How Cisco IT Upgraded Its ERP Purchasing Module
|
|
|
- Melvin Curtis
- 10 years ago
- Views:
Transcription
1 How Cisco IT Upgraded Its Module New ERP platform for Cisco quote-to-cash business process improves purchasing for customers and partners. Cisco IT Case Study / < Business Applications / : This case study describes Cisco IT s process of designing, deploying, and ensuring the adoption of a new ERP platform for Cisco s quote-to-cash business process. This project was vast in scope, affecting one out of three employees and more than 30,000 customers and partners. The new platform gives Cisco a strong foundation for the future; customers gained functionality that will support tailored user experiences and streamlined operations. Customers can draw on Cisco IT s real-world experience in this area as a model for similar large-scale projects. Everest was called an upgrade, but it was so much more. It was a huge project with a long-term vision to create a world-class purchasing experience. One out of every three employees was affected by the project. Everest had a global impact on business processes, and its effects extended out to our customers and partners. The scope of the project was the biggest challenge we upgraded several Oracle 11i modules, replaced a large amount of custom code with standard 11i modules and tools, and changed 37 of our 69 major business processes along the way. David Murray, Director for Release Management, Oracle Projects, Cisco IT BACKGROUND At Cisco Systems, the Everest project was the final phase of a multiyear series of foundational software releases relating to the move from Oracle 10.7 to Oracle 11i software. The previous deployments and enhancements carried out as part of this companywide initiative included: System integration refinements across multiple functional areas Manufacturing and finance data platform upgrade (Cisco IT case study ERP Manufacturing and Finance Platform at _of_it/erp_manufacturing_and_finance.html) Issue-to-Resolution (I2R) foundation and order configurator software upgrades Service and support system migration (Cisco IT case study ERP Technical Support at _of_it/erp_technical_support.html Service reporting using Oracle 11i capabilities Service part planning system replacement and update of online service request tool Oracle iprocurement implementation Upgrading, merging, and implementing iprocurement for international operations Naming this Oracle 11i project was easy, says Laura Coon, the Everest release manager within Cisco IT. The upgrade of our ERP foundational software looked as formidable as an expedition to scale Mt. Everest. With the upgrade to Oracle 11i, we knew that many functional areas within Cisco would have to seriously evaluate and change crucial business processes. The companywide support was phenomenal and this challenge turned into a huge All contents are Copyright Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 1 of 12
2 opportunity. Our goal with the Everest project was to end up with a world-class purchasing experience for our customers and partners, and the entire company shared the commitment to this vision. The Everest project, like the other Oracle 11i upgrades and migration efforts, resulted from a combination of driving forces. In response to market changes, Cisco experienced: Growing recognition of the power of cross-functional collaboration, and internal demand for systems and processes that facilitate better interactions. Increasing demand for collaboration with suppliers, distributors, partners, and customers. Opportunities for enhancing enterprise resource planning (ERP) systems in support of online business models. Several internal drivers added momentum to the project. Oracle 10.7 had reached end-of-life status, creating support challenges and introducing escalating cost of ownership across the company. The outdated technology platform slowed the introduction of enhancements and made it difficult to respond to changing business requirements. A growing base of customized software and tools further complicated support and increased complexity within the infrastructure that handled vital corporate business processes. The technical and business challenges were further complicated by new corporate requirements for Sarbanes Oxley compliance; these collective forces drove an executive-level decision to upgrade the ERP software foundation. CHALLENGES Goal Setting The main purpose for the Everest project was to simplify and standardize customer-facing processes and controls. This included order management, pricing, invoicing, tax, and collections all the functions that rely upon the Oraclebased ERP systems. With the new, more stable, and standardized Oracle 11i foundation, global business processes could be streamlined, application customizations reduced, and out-of-date tools retired. The project goals included addressing the latest requirements for Sarbanes Oxley compliance, and improving the outsourcing model by developing collaborative problem-solving processes that could result in stronger, more productive vendor partnerships. As project planning progressed, it became clear that success would require the development of cross-functional partnerships for process and policy optimizations. The project definition also included process and system integration requirements to increase productivity and enable corporate growth. Automated compliance and governance solutions were included in the Everest project, with the goal of establishing a companywide architecture supporting these critical functions. Understanding and Defining the Scope of the Project The IT release team focused on meticulous data gathering during the global design review process. The team first determined that the Oracle 11i upgrade would affect 37 business processes, and then identified and analyzed the subprocesses. Approximately 1000 questions were posed and discussed with relevant teams and departments. More than 300 points of feedback were captured during the review process, 122 action items identified and documented, and 11 potential showstoppers raised and analyzed. While large in scope, the technical upgrade was more straightforward than the business process changes. The upgrade would involve: Oracle instances: 2 New Oracle modules: 4 Legacy systems retired: 9 (spanning order management, accounts receivable, and pricing) All contents are Copyright Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 2 of 12
3 Reduction in customizations: 35 percent Custom reports eliminated: 400+ Boundary systems: 140+ Developer days (without reports, as of January 2004): 40,000+ (across 500+ work units) Business processes retired (changed to end of life status): 6 Internal Cisco users: 10,000+ users and stakeholders across six business processes, globally Partners and customers: approximately 30,000 Significant change to customer interface for technical support organization (changed from text-based to browser-based) Ensuring Adoption Changing foundational systems and processes required continuous evaluation to ensure user acceptance and broad adoption of the new software and procedures. Team building, communication, and training were vital components of the overall project. SOLUTION Before and after diagrams of the Cisco Quote-to-Cash (QTC) software foundations (Figure 1) summarize the extent of the changes. Project success was measured in terms of the smoothness of the overall deployment and the minimization of disruption to the businesses of Cisco and its customers during the actual changeover. The project achieved success by maintaining focus on priorities, people, and processes. Extensive preparations clearly defined every step of the project before, during, and after the actual go-live event. All contents are Copyright Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 3 of 12
