Project Governance. New Corporations Unit (NewCo) PWC Structural Separation Program

Size: px
Start display at page:

Download "Project Governance. New Corporations Unit (NewCo) PWC Structural Separation Program"

Transcription

1 New Corporations Unit (NewCo) Department of the Chief Minister Level 14, NT House, 22 Mitchell Street, Darwin PWC Structural Separation Program Project Governance January 2014

2 Table of Contents 1. Introduction Governance Principles Governance Structure Governance Roles and Responsibilities Decision Authority Forums and Meetings Project Management Tools and Templates Budgets

3 1. Introduction 1.1. PWC Structural Separation Program The Northern Territory Government has decided to divest the Power and Water Corporation (PWC) of the power generation and power retail functions, and to separately place these functions into two new Government Owned Corporations (GOCs), commencing 1 July The key objectives of the PWC Structural Separation Program are to significantly improve the financial transparency of PWC s various lines of business, to empower more focussed and specialised Boards and management, and to remove certain deterrents to competition. The Program has been divided into three main phases: Phase 1 Design Phase (December 2013 to January 2014) o Design of the Governance framework o Design of the Day 1 and Day X Operating Models o Planning for the separation of PWC into three GOCs, and the achievement of the Day 1 Operating Model Phase 2 Implementation Phase (February to June 2014) o Execution of activities to achieve the Day 1 Operating Model, and the legal and financial separation of the three GOCs o Planning for the activities required to achieve the Day X Operating Model Phase 3 Transition Phase (July 2014 to a date to be determined) o Management of transition service agreements (TSAs) o Execution of activities to achieve the Day X Operating Model, including transition off TSAs Purpose of this Document Governance, in the context of any major program of change, is defined as the framework of rules, relationships, systems and processes within and by which authority is exercised and controlled. This document outlines the planned design for the governance of the PWC Structural Separation Program. This document may be subject to amendments over the course of the Program. 2. Governance Principles The following set of principles has guided development of the governance framework for the structural separation of PWC, and will be a reference for any future changes to the governance design as the project progresses. 3

4 1. Decisions are to be made independently by people who do not have a vested or conflict of interest in the outcome of those decisions. 2. Clear accountability is to exist for all roles and responsibilities within the project. 3. Stakeholders are to be informed of the status of the project to ensure adequate understanding of progress, impacts, decisions and actions required. 4. The rights and responsibilities of PWC s existing Board and management are to be respected, while asking them to support and assist with the implementation of the Government s direction. 5. Project governance and management processes are to be simplified and streamlined where possible, without sacrificing the ability to monitor progress towards deadlines. 6. The project is to proceed on the basis of a clear and agreed understanding of Day 1 and Day X operating models, and the deliverables and milestones required to be achieved throughout the project. Together, compliance with these principles will ensure a governance structure that enables the right decisions to be made and implemented with regard to establishment of the new GOCs, while considering the impact on the residual Monopoly GOC. 3. Governance Structure The governance structure on the following page outlines, at a conceptual level, how roles, responsibilities, and reporting lines will be organised. 4

5 Shareholding Minister Portfolio Minister NewCo New Corporations Advisory Committee Chair Chairs designate Retail and Generation PWC Representative DTF Representative Separation PMO Representative PWC Board PWC External Advisors New Corporations (NewCo) Unit Executive Director PWC CEO Separation PMO NewCo Program Coordinator PWC Program Coordinator External Advisors Project Management Resources Retail GOC Project Leader Generation GOC Project Leader Change Management Workstream Communications Monopoly GOC Project Leader Accountable/ Responsible for Monopoly GOC Corporate Services Workstream Legal Workstream Accountable/ Responsible for Retail and Generation GOCS Informed/ Consulted DCIS / NTG Workstream Financial Workstream IT Workstream Retail Operations Workstream Generation Operations Workstream Residual Monopoly Operations Workstream Covering business units listed right Power Networks Water Services System Control Gas Remote Figure 1: PWC Structural Separation Governance Structure 5

6 4. Governance Roles and Responsibilities The key governance levels and their main roles and responsibilities are overviewed below Shareholding Minister Provide guidance as to the Government s overall objectives and requirements for structural separation. Achieve legislative amendments necessary to give effect to the structural separation agenda. Endorse senior appointments (chairs designate for the two new GOCs, and leadership of the New Corporations Unit (NewCo)). Endorse overall structural separation budget. Endorse governance structure and resourcing for the structural separation project. Monitor overall progress of structural reform across both NewCo and PWC New Corporations Unit (NewCo)/NewCo Executive Director Plan and manage all matters in relation to the creation of the two new GOCs prior to their legal establishment. Make all key decisions in relation to the creation of the two new GOCs, subject to appropriate consultation (see Decision Authority Section of this document). Ensure key risks have been identified and appropriate mitigation controls are in place. Negotiate all necessary contracts and service level agreements on behalf of the two new GOCs. Recommend project governance to the Shareholding Minister and Advisory Committee. Coordinate and execute information flows to the Shareholding Minister and Advisory Committee, as well as to the PWC Board and CEO. Engage external advisors as necessary NewCo Advisory Committee Inform and advise the New Corporations Unit (NewCo). Provide input and views on key decisions relating to design of the two new GOCs as well as the impact of structural separation on the Monopoly GOC. Act as a sounding board before decisions are made on contentious issues. Monitor progress in the establishment of the two new GOCs. Identify key risks and issues, and assist with resolution where possible. Advocate the interests of their respective stakeholder. Facilitate awareness of the readiness of the two new GOCs and the residual Monopoly GOC for Day 1. 6

