1 WATER RIGHTS BUSINESS PROCESS MANAGEMENT SYSTEM PROJECT MANAGEMENT PLAN (PMP) EXECUTIVE SPONSORS: RENEE MARTINEZ, CHIEF INFORMATION OFFICE JOHN ROMERO, WATER RIGHTS DIVISION CHIEF BUSINESS OWNER WRAP MANAGERS AND EMPLOYEES PROJECT MANAGERS: MERCEDES ORTEGA ORIGINAL PLAN DATE: MARCH 01, 2012 REVISION DATE: REVISION:
2 Table of Contents PREPARING THE PROJECT MANAGEMENT PLAN PROJECT OVERVIEW EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECT FUNDING AND SOURCES CONSTRAINTS DEPENDENCIES ASSUMPTIONS INITIAL PROJECT RISKS IDENTIFIED PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE STAKEHOLDERS PROJECT GOVERNANCE STRUCTURE EXECUTIVE REPORTING SCOPE PROJECT OBJECTIVES CRITICAL SUCCESS FACTORS PROJECT DELIVERABLES AND METHODOLOGY PROJECT MANAGEMENT LIFE CYCLE PRODUCT LIFE CYCLE PROJECT WORK WORK BREAKDOWN STRUCTURE (WBS) SCHEDULE ALLOCATION -PROJECT TIMELINE PROJECT BUDGET PROJECT TEAM STAFF PLANNING AND RESOURCE ACQUISITION PROJECT LOGISTICS PROJECT MANAGEMENT AND CONTROLS RISK AND ISSUE MANAGEMENT INDEPENDENT VERIFICATION AND VALIDATION - IV&V SCOPE MANAGEMENT PLAN PROJECT BUDGET MANAGEMENT COMMUNICATION PLAN PERFORMANCE MEASUREMENT (PROJECT METRICS) QUALITY OBJECTIVES AND CONTROL CONFIGURATION MANAGEMENT PROCUREMENT MANAGEMENT PLAN PROJECT CLOSE ATTACHMENTS... ERROR! BOOKMARK NOT DEFINED. PAGE 1
3 Revision History Revision Number Date Comment 1.0 April 2, 2011 Draft PMP 2.0 PAGE 2
4 PREPARING THE PROJECT MANAGEMENT PLAN 1.0 PROJECT OVERVIEW 1.1 EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECT The Office of the State Engineer and Interstate Stream Commission, collectively, the Agency, are responsible for actively managing the water resources of New Mexico. On a daily basis the Agency serves water right owners across the state of New Mexico by processing water right claims and related transactions (changes of ownership, permit applications, well log submittals, certificates of construction, proof of beneficial use, well meter readings). Customer service and agency efficiency with respect to processing water rights transactions is inextricably tied to the performance of the Agency s water rights process and supporting information management systems. The purpose of this project is to redesign and automate our water rights administration business process using business process management software (BPMS). A BPMS is an integrated suite of software technologies that addresses business users' desire to see and manage work as it progresses across organizational boundaries. Successful completion of work requires the tight coordination of people, systems and information. A BPMS supports this full view of work by coordinating the interactions among people, systems and information, which are all equally important aspects of work. A BPMS supports process modeling, design, development and execution via the runtime environment in one package. 1.2 FUNDING AND SOURCES SOURCE AMOUNT ASSOCIATED RESTRICTIONS Laws of 2011, Chapter 179, Section 4 $246,000 AVAILABLE UNTIL JUNE 30, 2012 Laws of 2012, Chapter 19, Section 7 $220,000 AVAILABLE UNTIL JUNE 30, 2014 Laws of 2012, Chapter 19, Section 4 $222,250 AVAILABLE UNTIL JUNE 30, 2013 Laws of 2013, Chapter 19, Section 4 $28,000 AVAILABLE UNTIL JUNE 30, 2014 APPROVERS OSE/ISC STATE IT PROJECT CERTIFICATION COMMITTEE OSE/ISC OSE/ISC 1.3 CONSTRAINTS Constraints are factors that restrict the project by scope, resource, or schedule. PAGE 3
5 NUMBER DESCRIPTION 1 THE SPECIAL APPROPRIATIONS FOR THE PROJECT MUST BE USED PRIOR TO JUNE 30, SEE 1.2 FUNDING AND SOURCES, ITEM # DEPENDENCIES Types include the following and should be associated with each dependency listed. Mandatory dependencies are dependencies that are inherent to the work being done. D- Discretionary dependencies are dependencies defined by the project management team. This may also encompass particular approaches because a specific sequence of activities is preferred, but not mandatory in the project life cycle. E-External dependencies are dependencies that involve a relationship between project activities and non-project activities such as purchasing/procurement NUMBER DESCRIPTION 1 PROFESSIONAL SERVICES AGREEMENTS MUST BE ESTABLISHED TO ACQUIRE IMPLEMENTATION SERVICES FROM THE SOFTWARE VENDOR. A STATE PRICE AGREEMENT WILL BE IN PLAN BASED ON THE VENDOR S GSA PRICING TERMS AND CONDITIONS. TYPE M,D,E E 1.5 ASSUMPTIONS Assumptions are planning factors that, for planning purposes, will be considered true, real, or certain. NUMBER DESCRIPTION 1 INVOLVEMENT OF EMPLOYEES FROM ALL WRAP DISTRICT OFFICES WILL BE REQUIRED THROUGH OUT THE PROJECT TO MODEL, DESIGN AND AUTOMATE BUSINESS PROCESSES. 2 IN ORDER TO FOCUS IT APPLICATION DEVELOPMENT STAFF ON THE PROJECT, CHANGES TO CURRENT APPLICATIONS WILL BE PAGE 4