4 Figure 1. Upgraded Quote-to-Cash Architecture Priorities To keep the team unified and the project focused on the goals, priorities were defined for regulating compromises: Top priority: Robust implementation of Oracle 11i quote-to-cash processes and systems to create a solid, long-term foundation for corporate initiatives. Second priority: Robust system-to-system integration within the foundation. Third priority: Optimization of quote-to-cash process (quote-to-book, book-to-revenue recognition, invoice-tocash) where possible given release constraints. These priorities were defined by the release team, and buy-in was achieved at all levels, beginning at the executive level. This corporatewide support of the project priorities was deemed critical for success, and especially necessary for overcoming the challenges relating to assigning and scheduling subject matter experts to various tasks. People More than 10 major organizations including manufacturing, finance, sales, customer service, and customer advocacy were affected by the upgrade. Cross-functional teams came together to share information about joint planning, business and system requirements, analysis, and approvals. Organizations loaned some of their most knowledgeable staff members to support the project, and information was shared across all groups through participation in weekly release forums, all-hands meetings, readiness reviews, guidance and steering committee meetings, and functional forums. At the highest strategic level, the steering committee provided executive-level visibility for issue resolution and resource allocations, meeting every three weeks for the duration of the project and coordinating monthly executive-level reviews. This multitiered approach facilitated consistent and timely analysis and communication of program impacts, status, and risks. Executive-level participation strengthened cross-functional relationships, allowed the release management team to make decisions quickly, and helped the Everest team determine the right priorities at the right time to effectively utilize all resources. All contents are Copyright Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 4 of 12
5 Cisco IT created a release management team for the day-to-day management and implementation tasks, driven by the project goals and directives from the steering committee and functional management teams. The release management team was responsible for providing regular status reports back to the steering committee and functional management teams, as well as disseminating information as needed to company executives and employees. The collective project team of 1000 people was distributed geographically, requiring global collaboration. A central repository was created for documentation and an increased focus was placed on documenting discussions and decisions. In some cases, deliverables were assigned wholly to a non-headquarters location in order to provide improved efficiencies for the deliverable. Design and development phases of the project were improved by sharing resources and information across organizations. Specifically, the team created centralized and dedicated system performance and setup teams, established cross-functional design reviews, and held regular cross-track forums to keep the lines of communication open and to resolve issues quickly as they arose. Cross-process business readiness and organizational adoption teams were formed to identify affects of the system upgrade, to prepare internal stakeholders for the release, and to effectively manage partner and customer expectations. Due to the magnitude of the project and the number of people involved in the actual implementation and deployment, a formal decision making structure was defined, and critical roles identified (Table 1). Table 1. Project Roles and Responsibilities Critical Roles Release manager and team Infrastructure System/transition readiness Business readiness QA Boundary readiness Data migration Business and IT processes Responsibilities Overall coordination across teams Issue/risk management Milestone tracking Ensuring the ability to audit the program Test environment development and management Support Code migration Dependencies and sequencing of the cut-over tasks Ramp-down and down-time requirements Post go-live support Business normalization support Testing and change control processes Database and application performance testing Coordination across affected ERP boundary systems Business decision making process Technical tasks required for the core upgrade and data conversion Requirement gathering Functional designs Development for business processes All contents are Copyright Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 5 of 12
6 Organizational adoption Communications and training needed for internal users, customers, and partners Everest involved so many organizations, says Susan Stemel, IT project manager for the QTC implementation. The project brought everyone together with excellent communications and team building. The groups worked together well and the decision-making process was effective. This was only possible because everyone knew their own roles and the roles of the others on the team. The clarity of the responsibilities and the common goals kept us all moving in the same direction. Team members agreed to negotiate and collaborate in order to meet their objectives. Active listening and clearly documented processes helped everyone understand the end-to-end processes and project implications. Analysts and project managers from cross-functional organizations worked together to propose jointly agreed-upon solutions to their management teams rather than expecting managers to make final decisions from an organizational point of view. Ownership was shared by jointly investing in the release and by making individual team agendas subordinate to project team goals. For example, at the highest level, the steering committee made directed moves to support the project with the best resources, and made decisions as a team to defer new scope requests in favor of supporting project priorities. In order to facilitate a greater sense of belonging and ownership, the project team empowered team members worldwide to act as representatives during local hours. To give special recognition to team members that made significant contributions to the release efforts, a peer-to-peer recognition program was put in place. The attention paid to team building was considered a two-fold investment: it would ensure a smooth deployment, and would also optimize the rate of end-user adoption. Several best practices formed the foundation of the project teams: Executive sponsorship helped business groups understand the impact of the upcoming changes. Templates drove consistent business readiness plans to monitor and correct course as needed. Business normalization metrics defined normal so that business and project teams had a clear understanding of success criteria. True partnerships were created between project teams and functional areas to build a sense of personal investment into the transition. End-user adoption was carefully analyzed throughout the project. To make the transition as comfortable as possible, the release management team employed numerous best practices: Up-front communications: Users were made aware of objectives, changes, impacts, and benefits, which generated readiness for project milestones and activities. Stakeholder impact and readiness data: A Web-based knowledge management database gave each functional area and job role 24x7 access to up-to-date information on the release impacts, activities, and status. Sponsorship and end-user network: Functional-level ambassadors were identified and recruited to ensure that users in each affected area were prepared and empowered during the change process. Ambassadors communicated with their user communities and solicited feedback about the impact analysis and business readiness plans. Theater visits were conducted with groups most impacted by the release in order to solicit their thoughts and concerns. As a result of the valuable feedback from user groups, management, and guidance committee members, plans were adjusted. Training and support: Training courses were creatively developed and delivered, and progress was monitored to ensure completion by stakeholders. A total of 120 hours of training modules included 13 instructor-led and 32 Web-based modules. Training and collateral were created in multiple languages in order to increase understanding by the culturally diverse group of customers and internal stakeholders. All contents are Copyright Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 6 of 12