7 4.4. Program Coordinators (separately for NewCo and PWC) Coordinate the program of work on behalf of the two new GOCs and PWC, respectively. Manage and coordinate stakeholder relationships and communication. Act as the eyes and ears of the two new GOCs and PWC, respectively. Identify, track and escalate issues and risks to NewCo and the PWC CEO relating to the successful achievement of the program objectives. Ensure that the objectives and targets are achieved through effective coordination between NewCo and PWC. Maintain the Program budget, which is cut by workstream and also separated into three Projects. Maintain project documentation for future reference or archiving, with the assistance of the Separation PMO Project Management Office (PMO)/Support Resources Develop and maintain the Operating Models documentation for each GOC. Monitor separation planning and implementation to ensure alignment to Operating Model design decisions. Develop and maintain a central program master plan, master issue, risk and decision logs that are shared between NewCo and PWC. Monitor issues and risks, and assist in resolving separation issues and risks that do not neatly fit into a workstream or specific GOC Project. Work with workstream leaders to gather project status, issues, risks and interdependencies. Develop program and project status reports, Executive Briefings and other governance related stakeholder communications, as necessary. Manage interdependencies between projects and workstreams and highlight issues in this area to the Program Coordinators. Alert the NewCo ED and Program Coordinators to any difficulties, roadblocks or issues that need to be resolved to enable the timely delivery of project objectives. Assist in maintaining appropriate records and documentation Retail and Generation Project Leaders Ensure the Retail and Generation GOCs are smoothly and successfully established and transitioned by the due date and within the budget they are allocated. Drive detailed design of the Retail and Generation GOCs Operating Models, including ongoing monitoring of implementation against original design decisions. Adopt an overall whole of business perspective of the structural separation for the Retail and Generation businesses respectively, owning the overall design of the new organisations. Review the overall Retail and Generation Project Charters to ensure they capture all necessary scope areas and activities. Represent the Retail and Generation perspectives when advising NewCo or its ED on key decisions. 7

8 Contribute to the development of all necessary contracts and service level agreements with the Monopoly GOC on behalf of the two new GOCs. Support the Separation PMO in driving and monitoring Day 1 readiness of the two new GOCs, ensuring no disruption to operations. Review workstream separation and transition plans and monitor implementation. Alert the Separation PMO to any difficulties in interactions or any unanticipated activities/dependencies Monopoly GOC Project Leader Ensure the implications of the Retail and Generation separation on the Monopoly GOC are managed by the due date. Drive design of the revised Monopoly GOC Operating Model, including ongoing monitoring of implementation against original design. Adopt an overall whole of business perspective of the structural separation for the Monopoly GOC business, owning the overall impact on the organisation. Review the overall Monopoly GOC Project Charter to ensure it captures all necessary scope areas and activities. Represent the Monopoly GOC perspective when advising NewCo or its ED on key decisions. Contribute to the development of all necessary contracts and service level agreements with the two new GOCs on behalf of the Monopoly GOC. Support the Separation PMO in driving and monitoring Day 1 readiness of the Monopoly GOC, ensuring no disruption to operations. Review workstream separation and transition plans and monitor implementation. Alert the Separation PMO to any difficulties in interactions or any unanticipated activities/dependencies Workstreams Prepare or endorse workstream charters, including scope, objectives, key dates and budget. Prepare separation plans, by GOC Project, for their workstream scope, in conjunction and consultation with the GOC Project Leaders. Ensure their respective workstream activities are completed by the due dates. Raise and report issues and risks and execute mitigating actions. Provide input into budget estimates and report through any variance to budget. Provide reports to the Separation PMO on workstream progress, status, budgets, decisions, interdependencies, issues and risks. Alert the Separation PMO to any difficulties in interactions or any unanticipated activities/dependencies PWC Board and CEO Oversee all associated organisational changes within the Monopoly GOC, in time for separation on 1 July

9 Through negotiations with NewCo Executive Director, establish shared services arrangements whether transitional or ongoing in nature and enter into the associated services level agreements or contracts with the new GOCs. Through negotiations with NewCo Executive Director, develop commercial contracts for the purchase or sale of all power-related inputs or outputs. Ensure continued delivery of PWC s responsibilities for all aspects of the supply of electricity in the Territory until 30 June

10 5. Decision Authority 5.1. Separation decision-making During the design and implementation phases of PWC s structural separation, and until such time as the Boards of the new Corporations are in place, the NewCo Executive Director Alan Tregilgas 1 will make or (where he delegates decision making to the Program Coordinator or the project leaders) he will take responsibility for all final decisions on behalf of the two new GOCs essential to their separation and establishment, including, but not limited to: the Day 1, and Day X, operating models for the two new GOCs; the additional Board members to be nominated for the Shareholding Minister s approval; the appointment of the CEOs for the two new GOCs; the Day 1 financial structure of the two new GOCs; the budget and costs related to the establishment of the two new GOCs; and any other matter which relates to the successful establishment and future success of the two new GOCs. These decisions will be made on the basis of the NewCo Executive Director s assessment as to which option, on balance, best achieves the Government s objectives for implementation of structural separation, namely that structural separation occurs in ways that ensure: the new Government Owned Corporations (GOCs) commence on 1 July 2014; there is no inconvenience and disruption to residential and small business customers; the transition of employees to new entities occurs smoothly and ensures the fair and equitable treatment of employees; the additional costs involved are within a total budget approved by the Treasurer; no net costs are incurred by Territory power consumers, with additional costs incurred at least offset by likely savings and other benefits made possible by structural separation; and the Government s goals of more effective competition and/or regulation are also achieved. Decisions will only be taken: after consultation with the Monopoly GOC about the costs and consequences (for the Monopoly GOC) of at least two alternative courses of action ( options ); taking into account an estimate of the relative costs as well as the relative benefits of the main options to the respective new GOC; and in the case of key decisions, after consultation with the NewCo Advisory Committee. 1 On 9 December 2013, the Shareholding Minister wrote to the PWC Board advising that he had asked Alan Tregilgas to take responsibility for establishment of the two new GOCs and I would ask that the Board do whatever needs to be done to allow him to complete this task consistent with the Government's stated objectives 10

11 The purpose of the above process is: to obtain timely decisions, which is less likely when decisions are made by committee; and to ensure that separation decisions with respect to individual GOCs, whether the two new GOCs or the Monopoly GOC, are made on a whole-of-industry basis and in accordance with the shareholder s requirements Decision Matrix The table below highlights a number of key decisions and the responsibilities of specific parties to assist in making the decisions. Key Decisions Recommender Review Consultation Approver High-Level Day 1 Operating Model for Retail and Generation GOC Retail and Generation Project Leaders NewCo Advisory Committee Monopoly GOC Project Leader NewCo High-Level Day X Operating Model for Retail and Generation GOC Retail and Generation Project Leaders NewCo Advisory Committee Monopoly GOC Project Leader NewCo and Chair Designates High-Level Day 1 and Day X Operating Model for Monopoly GOC Monopoly GOC Project Leader PWC CEO Retail and Generation Project Leaders, NewCo ED PWC Board Budget NewCo ED NewCo Advisory Committee PWC CEO Treasurer Service Agreements Retail and Generation Project Leaders/ Monopoly GOC Project Leader NewCo Advisory Committee/ PWC CEO NewCo / PWC Board Detailed decisions on level of functional separation from Monopoly GOC Retail and Generation Project Leaders NewCo Advisory Committee PWC workstreams NewCo A decision register, to be managed by the Separation PMO, will capture and track all key decisions. 11

