LINE Separate Product TRANSFER PRODUCT $? MM TRANSPORT PRODUCT $? MM COLLECT PRODUCT $? MM CONTROL FLOW $? MM Produce Reserves Equipment Equipment Equipment Equipment Value, Opportunity and Risk Figure 4: SimFAST Navigator 6.3 Key Assumptions Analysis & Testing Navigator (KAAT Navigator) Royer (2002 p 38) suggests that assumptions are introduced by organisationa l culture and, when unknowingly present in the project environment, foster incorrect perceptions and unrealistic optimism. The KAAT Navigator (refer Figure 5) uses a structured approach in relating the level 3 opportunity and risk breakdown items to the main component areas of the scope of work. Assumptions are analysed for inaccuracy, inconsistency and incompleteness. The outcomes are assessed as opportunities or risks. The key assumptions (and alternatives) are tested for stability and consequences. Level 3 ORBS Component Area 1 Component Area 2 Component Area 3 Client Direct Costs Assumptions Analysis Assumptions Testing Figure 5: KAAT Navigator Page 6 of 10
7 6.4 Forensic Investigation Risk Model (FIRM) This structured model provides the basis for a rigorous desktop assessment of project objectives and supporting documentation supplemented by project team interviews conducted by an independent review team. Key project areas are mapped against level 3 (systems) and level 4 (equipment) items. Information is extracted to assess the level of project definition as the basis for opportunity and risk analysis. Objectives Scope of work Options Cost Estimate Schedule Interfaces Other Project Documentation Technology Constructability Complexity Level 3 ORBS Level 4 ORBS Figure 6: FIRM 6.5 Project Contingency Assessment Model (ProCAM) The project contingency assessment model is adapted from the expected value method (Mak & Picken 2000; Mak et al. 1998). ProCAM (refer Figure 7) expands upon this method to include the assessment of fixed and variable opportunities, risks and value enhancing initiatives. The outcomes of the key assumptions and analysis testing and the forensic investigation support the decisions in identifying values prior to summation of allowances to calculate contingency. KAAT Figure 7: FIRM ProCAM Expected Cost ProCAM Page 7 of 10
8 6.6 Project Relationships and Influence Map (ProRIM) Key project component areas are allocated level 4 equipment items, design and operating parameters and activities are aligned. Scope, price, duration and complexity variables are mapped against the development / project components identifying accuracy and skew whilst building in value enhancing initiatives. Relationship Project Components Level 4 ORBS Design / Operating Parameters Figure 8: Activities (Design, Procure, Fabrication, Installation) ProRIM Scope Influence Accuracy Skew Value Enhancing Initiatives Price Duration Complexity 6.7 Integrated Risk Insight Model (i-rim) Scope, procurement items and installation activities are documented. Scope, price, duration and complexity variable distributions are transferred from ProRIM and dependencies created within the model. Monte Carlo simulation is used to calculate the expected cost and allocate a confidence range to that value. Scope Scope Procure Installation Price Duration Complexity Dependency Figure 9: i- RIM Page 8 of 10
9 7.0 Constraints (pre AC2 /AC3 vs. AC4) The following points have been identified: The tools provide for refinement of scope but no major changes in scope or catastrophes. Many risks carried on the register are intangible and cannot be quantified into schedule and / or cost metrics during the Select Phase 2. The relevance of the output values in the opportunity and risk report based on options may be short lived post AC3. It is not any quicker to run the AC12 process prior to AC2 if analysis is required. Some Development / Project Teams perceive the independent review to be an audit. Analysis is not always possible nor is it warranted pre-ac Benefits of Process / Tools The following points have been identified: Provides the opportunity to test the effect of buying flexibility of design. Allows for consideration of pre-investment. Models complexity. Considers all aspects of offshore / onshore field development from the Client, Contractor and Operator perspective. Uses consistent methodologies for comparison of configurations / options. Identifies key cost drivers. Provides an opportunity and risk adjusted capital expected cost and accuracy. Develops buy-in and use from internal customers and stakeholders. Provides valuable information to Senior Management decision-making. Leveraging experiences from other projects. Risk report provides observations and recommendations for action pre Final Investment Decision. 