7 Process The Cisco release management methodology (Figure 2) brought a quality approach and industry best practices to the Everest project. The milestones required sign-off at the steering committee, functional management, or executive levels (as appropriate for the specific milestone): Concept commit: After the initial project assessments, the release team articulated a proof of concept and process improvement opportunities to the management team. Initial estimates for resource allocations were reported and approved. Execute commit: A consolidated summary by the business processes (quote-to-cash, etc.) for all areas was reviewed before design work began. At this sign-off point, the project scope, risks, timelines, and resource requirements were defined and approved. Global design review: This milestone confirmed the assessments of project impact and the ability of the changed processes and solutions to support Cisco s global operations. At this point, it was also confirmed that no global showstoppers remained. This review was integral to identifying conflicting priorities and requirements, resolving the differences, and reaching agreement about how joint decisions would be made. Readiness reviews: Each of the readiness phases were aimed at evaluating the project in terms of the organizations ability to successfully deploy the changes, and to ensure that acceptable levels of risk were not exceeded. Three formal business readiness reviews were held so that each organization could present their readiness status, risks, and launch preparation challenges. Figure 2. Cisco s Release Management Methodology Software Development Lifecycle ID & Assess Concept Commit Analysis Execute Commit Design Design Review Build & Unit Test Build Review Readiness Review 1 Test Cycle A: Cycle Discovery A Enterprise Test Readiness Readiness Post Project Review 2 Review 3 Assessment TC-B: Discovery, Quality, Cycle Stability B TC-C: Quality, Cycle Regression C Implement Support & Maintain Change Control Process Concept Commit Release Change Approval Board (RLCAB) Strict Change Control Bug Release Bug Approval Board Go-Live Extended Bug Approval Board Preparations The Everest project team prepared three platforms for the development, testing, and staging of the new ERP software. These platforms provided stable environments for the distinct phases before actual deployment within the Cisco production environment. In addition to three enterprise test cycles for testing the new software, a final test was carried out as the first step in the actual implementation phase. During this fourth and final test phase or transition test a team of 200 rehearsed the steps required for the go-live event. The seven-day 24x7 test allowed tasks to be practiced after the required cross-functional planning and training was complete. The transition test included the thousands of actual steps later followed to bring up the Oracle 11i ERP solutions. Processes, communications, and scenarios were refined after the transition test. The Everest project, in terms of the cross-functional requirements and interactions, was the most unbelievable event that I ve ever seen, says Guillermo Diaz, Jr., director of IS and IT project leader for the Cisco customer advocacy organization during the transition to Oracle 11i. Everybody in the company even though we were in different organizations and part of different business processes shared one vision to get to the top of Everest. We learned a lot about our company s ability to work together and to accomplish amazing results. All contents are Copyright Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 7 of 12
8 The Go-Live Event The exhaustive preparations and rehearsals resulted in a system cutover that had minimal impact on Cisco and its customers and partners. The go-live event took less time than anticipated only four days of downtime for the key systems, and only seven days total for all of the tools and applications involved. All of the affected organizations were ready and prepared, with workarounds and alternative tools in place to smooth the transition. A central war room made release team experts available to support deployment teams, and a help desk was staffed with trained support teams to assist end users as soon as the new systems went live. The new Oracle 11i deployment included: Replaced Oracle modules Order Management, Accounts Receivable, Collections, Credit Card applications, Pricing, Tax Engine, plus legacy ordering and commerce tools. Retired software 400+ ERP reports, nine legacy applications, seven programs (a 20-percent reduction of customizations). Enhancements Re-engineering 37 out of 63 QTC subprocesses. Enhanced integrations Service contracts and installed base; manufacturing; service logistics. Business process optimization Customer data (better validation and standardization of data across functional areas); standard order (improved accuracy, tighter business controls); standard return (closed loop receipt process); trade-in and asset recovery (better enforcement of expiration dates); credit card (more automation for validation and authorizations); commerce tools and business-to-business impacts (consolidation of tools, better business controls, improved customer experience); bundles (increased customer visibility of discount netting); and program retirement (identified several programs). Post-Deployment Efforts After the go-live event, teams throughout Cisco continued sharing responsibility for normalizing the business. Crossfunctional Tiger Teams were put in place to address issues quickly. The Tiger Teams prioritized, assigned, and tracked the issues through to resolution. RESULTS Despite the large scope and impact of the Everest release, the Cisco business was normalized on schedule within one quarter. The new foundation will be the basis for many business enhancements, enabling future collaboration between organizations and outside partners. The overwhelming success of the Everest project has given Cisco management confidence about large-scale projects, says Murray. It surpassed our expectations in terms of collaboration and results. Our teams were able to sustain exceptional performance over a long period of time, and demonstrated that communications and a common vision can inspire teams to reach for high goals. Cisco customers are also beneficiaries of the new ERP foundation. With the consistent platform, reduction of customizations, and process improvements, Cisco customers gain an improved purchasing experience. Some of the immediate results enjoyed by the company include: Better financial controls and tax applications Supportable global procurement Simplified pricing systems for product and service Scalable order fulfillment, order management, and accounting Scalable, integrated service logistics and case management The results are best summarized in terms of the reactions from the various teams within Cisco that were most affected by the release, shared in the following sections. All contents are Copyright Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 8 of 12