12 6. Forums and Meetings To facilitate governance of the PWC structural separation project, the following schedule of meetings will be established for the duration of the project. Forum Description Frequency Chair Attendees Preparation Requirements Update to Treasurer Monthly formal updates to the Treasurer Monthly N/A NewCo ED 1. Monthly Treasurer Update Update to PWC Board and PWC CEO Monthly formal updates to the PWC Board and PWC CEO Monthly NewCo ED PWC Board, PWC CEO, Monopoly GOC Leader 1. Monthly Update Report for PWC New Corporations Advisory Committee Meeting Two monthly meetings, on alternating fortnights: o One General Meeting, focusing on strategic and high-level matters o One Special Meeting focused on operational and technical matters The General Meeting, tentatively on the 2nd last Thursday of each month, will resemble a Board style meeting, at which the focus will be on high-level, strategic or whole of business issues, risks and decisions requiring discussion; and The Special Meeting, tentatively on the 1st Thursday of each month, where the focus will be on operational, management-level and technical issues, risks and decisions requiring discussion, and so will not necessarily require the participation of the Chairs-Designate. Monthly General, with Chairs Designate Monthly - Special Meetings NewCo ED Generation Chair Designate, Retail Chair Designate, NewCo Program Coordinator PWC Rep, DTF Rep 1. Fortnightly Status Report 2. Decisions Log 3. Risk and Issue Log 4. Critical Path Core Team Meeting Weekly Core Team meeting to: Review progress reports from workstreams Weekly NewCo Program NewCo ED, PWC Program 1. Weekly Status Report 2. Decisions Log 12

13 Forum Description Frequency Chair Attendees Preparation Requirements Share workstream key priorities, risks and issues Align workstream activities to ensure that crossstream dependencies can be actively managed Highlight key decision requirements Coordinator Coordinator Retail Lead, Generation Lead Separation PMO 3. Risk and Issue Log 4. Critical Path PMO Coordination Meeting Weekly Separation PMO meeting to align focus on critical current and upcoming items and coordinate efforts Discuss project progress, required decisions, risks and issues, priorities and milestones for the week Weekly EY Program Coordinators Project Management Resources 1. Status Report 2.Separation Plan 3. Issue / Risk Register 4. Decision Register Workstream Meetings Weekly or fortnightly workstream meeting between workstream leads and Separation PMO (to be agreed with workstream leader and dependent on workstream scale and complexity) to discuss progress, risks and issues, and priorities and milestones for the week Discuss any key decisions required Acts as input to the overall Program Status Report Weekly Separation PMO Workstreams Program Coordinators/ Project Leaders may attend if interested 1. Project Plan distributed 2. Latest issues and risks 3. Relevant section of the overall Program Status Report completed by the Separation PMO during the meeting Project Oversight and Decision Meeting Fortnightly project status review to provide clarification and guidance to workstreams Fortnightly NewCo ED Workstream Leaders Project Coordinators 1. Status Update 2. Decision Register 13

14 7. Project Management Tools and Templates A set of tools and templates will be used by the Structural Separation Program to facilitate the management and reporting of the program during the design and implementation phases, and possibly beyond this. No. Tool/Template Description 1 Workstream Charter A short document which outlines the objectives and scope of a workstream including identifying the required resources, key risks, dependencies and activities 2 Detailed workstream workplans 3 Separation and Transition Plan A workplan includes all tasks and milestones that each workstream needs to complete for the separation and transition project A plan that consolidates all of the project level milestones and critical activities from the workstreams, in MS Project 4 Program Status Update A weekly status update document to be used for providing updates of key activities, risks, issues and decisions 5 Project Risks and Issues Register A register to capture and assess workstream or project wide risks and issues and identify mitigating actions 6 Decision Log A log to capture and track key workstream and project wide decisions, including accountabilities and status 7 AC - General Meeting Report A fortnightly report to provide a high-level progress update of the project to the Advisory Committee General meeting, including key decision points required and any risks to delivery of separation 7 AC Special Meeting Report A more detailed fortnightly report to provide more detailed view on the progress of the separation, including key risks, issues, decisions made or required for review, etc 8 Executive Brief A monthly summary report to the PWC Board, Executive and NT Treasury to provide a progress update of the separation project 14

15 15

16 8. Budgets Budgets will be established according to a number of principles. Principles have also been agreed for the on-going tracking and monitoring of budgets across the project Budget development principles Budgets will be developed top down by NewCo and then validated with workstreams. This is required to ensure clear understanding of the potential recuperation of costs by PWC. Each budget is split by: o workstream. o costs incurred pre-day 1 and post-day 1. o internal and external resource costs. Any additional ongoing costs will also need to be identified as inputs into pro-forma P&Ls. Internal costs are only to be included in the budget where a full time backfill is required or the associated labour costs are material. Where backfill is required, the role and time required must be clearly stated. External costs are to be broken down into the following categories: o travel and accommodation (number of personnel, frequency and duration of visit). o consultants/contracted services. o other third party suppliers. o purchases/expenses. Assumptions adopted by each workstream in developing their budget will be reviewed by the Program Coordinators and the NewCo ED. Where costs are contingent on outcomes/decisions still to be made, the budget will be prepared on a best case scenario Budget tracking and monitoring principles The Program Coordinators will keep a central budget and will track adherence to that budget. A Cost Centre with separate activity codes for each Project (Retail, Generation, Monopoly and Joint ) will be established to allow capture and allocation of costs incurred. Actual workstream transition costs will be reviewed on a monthly basis against the agreed budgets. Workstream Leads and Project Leads will be required to justify any significant variances to budget. The NewCo ED s endorsement will be required before a revised budget is put to the Shareholding Minister for approval. Any re-forecasting of budgets will require the endorsement of the NewCo ED and the approval of the Shareholding Minister. 16

Electricity Reform Project

Electricity Reform Project Electricity Reform Project Governance Arrangements July 2012 Department of Treasury and Finance Contents 1. Introduction... 2 2. Project Governance... 3 3. Work Streams... 4 4. Project Timeline... 5 5.

