ESB Networks Ltd Statement of Charges
|
|
|
- Daniel Crawford
- 10 years ago
- Views:
Transcription
1 ESB Networks Ltd Statement of Charges Revision Date: 9/2014 Revision No.: 11 Document No: DOC AXR Issued by: ESB NETWORKS LTD Approved by : CER Effective Date: 01/10/2014 Commercial and Renewable Regulation Asset Management ESB Networks Ltd.
2 ESB Networks Ltd. Statement Of Charges Table of Contents 1. About this document Scope... 3 Associated Documentation... 3 Implementation and Review... 3 Definitions of Terms Used in This Document Charges for Connection to the Distribution System... 5 About this Section Domestic Connection Charges Single Connection Domestic Connection Charges 2 to 19 Houses... 6 Domestic Scheme Connection Charges 20 Houses or more... 7 LV Business Demand Customer Connection Charges... 8 MV Single Business Demand Customer Connection Charges... 9 MV Network Charges and Trenching Charges Supplementary MV Network Charges Supplementary 38kV Network Charges Notes on Business Demand Customer Connection Charges Distribution Use Of System (DUoS) Charges About this Section Schedule of Non- Maximum Demand DUoS Group Tariff Groups (DG1 to DG5b) Special Notes for tariff groups DG3 and DG Schedule of Maximum Demand Tariff Groups (DG6 to DG9b) Notes for Maximum Demand Tariff Groups (DG6 to DG9b) Charges for Distribution Services and Third Party Damage About This Section Background Basis for Charges Schedule of Distribution Service Charges Third Party Damage Underground Cables and Equipment Third Party Damage Overhead Network Notes on Service and Third Party Damage Charges Transactional Charges for Additional Services to Use of System About this section Transaction Charges for Energisation, De-Energisation and Metering Services Sliding Scale of DUoS Transactional Charges Revision 11 Sept 2014 DOC No DOC AXR. Page 2 of 32
3 1. About this document. This document lists the current connection charges, distribution use of system charges (DUoS) and other service charges applied by ESB Networks Ltd. (ESBN) in its role as Distribution System Operator. The charges are based on procedures and policies as approved by CER. Each section is preceded by a section which sets out the high level basis for the charges and the underlying policies associated with the charges. Where the basis of charges for a section is too large to be included in this document, a separate Basis of Charges document is referenced and available for download separately. Scope This document lists the Standard Connection Charges for providing individual connection points for users of the Distribution System. In some cases a non-standard charging mechanism may need to be applied which is not covered by this document. For situations where non-standard connection charges apply see the Basis of Charges for Connection to the Distribution System document. This document also lists the Distribution Use of System charges that apply once a connection has been connected. Also included in this document are the current standard charges for various ancillary services provided to electricity suppliers and customers. This document does not describe the underlying policies and procedures associated with the charges or the connection process itself. These are described in more detail in the following documents which can be found on ESBN website Associated Documentation Document Title Source Basis of Charges for Connection to the Distribution System Rules for Application of Distribution Use of System Tariff Group Rules for Application of Transactional Charges for Additional Services to Use the System Guide to the Process for Connection to the Distribution System DSO DSO DSO DSO Distribution System Security and Planning only) Business Parks Policy Standards (demand customers DSO DSO Implementation and Review ESBN s duty of non-discrimination requires that these charges be applied consistently and fairly, in all situations and in all locations by ESBN. In addition, ESBN will implement a system to monitor the overall implementation of the charges to ensure that revenue is consistent with the amounts billed. Revision 11 Sept 2014 DOC No DOC AXR. Page 3 of 32
4 Definitions of Terms Used in This Document In general, the definitions of terms used in this document are the same as in the General Conditions for Connection of Industrial and Commercial Customers to the Distribution System, see 1.0 Definitions and Interpretation, p 3 9). The definitions of terms particular to this document are given below. Design costs Term Dedicated Connection Asset Distribution System Operator (DSO) HV Network Definition The actual estimated cost of constructing network Electrical network (lines, cables, switchgear etc.) used to connect a single user to the transmission or distribution system. The connection asset is specific to the user and does not form part of the connection to any other user. ESBN in its role as Distribution System Operator licence holder. Network operating at 38kV or more Least-cost technicallyacceptable solution MV Network LV Network Maximum Export Capacity (MEC) Maximum Import Capacity (MIC) Service Service Alteration The term that describes the cheapest connection method that meets the requirements in the Planning and Security Standards and the Distribution Code Network operating at 10kV or 20kV Network operating at 240V 380V The amount of electricity referred to as being the Maximum Export Capacity in the Connection Agreement. The amount of electricity referred to as being the Maximum Import Capacity in the Connection Agreement. A domestic service is an underground cable from a minipillar or pole, or overhead conductors from a pole. Overhead conductors may be bare separate conductors or insulated (bundled) conductors. This is defined as any situation where the service cable or conductors have to be disconnected and subsequently reconnected at the customer s meter. Revision 11 Sept 2014 DOC No DOC AXR. Page 4 of 32
5 2. Charges for Connection to the Distribution System About this Section. This section lists the current charges for connection to the distribution system. The charges stated in this section of the document are based on charging procedures and policies as approved by CER and are detailed in the Basis of Charges for Connection to the Distribution System document. Domestic Connection Charges Single Connection. The charges in the table below are standard charges for a connection to a single rural or urban house which is not part of a multi-unit residential or mixed development. Table 2.1 Domestic Connection Charges Single Connection Description Maximum Import Capacity kva Connection Charge including VAT Standard Connection 1 12kVA 1,805 Enhanced Connection (conditions apply) Upgrade Connection (conditions apply) 16kVA 2,444 12kVA to 16kVA 1,072 Family Apartment 12kVA 166 Non-Dwelling Farm Building 3kVA 50% of design costs Special Connection (single phase) 20kVA 1,673plus MV network charges Special Connection (single phase) 29kVA 2,240plus MV network charges Special Connection (three phase) 20kVA 2,332plus MV network charges Special Connection (three phase) 29kVA 2,994plus MV network charges Capacities 30 kva 30kVA N/A - See Business Connection Charges. 1 This level is to meet E u r o p e a n s t a n d a rd EN50160 Revision 11 Sept 2014 DOC No DOC AXR. Page 5 of 32