9 The Executive Team The implementation was world-class. It showed the results of excellent planning, excellent follow-through, and excellent execution. The team minimized the business risk involved and really focused, in a positive way, on the leverage we can gain from cross-functional collaboration to reduce business impact. John Chambers, President and CEO, Cisco Systems Oracle 11i, and specifically the Everest release, is unquestionably the most complex and sweeping system change Cisco has made in its history. Despite that complexity, the team did an outstanding job of delivering the project on time and with minimal impact to the business. The ability of the team to complete problem identification and resolution post go-live was outstanding. The success of this program is clearly attributable to the quality of the team and their dedication to meeting their commitments. Randy Pond, Senior Vice President, Operations, Processes and Systems, Cisco Systems Customer Service Where to begin The Everest implementation had a scope beyond immense, unprecedented complexity, and an execution totally dependent on the cross-functional cooperation and collaboration between hundreds of geographically dispersed people. What this team has pulled off is totally impressive. I credit the excellent preparation and training of the team, the multiple test cycles, and a response center team that had a plan ready for every situation. Dan Smoot, Director, Customer Services, Cisco Systems The new platform has given the Customer Services organization the stable, efficient platform required to handle hundreds of millions of dollars in orders each quarter. During the transition to go-live, the organization queued up 1700 orders. With the previous Oracle 10.7 foundation, processing the backlog would have required the dedication of their systems for 12 to 18 hours. When the new Everest release was turned on, the service team saw an immediate improvement: the backlog was processed without taking over the entire system, and was accomplished in only six hours. The smooth transition and fast normalization resulted from training more than 1100 employees during the months prior to the actual go-live. Finance Participation on the guidance committee was crucial for our organization. I received feedback from the release experts in my area, and had weekly opportunities to provide that feedback to the release management team. That regular communication and exchange of information between my team and the release management team kept us up to date and we resolved issues quickly. Our team was in the right mindset for the transition, and we were able to anticipate problems ahead of time, making it a much more positive process. Cesiah Tiran, Director of Corporate Finance, Cisco Systems With a multiyear project like Everest, the mission-critical QTC business process represented a major challenge. The implementation touched order entry and accounts receivable modules, affecting the revenue recognition for the company. Decisions had to be made without the ability to fully estimate the impact when the system would be deployed years later. With difficult-to-predict requirements, the finance team recognized the need for contingency planning. Success was achieved by focus on the rehearsals, and having a team and escalation process in place to address any surprises during the go-live event. Sales The Everest project was a huge endeavor for the sales organization more than 200 market-to-order applications touch the ERP system. We had to adjust all of those interfaces and redo our business processes. We adopted many new Oracle 11i tools and reduced our reliance on customized tools. This was all carried out with minimal impact on our customers. The preparation paid off and we had no surprises during the go-live transition. Perhaps even more important, the Everest project forced a major change in our organization. Where we had been previously separate from corporate with independent projects and systems we have now formed relationships with other functions in All contents are Copyright Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 9 of 12
10 Cisco. We are stronger today with our new understanding of related business operations, and stronger ties into other Cisco groups. Mrinalini Ingram, Director of Finance for U.S. Sales, Cisco Systems The entire Cisco sales force was affected by the upgrade of the ERP system. New tools and changed interfaces required extensive ongoing communications and training. By establishing stronger ties with corporate IT groups and other boundary organizations throughout Cisco, the sales organization gained a solid understanding of the potential challenges they would face during the transition. The collaborative preparation efforts resulted in reduced downtime for the sales team, and many enhanced business processes. Customer Advocacy Collaboration is part of the Cisco culture the Everest project is a great example. Without effective collaboration, this project could never have succeeded. Early on, the project leaders raised the profile for this program and got everyone aligned with the objectives. We could all look at the challenges and the tasks from a companywide perspective. Within Customer Advocacy, we learned a lot about how to manage a major IT implementation. The Everest release gives us the foundation we need to deliver a next-generation service contract solution we will be applying what we learned to a follow-on project that will greatly streamline our operation. Steve Blunt, Director of Customer Advocacy, Cisco Systems The new ERP platform required many changes in the interfaces facing the boundary systems such as the Customer Advocacy systems. This required the team to understand the integration issues for enabling data flow to the new ERP platform, and the performance requirements for meeting the service-level agreements (SLAs) of customers. In addition, the team had to ensure that the new interfaces would accommodate enhancements and new capabilities anticipated as needs for the future. By evaluating the Everest project in terms of both current and future business requirements, the Customer Advocacy team was able to inject their needs into the project design and planning phases. LESSONS LEARNED As project team members returned to pre-everest roles or moved on to new roles, they took with them a better understanding of teamworking behaviors that help to drive a more seamless customer experience across Cisco. At the same time, this project team is taking an increased understanding of customer impacts from internal Cisco projects back into their organizations roadmap discussions and planning exercises. Many teams have commented on the increased levels of proactive cross-functional planning. Their inter-cisco network has expanded to include contacts for answers to business process questions. Team members have also increased their appreciation for the value of end-user participation throughout project lifecycles. Instead of deferring to individual team messaging, Everest team members developed a new teamwork behavior and model allowing messaging to come from a sponsoring business process and then being tailored to meet their groups needs. This approach was used extensively by the Organization Adoption teams and is now accepted as a best practice for future initiatives. Universally, the Everest team has gained an increased sensitivity to team members in non-headquarter locations and how important it is to follow basic principles for meeting etiquette and scheduling. The company has also recognized the need to establish a site-project coordinator to streamline cross-functional discussions. Many lists of lessons learned have been shared in post-event presentations, with some highlights included here: Align organizational priorities and initiatives. Optimize use of subject matter expert time (off-load detailed deliverables and project management activities whenever possible). Actively mitigate risks to ensure release priorities are met. All contents are Copyright Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 10 of 12