6 1.6 INITIAL PROJECT RISKS IDENTIFIED [Risk 1 Change Management] CHANGE MANAGEMENT Probability: HIGH Impact: MODERATE FOR EMPLOYEES, CONSTITUENTS AND IT MITIGATION STRATEGY: PROFESSIONALS. THE A STRUCTURED APPROACH TO CHANGE MANAGEMENT PROJECT WILL WILL BE FOLLOWED DURING THE COURSE OF THE INTRODUCE MANY PROJECT STARTING WITH THE DEVELOPMENT OF A CHANGES. CHANGE MANAGEMENT PLAN. CRITICAL CHANGE MANAGEMENT PLAN COMPONENTS WILL INCLUDE: 1. COMMUNICATIONS THAT INFORMS VARIOUS STAKEHOLDERS OF THE REASONS FOR THE CHANGE, THE BENEFITS OF SUCCESSFUL IMPLEMENTATION AS WELL AS THE DETAILS OF THE CHANGE, 2.EDUCATION, TRAINING AND POTENTIAL RE-CLASSIFICATION OF IT JOBS, 3. ALIGNMENT OF EMPLOYEE PERFORMANCE PLANS WITH NEW BUSINESS PROCESS PERFORMANCE GOALS, 4.EMPLOYEE COUNSELING (IF REQUIRED) TO ALLEVIATE ANY CHANGE RELATED FEARS, AND 5. MONITORING THE RESULTS OF THE PROJECT AND FINE-TUNING THE CHANGE MANAGEMENT APPROACH AS REQUIRED. CONTINGENCY PLAN: THE SYSTEM WILL NOT BE DEPLOYED UNTIL USER ACCEPTANCE TEST AND TRAINING ARE SUCCESSFUL [Risk 2 Cloud SaaS Experience] UNKNOWN TECHNICAL Probability: HIGH Impact: MODERATE AND IMPLEMENTATION ISSUE MAY IMPACT MITIGATION STRATEGY: SCHEDULE AND COSTS DUE TO INEXPERIENCE WITH IMPLEMENTING THIS CLOUD SOFTWARE AS A SERVICE SOLUTION THE OSE/ISC IS UTILIZING THE SERVICES OF AN IT RESEARCH AND ADVISORY COMPANY, GARTNER GROUP, TO LEARN AND APPLY BEST PRACTICES FOR THE EVALUATION, ACQUISITION AND IMPLEMENTATION OF CLOUD SOFTWARE AS SERVICE SOLUTIONS. CONTINGENCY PLAN: THE PROJECT MANAGER WILL IDENTIFY ISSUES THAT MAY IMPACT COST AND SCHEDULE ON A REGULAR BASIS AND ASSIGNED RESPONSIBILITY FOR RESOLVING THE ISSUES IS AN APPROPRIATE TIME PERIOD. PAGE 5
7 2.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE The Project Organization describes the roles and responsibilities of the project team. It also identifies the other organizational groups that are part of the project and graphically depicts the hierarchical configuration of those groups. It exists to clarify interaction with the project team. 2.1 STAKEHOLDERS NAME STAKE IN PROJECT ORG TITLE WATER RESOURCE ALLOCATION PROGRAM (WRAP) WRAP EMPLOYEES AND MANAGERS WILL USE THIS SYSTEM TO AUTOMATE THEIR WATER RIGHTS ADMINISTRATION BUSINESS PROCESS. THE SYSTEM WILL ALLOW USERS TO SEE AND MANAGE WORK AS IT PROGRESSES ACROSS ORGANIZATIONAL BOUNDARIES. OSE PROGRAM DIRECTOR DISTRICT MANAGERS WATER RIGHTS SPECIALISTS WATER RIGHTS ABSTRACT SPECIALISTS 2.2 PROJECT GOVERNANCE STRUCTURE DESCRIBE THE ORGANIZATIONAL STRUCTURE ORG CHART OSE-ISC IT Governance Committee Meeting Role: Project Investment, Project Portfolio Management Project Steering Committee Role: Project Planning & Oversight Project Team Role: Project Execution PAGE 6
8 2.2.2 DESCRIBE THE ROLE AND MEMBERS OF THE PROJECT STEERING COMMITTEE John Romero, WRAP Director, Role: Represents needs of the Water Resource Allocation Program as primary users of the system Rick DeSimone, WRAP Water Rights Abstracting Bureau Chief, Role: Represents needs of the Water Rights Abstracting Bureau as primary users of the system Vince Chavez, WRAP District VI (Santa Fe), Role: Represents needs of all WRAP district offices as primary users of the system Charles (Tink) Jackson, WRAP District IV (Deming), Role: Represents needs of all WRAP district offices as primary users of the system Renée Martínez, OSE/ISC Chief Information Office and IT Services Bureau Chief, Role: Manages IT resources for the project Mercedes Ortega, OSE IT Applications Manager, Role: Represents the IT technical staff who will be engaged on this project Lela Hunt, Public Information Officer, Role: Develops and implements the communications plan for the project Curtis Eckhart, Budget Director, Role: Manages Agency financial resources for the project ORGANIZATIONAL BOUNDARIES, INTERFACES AND RESPONSIBILITIES John Romero and Renée Martínez will be responsible for keeping the OSE/ISC IT Governance Committee apprised of project status and outcomes. All other agency programs will be interested on how and when the business process management software suite and business process improvement standards and methods will be available to their programs once this project is completed. 2.3 EXECUTIVE REPORTING See section above. 3.0 SCOPE 3.1 PROJECT OBJECTIVES BUSINESS OBJECTIVES NUMBER DESCRIPTION 1 IMPROVE BUSINESS AGILITY, THAT IS, TO SIGNIFICANTLY (BY 30% AND GREATER) REDUCE THE TIME AND EFFORT REQUIRED TO CHANGE BUSINESS PROCESSES AND INFORMATION SYSTEMS TO ADAPT TO EVOLVING BUSINESS RULES, REGULATIONS AND PRIORITIES 2 IMPROVE STAFF PRODUCTIVITY 3 INCREASE BUSINESS PROCESS TRANSPARENCY AND PERFORMANCE MANAGEMENT 4 REDUCE THE COST FOR SYSTEM MAINTENANCE AND FUTURE DEVELOPMENT PAGE 7
9 NUMBER DESCRIPTION 5 IMPROVE CONSTITUENT (WATER RIGHTS OWNERS, COURTS, LEGISLATORS) SATISFACTION WITH OSE SERVICES TECHNICAL OBJECTIVES NUMBER DESCRIPTION 1 PROVIDE FOR QUICK PROCESS AND RULE RECONFIGURATION WITH MINIMAL DOWNTIME 2 PROVIDE USER INTERFACES THAT ARE INTUITIVE, EASY TO LEARN AND USE, AND WEB-BASED 3 PROVIDE AUTOMATED WORKFLOW, BUSINESS RULES AND EXCEPTION HANDLING 3 PROVIDE REAL-TIME WORKFLOW STATE REPORTING 4 SHIFT IT WORKLOAD FROM PROGRAMMER TO BUSINESS ANALYST- RESOURCES 5 MAXIMIZE RE-USE OF EXISTING APPLICATION ASSETS 6 ADOPT INDUSTRY-STANDARD CLOUD INFRASTRUCTURE AND OPERATIONS PROCEDURES 7 PROVIDE CUSTOMER SELF-SERVICE FUNCTIONS WITH INTUITIVE, EASY TO LEARN AND USE, WEB-BASED USER INTERFACES 3.2 PROJECT EXCLUSIONS No exclusions. 3.3 CRITICAL SUCCESS FACTORS NUMBER DESCRIPTION 1 BUY-IN AND INVOLVEMENT OF BUSINESS USERS AND BUSINESS MANAGERS IS CRITICAL. THE PROJECT WILL RELY ON BUSINESS MANAGERS AND USERS TO DEVELOP EFFECTIVE FUTURE STATE BUSINESS PROCESSES AND TO AGREE ON STANDARD WAYS TO PROCESS WATER RIGHT APPLICATIONS. 2 DEDICATION AND FOCUS OF IT APPLICATIONS DEVELOPMENT STAFF IS CRITICAL. THIS PROJECT WILL BE CONSIDERED A HIGH PRIORITY OVER OTHER IT APPLICATION PROJECTS, DUE TO ITS STRATEGIC IMPORTANCE TO AGENCY OPERATIONS. 4.0 PROJECT DELIVERABLES AND METHODOLOGY 4.1 PROJECT MANAGEMENT LIFE CYCLE PAGE 8
