1 Feature Story Raleigh s District Cooling Solution: Performance contracting finances system upgrades John S. Andrepont, President, The Cool Solutions Company; Kevin P. Gillespie, PE, Energy Engineer, Pepco Energy Services; and Richard B. Beversdorf, PE D istrict energy is once again at the heart of an economically attractive solution to complicated energy issues at the North Carolina State Capitol Complex in downtown Raleigh, N.C. This solution entailed a self-financing, energy service performance contract to improve energy efficiencies and energy costs while upgrading aging energy infrastructure within existing buildings and within an existing, limited district cooling system. A team of designers, suppliers, and contractors led by Pepco Energy Services recommended fairly typical energy conservation measures plus an inventive departure from the initially requested approach: The company chose to invest heavily in district cooling rather than merely replacing existing in-building chillers. As is increasingly common with performance contracting for federal and state entities, the entire project is self-financed by the energy cost savings relative to the state s base case energy utilization. The combination of four key elements district cooling, thermal energy storage (TES), a packaged chiller plant and pressureindependent flow control is creating maximum savings and value that would otherwise be unattainable if one or more of those elements were excluded from the project. The Challenge The North Carolina state government occupies numerous buildings clustered in the capital of Raleigh. A strong commitment to reducing energy consumption, renewal of aging infrastructure, budget cuts and rising energy costs caused the state to explore the use of performance contracting to modernize its energy infrastructure while avoiding the associated capital investment. A selected performance contractor, or ESCO (energy service company), would finance the project and utilize a portion of the savings in the state s operating energy budget to recover the project capital costs. In late 2004, the state issued a request for proposals from performance contrac- Most of the buildings in North Carolina s State Capitol Complex in Raleigh, including the State Capitol itself (center bottom), are connected to the district cooling system. The system s old central chiller plant is located within the quadrangle of buildings shown just above the State Capitol building grounds. The new chilled-water tank (not shown in this older photo) is located beyond the tallest building on the left side of the photo. Reprinted from Fourth Quarter 2007 District Energy magazine with permission of IDEA. Fourth Quarter
2 The Solution The successful solution involved an approach integrating existing assets that were modernized and improved as well as new equipment and infrastructure. These improvements involved four groups of energy conservation measures: lighting upgrades in various buildings, HVAC and control improvements within the buildings, water conservation initiatives, and a major expansion and modernization of the district cooling system. The latter included a new TES system, a new packaged chiller plant, upgrades to existing chillers and the existing TES system, system control modifications to ensure a high delta T throughout the chilled-water system, and expansion of the existing cooling loop to accommodate additional and future facilities. The project benefits are as follows: More than $2 million per year in energy savings 8 District Energy Courtesy Natgun Corporation. tors. The RFP specified that numerous and varied types of energy conservation measures could be included within the scope of the project. The RFP also requested that several concerns be addressed regarding specific inefficient and poorly operating cooling systems. These included (1) an aging and relatively small district cooling plant that serves a core of 10 of the state s oldest buildings; (2) an old, unused 740,000-gal chilledwater TES tank associated with the old cooling network; and (3) aging, inefficient chillers and degraded cooling towers in four large buildings remote from the existing district cooling network. (Their capacity was to be replaced, presumably within those buildings.) (Note: The state complex is also served by an existing steam district heating network that was not included in the RFP.) The state selected the proposal offered by Pepco Energy Services. The company then performed the detailed audit phase of the project throughout the first half of Project implementation began in November 2005, with completion of the energy conservation measures in late 2006 and The expanded district cooling system was commissioned and placed in service during spring 2007 and commissioned during the summer. Raleigh s upgraded district energy system includes a new 26,270 ton-hr thermal energy storage tank. Designed to blend architecturally with an adjacent parking structure, the tank was partially buried, which minimize its height and aesthetic impact. Approximately $18.9 million in new infrastructure Reductions in energy usage of more than 20,000,000 kwh/year Reductions in water consumption of more than 10,000,000 gal/year Improved building comfort More than $7 million in future capital cost avoidance Expanded cooling capacity and system redundancy The district energy solution was dependent on the integrated use of four important elements: district cooling, thermal energy storage, packaged chiller plant and improved chilled-water delta T. District Cooling Is Backbone The energy services contractor based its unique and successful proposal not on replacing the four large in-building chiller plants with new in-building plants, but rather on a major expansion of the existing district cooling network to include those four buildings as well as other new additions. The old central chiller plant, which had served 10 state buildings totaling 1.3 million sq ft of space, was modernized; the existing unused chilled-water TES tank was repaired and re-commissioned. However, the primary investment in new chiller capacity was focused on an all-new, larger-scale, highly energy-efficient packaged chiller plant located at a more centralized site within the expanded district cooling network. The expanded system now serves 20 buildings that total 3.5 million sq ft. No new chillers were purchased for any individual buildings. The new packaged chiller plant became the primary source of chilled-water generation. The old, rehabilitated chilledwater plant became a secondary source at a satellite location. Additionally, the most reliable and efficient of the remaining inbuilding chiller plants became available as distributed, local, tertiary sources of chilled-water generation, used only for peaking capacity or emergency backup capacity in extreme cooling conditions. The majority of the new piping used in the district cooling system is directburied, high-density polyethylene (HDPE) pipe. HDPE was chosen due to its ease of installation, longevity, and life-cycle-cost considerations. Insulated steel piping is used for all above-ground and in-building applications. TES Enhances Solution Critical to the successful economics of the project, in addition to rehabilitation of the old, relatively small TES tank, was installation of a new 2.7 million gallon TES tank, located at the site of the new packaged district cooling plant. This large, new stratified chilled-water TES tank provides two key economic benefits: It minimizes the use of chillers during high-cost, on-peak utility periods, greatly reducing demand costs and also benefiting from Reprinted from Fourth Quarter 2007 District Energy magazine with permission of IDEA.