6 Domestic Connection Charges 2 to 19 Houses The charges in the table below are standard charges for connection to houses which form part of a simple domestic development (Housing Scheme) with individual services but not part of a mixed business and domestic apartment development. Table 2.2 Standard Charges for Small Domestic Developments (2-19 Houses) excluding VAT Connection Capacity 12kVA only No. of Houses Charges for 2 to 4 houses where the average length of roadway per house is up to a max of 50m 2,3101see footnote 3,0291see footnote 3,7491see footnote No. of Houses No. of Houses Charges for 5 to 8 houses where the average length of roadway per house is up to a max of 14m 4,468 5,188 5,907 6,627 Charges for 9-19 houses average length of roadway per house as shown 1m 2m 3m 4m 5m 6m 7m 8m 9m 10m 11m 12m 13m 14m 6,453 6,664 6,891 7,110 7,346 7,548 7,759 7,969 8,188 8,399 8,626 8,836 9,064 9,266 7,061 7,298 7,554 7,800 8,065 8,293 8,530 8,766 9,013 9,250 9,505 9,742 9,998 10,225 7,669 7,932 8,216 8,490 8,785 9,038 9,301 9,564 9,838 10,101 10,385 10,648 10,932 11,185 8,277 8,566 8,879 9,180 9,504 9,782 10,072 10,361 10,662 10,952 11,264 11,554 11,866 12,144 8,885 9,201 9,542 9,870 10,224 10,527 10,843 11,159 11,487 11,803 12,144 12,460 12,801 13,104 9,493 9,835 10,204 10,560 10,943 11,272 11,614 11,956 12,312 12,654 13,023 13,365 13,735 14,063 10,101 10,469 10,867 11,250 11,663 12,016 12,385 12,753 13,136 13,505 13,903 14,271 14,669 15,023 10,708 11,103 11,530 11,940 12,382 12,761 13,156 13,551 13,961 14,356 14,782 15,177 15,603 15,982 11,316 11,737 12,192 12,630 13,102 13,506 13,927 14,348 14,786 15,207 15,662 16,083 16,537 16,942 11,924 12,372 12,855 13,320 13,821 14,251 14,698 15,145 15,611 16,058 16,541 16,988 17,472 17,901 12,532 13,006 13,517 14,010 14,541 14,995 15,469 15,943 16,435 16,909 17,421 17,894 18,406 18,861 1 For two, three and four house domestic developments an upper limit of 50 metres average length of roadway per house applies. Revision 11 Sept 2014 DOC No DOC AXR. Page 6 of 32
7 Domestic Scheme Connection Charges 20 Houses or more The table below lists the standard charges for houses in domestic developments where there are twenty or more houses, each with a MIC of 12kVA Table 2.3 Standard Charges for Housing Schemes (20 houses or more) excluding VAT Connection Capacity 12kVA only Average Length of Roadway per House 1m 2m 3m 4m 5m 6m 7m 8m 9m 10m 11m 12m 13m 14m Charge per House Notes: Multiple Connections of MIC >12 kva are charged at 50% of Design Costs Domestic Connection Capacities of MIC > = 30 kva are treated under Business Charges Where the average length of roadway per house exceeds 14m, 50% of Design Costs are charged Revision 11 Sept 2014 DOC No DOC AXR. Page 7 of 32
8 LV Business Demand Customer Connection Charges Table 2.4 LV Business Demand Customer Connection Charges (MIC 2kVA to 1000kVA) LV Single Phase < 2kVA Connection Method Standard Charge (per installation) 10m clipped service m UG only m UG joint hole m UG (Br Joint) 1, LV OH/UG <200m 1, Pole & Transformer 2, LV Single Phase Connection < 30kVA MIC (kva) Standard Charge 15 1, , LV Three Phase Connection MIC (kva) Standard Charge 15 1, , , , , , , , , , , , Note: Due to higher capacity charges and higher DUoS charges, LV connections greater than 500kVA may not be economical for the customer. However, the remainder of this Table may be used for small increases where technically possible. LV Three Phase Connection MIC (kva) Standard Charge , , , , , , , , , , , Revision 11 Sept 2014 DOC No DOC AXR. Page 8 of 32
9 MV Single Business Demand Customer Connection Charges Table 2.5 MV Business Demand Customer Connection Charges (MIC 100kVA to 5MVA) MV Three Phase Connection (10kV or 20kV) MIC Standard Charge 500 8, , , , ,800 1,000 16,670 1,200 19,670 1,400 22,650 1,600 25,630 1,800 28,650 2,000 31,620 2,200 34,620 2,400 37,620 2,500 39,040 2,600 40,600 2,800 43,610 3,000 46,590 3,200 49,600 3,400 52,560 3,600 55,580 3,800 58,550 4,000 61,540 4,200 72,370 4,400 83,910 4, ,570 4, ,070 Revision 11 Sept 2014 DOC No DOC AXR. Page 9 of 32
10 Table 2.6 MV Business Demand Customer Connection Charges (MIC 5MVA to 15MVA) MV Three Phase Connection (10kV or 20kV) MIC Standard Charge (per installation) 5, ,300 5, ,520 5, ,460 5, ,110 5, ,650 6, ,030 6, ,110 6, ,220 6, ,020 6, ,820 7, ,320 7, ,670 7, ,900 7, ,990 7, ,920 8, ,700 8, ,100 8, ,490 8, ,910 8, ,280 9, ,690 9, ,080 9, ,490 9, ,870 9, ,290 MV Three Phase Connection (20kV Only ) MIC Standard Charge (per installation) 10, ,680 10, ,150 10, ,650 10, ,970 10, ,310 11, ,480 11, ,540 11, ,560 11, ,460 11, ,200 12, ,940 12,200 1,015,670 12,400 1,059,280 12,600 1,103,720 12,800 1,149,050 13,000 1,195,330 13,200 1,242,650 13,400 1,290,650 13,600 1,339,810 13,800 1,389,690 14,000 1,440,550 14,200 1,492,410 14,400 1,544,980 14,600 1,598,680 14,800 1,653,110 15,000 1,708,520 Revision 11 Sept 2014 DOC No DOC AXR. Page 10 of 32
11 Table 2.7 MV Business Demand Customer Connection Charges (MIC 15MVA to 20MVA) Note that due to network constraints MV connections over 15MVA may not be offered. However, this Table may be used for small increases where technically possible. MV 3 Phase Connection (20kV only) MIC Standard Charge (Per installation) 15,000 1,708,520 15,200 1,731,320 15,400 1,754,120 15,600 1,777,040 15,800 1,799,850 16,000 1,822,650 16,200 1,845,460 16,400 1,868,260 16,600 1,891,040 16,800 1,913,830 17,000 1,936,620 17,200 1,959,430 17,400 1,982,210 17,600 2,005,020 17,800 2,027,810 18,000 2,050,750 18,200 2,073,530 18,400 2,096,340 18,600 2,119,120 18,800 2,141,930 19,000 2,164,710 19,200 2,187,530 19,400 2,210,310 19,600 2,233,120 19,800 2,255,900 20,000 2,278,690 Note: The standard charge for 38kV connections is the same as the standard charge for the MIC level at MV and can be taken from the MV table. Revision 11 Sept 2014 DOC No DOC AXR. Page 11 of 32
12 Table 2.8 MV Business Demand Customer Connection Charges (MIC 20MVA to 25MVA) Note that due to network constraints MV connections over 15MVA may not be offered. However, this Table may be used for small increases where technically possible. MV 3 Phase Connection (20kV only) MIC Standard Charge (per installation) 20,200 2,301,640 20,400 2,324,420 20,600 2,347,230 20,800 2,370,020 21,000 2,392,840 21,200 2,415,620 21,400 2,438,430 21,600 2,461,210 21,800 2,484,000 22,000 2,506,800 22,200 2,529,600 22,400 2,552,390 22,600 2,575,330 22,800 2,598,130 23,000 2,620,920 23,200 2,643,720 23,400 2,666,520 23,600 2,689,310 23,800 2,712,110 24,000 2,734,900 24,200 2,757,720 24,400 2,780,510 24,600 2,803,300 24,800 2,826,230 25,000 2,849,010 Revision 11 Sept 2014 DOC No DOC AXR. Page 12 of 32
13 MV Network Charges and Trenching Charges Table 2.9 MV Network Charges and Trenching Charges MV Overhead Line Network Charge for New Network per metre + VAT Single Phase (Unmetered) Single Phase (Metered) Phase (< 5MVA) Phase (>= 5MVA) MV Underground Cable Network Charge for New Cable per metre + VAT Single Phase (Unmetered) Single Phase (Metered) Phase (70/185s) Phase (400s) Trenching Charges Trenching Location Charge per metre + VAT Road/Path Grass Supplementary MV Network Charges Table 2.10 Business Demand Customer Supplementary MV Charges where MV MIC > 500kVA and > 7km from the station Km kva ,100 2,200 3,300 4,500 5,600 6,700 7,800 8, ,200 4,500 6,700 8,900 11,100 13,400 15,600 17, ,300 6,700 10,000 13,400 16,700 20,000 23,400 26, ,500 8,900 13,400 17,800 22,300 26,700 31,200 35, ,600 11,100 16,700 22,300 27,800 33,400 38,900 44, ,700 13,400 20,000 26,700 33,400 40,100 46,700 53, ,800 15,600 23,400 31,200 38,900 46,700 54,500 62, ,900 17,800 26,700 35,600 44,500 53,400 62,300 71, ,000 20,000 30,000 40,100 50,100 60,100 70,100 80, ,100 22,300 33,400 44,500 55,600 66,800 77,900 89, ,200 24,500 36,700 49,000 61,200 73,400 85,700 97, ,400 26,700 40,100 53,400 66,800 80,100 93, , ,500 28,900 43,400 57,900 72,300 86, , , ,600 31,200 46,700 62,300 77,900 93, , , ,700 33,400 50,100 66,800 83, , , ,500 Revision 11 Sept 2014 DOC No DOC AXR. Page 13 of 32
14 Supplementary 38kV Network Charges Table 2.11 Business Demand Customer Supplementary 38kV Charges where 38kV MIC > 2500kVA and connected to circuits longer than 18km Km kva ,000 7,100 12,100 17,200 22,200 27,300 32,300 37,400 42, ,000 14,100 24,200 34,300 44,400 54,500 64,600 74,700 84, ,100 21,200 36,300 51,500 66,600 81,800 96, , , ,100 28,300 48,500 68,600 88, , , , , ,100 35,300 60,600 85, , , , , , ,100 42,400 72, , , , , , , ,100 49,500 84, , , , , , , ,200 56,500 96, , , , , , , ,200 63, , , , , , , , ,200 70, , , , , , , , ,200 77, , , , , , , , ,200 84, , , , , , , , ,200 91, , , , , , , , ,300 98, , , , , , , , , , , , , , , , ,000 Revision 11 Sept 2014 DOC No DOC AXR. Page 14 of 32