10 Phase Summary of Phase Key Deliverables DEVELOP ROADMAP FOR CURRENT STATE ANALYSIS WATER RIGHTS TARGET-STATE ANALYSIS APPLICATION ARCHITECTURE ROADMAP ARCHITECTURE PLANNING & ENVISIONING *COMPLETE SOLUTION EVALUATION & SELECTION *COMPLETE IMPLEMENTATION PLANNING (RELEASE 1) RELEASE 1 CLOSE-OUT IMPLEMENTATION PLANNING (RELEASE 2) RELEASE 2 CLOSE-OUT IMPLEMENTATION PLANNING (RELEASE 3) RELEASE 3 CLOSE-OUT EVALUATE AND SELECT TECHNOLOGY SPECIFY APPLICATION SCOPE & RESOURCES NEEDED TO COMPLETE RELEASE 1 EVALUATE AND DOCUMENT RELEASE RESULTS SPECIFY APPLICATION SCOPE & RESOURCES NEEDED TO COMPLETE RELEASE 2 EVALUATE AND DOCUMENT RELEASE RESULTS SPECIFY APPLICATION SCOPE & RESOURCES NEEDED TO COMPLETE RELEASE 3 EVALUATE AND DOCUMENT PROJECT RESULTS RFI & RFI RESPONSE TECHNOLOGY PROOF OF CONCEPT BUSINESS CASE COST MODEL VENDOR AGREEMENTS PROJECT IMPLEMENTATION PHASE CERTIFICATION PROJECT MANAGEMENT PLAN PROJECT SCHEDULE USER AND EXTERNAL LOGON LICENSES BPMS TRAINING IV&V INITIAL ASSESSMENT CHANGE MANAGEMENT PLAN POST IMPLEMENTATION ASSESSMENT USER AND EXTERNAL LOGON LICENSES VENDOR AGREEMENTS PROJECT MANAGEMENT PLAN PROJECT SCHEDULE IV&V ASSESSMENT POST IMPLEMENTATION ASSESSMENT VENDOR AGREEMENTS PROJECT MANAGEMENT PLAN PROJECT SCHEDULE POST IMPLEMENTATION ASSESSMENT PROJECT CLOSE CERTIFICATION PROJECT MANAGEMENT DELIVERABLES Project Deliverables are work products or artifacts that are driven by the project management methodology requirements and standard project management practices regardless of the product requirements of the project DELIVERABLE 1 - PROJECT WORK PLAN PROJECT WORK PLAN DELIVERABLE ACCEPTANCE CRITERIA PROJECT PLAN AND REVISIONS TO BE APPROVED BY PROJECT STEERING COMMITTEE STANDARDS FOR CONTENT AND FORMAT MS PROJECT PAGE 9
11 QUALITY REVIEW AGENCY CIO WILL REVIEW FOR QUALITY, IV&V VENDOSE WILL REVIEW FOR QUALITY DELIVERABLE 2 PROJECT STATUS REPORTS MONTHLY PROJECT STATUS REPORT (CONTAINS COSTS, ISSUES AND RISKS) DELIVERABLE ACCEPTANCE CRITERIA - PROJECT STATUS REPORTS APPROVED BY PROJECT STEERING COMMITTEE STANDARDS FOR CONTENT AND FORMAT A STANDARD AGENCY TEMPLATE FOR ALL IT PROJECTS WILL BE USED QUALITY REVIEW PROJECT STEERING COMMITTEE WILL REVIEW FOR QUALITY DELIVERABLE APPROVAL AUTHORITY DESIGNATIONS DELIVERABLE NUMBER DELIVERABLE APPROVERS (WHO CAN APPROVE) DATE APPROVED PRJ-DEL-001 PROJECT MANAGEMENT PLAN (PMP) PROJECT STEERING COMMITTEE APRIL 14, 2012 (TARGET DATE) ALL SEE DELIVERABLES IN SECTION 4.1 ABOVE PROJECT STEERING COMMITTEE UPON REVIEW AND SIGN OFF FROM PROJECT STEERING COMMITTEE DELIVERABLE ACCEPTANCE PROCEDURE Deliverables will be reviewed by Project Manager and Project Team, then passed on to the Project Steering Committee for final approval. All defects will be communicated to the Contractor or Project Manager for correction before final approval and acceptance. 4.2 PRODUCT LIFE CYCLE Phase PLANNING & ENVISIONING *COMPLETE TECHNOLOGY SELECTION *COMPLETE Summary of Phase DEVELOP ROADMAP FOR WATER RIGHTS APPLICATION ARCHITECTURE EVALUATE AND SELECT TECHNOLOGY Key Deliverables CURRENT STATE ANALYSIS TARGET-STATE ANALYSIS ARCHITECTURE ROADMAP BPMS RFI BPMS TECHNOLOGY PROOF OF CONCEPT PROJECT BUSINESS CASE COST MODEL PAGE 10
12 Phase BPMS EDUCATION *COMPLETE DETERMINE DELIVERY AND OPERATIONS APPROACH *COMPLETE DOMESTIC WATER RIGHTS PROCESS MODELING, DESIGN, BUILD, TEST, DEPLOY (RELEASE 1) RELEASE 1 CLOSE-OUT NON- DOMESTIC WATER RIGHTS PROCESS MODELING, DESIGN, BUILD, TEST, DEPLOY (RELEASE 2) RELEASE 2 CLOSE-OUT NON- DOMESTIC WATER RIGHTS PROCESS MODELING, DESIGN, BUILD, TEST, DEPLOY (RELEASE 3) Summary of Phase EDUCATE IT STAFF ON NEW APPROACH TO APPLICATION DEVELOPMENT DETERMINE RESOURCE STRATEGY FOR PROJECT PROCESS & APPLICATION DEVELOPMENT LIFECYLE EVALUATE AND DOCUMENT RELEASE RESULTS PROCESS & APPLICATION DEVELOPMENT LIFECYLE EVALUATE AND DOCUMENT RELEASE RESULTS PROCESS & APPLICATION DEVELOPMENT LIFECYLE Key Deliverables REQUIREMENT SPECIFICATION TRAINING BUSINESS PROCESS DEFINITION TRAINING USE CASE SPECIFICATIONS TRAINING SOLUTION DELIVERY APPROACH SOLUTION OPERATIONS APPROACH COST MODEL PROCESS & APPLICATION REQUIREMENTS APPLICATION DESIGN APPLICATION BUILD TEST PLAN & RESULTS USER TRAINING PLAN & MATERIALS APPLICATION IN PRODUCTION POST IMPLEMENTATION ASSESSMENT USER AND EXTERNAL LOGON LICENSE SUBSCRIPTIONS PROCESS & APPLICATION REQUIREMENTS APPLICATION DESIGN APPLICATION BUILD TEST PLAN & RESULTS USER TRAINING PLAN & MATERIALS APPLICATION IN PRODUCTION POST IMPLEMENTATION ASSESSMENT PROCESS & APPLICATION REQUIREMENTS APPLICATION DESIGN APPLICATION BUILD TEST PLAN & RESULTS PAGE 11
13 Phase RELEASE 3 CLOSE-OUT Summary of Phase EVALUATE AND DOCUMENT PROJECT RESULTS Key Deliverables USER TRAINING PLAN & MATERIALS APPLICATION IN PRODUCTION POST IMPLEMENTATION ASSESSMENT CERTIFY PROJECT CLOSE TECHNICAL STRATEGY TECHNOLOGY SOLUTION: The purpose of this project is to redesign and automate our water rights administration business process using business process management software (BPMS). A BPMS is an integrated suite of software technologies that addresses business users' desire to see and manage work as it progresses across organizational boundaries. A BPMS supports this full view of work by coordinating the interactions among people, systems and information, which are all equally important aspects of work. A BPMS supports process modeling, design, development and execution via the runtime environment in one package. To support the process life cycle from modeling through execution to monitoring, the process model becomes the business process that is executed. Making the model fully executable and enabling business people to interact with business transactions running in the environment require a suite of