9.0 Applicability Examples of applicability are new onshore / offshore oil and gas facilities, existing oil and gas field expansions, pipeline and onshore terminals, systems modifications, asset functionality, asset life extension, equipment upgrades and technology changes. The process and tools have demonstrated improved qua lity of the information available to the decision makers from the implementation of a strategic, structured and practical process for a rigorous assessment of complex oil and gas projects. It adds new knowledge and understanding in the area of uncertainty management (value, opportunity and risk). The process has demonstrated capacity to influence opportunity and project realisation processes and practices. It demonstrates advanced professional practice and provides a record for ongoing development of the opportunity and risk analysis body of knowledge PIRI process and tools life expectancy The integrated analysis process and tools have an improvement life expectancy for the majority of twenty (20) years from now until the underlying premise to sustainables and renewables is realised and the energy chain is decarbonised with energy alternatives to gas, gas enabled or renewable sources of energy. Notwithstanding, the potential for adaptation to other industries is currently under evaluation Conclusions Appropriate Project Integrated Risk Insight is a discipline for thinking rigorously and systematically about uncertainty. It provides the basis of developing plans for the future based on patterns from the past, whilst approaching the virtual edge of embracing technology for project success. The model reflects complexity and provides cumulatively defined insights that have been independently and Page 9 of 10
10 interdependently built in. The process is intended to disturb and assist the development / project team in discovering and making decisions on a rational basis instead of dictating Acknowledgements The material for this paper was extracted from a Doctor of Technology (DTech) thesis in Project Risk Analysis through Deakin University, Victoria, Australia. The findings are based on a selection of ten case studies conducted for three Divisions / Business Units at Woodside Energy Ltd, Perth, Western Australia. The implementation of Risk Insight has demonstrated and proven exposure to AUD 13.2 Billion (disclosed) Development / Projects over a three year period through 50 workshops and 20 assurance reviews. Acknowledgement is given to Professor Peter Hodgson, Dr Richard White and Dr Julian Mote from Deakin University for their support and advice during the doctoral project. Thanks are due to Mr Roy Thompson (General Manager, Offshore Projects) and Mr Gary Keenan (Business Manager, NWSSDD Support Services) both of Woodside Energy Ltd, Perth, Western Australia for supporting the trialling and implementation of the development / project risk management and assurance processes. Contributions from the Woodside Energy Ltd Oil and Gas Business Units are also gratefully acknowledged References Hillson, D. 2002, 'Understanding risk exposure with the Risk Breakdown Structure (RBS)', PMI Risk Management Newsletter, vol. 4, no. 5. Mak, S. & Picken, D. 2000, 'Using risk analysis to determine construction project contingencies', Journal of Construction Engineering and Management, vol. 126, no. 2, pp Mak, S., Wong, J. & Picken, D. 1998, 'The effect on contingency allowances of using risk analysis in capital cost estimating: a Hong Kong case study', Construction Management and Economics, vol. 16, pp Royer, P. S. 2002, Project Risk Management: A Proactive Approach, Management Concepts, Vienna, VA, USA. Woodside Energy Ltd 1999, Value Improving Practice: Risk Management [Homepage of Woodside Intranet], [Online]. [2003, May]. Woodside Energy Ltd 2000, Opportunity Framing Facilitators Handbook, Perth, Australia. Page 10 of 10
THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini)
PAGE 1 THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) Ing. Guido Mattu More than 25 years experience in Engineering and Project Management activities
More informationAmajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
More informationRISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT
RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.