15 Notes on Business Demand Customer Connection Charges 1. The standard charge includes the appropriate transformer capacity charge and the direct cost of connection and metering. MV overhead lines, MV underground cables and trenching where carried out by ESBN are charged separately on a "euro per metre" ( /m) basis. A revenue allowance has been given where appropriate. 2. MV overhead line is charged on a "euro per metre" ( /m) basis. The /m for 3ph MV up to 5MVA is weighted to include 150 s AL,92 s SCA, 50 s CU and 50 s SCA based on total km of each conductor type used, above 5MVA the /m is based on 150's AL. The /m charge for 1ph is based on 50 s SCA. Both 1ph and 3ph /m charges are weighted to include bog, rock and standard ground conditions. 3. MV underground cable is charged on a "euro per metre" ( /m) basis, 3 x 70/185 s and 3 x 400's XLPE are separately shown. Trenching is not included and if carried out by ESBN is charged on a /m basis. 4. Additional charge where trenching (MV or LV) is carried out by ESBN. The charge is weighted for footpaths and roadways in concrete or bitmac. Granite footpaths not included. Separate charge is shown for trenching in grass. 5. The standard charge includes 38 kv and MV capacity charges. A supplementary charge is added if the entire MV circuit exceeds 7.0 km and MIC exceeds 500kVA. A supplementary charge is added if the entire 38kV circuit exceeds 18.0 km and MIC exceeds 2500kVA. Details on Table 2.10 and LV connections in the range 500 kva kva are possible but due to charges for MV/LV transformer capacity (as well as MV & 38 kv capacity charges) they are more costly. Details on Table The standard charge for 38kV connections is the same as the standard charge for the MIC level at MV and can be taken from the MV table. A supplementary charge must be added if the entire 38kV circuit length exceeds18.0 km and the MIC exceeds 2500 kva, details on Table A9. New 38kV Lines/Cables charged at 50%. 8. For MIC > 5MVA, any new 38kV/110kV network is chargeable as a capital contribution at 50% of Attributable Costs. The Attributable Cost of the 38kV/110kV network is determined as a proportion of the firm capacity of the station taken up by the customer. If the customer was taking up 60% of the station then the customer would be charged 50% of 60% of the cost of the 38kV/110kV lines / cables. e.g. MIC 15MVA, new 110kV line to new station required, station a 2x20MVA station with a firm capacity of 25MVA, customer charged 50% of 15/25ths (MIC/Firm Capacity 15MVA/25MVA) of the cost of the new 110kV line. Revision 11 Sept 2014 DOC No DOC AXR. Page 15 of 32
16 3. Distribution Use Of System (DUoS) Charges About this Section This Section sets out the charges that apply for use of the Distribution System by Connected Customers. These charges are normally passed on to the Customer s Electricity Supplier and are applied using rules approved by CER which are contained in the document titled Rules for Application of DUoS Tariff Group. The tables contained in the schedule below set out the current charges as they are applied to the various DUoS groupings. The charges in each table are not inclusive of VAT. Revision 11 Sept 2014 DOC No DOC AXR. Page 16 of 32
17 Schedule of Non- Maximum Demand DUoS Group Tariff Groups (DG1 to DG5b) Table 3.1 DUoS Group 1 (DG1) Urban Domestic Customers Charge Unit Standard Meter Day and Night Meter Standing Charge Per Customer per annum c c Per kwh 24 Hour N/A Unit Rates Per kwh Day N/A Per kwh Night Table 3.2 DUoS Group 2 (DG2) Rural Domestic Customers Charge Unit Standard Meter Day and Night Meter Standing Charge Per Customer per annum c c Per kwh 24 Hour N/A Unit Rates Per kwh Day N/A Per kwh Night Revision 11 Sept 2014 DOC No DOC AXR. Page 17 of 32
18 Table 3.3 DUoS Group 3 (DG3) Unmetered Connections inc. Public Lighting Charge Unit C Unit Rates Per kwh Table 3.4 DUoS Group 4 (DG4) local Authority Unmetered Connections inc. Public Lighting Charge Unit C Unit Rates Per kwh (ex. DG premium) 1 Special Notes for tariff groups DG3 and DG4 1. DUoS Group 3 applies to unmetered public lighting connections and other business connections 2 with loads up to and including 2kVA The DG4 Use of System tariff will apply to all unmetered public lighting and other unmetered load types where the registered customer is a local authority. Relevant Local Authorities include: Dublin Corporation, County Councils, Urban Councils, Borough Councils and the NRA. Public Lighting registered to Private Developers, Private Public Partnerships and Harbour and Port Authorities will continue to be billed on DG3 Use of System tariff. 3. The DG4 tariff is based on the DG3 tariff, and also incurs an additional charge in accordance with the agreement between ESB Networks and the City and County Managers Association in respect of additional costs incurred on public lighting installations incurred by ESB Networks on behalf of local authorities. 4. The load types covered by the DG4 tariff cover all Public Lights types including LEDs, PEDs, Bollards, Beacons, etc. 5. The DG4 tariff commenced on 1st January The DG4 tariff also incurs an additional premium in respect of additional costs incurred on public lighting installations. This premium is 0.01 c/kwh but it is currently being reviewed. See Notes above. 2 For example connections to street furniture, kiosks and bus shelters. 3 This is in accordance with the Rules for Application of DUoS Group approved by CER in September Public lighting loads and other business connections greater than 2kVA are metered. Revision 11 Sept 2014 DOC No DOC AXR. Page 18 of 32
19 Table 3.5 DUoS Group 5 (DG5) and DUoS Group 5b (DG5b) Low Voltage Business Customers (non Maximum Demand) Charge Unit Standard Meter Day and Night Meter Standing Charge Per Customer per annum c c Per kwh All Units N/A Unit Rates Low Power Factor Surcharge Per kwh Day N/A Per kwh Night Per kvarh Table 3.6 DUoS Group 5a (DG5a) Low Voltage Autoproducers MEC > MIC (non Maximum Demand) Charge Unit Standard Meter Day and Night Meter Standing Charge Per Customer per annum N/A N/A c c N/A Unit Rates Low Power Factor Surcharge Per kwh Day N/A Per kwh Night Per kvarh Revision 11 Sept 2014 DOC No DOC AXR. Page 19 of 32
20 Notes for tariff groups DG1, DG2, DG5, DG5a & DG5b: 1. The hours during which the day and night charges apply for non quarterhourly metered customers are controlled by time switches at the customer s premises. The day rate is applicable to kwh metered between 8.00 a.m. and p.m. (GMT). As no alterations are made to time switches at the beginning and end of summertime, the hours during the summer time are one hour later (i.e. 9.00am to 12.00am). For quarterhourly metered customers day rates apply 8.00 am to 11.00pm summer and winter. 2. The night c/kwh rates are applicable to night storage heating, which is separately metered and controlled by a time switch. 3. The published Standing Charges are per annum, actual charges are prorated per billing period. 4. For low voltage non-domestic customers, the low power factor surcharge applies to all kvarh recorded in any two monthly period if: The metered kvarh is more than one third of the metered kwh in any two monthly period. The charge is applicable to the kvarh in excess of one third of the kwh. The Low Power Factor Surcharge does not apply to customers with MEC>0. 5. For combined residential and business premises, DUoS Group 5 (DG5) rates will apply. 6. An Autoproducer (AP) is as defined in CER s Direction CER03/ DUoS Group 5 or DUoS Group 5b apply to low voltage APs and CHP producers (non Maximum Demand): With Maximum Import Capacity (MIC) > Maximum Export Capacity (MEC); or, Who have not bought out their connection agreement. Where such APs and CHPs have on-line interval metering installed, the DG5b tariff will apply; this means that the unit charges will be calculated based on netted consumption. Where such APs and CHPs do not have on-line metering installed the DG5 tariff applies. DUoS Group 5a applies to generators (including autoproducers) which have an MEC greater than the MIC and which have paid 100% of the connection costs. Revision 11 Sept 2014 DOC No DOC AXR. Page 20 of 32
