Options for real options Dealing with uncertainty in investment decisions for electricity networks

Size: px
Start display at page:

Download "Options for real options Dealing with uncertainty in investment decisions for electricity networks"

Transcription

1 Options for real options Dealing with uncertainty in investment decisions for electricity networks Ype C. Wijnia Risk Manager of Asset Management Essent Netwerk Den Bosch, The Netherlands Abstract - Part of the liberalization effort in the Netherlands was to regulate the income of the network companies. Although the reduction in income was not as dramatic as in the United Kingdom, it still forced the network companies to review their expenditures. Complicating the challenge was the silent requirement that the cost reduction should not result in more risk. This required a change in the valuation methods. So far these valuation methods have changed from purely technical criteria into a more risk based, net present value alike approach. The real option theory is not commonly used in the decisions. This seems a bit odd, as major uncertainties influence the valuation process. In this paper a few options in which the real option theory might be valuable are presented. It is an invitation to the real option specialists to show the network companies how real options could be of value. Keywords: Electricity Grid, Investment, Decision- Making, Real Options, Uncertainty. 1 Introduction According to the European regulations the electricity markets have to be liberalized. In this system competition is supposed to drive down costs and improve service levels. This competition presumably will not work for the networks, because the huge investments needed to build a competing network can never be recovered by gains in operating efficiency. Networks are `natural monopolies`. Because real competition is not feasible, regulators simulate competition by posing income cuts on the network companies. These cuts can be substantial. In the United Kingdom the average income cut for the network companies in the year april/march 1 was 1,%. The total average income cut over the period was more than 5%[1].The level of the income cut is determined by the efficiency improvement of the best player. In this situation it pays to be the most efficient network operator. Reacting to this incentive the network companies started to rationalize their expenditure patterns Paulien M. Herder Faculty of Technology, Policy and Management Delft University of Technology Delft, The Netherlands P.M.Herder@TBM.TUDelft.nl for the network. This is called Asset management by most companies. For asset management different definitions exist, although the differences in work practices are almost negligible. All Asset managers try to postpone investment, reduce operating cost and improve the performance of the network. To realize those seemingly conflicting targets at the same time two approaches can be followed regarding the investment opportunities 1 : 1. Optimize the individual opportunity. In this approach investment proposals are scanned for unnecessary or contra-productive activities. For example, Preventative Maintenance is based on the bathtub curve, according to which components have a high failure rate right after their start up (infant mortality) or after a certain period (wear out). However, while 7% of components suffer from infant mortality, only 11% shows wear out problems[]. In % of the cases maintenance would do more harm than good by introducing a new infant mortality phase.. Optimize the portfolio of investment opportunities. In this approach the effort is not spent on improving the individual proposals, but on searching for better opportunities in the network. For example, if the regulator sets a target for the Customer Average Interruption Duration Index (CAIDI) [3], this approach would identify all opportunities for improvement and start with the ones with the highest yield (CAIDI improvement per Euro spent). Of these alternatives the first is relatively straightforward, as it does not require a new approach to valuing the investment opportunities. The second one does. It requires a framework with which one can value the different aspects involved in infrastructure decision making, and there are many. All asset managers have somehow 1 In the context of this paper maintenance is also an investment opportunity.

2 introduced a multi criteria analysis in their decision making. This MCA can be a cost benefit approach, a costrisk approach, or any other variety of MCA available. Sometimes the MCA is performed at the individual investment, sometimes it looks at the portfolio, a few look even at the dependencies within the total expenditure portfolio 3. Although these new valuation frameworks have brought tremendous efforts [], most decisions are still plagued by large uncertainties in the prognoses. In financial asset management options are used to reduce the risk of uncertainties, and real options can be used for real asset management. However, so far real options are not commonly used in valuing the investment opportunities in electricity networks. In this paper we will explore the possibilities for the use of real options in valuing investments opportunities. To do so we will first describe the system in which the decisions about the infrastructure are made. Secondly, we will introduce a common decision problem for network managers. For this case we will use a number of decision criteria (both technical and economic), all resulting in a different outcome for investment timing. We then identify the uncertainties that drive these differences. A few of these uncertainties have been resolved over the years. Others have not. Finally, we will look at some opportunities for the real option theory to value solutions to overcome those remaining uncertainties. System description In this paper we look at decision making about investment opportunities in electricity networks. In this section we will describe the system in which the decisions are made and specify what we mean with an investment opportunity..1 Investment decisions Investment decisions in electricity infrastructures are quite different from financial investment decisions. Financial investments are supposed to deliver a series of future cash flows that, adjusted for the opportunity cost of capital, has a higher value to the investor than the initial payment[5]. An investment for which this is the case is said to have a positive Net Present Value (NPV). The decision rule is very simple: only make investments that have a positive NPV. Investment decisions in electricity networks cannot be based on such a simple rule. There are 3 major causes for this deviation: 1. It is very difficult to allocate cash inflows to specific network elements. Most elements can be removed individually without effects on the cash PRIMO, a portfolio optimizing tool developed by TNO telecom and Essent Netwerk. 3 For this a tool like dependency can be used ( inflow, but removing all elements will stop the cash inflow. Most investments in the network do not directly induce new income, but only create the opportunity to connect new customers.. Investments that do induce new income are new connections. However, to protect the customer against monopolistic behavior the network companies have the obligation to connect anyone requesting it to the network against predetermined tariffs, even if the new connection has a negative NPV. 3. Investments often deliver benefits on other values than the financial one, for example on safety, sustainability or reliability. For those values the agreed upon monetary equivalent is only an order of magnitude. For example, a fatality is mostly valued between 1 and 1 million euros. This is not nearly accurate enough to be used in Net Present Value calculations. Because of these differences with normal investment decisions we will call decision making in electricity networks risk management. This risk management consists of two control loops, as shown in the picture below. Decisions Institutional Environment of the system: Government and Public Regulations Control system: Decision makers, Engineers and Operators Risk Management (valuing opportunities) Network Risk Governance ( valuing risks) Network performance Network company performance Figure 1: The risk management model The first control loop is risk governance in which is decided about the monetary equivalent of the non financial values. Decided is put between quotation marks, as it often is no explicit valuation, but an implicit valuation that can be derived from the decision to implement certain regulations. If the costs and the benefits of those measures are known, the monetary equivalent can be calculated. Risk Governance involves multiple actors. The second control loop is risk management. In this loop the costs, the projected (non financial) benefits and the monetary value of those benefits are calculated and tested for a positive NPV. For this calculation the non financials have to be discounted at the same rate as the financials[].. Investment opportunities The problem space in the risk management cycle is very large. Although we only look at one case study, we do not