3 Courtesy Natgun Corporation. time-of-day energy rates, and it reduces total capital cost relative to a conventional (non-tes) chiller plant installation. The new TES tank was partially buried. Though adding cost, this was done to minimize its height and aesthetic impact. The partially buried tank configuration supported the choice of a concrete tank, which uses a precast, prestressed design in accordance with American Water Works Association standard D110, Type III. The new TES tank and the adjacent new packaged district cooling plant comprise the Energy Conservation Center, the heart of the expanded district cooling system. The tank s façade was also designed to architecturally blend with the existing multilevel parking structure immediately behind the Energy Conservation Center. The new TES tank and the adjacent new packaged district cooling plant comprise the Energy Conservation Center, the heart of the expanded district cooling system. The existing underground TES tank had a nominal 740,000-gal volume (33 ft wide x 100 ft long x 30 ft deep). Installed in 1988, the concrete, stratified chilledwater TES tank was unused prior to this performance contract for a number of The Energy Conservation Center serving the North Carolina state government complex includes a new packaged chiller plant with a 2,900-ton cooling capacity. reasons, including a high rate of water leakage, poor stratification performance and difficulty controlling the flows of water to and from the tank and the water level within the tank. These issues were addressed as part of the performance contract. During the detailed audit phase of the project, scuba divers and underwater video identified the sources of the tank leakage (occurring at the sleeves around the piping penetrations of the concrete tank walls and in one of the distribution lines leaving the tank) and the cause of the poor stratification performance (attributable to broken PVC pipe flow diffusers in the original TES tank design). During project execution, the tank wall penetrations were repaired using leak-resistant sleeves, and new internal flow diffusers were designed and installed by the new TES tank supplier using primarily welded-steel piping. In addition, the TES tank pumping and valving interface with the balance of the district cooling network was redesigned to accomplish simple and reliable control of flow and level. This TES tank, though originally designed to provide approximately 5,300 ton-hr of capacity at a 12 degrees F delta T, had been providing no TES capacity due to its past operational problems. Now it can provide more than 7,000 ton-hr of capacity at a 16 F delta T. Prioritizing Investments for Energy Efficiency Existing Chilled-Water Plant The existing plant had three aged (and dissimilar) chillers piped in parallel; the two oldest chillers were specified for a 12 F delta T and the newest for a 10 F delta T. However, all three chillers were typically operating at only a 6-9 F delta T. The plant capacity was also constrained by the existing cooling towers and the electric power feed. Each of these factors contributed to limiting the operation to a maximum of two of the three chillers at any one time. The congested plant layout and equipment age and inefficiency dictated that only limited capital should be invested at this site, in lieu of a more justified investment in primary capacity at the new Energy Conservation Center. The cooling towers and electrical service were upgraded, and the three chillers were upgraded and re-rated for operation at supply and return temperatures of 39 F and 55 F, consistent with the expanded district cooling system design. New District Cooling Plant The use of a turnkey, design-built, packaged district cooling plant, rather than the conventional stick-built plant, provided multiple significant benefits to the project. They included a much smaller required plot plan for easier siting and less visual impact; a much shorter overall schedule and on-site installation schedule; high energy-efficiency compressors, with 39 F supply temperature and high delta T; low installed capital cost per ton; and single-point responsibility with guarantees of total plant tonnage and kw per ton. The installed capacities of the new and old chillers and new and old TES are summarized in table 1, along with the peak design day cooling loads. Optimizing High Chilled-Water Delta T Another crucial aspect of achieving the economically successful district cooling solution was the use of a relatively high temperature differential between the chilled-water supply and return temperatures. The small, pre-existing network suffered from operating at very low chilledwater delta T (typically 6-9 F). Increasing the delta T resulted in very significant benefits: smaller new pipes with lower capital cost and more capacity in existing piping; smaller new pumps with lower capital cost; more capacity in existing pumps and lower pump horsepower with associated lower operating costs; more capacity in the existing TES tank; and a smaller new TES tank with lower capital cost and less concern with issues of space allocation and aesthetic impact. The higher delta T was accomplished by both lowering the chilled-water supply temperature at the new and old plants and by assuring a high chilled-water return temperature at the buildings cooling loads. The latter result was accomplished by the installation of pressure-independent flow control valves at all major air-handling units throughout the connected buildings. Some buildings are now achieving a delta T of 18 F, even at below-design loads. Reprinted from Fourth Quarter 2007 District Energy magazine with permission of IDEA. Fourth Quarter