11 Ownership must be driven by the business function. Collaboration brings results. Well-managed business rules and smooth order processes are directly related (affecting design and normalization). NEXT STEPS This last phase in the multiyear migration to the Oracle 11i platform now becomes the beginning of a new multiyear journey to take full advantage of the new platform. All the affected organizations are focused on getting back to business as usual, while looking forward to many innovative advances in business processes made possible by the enhanced technology foundation. Highly efficient cross-functional business processes now characterize Cisco s operations, and every team enjoys confidence in the company s ability to cooperate across functional areas to overcome business challenges. Some of the planned enhancements enabled by the new platform include: Global, segmented pricing models, policies, and processes Integrated offers: hardware, software, service, financing Improved and segmented ordering experience Widescale automation of financial controls Productivity improvements for sales, partners, and customers All contents are Copyright Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 11 of 12
12 FOR MORE INFORMATION To read the entire case study or for additional Cisco IT case studies on a variety of business solutions, visit Cisco on Cisco: Inside Cisco IT NOTE This publication describes how Cisco has benefited from the deployment of its own products. Many factors may have contributed to the results and benefits described; Cisco does not guarantee comparable results elsewhere. CISCO PROVIDES THIS PUBLICATION AS IS WITHOUT WARRANTY OF ANY KIND, EITHER EXPRESS OR IMPLIED, INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. Some jurisdictions do not allow disclaimer of express or implied warranties, therefore this disclaimer may not apply to you. All contents are Copyright Cisco Systems, Inc. All rights reserved. This document is Cisco Public Information. Page 12 of 12
How Cisco IT Migrated to an ERP Technical Support Module
How Cisco IT Migrated to an Module Companywide migration to standard tools for services management and configuration enable enterprise integration, full support for solutions, and smooth path for future
How Cisco IT Improved Strategic Vendor Management
How Cisco IT Improved Strategic Strategic sourcing for vendor management results in flexibility, simplicity, and reduced costs. Cisco IT Case Study / Business Management / : This case study describes the
SEVEN WAYS THAT BUSINESS PROCESS MANAGEMENT CAN IMPROVE YOUR ERP IMPLEMENTATION SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND
SEVEN WAYS THAT BUSINESS PROCESS MANAGEMENT CAN IMPROVE YOUR ERP IMPLEMENTATION SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND CONTENTS INTRODUCTION 3 EFFECTIVELY MANAGE THE SCOPE OF YOUR IMPLEMENTATION
Project, Program & Portfolio Management Help Leading Firms Deliver Value
in collaboration with Project, Program & Portfolio Help Leading Firms Deliver Value Managing Effectively & Efficiently Through an Enterprise PMO Program & Portfolio : Aligning IT Capabilities with Business
The New Value of Change Management: Success at Microsoft
The New Value of Change Management: Success at Microsoft by Molly Cooper, Microsoft IT Page 1 of 8 Summary Microsoft recently completed a significant IT transformation effort by replacing the existing
Cisco Unified Communications and Collaboration technology is changing the way we go about the business of the University.
Data Sheet Cisco Optimization s Optimize Your Solution using Cisco Expertise and Leading Practices Optimizing Your Business Architecture Today, enabling business innovation and agility is about being able
How Cisco IT Reduced Costs Through PC Asset Management
How Cisco IT Reduced Costs Through PC Asset Management Centralized network-based PC management program keeps employee desktops current and reduces costs. Cisco IT Case Study / IT Services Expense Management
How Cisco IT Uses Software Configuration Management to Minimize Business Risk
How Cisco IT Uses to Minimize Business Risk Application change management process improves software quality and developer productivity. Cisco IT Case Study / Business Management / : This case study describes
Mergers and Acquisitions: The Data Dimension
Global Excellence Mergers and Acquisitions: The Dimension A White Paper by Dr Walid el Abed CEO Trusted Intelligence Contents Preamble...............................................................3 The
Today, the Cisco Enterprise B2B team has created automated and standardized processes in the following areas:
How Cisco Enables Electronic Interactions with Sales, Manufacturing, and Service Partners Business-to-business drives productivity, growth, and an improved customer experience. Cisco IT Case Study/Business
Best Practices in Contract Migration
ebook Best Practices in Contract Migration Why You Should & How to Do It Introducing Contract Migration Organizations have as many as 10,000-200,000 contracts, perhaps more, yet very few organizations
Wilhelmenia Ravenell IT Manager Eli Lilly and Company
Wilhelmenia Ravenell IT Manager Eli Lilly and Company Agenda Introductions The Service Management Framework Keys of a successful Service management transformation Why transform? ROI and the customer experience
Enabling Business Transformation with Enterprise Architecture and IT Service Management
Cisco IT Article September 2012 Enterprise Architecture and IT Service Management Business Transformation through Architectures Enabling Business Transformation with Enterprise Architecture and IT Service
How Cisco IT Implemented Organizational Change and Advanced Services for Operational Success
How Cisco IT Implemented Organizational Change and Advanced Services for Operational Success New organizational framework greatly improves operations. Given today s pressing need to optimize IT services
CA Service Desk On-Demand
PRODUCT BRIEF: CA SERVICE DESK ON DEMAND -Demand Demand is a versatile, ready-to-use IT support solution delivered On Demand to help you build a superior Request, Incident, Change and Problem solving system.
CA Service Desk Manager
PRODUCT BRIEF: CA SERVICE DESK MANAGER CA Service Desk Manager CA SERVICE DESK MANAGER IS A VERSATILE, COMPREHENSIVE IT SUPPORT SOLUTION THAT HELPS YOU BUILD SUPERIOR INCIDENT AND PROBLEM MANAGEMENT PROCESSES
SERVICES. Designing, deploying and supporting world class communications solutions.
Designing, deploying and supporting world class communications solutions. DESIGN Expertise, technologies, tools and ideas Business environments, regulation, expansion and obsolescence are drivers that
How Cisco IT Planned and Executed a Global Data Center Strategy
Cisco IT Case Study November 2012 Global Data Center Program: Conclusion How Cisco IT Planned and Executed a Global Data Center Strategy We Value Your Feedback EXECUTIVE SUMMARY CHALLENGE Increase capacity
TECHNOLOGY STRATEGY AUDIT
TECHNOLOGY STRATEGY AUDIT Executive Summary It is our intention to facilitate the understanding of technology strategy and its integration with business strategies. This guideline is organized as series
Your asset is your business. The more challenging the economy, the more valuable the asset becomes. Decisions are magnified. Risk is amplified.
