OVERCOMING KEY BARRIERS TO OFFSHORE WIND DEVELOPMENT IN THE NORTHEAST
|
|
|
- Marion Jones
- 9 years ago
- Views:
Transcription
1 OVERCOMING KEY BARRIERS TO OFFSHORE WIND DEVELOPMENT IN THE NORTHEAST Michael Ernst, Esq, Director of Regulatory Affairs Pace Law School & Environmental Review White Plains, NY March 2, 2012
2 Introduction to Tetra Tech Tetra Tech, Inc. Founded in 1966 Publicly traded on NASDAQ (TTEK) FY 2010 Revenues - $2.2 billion. More than 12,000 employees in 330 offices worldwide. Ranked #1 Wind Development Consulting Firm in 2010 and Top 10 Environmental Firms by Engineering News Record Full-Service Firm Providing Integrated Services Consulting (Siting, Surveys, Permitting), Engineering & Construction Supported Development of over 1000 Energy Projects last decade Supporting 450 wind projects totaling 22,000 MW Supporting 65 utility scale solar projects 30 Energy Construction projects 2500 MW and $500 M Siting & Permitting 10 Offshore Wind Farms Atlantic Coast: Maine, Rhode Island, MA, NY, NJ, DE, MD, VA Lakes Erie & Michigan
3 Outline of Presentation Offshore Wind Resource for Coastal States & New York Federal Offshore Wind Leasing Process Identify Wind Energy Areas/Environmental Assessments Requests for Information & Lease Block Nominations Competitive Bidding or Non-Competitive Process Site Assessment Plan (Surveys) & Construction & Operations Plan Offshore Submarine Cables Leasing Proposed Cables Federal & State Approvals Environmental, Legal, Technical & Financial Challenges Policies to Overcome Challenges Status of Northeast Leasing MA, RI, NJ, NY
4 Introduction to Offshore Wind Resource Wind Power Classification Wind Power Class Resource Potential Wind Power Density at 50 m W/m 2 a Wind Speed at 50 m m/s a Wind Speed at 50 m mph a Fair Good Excellent Outstanding Superb Wind speeds are based on a Weibull k value of
5 New York Offshore Wind Resource Renewable Portfolio Std: 24% by 2013 X MWs?? Long Island Power Authority RFP 2001?? Cancelled: Rising Costs NYPA Great Lakes RFP 2008?? RFP: 3 Bidder Interviews Postponed: High Costs LIPA All Resource RFP 2010?? Deepwater proposes cable from Rhode Island Wind Farm Cable interconnection to Mass. LIPA, Con Ed, NYPA Unsolicited Lease Nomination off Long Island [Add MAP=>
6 New York Offshore Wind Proposals Renewable Portfolio Std: 24% by 2013 or about 8000 MWs Long Island Power Authority RFP 2004 Costs rose to 29 c/kwh NYPA Great Lakes RFP 2009 RFP: 3 Bidder Interviews Postponed: High Costs LIPA All Resource RFP 2010 Deepwater proposes cable from Rhode Island Wind Farm Cable interconnection to Mass. NYPA, LIPA, Con Ed 2011 Unsolicited Lease Nomination 13M off Long Island NYPA 2011 Site Nomination =>
7 Alternative Energy Rulemaking EPACT 2005 directs issuance of rules within 270 days Programmatic EIS: May 2005 December pages of analysis plus appendices PEIS Conclusion: In general, most impacts would be negligible to moderate for all phases of wind energy development assuming that proper siting and mitigation measures are followed. Notice of Proposed Rulemaking: July 9, 2008 Tetra Tech helped draft AWEA Offshore Wind Working Group comments on Draft Rule to reduce proposed 3 Environmental Impact Statements Final Rule June 29, 2009 (233 pages in Federal Register) Minerals Management Service acknowledged final lease process may take 5-7 years or more due to 2 EISs Negotiations with MMS, lead NEPA agency, in late 2009 to reduce length of process consistent with NEPA and other federal laws: Level of NEPA review commensurate with likely environmental impacts Offshore Wind Development Coalition meetings with DOI and BOEMRE on more streamlining of process in January, March & April 2011 BOEM Smart from the Start Program: BOEM EA for Site Assessment
8 BOEM Lease Process State Task Forces Identify Area of Interest or Wind Energy Area (WEA) Request For Interest (RFI) Call for Information (Call) Determination of Competitive Interest Lease issued for site assessment Site Assessment Plan (SAP) & Surveys Construction & Operations Plan (COP) File Permit Applications NEPA Review Draft EIS (Third Party Contractor) Final EIS Record of Decision COP approved Certified Verification Agent approves Design & Construction Plans aka a Final