4 Table 1. Chiller and TES Capacity and Design Day Cooling Loads. Primary Chiller Capacity (New Packaged Chiller Plant) Secondary Chiller Capacity (Rehabilitated Chiller Plant) Peaking & Reserve Chiller Capacity Administration Building Albemarle Building New Revenue Building Highway Building TES Capacities New Chilled-Water TES Tank Old Chilled-Water TES Tank Total Available Capacity Chillers Only Chillers Plus TES Discharge Design Day Peak Load Design Day 24-hr Average Load The existing in-building chillers, which can provide peaking and reserve cooling capacity, are not designed for the low (39 F) chilled-water supply temperature. However, they are used on a limited basis, and are not planned to feed the district cooling network. In those instances when in-building chillers are dispatched, they are used solely to serve load within their own individual buildings, effectively shedding that load from the district cooling system. Results and Benefits Management of Energy and Energy Costs Each state building is now independently metered and billed in accordance with that building s applicable standard electric utility tariff. Because buildings have been connected to the district cooling network, the Energy Conservation Center can be used to adapt to and control the load profiles of the individual buildings. This is made possible primarily though the use of the TES. These strategies allow the state to select the most advantageous electric rate tariff for each building, further increasing the energy cost savings. Through the avoidance of inbuilding chiller operation in many of the 2,900 tons (operates off peak and, often, as needed, on peak) Approximately 1,800 tons (operates off peak and, at times, as needed, on peak) (operates only rarely and always off peak) 485 tons 450 tons 750 tons 375 tons (discharges on peak, recharges off peak) 3,700 tons of discharge (26,270 ton-hr total) 800 tons of discharge (7,100 ton-hr total) 6,760 tons 11,260 tons With Initial Buildings Only 4,872 tons 5,881 tons 3,500 tons 4,162 tons Also With Legislature and Legislative Office Building large buildings, the state can benefit from the use of the more economical Small Time-of-Use tariff. The old chiller plant and the new Energy Conservation Center, each with a nearby TES tank, are billed on the attractive TES tariff. Excess storage and chiller capacity also allow both chiller plants to avoid operation during the day-time peak periods of high demand and energy charges during the cooler months. Additionally, water flow within the network is managed through the use of variable speed pumps to further enhance system efficiency and control. A new custom-applied Siemens Energy Management Control system monitors, controls and coordinates the two chiller plants, the TES systems, the individual building chilled-water needs and the district cooling flow. Also, each facility served by the system is metered to determine the actual flow rates and temperature differentials. Expandability for Future Load Growth Several steps were taken in designing the project to accommodate future district cooling system expansion. First, the piping headers were sized large enough to accommodate the incorporation of two additional large existing state buildings and three large future buildings. Second, the new TES tank was oversized beyond that necessary for leveling present peak day loads not an idle investment, as it can be used now to shift larger cooling loads and achieve larger electric demand management. Third, the new packaged chiller plant was designed to allow for easy future capacity expansion. Reliability and Redundancy The project now provides a minimum of N+1 redundancy in critical mechanical items such as chillers and pumps. The use of an integrated district cooling system permits this to be economically achieved, whereas it would not have been economically feasible if serving each building only with its own in-building chiller plant. This added redundancy and reliability is a benefit that the state did not previously enjoy, and would not now be enjoying without the use of district cooling. The upgrade of Raleigh s state government energy infrastructure, under the direction of Pepco Energy Services, achieved an innovative and extremely beneficial result. The magnitude of the project benefits, and even the economic viability of having a project at all, was dependent on the integration of the key technical elements: district cooling, TES, packaged chiller plants, pressure-independent flow control valves and the tactical use of various existing assets. The project is a showcase of what district energy can deliver, especially when it is leveraged with complementary technologies that are not as readily deployed on the scale of individual building systems. The result for the performance contractor is an attractive rate-of-return applied to a large investment, thus creating a large net present value. The result for the state is a much better-than-anticipated solution to their cooling issues, with much more new infrastructure, much 10 District Energy Reprinted from Fourth Quarter 2007 District Energy magazine with permission of IDEA.