More informationProject Risk Management. Presented by Stephen Smith
Project Risk Management Presented by Stephen Smith Introduction Risk Management Insurance Business Financial Project Risk Management Project A temporary endeavour undertaken to create a unique product
More informationAIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM) February 2010 Version 1.12 Copyright: Australian Institute of Project Management Document
More informationPart B1: Business case developing the business case
Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project
More informationAIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document
More informationTechnology based Project Management Consulting (T-PMC): Innovate to Reduce Costs
Technology based Project Management Consulting (T-PMC): Innovate to Reduce Costs Graham Freeth, North African Oil and Gas Summit, Tunis, Tunisia October 2009 J P Kenny Offices World Wide Aberdeen Stavanger
More informationA Risk Management Standard
A Risk Management Standard Introduction This Risk Management Standard is the result of work by a team drawn from the major risk management organisations in the UK, including the Institute of Risk management
More informationDepartment of Infrastructure and Planning: Governance Framework for Infrastructure Delivery Special Purpose Vehicles
Department of Infrastructure and Planning: Governance Framework for Infrastructure Delivery Special Purpose Vehicles Governance Framework for Special Purpose Vehicles Table of Contents Executive Summary...3
More informationEnhanced Portfolio Management in uncertain times
Enhanced Portfolio Management in uncertain times How businesses can generate and protect value through enhanced, risk return techniques improving portfolio and capital allocation decisions Contents Executive
More informationAcompany that consistently selects the right projects and
PM.01 How to Create a World Class Project Management Organization Dr. Nick J. Lavingia, PE Acompany that consistently selects the right projects and executes them with excellence can improve return on
More informationIntroduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
More informationPORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)
PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value
More informationRisk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge
1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project
More information2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology
2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our
More informationProject Time Management an essential element to project success
Project Time Management an essential element to project success Abstract This paper discusses the reasons behind the necessity to apply sound Project Time Management principles and processes to projects
More informationQuick Guide: Meeting ISO 55001 Requirements for Asset Management
Supplement to the IIMM 2011 Quick Guide: Meeting ISO 55001 Requirements for Asset Management Using the International Infrastructure Management Manual (IIMM) ISO 55001: What is required IIMM: How to get
More informationProject Management Competency Standards
BSB01 Business Services Training Package Project Management Competency Standards CONTENTS BSBPM401A Apply scope management techniques...3 BSBPM402A Apply time management techniques...8 BSBPM403A Apply
More informationUsing the Proxy NPV Model for Value-Based Strategic Decisions
Using the Proxy NPV Model for Value-Based Strategic Decisions January 2011 Westney Consulting Group, Inc. www.westney.com The Importance of Value-Based Development Decisions The Influence Curve has long
More informationCOMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited
PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date
More informationPurpose: Content: Definition: Benefits: outputs outcomes benefits Business Case dis-benefit Key Responsibilities: Approach: Executive Developed
Key Learning Points The Swirl Logo is a trade mark of the AXELOS Limited. Is used by the Project Board throughout the project to verify its continued viability:- Is the investment in this project still
More informationWhite Paper. PPP Governance
PPP Governance The Governance of Projects, Programs and Portfolios (PPP) (sometimes called project governance for convenience) is the sub-set of corporate and organisational governance 1 focused on assisting
More informationENERGISTICS E&P BUSINESS PROCESS REFERENCE MODEL
ENERGISTICS E&P BUSINESS PROCESS REFERENCE MODEL Access, receipt, or use of the E&P Business Process Reference Model is subject to the Energistics Product License Agreement found on the Energistics website.
More informationP3M3 Portfolio Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Portfolio Management Self-Assessment P3M3 is a registered trade mark of AXELOS Limited Contents Introduction
More informationPMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview
PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview Sante Torino PMI-RMP, IPMA Level B Head of Risk Management Major Programmes, Selex ES / Land&Naval Systems Division
More informationThe Gateway Review Process
The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible
More informationPROJECT RISK MANAGEMENT
11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and
More informationProject Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
More informationMonte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson
Page 1 of 13 Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models Martin Hopkinson Abstract Monte Carlo schedule risk analysis has become a widely practiced
More informationTEC Capital Asset Management Standard January 2011
TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining
More informationUnderstanding risk exposure using multiple hierarchies. Introduction
Understanding risk exposure using multiple hierarchies David Hillson PhD PMP FAPM FIRM MCMI FRSA Director, Risk Doctor & Partners Introduction Risk management is recognised as an essential contributor
More informationWhat we are seeing is sustained growth and increasing interest by corporates in adopting and enhancing a captive strategy.