9 Request for Interest Request for Interest Process State Task Force Sets Area of Interest State Constraint Analyses & Meetings Request for Interest Nominations for specific lease blocks Demonstrate Legal, Technical & Financial Qualifications Public comments on any concerns Call for Nominations & Information Environmental Assessment for Site Surveys Determination of Competitive Interest Geographic overlap of nominated sites Total nominated capacity exceeds maximum target state s If either, initiate Competitive Process Delaware Constraints Map
10 Competitive Interest Process Competitive Interest Process Call for Information & Nominations Area Identification by BOEM after State Input NEPA Review & Coastal Zone Management Act Consistency Determination Proposed Sale Notice & 60-day Comments Final Sale Notice Competitive Auction Process Options: Sealed bidding Ascending bidding Two-stage bidding Multifactor bidding (30 CFR ) Bid Evaluation Issuance of Lease
11 Site Assessment Plan Survey Plan Development Per the BOEM Rules, the SAP or GAP must: Describe the survey activities proposed to characterize the development area; Demonstrate how site assessment activities will collect the necessary information and data required for the COP filing; and Show how the developer will comply with all relevant Federal statutes when conducting survey activities. The following 5 offshore site assessment surveys will play an integral part of offshore wind facility siting, planning, permitting, construction and operation. Avian and Bat Surveys Marine Mammal and Sea Turtle Surveys Geological, Geophysical and Hazard Surveys Marine Cultural Resource Surveys; and Benthic Surveys Each survey plan should be developed in close coordination with resource agencies of concern before implementation. Regional Environmental Assessments will reduce study & review requirements for standard surveys
12 Construction & Operations Plan BOEM COP Regs & Guidelines (30 CFR ) Site Investigation Report - Survey Results (shallow hazards, geological, geotechnical, biological, archeological) Construction & operation concept Compliance with Lease Stipulations Interconnection cables and power lines Decommissioning Plan Mitigation Measures List of Federal, State & Local Approvals NEPA Compliance Analysis Oil Spill Response Plan Safety Management System
13 Offshore Submarine Cables to Interconnect Renewable Projects to Grid BOEM Regulations for Cable Associated with Offshore Wind Farm A commercial lease will confer the right to a project easement to install on the OCS gathering, transmission, and distribution cables 30 CFR (b) Preliminary transmission plans submitted with the Construction & Operations Plan (COP) or General Activities Plan (GAP) Terms and conditions for the project easement will be issued by BOEM in an addendum to the lease
14 Offshore Cables for Renewable Projects Regulations for Independent Cable to Transmit Offshore Renewable Energy BOEM will issue ROW grants to allow for the construction and use of a cable or pipeline for the purpose of gathering, transmitting, distributing, or otherwise transporting electricity generated or produced from renewable energy not generated on a lease issued under this part. Final Rule, 74 Federal Register 19647; (a). BOEM will consider on a case-by-case basis, renewable energy ROWs supporting the transmission of energy from oil or gas sources that is combined with energy from sources other than oil or gas, provided that renewable energy generated from sources other than oil and gas is primarily what is being transmitted. 74 Fed Register Application for ROW (200 foot width plus area necessary for substation(s) Competitive Interest Determination General Activities Plan & NEPA Review Atlantic Wind Connection filed ROW Request with BOEM March 2011
15 Offshore Submarine Cable Backbone Atlantic Wind Connection 6000 MW HVDC Cable Interconnections in NY, NJ, DE & VA Filed application for lease & GAP at BOEM in March 2011 Competitive Interest Notice Deepwater Wind Cable Rhode Island Sound Wind Farm Cable to Long Island Mass. RFI 2 Cable Bids Dominion Resources Study Virginia Cable Study multiple wind farms Delaware Atlantic Coast Weather Study Great Lakes Cable Backbones? Lake Erie Canada & US interconnections