Asset management Your asset is your business. The more challenging the economy, the more valuable the asset becomes. Decisions are magnified. Risk is amplified. Data is about more than numbers. It tells
Accenture CAS: Solution Implementation Making change happen
Accenture CAS: Solution Implementation Making change happen Rooted in a strong culture of client service and success, our smart, committed and experienced professionals collaborate as global teams to create
Field Service in the Cloud: Solving the 5 Biggest Challenges of Field Service Delivery
Field Service in the Cloud: Solving the 5 Biggest Challenges of Field Service Delivery The ServiceMax Whitepaper Executive Summary The time has come for field service organizations to also reap the benefits
Planning an ERP Implementation Project @ Small and Medium Enterprises
Planning an ERP Implementation Project @ Small and Medium Enterprises 27 th Regional WIRC Conference 31 August 2012 Table of Contents What is an SME and ERP Why an ERP for the SME segment Assessing the
Integrating Project Management and Service Management
Integrating Project and Integrating Project and By Reg Lo with contributions from Michael Robinson. 1 Introduction Project has become a well recognized management discipline within IT. is also becoming
Relationship management is dead! Long live relationship management!
XRM: From Fragmentation to Integration Executive Summary Relationship management is dead! Long live relationship management! But it s not just about customers anymore. The value chain has grown so long
Enterprise Data Governance
DATA GOVERNANCE Enterprise Data Governance Strategies and Approaches for Implementing a Multi-Domain Data Governance Model Mark Allen Sr. Consultant, Enterprise Data Governance WellPoint, Inc. 1 Introduction:
How Technology Supports Project, Program and Portfolio Management
WHITE PAPER: HOW TECHNOLOGY SUPPORTS PROJECT, PROGRAM AND PORTFOLIO MANAGEMENT SERIES 4 OF 4 How Technology Supports Project, Program and Portfolio Management SEPTEMBER 2007 Enrico Boverino CA CLARITY
BAE Systems adopts eprocurement for enterprise efficiency
C A S E S T U D Y BAE Systems adopts eprocurement for enterprise efficiency Leveraging a hosted solution to reduce cost and improve service levels Company Profile BAE Systems is a premier global defense
2015 Strategic Business Plan Franklin County Data Center Ishreth Sameem, CIO
2015 Strategic Business Plan Franklin County Data Center Ishreth Sameem, CIO Mission The Franklin County Data Center partners with County agencies to deliver cost efficient business solutions and provide
15 Principles of Project Management Success
15 Principles of Project Management Success Project management knowledge, tools and processes are not enough to make your project succeed. You need to get away from your desk and get your hands dirty.
Development, Acquisition, Implementation, and Maintenance of Application Systems
Development, Acquisition, Implementation, and Maintenance of Application Systems Part of a series of notes to help Centers review their own Center internal management processes from the point of view of
Colorado Department of Health Care Policy and Financing
Colorado Department of Health Care Policy and Financing Solicitation #: HCPFRFPCW14BIDM Business Intelligence and Data Management Services (BIDM) Appendix B BIDM Project Phases Tables The guidelines for
Request for Proposal for Application Development and Maintenance Services for XML Store platforms
Request for Proposal for Application Development and Maintenance s for ML Store platforms Annex 4: Application Development & Maintenance Requirements Description TABLE OF CONTENTS Page 1 1.0 s Overview...
SAP ERP Upgrade Checklist Project Preparation
A SAP ERP Upgrade Checklist Project Preparation Upgrade Project Phase Project Preparation Definition From the project perspective the project preparation phase includes: Learning about the new functionality
Solution brief. HP solutions for IT service management. Integration, automation, and the power of self-service IT
Solution brief HP solutions for IT service management Integration, automation, and the power of self-service IT Make IT indispensable to the business. Turn IT staff into efficient, cost-cutting rock stars.
Project Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1)
Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Date: October 1, 2014 Version: 3.1 DOCUMENT REVISION HISTORY Version Date Changes Updated By 0.1 02/13/014 Initial
IT Services. We re the IT in OrganIsaTion. Large Organisations
IT Services. We re the IT in OrganIsaTion Large Organisations IT for Large Organisations. As the world of business technology has changed, so have we. From designing, building and optimising tailored
How Cisco IT Migrated High-Volume Linksys Contact Center to IP Network
How Cisco IT Migrated High-Volume Linksys Contact Center to IP Network Cisco Unified Contact Center solution receives and routes 40,000 calls per day while providing greater flexibility and availability.
How To Implement An Enterprise Resource Planning Program
ERP Implementation Program Key phases of ERP implementation: Analysis of the company existing or designing new business process descriptions Inventory of the company s existing formal workflows or designing
SEVEN WAYS TO AVOID ERP IMPLEMENTATION FAILURE SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND
SEVEN WAYS TO AVOID ERP IMPLEMENTATION FAILURE SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND CONTENTS INTRODUCTION................................ 3 UNDERSTAND YOUR CURRENT SITUATION............ 4 DRAW
Driving Excellence in Implementation and Beyond The Underlying Quality Principles
SAP Thought Leadership Paper SAP Active Quality Management Driving Excellence in Implementation and Beyond The Underlying Quality Principles 2014 SAP AG or an SAP affiliate company. All rights reserved.