3 want to tempt the reader into thinking that decision making in infrastructures is easy. To get a feeling for the immensity of the problem space the table below shows some dimensions of the problem space with the upper and lower limit on the dimensions[7]. Table 1 Dimensions and upper and lower limit of the problem space village will not be interrupted if one of the cables fails. The power consumption in the village is growing. A question every asset managers asks is when the cable section should be upgraded with a third cable. The diagram below shows the basic outline of the problem. 11kV Dimension Lower limit (example) Consequenc Voltage sag e of failure Failure 1 ms (voltage duration sag) Probability <1- (Nuclear (1/yr) meltdown) Mitigation 1 (switchgear Size maintenance) Complexity Single criterion threshold (load level exceeded) Scope Technical (device settings) Time horizon Actors Risk Perception Tomorrow (new customer application) Single actor single objective Perception in line with objective risk analysis Upper limit (example) European blackout Weeks (France 1999) >1 (medium voltage interruptions) >1 G (new high capacity power plant) Multi criteria weighted sum (maintenance concept) Ethical (Can we continue operating overhead lines if this might increase the probability of leukemia) 5 years (network design for distributed generation) Multi actor multi objective Perception deviating from objective risk analysis Uncertainty Almost certain Uncertainty about consequences and likelihood Ambiguity Shared objectives Conflicting objectives High voltage substation 1 kv 3 Al, 1 3 Al, 1,5 Medium voltage substation1 kv Figure : The capacity decision problem In this diagram we see a redundant high voltage substation, to which the medium voltage substation is connected with two cables which have a nominal rating of 1 5. The total load connected to the substation is 1 and grows with 3% a year. The diagram below shows the development of power consumption in the last years and the prognosis of future demand Load development Figuur 3: Load development,5,5,5 Projected peak Historic peak In this table we can see 11 dimensions with upper and lower limits that can differ more than a factor 1 million. This makes it very difficult for the decision maker to keep the portfolio of activities consistent, or if that is not possible, at least coherent. 3 Case introduction The case we will look at is a fairly common capacity problem. A village of 5 customers is connected to the high voltage grid with two medium voltage cables. These two cables are designed to be redundant, meaning that the A single cable has a failure rate of about hours every 1 years. The likelihood of the second cable failing in this window is again hours per 1 years, resulting in a total likelihood of about once every 1 years with an average duration of about hours (half the window). As both cables can be the first to fail the combined frequency is doubled. This number does not account for common cause failures, in which a single event takes out both cables. 5 The real power capacity (in MW) is about 9% of the rating. The actual growth rate of electricity consumption is estimated between 1% and 3% annually, depending mostly on economic development.

4 Technical valuation.1 The classic approach: nominal rating The most safe decision approach is to upgrade the circuit with a third cable once the nominal rating of a single cable is reached. This means regardless of the circumstances, the remaining cable will not be overloaded in case the other cable fails. In the example above this would mean to upgrade the circuit in the year 5. This safe investment strategy therefore is an expensive one, as investments are made relatively early.. The enhanced approach: dynamic rating The failure mechanism behind overload is temperature related degradation of the insulation material. This means the overloaded cable will not fail immediately after an overload occurs, but only if the temperature has reached a critical level. As the cable and the surrounding ground need time to heat up, an overload could be accepted for a limited time. The diagram below shows the maximum allowed load levels (MALL) for some periods [],[9] second 3 Maximum allowed load levels 1 hour hour Time hour continuous MALL Figure : Maximum allowed load levels (MALL) of the electricity cable used in the example. All failures in the cables will be repaired within hours. In the figure above we can see that the cable can bear a load of 1 for hours. Investment timing Investment moment Investment moment according to according to hour continuous rating MALL Prognosis Historic Figure 5: The delay of investment by changing the criterion This means the circuit does not need upgrading before the load level has reached 1. This will only happen in 1. We see in figure 5 the replacement of the allowed nominal current by the allowed dynamic current delays the investment by years. Only in case the cable will not be repaired within hours there will be a slight increase in the risk. In the diagram below the shift from continuous rating to the hour MALL is visualized. 5 Economic valuation In the previous two decision approaches the decision criterion was technical. Could the customers be supplied if a failure occurred in one cable? In the decision no attention was paid to the value of the new cable. To value an investment in reliability a figure is needed for the value of reliability. As no real market exists for reliability this is a very difficult task. A figure commonly used for valuation of reliability is the economic damage caused by an interruption. However, this is a highly volatile number. A report by KEMA [1] showed values ranging between,5 EUR/kW and EUR/kW. For the quality regulation in the Netherlands the figure to be used is,5 EUR per customer minute lost (CML). With an average of kw per customer and an average interruption duration of two hours this equals 15 EUR/kW, well within the specified range. In this paper we will use the figure expressed in EUR/CML, as the interruption duration in the case deviates a factor from the average interruption duration in the Netherlands. To use this economic value in the decision we need a model to calculate the expected unreliability. In the base case we will assume that the cable will fail if its load exceeds the previously specified value of 1. The value of an interruption will be 5 customers times minutes times,5 EUR/CML equals Euro. Such an interruption is expected once every 5 years 7. The expected annual value of an interruption is then 19 euros. The economic value of the cable would be the net present value of this figure over 3 years (the life expectancy of the cable), resulting in a value of.111. euro. As the costs of a third cable are about 1.. euro 9, the benefits clearly exceed the costs. If in case of a failure only the part of the load that exceeds the maximum load level is interrupted, the economic damage could be limited very much. This is called load shedding. In the figure below the cost of load shedding are compared with the annuity of the investment (3 year,,5% real interest) in a new cable. For the 7 The failure rate of a single cable is 1 per 1 years. As there are cables, the failure rate of the circuit is per 1 years or 1 per 5 years. Based on a real interest rate of,5%. 9 Cables cost about 1 euro per kilometre

5 maximum allowed load level the safe value of 1 is used. We can see that there is no cost of load shedding until 1, the year in which the load exceeds1. Load shedding is the low cost alternative until the year 5. This means the use of a very simple risk calculation method will postpone the investment in a new cable until the year 5, a delay of years compared with the classical approach. load level is only 5,5. The peak load occurs only in blocks of hours, so with the current load pattern the limitation to the hour MALL is very risk averse. Even the use of the hour MALL combined with the maximum occurring load level would be risk averse. 1 Load pattern 1 Minimum Euro/year x Optimal investment timing Figure : Optimal timing of investment Valuing load shedding Cost of load shedding Annual cost cable Economic optimum The previous section showed a possible delay of investment in new capacity of about years. This would solve the expected problem of the income cuts for the network managers. They even would not have to think about investing in new capacity for at least 15 years. However, this only holds if load shedding is valued equally as the unintended power interruptions. There is evidence this is not the case. After the energy crisis in California the market was restructured to prevent any further rolling blackouts. The costs involved in this restructuring was a thousand times more than the expected economic damage resulting from those rolling blackouts[11]. This would result in a value of 5 euro/cml. If this figure is used for calculating the optimal investment moment it will not result in an extra delay compared with the dynamic rating example. In the following sections we will not consider involuntary load shedding any more. Instead, we will look further into the uncertainties of the risk model. 7 Uncertainties In the previous examples we did assume certainty in modelling the decision. Unfortunately we are not at all certain about the behaviour of cables and loads in reality. The first major deviation is the load pattern. The model assumed a continuous load level. In reality the load shows a pattern. In the diagram below the load pattern of the described case study is shown. The maximum load of 1 is only reached one hour a year. The average Hour in week,5 percentile 1, percentile Average 3,3 percentile 97,5 percentile Maximum Figuur 7: Actual Load pattern for a village recorded at Essent Netwerk. The diagram shows the distribution per hour of the week. For example, the maximum load of 1 occurred at hour 1 of the week, which is between 19. and. of a Saturday. However, for 3 (or 3%) of the 5 weeks the load in this hour 1 did not exceed 9. The second deviation is the timing of the incident. In the model we assumed that the interruptions were evenly distributed over the years. This is in accordance with cost benefit analyses[1] and net present value calculations[5]. However, in reality either a large interruption occurs, or no interruption at all. There is a reasonable likelihood that the circuit will not experience any failure in its lifetime. For a circuit with a failure rate of 5% per year the probability of no interruption at all in 3 years is more than %. It is clear that in an perfectly working circuit the redundant cable has no value. The third deviation is the actual economic damage caused by the interruption. As we have seen the damage can vary by a factor 1, depending on the type of customer connected. Not all areas have the same distribution of customer types. Optimizing the reliability on the average value would lead to a too low quality in areas with a high concentration of vulnerable customers, and vice versa. Besides, as customers move, the distribution is not constant over time. Therefore the true economic damage caused by failures is uncertain both in location and in time. The last major deviation is that the Maximum Allowed Load Levels are safe figures, at which a cable will not fail for certain. The model assumed that cables would fail for certain if the load exceeded the figure. This is most likely not the case. Unfortunately, the relation between load level and failure rate is not known very well. In some cases the load can be up to % of the MALL without causing any damage, in other cases the cables