16 Major Federal, State & Local Approvals Federal, state and local approvals and consultations for the project will include but not be limited to: CZMA Consistency Determination for SAP and COP (NY Dept. of State) NOAA Letter of Concurrence to support Geophysical surveys activities USACE Section 10/404 Permit EPA Air Permit (construction vessel emissions) NOAA Incidental Harassment Authorization/Incidental Take (IHA/ITS) Permits under ESA and Marine Mammals Protection Act USFW Consultation and possible Incidental Take Permit under ESA for Eagles or EFH for endangered species, and Migratory Bird Treaty Act Advisory Council on Historic Preservation & SHPO Consultation under NHPA Dept. of Defense Consultation for military practice areas and defense radar USCG Private Aid to Navigation (PATON) and Local Notice to Mariners (LNM) Article VII CPCN from NY PSC (no Article X jurisdiction out of state) Submerged Lands Easement (NY Office of General Services) NY DEP: Art.XV Protection of Waters Permit, Tidal and Freshwater Wetlands Permits, Coastal Erosion Permit, 401 Water Quality Certification, NPDES Stormwater Construction Permit NYSDOT Highway Construction Permit Local zoning and building code approvals for interconnections & substations
17 Hydrokinetic Projects BOEM must first issue a lease, easement or Rightof-Way FERC may then issue a license to construct and operate March 2009 Memorandum of Understanding FERC & BOEM
18 Environmental Challenges Significant Environmental Issues Birds & Bats USF&W wants 3 yr studies Commercial Fishermen oppose any infringement of fishing grounds or spawning areas Marine mammals Collision risk during construction Icing in Great Lakes Collision with floating icebergs Cultural Issues Native American historic sites Radar Interference for DOD security, aircraft, weather Shipping routes: adequate buffer zones, warning devices Visibility from Sensitive Viewpoints on Shoreline
19 Overcoming Environmental Challenges Significant Environmental Issues Birds & Bats 3 years of pre-construction studies + post construction Commercial Fishing Avoid or accommodate within wind park Marine Mammal Construction warning systems Icing Foundation skirts & equipment protection Cultural Issues Archeological studies GGARCH Guidelines Radar Interference Negotiate with other agencies Shipping routes Negotiate navigation buffers & warning devices Visibility from Sensitive Viewpoints Minimize by siting further offshore
20 Legal & Technical Challenges Permitting Process First projects & impacts reviewed under current laws which did not anticipate offshore wind projects & interconnections New Legislation must be enacted & then new regulations Transmission Interconnections Sensitive coastal habitat: tidal and freshwater wetlands Inadequate capacity of shoreline grid along most shores Michigan Study: ~$200 Million for new lines & upgrades in U.P. New lines will be needed after initial offshore wind parks ISO-NE, MISO & PJM policy requires new generator to pay for interconnections and grid upgrades
21 Overcoming Legal & Technical Challenges Permitting Process Negotiate coordinated and streamlined siting under current and new laws NY Joint Application Expedite enactment of new legislation & drafting new rules Transmission Interconnections Study and Subsidize Grid Upgrades FERC 1000: ISOs must consider renewable policies in regional transmission planning & cost allocation Proposed offshore submarine cable backbones Atlantic Wind Connection (NJ to VA, initially) Deepwater Rhode Island Sound to Long Island New Integration Technologies: Energy Storage
22 Offshore Wind Financial Challenges Total Offshore Wind Development Costs Construction of Offshore Foundations with Special Vessels European Supply Chain for Turbines & Cables European Construction Expertise for Turbines & Cables Production & Investment Tax Credits Short Term Expiring 2012 U.S. Offshore Wind Project Prices Fishermen s Energy Atlantic City Pilot (20 MW) NJ BPU denies ORECs at ~30 cents/kwh Deepwater Block Island Rhode Island Pilot (30 MW) Legislative Act to override RIPUC rejection at 24.4 cents/kwh Cape Wind, Cape Cod (454 MW) Legislative Mandate & Merger Settlement to sell 77% at 18.7 cents/kwh
23 Overcoming Financial Challenges Offshore Wind Development Cost Savings Manufacture Turbines, Components, Cables in U.S. Manufacturing Tax Credits Offshore Submarine Cable Backbone for Many Wind Farms Construct U.S. Construction Vessels; Train U.S. Crews Extend Production & Investment Tax Credits Competitive Long Term Contract RFPs Broad Net Benefits Standard of Review for PPA for PUC OKs Increase Ocean Renewable Energy Credits (ORECs-NJ) Federal and State Loan Guarantees Federal and State Low Interest Loans Accelerated Depreciation Federal R&D (foundations; turbines, e.g.,floating) Future U.S. Offshore Wind Project Prices Deepwater projects low teens/kwh for 1000 MW wind farms DOE & U.Maine project 10 cents/kwh by 2030