5 larger levels of energy conservation and energy cost reduction, the realization of reliability and redundancy that could not have been economically achieved with individual in-building chiller systems, and the ease of expandability of all those benefits to even more buildings in the future. The project is a showcase of what district energy can deliver, especially when it is leveraged with complementary technologies that are not as readily deployed on the scale of individual building systems. Authors Note: The authors recognize the foresight of the State of North Carolina in supporting this important energy conservation and cost-reducing district cooling development. Specifically they wish to recognize the North Carolina Department of Administration, including Speros Fleggas, Greg Driver, Michael Hughes, Hany Botros and Cindy Browning of the North Carolina State Construction Office, as well as Larry Shirley, director of the North Carolina State Energy Office. In addition, the authors acknowledge the key members of the district cooling project team: Pepco Energy Services, performance contractor/team leader; The Cool Solutions Company, district cooling and TES consultant; Affiliated Engineers Inc., engineering consultant; TAS Ltd., packaged district cooling plant; Natgun Corporation, TES tank; Cool Systems Inc./Flow Control Industries, pressureindependent flow control valves; Siemens Building Technologies, controls; Progress Energy, electric utility. John S. Andrepont is the founder and president of The Cool Solutions Company, which provides professional consulting services in the areas of thermal energy storage, district cooling and turbine inlet cooling. Andrepont served on IDEA s board of directors for five years and has cochaired three IDEA cooling conferences. He has also held leadership positions in the American Society of Heating, Refrigerating and Air-Conditioning Engineers and the Turbine Inlet Cooling Association. A graduate of Rensselaer Polytechnic Institute with bachelor and master degrees in mechanical engineering, Andrepont is the named inventor on more than one dozen U.S. patents. He can be reached at [email protected]. Kevin P. Gillespie, PE, is an energy engineer for Pepco Energy Services, an energy services company that develops, installs and finances projects designed to improve the energy efficiency and maintenance costs for facilities of all types. Gillespie provided design guidance throughout the project implementation stage as well as managed final commissioning of all interrelated mechanical systems. A graduate of North Carolina State University with a bachelor s degree in mechanical engineering, he is a registered professional engineer in North and South Carolina. He can be contacted at [email protected]. Richard B. Beversdorf, PE, also contributed to this article. Sustainable Campus Energy We Get It! University and College campus energy dynamics are rapidly shifting. It has become imperative for campuses to provide sustainable energy solutions that are reliable and flexible for future technologies, but can also efficiently meet today s needs. AEI is a national expert for planning, analyzing, designing and implementing: Whole Campus Energy Systems Master Planning Utilities Master Planning Carbon Footprint Analysis Emissions Control Alternative & Renewable Fuel Analysis Chilled Water Underground Utility Distribution Thermal Storage CHP Steam/Steam Condensate Commissioning Hydraulic Modeling Building Management/ Control Systems Compressed Gases Contact Jerry Schuett, P.E., Principal, at to discuss your campus energy needs. Chapel Hill, NC Champaign, IL Chicago, IL Gainesville, FL Houston, TX Madison, WI Metro DC Phoenix, AZ Seattle, WA Tampa, FL Walnut Creek, CA Reprinted from Fourth Quarter 2007 District Energy magazine with permission of IDEA. Fourth Quarter
One of the many issues facing cities, towns and campuses throughout. Making Connections in Miami: Cover Story
Cover Story Making Connections in Miami: County improves plants, integrates cooling loops One of the many issues facing cities, towns and campuses throughout North America is the challenge of replacing
TES for Medical Center
First Place: Industrial Facilities or Processes, New This article was published in ASHRAE Journal, November 2012. Copyright 2012 ASHRAE. Reprinted here by permission from ASHRAE at www.tecothermalenergy.com.
Power and Thermal Services. Power and Thermal Services
Power and Thermal Services Power and Thermal Services Landfill Gas to Energy Projects Project Name/ Location Bethlehem Landfill LFG to Energy Facility, Bethlehem, PA Eastern Landfill LFG to Energy Facility,
CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0.
Innovation Park Charlotte. NC 28262 DRAFT V0.1 Page 2 CyberFortress Data Center at Innovation Park BECO South purchased Innovation Park in March 2010 and immediately launched a dramatic top-to-bottom $30M
OPTIMIZING CONDENSER WATER FLOW RATES. W. A. Liegois, P.E. Stanley Consultants, Inc. Muscatine, Iowa
OPTIMIZING CONDENSER WATER FLOW RATES W. A. Liegois, P.E. Stanley Consultants, Inc. Muscatine, Iowa T.A. Brown, P.E. Thermal Energy Corporation Houston, Texas ABSTRACT Most chillers are designed for a
Case Studies of District Cooling Operating and Capital Cost Savings Using Chilled Water and Low Temperature Fluid TES
Case Studies of District Cooling Operating and Capital Cost Savings Using Chilled Water and Low Temperature Fluid TES John S. Andrepont, President The Cool Solutions Company George Berbari, CEO DC PRO
Historic Georgia Tech Archibald D. Holland Central Heating and Cooling Plant
Historic Georgia Tech Archibald D. Holland Central Heating and Cooling Plant Georgia Tech s Facilities Management, Utilities Maintenance team has recently completed the beautification of the Holland Plant.