6 might fail below the continuous level, if hot spots 1 are present in the circuit. Uncertainties resolved In this section we describe the methods that are currently in use to resolve two of the uncertainties..1 Load pattern A way to overcome the uncertainty in the load pattern is to replace the peak load characterization with a thermal equivalent load. This is the continuous load which dissipates the same amount of heat in the cable as the load pattern. As heat dissipation is proportional to the squared current, the thermal equivalent is the Root Mean Square (RMS) value of the pattern. In the example, the max line has a RMS value of,9. This is shown in the figure below. 1 1 Load pattern Hour in week Minimum,5 percentile 1, percentile Average 3,3 percentile 97,5 percentile Maximum RMS maximum Figure : the RMS value of the maximum If this RMS value is used in combination with the hour MALL, it is highly unlikely that in case of a cable failure the other cable will fail because of an overload. The diagram below shows the optimal investment timing Investment timing Investment moment according to hour MALL and RMS value Projected RMS Historic RMS Figure 9: Investment timing according to RMS value The use of the RMS value delays the investment until the year. This is again a technical judgment, in which no 1 A hot spot is a section of the cable in which the heat dissipating capacity is limited. This might be caused by the proximity of other cables, tree roots, air ducts or soil with a high heat resistance. attention is paid to the costs of the investment, or the expected costs of an interruption.. Incident timing In our base case model we assumed that every year a small interruption would occur, whereas in reality it would be a large interruption or no interruption at all. For a single circuit with a failure rate of 5% per year the probability of a worthless redundancy for the next 3 years is more than %. Fortunately, if one looks at multiple circuits at the same time, the behaviour of this set is represented correctly by the sum of the average interruption sizes of the individual circuit. As networks are a large set of circuits (the three large network companies in the Netherlands each have.5 million customers, corresponding to 5 circuits as described) this uncertainty automatically resolves itself if looked at from the portfolio perspective. 9 Options for real options Of the major uncertainties are more or less resolved currently, which was described in the previous section. However, major uncertainties remain. The first one is the true economic damage caused by an interruption; the other is the true capacity of the cable. Uncertainties lend themselves for real options. In case of the electricity network these would be waiting and learning before investing and making the capacity more flexible. In this section we will describe a few examples of those real options. Currently these investment alternatives are ignored by decision makers because of the problems in assigning the proper value. 9.1 True economic damage An approach to get a better estimate of the true economic damage in case of an interruption is to characterize the customers in the area for their vulnerability. However, as the valuation of the involuntary load shedding might differ by a factor 1 from the true economic damage, it seems reasonable to question this approach for its validity. Another approach is the use of load management contracts. A load management contract is an agreement between the network company and a customer, in which the customer commits itself to reduce power consumption when requested for by the network company. The network company pays a fee for this right. However, negotiating such a load management contract is quite a challenge, as it is vulnerable to all sorts of strategic behaviour. For example, a customer would try to get a fee as high as possible, regardless of the economic damage caused by the interruption. The price of the contract therefore would not be a measure of the true economic damage, but it would be a true measure of the value of the interruption. The limitations in this game are this expected damage as the lower limit and the worth of the investment postponement

7 for the network company. To be able to play this game correctly the network company needs to value the investment postponement, for which the real option theory seems the appropriate instrumentation. However, it is not clear yet to those network companies how the theory should be applied. 9. True cable capacity The true cable capacity is mostly determined by hotspots. At the moment the technology is available to measure the temperature of the cable real-time. This would allow the operator to monitor the cable for overload situations, and thus preventing a failure caused by such an overload. The costs of such a built-in thermometer are relatively modest. If such a technology was used in combination with the current design practices, it would become valuable in to 3 years. However, its worth is yet unknown. 9.3 Circuit upgrading options A final opportunity for the real option theory is to value a cable which can be upgraded relatively cheaply. For example, using a kv cable instead of a 1 kv cable allows for doubling the capacity if needed. It would require two 1/ kv transformers at both ends of the cable, but for long stretches of cable this would cost less than a new cable. The question is if the value of the option to expand relatively cheaply exceeds the extra cost of the cable. 1 Conclusions Network managers try to postpone investment in new capacity because of the income cuts posed upon them by the regulator. If the investment strategy for new capacity was based on maximum allowed load levels for continuous loads and the occurred peak load there are lots of opportunities to delay investment. This can be reached without any economic valuation, just by using common sense to review the investments. However, not all uncertainties can be resolved by using common sense. In case of load management contracts, cable monitoring equipment and circuit upgrading options the real option theory seems to be the appropriate tool to value the investment opportunities. If the real option theory could be used to value these uncertainties properly, it would be a great support for the decision makers of the future. Acknowledgement The research of the author, described in this paper, is sponsored by the Next Generation Infrastructures research programme ( References [1] Electricity Association, Electricity industry review,. [] ALM-3-79-C, "Reliability Centered Maintenance." [3] T. Short, "Reliability indices," presented at T&D World Expo, Indianapolis,. [] Y. C. Wijnia, "The Challenges of a risk based asset management organization," Strategic asset management, pp. 3-37,. [5] R. A. Brealey and S. C. Myers, Principles of corporate Finance. New York: McGraw-Hill,. [] "Spec Ranking regulatory investments in public health," in Treasury and General Government Appropriation Act, vol. Public law 1-55, 1. [7] Y. C. Wijnia and P. M. Herder, "Modeling Interdependencies in electricity infrastructure risk," presented at 1st Annual CZAEE International Conference Critical Infrastructure in the energy sector: Vulnerabilities and protection, Prague,. [] IEC 7, "Electric cables- calculation of the current rating," in Part 1-3: Current rating equations(1% load factor) and calculation of losses- current sharing between parallel single-core cables and calculation of circulating current losses,. [9] IEC 53, "Calculation of the cyclic and emergency current rating of cables," in Part 1: Cyclic rating factors for cables up to and including 1/3 (3) kv, 195. [1] KEMA, "Wensstromen: Gewenste kwaliteit- De waardering van de kwaliteit van levering van elektrische energie door aangeslotenen," KEMA, Arnhem PREGO 1 33-TDC 3-3B,. [11] M. de Bruijne, "Reliability against the odds: California's electricity crises," presented at 1st Annual CZAEE International Conference Critical Infrastructure in the energy sector: Vulnerabilities and protection, Prague,. [1] R. Sugden and A. Williams, The principles of practical Cost Benefit Analysis. Oxford: Oxford University Press, 197.