Bringing Control to Global Supply Management Business Process Management (BPM) and Advanced Project Management Practices
Bringing Control to Global Supply Management Business Process Management (BPM) and Advanced Project Management Practices Jason Klemow, CTP, Partner The JK Group 301/948-2134; [email protected] Francine
When companies purchase an integrated learning
Feature 2. Project team members are required to perform their regular responsibilities in addition to committing their time to the implementation. Organizations can overcome these challenges if they find
ORACLE PROJECT MANAGEMENT
ORACLE PROJECT MANAGEMENT KEY FEATURES Oracle Project Management provides project managers the WORK MANAGEMENT Define the workplan and associated resources; publish and maintain versions View your schedule,
AN APPLICATION-CENTRIC APPROACH TO DATA CENTER MIGRATION
AN APPLICATION-CENTRIC APPROACH TO DATA CENTER MIGRATION Five key success factors IT organizations today are under constant business pressure to transform their infrastructure to reduce costs, increase
Release Management: Effective practices for IT delivery
Release Management: Effective practices for IT delivery Introduction Today s health plans face a unique combination of technology challenges due to their complex IT environments. These environments serve
Keys to a Successful Outsourcing Transition
Keys to a Successful Outsourcing Transition finance.arvato.com Getting it Right the First Time: Keys to a Successful Outsourcing Transition A large part of success in outsourcing depends on a seamless
OE PROJECT CHARTER TEMPLATE
PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,
Introduction. What is ITIL? Automation Centre. Tracker Suite and ITIL
1 Introduction The Information Technology Infrastructure Library (ITIL) aims to improve the management of IT services within the organization, for lowered costs, improved efficiency and productivity. But
How Cisco IT Automated Employee Travel and Event Management
How Cisco IT Automated Employee Travel and Event Management Cisco Unified Contact Center enables Cisco to control costs and provide better service for employee events and travel worldwide. Cisco IT Case
ENTERPRISE MANAGEMENT AND SUPPORT IN THE TELECOMMUNICATIONS INDUSTRY
ENTERPRISE MANAGEMENT AND SUPPORT IN THE TELECOMMUNICATIONS INDUSTRY The Telecommunications Industry Companies in the telecommunications industry face a number of challenges as market saturation, slow
Best Practices for Implementing Software Asset Management
Best Practices for Implementing Software Asset Management Table of Contents I. The Case for Software Asset Management (SAM)............................ 2 II. Laying the Groundwork for SAM............................................
Agile Master Data Management TM : Data Governance in Action. A whitepaper by First San Francisco Partners
Agile Master Data Management TM : Data Governance in Action A whitepaper by First San Francisco Partners First San Francisco Partners Whitepaper Executive Summary What do data management, master data management,
How Cisco IT Migrated Call Centers to IP Contact Center
How Cisco IT Migrated Call Centers to IP Contact Center Cisco Unified Contact Center migration reduces costs, improves operational efficiency, and provides better service for callers. Cisco IT Case Study
Equinix Increases IT and Employee Productivity with ServiceNow Cloud-Based IT Service Automation Solution
IDC ExpertROI SPOTLIGHT Equinix Increases IT and Employee Productivity with ServiceNow Cloud-Based IT Service Automation Solution Sponsored by: ServiceNow Matthew Marden April 2014 Randy Perry Overview
Best Practices in Release and Deployment Management
WHITEPAPER Best Practices in Release and Deployment Management Mark Levy Through 2016, a lack of effective release management will contribute up to 80% of production incidents in large organizations with
Achieving business excellence through quality in a BPO environment
Achieving business excellence through quality in a BPO environment Worldwide BPO Forecast for Horizontal Business Functions, 2004 2009, US$M Worldwide spending on horizontal business process outsourcing
CA HalvesThe Cost Of Testing IT Controls For Sarbanes-Oxley Compliance With Unified Processes.
TECHNOLOGY BRIEF: REDUCING COST AND COMPLEXITY WITH GLOBAL GOVERNANCE CONTROLS CA HalvesThe Cost Of Testing IT Controls For Sarbanes-Oxley Compliance With Unified Processes. Table of Contents Executive
AN APPLICATION-CENTRIC APPROACH TO DATA CENTER MIGRATION
AN APPLICATION-CENTRIC APPROACH TO DATA CENTER MIGRATION Five key success factors Whether the decision to relocate or consolidate a data center is driven by cost pressure or the need for greater IT efficiency,
The Future of Census Bureau Operations
The Future of Census Bureau Operations Version 1.0 April 25, 2013 The Future of Census Bureau Operations Page ii [This page intentionally left blank] The Future of Census Bureau Operations Page iii Document
IBM Tivoli Asset Management for IT
Cost-effectively manage the entire life cycle of your IT assets IBM Highlights Help control the costs of IT assets with a single product installation that tracks and manages hardware, software and related
Oracle Data Centre Rationalisation
Ian Gardner - Oracle Applications Architect 2012-06-13 Oracle Data Centre Rationalisation A Practical View [email protected] Tel. 07740 923060 2012 IBM Corporation Why perform Oracle Data Centre Rationalisations...
How Cisco Tracks RFID with Active RFID and Wireless LANs
How Tracks RFID with Active RFID and Wireless LANs Active RFID tags and WLANs ensure compliance with corporate finance and government regulations. IT Case Study / Wireless / RFID Solutions: Maintaining
NCOE whitepaper Master Data Deployment and Management in a Global ERP Implementation
NCOE whitepaper Master Data Deployment and Management in a Global ERP Implementation Market Offering: Package(s): Oracle Authors: Rick Olson, Luke Tay Date: January 13, 2012 Contents Executive summary
Practice makes perfect Simulation games to increase the return-on-investment of ITIL training
Practice makes perfect Simulation games to increase the return-on-investment of ITIL training By Paul Wilkinson, GamingWorks * In an effort to improve the performance of IT service delivery many IT organizations
Netstar Strategic Solutions Practice Development Methodology
Netstar Strategic Solutions Practice Development Methodology Netstar Corporation Abstract This document contains a high level description of the development methodology used by the Netstar Strategic Solutions
Whitepaper: 7 Steps to Developing a Cloud Security Plan
Whitepaper: 7 Steps to Developing a Cloud Security Plan Executive Summary: 7 Steps to Developing a Cloud Security Plan Designing and implementing an enterprise security plan can be a daunting task for
PROCUREMENT OUTSOURCING: The 10 Things Companies Really Want to Know
PROCUREMENT OUTSOURCING: The 10 Things Companies Really Want to Know By Jason Gilroy Vice President of Outsourcing ICG Commerce As featured in: Over the past year, ICG Commerce has seen an unprecedented
IBM Infrastructure Resource Management Services Offering Overview. IBM Global Services
IBM Infrastructure Resource Management Services Offering Overview The role of IT infrastructure within the enterprise has evolved as business functions have become virtually inseparable from the IT that
Kenandy TM Cloud ERP White Paper. Kenandy Cloud ERP Overview
White Paper Kenandy Cloud ERP Overview Kenandy TM Cloud ERP Key Benefits Easy to use Global Social Mobile Real-time visibility Fast deployment Users can tailor Add fields Change workflows Create reports
An Oracle White Paper March 2013. Project Management Office Starter Kit
An Oracle White Paper March 2013 Project Management Office Starter Kit Executive Overview... 1 Introduction... 1 Plan Phase... 2 Create Statement of Purpose and Goals... 2 Define Scope and Target Maturity...