24 Statoil Floating Wind Turbine Hywind Maine Hollow Cylinder seawater & sand Siemens 2.3 MW Turbine 2 years off Norway at 50% capacity Maine Pilot: 4 Siemens 3 MW 23 miles offshore 500 feet deep
25 Questions??? Contact Info: Michael Ernst, Esq. Director, Regulatory Affairs Tetra Tech Energy Program Federal Street Suite 300 Boston, MA 02110
26 Overcoming Challenges: Cross Sound Cable CT-NY 25 Mile Submarine Cable connecting New Haven, CT to Shoreham, NY 4 Shellfishermen asked for $8 million for minor, temporary impacts CT Attorney General became interested and then outspoken opponent CT Siting Board rejected initial project route Army Corps agrees to Permit 1 st Cable under Fed Navigation Channel CT Siting Board approves new route and mitigation Unanticipated Bedrock Prevents Full Compliance with Permits Negotiated Settlement with Shellfishermen then State Officials State lawsuit, DOE Order, FERC Application, partial reburial: $25M 4 yrs LESSONS: Appropriate siting and thorough initial and final environmental analyses Early PR & Education Campaign for public officials, stakeholders, public Negotiate settlement with well-funded opposition early Negotiate sufficient community compensation in PILOT agreement early
27 Massachusetts Cape Wind Cape Wind USACE Application 2001 BOEM FEIS, Lease & Construction & Ops Plan MA Energy Facilities Siting Bd Approved interconnection Chapter 91 Tidelands License Development of Regional Impact (Cape Cod Com n) Barnstable & Yarmouth OKs Environmental Impact Report Appeal to State Supreme Court Challenge to delegation of DEP Chap.91 authority to EFSC Appeal denied
28 Massachusetts BOEM Call BOEM Request for Information Dec Bids for leases >2,000 sq. naut. miles Commercial fishermen objected: => 1,000 miles Call for Nominations February 2012 Competitive process 2013
29 Rhode Island Special Area Management Plan (SAMP) RI-MA Area of Mutual Interest 2 Unsolicited Nominations Deepwater Wind Neptune LLC Both Qualified Call for Nominations February 23, 2012 Competitive Process? BOEM Wind Energy Area
30 New Jersey BPU RFP 3Bidders BOEM Call Nominations and Comments due June 6 Ocean RECs for 1100 MW Barrier Beaches Pinelands CAFRA [NEW MAP OF WEA]
LEASING & PERMITTING OFFSHORE WIND & CABLES IN NEW ENGLAND
LEASING & PERMITTING OFFSHORE WIND & CABLES IN NEW ENGLAND Michael Ernst, Esq, Director of Regulatory Affairs EBC Renewable Energy Committee Meeting Boston, MA January 15, 2013 Introduction to Tetra Tech
Regulating Offshore Renewable Energy Leasing and Development
Regulating Offshore Renewable Energy Leasing and Development Robert P. LaBelle Acting Associate Director Offshore Energy and Minerals Management Bureau of Ocean Energy Management, Regulation and Enforcement
Jen Banks Wind Energy Project Coordinator North Carolina Solar Center
Jen Banks Wind Energy Project Coordinator North Carolina Solar Center North Carolina Solar Center Mission Statement to advance the use of renewable energy resources to ensure a sustainable economy that
Pipeline Regulatory and Environmental Permits
Chapter 3 Pipeline Regulatory and Environmental Permits William E. Bauer Chapter Outline Introduction 57 3.1 Regulation of Interstate Pipelines 58 3.1.1 FERC-Regulated Natural Gas Pipelines 58 3.1.2 FERC-Regulated
Offshore Renewable Energy in Virginia
Offshore Renewable Energy in Virginia Presented to the Renewable Natural Resources Foundation December, 8 2009 Neil Rondorf Vice President, Maritime Operations Science Applications International Corporation
GAO PIPELINE PERMITTING. Interstate and Intrastate Natural Gas Permitting Processes Include Multiple Steps, and Time Frames Vary
GAO United States Government Accountability Office Report to Congressional Committees February 2013 PIPELINE PERMITTING Interstate and Intrastate Natural Gas Permitting Processes Include Multiple Steps,
28 September 2012 BY ELECTRONIC FILING
1200 18TH STREET, N.W., STE. 1200 WASHINGTON, D.C. 20036-2516 U.S.A. TEL +1 202 730 1300 FAX +1 202 730 1301 WWW.WILTSHIREGRANNIS.COM ATTORNEYS AT LAW BY ELECTRONIC FILING Ms. Jennifer Golladay Bureau
For additional information on qualifications and experience of representative EDGE senior staff members, please contact us.