More information

OE PROJECT CHARTER TEMPLATE

OE PROJECT CHARTER TEMPLATE PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,

More information

Project Assessment Framework Establish service capability

Project Assessment Framework Establish service capability Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.

More information

august09 tpp 09-05 Internal Audit and Risk Management Policy for the NSW Public Sector OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper

august09 tpp 09-05 Internal Audit and Risk Management Policy for the NSW Public Sector OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper august09 09-05 Internal Audit and Risk Management Policy for the NSW Public Sector OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Preface Corporate governance - which refers broadly to the processes

More information

APPLICATION OF KING III CORPORATE GOVERNANCE PRINCIPLES 2014

APPLICATION OF KING III CORPORATE GOVERNANCE PRINCIPLES 2014 WOOLWORTHS HOLDINGS LIMITED CORPORATE GOVERNANCE PRINCIPLES 2014 CORPORATE GOVERNANCE PRINCIPLES 2014 CORPORATE GOVERNANCE PRINCIPLES 2014 This table is a useful reference to each of the King III principles

More information

Application of King III Corporate Governance Principles

Application of King III Corporate Governance Principles APPLICATION of KING III CORPORATE GOVERNANCE PRINCIPLES 2013 Application of Corporate Governance Principles This table is a useful reference to each of the principles and how, in broad terms, they have

More information

Operations. Group Standard. Business Operations process forms the core of all our business activities

Operations. Group Standard. Business Operations process forms the core of all our business activities Standard Operations Business Operations process forms the core of all our business activities SMS-GS-O1 Operations December 2014 v1.1 Serco Public Document Details Document Details erence SMS GS-O1: Operations

More information

Policy (Board Approved)

Policy (Board Approved) Policy (Board Approved) Compliance and Regulatory Management Document Number GOV-POL-20 1.0 Policy Statement Stanwell Corporation Limited (Stanwell) is a Queensland company Government Owned corporation.

More information

Organization. Project Name. Project Overview Plan Version # Date

Organization. Project Name. Project Overview Plan Version # Date Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents

More information

Application of King III Corporate Governance Principles

Application of King III Corporate Governance Principles Application of Corporate Governance Principles Application of Corporate Governance Principles This table is a useful reference to each of the principles and how, in broad terms, they have been applied

More information

Programme Governance and Management Plan Version 2

Programme Governance and Management Plan Version 2 PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from

More information

Shareholder Communications Policy (v2.0)

Shareholder Communications Policy (v2.0) Shareholder Communications Policy (v2.0) Version History REV NO. DATE REVISION DESCRIPTION APPROVAL 1.0 June 2010 First version Board, June 2010 1.1 Nov 2014 Incorporate new requirements Reflect new Retail

More information

Governance Document Management Framework

Governance Document Management Framework Governance Document Management Framework Relevant Definitions: In the context of this document: AB means Academic Board Contact Officer means the position responsible for the day to day implementation

More information

COMMUNICATIONS MANAGEMENT PLAN <PROJECT NAME>

COMMUNICATIONS MANAGEMENT PLAN <PROJECT NAME> COMMUNICATIONS MANAGEMENT PLAN TEMPLATE This Project Communications Management Template is free for you to copy and use on your project and within your organization. We hope that you find this template

More information

APPLICATION OF THE KING III REPORT ON CORPORATE GOVERNANCE PRINCIPLES

APPLICATION OF THE KING III REPORT ON CORPORATE GOVERNANCE PRINCIPLES APPLICATION OF THE KING III REPORT ON CORPORATE GOVERNANCE PRINCIPLES Ethical Leadership and Corporate Citizenship The board should provide effective leadership based on ethical foundation. that the company

More information

WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)?

WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? Due to the often complex and risky nature of projects, many organizations experience pressure for consistency in strategy, communication,

More information

Project Governance A N T I C I P A T I N G A N A U D I T

Project Governance A N T I C I P A T I N G A N A U D I T Project Governance A N T I C I P A T I N G A N A U D I T Public sector Project Management characteristics Multi-million rand projects Often National interest projects Subject to intense scrutiny Uncertainty

More information

Position Description

Position Description Position Description Job title Group Section Responsible to Responsibility for staff Project Coordinator Natural Resource Operations Rotorua Lakes Protection & Restoration Programme Rotorua Lakes Business

More information

Advisory Council member responsibilities include:

Advisory Council member responsibilities include: GOVERNANCE AND OVERSIGHT OF THE KUALI PROJECT: The following provides a chart of the Governance and Oversight Structure for the Kuali Project. In addition to the below, is a Functional Council that includes

More information

Release Management: Effective practices for IT delivery

Release Management: Effective practices for IT delivery Release Management: Effective practices for IT delivery Introduction Today s health plans face a unique combination of technology challenges due to their complex IT environments. These environments serve

More information

RYDER SYSTEM, INC. COMPENSATION COMMITTEE CHARTER

RYDER SYSTEM, INC. COMPENSATION COMMITTEE CHARTER RYDER SYSTEM, INC. COMPENSATION COMMITTEE CHARTER Purposes The purposes of the Compensation Committee of the Board of Directors of Ryder System, Inc. are to (a) assist the Board of Directors in fulfilling

More information

Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt. Programme, Project & Service Management Analysis

Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt. Programme, Project & Service Management Analysis Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt Programme, Project & Service Management Analysis Table of Content 1 Executive Summary... 3 1.1 Scope of Work... 3 1.2 Methodology for

More information

NATIONAL PARTNERSHIP AGREEMENT ON TRANSITIONING RESPONSIBILITIES FOR AGED CARE AND DISABILITY SERVICES

NATIONAL PARTNERSHIP AGREEMENT ON TRANSITIONING RESPONSIBILITIES FOR AGED CARE AND DISABILITY SERVICES National Partnership Agreement on Transitioning Responsibilities for Aged Care and Disability Services NATIONAL PARTNERSHIP AGREEMENT ON TRANSITIONING RESPONSIBILITIES FOR AGED CARE AND DISABILITY SERVICES

More information

INTEGRATED SILICON SOLUTION, INC. CORPORATE GOVERNANCE PRINCIPLES. Effective January 9, 2015

INTEGRATED SILICON SOLUTION, INC. CORPORATE GOVERNANCE PRINCIPLES. Effective January 9, 2015 INTEGRATED SILICON SOLUTION, INC. CORPORATE GOVERNANCE PRINCIPLES Effective January 9, 2015 These principles have been adopted by the Board of Directors (the "Board") of Integrated Silicon Solution, Inc.