21 Schedule of Maximum Demand Tariff Groups (DG6 to DG9b) Table 3.7 DUoS Group 6 (DG6) and DUoS Group 6b (DG6b) Low Voltage Business Customers (Maximum Demand) Charge Unit Standing Charge Per Customer per annum Capacity Charge Per kva of MIC per annum c Unit Rates Low Power Factor Surcharge Per kwh Day Per kwh Night Per kvarh Table 3.8 DUoS Group 6a (DG6a) Low Voltage Autoproducers MEC > MIC (Maximum Demand) Charge Unit Standing Charge Per Customer per annum N/A Capacity Charge Per kva of MIC per annum N/A c Unit Rates Low Power Factor Surcharge Per kwh Day Per kwh Night Per kvarh Revision 11 Sept 2014 DOC No DOC AXR. Page 21 of 32
22 Table 3.9 DUoS Group 7 (DG7) and DUoS Group 7b (DG7b) Medium Voltage Customers (Maximum Demand) Charge Unit Standing Charge Per Customer per annum Capacity Charge Per kva of MIC per annum c Unit Rates Low Power Factor Surcharge Per kwh Day Per kwh Night Per kvarh Table 3.10 DUoS Group 7a (DG7a) Medium Voltage Autoproducers MEC > MIC (Maximum Demand) Charge Unit Standing Charge Per Customer per annum N/A Capacity Charge Per kva of MIC per annum N/A c Unit Rates Low Power Factor Surcharge Per kwh Day Per kwh Night Per kvarh Revision 11 Sept 2014 DOC No DOC AXR. Page 22 of 32
23 Table 3.11 DUoS Group 8 (DG8) and DUoS Group 8b (DG8b) 38 kv Looped Customers (Maximum Demand) Charge Unit Standing Charge Per Customer per annum Capacity Charge Per kva of MIC per annum 5.21 c Unit Rates Low Power Factor Surcharge Per kwh Day Per kwh Night Per kvarh Table 3.12 DUoS Group 8a (DG8a) 38 kv Looped Autoproducers MEC > MIC (Maximum Demand) Charge Unit Standing Charge Per Customer per annum N/A Capacity Charge Per kva of MIC per annum N/A c Unit Rates Low Power Factor Surcharge Per kwh Day Per kwh Night Per kvarh Revision 11 Sept 2014 DOC No DOC AXR. Page 23 of 32
24 Table 3.13 DUoS Group 9 (DG9) and DUoS Group 9b (DG9b) 38kV Tailed Customers (Maximum Demand) Charge Unit Standing Charge Per Customer per annum Capacity Charge Per kva of MIC per annum 5.21 c Unit Rates Low Power Factor Surcharge Per kwh Day Per kwh Night Per kvarh Table 3.14 DUoS Group 9a (DG9a) 38kV Tailed Autoproducers MEC > MIC (Maximum Demand) Charge Unit Standing Charge Per Customer per annum N/A Capacity Charge Per kva of MIC per annum N/A c Unit Rates Low Power Factor Surcharge Per kwh Day Per kwh Night Per kvarh Revision 11 Sept 2014 DOC No DOC AXR. Page 24 of 32
25 Notes for Maximum Demand Tariff Groups (DG6 to DG9b) 1. DG6, DG6a and DG6b: The hours during which the day and night charges apply for non quarter-hourly metered customers are controlled by time switches at the customer s premises. The day rate is applicable to kwh metered between 8.00 a.m. and p.m. (GMT). As no alterations are made to time switches at the beginning and end of summertime, the hours during the summer time are one hour later (i.e. 9.00am to 12.00am). For quarterhourly metered customers day rates apply 8.00 am to pm summer and winter. 2. DG7, DG7a, DG7b, DG8, DG8a, DG8b, DG9, DG9a, DG9b: Night rates apply from pm. to 8.00 am summer and winter. 3. The low power factor surcharge applies when the metered kvarh is more than one third of the metered kwh in any two monthly period where NQH metering is installed or any monthly period where on-line interval (QH) metering is installed. The charge is applicable to the kvarh in excess of one third of the kwh for the billing period. The Low Power Factor Surcharge does not apply to customers with MEC>0. 4. The published Standing Charges and Capacity Charges are per annum, actual charges will be pro-rated per billing period. 5. In the event that the peak demand (in kva), exceeds the maximum import capacity (MIC), a surcharge of 6 x capacity charge rate x excess kva will apply in the billing period for NQH installations and 5 x capacity charge rate x excess kva for QH installations in the billing period, during which the MIC was exceeded. Please note that for autoproducers or generators, in the event that peak demand exceeds their MIC, the surcharge which will apply will be as per other customers in the DG group e.g. if autoproducer is DG6a, then the surcharge to apply will be as per DG6. 6. Where there are two connections at different voltages at the same connection point, i.e. to a single site, the relevant DUoS charges apply in full to each connection. 7. Tariff groups 6, 7, 8, 9 or 6b, 7b, 8b, 9b apply to APs and CHP Producers (MD) where: These APs and CHP producers have an MIC > MEC; or, These APs and CHP producers have not bought out their connection agreement. Where such APs and CHPs have on-line interval metering installed, the relevant DGb tariff will apply; this means that the unit charges will be calculated based on netted consumption. Where such APs and CHPs do not have on-line metering installed the relevant DG tariff applies. The relevant DGa tariff will apply to generators (including autoproducers) which have an MEC greater than the MIC and which have paid 100% of the connection costs). Revision 11 Sept 2014 DOC No DOC AXR. Page 25 of 32
26 4. Charges for Distribution Services and Third Party Damage About This Section This section lists the charges that apply for miscellaneous services requested by customers from ESBN. It also sets out the charges that apply where a third party damages ESB plant or equipment. Background This section summarises the background and the reasons for the application of Standard Charges for Distribution Services and Third Party Damage as follows: - ESBN provides a range of distribution services in addition to connections and metering services for supply companies. These services are usually initiated by the owner (or tenant) of the premises and include alterations to the method of connection and responding to no supply calls. - ESBN does not recoup the costs involved in the above additional services, either through the DUoS charges or the Schedule of Transactional Charges or the Charges for Connection to the Distribution System. In the interest of economic efficiency and all users of the Distribution System, ESB Networks needs to apply appropriate charges for these services. - ESBN is obliged to apply equality of treatment when responding to and carrying work for all users of the Distribution System. For this reason, the application of Standard Charges will ensure that all such users are required to pay the same amounts for the various types of additional services. - ESBN incurs substantial damages to underground cables, electrical equipment and overhead networks as a result of activities by excavation contractors, members of the public and other third parties. Such damages can have serious safety implications as well as compromising the continuity of supply and necessitating expensive repairs. It is necessary to charge for these repairs in order to recoup the costs involved and to discourage such damages in the future. Basis for Charges The Standard Charges are based on the average actual costs incurred in providing the services and/or the carrying out of the work involved. All work is carried out on the basis of the Least Cost Technically Acceptable Design. Revision 11 Sept 2014 DOC No DOC AXR. Page 26 of 32