About Us Edge Engineering & Science, LLC (EDGE) is a privately owned professional services firm headquartered in Houston, Texas. EDGE was established with the primary goal of providing high quality environmental
Northern Middlesex Council of Governments
Northern Middlesex Council of Governments The Federal Energy Commission (FERC) is the agency charged with evaluating whether the proposed route should be approved Cooperating agencies generally include
City of Vernon Request for Expressions of Interest and Information (RFI)
City of Vernon Request for Expressions of Interest and Information (RFI) Potential Wind Energy Project/Wind-Solar Energy Project City of Vernon Light & Power Department 4305 Santa Fe Avenue, Vernon CA
Overview of Long Island Electric Service Territory
Overview of Long Island Electric Service Territory Long Island Electric Service Territory» Long Island s electric service customers are located in Nassau County and Suffolk County (except for the villages
Position Statement regarding Offshore Wind Proposals on Lake Huron. Lake Huron Centre for Coastal Conservation
Position Statement regarding Offshore Wind Proposals on Lake Huron Lake Huron Centre for Coastal Conservation June 2010 Lake Huron Centre for Coastal Conservation (LHCCC) Corporate Position related to:
Gulf Coast Restoration & recovery 101 Basic policies, legal processes, and terms relevant to the Deepwater Horizon disaster
E N V I R O N M E N T A L L A W I N S T I T U T E O C E A N P R O G R A M W W W. E L I - O C E A N. ORG/ G U L F 1 7 3 0 M S T N W, S TE 700, W A S H I N G T O N, DC 2 0 0 3 6 T EL: 2 0 2. 9 3 9. 3 8 4
Worker Health and Safety on Offshore Wind Farms. June 17, 2014
Worker Health and Safety on Offshore Wind Farms June 17, 2014 Committee VADM James C. Card, United States Coast Guard (retired), Chair Dr. Thomas J. Lentz, National Institute for Occupational Safety and
THE LOCAL ROLE IN PERMITTING INTERSTATE NATURAL GAS PIPELINES MASSACHUSETTS ASSOCIATION OF CONSERVATION COMMISSIONS
THE LOCAL ROLE IN PERMITTING INTERSTATE NATURAL GAS PIPELINES PRESENTATION AT CITIZEN PLANNER TRAINING COLLABORATIVE CONFERENC E BY EUGENE B. BENSON, EXECUTIVE DIRECTOR, MACC MARCH 21, 2015 Massachusetts
Developing Ocean Energy in Ireland. Belmullet Wave Energy Test Site
Developing Ocean Energy in Ireland Belmullet Wave Energy Test Site Where does our energy come from? Most of the energy we use in Ireland comes from fossil fuels such as oil, coal, peat and gas. We burn
How PURPA is driving utility scale solar in North Carolina By QF Solutions April 7, 2015
How PURPA is driving utility scale solar in North Carolina By QF Solutions April 7, 2015 Overview 1. Utility Scale Solar in North Carolina 2. PURPA 101 What is PURPA? 3. How Avoided Costs are calculated
How To Build A Power Line From A Single Campus To A Power Plant
Combined Heat Power Supported Microgrids: Essential for the Evolution of Distributed Generation October 16, 2012 Joe Sullivan, VP, Energy Policy & Development Concord Engineering District Energy CCHP Historic
Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE
WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE 1 1 Welcome to The Eldorado-Ivanpah Transmission Project Open House How is the open house organized? This
Offshore Wind. IEEE Boston PES - November 16, 2010
Offshore Wind IEEE Boston PES - November 16, 2010 Offshore Wind A high-level overview of offshore wind project development identifying current technologies, challenges, risks and costs. Presented by: Brook