bpm-enabling software technologies. The BPMS combines several bpm-enabling technologies, such as business process modeling, business activity monitoring (BAM), business rule engines, portals, web servicesbased integration and information management. A suite increases the effectiveness of these tools through interoperability and an explicit approach to coordinating workflow, including human tasks, "systematized" tasks, policies and information flows. The typical core bpm-enabling technologies that are architecturally integrated into a BPMS include the following: Orchestration engines coordinate the sequencing of activities and steps (systematized and manual, human workflow steps) according to the flows and rules in the process model. Human workflow management put controls around human activities to make them visible and more manageable. Business intelligence and analysis tools support the analysis of data produced during process execution. Capabilities range from reporting to online analytical processing (olap) analysis to graphical user dashboards. BAM systems do this in real time with proactive alerting. Complex-event processing helps discover activities and events of significance in the context that a process participates in to keep the process in synch with the changing conditions. Automated business process discovery provides the ability to discover current and best practices for existing processes. Rule engines execute rules that abstract business policies and decision tables from the underlying applications and make more-flexible process changes possible. PAGE 12
14 Business rule management aggregates collections of logically related rules and associates them to business policies and anticipated business scenarios to coordinate changes for quick process adaptation. Process metadata repository/registry contains process definitions, process components, process models, business rules and other process data that can be browsed by business and it professionals to foster greater understanding and to enable reuse across multiple domains. The orchestration engine uses this information at runtime to dynamically find and then bind to these process components. Simulation and optimization tools enable business managers to compare new process designs with operational performance. Scenarios are executed, altering resource constraints and business goals, to assess risk and display the financial and operational (that is, timeliness and quality) impact on the organization. Integration tools link the model to other system assets (data and logic) that support work steps. Portal/other user interface technology manages the interactions with users through user interfaces. Enterprise content management technology manages structured and unstructured information created and used in a process. Collaboration technologies, such as , instant messaging, virtual team rooms, whiteboards and social networks, support human collaboration within a process. Case management is a representation of a business activity and outcomes that becomes the current state of said activity. This is essential for tracing the completion of collaborative and unstructured knowledgebased processes. TECHNOLOGY TRANSITION: All IT application development staff in the Agency will attend 5 to 10 days of training on how to use the BPMS technologies to deploy business application solutions. Professional services from the software vendor will be acquired to provide for direct assistance and knowledge transfer to the agency IT application development staff during release 1 application development. The goal of the project is to gain the skills and knowhow from the software vendor during release 1 and to work more independently during releases 2 and 3. TECHNOLOGY OPERATIONS: The Agency has decided to use the software vendor s cloud software and platform as a service platform and the operational framework for this application. This allows the Agency to focus its IT resources on business process modeling, automation and monitoring versus infrastructure installation and maintenance. Appian warrants that the Agency s production instance of the Service Offering will be available ninety-nine and one-half percent (99.5%) of the time on a monthly basis 24x7, 365 days per year. Appian is responsible for all software and hardware upgrades and patches. Appian will provide development, testing and production environments to support the project PRODUCT AND PRODUCT DEVELOPMENT DELIVERABLES Product Deliverables are work products or artifacts that are driven by the product management methodology requirements and standard project management practices regardless of the product requirements of the project. PAGE 13