30 NATURAL RESOURCES MARKET REVIEW 2015 What we are seeing is sustained growth and increasing interest by corporates in adopting and enhancing a captive strategy. NATURAL RESOURCES MARKET REVIEW 2015 31
More informationMining & Construction Transforming your fleet performance
Mining & Construction Transforming your fleet performance Giving you greater focus on your business Today s difficult economy challenges organisations within the mining and construction sector to deliver
More informationOptimizing Mega Project Execution with Integrated Interface Management and Project Scheduling
Optimizing Mega Project Execution with Integrated Interface Management and Project Scheduling By: Sandra MacGillivray VP, Product & Marketing 519-772-3181 Introduction In today s mega projects, implementing
More informationTapping the benefits of business analytics and optimization
IBM Sales and Distribution Chemicals and Petroleum White Paper Tapping the benefits of business analytics and optimization A rich source of intelligence for the chemicals and petroleum industries 2 Tapping
More informationPROJECT RISK ANALYSIS AND MANAGEMENT
PROJECT RISK ANALYSIS AND MANAGEMENT A GUIDE BY THE ASSOCIATION FOR PROJECT MANAGEMENT (formerly The Association Of Project Managers) Compiled from information provided by members of the Special Interest
More informationCertification in Humanitarian Supply Chain Management (CHSCM) Competence Model. Final Version 2007
Certification in Humanitarian Supply Chain Management (CHSCM) Competence Model Final Version 2007 Contents Competence Model Context... 3 Functional Map... 6 UNIT 1 Supply Chain Planning... 7 UNIT 2 Supply
More informationProject Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
More informationConfident in our Future, Risk Management Policy Statement and Strategy
Confident in our Future, Risk Management Policy Statement and Strategy Risk Management Policy Statement Introduction Risk management aims to maximise opportunities and minimise exposure to ensure the residents
More informationAppendix V Risk Management Plan Template
Appendix V Risk Management Plan Template Version 2 March 7, 2005 This page is intentionally left blank. Version 2 March 7, 2005 Title Page Document Control Panel Table of Contents List of Acronyms Definitions
More informationpm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage
More informationBest Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
More informationProcurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire
More informationInformation Sharing Lessons Learned from Gateway Reviews: Gate 5 Benefits Realisation Review
Information Sharing Lessons Learned from Gateway Reviews: Gate 5 Benefits Realisation Review October 2013 The purpose of this document is to share lessons learned to support agencies to better identify
More informationGuidelines for the Application of Asset Management in Railway Infrastructure Organisations
Guidelines for the Application of Asset Management in Railway Infrastructure Organisations INTERNATIONAL UNION OF RAILWAYS (UIC) 16 rue Jean Rey - F-75015 PARIS Tel: +33 (0)1 44 49 20 20 Fax: +33 (0)1
More information4 Adoption of Asset Management Policy and Strategy
4 Adoption of Asset Management Policy and Strategy Abstract The report recommends the adoption of an updated Asset Management Policy 2014 and an Asset Management Strategy 2014-2019. Both documents are
More informationFive steps to Enterprise Risk Management
risk decisions 2011 Five steps to Enterprise Risk Management by Val Jonas CEO Risk Decisions Group www.riskdecisions.com management solutions Val Jonas: Five steps to Enterprise Risk Management Five steps
More informationEffective & Practical. Management of Projects
Effective & Practical Concepts, Methods & Techniques Project Planning & Delivery Management of Project Risks High Quality Training Courses presented by Internationally Recognised Expert Speakers The Diamond
More informationThe Asset Management Landscape
The Asset Management Landscape ISBN 978-0-9871799-1-3 Issued November 2011 www.gfmam.org The Asset Management Landscape www.gfmam.org ISBN 978-0-9871799-1-3 Published November 2011 This version replaces