More information

NSW SENIOR EXECUTIVE SERVICE

NSW SENIOR EXECUTIVE SERVICE NSW SENIOR EXECUTIVE SERVICE NSW DEPARTMENT OF EDUCATION AND TRAINING Position Description POSITION DETAILS Position Title: Reports to: Location: Directorate: Chief Financial Officer Deputy Director-General,

More information

NATIONAL PARTNERSHIP AGREEMENT ON ENERGY EFFICIENCY

NATIONAL PARTNERSHIP AGREEMENT ON ENERGY EFFICIENCY NATIONAL PARTNERSHIP AGREEMENT ON ENERGY EFFICIENCY Council of Australian Governments An agreement between the Commonwealth of Australia and the States and Territories, being: The State of New South Wales

More information

Information Technology Governance Overview and Charter

Information Technology Governance Overview and Charter Information Technology Governance Overview and Charter Prepared by: Project #: Date submitted Document version: IT Governance Charter v03.05.2012 1.0 48.0 - Page 1 of 34 Document History Version Date Author

More information

Department of Administration Portfolio Management System 1.3 June 30, 2010

Department of Administration Portfolio Management System 1.3 June 30, 2010 E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2

More information

TERMS OF REFERENCE Electronic Communications Resilience and Response Group (EC RRG)

TERMS OF REFERENCE Electronic Communications Resilience and Response Group (EC RRG) TERMS OF REFERENCE Electronic Communications Resilience and Response Group (EC RRG) Goal Aims To ensure the availability of Electronic Communications infrastructure for the UK and provide an industry emergency

More information

Corporate Governance Guidelines. 1. The Board of Directors

Corporate Governance Guidelines. 1. The Board of Directors Corporate Governance Guidelines 1. The Board of Directors The Board of Directors (the Board ) of Zep Inc. (the Company ) is elected by the stockholders of the Company. The Board s primary goal is to maximize

More information

EXECUTIVE DIRECTOR, SKILLS & EMPLOYMENT JOB & PERSON SPECIFICATION SEPTEMBER 2015

EXECUTIVE DIRECTOR, SKILLS & EMPLOYMENT JOB & PERSON SPECIFICATION SEPTEMBER 2015 EXECUTIVE DIRECTOR, SKILLS & EMPLOYMENT JOB & PERSON SPECIFICATION SEPTEMBER 2015 EXECUTIVE ROLE STATEMENT JOB TITLE: CONTRACT TERM: Executive Director, Skills and Employment SAES2 3-5 years DEPARTMENT:

More information

ANGLOGOLD ASHANTI LIMITED

ANGLOGOLD ASHANTI LIMITED ANGLOGOLD ASHANTI LIMITED Registration No. 1944/017354/06 ( AGA or the Company ) REMUNERATION AND HUMAN RESOURCES COMMITTEE TERMS OF REFERENCE APPROVED BY THE BOARD OF DIRECTORS ON 30 OCTOBER 2014 1.0

More information

CONTRACT MANAGEMENT FRAMEWORK

CONTRACT MANAGEMENT FRAMEWORK CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

Department of Infrastructure and Planning: Governance Framework for Infrastructure Delivery Special Purpose Vehicles

Department of Infrastructure and Planning: Governance Framework for Infrastructure Delivery Special Purpose Vehicles Department of Infrastructure and Planning: Governance Framework for Infrastructure Delivery Special Purpose Vehicles Governance Framework for Special Purpose Vehicles Table of Contents Executive Summary...3

More information

Guide to the Performance Management Framework

Guide to the Performance Management Framework Guide to the Performance Management Framework November 2012 Contents Contents... Guide to the Performance Management Framework...1 1. Introduction...4 1.1 Purpose of the guidelines...4 1.2 The performance

More information

CORPORATE GOVERNANCE GUIDELINES

CORPORATE GOVERNANCE GUIDELINES CORPORATE GOVERNANCE GUIDELINES The following guidelines have been approved by the Board of Directors and, along with the charters of the Board committees, provide the framework for the governance of Darden

More information

Why are PMO s are Needed on Large Projects?

Why are PMO s are Needed on Large Projects? Why are PMO s are Needed on Large Projects? Keeps Project Manager focused on: Priority risks Priority issues Stakeholder alignment Technical challenges Ensures administrative tasks are completed: Projects

More information

Duration: One year with the option of an additional year based on performance.

Duration: One year with the option of an additional year based on performance. Position: Adviser to the Internal Audit Unit Objectives: A person to support the newly established Internal audit unit to transform it from its infancy stage to a unit that is a trusted adviser, and more

More information

Trust Board Report. Review of the effectiveness of the IM&T Committee

Trust Board Report. Review of the effectiveness of the IM&T Committee 1. Introduction Trust Board Report Review of the effectiveness of the The meets every eight weeks, with a specific responsibility for governance, strategic direction, approval and direction of developments

More information

Victorian Government Information and Communication Technology (ICT) Governance

Victorian Government Information and Communication Technology (ICT) Governance Governance Victorian Government Information and Communication Technology (ICT) Governance Framework A framework to describe ICT governance in the Victorian Government Keywords: ICT Strategy; governance;

More information

CORPORATE GOVERNANCE - BOARD CHARTER PART A DEFINING GOVERNANCE ROLES

CORPORATE GOVERNANCE - BOARD CHARTER PART A DEFINING GOVERNANCE ROLES CORPORATE GOVERNANCE - BOARD CHARTER PART A DEFINING GOVERNANCE ROLES 1. ROLE OF THE BOARD 1.1 Function The Board of Directors of Exalt Resources Limited have approved the following charter formalising

More information

Nomination, Remuneration and Human Resources Committee Charter

Nomination, Remuneration and Human Resources Committee Charter Nomination, Remuneration and Human Resources Committee Class Limited (ACN 116 802 054) As approved by the Board on 6 October 2015 1. Purpose of this The purpose of this is to specify the authority delegated