WHITEPAPER CABLE CONDUCTOR SIZING

WHITEPAPER CABLE CONDUCTOR SIZING WHITEPAPER CABLE CONDUCTOR SIZING FOR MINIMUM LIFE CYCLE COST Bruno De Wachter, Walter Hulshorst, Rodolfo di Stefano July 2011 ECI Available from www.leonardo-energy.org/node/156451 Document Issue Control

More information

Appropriate discount rates for long term public projects

Appropriate discount rates for long term public projects Appropriate discount rates for long term public projects Kåre P. Hagen, Professor Norwegian School of Economics Norway The 5th Concept Symposium on Project Governance Valuing the Future - Public Investments

More information

MBA Finance Part-Time Present Value

MBA Finance Part-Time Present Value MBA Finance Part-Time Present Value Professor Hugues Pirotte Spéder Solvay Business School Université Libre de Bruxelles Fall 2002 1 1 Present Value Objectives for this session : 1. Introduce present value

More information

Chapter 22 Real Options

Chapter 22 Real Options Chapter 22 Real Options Multiple Choice Questions 1. The following are the main types of real options: (I) The option to expand if the immediate investment project succeeds (II) The option to wait (and

More information

Distributed Temperature Monitoring of Energy Transmission and Distribution Systems

Distributed Temperature Monitoring of Energy Transmission and Distribution Systems 1 m 40000m0 range 61850 IEC spatial resolution Distributed Temperature Monitoring of Energy Transmission and Distribution Systems Ensuring a Reliable Supply of Electrical Power for Today s World www.en-sure.pro

More information

6. FINANCIAL MANAGEMENT

6. FINANCIAL MANAGEMENT 6. FINANCIAL MANAGEMENT Syllabus Financial Management: Investment-need, Appraisal and criteria, Financial analysis techniques-simple pay back period, Return on investment, Net present value, Internal rate

More information

Using simulation to calculate the NPV of a project

Using simulation to calculate the NPV of a project Using simulation to calculate the NPV of a project Marius Holtan Onward Inc. 5/31/2002 Monte Carlo simulation is fast becoming the technology of choice for evaluating and analyzing assets, be it pure financial

More information

1.0 03/02/2014 N/A Adrian Searle N/A Initial version (ED1 July 2013 submission baseline) 1.1 13/02/2014 Chris Ong All Reformatting of initial version

1.0 03/02/2014 N/A Adrian Searle N/A Initial version (ED1 July 2013 submission baseline) 1.1 13/02/2014 Chris Ong All Reformatting of initial version Document History Version Date Revision Class Originator Section Update Details 1.0 03/02/2014 N/A Adrian Searle N/A Initial version (ED1 July 2013 submission baseline) 1.1 13/02/2014 Chris Ong All Reformatting

More information

Assessing the Value of Flexibility in the Dutch Office Sector using Real Option Analysis

Assessing the Value of Flexibility in the Dutch Office Sector using Real Option Analysis Assessing the Value of Flexibility in the Dutch Office Sector using Real Option Analysis Joost P. Poort, Jun Hoo Abstract Flexibility is one of the key aspects of the Zuidas project, a major construction

More information

Real Options for the Future Energy Mix

Real Options for the Future Energy Mix August 08 Real Options for the Future Energy Mix A fair valuation of future investments In the coming years, both the demand for climate-friendly energy generation and the replacement of aging conventional

More information

FACOGAZ Association of European Gas Meter Manufacturers

FACOGAZ Association of European Gas Meter Manufacturers Page 1 of 13 GAS SMART METERING SYSTEM DRAFT MARCOGAZ/FACOGAZ POSITION PAPER FINAL 1. Introduction Marcogaz Members representing more than 100 million installed domestic gas meter in Europe owned by Distribution

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

The Importance of the X/R Ratio in Low-Voltage Short Circuit Studies

The Importance of the X/R Ratio in Low-Voltage Short Circuit Studies The Importance of the X/R Ratio in Low-Voltage Short Circuit Studies DATE: November 17, 1999 REVISION: AUTHOR: John Merrell Introduction In some short circuit studies, the X/R ratio is ignored when comparing

More information

Principles of Distribution charging:

Principles of Distribution charging: Principles of Distribution charging: Electricity networks Introduction A three-stage approach involves the following steps: 1. The analysis and quantification of costs. The cost concept that is relevant

More information

FULL ELECTRICAL LNG PLANTS: HIGHEST AVAILABILITY AND ENERGY EFFICIENCY THROUGH OVERALL SYSTEM DESIGN

FULL ELECTRICAL LNG PLANTS: HIGHEST AVAILABILITY AND ENERGY EFFICIENCY THROUGH OVERALL SYSTEM DESIGN FULL ELECTRICAL LN PLANTS: HIHEST AVAILABILITY AND ENERY EFFICIENCY THROUH OVERALL SYSTEM DESIN Dr. Edwin Lerch Siemens A Infrastructure and Cities Sector, IC S SE PTI, ermany Phone: 49-9131-7-34052 Fax:

More information

CE Entrepreneurship. Investment decision making

CE Entrepreneurship. Investment decision making CE Entrepreneurship Investment decision making Cash Flow For projects where there is a need to spend money to develop a product or establish a service which results in cash coming into the business in

More information

21 st Century Facilities

21 st Century Facilities Electrical Testing 21 st Century Facilities Facility Owners face tough challenges 24 X 7 reliability needed Non linear loads cause harmonics VFD Computers Switching transients disrupt operations Less customer

More information

Cable Size Selection for Energy Efficiency

Cable Size Selection for Energy Efficiency Cable Size Selection for Energy Efficiency Introduction The traditional method for determining the appropriate cable size for a particular installation involves the selection of the smallest size conductor

More information

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Lecture - 36 Location Problems In this lecture, we continue the discussion

More information

Nuclear Power Plant Electrical Power Supply System Requirements

Nuclear Power Plant Electrical Power Supply System Requirements 1 Nuclear Power Plant Electrical Power Supply System Requirements Željko Jurković, Krško NPP, zeljko.jurkovic@nek.si Abstract Various regulations and standards require from electrical power system of the

More information

PMCS. Integrated Energy Management Solution. Unlock the Full Potential of Power Networks Through Integration. Complete Solution. Informed Decisions