More informationSTAGE 1 COMPETENCY STANDARD FOR PROFESSIONAL ENGINEER
STAGE 1 STANDARD FOR PROFESSIONAL ENGINEER ROLE DESCRIPTION - THE MATURE, PROFESSIONAL ENGINEER The following characterises the senior practice role that the mature, Professional Engineer may be expected
More informationRisk Management Primer
Risk Management Primer Purpose: To obtain strong project outcomes by implementing an appropriate risk management process Audience: Project managers, project sponsors, team members and other key stakeholders
More informationSTRATEGIC ASSET MANAGEMENT AT THE PORT OF MELBOURNE
STRATEGIC ASSET MANAGEMENT AT THE PORT OF MELBOURNE by by Domenic (Mick) Lo Bianco 1 and Barry Giddings 2 ABSTRACT The objective of this paper is to discuss the Port of Melbourne s journey and experiences
More informationIntegration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process
More informationNSW Government ICT Benefits Realisation and Project Management Guidance
NSW Government ICT Benefits Realisation and Project Management Guidance November 2014 CONTENTS 1. Introduction 1 2. Document purpose 1 3. Benefits realisation 1 4. Project management 4 5. Document control
More informationPROJECT RISK ASSESSMENT & MANAGEMENT
PETROSYNC S PROJECT MANAGEMENT SERIES PROJECT RISK ASSESSMENT & MANAGEMENT Your Key To Analyse & Identify Risk In Project Risk Management 1 March 4 March 2016 Bali, Indonesia Supported By Course Overview
More informationBuilding Infrastructure Asset Management Plan
Building Infrastructure Asset Management Plan Version 1.1 Building Infrastructure Asset Management Plan (Version 1.1) Page 1 of 19 Document Control Council policy documents change from time to time and
More informationPMI Risk Management Professional (PMI-RMP) Exam Content Outline
PMI Risk Management Professional (PMI-RMP) Exam Content Outline Project Management Institute PMI Risk Management Professional (PMI-RMP) Exam Content Outline Published by: Project Management Institute,
More informationAn Effective Approach to Transition from Risk Assessment to Enterprise Risk Management
Bridgework: An Effective Approach to Transition from Risk Assessment to Enterprise Risk Management @Copyright Cura Software. All rights reserved. No part of this document may be transmitted or copied without
More informationThe Human Capital Management Systems Business Case A Checklist to assist agencies developing a business case
The Human Capital Management Systems Business Case A Checklist to assist agencies developing a business case Final version for release Human Capital Management See more at psc.nsw.gov.au/hcm Index - Business
More informationCHANGE MANAGEMENT PLAN WORKBOOK AND TEMPLATE
CHANGE MANAGEMENT PLAN WORKBOOK AND TEMPLATE TABLE OF CONTENTS STEP 1 IDENTIFY THE CHANGE... 5 1.1 TYPE OF CHANGE... 5 1.2 REASON FOR THE CHANGE... 5 1.3 SCOPE THE CHANGE... 6 1.4 WHERE ARE YOU NOW?...
More informationManagement and Leadership. Level 5 NVQ Diploma in Management and Leadership (QCF)
Management and Leadership Level 5 NVQ Diploma in Management and Leadership (QCF) 2014 Skills CFA Level 5 NVQ Diploma in Management and Leadership (QCF) Page 1 Level 5 NVQ Diploma in Management and Leadership
More informationOperational Excellence Management System
Operational Excellence Management System Operational Excellence Management System FTO Services is committed to conducting business in a manner that is compatible with the environmental and economic needs
More informationProject Systems Management Providing Value-Added Solutions
Project Systems Management Providing Value-Added Solutions UPSTREAM MIDSTREAM AUTOMATION PROCESS & INDUSTRIAL PIPELINE PROCESS PLANTS Adding Value to Your Project Mustang couples global engineering, design,
More informationHIGHWAY INFRASTRUCTURE ASSET MANAGEMENT STRATEGY
HIGHWAY INFRASTRUCTURE ASSET MANAGEMENT STRATEGY 16 November 2015 Highway Infrastructure Asset Management Strategy Contents Introduction 1.0 The Need for Asset Management 1.1. Background 1.2. Aims and