27 Schedule of Distribution Service Charges Table 4.1 Schedule of Distribution Service Charges Service Type Description Basis for Charge Cost ( ) including VAT Service Alteration Alteration to an overhead or underground domestic service, at the request of the customer including an alteration necessitated by a request to relocate a meter. This charge also applies on alterations associated with the installation of External Wall Insulation. Cost of a typical new underground service 401 Re-wire at the meter / ESB main fuse Adjust the connections to the meter / ESB main fuse - necessitated by the customer making changes to his / her electrical installation. Average cost of carrying out this work 163 Fire Call Out Call out to a fire at the request of the fire brigade. The average Call Out duration 132 Single Customer Fault Call Out Re-design Housing Scheme Site Revisit Call out at the request of the customer in response to a no supply situation to replace the ESB main fuse between 11 pm and am. This charge also applies in all instances where the fault is found to be on the customer s side of the meter. Where ESB design staff are required to redesign or modify a housing scheme to accommodate additional units or a change in layout and/or where ESB Central Site staff have already patched in the developers original site layout map. This charge applies where ESB staff have to leave a site and return at a later date due to the customer s works being incomplete e.g. unfinished ducting or incorrectly installed meter box. The average Call Out duration As per agreement with the IHBA Average cost of the associated lost time Revenue Protection: Inspect and re-seal Where meter seals have been discovered to be broken (perhaps by a meter reader). ESB staff will attend the site, inspect meter for signs of interference, and where no interference is suspected reseal the meter 1. Average cost of the associated lost time 176 Call out to Replace damaged Meter Where a meter has been damaged and a replacement meter is required. Cost of time and material Where upon inspection of a site where the meter seals have been broken, there is evidence of probable interference the costs associated with the investigation and repair of equipment should be calculated and charged on a case by case basis. Revision 11 Sept 2014 DOC No DOC AXR. Page 27 of 32
28 Third Party Damage Underground Cables and Equipment Table 4.2 Third Party Damage UG Cables and Equipment Damage Type Description Basis for the Charge Cost ( ) excl. VAT 1 Minor Repair (LV or MV) 1,557 2 LV Mains cable 2, MV Cable LV 1 Phase Service Cable Average cost of carrying out this work 3, LV 3 Phase Service Cable 1,752 6 Replace Minipillar or Section Pillar (including excavation and reinstatement) 4,671 Third Party Damage Overhead Network Table 4.3 Third Party Damage Overhead Network Damage Type Description Basis for the Charge Cost ( ) excl. VAT 1 LV Overhead Service LV 3 Phase Mains 3, MV Overhead Network Replace LV Pole Average cost of carrying out this work 1,147 3,760 5 Replace Stay 697 Revision 11 Sept 2014 DOC No DOC AXR. Page 28 of 32
29 Notes on Service and Third Party Damage Charges 1. Charges will be adjusted on an annual basis in line with material costs and labour rates. 2. If an underground service is installed to replace an overhead one at the request of the owner of the property, the owner is required to excavate a trench (both inside and outside the site, as applicable) and provide ducting, all to ESBN specifications and reinstate fully. 3. Standard charges for third party damage to cables apply to LV and MV cables using typical excavation and reinstatement charges for tarmac concrete surfaces only. There will be situations where repair costs are not covered by standard charges, and in such situations individual costs will be collected. Examples of such instances include: - Damage to 38kV or higher voltage cables - Standard charges assume tarmac or concrete surfaces. Where other surfaces apply, e.g. cobble lock, granite paving, individual costs are required - Standard charges assume excavation of three metre trench cable repairs. Where the extent of damage exceeds this, individual costs are required - There may be other special requirements, e.g. traffic management, archaeological supervision of site etc., which are not covered by standard charges and these should be individually costed 4. The above standard charge for third party damage to LV service cable should be used for normal domestic single phase cables only and where the damage has occurred in a grassed area. In hard surface areas e.g. concrete or bitumen, the full actual cost of repairing the damage should be charged. 5. The above standard charges apply in the case of the specified damage types only. In the event of damage to other ESB assets, the full cost of repairs will be charged. Revision 11 Sept 2014 DOC No DOC AXR. Page 29 of 32
30 5. Transactional Charges for Additional Services to Use of System. About this section This section details the charges for services carried out on foot of special requests made by Electricity Suppliers. Standard Distribution Services covered by use of system will not be the subject of these charges. The rules under which these charges are applied are approved by CER and contained in a document titled Rules for Application of Transactional Charges for Additional Services to Use of System. The following conditions apply: - Must be in accordance with the Networks Code of Practice where relevant. - The charges in the Tables below are based on Normal Working hours. Specific times outside normal hours may not be guaranteed. Services carried out outside of normal working hours are subject to a charge equal to the appropriate charge in the table below multiplied by a factor of For non-standard de-energisations which involve additional work over the normal means of de-energisation (movement of any isolator, breaker, switch or the removal of any fuse), individually assessed charges will be quoted. A rights of entry (if required) is to be provided by the supplier. - The way in which some additional services are provided will depend on site-specific requirements and/or Supplier instructions. - All prices exclude VAT. Revision 11 Sept 2014 DOC No DOC AXR. Page 30 of 32
31 Transaction Charges for Energisation, De-Energisation and Metering Services Table 5.1 Transaction Charges Charge ( ) (excl VAT) No Type of Additional Service Charge Code 1 Visit to energise the connection point: For each visit to premises at the Supplier s request to energise a connection point. A Visit to de-energise: not actioned For each visit to a premises at the Supplier s request and the request is not actioned through no fault of DSO (cases specified in the Networks Code of Practice). A Visit to de-energise: For each visit to a premises at the Supplier s request for any reason, resulting in de-energisation by withdrawal of fuses. A Visit to disconnect: Where the User requests the disconnection of a site. A Visit to Read Meter (Special Read): Where the Supplier requests an unscheduled meter reading. A Major Meter Test: Visit and carry out major meter test A Check meter Accuracy A Meter Exchanges: From ST to DT - Single Phase Whole Current 1 From DT to ST - Single Phase Whole Current 2 From GP to MD (kwh Meter to MFM) MD meter for MFM meter plus signals. 9 Install/remove signals - existing MFM meter 10 Installation of an additional kwh meter and time-switch for NSH circuit 11 Reconfigure MFM meter A8 A9 A10 A A A A This charge is waived on the first occasion that a customer elects to switch from a single tariff meter to a double tariff meter at a specified connection point. The standard A8 charge applies to the second and subsequent meter changes at that connection point. 2 Also covers removal of NSH meter and time-switch. Revision 11 Sept 2014 DOC No DOC AXR. Page 31 of 32
32 Sliding Scale of Transactional Charges A sliding scale of charges applies to those situations where DSO undertakes multiple energisations, de-energisations or disconnections at the same site. Savings in travel time and job set-up time are reflected in a sliding scale of charges as listed below. Table 5.2 Sliding Scale of Transaction Charges Table 5.2 Sliding Scale of Transaction Charges No. of Meters at the same site A1 Visit to energise. Charge (excl VAT) A3 Visit to de-energise. Charge (excl VAT) A4 Visit to disconnect. Charge (excl VAT) 1 meter meters meters meters meters meters meters meters meters meters meters meters meters meters meters meters meters meters meters meters meters meters meters meters meters meters meters meters Revision 11 Sept 2014 DOC No DOC AXR. Page 32 of 32
Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd.