15 Deliverable 1 - Business Process and Application Implementation Plan (Release 1) Description: SCOPE AND RESOURCE (TIME, BUDGET, STAFF, BUSINESS PROCESS, SYSTEM INTEGRATION) PLAN FOR RELEASE 1 DELIVERABLE ACCEPTANCE CRITERIA - PROJECT STEERING COMMITTEE (PSC) REVIEW, COMMENT, DISCUSSION, AND APPROVAL STANDARDS FOR CONTENT AND FORMAT MS PROJECT FOR WORK PLAN MS WORD FOR IMPLEMENTATION PLAN QUALITY REVIEW - PROJECT MANAGER AND CIO REVIEW, THEN PSC REVIEW Deliverable 2 - Business Process & Application Requirements (Release 1) Description: REQUIREMENT SPECIFICATIONS FOR BUSINESS PROCESS, SYSTEM INTEGRATION, WORKFLOW, BUSINESS RULE, & USER INTERFACE Deliverable 3 - Change Management Plan Description: PLAN COMPONENTS: 1. AWARENESS CAMPAIGN, 2. TRAINING PLAN, 3. JOB ALIGNMENT, 3. EMPLOYEE PERFORMANCE PLAN ALIGNMENT, 4.EMPLOYEE COUNSELING, AND 5. PROJECT RESULTS MONITORING. DELIVERABLE ACCEPTANCE CRITERIA - PROJECT STEERING COMMITTEE (PSC) REVIEW, COMMENT, DISCUSSION, AND APPROVAL STANDARDS FOR CONTENT AND FORMAT TABLE OF CONTENTS FOR REQUIREMENTS ARE SPECIFIED BY THE AGENCY. QUALITY REVIEW - PROJECT MANAGER AND CIO REVIEW, THEN PSC REVIEW DELIVERABLE ACCEPTANCE CRITERIA - PROJECT STEERING COMMITTEE (PSC) REVIEW, COMMENT, DISCUSSION, AND APPROVAL STANDARDS FOR CONTENT AND FORMAT MS WORD. TEMPLATE FOR PLAN TO BE APPROVED BY PSC. QUALITY REVIEW - PROJECT MANAGER AND CIO REVIEW, THEN PSC REVIEW Deliverable 4 - Business Process & Application Design Specifications (Release 1) Description - DESIGN SPECIFICATIONS FOR BUSINESS PROCESS, SYSTEM INTEGRATION, WORKFLOW, BUSINESS RULE, & USER INTERFACE DELIVERABLE ACCEPTANCE CRITERIA - PROJECT STEERING COMMITTEE (PSC) REVIEW, COMMENT, DISCUSSION, AND APPROVAL STANDARDS FOR CONTENT AND FORMAT TABLE OF CONTENTS FOR DESIGN SPECIFICATIONS ARE SPECIFIED BY THE AGENCY. QUALITY REVIEW - PROJECT MANAGER AND CIO REVIEW, THEN PSC REVIEW Deliverable 5 - Business Process & Application Build & Demonstration (Release 1) Description - SOFTWARE DEVELOPMENT AND CONFIGURATION OF DELIVERABLE ACCEPTANCE CRITERIA - PROJECT STEERING COMMITTEE (PSC) REVIEW, COMMENT, DISCUSSION, AND APPROVAL PAGE 14
16 BUSINESS PROCESS, SYSTEM INTERFACES, WORKFLOW, BUSINESS RULES, & USER INTERFACES STANDARDS FOR CONTENT AND FORMAT N/A QUALITY REVIEW - PROJECT MANAGER AND CIO REVIEW, THEN PSC REVIEW Deliverable 6 Business Process & Application User Acceptance & Training (Release 1) DESCRIPTION USER ACCEPTANCE TEST PLAN, SCRIPTS AND RESULTS; USER TRAINING PLAN, SCHEDULE & MATERIALS DELIVERABLE ACCEPTANCE CRITERIA - PROJECT STEERING COMMITTEE (PSC) REVIEW, COMMENT, DISCUSSION, AND APPROVAL STANDARDS FOR CONTENT AND FORMAT MICROSOFT WORD, EXCEL AND PROJECT USED FOR TRAINING AND TESTING DOCUMENTS AND SCHEDULE. QUALITY REVIEW - PROJECT MANAGER AND CIO REVIEW, THEN PSC REVIEW Deliverable 7 Business Process & Application Deployment (Release 1) DESCRIPTION USERS ARE GIVEN ACCOUNTS AND COACHED ON HOW TO USE THE SYSTEM. DAILY POST IMPLEMENTATION MEETINGS ARE HELD TO DISCUSS ISSUES AS THEY SURFACE DELIVERABLE ACCEPTANCE CRITERIA ALL FUNCTIONS ARE WORKING AS SPECIFIED STANDARDS FOR CONTENT AND FORMAT MS WORD AND EXCEL USED TO DOCUMENT POST IMPLEMENTATION ISSUES QUALITY REVIEW - PROJECT MANAGER AND CIO REVIEW, THEN PSC REVIEW DELIVERABLE APPROVAL AUTHORITY DESIGNATIONS DELIVERABLE NUMBER DELIVERABLE APPROVERS (WHO CAN APPROVE) DATE APPROVED ALL ALL AGENCY CIO, RENEE MARTINEZ ON BEHALF OF THE PROJECT STEERING COMMITTEE DELIVERABLE ACCEPTANCE PROCEDURE The Project Manager will review and comment on each deliverable as to conformance with requirements and acceptance criteria. The Agency CIO will them comment on each deliverable as to conformance PAGE 15
17 with requirements and acceptance criteria. A summary of each deliverable will be presented to the Project Steering Committee for comment and approval. 5.0 PROJECT WORK 5.1 WORK BREAKDOWN STRUCTURE (WBS) Identifier Work Package Description Definition/Objective Milestone/Deliverable 1.0 Planning & Envisioning *Complete 2.0 Solution Evaluation & Selection *Complete 3.0 Solution Implementation Planning- Release Solution Implementation Design & Build Release Solution Implementation Deployment Release 1 Develop Roadmap for Future Water Rights Application Evaluate and Select Technology Develop implementation plan (scope, schedule, budget, staff) Develop process and system design specifications and software builds Test solution, train users, deploy solution Current State Analysis Target-State Analysis Architecture Roadmap RFI & RFI Response BPMS Technology Proof of Concept Business Case Cost Model Implementation Plan & Schedule Process-System Design Specification & Build Out Process- System Solution in Place 5.2 SCHEDULE ALLOCATION -PROJECT TIMELINE The latest project work plan, in MS Project format, is provided below as an inserted object. 5.3 PROJECT BUDGET PROJECT PHASE PROJECT MILESTONE TARGET DATE BUDGET Implementation Establish Price and Purchase Agreements with Vendors 4/30/2012 $0 Implementation Certify Project 4/30/2012 $0 Implementation Purchase User and External Logon Licenses (Year 1) 6/30/2012 $428,000 Implementation Conduct Release 1 Implementation Plan Engagement 7/15/2012 $38,000 Implementation Conduct Training (5 Day, On-Site) 7/15/2012 $32,250 Implementation Specify Process & Application Requirements (Release 1) 8/31/2012 $10,000 Implementation Design Application (Release 1) 11/30/2012 $10,000 PAGE 16
18 PROJECT PHASE PROJECT MILESTONE TARGET DATE BUDGET Implementation Build Application (Release 1) 3/31/2013 $20,000 Implementation Specify Process & Application Requirements (Release 2) 3/31/2013 $0 Implementation Test, User Training and Deploy Application (Release 1) 6/30/2013 $0 Implementation Independent Verification and Validation Service (Year 1) 6/30/2013 $8,000 Implementation Purchase User and External Logon Licenses (Year 2) 4/30/2013 $142,000 Implementation Design, Build, Test, Deploy Release 2 and Release 3 6/30/2014 $20,000 Implementation Independent Verification and Validation Services (Year 2) 6/30/2014 $8, PROJECT TEAM PROJECT TEAM ORGANIZATIONAL STRUCTURE Project Manager (Agency, Contractor) Application Developers (Process Model, Workflow, User Interface, Business Rules, System Integration) BPMS Vendor (Implementation Guidance, Training, Knowledge Transfer) IT Infrastructure Experts (Cloud Platform Network and System Integration) Program Staff (Process Model, Workflow, User Interface, Business Rules, System Integration) PAGE 17