More informationMeasuring returns on community investments in mining
Measuring returns on community investments in mining Veronica Nyhan Jones IFC, United States Jelena Lukic* IFC, United States Arjun Bhalla IFC, United States Dafna Tapiero IFC, United States ABSTRACT To
More informationOur business approach Risk Management
Our business approach Risk Management Manage your risks to prepare your future and achieve your objectives Technip at a glance Technip is a world leader in project management, engineering and construction
More informationTHE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
More informationNORWEGIAN PROJECT MANAGEMENT PRINCIPLES APPLIED IN THE JURONG ROCK CAVERN PROJECT
NORWEGIAN PROJECT MANAGEMENT PRINCIPLES APPLIED IN THE JURONG ROCK CAVERN PROJECT FINN FAGERVIK 1, PETTER PLASSBAK 1 and TEO TIONG YONG 2 1 Sintef-Tritech-Multiconsult (STM) Consortium, Singapore E-mail:ff@multiconsult.no
More informationDepartment of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB51407 Diploma of Project Management
Department of Training and Workforce Development Western Australia RPL Assessment Tool Kit BSB51407 Diploma of Project Management First published 2010 ISBN 978-1-74205-511-4 Department of Training and
More informationIRM CERTIFICATE AND DIPLOMA OUTLINE SYLLABUS
IRM CERTIFICATE AND DIPLOMA OUTLINE SYLLABUS 1 Module 1: Principles of Risk and Risk Management Module aims The aim of this module is to provide an introduction to the principles and concepts of risk and
More informationAvondale College Limited Enterprise Risk Management Framework 2014 2017
Avondale College Limited Enterprise Risk Management Framework 2014 2017 President s message Risk management is part of our daily life, something we do regularly; often without realising we are doing it.
More informationWATE R O&M S E RV I CE S An asset management perspective
WATE R O&M S E RV I CE S An asset management perspective Smart asset management solutions create long term value With more than 150 years of water industry experience and responsibility for operations
More informationMonte Carlo Simulations for Patient Recruitment: A Better Way to Forecast Enrollment
Monte Carlo Simulations for Patient Recruitment: A Better Way to Forecast Enrollment Introduction The clinical phases of drug development represent the eagerly awaited period where, after several years
More informationImproving pre-operational production efficiency estimates
Improving pre-operational production efficiency estimates ESRA seminar 28 th January 2015 Classification: Internal Production efficiency (PE) 100% Estimated production loss PE Production efficiency (PE)
More informationA Systems Approach for the ment and Management of Physical Infrastructure Dr D.S. Thorpe Queensland Department of Main s, Australia E-mail: David.S.Thorpe@Mains.qld.gov.au ABSTRACT: A methodology has been
More informationContract Management The Mavericks Won t Like This!
Contract Management The Mavericks Won t Like This! Keith Wallis How Much Did That Project Cost? Real Life Example Original contract amount $500K Variations scope changes not visible Total variations =
More informationThe 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
More informationA structured approach to Enterprise Risk Management (ERM) and the requirements of ISO 31000
A structured approach to Enterprise Risk Management (ERM) and the requirements of ISO 31000 Contents Executive summary Introduction Acknowledgements Part 1: Risk, risk management and ISO 31000 1 Nature
More informationTrade risk management: a global approach
World Customs Journal Trade risk management: a global approach Abstract Lorraine Trapani This article discusses IBM s global approach to managing risk associated with importing product into more than 170
More informationHEALTH, SAFETY, ENVIRONMENT AND COMMUNITY MANAGEMENT STANDARDS. OCTOBER 2011- ISSUE No 01. Doc No: HSEC MS 001
HEALTH, SAFETY, ENVIRONMENT AND COMMUNITY MANAGEMENT S OCTOBER 2011- ISSUE No 01 Doc No: MS 001 Introduction Celtique Energie is in the business of exploring for oil and gas in proven basins in Europe.