Networks ESB Networks Ltd Basis of Charges for Connection to the Distribution System Revision Date: 14/01/20010 Revision No.: 1 Document No: DOC-10129-AXQ Issued by: ESB Networks Ltd Approved by : CER
Pass Through Costs for Business Electricity Customers from 1 st October 2015
Pass Through Costs for Business Electricity Customers from 1 st October 2015 DOCUMENT TYPE: Information Note REFERENCE: CER 15/226 DATE PUBLISHED: 22 nd September 2015 The Commission for Energy Regulation,
POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends
POWER NETWORKS 2014-15 Electricity Network Tariffs and Charges and Future Price Trends August 2014 Power and Water Corporation Table of Contents 1 Business Characteristics... 3 2 2014 Network Price Determination...
NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM
NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM BY AUTHORISED PERSONS Effective from 1 October 2011 to 30 September
Conditions means the standard terms and conditions set out in this document;
October 2014 Conditions of Supply for Electricity SME Business Customers These are our terms and conditions which are applicable to Commercial Customers with tariffs in Duos Group DG1, DG2, DG 5 or DG
DISTRIBUTION CONNECTION
DISTRIBUTION CONNECTION POLICY Page 1/15 TABLE OF CONTENTS 1 Introduction... 3 2 Acceptance of requests for a connection... 3 2.1 Who can request a connection... 3 2.2 How to request a connection... 4
INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION
INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION February 2013 NOTE: If conflict exists between St. Thomas Energy s Conditions of Service and this document, the Conditions
Network Price List (excludes GST)
Network Price List (excludes GST) Effective from 1 July 2007 Monthly Monthly Monthly Network Network Network Energy Rates Step Rates Demand Capacity Capacity Price Network Price DLF Access Rates Rates
STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK
STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK This statement is effective from 1 April 2010 This statement is approved by the Gas and Electricity
NETWORK OPERATIONS. Siteworks Charging. From May 2014 - 1 -
NETWORK OPERATIONS Siteworks Charging From May 2014-1 - Table of Contents: NETWORK OPERATIONS... 1 TABLE OF CONTENTS:... 2 INTRODUCTION:... 3 GENERAL CONDITIONS:... 4 1. CONNECTION SERVICES... 5 2. COMMISSIONING
STATEMENT OF CHARGES FOR USE OF SP MANWEB s ELECTRICITY DISTRIBUTION NETWORK
STATEMENT OF CHARGES FOR USE OF SP MANWEB s ELECTRICITY DISTRIBUTION NETWORK This statement is effective from 1st October 2008 SP Energy Networks New Alderston House Dove Wynd Strathclyde Business Park
BGE/BE/TAC/0710. NQH Business electricity Terms and conditions
BGE/BE/TAC/0710 NQH Business electricity Terms and conditions These are our standard terms and conditions of NQH business electricity supply. As a NQH business customer you will be deemed to have accepted
Domestic Customer Tariff Breakdown - RoI Note this is approximate due to tariff and consumption variations
Guide to Electricity price formation in Ireland and Northern Ireland The numbers The average household consumes 4,300 kwh 1 of electricity per annum in Ireland and 4,100 in Northern Ireland. At an average
Daily Daily Network Network Network Energy Rates Step Rates Capacity. Price Rates Rates
Excludes GST Effective from 1 July 2010 Tariff Class Daily Daily Network Network Network Energy Rates Step Rates Capacity Capacity Price Rates Rates No. Network Price DLF Access Non-ToU Time of Use (ToU)
The Electrical Safety Regulation (pre and post 1 January 2014)
The Electrical Safety Regulation (pre and post 1 January 2014) The following table provides an overview comparison between the Electrical Safety Regulation 2002 (the ESR 2002) current as at 1 July 2013
ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV
1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled
ELECTRICITY [CH.194 35
ELECTRICITY [CH.194 35 ABACO ELECTRIC COMPANY LIMITED REGULATIONS (SECTION 60) [Commencement 15th May, 1972] 1. These Regulations may be cited as the Abaco Electric Company Limited Regulations. 2. In these
RETAIL ELECTRIC SERVICE TARIFF P.S.C. Md. No. 3 R Sheet 61
R Sheet 61 SCHEDULE R RESIDENTIAL SERVICE AVAILABILITY Available throughout the area served by the Cooperative to individual residences and individually metered dwelling units in multiple-occupancy buildings
BC Hydro. Electric Distribution System Cost of Service Study
BC Hydro Electric Distribution System Reimer Consulting Group Inc. Arnie Reimer May 7, 2010 Table of Contents 1. Executive Summary... 3 2. BC Hydro Electric Distribution System... 4 2.1. General Description...
Electricity & Gas Retail Markets Annual Report 2013
Electricity & Gas Retail Markets Annual Report 2013 DOCUMENT TYPE: REFERENCE: Information Paper CER/14/134 DATE PUBLISHED: 25 th June 2014 QUERIES TO: Adrienne Costello [email protected] The Commission
ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe
NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3
NETWORK PRICE LIST 2014/2015. Effective 1 July 2014
NETWORK PRICE LIST 2014/2015 Effective 1 July 2014 Document Amendment History Version No. Publication Date Comments 1.0 17 June 2014 AER Approved Pricing 2.0 15 July 2014 Updated Substation and Transformer
SCHUYLER DEPARTMENT OF UTILITIES SCHUYLER, NEBRASKA ELECTRIC RATES
SCHUYLER DEPARTMENT OF UTILITIES SCHUYLER, NEBRASKA ELECTRIC RATES TABLE OF CONTENTS SECTION I SECTION II SECTION III SECTION IV SECTION V SECTION VI SECTION VII SECTION VIII SECTION IX SECTION X SECTION
Distribution Substation Manual (DSM) Section I - Introduction
(DSM) Section I - Introduction March 2007 Document release information Client Project name Western Power Distribution Substation Manual Document number 3463019 Document title Revision status Introduction
BASIC NEC CODE RULES AND DESIGN PRACTICE
BASIC NEC CODE RULES AND DESIGN PRACTICE Wire Ampacity and Size Circuit Breaker Size 1. Maximum loading for any branch circuit is 80% of rating of circuit for ampacity of wire for any load. NEC 220-2,
Electricity & Gas Retail Markets Annual Report 2014
Electricity & Gas Retail Markets Annual Report 2014 DOCUMENT TYPE: REFERENCE: Information Paper CER/15/15112 DATE PUBLISHED: June 2015 QUERIES TO: [email protected] The Commission for Energy Regulation, The
ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1
ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 Design and Planning Specification for New Low Voltage Installations for Housing Developments 1. SCOPE This appendix to ENA
Statement of Charges for Use of Energetics Electricity Ltd s Distribution System
Statement of Charges for Use of Energetics Electricity Ltd s Distribution System st Effective from 1 April 2009 (Subject to Ofgem Approval) Energetics Electricity International House Stanley Boulevard
Connecting to the network information pack Version 2
Connecting to the network information pack Version 2 Updated: Contents 1.0 What is a new connection or connection alteration?... 3 2.0 Connection enquiry... 3 3.0 Connection application... 3 3.1 Processing
3. TYPES OF SERVICE AVAILABLE. 3.1 Scope
3. TYPES OF SERVICE AVAILABLE 3.1 Scope UI supplies 60 hertz, alternating current with different voltage and ampere ratings. Not all voltage and ampere ratings are available throughout the entire service
Standard Electricity Prices and Charges *
Standard Electricity Prices and Charges * South West Interconnected System Effective *All prices quoted include GST and are subject to change. IMPORTANT: Customers need to assess each tariff and any associated
How To Get A Power Line Extension
GUIDELINES FOR COMMERCIAL ELECTRIC SERVICE HOOKUP 1 Steps to Commercial Service Pay the Design Deposit Commercial Buildings: Up to 1, sq ft = $1,. 1, 5, sq ft = $2,. Over 5, sq ft = $3,. Commercial jobs
For the purpose of this Schedule the following words and phrases shall have the same meanings as assigned to them herein:
SCHEDULE OF STANDARD PRICES FOR ESKOM TARIFFS 1 APRIL 2014 TO 31 MARCH 2015 FOR NON-LOCAL AUTHORITY SUPPLIES, AND 1 JULY 2014 TO 30 JUNE 2015 FOR LOCAL AUTHORITY SUPPLIES 1. Standard prices The standard
Online Fixed Energy A Guaranteed Deal
Online Fixed Energy A Guaranteed Deal Online Fixed Price Energy July 2015 Offer Prices effective from 8th April 2014 Limited Offer subject to availability and may be withdrawn from sale at any time. Online
TRANSMISSION SERVICE RATE SCHEDULE Effective from 1 April 2015
TRANSMISSION SERVICE RATE SCHEDULE Effective from 1 April 2015 A SERVICE CONNECTION CHARGES Note : All charges in this Schedule are exclusive of GST. 1 Service Connection This includes cables, associated
Online Fixed Energy A Guaranteed Deal
Online Fixed Energy A Guaranteed Deal Online Fixed Price Energy August 2014 Offer Prices effective from 20th March 2013 Limited Offer subject to availability and may be withdrawn from sale at any time.