19 5.4.2 PROJECT TEAM ROLES AND RESPONSIBILITIES ROLE RESPONSIBILITY NAME FUNCTIONAL AREA Project Sponsor Oversee Project Renée Martínez, John Romero Project Manager Manage Project Mercedes Ortega Sanchita Gupta IT WRAP IT VENDOR Contract Administrator Manage Contracts Marcos Mendiola ISC Water Rights District Managers Business Process Management Expertise Jess Ward Tink Jackson WRAP Andrea Mendoza Vince Chavez Tim Farmer Water Rights Specialists (District Offices) Business Process Expertise David Andersen Katherine Behrendsen WRAP Elisa Dominguez Bill Duemling Andrew Erdmann, Jennifer Grado Juan Hernandez Savannah Lindsay Yolanda Mendiola Joseph Montoya Mark Munoz Louisa Paiz Yvette Quintana Sue Raffay Doug Rappuhn Nancy Riley Sarah Rodriguez Priscilla Sanchez Lois Turnage Jerold Welton Water Rights Abstracting Specialists Business Process Expertise Sylvia Lucero Joanne Koferl WRAP Rick DeSimone PAGE 18
20 ROLE RESPONSIBILITY NAME FUNCTIONAL AREA IT Business Analyst Design Process Models, Specify Application Design, Plan and Conduct User Acceptance Test, Plan and Conduct User Training Jina Lindsay IT IT Applications Development Specialist Design, Build, Test and Deploy Application Components Michael Mackenzie Diana Hardy Sarah Balch IT IT Infrastructure Specialist Support Agency Network Integration with Cloud Platform John Buchser IT 5.5 STAFF PLANNING AND RESOURCE ACQUISITION Complete the chart below identifying the project team members and details concerning their project commitment. Project staff should include State, Contract, Customer (Business Owner), or Vendor team members PROJECT STAFF Resource Cost Estimate Est. Hours Availability Skill Set Work Product/Deliverable Contractor-Project Manager $10, % PM Expertise Project Work Plan & Status Reports Contractor- BPMS Application Developer $68, % Software Development System Specifications and Software Contractor-Training Specialist $30, % Training Expertise System Training Plan & Materials Agency Project Manager N/A % PM Expertise Project Work Plan & Status Reports Agency Project Sponsor N/A 100 5% Business Management Project Steering Committee N/A 30 10% Program Management Agency Functional Experts N/A 1,000 50% Functional Expertise Project Status Report, Approve Deliverables Approve Deliverables Process & System Requirements, Design and Build Agency IT Experts N/A 4,000 80% IT Expertise Process & System Requirements, Design, Build, Deployment $108,000 5,930 PAGE 19
21 5.5.2 NON-PERSONNEL RESOURCES Use this section to list services or product (HW/SW and such) needed for project Resource Cost Estimate Estimated units/hours Availability Source Work Product/Deliverable Software license subscriptions (5 years) $570, named users, 160,000 external customer logons per year 24x7, 99.99% availability Appian, Inc. Hardware and Software Development, Test and Production Environments 5.6 PROJECT LOGISTICS Project work will be conducted primarily in the Santa Fe and Albuquerque offices with IT staff working directly with WRAP staff. Web and video-conferencing tools will be used to involve project team members who are located in other WRAP district offices PROJECT TEAM TRAINING Resource Cost Estimate Estimated Hours Availability Skill Set Work Product/Deliverable IT Business Analysts, IT Applications Developers, Program Business Analysts $38, % Appian BPMS Release 1 Process and System Model, Design, Build, Test, Deploy 6.0 PROJECT MANAGEMENT AND CONTROLS 6.1 RISK AND ISSUE MANAGEMENT RISK MANAGEMENT STRATEGY This project has minimal technical and business risks as noted in Section 1.6. The Project Steering Committee is minimizing risk by meeting monthly to address issues and risks. Also an iterative process and system design, build, test and deploy process will be used PROJECT RISK IDENTIFICATION Risks will be identified through periodic assessments, project reports, and meetings PROJECT RISK MITIGATION APPROACH A mitigation plan will be developed for all risks rated with a high probability of occurrence and a medium or high impact. The following information will be carried in each monthly project status report. Major Project Risks: No. Description Probability Impact Trigger Mitigation Actions Being Taken PAGE 20
22 6.1.4 RISK REPORTING AND ESCALATION STRATEGY Risks will be reported on monthly status reports and reviewed monthly by the project steering committee. Risks will be escalated per the direction of the Project Steering Committee PROJECT RISK TRACKING APPROACH Please see response to item above ISSUE MANAGEMENT Internal Issue Escalation and Resolution Process A three tier issue escalation process will be followed. The project team will identify and track issues on an ongoing basis. Issues that cannot be resolved at the project team level will be escalated to the Project Steering Committee which will meet monthly to in-part address outstanding issues. Issues that cannot be resolved by the Project Steering Committee will be addressed by the Agency IT Governance Committee. The Project Manager will manage issue resolution assignments just like other project tasks External Issue Escalation and Resolution Process Please see response to item above. 6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V The services of a qualified IV&V vendor, with an active State of New Mexico IT Price Agreement, will be retained to conduct an initial assessment and a follow-up assessment after release 1 of the application is deployed into production. 6.3 SCOPE MANAGEMENT PLAN CHANGE CONTROL Change Control Process CHANGE CONTROL Change Control Process The project steering committee will review and decide on any significant changes requested by the project team Change Control Board (CCB) The project steering committee will serve as the CCB Change Control Board (CCB) The project steering committee will serve as the CCB if necessary. PAGE 21