More informationMuch attention has been focused recently on enterprise risk management (ERM),
By S. Michael McLaughlin and Karen DeToro Much attention has been focused recently on enterprise risk management (ERM), not just in the insurance industry but in other industries as well. Across all industries,
More informationLinking Risk Management to Business Strategy, Processes, Operations and Reporting
Linking Risk Management to Business Strategy, Processes, Operations and Reporting Financial Management Institute of Canada February 17 th, 2010 KPMG LLP Agenda 1. Leading Practice Risk Management Principles
More informationKey features Q2 FY16. Managing Director s comments
27 January 2016 Key features Q2 FY16 Production steady: 123 kbbl in the 3 months to 31 December, vs previous quarter of 125 kbbl and up 2% on pcp of 118 kbbl Revenue of $7.0 million: down from $7.6 million
More informationTHE SOUTH AFRICAN HERITAGE RESOURCES AGENCY ENTERPRISE RISK MANAGEMENT FRAMEWORK
THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY ENTERPRISE RISK MANAGEMENT FRAMEWORK ACCOUNTABLE SIGNATURE AUTHORISED for implementation SIGNATURE On behalf of Chief Executive Officer SAHRA Council Date Date
More informationWHITE PAPER Business Process Services: A Successful Transition Is the Foundation of World- Class Outsourcing cgi.com
WHITE PAPER Business Process Services: A Successful Transition Is the Foundation of World- Class Outsourcing A summary of the key transition questions asked by our clients In this paper, we examine five
More informationGeneral Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.
Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60
More informationInternational Diploma in Risk Management Syllabus
International Diploma in Risk Management Syllabus Module 1: Principles of Risk and Risk Management The aim of this module is to provide an introduction to the principles and concepts of risk and risk management.
More informationEnterprise Risk Management & Information Technology
Enterprise Risk Management & Information Technology Presented by Scott Perry and Gary Ross Slalom Consulting, San Francisco Agenda Introductions Session Objectives Overview of Enterprise Risk Management
More informationFUNBIO PROJECT RISK MANAGEMENT GUIDELINES
FUNBIO PROJECT RISK MANAGEMENT GUIDELINES OP-09/2013 Responsible Unit: PMO Focal Point OBJECTIVE: This Operational Procedures presents the guidelines for the risk assessment and allocation process in projects.
More informationHow to Value Returns on Sustainability Investments in Emerging and Frontier Economies: Linking Community Outcomes and Business Value
March 2011 REFLECTIONS FROM PRACTICE How to Value Returns on Sustainability Investments in Emerging and Frontier Economies: Linking Community Outcomes and Business Value Authors: Veronica Nyhan Jones,
More informationThe PMO as a Project Management Integrator, Innovator and Interventionist
Article by Peter Mihailidis, Rad Miletich and Adel Khreich: Peter Mihailidis is an Associate Director with bluevisions, a project and program management consultancy based in Milsons Point in Sydney. Peter
More informationROAD NETWORK ASSET MANAGEMENT AS A BUSINESS PROCESS. Paper prepared for the REAAA Conference in Japan, 4 9 September 2000
ROAD NETWORK ASSET MANAGEMENT AS A BUSINESS PROCESS Paper prepared for the REAAA Conference in Japan, 4 9 September 2000 Florentina Mihai, BEng, GDipMgt, MIEAust Main Roads Western Australia Neville Binning,
More informationIntegrated Risk Management:
Integrated Risk Management: A Framework for Fraser Health For further information contact: Integrated Risk Management Fraser Health Corporate Office 300, 10334 152A Street Surrey, BC V3R 8T4 Phone: (604)
More informationPROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
More informationDo not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.
APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use
More informationProject Risk Management
PROJECT ADVISORY Project Risk Management Leadership Series 9 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes, but its content is
More informationEducational simulation in construction project risk management Setting the stage
Creative Construction Conference 2015 Educational simulation in construction project risk management Setting the stage Constanta-Nicoleta Bodea a), Augustin Purnus b) * a) Bucharest University of Economic
More informationIndustry Solutions Oil and Gas Engineering Document Control and Project Collaboration Solutions for Oil and Gas
Industry Solutions Oil and Gas Engineering Document Control and Project Collaboration Solutions for Oil and Gas Industry Solutions Managing the complexity of major capital projects in today s oil and gas
More informationCGAM022.1/12/10. Asset Management Improvement Strategy 2010
Asset Management Improvement Strategy 2010 Version Control Version No. Date Details Author/s 1.0 July 2009 Adopted Strategy 2.0 October 2010 Update TABLE OF CONTENTS OF CONTENTS 4 OF THE ASSET MANAGEMENT
More information