December 12, 2012. Dear Ms. Bornholdt:
December 12, 2012 Maureen Bornholdt Renewable Energy Program Manager Office of Renewable Energy Bureau of Ocean Energy Management 381 Elden Street Herndon, Virginia 20170 RE: Proposed Mitigation Measures
National Ocean Council
LEGAL AUTHORITIES RELATING TO THE IMPLEMENTATION OF COASTAL AND MARINE SPATIAL PLANNING TABLE OF CONTENTS I. THE LEGAL AUTHORITY FOR COASTAL AND MARINE SPATIAL PLANNING (CMSP)...1 II. OPERATIONAL PROGRAMS...2
US 281 AT PREMONT PUBLIC HEARING. US 281 at Premont Public Hearing
US 281 AT PREMONT PUBLIC HEARING Hearing Purpose The purpose of tonight s Public Hearing is for the public to: Learn about the status of the proposed project Review the purpose and need for the project
NOAA s Role in the Licensing of Offshore LNG Terminals
NOAA s Role in the Licensing of Offshore LNG Terminals Emily Lindow, National Oceanic and Atmospheric Administration Senior Advisor to the Under Secretary of Commerce for Oceans and Atmosphere NOAA and
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Elba Liquefaction Company, L.L.C. Southern LNG Company, L.L.C. Elba Express Company, L.L.C. Docket No. PF13-3-000 NOTICE OF INTENT TO PREPARE
Experience from the first large scale tidal turbine EIA in Europe. How do we work towards effective and proportionate EIA?
Independent, integrated thinking Experience from the first large scale tidal turbine EIA in Europe How do we work towards effective and proportionate EIA? Liz Foubister IEMA Webinar 30 th July 2014 What
Offshore Wind Energy Development In North Carolina
Bailey Stearns Miles Murphy Sara Marriott Evan Gruetter Johanna Colburn Jessica Gray Lindsey Cole Michelle Shreve Offshore Wind Energy Development In North Carolina Master of Coastal and Ocean Policy Candidates
An Act To Facilitate Testing and Demonstration of Renewable Ocean Energy Technology Be it enacted by the People of the State of Maine as follows:
PLEASE NOTE: Legislative Information cannot perform research, provide legal advice, or interpret Maine law. For legal assistance, please contact a qualified attorney. An Act To Facilitate Testing and Demonstration
National Marine Sanctuaries Act
Please note: This text is from the fourth edition of Federal Historic Preservation Laws, published in 2006 by the National Center for Cultural Resources, National Park Service, Department of the Interior.
Overview of Atlantic Offshore Renewable Energy Studies Program. Brian Hooker Office of Renewable Energy Programs
Overview of Atlantic Offshore Renewable Energy Studies Program Brian Hooker Office of Renewable Energy Programs February 2012 Completed Studies of Interest Compendium of Avian Information and Comprehensive
Minerals Management Service. U.S. Department of the Interior. Office of Offshore Alternative Energy Programs
Guidelines for the Minerals Management Service Renewable Energy Framework July 2009 U.S. Department of the Interior Herndon, VA Minerals Management Service Office of Offshore Alternative Energy Programs
Standardized Environmental Survey Protocols
14 Best Practices for Sustainable Wind Energy Development in the Great Lakes Region Great Lakes Wind Collaborative Best Practice #14 Standard environmental survey protocols should be developed by federal
Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment
Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment March 20, 2009 Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Table of Contents:
Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.