23 6.4 PROJECT BUDGET MANAGEMENT BUDGET TRACKING Budget tracking is the responsibility of the project manager with oversight by the Project Steering Committee. The following information will be carried in each monthly project status report. Financial Summary: Project Budget: $ Project Expenditures to Date: $ Project Expenditures Estimate to Complete: $ Projected Variance: $0 6.5 COMMUNICATION PLAN COMMUNICATION MATRIX A formal communication plan and matrix will be developed as part of the Project Change Management Plan. Communications that informs various stakeholders of the reasons for the change, the benefits of successful implementation as well as the details of the change will be planned and implemented as appropriate times and intervals STATUS MEETINGS Weekly project team status meetings will be held. Monthly Project Steering Committee meetings will be held PROJECT STATUS REPORTS Project status reports will be generated monthly using the standard Agency IT project status report template. PAGE 22
24 6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS) BASELINES Project Area Category Measure All Schedule Deliverables received on schedule Deliverables approved on schedule All Cost Deliverable and product costs do not exceed budget All Quality Deliverables meet specifications METRICS LIBRARY Monthly Project Status Reports will document any and all variances on schedule, cost and quality. An electronic file of all status reports will be established and will serve as the project metrics library. 6.7 QUALITY OBJECTIVES AND CONTROL Quality Management includes the processes required to ensure that the project will satisfy the needs for which it was undertaken. It includes all activities of the overall management function that determine the quality policy, objectives, quality assurance, quality control, and quality improvement, within the quality system. If a separate Quality Plan is used, include a high level summary in this document and refer to the appropriate appendix QUALITY STANDARDS Describe the agency, industry or regulatory project performance standards that will be followed and assessed by the project. These quality standards will be used to assess whether the quality objectives were achieved. Identify each of the project quality standards that are directly related to the project and not to the performance of the actual product and/or service. For each quality standard, identify the tracking tool or measure such as number of project reviews or Project Status. No. Quality Standard Tracking Tool or Measure 1 A project management plan is in place and revised as needed Verification by Project Steering Committee 2 Project budget and schedule variances are reported to the OSE/ISC IT Governance Committee Verification by Project Steering Committee PAGE 23
25 6.7.2 PROJECT AND PRODUCT REVIEW AND ASSESSMENTS Review Type Quality Standard Tools Reviewer Reports Requirements Approved by all Project Stakeholders Requirements Document with Stakeholder Signature Page Project Sponsors, Project Steering Committee Same as Tool Plans Approved by all Project Steering Committee Members (PSC) Plan Documents with PSC Signature Page Project Sponsors, Project Steering Committee Same as Tool Milestones Approval to Proceed from Project Steering Committee Monthly Project Status Reports Project Sponsors, Project Steering Committee Same as Tool Testing All Deficiencies Corrected User Acceptance Test Document with Project Sponsor Signature Page Project Sponsors Same as Tool AGENCY/CUSTOMER SATISFACTION The project manager should assess the on-going sense of the customer agency about how they feel the project is going, and how team members are acting on the project. This feedback would be helpful to the success of the project and the professional growth of the project team members. The Post-Implementation Evaluation report will report feedback from stakeholders. Examples: Areas of feedback When How Often Agency awareness Quality of communications Manages project tasks Productive Meetings PRODUCT DELIVERABLE ACCEPTANCE PROCESS The process specified in the State of New Mexico standard IT professional services agreement will be followed for all products delivered during the project, whether vendor generated or Agency generated. 6.8 CONFIGURATION MANAGEMENT VERSION CONTROL The Agency will adopt a file naming convention that specifies the version of all artifacts within the project document repository. PAGE 24
26 6.8.2 PROJECT REPOSITORY (PROJECT LIBRARY) The Agency will manage and make available all deliverables in a electronic repository with open access for the Agency to review. 6.9 PROCUREMENT MANAGEMENT PLAN The Agency budget director, contracts manager, general counsel and CIO will collaborate on all procurements to support the project. A procurement plan is already in place. The Agency will solicit proposals for IV&V professional services from vendors on the State IT Price Agreement. Competing proposals will be compared and proposals that represent the greatest value to the Agency will be selected PROJECT CLOSE 7.1 ADMINISTRATIVE CLOSE The Agency Project Steering Committee will determine when to close the project based on a review of project objectives once all project tasks have been completed or a decision to stop to project has been made. The Project Steering Committee will inform the Agency IT Governance Committee of their decision to close the project and will present a summary of the project. 7.2 CONTRACT CLOSE Contract close is similar to administrative close in that it involves product and process verification for contract close. PAGE 25