Digital Realty Data Center Solutions Digital Chicago Datacampus Franklin Park, Illinois Owner: Digital Realty Trust Engineer of Record: ESD Architect
Digital Realty Data Center Solutions Digital Chicago Datacampus Franklin Park, Illinois Owner: Digital Realty Trust Engineer of Record: ESD Architect of Record: SPARCH Project Overview The project is
Thermal Energy Storage Strategies for Commercial HVAC Systems
APPLICATION NOTE An In-Depth Examination of an Energy Efficiency Technology Thermal Energy Storage Strategies for Commercial HVAC Systems Summary...1 How This Technology Saves Energy...2 Types of Demand
HVAC: Cool Thermal Storage
HVAC: Cool Thermal Storage Thermal storage systems offer building owners the potential for substantial operating cost savings by using offpeak electricity to produce chilled water or ice for use in cooling
Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings
Advanced Energy Design Guide LEED Strategies for Schools and High Performance Buildings Today s Presenters Stephen Koontz, LEED AP Energy Services Leader Tampa Bay Trane Allen Irvine General Sales Manager
THIRD QUARTER 2011 TECO
District Energy www.districtenergy.org THIRD QUARTER 2011 TECO Completes Major System Expansion Responding to Water Scarcity U.S. Biomass System Trends Maximizing Efficiency With Filtration Introducing
Second Place: Industrial Facilities or Processes, New
Second Place: Industrial Facilities or Processes, New Photo: Paul Howell Texas Medical Center in Houston is the largest medical center in North America. It has a chilled water system of 160,000 tons. Big
Optimization of Water - Cooled Chiller Cooling Tower Combinations
Optimization of Water - Cooled Chiller Cooling Tower Combinations by: James W. Furlong & Frank T. Morrison Baltimore Aircoil Company The warm water leaving the chilled water coils is pumped to the evaporator
UTILITIES AND ENERGY MANAGEMENT
UTILITIES AND ENERGY MANAGEMENT University of Texas at Austin increases investment in co-generation to achieve greater utility reliability and economy. ENVIRONMENTAL BENEFITS AND ENERGY SAVINGS Power plant
University of Maryland College Park District Energy System. IDEA Campus Energy Conference February 9, 2012
University of Maryland College Park District Energy System IDEA Campus Energy Conference February 9, 2012 UMCP District Energy System The University of Maryland district energy system consists of a well
Ener.co & Viridian Energy & Env. Using Data Loggers to Improve Chilled Water Plant Efficiency. Randy Mead, C.E.M, CMVP
Ener.co & Viridian Energy & Env. Using Data Loggers to Improve Chilled Water Plant Efficiency Randy Mead, C.E.M, CMVP Introduction Chilled water plant efficiency refers to the total electrical energy it
SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP
research journal 2013 / VOL 05.01 www.perkinswill.com SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP ARCHITECTURE AND ENGINEERING OF SUSTAINABLE BUILDINGS Current Trends in Low-Energy HVAC Design
ABSTRACT DCMCCT PROJECT OVERVIEW
Title: Case Study of the Austin Energy Dell Regional Children s Medical Center of Central Texas Packaged Hybrid CHP Energy Plant in Austin, Texas Authors: Mr. Ed Mardiat, Burns & McDonnell Mr. Jim Teigen,
Dallas/Fort Worth International Airport District Energy Plant Upgrades Project Making More with Less Sustainable Communities Conference Dallas, TX
Dallas/Fort Worth International Airport District Energy Plant Upgrades Project Making More with Less Sustainable Communities Conference Dallas, TX March 10, 2009 Agenda DFW Capital Development Program
Creating Efficient HVAC Systems
Creating Efficient HVAC Systems Heating and Cooling Fundamentals for Commercial Buildings Heating, ventilating, and air conditioning (HVAC) systems account for nearly half of the energy used in a typical
District Cooling as an Energy and Economically Efficient Urban Utility
1 District Cooling as an Energy and Economically Efficient Urban Utility Its Implementation at Marina Bay Business District in Singapore Tey Peng Kee, Singapore District Cooling Pte Ltd Abstract-- In a
Denver International Airport Total Facility Optimization. Josh Foerschler Aurom Mahobian
Denver International Airport Total Facility Optimization Josh Foerschler Aurom Mahobian AGENDA DIA Intro BMcD-DIA History Optimization Projects Results Conclusion Denver International Airport Opened February
NEW JERSEY CENTER OF EXCELLENCE
Overview NEW JERSEY Page 1 The Plant (CUP) provides electricity via a cogeneration system, chilled water for environmental cooling, steam for heating, and compressed air primarily for HVAC control Serves
Columbia University Master Planning & Optimization
Columbia University Master Planning & Optimization February 20, 2014 Mr. Frank Martino Vice President, Operations 1 Agenda Columbia University Campus District Energy Overview Evolution of Columbia s District
POLK STATE COLLEGE CHILLER PLANT EVALUATION WINTER HAVEN, FLORIDA APRIL 2, 2014. C arastro & A ssociates, C&A# 5747
POLK STATE COLLEGE WINTER HAVEN, FLORIDA CHILLER PLANT EVALUATION APRIL 2, 2014 C&A# 5747 C arastro & A ssociates, c o n s u l t i n g e n g i n e e r s inc. 2609 W. De Leon Street, Tampa, Florida 33609
Typical Cooling Load Profile
Ice Storage Systems and Impact on Electric Demand Georges Hoeterickx Specialists in Heat Transfer Products and Services 1 2 Cooling Load Typical Cooling Load Profile 0 2 4 6 8 10 12 14 16 18 20 22 Time
Assessment of Existing Data Centers for Critical Facilities Round Table Group
Assessment of Existing Data Centers for Critical Facilities Round Table Group Chuck Shalley, P.E. Consulting Electrical Engineers BACKGROUND INFORMATION ASSIGNMENT Data Center Criteria Type Raised Floor
PAYGO for Data Center -- Modular Infrastructure
PAYGO for Data Center -- Modular Infrastructure Introduction The infrastructure costs for Data Centers are increasing at a significant pace. Construction costs and their environmental impact are also soaring.