PMCS. Integrated Energy Management Solution. Unlock the Full Potential of Power Networks Through Integration. Complete Solution. Informed Decisions PMCS Integrated Energy Management Solution Unlock the Full Potential of Power Networks Through Integration Power Management Control System (PMCS) is a highly customizable, fully integrated end-to-end Energy

More information

(Relevant to AAT Examination Paper 4: Business Economics and Financial Mathematics)

(Relevant to AAT Examination Paper 4: Business Economics and Financial Mathematics) Decision making made easy (Relevant to AAT Examination Paper 4: Business Economics and Financial Mathematics) YO Lam, SCOPE, City University of Hong Kong In the competitive world of business, we need to

More information

Absolute and relative humidity Precise and comfort air-conditioning

Absolute and relative humidity Precise and comfort air-conditioning Absolute and relative humidity Precise and comfort air-conditioning Trends and best practices in data centers Compiled by: CONTEG Date: 30. 3. 2010 Version: 1.11 EN 2013 CONTEG. All rights reserved. No

More information

Simulation of Cable Overloading Problem on a University Distribution System

Simulation of Cable Overloading Problem on a University Distribution System Advance in Electronic and Electric Engineering. ISSN 2231-1297, Volume 3, Number 6 (2013), pp. 765-770 Research India Publications http://www.ripublication.com/aeee.htm Simulation of Cable Overloading

More information

Analysis of the electricity prices in the Slovak Republic and their impact on the individuals energy security

Analysis of the electricity prices in the Slovak Republic and their impact on the individuals energy security Analysis of the electricity prices in the Slovak Republic and their impact on the individuals energy security Abstract Martina Mokrišová Department of Finance and Accounting Faculty of Management University

More information

MAINTENANCE STRATEGIES FOR DISTRIBUTION NETWORKS

MAINTENANCE STRATEGIES FOR DISTRIBUTION NETWORKS MAINTENANCE STRATEGIES FOR DISTRIBUTION NETWORKS M. Marketz 1*, J. Polster 1, M. Muhr 2 1 KELAG - Kärntner Elektrizitäts-Aktiengesellschaft, Klagenfurt, Austria 2 University of Technology, Institute of

More information

Explaining and avoiding faults Increasing availability

Explaining and avoiding faults Increasing availability Explaining and avoiding faults Increasing availability > Cables > Cable joints > Cable terminals Cables, cable joints, cable terminals Increasing availability A cable breakdown usually means an unexpected

More information

READING 11: TAXES AND PRIVATE WEALTH MANAGEMENT IN A GLOBAL CONTEXT

READING 11: TAXES AND PRIVATE WEALTH MANAGEMENT IN A GLOBAL CONTEXT READING 11: TAXES AND PRIVATE WEALTH MANAGEMENT IN A GLOBAL CONTEXT Introduction Taxes have a significant impact on net performance and affect an adviser s understanding of risk for the taxable investor.

More information

Capital Budgeting OVERVIEW

Capital Budgeting OVERVIEW WSG12 7/7/03 4:25 PM Page 191 12 Capital Budgeting OVERVIEW This chapter concentrates on the long-term, strategic considerations and focuses primarily on the firm s investment opportunities. The discussions

More information

RCP2 Portfolio Overview Document

RCP2 Portfolio Overview Document RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Base Capex Expenditure Category: Grid Replacement & Refurbishment As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016

More information

Weekly Relative Value

Weekly Relative Value Back to Basics Identifying Value in Fixed Income Markets As managers of fixed income portfolios, one of our key responsibilities is to identify cheap sectors and securities for purchase while avoiding

More information

Optimization in the Virtual Data Center

Optimization in the Virtual Data Center THE INFORMATION SOURCE FOR THE DATA CENTER INDUSTRY Data Center Knowledge Guide to Optimization in the Virtual Data Center Realizing the full potential of a mission critical investment March 2013 Brought

More information

WHAT IS CAPITAL BUDGETING?

WHAT IS CAPITAL BUDGETING? WHAT IS CAPITAL BUDGETING? Capital budgeting is a required managerial tool. One duty of a financial manager is to choose investments with satisfactory cash flows and rates of return. Therefore, a financial

More information

NETWORK OUTPUT MEASURES CONSULTATION

NETWORK OUTPUT MEASURES CONSULTATION NETWORK OUTPUT MEASURES CONSULTATION Great Britain s electricity transmission network transmits high-voltage electricity from where it is produced to where it is needed throughout the country. It broadly

More information

Financial Analysis of Solar Photovoltaic Power plant in India

Financial Analysis of Solar Photovoltaic Power plant in India Financial Analysis of Solar Photovoltaic Power plant in India M. Ganga Prasanna, S. Mahammed Sameer, G. Hemavathi Department of Management Studies MadanapalleInstitute of Technology& Science Post Box No:

More information

A Review of Engineering Recommendations P15, P17 and P27 (Transformers, Cables and Overhead Lines)

A Review of Engineering Recommendations P15, P17 and P27 (Transformers, Cables and Overhead Lines) A Review of Engineering Recommendations P15, P17 and P27 (Transformers, Cables and Overhead Lines) DOCUMENT NUMBER CLNR-L263 AUTHORS David Miller, Northern Powergrid Duncan Yellen and Daniel Hollingworth,

More information

PRESENT DISCOUNTED VALUE

PRESENT DISCOUNTED VALUE THE BOND MARKET Bond a fixed (nominal) income asset which has a: -face value (stated value of the bond) - coupon interest rate (stated interest rate) - maturity date (length of time for fixed income payments)

More information

Life Cycle Asset Allocation A Suitable Approach for Defined Contribution Pension Plans

Life Cycle Asset Allocation A Suitable Approach for Defined Contribution Pension Plans Life Cycle Asset Allocation A Suitable Approach for Defined Contribution Pension Plans Challenges for defined contribution plans While Eastern Europe is a prominent example of the importance of defined

More information

Capacity planning for fossil fuel and renewable energy resources power plants

Capacity planning for fossil fuel and renewable energy resources power plants Capacity planning for fossil fuel and renewable energy resources power plants S. F. Ghaderi *,Reza Tanha ** Ahmad Karimi *** *,** Research Institute of Energy Management and Planning and Department of

More information

How To Know Market Risk

How To Know Market Risk Chapter 6 Market Risk for Single Trading Positions Market risk is the risk that the market value of trading positions will be adversely influenced by changes in prices and/or interest rates. For banks,

More information

A GLANCE AT THE EUROPEAN ENERGY MARKET LIBERALIZATION

A GLANCE AT THE EUROPEAN ENERGY MARKET LIBERALIZATION A GLANCE AT THE EUROPEAN ENERGY MARKET LIBERALIZATION Delia Vasilica Rotaru * Abstract: This paper offers a presentation on the liberalization process on the energy markets that started two decades ago

More information

Electric Gridlock: A National Solution

Electric Gridlock: A National Solution Electric Gridlock: A National Solution Jay Apt and Lester B. Lave Submitted August 27, 2003 Accepted for publication in the October 1, 2003 Public Utilities Fortnightly The August 14 th blackout was not

More information

Market Value of Insurance Contracts with Profit Sharing 1

Market Value of Insurance Contracts with Profit Sharing 1 Market Value of Insurance Contracts with Profit Sharing 1 Pieter Bouwknegt Nationale-Nederlanden Actuarial Dept PO Box 796 3000 AT Rotterdam The Netherlands Tel: (31)10-513 1326 Fax: (31)10-513 0120 E-mail:

More information

Executive summary 2. 1 Introduction 4

Executive summary 2. 1 Introduction 4 Flexible Networks for a Low Carbon Future Future Network Monitoring Strategy September 2015 Contents Executive summary 2 Glossary 3 1 Introduction 4 2 Fundamental principles of monitoring 5 2.1 LCT monitoring

More information

What is geotechnical risk?