More information

Joint Operations Steering Committee Charter

Joint Operations Steering Committee Charter JOINT GOVERNANCE DOCUMENTS Document #: XXX-0001 - CHARTER - Joint Operations Steering Committee.doc Last Updated: 03/05/2011 Joint Operations Steering Committee Charter The Directors of the Department

More information

PROJECT MANAGEMENT GUIDELINES NATIONAL TRANSPORT AUTHORITY

PROJECT MANAGEMENT GUIDELINES NATIONAL TRANSPORT AUTHORITY PROJECT MANAGEMENT GUIDELINES FOR PROJECTS FUNDED BY THE NATIONAL TRANSPORT AUTHORITY (UP TO 20 MILLION IN VALUE) december 2011 Table of Contents Section A 1. Introduction 4 1.1 Purpose 4 1.2 Applicability

More information

Gladstone Ports Corporation Limited

Gladstone Ports Corporation Limited Gladstone Ports Corporation Limited Human Resources Committee Charter #159378v5 Adopted by Board 17/7/07 1 Table of Contents 1. TERMS OF REFERENCE... 3 2. ROLE AND RESPONSIBILITIES... 3 3. RELATIONSHIP

More information

JASON INDUSTRIES, INC. CORPORATE GOVERNANCE GUIDELINES

JASON INDUSTRIES, INC. CORPORATE GOVERNANCE GUIDELINES JASON INDUSTRIES, INC. CORPORATE GOVERNANCE GUIDELINES Jason Industries, Inc. (the Company ) is committed to developing effective, transparent and accountable corporate governance practices. These Corporate

More information

CONTRACT MANAGEMENT POLICY

CONTRACT MANAGEMENT POLICY CONTRACT MANAGEMENT POLICY Section Finance Approval Date 25/08/2014 Approved by Directorate Next Review Aug 2016 Responsibility Chief Operating Officer Key Evaluation Question 6 PURPOSE The purpose of

More information

Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997

Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997 Why a Project Check List? A good way to ensure that all start-up tasks are completed prior to actually starting the project is to develop a start-up check list. The check list can be developed and then

More information

EQT GP HOLDINGS, LP (EQT GP Services, LLC) Corporate Governance Guidelines. (Adopted by the Board on April 30, 2015)

EQT GP HOLDINGS, LP (EQT GP Services, LLC) Corporate Governance Guidelines. (Adopted by the Board on April 30, 2015) EQT GP HOLDINGS, LP (EQT GP Services, LLC) Corporate Governance Guidelines (Adopted by the Board on April 30, 2015) 1. Statement of Governance. EQT GP Holdings, LP (the Partnership ) is governed by a limited

More information

Update on Programme Management Controls & Risks

Update on Programme Management Controls & Risks Committee and Date Audit Committee 26/06/14 Update on Programme Management Controls & Risks Responsible Officer George Candler Director of Commissioning e-mail: George.Candler@shropshire.gov.uk Tel: 01743

More information

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3 /01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,

More information

How To Integrate Hr

How To Integrate Hr Houston Compensation & Benefits Post-Deal Integration Planning for Compensation & Benefits Wednesday, April 22, 2015 Agenda Deal Timeline/Background Integration of Compensation and Benefits Medical/Retirement

More information

Role and Skill Descriptions. For An ITIL Implementation Project

Role and Skill Descriptions. For An ITIL Implementation Project Role and Skill Descriptions For An ITIL Implementation Project The following skill traits were identified as fairly typical of those needed to execute many of the key activities identified: Customer Relationship

More information

Commonwealth of Massachusetts CommonWay Schedule Management Guidelines. Common Values - Common Goals Common Way. Schedule Management.

Commonwealth of Massachusetts CommonWay Schedule Management Guidelines. Common Values - Common Goals Common Way. Schedule Management. Schedule Management Values - Goals Schedule Management Schedule Management v1.0 1 of 6 10/27/2010 Schedule Management Values - Goals Table of Contents 1 Schedule Management Guideline... 3 1.1 Determine

More information

BOD/2015/10 DOC 06-Decision Meeting of the Board of Directors October 16, 2015

BOD/2015/10 DOC 06-Decision Meeting of the Board of Directors October 16, 2015 BOD/2015/10 DOC 06-Decision Meeting of the Board of Directors October 16, 2015 Approved Decisions and Secretariat Actions Based on Recommendations set out in BOD/2015/10 DOC 06 - Proposal for a More Effective

More information

Position Description. Enterprise Agreement: Budget Responsibility: Nil

Position Description. Enterprise Agreement: Budget Responsibility: Nil Position Description Position Details Position Scope Title: Division: Project Manager Finance & Corporate Services Enterprise Agreement: Budget Responsibility: Department: Payroll Authority Level: Ambulance

More information

BOARD MANDATE. an Audit Committee, and a Governance, Nominating & Compensation Committee.

BOARD MANDATE. an Audit Committee, and a Governance, Nominating & Compensation Committee. BOARD MANDATE 1.0 Introduction The Board of Directors (the "Board") of Baja Mining Corp. (the "Company") is responsible for the stewardship of the Company and management of its business and affairs. The

More information

Final. North Carolina Procurement Transformation. Governance Model March 11, 2011

Final. North Carolina Procurement Transformation. Governance Model March 11, 2011 North Carolina Procurement Transformation Governance Model March 11, 2011 Executive Summary Design Approach Process Governance Model Overview Recommended Governance Structure Recommended Governance Processes

More information

Part B1: Business case developing the business case

Part B1: Business case developing the business case Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

NATIONAL PARTNERSHIP AGREEMENT ON THE NATIONAL QUALITY AGENDA FOR EARLY CHILDHOOD EDUCATION AND CARE

NATIONAL PARTNERSHIP AGREEMENT ON THE NATIONAL QUALITY AGENDA FOR EARLY CHILDHOOD EDUCATION AND CARE NATIONAL PARTNERSHIP AGREEMENT ON THE NATIONAL QUALITY AGENDA FOR EARLY CHILDHOOD EDUCATION AND CARE Council of Australian Governments An agreement between the Commonwealth of Australia and the States

More information

State and Regional Emergency Management Committees Part 5: Emergency Management Manual Victoria

State and Regional Emergency Management Committees Part 5: Emergency Management Manual Victoria State and Regional Emergency Management Committees Part 5: Emergency Management Manual Victoria Contents 5.1 Introduction...5 1 5.2 Committees in Emergency Management...5 1 5.3 State Crisis and Resilience

More information

Ambulance Victoria. Position Description

Ambulance Victoria. Position Description Position Title: IT Project Manager Team Leader Position Description Division: Information & Technology Department: Solution Delivery Reports To: Manager Solution Delivery Direct Reports: IT Project Managers

More information

Documents and Policies Pertaining to Corporate Governance

Documents and Policies Pertaining to Corporate Governance Documents and Policies Pertaining to Corporate Governance 3.1 Charter of the Board of Directors IMPORTANT NOTE Chapter 1, Dream, Mission, Vision and Values of the CGI Group Inc. Fundamental Texts constitutes

More information

Job Description. Line Management of a small team of staff administrating and managing patient and professional feedback and incidents.