ULTRA-EFFICIENT HVAC DESIGN AND CONTROL
CASE STUDY ULTRA-EFFICIENT HVAC DESIGN AND CONTROL MAJOR HEATING, VENTILATING AND AIR- CONDITIONING REPLACEMENT AT THE COUNTY OF SAN DIEGO CRIME LAB December 30, 2005 8520 Tech Way, Suite 110 San Diego,
Florida Power & Light Company. Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards. Effective: November 9, 2015
Florida Power & Light Company Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards Effective: November 9, 2015 Table of Contents Eligibility Requirements - Chiller... 2 Rebate Amount
CURBING THE COST OF DATA CENTER COOLING. Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers
CURBING THE COST OF DATA CENTER COOLING Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers OVERVIEW Compare Cooling Strategies in Free- Standing and In-Building
DEVELOPMENT OF A CAMPUS WIDE DISTRICT CHILLED WATER SYSTEM SAMFORD UNIVERSITY
DEVELOPMENT OF A CAMPUS WIDE DISTRICT CHILLED WATER SYSTEM SAMFORD UNIVERSITY Mr. Rick Stephens, Director of Campus Planning Samford University, Birmingham, Alabama Mr. David W. Wade, P. E., President
ENERGY AUDIT REPORT MINIMUM REQUIREMENTS
ENERGY AUDIT REPORT MINIMUM REQUIREMENTS Energy Audit Reports must contain the following: 1) Eligibility Criteria: a) Evidence demonstrating that the Eligibility Criteria were met. 2) Participant Information:
HVAC: Cool Thermal Storage
PDHonline Course M145 (4 PDH) HVAC: Cool Thermal Storage Instructor: A. Bhatia, B.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org
Data Realty Colocation Data Center Ignition Park, South Bend, IN. Owner: Data Realty Engineer: ESD Architect: BSA LifeStructures
Data Realty Colocation Data Center Ignition Park, South Bend, IN Owner: Data Realty Engineer: ESD Architect: BSA LifeStructures Project Overview Data Realty is a data center service provider for middle
THERMAL STORAGE WITH ICE HARVESTING SYSTEMS
THERMAL WITH ICE HARVESTING SYSTEMS DAVID E. KNEBEL, P.E. Vice-President Turbo Refrigerating Company Denton, Texas ABSTRACT Application of Harvesting Ice Storage Syst ems. Thermal storage systems are becoming
CHILLER PLANT CONTROL MULTIPLE CHILLER CONTROLS
CHILLER PLANT CONTROL MULTIPLE CHILLER CONTROLS By: Michael J. Bitondo, Mark J. Tozzi Carrier Corporation Syracuse, New York August 1999 INTRODUCTION In December of 1998, the American Refrigeration Institute
Selection Tips For Air-Conditioning Cooling Systems
PDHonline Course M117 (2 PDH) Selection Tips For -Conditioning Cooling Systems Instructor: A. Bhatia, B.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088
Air Conditioning. The opportunity for energy efficiency. Low cost actions to reduce energy usage now
Fact Sheet #6 Air Conditioning In this fact sheet you will discover: The opportunity for energy efficiency How air conditioning works Low cost actions to reduce energy usage now Investments to reduce costs
HEAT RECOVERY FROM CHILLED WATER SYSTEMS. Applications for Heat Reclaim Chillers
HEAT RECOVERY FROM CHILLED WATER SYSTEMS Applications for Heat Reclaim Chillers April 2008 TABLE OF CONTENTS INTRODUCTION... 3 WASTE HEAT SOURCES... 3,4 Capturing Sufficient Heat for Useful Purposes...
Texas State University Utility Analysis. Sheri Lara, CEM, CEFP Texas State University Morgan Stinson, PE, LEED AP - EEA Todd Schmitt, PE, LEED AP EEA
Texas State University Utility Analysis Sheri Lara, CEM, CEFP Texas State University Morgan Stinson, PE, LEED AP - EEA Todd Schmitt, PE, LEED AP EEA Texas State University - San Marcos The rising STAR
Water cooled chiller plant (cp/vs)
Data Center Water cooled chiller plant (cp/vs) Design Envelope File No: 9.573 Date: december 16, 2014 Supersedes: 9.573 Date: november 14, 2014 design envelope s performance improvements are among the
SEATTLE STEAM COMPANY FREQUENTLY ASKED QUESTIONS
SEATTLE STEAM COMPANY FREQUENTLY ASKED QUESTIONS What products/services does Seattle Steam provide? The company provides thermal energy (heat) produced at two central heating plants in downtown Seattle.
Self-benchmarking Guide for Data Center Infrastructure: Metrics, Benchmarks, Actions 6-28-10. Sponsored by:
Self-benchmarking Guide for Data Center Infrastructure: Metrics, Benchmarks, Actions 6-28-10 Sponsored by: Disclaimer This document was prepared as an account of work sponsored by the United States Government.