Submarine Power Cables State-of-the-art production facility, more than 100 years of experience and reference installations around the world. Reliable submarine power cables ABB is one of the world s most
Section 401 Water Quality Certification
Section 401 Water Quality Certification Department of Health Environmental Management Division Clean Water Branch Voice: (808) 586-4309 Fax: (808) 586-4352 http://www.hawaii.gov/health/environmental/water/cleanwater/index.html
Solar Energy Engineering, Consulting & Permitting Services
Page 1 of 5 Solar Energy Engineering, Consulting & Permitting Services Atlantic Design Engineers, Inc. (Atlantic) is a multi-disciplinary consulting firm providing professional services since 1987 in civil
Preliminary Views on the Draft Early Restoration Programmatic Environmental Impact Statement and Phase III Early Restoration Plan
Preliminary Views on the Draft Early Restoration Programmatic Environmental Impact Statement and Phase III Early Restoration Plan The Deepwater Horizon Natural Resource Damage Assessment Trustees (Trustees)
PUBLIC NOTICE PROJECT: Trans Bay Cable Maintenance Project
SAN FRANCISCO DISTRICT PUBLIC NOTICE PROJECT: Trans Bay Cable Maintenance Project Regulatory Division 1455 Market Street, 16 th Floor San Francisco, CA 94103-1398 PUBLIC NOTICE NUMBER: 2004-28512S PUBLIC
Environmental Law Primer. Adapted from Vermont Law School s Environmental Law Primer for Journalists
Environmental Law Primer Adapted from Vermont Law School s Environmental Law Primer for Journalists General Categories Command and Control Liability Disclosure Ecosystem and Place-based Programs Marketable
The National Environmental Policy Act (NEPA)
The National Environmental Policy Act (NEPA) Steve Kokkinakis National Oceanic and Atmospheric Administration Office of Program Planning and Integration NEPA Compliance and Coordination The National Environmental
Ocean Dumping Act: A Summary of the Law
Claudia Copeland Specialist in Resources and Environmental Policy December 15, 2010 Congressional Research Service CRS Report for Congress Prepared for Members and Committees of Congress 7-5700 www.crs.gov
3. The submittal shall include a proposed scope of work to confirm the provided project description;
QIN Shoreline Master Program Project Summary The Shoreline Master Program (SMP) development process for the Quinault Indian Nation (QIN) includes the completion of inventory and analysis report with corresponding
Appendix J Online Questionnaire
Appendix J Online Questionnaire In accordance with the Paperwork Reduction Act, this questionnaire was approved by the Office of Management and Budget (OMB). The OMB control number and expiration date
Strategy of the German Government on the use of off-shore wind energy
Strategy of the German Government on the use of off-shore wind energy in the context of its national sustainability strategy Ministries involved: Federal Ministry for the Environment, Nature Conservation
SECTION 9 SUMMARY OF COORDINATION, PUBLIC VIEWS AND COMMENTS
SECTION 9 SUMMARY OF COORDINATION, PUBLIC VIEWS AND COMMENTS This page intentionally left blank. 9.0SUMMARY OF COORDINATION, PUBLIC VIEWS AND COMMENTS 9.1 PUBLIC OUTREACH AND PUBLIC INVOLVEMENT Public
Renewable and Alternative Energy Outlook
Renewable and Alternative Energy Outlook Mary Doswell Senior Vice President Alternative Energy Solutions Governor s Conference on Energy October 13, 2010 Dominion: One of America s Leading Energy Companies
Environmental Compliance Questionnaire for National Oceanic and Atmospheric Administration Federal Financial Assistance Applicants
OMB Approval No.: 0648-0538 Environmental Compliance Questionnaire for National Oceanic and Atmospheric Administration Federal Financial Assistance Applicants Instructions The National Environmental Policy
Chapter 5. Other Accounts 5-1
Chapter 5 Other Accounts 5-1 Other Discretionary Funds (Dollars in Thousands) FY 2006 FY 2007 Program Changes Total Other Discretionary Funds Coastal Zone Management Fund $0 $0 $0 $0 Fisherman's Contingency
DESC Renewables & ESPCs
WARFIGHTER FOCUSED, GLOBALLY RESPONSIVE SUPPLY CHAIN LEADERSHIP DEFENSE LOGISTICS AGENCY AMERICA S COMBAT SUPPORT LOGISTICS AGENCY DESC Renewables & ESPCs John Nelson, Energy Analyst April 2010 WARFIGHTER
London Array. Operations and Maintenance
London Array londonarray.com London Array Operations & Maintenance Base Port of Ramsgate Military Road Ramsgate CT11 9LG Registered in England and Wales No 04344423 Operations and Maintenance 1 2 Operations
151 FERC 62,145 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION
151 FERC 62,145 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Cross-Sound Cable Company, LLC AIA Energy North America, LLC Docket No. EC15-122-000 ORDER AUTHORIZING ACQUISITION AND DISPOSITION
A View from the (Deepwater) Horizon: Regulatory and Statutory Developments Affecting Offshore Drilling and. Spill Liability.