STANDARD ELECTRICITY PRICES AND CHARGES *
STANDARD ELECTRICITY PRICES AND CHARGES * SOUTH WEST INTERCONNECTED SYSTEM *Effective 1 July 2015 *All prices quoted include GST and are subject to change. IMPORTANT: Customers need to assess each tariff
ELECTRICITY PRICING INFORMATION. This list shows the terms that appear on electricity bills and what they mean:
ELECTRICITY PRICING INFORMATION GLOSSARY OF BILLING TERMS: The Government of Ontario requires all electricity distributors to issue standardized bills to their low- volume consumers, such as residential
Network Price List and Explanatory Notes
Essential Energy Network Price List (Excluding GST) Effective 1 July 2014 Tariff Code Obsolete tariffs on same rate Description Network Energy Energy Energy Energy Energy Energy Energy Peak Shoulder OffPeak
Building Electrical Infrastructure
Building Electrical Infrastructure Industrial & Commercial Connections, Industrial / Urban Residential Development, Asset Relocation, Street Lighting Our Company Our vision is to combine electrical engineering
Standard Electricity Prices and Charges*
Standard Electricity Prices and Charges* South West Interconnected System Effective 1 July 2012 *All prices quoted include GST and are subject to change. energy solutions you can use IMPORTANT: Customers
A least-cost electrification proposal for Kisiizi, Uganda Sten Bergman Sr. Energy Specialist, The World Bank
A least-cost electrification proposal for Kisiizi, Uganda Sten Bergman Sr. Energy Specialist, The World Bank 1. Introduction Kisiizi Hospital is a Church of Uganda "Private not-for-profit health care provider
For the purpose of this Schedule the following words and phrases shall have the same meanings as assigned to them herein:
SCHEDULE OF STANDARD PRICES FOR ESKOM TARIFFS 1 APRIL 2013 TO 31 MARCH 2014 FOR NON-LOCAL AUTHORITY SUPPLIES AND 1 JULY 2013 TO 30 June 2014 FOR LOCAL AUTHORITY SUPPLIES 1. STANDARD PRICES The standard
MASSACHUSETTS ELECTRIC COMPANY
MASSACHUSETTS ELECTRIC COMPANY Residential Regular R-1 Effective M.D.P.U. No.1119 March 1, 2008 Adjusted By: Transition Cost Adjustment March 1, 2008 Transmission Service Cost Adjustment March 1, 2008
INTRODUCTION Tariff Objective Factors
TARIFF INTRODUCTION Tariff is the schedule or rates framed for supply of electrical energy to various consumers. Objective is to distribute the equitably the cost of generation amongst various consumers
FIXED CHARGE: This is a cost that goes towards making the service available, including
ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer
How to Apply For Electricity Connection
How to Apply For Electricity Connection This handbook is published by SP PowerGrid Ltd in collaboration with SP Services Ltd June 2015 Procedures and requirements highlighted in this handbook are correct
Fixed Price Energy A Guaranteed Deal
Fixed Price Energy A Guaranteed Deal EnergySure COLLECTIVE MARK Fixed Price Energy January 2015 Prices effective from 7th June 2011 No price rises until January 2015 with our Fixed Price Energy January
NOTES ON AURORA LINE CHARGES FOR NETWORK DESIGNERS, CONSULTANTS AND ELECTRICAL CONTRACTORS
ov 26 OTES O AURORA LIE CHARGES FOR ETWORK DESIGERS, COSULTATS AD ELECTRICAL COTRACTORS 1. PURPOSE AD SCOPE OF THIS DOCUMET This document provides general advice for personnel involved in the alteration
Queensland Government Gazette
[555] Queensland Government Gazette Extraordinary PUBLISHED BY AUTHORITY ISSN 0155-9370 Vol. 366] Friday 18 July 2014 [No. 62 Electricity Act 1994 RETAIL ELECTRICITY PRICES FOR CUSTOMERS ON STANDARD RETAIL
DESCRIPTION DWG DESCRIPTION DWG
DESCRIPTION DWG DESCRIPTION DWG Ferroresonance 3451/1 3451/2 3451/3 Electro-magnetic Fields (EMF) 3462/1 HV & LV Insulators (Links) 3463/1 A ORIGINAL ISSUE B 14.07.09 APPROVED DATE J. Brooks 25.02.03 INDEX
Ladies and Gentlemen,
Ladies and Gentlemen, I would like to begin my speech by thanking deeply the Maniatakeion Foundation and especially the Chairman, Mr. Dimitris Maniatakis for his invitation and to congratulate him for
20th February 2015 ScottishPower Standard Domestic Tariff. Prices. Your domestic gas and electricity pricing information
20th February 2015 ScottishPower Standard Domestic Tariff Prices Your domestic gas and electricity pricing information How to find your electricity supply area See what supply area you are in by using
environment briefing02
PRODUCED BY THE SAFETY, HEALTH & ENVIRONMENT GROUP OF THE ENERGY NETWORKS ASSOCIATION - JULY 2006 environment briefing02 transporting electricity Overhead Lines or Underground Cables? Introduction The
MIDVAAL LOCAL MUNICIPALITY
MIDVAAL LOCAL MUNICIPALITY Determination of Charges Payable for Electricity July 2011 to Jun 2012 Tariff of Charges PART I: SUPPLY OF ELECTRICITY 1. BASIC CHARGES 1.1 Except as provided in 1.2 the following
Addendum #2 Contract UK-11-13
Addendum #2 Contract UK-11-13 Utilities Kingston Purchase and Replacement of Switchgear at Kingston Hydro Substation MS11 March 25, 2011 Delivered to: All RFP recipients Total number of pages: Nine (9)
AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES
overhead 23/11/04 2:28 PM Page 1 AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES ESB Code 9803203 overhead 23/11/04 2:28 PM Page 2 overhead 23/11/04 2:28 PM Page 3 Page 1 of 20
G8 - Contracts for Difference Metering
PUBLIC G8 - Contracts for Difference Metering EMRS Guidance EMR Settlement Limited Version 1.0 12 October 2015 CONTENTS Change Amendment Record...4 1. Introduction...5 2. Purpose...5 3. What is the Electrical
SA Power Networks Network Tariffs - Residential APPLIES TO USAGE FROM 1 JULY 2015
SA Power Networks Network Tariffs - Residential Low Voltage Residential - Single Rate DUOS excl TUOS excl PV JSO excl Total excl Total incl Block 1 Usage Rate $/kwh First 333.3 kwh/mth 0.0745 0.0300 0.0130
ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas
ENERGY NETWORKS ASSOCIATION Electricity Industry EMF Measurement Protocol for High Field Areas Contents 1 Introduction 1.1 Background 1.2 High Field Areas 2 High Field Area - Generation Businesses 2.1
CitiPower 2016 Pricing Proposal
CitiPower 2016 Pricing Proposal This page is intentionally left blank. 2 CitiPower 2016 Pricing Proposal Table of Contents 1 INTRODUCTION... 5 1.1 Our business...7 1.2 Network and metering tariffs...8
Phase Attribute Identification using GPS Technology
Phase Attribute Identification using GPS Technology Date 11 June 2009 John Sinclair Power Quality Manager Slide 1 Topics of Discussion Remote Phase Identification How it works Principals of operation Benefits
We Energies Electric Rates
We Energies Electric Rates for Michigan customers July 2015 The rates in this brochure reflect the authorized base rates of Wisconsin Electric Power Company, doing business under the name of We Energies,
Hyperlinks are Inactive