What is geotechnical risk? 1 MANAGING GEOTECHNICAL RISK Dr David Cathie, Cathie Associates What is geotechnical risk? The saying "ignorance is bliss" applies well to geotechnical problems. Out of sight, out of mind often applies

More information

M & V Guidelines for HUD Energy Performance Contracts Guidance for ESCo-Developed Projects 1/21/2011

M & V Guidelines for HUD Energy Performance Contracts Guidance for ESCo-Developed Projects 1/21/2011 M & V Guidelines for HUD Energy Performance Contracts Guidance for ESCo-Developed Projects 1/21/2011 1) Purpose of the HUD M&V Guide This document contains the procedures and guidelines for quantifying

More information

3-PHASE LOW VOLTAGE NETWORK LOAD BALANCER : A COST EFFECTIVE SOLUTION TO LINE VOLTAGE VARIATIONS

3-PHASE LOW VOLTAGE NETWORK LOAD BALANCER : A COST EFFECTIVE SOLUTION TO LINE VOLTAGE VARIATIONS 3-PHASE LOW VOLTAGE NETWORK LOAD BALANCER : A COST EFFECTIVE SOLUTION TO LINE VOLTAGE VARIATIONS Pierre FRISTOT Olivier CONSTANT Catherine MONCET Omegawatt - France Omegawatt - France SDET - France pierre.fristot@omegawatt.fr

More information

Determining the Economic Value of Preventive Maintenance

Determining the Economic Value of Preventive Maintenance Determining the Economic Value of Preventive Maintenance Preventive maintenance has been more popular in principle than in practice over the years. One scarcely can argue with the idea of keeping equipment

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2

More information

RGI Cable Workshop Understanding Underground Cables 13 and 14 February in Spreitenbach, Switzerland A workshop kindly hosted by Swissgrid

RGI Cable Workshop Understanding Underground Cables 13 and 14 February in Spreitenbach, Switzerland A workshop kindly hosted by Swissgrid RGI Cable Workshop Understanding Underground Cables 13 and 14 February in Spreitenbach, Switzerland A workshop kindly hosted by Swissgrid During the 1.5 day workshop, more than 70 participants from industry,

More information

How To Calculate Discounted Cash Flow

How To Calculate Discounted Cash Flow Chapter 1 The Overall Process Capital Expenditures Whenever we make an expenditure that generates a cash flow benefit for more than one year, this is a capital expenditure. Examples include the purchase

More information

IASB/FASB Meeting Week beginning 11 April 2011. Top down approaches to discount rates

IASB/FASB Meeting Week beginning 11 April 2011. Top down approaches to discount rates IASB/FASB Meeting Week beginning 11 April 2011 IASB Agenda reference 5A FASB Agenda Staff Paper reference 63A Contacts Matthias Zeitler mzeitler@iasb.org +44 (0)20 7246 6453 Shayne Kuhaneck skuhaneck@fasb.org

More information

The Quest for Energy Efficiency. A White Paper from the experts in Business-Critical Continuity

The Quest for Energy Efficiency. A White Paper from the experts in Business-Critical Continuity The Quest for Energy Efficiency A White Paper from the experts in Business-Critical Continuity Abstract One of the most widely discussed issues throughout the world today is the rapidly increasing price

More information

CABLE MONITORING SOLUTION

CABLE MONITORING SOLUTION POWER CABLE MONITORING SOLUTION Kuljit Singh BSc Honours MIEE(IET,UK) Dan Watley Ph. D, B.A MEng (UK), MIEEE, UK 8-9 November 2011 PREDICT WITH CERTAINTY Definition DTS: Distributed Temperature Sensor

More information

Estimation of electrical losses in Network Rail Electrification Systems

Estimation of electrical losses in Network Rail Electrification Systems Estimation of electrical losses in Network Rail Electrification Systems Page 1 of 16 Contents 1. BACKGROUND...3 2. PURPOSE...3 3. SCOPE...3 4. DEFINITIONS & ABBREVIATIONS...4 5. NETWORK RAIL INFRASTRUCTURE

More information

European Distribution System Operators for Smart Grids. Position paper on Electric Vehicles Charging Infrastructure

European Distribution System Operators for Smart Grids. Position paper on Electric Vehicles Charging Infrastructure European Distribution System Operators for Smart Grids Position paper on Electric Vehicles Charging Infrastructure European Distribution System Operators for Smart Grids Position paper on ELECTRIC VEHICLES

More information

LECTURES ON REAL OPTIONS: PART I BASIC CONCEPTS

LECTURES ON REAL OPTIONS: PART I BASIC CONCEPTS LECTURES ON REAL OPTIONS: PART I BASIC CONCEPTS Robert S. Pindyck Massachusetts Institute of Technology Cambridge, MA 02142 Robert Pindyck (MIT) LECTURES ON REAL OPTIONS PART I August, 2008 1 / 44 Introduction

More information

QUANTITATIVE MODEL FOR INFORMATION SECURITY RISK MANAGEMENT

QUANTITATIVE MODEL FOR INFORMATION SECURITY RISK MANAGEMENT QUANTITATIVE MODEL FOR INFORMATION SECURITY RISK MANAGEMENT Rok Bojanc ZZI d.o.o. rok.bojanc@zzi.si Abstract: The paper presents a mathematical model to improve our knowledge of information security and

More information

Electric System Performance Review Trustees Briefing. April 2013

Electric System Performance Review Trustees Briefing. April 2013 Electric System Performance Review Trustees Briefing April 2013 Electric Reliability Indices All Metrics Continue to Perform Within Historical Range Reliability Index 2012 Trend to 5-Year Avg. LIPA MSA

More information

Oligopoly: How do firms behave when there are only a few competitors? These firms produce all or most of their industry s output.