A View from the (Deepwater) Horizon: Regulatory and Statutory Developments Affecting Offshore Drilling and Spill Liability Gerald D. Higdon 600 Travis, Suite 2800 Houston, TX 77002 713-238-3709 [email protected]
Regulation of Natural Gas Pipelines. June 23, 2008
Regulation of Natural Gas Pipelines June 23, 2008 Federal and State Regulations Federal: 49 United States Code 60101. et. seq. Title 49 Code of Federal Regulations The Office of Pipeline Safety (OPS),
NATIONAL MARINE FISHERIES SERVICE INSTRUCTION 02-110-17
Department of Commerce $ National Oceanic & Atmospheric Administration $ National Marine Fisheries Service NATIONAL MARINE FISHERIES SERVICE INSTRUCTION 02-110-17 Protected Resource Management Endangered
The Northwest National Marine Renewable Energy Center
The Northwest National Marine Renewable Energy Center Meleah Ashford, Program Manager Oregon State University Northwest National Marine Renewable Energy Center One of two national marine renewable energy
Presentation to: Federal Renewable Ocean Energy Working Group Oregon Military Department (OMD) Marine Renewable Energy
Presentation to: Federal Renewable Ocean Energy Working Group Oregon Military Department (OMD) Marine Renewable Energy Energy Independence Energy Security Disaster Resilience Camp Rilea Energy The Model
2012 Project Summary NORTHEAST RECREATIONAL BOATER SURVEY
2012 Project Summary NORTHEAST RECREATIONAL BOATER SURVEY image courtesy of Urban Harbors Institute of UMass Boston A partnership among industry, government, and nongovernmental organizations conducted
The Donut Hole Sunset The San Francisco-Pacifica Exclusion Zone
The Donut Hole Sunset The San Francisco-Pacifica Exclusion Zone Changes to the exclusionary factors since designation Presentation to the Gulf of the Farallones National Marine Sanctuary Advisory Council
U.S. Army Corps. of Engineers. A Learning Organization
U.S. Army Corps A Learning Organization The Corps is committed to the protection of coral reefs and the effective mitigation of any impacts. The Corps believes that there is a need to improve the understanding
CLEAN LINE ENERGY PARTNERS:
CLEAN LINE ENERGY PARTNERS: Building Transmission To Facilitate Large-Scale Renewable Energy Development Overview: Clean Line Energy Partners is developing four large transmission projects to connect areas
Photo by Jeff Thibodeau, Helios Land Design
SECTION 11 REFERENCES Photo by Jeff Thibodeau, Helios Land Design PUBLIC REVIEW DRAFT Cape Cod Commission, Affordable Housing Funds, Memo from Paul Ruchinskas to County Commissioners, January 4, 2006.
Statement for the Record
Statement for the Record Kevin R. Hennessy Director Federal, State and Local Affairs New England Dominion Resources, Inc. Infrastructure Needs for Heat and Power Quadrennial Energy Review Task Force April
Department of the Interior
Vol. 79 Tuesday, No. 189 September 30, 2014 Part V Department of the Interior Bureau of Land Management 43 CFR Parts 2800 and 2880 Competitive Processes, Terms, and Conditions for Leasing Public Lands
Dominion. Dan Weekley Vice President, Corporate Affairs. Dan Stoddard Senior Vice President, Nuclear Operations. March 24, 2016
Dominion Dan Weekley Vice President, Corporate Affairs Dan Stoddard Senior Vice President, Nuclear Operations March 24, 2016 Dominion Profile Power and Natural Gas Infrastructure Overview Leading provider
Department of Defense MANUAL
Department of Defense MANUAL NUMBER 4715.03 November 25, 2013 USD(AT&L) SUBJECT: Integrated Natural Resources Management Plan (INRMP) Implementation Manual References: See Enclosure 1 1. PURPOSE. In accordance
30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE FEDERAL NAVIGATION PROJECT IN COHASSET HARBOR COHASSET AND SCITUATE, MASSACHUSETTS
.-ro:'j - I US Army Corps of Engineers r& New England District 696 Virginia Road Concord, MA 01742-2751 Public Notice In Reply Refer to: Mr. Craig Martin [email protected] Programs/Project Management
MINERALS MANAGEMENT SERVICE
MINERALS MANAGEMENT SERVICE Mission The Minerals Management Service was formed by Secretarial Order in 1982 to facilitate the Nation s mineral revenue collection efforts and the management of its Outer