Job Description. Line Management of a small team of staff administrating and managing patient and professional feedback and incidents. Job Description Job Title Pay Band Base Dept./Team Responsible to Accountable to Responsible for Complaints, Incidents and Governance Manager New Alderley House, Macclesfield Eastern Cheshire Clinical

More information

South East Water Corporation Finance Assurance and Risk Management Committee Charter

South East Water Corporation Finance Assurance and Risk Management Committee Charter South East Water Corporation Finance Assurance and Risk Management Committee Charter Created: October 2012 Document number: BS 2359 Last reviewed: May 2015 1. Purpose The South East Water Corporation Board's

More information

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided. Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60

More information

CONFIGURATION COMMITTEE. Terms of Reference

CONFIGURATION COMMITTEE. Terms of Reference SWBTB (8/13) 166 (g) CONFIGURATION COMMITTEE Terms of Reference 1. CONSTITUTION 1.1 The Board hereby resolves to establish a Committee of the Board to be known as the Configuration Committee (The Committee).

More information

COMMUNICATIONS MANAGEMENT PLAN <PROJECT NAME>

COMMUNICATIONS MANAGEMENT PLAN <PROJECT NAME> COMMUNICATIONS MANAGEMENT PLAN TEMPLATE This Project Communications Management Template is free for you to copy and use on your project and within your organization. We hope that you find this template

More information

Performance Management. Date: November 2012

Performance Management. Date: November 2012 Performance Management Date: November 2012 SSBA Background Document Background 3 4 Governance in Saskatchewan Education System 5 Role of School Boards 6 Performance Management Performance Management Overview

More information

Developing a Project Governance Framework

Developing a Project Governance Framework Developing a Project Governance Framework Ross Garland 1 Introduction The UK Government lists "decision making failures" as one of the top 5 causes of project failure. Victorian Treasury which runs the

More information

[action here] [action here] 3 Minutes of the last board / committee meeting 3.2

[action here] [action here] 3 Minutes of the last board / committee meeting 3.2 This is a sample agenda. On the following pages, you will find explanations of the purpose of each element of the agenda. Some of the elements of the agenda may require amendment for use as committee meeting

More information

Role Description Curator - Digital Assets

Role Description Curator - Digital Assets Role Description Curator - Digital Assets Cluster Agency Division/Branch/Unit Location Department of Planning & Environment Sydney Living Museums Collections & Access The Mint Classification/Grade/Band

More information

Project Management Methodology

Project Management Methodology Project Management Methodology 1/6/2015 PAGE 1 OF 28 Version 2.0 Contents INTRODUCTION... 4 1. Overview... 4 PHASE 1 PROJECT INITIATION... 5 1. Governance Model... 6 2. Project Prioritization Process...

More information

Project Management Fact Sheet:

Project Management Fact Sheet: Project Management Fact Sheet: Steering Committee nuts and bolts Version: 1.2, November 2008 DISCLAIMER This material has been prepared for use by Tasmanian Government agencies and Instrumentalities. It

More information

INTEGRATED PROJECT MANAGEMENT (IPM) DOCUMENT SECTION 1

INTEGRATED PROJECT MANAGEMENT (IPM) DOCUMENT SECTION 1 PMO QA/Approval: September 11, 2015 Project Title/Subject: INTEGRATED PROJECT MANAGEMENT (IPM) DOCUMENT SECTION 1 Back Office Collaboration and Integration Project GENERAL INFORMATION [this section completed

More information

PROJECT SCOPE STRENGTHENING COMMUNITY GOVERNANCE IN RSD SITES IN CENTRAL AUSTRALIA. December 2010

PROJECT SCOPE STRENGTHENING COMMUNITY GOVERNANCE IN RSD SITES IN CENTRAL AUSTRALIA. December 2010 PROJECT SCOPE STRENGTHENING COMMUNITY GOVERNANCE IN RSD SITES IN CENTRAL AUSTRALIA December 2010 PROJECT DETAILS Project Title Strengthening community governance in RSD sites in central Australia Project

More information

NORTHERN TERRITORY OF AUSTRALIA HEALTH SERVICES ACT 2014. As in force at 1 July 2014. Table of provisions

NORTHERN TERRITORY OF AUSTRALIA HEALTH SERVICES ACT 2014. As in force at 1 July 2014. Table of provisions NORTHERN TERRITORY OF AUSTRALIA HEALTH SERVICES ACT 2014 As in force at 1 July 2014 Table of provisions Part 1 Preliminary matters 1 Short title... 1 2 Commencement... 1 3 Principles and objectives of

More information

A New Service Framework for Health and Hospital Services in the Northern Territory

A New Service Framework for Health and Hospital Services in the Northern Territory A New Service Framework for Health and Hospital Services in the Northern Territory November 2012 www.nt.gov.au/health Acknowledgement Photographs are courtesy of Media and Corporate Communications and

More information

INTERNAL AUDIT FRAMEWORK

INTERNAL AUDIT FRAMEWORK INTERNAL AUDIT FRAMEWORK April 2007 Contents 1. Introduction... 3 2. Internal Audit Definition... 4 3. Structure... 5 3.1. Roles, Responsibilities and Accountabilities... 5 3.2. Authority... 11 3.3. Composition...