Oligopoly: How do firms behave when there are only a few competitors? These firms produce all or most of their industry s output. Topic 8 Chapter 13 Oligopoly and Monopolistic Competition Econ 203 Topic 8 page 1 Oligopoly: How do firms behave when there are only a few competitors? These firms produce all or most of their industry

More information

Matching Investment Strategies in General Insurance Is it Worth It? Aim of Presentation. Background 34TH ANNUAL GIRO CONVENTION

Matching Investment Strategies in General Insurance Is it Worth It? Aim of Presentation. Background 34TH ANNUAL GIRO CONVENTION Matching Investment Strategies in General Insurance Is it Worth It? 34TH ANNUAL GIRO CONVENTION CELTIC MANOR RESORT, NEWPORT, WALES Aim of Presentation To answer a key question: What are the benefit of

More information

The Internal Rate of Return Model for Life Insurance Policies

The Internal Rate of Return Model for Life Insurance Policies The Internal Rate of Return Model for Life Insurance Policies Abstract Life insurance policies are no longer seen solely as a means of insuring life. Due to many new features introduced by life insurers,

More information

CHAPTER 15: THE TERM STRUCTURE OF INTEREST RATES

CHAPTER 15: THE TERM STRUCTURE OF INTEREST RATES Chapter - The Term Structure of Interest Rates CHAPTER : THE TERM STRUCTURE OF INTEREST RATES PROBLEM SETS.. In general, the forward rate can be viewed as the sum of the market s expectation of the future

More information

CREATING SYNERGY THROUGH MERGER AND ACQUISITION INTEGRATION: AN OVERVIEW

CREATING SYNERGY THROUGH MERGER AND ACQUISITION INTEGRATION: AN OVERVIEW 168 CREATING SYNERGY THROUGH MERGER AND ACQUISITION INTEGRATION: AN OVERVIEW SUMANTA DUTTA*; PROF.UTTAM KUMAR DUTTA**; SAJAL DAS*** *Assistant Professor, Department of Business Administration, Dinabandhu

More information

Guideline for Energy Efficient Electrical systems for building. Presentation by TERI

Guideline for Energy Efficient Electrical systems for building. Presentation by TERI Guideline for Energy Efficient Electrical systems for building Presentation by TERI Objective of study The study highlights how BBMP can implement energy efficiency measures in building in co-ordination

More information

Creating more Value out of Storage

Creating more Value out of Storage Creating more Value out of Storage By Gary Howorth, Founder Energy-Redefined Introduction Gas Storage is a complicated business which carries with it large risks and potentially low rewards. Assets can

More information

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H.

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H. POWER SUPPLY SYSTEMS AND ELECTRICAL EQUIPMENT FOR DESALINATION PLANTS Y.M. Hamud and A.H. Anwar Abu Dhabi Water and Electricity Authority, Abu Dhabi, UAE Keywords : Electrical System, Network for Desalination,

More information

ABB Fuses Competitive Advantages

ABB Fuses Competitive Advantages GPMM Tomasz Komalski 2009 ABB Fuses Competitive Advantages May 14, 2009 Slide 1 Basic comments ABB is a global manufacturer of both current limiting and expulsion (non-current limiting) fuses for medium

More information

Comparative study for cables and busbars

Comparative study for cables and busbars Comparative study for cables and busbars Preliminary considerations To compare the prices of two categories of product as different as traditional cables and busbars, it is necessary to make some preliminary

More information

Bonds. Valuation and Measures of Sensitivity

Bonds. Valuation and Measures of Sensitivity Bonds Valuation and Measures of Sensitivity Maturity management is essential, especially if a risk profile is asymmetric, as is typically the case when interest rates are low. Hans-Jörg Naumer Global Head

More information

Chapter 10. What is capital budgeting? Topics. The Basics of Capital Budgeting: Evaluating Cash Flows

Chapter 10. What is capital budgeting? Topics. The Basics of Capital Budgeting: Evaluating Cash Flows Chapter 10 The Basics of Capital Budgeting: Evaluating Cash Flows 1 Topics Overview and vocabulary Methods NPV IRR, MIRR Profitability Index Payback, discounted payback Unequal lives Economic life 2 What

More information

SWAN. The Value of Online Water Network Monitoring SUMMARY

SWAN. The Value of Online Water Network Monitoring SUMMARY SWAN S m a r t W a t e r N e t w o r k s F o r u m The Value of Online Water Network Monitoring SUMMARY Online water monitoring is the use of data transmitted from network elements, meters and sensors

More information

CHANGE MANAGEMENT PLAN WORKBOOK AND TEMPLATE

CHANGE MANAGEMENT PLAN WORKBOOK AND TEMPLATE CHANGE MANAGEMENT PLAN WORKBOOK AND TEMPLATE TABLE OF CONTENTS STEP 1 IDENTIFY THE CHANGE... 5 1.1 TYPE OF CHANGE... 5 1.2 REASON FOR THE CHANGE... 5 1.3 SCOPE THE CHANGE... 6 1.4 WHERE ARE YOU NOW?...

More information

The Real Options Attached to an Investment Project

The Real Options Attached to an Investment Project The Real Options Attached to an Investment Project Mihai-Cristian DINICĂ 1 ABSTRACT The real options capture the importance of the managerial team s role in creating value through investment projects.

More information

How to Ensure Adequate Retirement Income from DC Pension Plans

How to Ensure Adequate Retirement Income from DC Pension Plans ISSN 1995-2864 Financial Market Trends OECD 2009 Pre-publication version for Vol. 2009/2 Private Pensions and 0B the Financial Crisis: How to Ensure Adequate Retirement Income from DC Pension Plans Pablo

More information

PROVIDING RETIREMENT INCOME WITH STRUCTURED PRODUCTS

PROVIDING RETIREMENT INCOME WITH STRUCTURED PRODUCTS PROVIDING RETIREMENT INCOME WITH STRUCTURED PRODUCTS CUBE INVESTING David Stuff david.stuff@cubeinvesting.com ABSTRACT Structured products are an attractive type of investment for income seeking investors.

More information

REPLACEMENT PLANNING STRATEGY TO OPTIMIZE LIFE CYCLE PROFIT. N-7034 Trondheim Willy Hanssen, Trondheim Energiverk Nett AS

REPLACEMENT PLANNING STRATEGY TO OPTIMIZE LIFE CYCLE PROFIT. N-7034 Trondheim Willy Hanssen, Trondheim Energiverk Nett AS REPLACEMENT PLANNING STRATEGY TO OPTIMIZE LIFE CYCLE PROFIT Arnt Ove Eggen, Eivind Solvang Jan A. Foosnæs, Nord-Trøndelag Elektrisitetsverk SINTEF Energy Research Kjell Harald Hansen, Troms Kraft Nett

More information

arxiv:1605.04941v1 [q-fin.pr] 5 Mar 2016

arxiv:1605.04941v1 [q-fin.pr] 5 Mar 2016 On Mortgages and Refinancing Khizar Qureshi, Cheng Su May 18, 2016 arxiv:1605.04941v1 [q-fin.pr] 5 Mar 2016 Abstract In general, homeowners refinance in response to a decrease in interest rates, as their

More information

TAN δ (DELTA) CABLE TESTING OVERVIEW AND ANSWERS TO FREQUENTLY ASKED QUESTIONS. What Is Tan δ, Or Tan Delta?