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
Online Fixed Energy A Guaranteed Deal
Online Fixed Energy A Guaranteed Deal Online Fixed Price Energy September 2016 Prices effective from 27th August 2015 Subject to availability and may be withdrawn from sale at any time. Online Fixed Price
MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING
Training Title MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Duration 5 days Training Date MV, HV and EHV Switchgear Testing & Commissioning 5 20 24 Apr $3,750 Dubai, UAE In any of the 5 star
Code of Practice Electricity transmission and distribution asset management. February 2009
Code of Practice Electricity transmission and distribution asset management February 2009 CONTENTS 1 PREFACE...4 2 APPLICATION AND OBJECTIVES...5 3 SCOPE...6 4 DEFINITIONS...7 5 DESIGN AND CONSTRUCTION...11
Approved Meter Sockets and Cabinets
Single Unit Residential Guide 1 PHASE, 120/240 VOLT S METERING (Metering sockets and cabinets are supplied by Customer). Outdoor meter mounting height is 1730 mm ( 5 8 ) to center of meter ± 100 mm ( 4
Standard Electricity Prices and Charges *
Standard Electricity Prices and Charges * South West Interconnected System *All prices are correct as at 1 September 2016. All prices quoted include GST and are subject to change. IMPORTANT: Customers
TARIFF SCHEDULE FOR THE 2014/2015 FINANCIAL YEAR
TARIFF SCHEDULE FOR THE 2014/2015 FINANCIAL YEAR MBOMBELA LOCAL MUNICIPALITY CHARGES FOR ELECTRICITY Mbombela Local Municipality hereby gives notice in terms of Section 75A of the Local Government Municipal
CODE OF PRACTICE NINE
CODE OF PRACTICE NINE CODE OF PRACTICE FOR THE METERING OF IMPORT AND EXPORT ACTIVE ENERGY VIA LOW VOLTAGE CIRCUITS FOR NON-HALF HOURLY SETTLEMENT PURPOSES Issue 1 Version 5.0 DATE: 26 November 2009 Balancing
Principles of Distribution charging:
Principles of Distribution charging: Electricity networks Introduction A three-stage approach involves the following steps: 1. The analysis and quantification of costs. The cost concept that is relevant
Document No Amendment No Approved By Approval Date Review Date NS112 DESIGN STANDARDS FOR INDUSTRIAL AND COMMERCIAL DEVELOPMENTS
Network Standard NETWORK Document No Amendment No Approved By Approval Date Review Date : : : : : NW000-S0041 1 Chief Engineer 26/10/2015 13/04/2018 NW000-S0041 NS112 DESIGN STANDARDS FOR INDUSTRIAL AND
A GUIDE TO. Connecting Renewable and CHP Electricity Generators to the Electricity Network
A GUIDE TO Connecting Renewable and CHP Electricity Generators to the Electricity Network A Guide to Connecting Renewable and CHP Electricity Generators to the Electricity Network October 2008 Guide prepared
Electricity Tariff Structure Review: Alternative Tariff Structures. A Consultation Paper
Electricity Tariff Structure Review: Alternative Tariff Structures A Consultation Paper CER/04/239 July 1 st 2004 SUMMARY Since 2000, the Commission has reviewed customer tariff levels on an annual basis.
PWC SCHEDULE OF DEPOSITS, FEES AND CHARGES. Table of Contents
PWC SCHEDULE OF DEPOSITS, FEES AND CHARGES Table of Contents I. DEFINITIONS... 2 II. DEPOSITS... 3 A. Establishment of Credit:... 3 B. Deposit Refunds:... 4 III. CUSTOMER SERVICE FEES AND CHARGES... 4
Monitoring your Energy Bills in Your Business
Fact Sheet #2 Monitoring your Energy Bills in Your Business In this fact sheet you will discover: What to look for on your energy bills to indentify problems and reduce costs. How to monitor and track
Power NI: tariff methodology
Research and Information Service Paper 12/14 23 September 213 NIAR 640-13 Aidan Stennett Power NI: tariff methodology 1 Introduction The following paper supplements Northern Ireland Assembly Research and
CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services
CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services SpecialistS IN ELECTRICAL SUPPORT SERVICES TO MINING, UTILITIES & industry Ampcontrol is committed to supporting our customers to maintain efficient
Getting Connected. A guide to how to apply for a New Connection to the Network
Getting Connected A guide to how to apply for a New Connection to the Network About Us SP Energy Networks is part of the ScottishPower Group of companies. We provide power on behalf of supply companies
POWER CORPORATION Requirements for Distribution Wires Access
POWER CORPORATION Requirements for Distribution Wires Access Contact Information: ENMAX Power Corporation 8820 52 St SE Phone: 514-3700 Calgary, Alberta Fax: 514-3719 T2C 4E7 Version 3.0 January 2005 i
AUSTIN UTILITIES. CHARACTER OF SERVICE: AC, 60 cycles, 120/240 Volt, three wire, single-phase; or 120 Volt, two wire.
AVAILABLE: Within established City Limits. AUSTIN UTILITIES Schedule (110) Issued 11/12/13 Supersedes (110) Issued 11/13/12 Sheet No. 1 of 1 RESIDENTIAL SERVICE APPLICABLE: To single-family residences
SCHEDULED ELECTRIC RATES
SCHEDULED RATES Volume lll,16 th Revision, Sheet No. 2.00 Amendment 508, Schedule TOC TABLE OF CONTENTS Item Rate Sheet No. Fuel Adjustment 3.00 GENERAL SERVICE General Service Gs-1 4.00 General Service
Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation
Medium Voltage (MV) & High Voltage (HV) Training Module 6 Date of the presentation Electrical System Basics MV vs. HV - Definitions Differences between USA and the rest of the world IEC define a high voltage
Ausgrid s Policy on Public Lighting - Contestable Projects. AUSPL CONPOL01 September 2012
Ausgrid s Policy on Public Lighting - Contestable Projects AUSPL CONPOL01 September 2012 Ausgrid s Policy on Public Lighting - Contestable Projects September 2012 Contents 1 OBJECTIVE... 3 2 SCOPE AND
ELECTRICITY NORTH WEST QUOTATION ACCURACY SCHEME FOR SMALL SCALE CONNECTIONS HOW TO CHALLENGE THE ACCURACY OF A CONNECTION CHARGE
ELECTRCTY NORTH WEST QUOTATON ACCURACY SCHEME FOR SMALL SCALE CONNECTONS HOW TO CHALLENGE THE ACCURACY OF A CONNECTON CHARGE Approved by the Gas & Electricity Markets Authority in accordance with Distribution
Contract for the supply of electricity to business premises
Conditions of supplying electricity These conditions apply if you are a business customer (which includes a Micro Business customer) and are using our electricity services to supply your Premises. (For
Contractor Connect Scheme Electrical Contractor and Worker Handbook
Contractor Connect Scheme Electrical Contractor and Worker Handbook January 2016 Document release information Document number 13553681 Document title Revision status Contractor Connect Scheme handbook
REVISED CONSUMPTIVE TARIFFS, RATES AND BASIC CHARGES FOR ELECTRICITY SERVICES, WATER AND SANITATION SERVICES AND SOLID WASTE MANAGEMENT SERVICES
ANNEXURE 4 REVISED CONSUMPTIVE TARIFFS, RATES AND BASIC CHARGES FOR ELECTRICITY SERVICES, WATER AND SANITATION SERVICES AND SOLID WASTE MANAGEMENT SERVICES 1. ELECTRICITY 1.1 General The proposed revisions