More information

INTERGOVERNMENTAL AGREEMENT FOR THE NATIONAL DISABILITY INSURANCE SCHEME (NDIS) LAUNCH

INTERGOVERNMENTAL AGREEMENT FOR THE NATIONAL DISABILITY INSURANCE SCHEME (NDIS) LAUNCH INTERGOVERNMENTAL AGREEMENT FOR THE NATIONAL DISABILITY INSURANCE SCHEME (NDIS) LAUNCH Part 1 Preliminaries 1. The Commonwealth of Australia (the Commonwealth) and States and Territories (the States) are

More information

3 August 2012 Policy updated to reflect name changes and alignment with current Aurora Energy Group Policy standards.

3 August 2012 Policy updated to reflect name changes and alignment with current Aurora Energy Group Policy standards. Aurora Energy Risk Management Policy Version History REV NO. DATE REVISION DESCRIPTION APPROVAL 0 19/11/98 Risk Management Policy Prepared by: Manager Internal Audit 1 March 2007 Risk Management Policy

More information

R U N D O. The ECU Technology Governance Framework A brief guide

R U N D O. The ECU Technology Governance Framework A brief guide PLAN R U N D O DO The ECU Technology Governance Framework A brief guide The ECU Technology Governance Framework A brief guide The ECU Technology Governance Framework is made up of a set of processes, effected

More information

5.2. 5.2 Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name]

5.2. 5.2 Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name] 231 5.2 Template for IT Project Plan Name of the Tool: Source: Usage: Description: Template for IT Project Plan GIZ This template has been designed as a tool to support the planning of IT projects for

More information

TERMS OF REFERENCE - MAJOR EVENTS PANEL

TERMS OF REFERENCE - MAJOR EVENTS PANEL TERMS OF REFERENCE - MAJOR EVENTS PANEL OVERVIEW The Major Events Panel is a specialist advisory body to the UK Sport Board and its Major Events Team. Its main purpose is to represent the interests of

More information

Coach, Inc. Corporate Governance Principles

Coach, Inc. Corporate Governance Principles Coach, Inc. Corporate Governance Principles The following principles have been approved by the Board of Directors and, along with the charters and protocols of the Board committees, provide the framework

More information

In order to achieve these things, thereby delivering better outcomes for all Tasmanians, change is required.

In order to achieve these things, thereby delivering better outcomes for all Tasmanians, change is required. Second Reading Speech Electricity Reform Bill 2012 Mr Speaker, a key priority of the Government is to ensure Tasmanians have access to the lowest sustainable electricity bills. In addition, the safe and

More information

GREAT PLAINS ENERGY INCORPORATED BOARD OF DIRECTORS CORPORATE GOVERNANCE GUIDELINES. Amended: December 9, 2014

GREAT PLAINS ENERGY INCORPORATED BOARD OF DIRECTORS CORPORATE GOVERNANCE GUIDELINES. Amended: December 9, 2014 GREAT PLAINS ENERGY INCORPORATED BOARD OF DIRECTORS CORPORATE GOVERNANCE GUIDELINES Amended: December 9, 2014 Introduction The Board of Directors (the Board ) of Great Plains Energy Incorporated (the Company

More information

LMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012

LMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 TABLE OF CONTENTS INTRODUCTION... 2 PROJECT MANAGEMENT APPROACH... 2 PROJECT SCOPE... 2 MILESTONE LIST... 2 SCHEDULE BASELINE

More information

EXECUTIVE COMMITTEE TERMS OF REFERENCE

EXECUTIVE COMMITTEE TERMS OF REFERENCE (Registration Number: 1966/009846/06) EXECUTIVE COMMITTEE TERMS OF REFERENCE Approved by the Executive Committee on 4 November 2013 Approved by the Board on 14 November 2013 1. Definitions Unless the context

More information

Governance Principles

Governance Principles Governance Principles copyright 2013 general electric company Governance Principles The following principles have been approved by the board of directors and, along with the charters and key practices

More information

School Council Funds Management Guide

School Council Funds Management Guide School Council Training Day School Council Funds Management Guide 27 September 2014 1 Overview Provide background on: Policy Procedure Funds Management Guide Future Direction 2 Policy P.133.FIN - Management

More information

IT Governance Framework Summary

IT Governance Framework Summary IT Governance Framework Summary Purpose This summary provides an overview of the IT Governance Framework the UoN has adopted that is aligned with the UoN NeW Directions Strategic Plan 2013-2015. Aligned

More information

HHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC)

HHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC) Office of the Chief Information Officer Office of the Assistant Secretary for Resources and Technology Department of Health and Human Services HHS OCIO Policy for Information Technology (IT) Enterprise

More information

Hunter Hall International Limited

Hunter Hall International Limited Hunter Hall International Limited ABN 43 059 300 426 Board Charter 1. Purpose 1.1 Hunter Hall International Limited (Hunter Hall, HHL) is an ASX-listed investment management company. 1.2 This Board Charter

More information

MNLARS Project Audit Checklist

MNLARS Project Audit Checklist Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?

More information

AUDIT COMMITTEE BEST PRACTICES CHECKLIST

AUDIT COMMITTEE BEST PRACTICES CHECKLIST AUDIT COMMITTEE BEST PRACTICES CHECKLIST General 1. Members have the appropriate predefined qualifications to meet the objectives of the audit committee s charter, including appropriate financial literacy.

More information

PROJECT AGREEMENT FOR INDEPENDENT PUBLIC SCHOOLS INITIATIVE

PROJECT AGREEMENT FOR INDEPENDENT PUBLIC SCHOOLS INITIATIVE PROJECT AGREEMENT FOR INDEPENDENT PUBLIC SCHOOLS INITIATIVE An agreement between: - the Commonwealth of Australia; and - the State of South Australia. This project will increase the autonomy of government

More information

I. The Role of the Board of Directors II. Director Qualifications III. Director Independence IV. Director Service on Other Public Company Boards

I. The Role of the Board of Directors II. Director Qualifications III. Director Independence IV. Director Service on Other Public Company Boards Corporate Governance Guidelines The Board of Directors (the Board ) of (the Corporation ) has adopted these governance guidelines. The guidelines, in conjunction with the Corporation s articles of incorporation,

More information

Risk Committee Charter

Risk Committee Charter Risk Committee Charter St Andrew s Insurance (Australia) Pty Ltd St Andrew s Life Insurance Pty Ltd St Andrew s Australia Services Pty Ltd Scope The Risk Committee ( the Committee ) performs the functions

More information