14 TRUTHS: How To Prepare For, Select, Implement And Optimize Your ERP Solution
2015 ERP GUIDE 14 TRUTHS: How To Prepare For, Select, Implement And Optimize Your ERP Solution Some ERP implementations can be described as transformational, company-changing events. Others are big disappointments
HR - A STRATEGIC PARTNER Evolution in the adoption of Human Capital Management systems
www.wipro.com HR - A STRATEGIC PARTNER Evolution in the adoption of Human Capital Management systems FUTURE READY SYSTEM FOR AN INSPIRED WORKFORCE Anand Gupta, Director, Oracle Cloud Services, Wipro Table
AGILE SOFTWARE TESTING
AGILE SOFTWARE TESTING Business environments continue to rapidly evolve, leaving many IT organizations struggling to keep up. This need for speed has led to an increased interest in the Agile software
Qlik UKI Consulting Services Catalogue
Qlik UKI Consulting Services Catalogue The key to a successful Qlik project lies in the right people, the right skills, and the right activities in the right order www.qlik.co.uk Table of Contents Introduction
ERP. Key Initiative Overview
Jeff Woods Research Managing Vice President This overview provides a high-level description of the ERP Key Initiative. IT leaders can use this overview to better understand what they need to do to prepare
Jabil builds momentum for business analytics
Jabil builds momentum for business analytics Transforming financial analysis with help from IBM and AlignAlytics Overview Business challenge As a global electronics manufacturer and supply chain specialist,
How Cisco Transformed Its Supply Chain
Cisco on Cisco Case Study Supply Chain Transformation How Cisco Transformed Its Supply Chain Single global ERP instance, new business models, standardization, and automation throughout supply chain boost
Simplify Your Windows Server Migration
SOLUTION BRIEF: ENDPOINT MANAGEMENT........................................ Simplify Your Windows Server Migration Who should read this paper Windows Server 2003 customers looking to migrate to the latest
Cisco IT Technology Tutorial Overview of ITIL at Cisco
Cisco IT Technology Tutorial Overview of ITIL at Cisco Ian Reddy, IT Manager David Lietzell, IT Program Manager May 2009 Produced by the Cisco on Cisco team within Cisco IT 2007 Cisco Systems, Inc. All
Dell Connected Learning for Schools. Transforming Education for the Digital Age
Dell Connected Learning for Schools Transforming Education for the Digital Age This document was created to provide Dell s point of view for primary and secondary schools and contains the following sections:
QUICK FACTS. Replicating Canada-based Database Support at a New Facility in the U.S. TEKSYSTEMS GLOBAL SERVICES CUSTOMER SUCCESS STORIES
[ Energy Services, Managed Services Offering/ Network Infrastructure Services ] TEKSYSTEMS GLOBAL SERVICES CUSTOMER SUCCESS STORIES Client Profile Industry: Oil and natural gas Revenue: Approximately $5.2
Project Knowledge Areas
From Houston S: The Project Manager s Guide to Health Information Technology Implementation. Chicago: HIMSS; 2011; pp 27 39. This book is available on the HIMSS online bookstore at www. himss.org/store.
Business Service Management Links IT Services to Business Goals
WHITE PAPER: BUSINESS SERVICE MANAGEMENT Business Service Management Links IT Services to Business Goals JANUARY 2008 Sarah Meyer CA SOLUTIONS MARKETING Table of Contents Executive Summary SECTION 1 2
Project Implementation Process (PIP)
Vanderbilt University Medical Center Project Implementation Process (PIP).......... Project Implementation Process OVERVIEW...4 PROJECT PLANNING PHASE...5 PHASE PURPOSE... 5 TASK: TRANSITION FROM PEP TO
Documentation for data centre migrations
Documentation for data centre migrations Data centre migrations are part of the normal life cycle of a typical enterprise. As organisations expand, many reach a point where maintaining multiple, distributed
Critical Steps to Help Small and Mid-Sized Businesses Ensure CRM Success
Critical Steps to Help Small and Mid-Sized Businesses Ensure CRM Success Table of Contents Abstract............................................ 3 CRM Drivers and Benefits............................. 4
IT & Management Consulting Services
2008 Microsoft Corporation. All rights reserved. This document is for informational purposes only. MICROSOFT MAKES NO WARRANTIES, EXPRESS OR IMPLIED, IN THIS SUMMARY. Microsoft, Excel, Microsoft Dynamics,
Business Analyst Position Description
Analyst Position Description September 4, 2015 Analysis Position Description September 4, 2015 Page i Table of Contents General Characteristics... 1 Career Path... 2 Explanation of Proficiency Level Definitions...
White Paper Case Study: How Collaboration Platforms Support the ITIL Best Practices Standard
White Paper Case Study: How Collaboration Platforms Support the ITIL Best Practices Standard Abstract: This white paper outlines the ITIL industry best practices methodology and discusses the methods in
Productivity Gains for SMBs with OnCloud ERP PestBusters takes 1st mover advantage
2012 Productivity Gains for SMBs with OnCloud ERP PestBusters takes 1st mover advantage GreeneStep OnCloud ERP enables SMBs to take advantage of an agile business automation and processes integration system