Stationary Energy Storage Solutions 3. Stationary Energy Storage Solutions
Stationary Energy Storage Solutions 3 Stationary Energy Storage Solutions 2 Stationary Energy Storage Solutions Stationary Storage: Key element of the future energy system Worldwide growing energy demand,
The Piping System Model a New Life Cycle Document. Elements of the Piping System Model
Piping System Model as a Life Cycle Document White Paper Introduction When designing piping systems, a variety of documents are created providing the details necessary to design, purchase, build, and test
Building Performance With District Cooling
Reprinting this proof for distribution or posting on web sites is not permitted. Authors may request permission to reprint or post on their web site once the fi nal version has been published. A reprint
HEATING, VENTILATION & AIR CONDITIONING
HEATING, VENTILATION & AIR CONDITIONING as part of the Energy Efficiency Information Grants Program Heating and cooling can account for approximately 23 % of energy use in pubs and hotels 1. Reducing heating
Dallas, Texas, is the site of the
FEATURE Dallas s Mega Health Care Project: New hospital served by state-of-the-art central plant Jeff Easton, PE, CEM, LEED AP BD+C, Project Manager, OnSite Energy & Power Group, Burns & McDonnell; and
By Steven C. Severini, P.E., Member ASHRAE
The following article was published in ASHRAE Journal, July 2004. Copyright 2004 American Society of Heating, Refrigerating and Air- Conditioning Engineers, Inc. It is presented for educational purposes
Data Center Rack Level Cooling Utilizing Water-Cooled, Passive Rear Door Heat Exchangers (RDHx) as a Cost Effective Alternative to CRAH Air Cooling
Data Center Rack Level Cooling Utilizing Water-Cooled, Passive Rear Door Heat Exchangers (RDHx) as a Cost Effective Alternative to CRAH Air Cooling Joshua Grimshaw Director of Engineering, Nova Corporation
HVAC Systems: Overview
HVAC Systems: Overview Michael J. Brandemuehl, Ph.D, P.E. University of Colorado Boulder, CO, USA Overview System Description Secondary HVAC Systems Air distribution Room diffusers and air terminals Duct
THE EUROPEAN GREEN BUILDING PROGRAMME. Technical Module on Combined Heat and Power
THE EUROPEAN GREEN BUILDING PROGRAMME Technical Module on Combined Heat and Power Contents Foreword...1 1. Introduction...2 2. Inventory of the CHP system...3 3. Assessment of technical energy saving measures...5
New business segments for the energy saving industry Energy efficiency and decentralised energy systems in the building & housing sector
New business segments for the energy saving industry Energy efficiency and decentralised energy systems in the building & housing sector Workshop on ESCOs Energy Service Companies March 28-29, 2012, Ramat
Pharmaceutical central utility plants
Reprinted from PHARMACEUTICAL ENGINEERING The Official Magazine of ISPE May/June 2011, Vol. 31 No. 3 www.ispe.org Copyright ISPE 2011 This article presents annual energy savings of more than $600,000 per
apv heat exchanger APV ParaFlow Plate Heat Exchangers
apv heat exchanger APV ParaFlow Plate Heat Exchangers For HVAC Applications SPX offers an extensive portfolio of plate heat exchanges covering many industrial applications. Regularly SPX heat exchangers
CONCEPTUALIZATION OF UTILIZING WATER SOURCE HEAT PUMPS WITH COOL STORAGE ROOFS
CONCEPTUALIZATION OF UTILIZING WATER SOURCE HEAT PUMPS WITH COOL STORAGE ROOFS by Dr. Bing Chen and Prof. John Bonsell Passive Solar Research Group University of Nebraska-Lincoln Omaha campus and Richard
In the compression-refrigeration loop (air conditioning), which is likely to be warmer? 1. Condenser coil 2. Evaporator coil
In the compression-refrigeration loop (air conditioning), which is likely to be warmer? 1. Condenser coil 2. Evaporator coil Answer: (1) Condenser coil See the video. A.R.E. Building Systems Study Guide
Gas Absorption Heat Pumps. Future proofing your heating and hot water
Gas Absorption Heat Pumps Future proofing your heating and hot water Gas Absorption Heat Pumps 1 Contents Gas Absorption Heat Pumps (GAHPs) The heating solution What is a Gas Absorption Heat Pump? How
This presentation is posted for public use. ACEEE does not endorse any product or service.
This presentation is posted for public use. ACEEE does not endorse any product or service. ACEEE accepts no responsibility for any facts or claims this presentation may contain. SOLAR Solar Water Heating
Modular Chiller Plants for data centers. Downtime isn t acceptable
Modular Chiller Plants for data centers Downtime isn t acceptable Reducing risk with Quick Start A direct solution to your most important challenge uptime. At Johnson Controls we protect our customers
BCA-IDA Green Mark for Existing Data Centres Version EDC/1.0
BCA-IDA Green Mark for Existing Data Centres Version EDC/1.0 To achieve GREEN MARK Award Pre-requisite Requirement All relevant pre-requisite requirements for the specific Green Mark Rating are to be complied
Challenges of District Cooling System (DCS) Implementation in Hong Kong
Challenges of District Cooling System (DCS) Implementation in Hong Kong Authors: Lo, Alvin 1 ; Lau, Barry 2 ; Cheng, Vincent 3 ; Cheung, Patrick 4 1 Arup, Hong Kong, China 2 Arup, Hong Kong, China 3 Arup,
Thermal Coupling Of Cooling and Heating Systems
This article was published in ASHRAE Journal, February 2011. Copyright 2011 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. Posted at www.ashrae.org. This article may not
CHP - The Business Case
CHP - The Business Case An Introduction to Combined Heat and Power CHP 100 1 Acknowledgements 2 Overview! When Does CHP Make Sense! Where is CHP Practical?! Problems in CHP Economic Analysis 3 When Does
Compressed Air Systems
Efficiency Vermont Guide to Savings Helping Vermont businesses save energy and money Compressed Air Systems 888-921-5990 www.efficiencyvermont.com 1 Save money and optimize system performance Air compressors
Printing and Publishing Energy Savings Guide
Printing and Publishing Energy Savings Guide Oregon printing and publishing plants face challenges of rising operating costs, environmental and other regulations, outdated equipment and customer demand
Chapter 3.4: HVAC & Refrigeration System
Chapter 3.4: HVAC & Refrigeration System Part I: Objective type questions and answers 1. One ton of refrigeration (TR) is equal to. a) Kcal/h b) 3.51 kw c) 120oo BTU/h d) all 2. The driving force for refrigeration
See any red flags? Let s take a look at the problems that occurred on the job and how to avoid making the same mistakes.
providing insights for today s hvac system designer Engineers Newsletter volume 43 2 Chilled-Water Systems Design Issues Learning from past mistakes As with anything in life, you can learn HVAC design
OPERATOR - FACILITY ADDRESS - DATE
. Facility Criteria (RFP).0 Location Characteristics Criteria Requirements 1 Ownership and Management: Please identify the owner(s) and managers of the property and indicate if there is on-site management.