TAN δ (DELTA) CABLE TESTING OVERVIEW AND ANSWERS TO FREQUENTLY ASKED QUESTIONS. What Is Tan δ, Or Tan Delta? TAN δ (DELTA) CABLE TESTING OVERVIEW AND ANSWERS TO FREQUENTLY ASKED QUESTIONS What Is Tan δ, Or Tan Delta? Tan Delta, also called Loss Angle or Dissipation Factor testing, is a diagnostic method of testing

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT 11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and

More information

Final Exam MØA 155 Financial Economics Fall 2009 Permitted Material: Calculator

Final Exam MØA 155 Financial Economics Fall 2009 Permitted Material: Calculator University of Stavanger (UiS) Stavanger Masters Program Final Exam MØA 155 Financial Economics Fall 2009 Permitted Material: Calculator The number in brackets is the weight for each problem. The weights

More information

FIXED CHARGE: This is a cost that goes towards making the service available, including

FIXED CHARGE: This is a cost that goes towards making the service available, including ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer

More information

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage Totally Integrated Power SIESTORAGE The modular energy storage system for a reliable power supply www.siemens.com/siestorage Totally Integrated Power (TIP) We bring power to the point. Our products, systems,

More information

Airline Fleet Maintenance: Trade-off Analysis of Alternate Aircraft Maintenance Approaches

Airline Fleet Maintenance: Trade-off Analysis of Alternate Aircraft Maintenance Approaches 2003 2004 2005 2006 2007 2008 2009 2010 Cost per Flight Hour (USD) Airline Fleet Maintenance: Trade-off Analysis of Alternate Aircraft Maintenance Approaches Mike Dupuy, Dan Wesely, Cody Jenkins Abstract

More information

SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES

SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES Table of Contents 1st. INTRODUCTION... 3 2nd. ELECTRICITY SECTOR BACKGROUND. 4 3rd. SCOPE OF WORK. 6 PHASE :

More information

CHAPTER 4: FINANCIAL ANALYSIS OVERVIEW

CHAPTER 4: FINANCIAL ANALYSIS OVERVIEW In the financial analysis examples in this book, you are generally given the all of the data you need to analyze the problem. In a real-life situation, you would need to frame the question, determine the

More information

Session 9b L&H Insurance in a Low Interest Rate Environment. Christian Liechti

Session 9b L&H Insurance in a Low Interest Rate Environment. Christian Liechti Session 9b L&H Insurance in a Low Interest Rate Environment Christian Liechti L&H Insurance in a Low Interest Rate Environment SOA Annual Symposium 24-25 June 2013 Macau, China Christian Liechti Swiss

More information

. In this case the leakage effect of tax increases is mitigated because some of the reduction in disposable income would have otherwise been saved.

. In this case the leakage effect of tax increases is mitigated because some of the reduction in disposable income would have otherwise been saved. Chapter 4 Review Questions. Explain how an increase in government spending and an equal increase in lump sum taxes can generate an increase in equilibrium output. Under what conditions will a balanced

More information

CHAPTER 6: RISK AVERSION AND CAPITAL ALLOCATION TO RISKY ASSETS

CHAPTER 6: RISK AVERSION AND CAPITAL ALLOCATION TO RISKY ASSETS CHAPTER 6: RISK AVERSION AND CAPITAL ALLOCATION TO RISKY ASSETS PROBLEM SETS 1. (e). (b) A higher borrowing is a consequence of the risk of the borrowers default. In perfect markets with no additional

More information

Proceedings of the 38th Hawaii International Conference on System Sciences - 2005

Proceedings of the 38th Hawaii International Conference on System Sciences - 2005 The use of Multi-Attribute Trade-Off Analysis in Strategic Planning For an Electric Distribution utility: An Analysis of Abu Dhabi Distribution Company Richard D. Tabors, Ph.D. Rick Hornby Tabors Caramanis

More information

Investment Appraisal INTRODUCTION

Investment Appraisal INTRODUCTION 8 Investment Appraisal INTRODUCTION After reading the chapter, you should: understand what is meant by the time value of money; be able to carry out a discounted cash flow analysis to assess the viability

More information

Scorecard MD&A - General Overview

Scorecard MD&A - General Overview Scorecard MD&A - General Overview In 2014, Essex Powerlines Corporation has exceeded all performance targets except for the Net Annual Peak Demand Savings. Essex has seen improvement in some areas from

More information

During the analysis of cash flows we assume that if time is discrete when:

During the analysis of cash flows we assume that if time is discrete when: Chapter 5. EVALUATION OF THE RETURN ON INVESTMENT Objectives: To evaluate the yield of cash flows using various methods. To simulate mathematical and real content situations related to the cash flow management

More information

Optimal Exercise Strategies for Employee Stock Options

Optimal Exercise Strategies for Employee Stock Options Optimal Exercise Strategies for Employee Stock Options Congratulations! If you are reading this paper with more than a casual interest, it is very likely that you are the owner of Employee Stock Options

More information

PART III: HORIZONTAL RULES. Criteria for the analysis of the compatibility of state aid for training subject to individual notification 1

PART III: HORIZONTAL RULES. Criteria for the analysis of the compatibility of state aid for training subject to individual notification 1 Page 1 PART III: HORIZONTAL RULES Criteria for the analysis of the compatibility of state aid for training subject to individual notification 1 1 Introduction (1) Training usually has positive external

More information

The Industrial Wireless Book - Articles TECHNICAL ARTICLE: USING GPRS TO CONNECT SMALL, OUTLYING STATIONS

The Industrial Wireless Book - Articles TECHNICAL ARTICLE: USING GPRS TO CONNECT SMALL, OUTLYING STATIONS Page 1 of 6 Print this Page Close this Window TECHNICAL ARTICLE: USING GPRS TO CONNECT SMALL, OUTLYING STATIONS Process monitoring and control for electricity distribution grids until now has been available

More information

23 Jan 2015 Hong Kong Electricity Market A Review & The Way Forward

23 Jan 2015 Hong Kong Electricity Market A Review & The Way Forward 23 Jan 2015 Hong Kong Electricity Market A Review & The Way Forward HK PolyU - School of Accounting & Finance Background Ongoing public discussion on energy policy 2015 Policy Address: consult the public

More information

Subordinated Debt and the Quality of Market Discipline in Banking by Mark Levonian Federal Reserve Bank of San Francisco

Subordinated Debt and the Quality of Market Discipline in Banking by Mark Levonian Federal Reserve Bank of San Francisco Subordinated Debt and the Quality of Market Discipline in Banking by Mark Levonian Federal Reserve Bank of San Francisco Comments by Gerald A. Hanweck Federal Deposit Insurance Corporation Visiting Scholar,

More information

Management Systems 10 Electrical Safety Audit 14 PPE 20 Arc Mitigation 22 Hazard Assessment 26

Management Systems 10 Electrical Safety Audit 14 PPE 20 Arc Mitigation 22 Hazard Assessment 26 Management Systems 10 Electrical Safety Audit 14 PPE 20 Arc Mitigation 22 Hazard Assessment 26 Assessing The Hazards Of High and Low Voltage Single-Phase Arc-Flash By Albert Marroquin One common question

More information

Credit Card Market Study Interim Report: Annex 5 Firm business model analysis

Credit Card Market Study Interim Report: Annex 5 Firm business model analysis MS14/6.2: Annex 5 Market Study business model analysis November 2015 Introduction 1. This annex summarises issuers approach to evaluating profitability, as well as a summary of the role of affinity and

More information