GEOTHERMAL HEATING AND COOLING INTRODUCTION
GEOTHERMAL HEATING AND COOLING INTRODUCTION Geothermal Heating and Cooling Systems provide space conditioning -- heating, cooling, and humidity control. They may also provide water heating -- either to
SOLEL SUNCOOLER SOLAR-POWERED AIR-CONDITIONING / HEATING SYSTEM
SOLEL SUNCOOLER SOLAR-POWERED AIR-CONDITIONING / HEATING SYSTEM organization / project coordinator (address, telephone, email) Solel Solar Systems Ltd./ Mr. Avi Brenmiller 3, Hac'shara St, Industrial Zone
Maximize energy savings Increase life of cooling equipment More reliable for extreme cold weather conditions There are disadvantages
Objectives Increase awareness of the types of economizers currently used for data centers Provide designers/owners with an overview of the benefits and challenges associated with each type Outline some
Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia
Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia Prepared for the U.S. Department of Energy s Federal Energy Management Program
A heat pump system with a latent heat storage utilizing seawater installed in an aquarium
Energy and Buildings xxx (2005) xxx xxx www.elsevier.com/locate/enbuild A heat pump system with a latent heat storage utilizing seawater installed in an aquarium Satoru Okamoto * Department of Mathematics
Energy Efficient Data Centre at Imperial College. M. Okan Kibaroglu IT Production Services Manager Imperial College London.
Energy Efficient Data Centre at Imperial College M. Okan Kibaroglu IT Production Services Manager Imperial College London 3 March 2009 Contents Recognising the Wider Issue Role of IT / Actions at Imperial
The Different Types of Air Conditioning Equipment for IT Environments
The Different Types of Air Conditioning Equipment for IT Environments By Tony Evans White Paper #59 Executive Summary Cooling equipment for an IT environment can be implemented in 10 basic configurations.
Renewable Solid Fuel Boiler Project
22nd Annual IDEA Campus Energy Conference Northern Michigan University Renewable Solid Fuel Boiler Project Presented By: Robert Ryan, P.E. Northern Michigan University Randy Russell, P.E. HDR Cummins &
District Cooling Plant : Refrigeration Plant Simulation
1 District Cooling Plant : Refrigeration Plant Simulation Dr. Chirdpun Vitooraporn Department of Mechanical Engineering Chulalongkorn University Phayathai Rd., Patumwan, Bangkok, 13. THAILAND E-mail: [email protected]
Overview of Green Energy Strategies and Techniques for Modern Data Centers
Overview of Green Energy Strategies and Techniques for Modern Data Centers Introduction Data centers ensure the operation of critical business IT equipment including servers, networking and storage devices.
How To Use A Water Source Heat Pump
Geothermal Energy Using Water-Source Heat Pumps By VIRSTAR Corporation Geothermal Expertise Since 1978 All information contained herein is the exclusive property of VIRSTAR Corporation, all rights reserved.
Geothermal Ice Arenas
Geothermal Ice Arenas For more information, call: Ltd. 41 St. Paul Blvd. West St. Paul, MB R2P 2W5 Ph: (204) 255-5959 Fax: (204) 255-7365 Email: [email protected] Website: www.icekubeheat.com ICE Ice KUBE
Q1 2011 Utility Rebate Report. Houston, TX
Q1 2011 Utility Rebate Report A service of the Sustainable Corporate Real Estate Roundtable Houston, TX April 7, 2011 (Captures regulations through March 31, 2011) This Report is one of a series of reports
HEAT PUMPS A KEY COMPONENT IN LOW CARBON FUTURE
HEAT PUMPS A KEY COMPONENT IN LOW CARBON FUTURE Satish Joshi Managing Director CONTENTS 1. INTRODUCTION, APPLICATIONS 2. TECHNOLOGY, PROJECTS DONE, COST COMPARISION 3. HEAT PUMPS IN THE RENEWABLES DIRECTIVE,
Data Center. Ultra-Efficient chilled water system optimization. White paper. File No: 9.236 Date: december 03, 2015 Supersedes: new Date: new
Data Center Ultra-Efficient chilled water system optimization White paper File No: 9.236 Date: december 03, 2015 Supersedes: new Date: new Data Center - Ultra-Efficient white paper 3 abstract The primary
Overview of Heat Recovery Boiler Systems and Operating Costs Factors Effecting Blowdown Blowdown Heat Recovery The Energy Tank
Overview of Heat Recovery Boiler Systems and Operating Costs Factors Effecting Blowdown Blowdown Heat Recovery The Energy Tank Unbiased, Third-Party, Water & Energy Management Consulting Firm: - Not affiliated
Princeton University Microgrid
Princeton University Microgrid IDEA evolvingenergy Conference Toronto, Canada 28th 30th October 2014 Edward Ted Borer, PE [email protected] Overview Campus Energy Demands Energy Plant Equipment Combined