ORIGINAL PLAN DATE: MARCH 1, 2012 REVISION DATE: REVISION:
WATER RIGHTS BUSINESS PROCESS MANAGEMENT SYSTEM PROJECT CHARTER FOR CERTIFICATION EXECUTIVE SPONSORS: RENEE MARTINEZ, CHIEF INFORMATION OFFICE JOHN ROMERO, WATER RIGHTS DIVISION CHIEF BUSINESS OWNER WRAP
More informationMNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
More informationProgram Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
More informationDepartment of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
More information<name of project> Software Project Management Plan
The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor
More informationPROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
More informationPHASE 8: IMPLEMENTATION PHASE
PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the
More informationPHASE 1: INITIATION PHASE
PHASE 1: INITIATION PHASE The Initiation Phase begins when agency management determines that a business function requires enhancement through an agency information technology (IT) project and investment
More informationPHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
More informationManag. Roles. Novemb. ber 20122
Information Technology Manag gement Framework Roles and Respo onsibilities Version 1.2 Novemb ber 20122 ITM Roles and Version History Version ed By Revision Date Approved By Approval Date Description of
More informationProject Type Guide. Project Planning and Management (PPM) V2.0. Custom Development Version 1.1 January 2014. PPM Project Type Custom Development
Project Planning and Management (PPM) V2.0 Project Type Guide Custom Development Version 1.1 January 2014 Last Revision: 1/22/2014 Page 1 Project Type Guide Summary: Custom Development Custom software
More informationProgram Management Professional (PgMP) Examination Content Outline
Program Management Professional (PgMP) Examination Content Outline Project Management Institute Program Management Professional (PgMP ) Examination Content Outline April 2011 Published by: Project Management
More informationMinnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
More informationBest Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
More informationPHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
More informationBusiness Continuity Position Description
Position Description February 9, 2015 Position Description February 9, 2015 Page i Table of Contents General Characteristics... 2 Career Path... 3 Explanation of Proficiency Level Definitions... 8 Summary
More informationPositive Train Control (PTC) Program Management Plan
Positive Train Control (PTC) Program Management Plan Proposed Framework This document is considered an uncontrolled copy unless it is viewed online in the organization s Program Management Information
More information- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and
More informationPHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
More informationITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
More informationPROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
More informationTemplate K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
More informationHow To Write A Project Management Plan
Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents
More informationATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES
1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through
More informationU.S. Department of Education Federal Student Aid
U.S. Department of Education Federal Student Aid Lifecycle Management Methodology Stage Gate Review Process Description Version 1.3 06/30/2015 Final DOCUMENT NUMBER: FSA_TOQA_PROC_STGRW.NA_001 Lifecycle
More informationStepping Through the Info Security Program. Jennifer Bayuk, CISA, CISM
Stepping Through the Info Security Program Jennifer Bayuk, CISA, CISM Infosec Program How to: compose an InfoSec Program cement a relationship between InfoSec program and IT Governance design roles and
More informationINTRODUCTION. Page 1 of 16
INTRODUCTION CALIFORNIA STATE TEACHERS RETIREMENT SYSTEM REQUEST FOR QUOTE JAMA LICENSING AND SERVICES RFQ NUMBER 201204 Offer Due Date: July 23, 2013, 2:00 p.m. Pacific Time (PT) The California State
More informationInformation Technology Governance Overview and Charter
Information Technology Governance Overview and Charter Prepared by: Project #: Date submitted Document version: IT Governance Charter v03.05.2012 1.0 48.0 - Page 1 of 34 Document History Version Date Author
More informationDraft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing
STATE OF MICHIGAN SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing Executive Summary The State of Michigan has dedicated integrated team of resources for the
More informationITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...
More informationSTATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840
MARYLAND STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 Bobbie S. Mack, Chairman David J. McManus, Jr., Vice Chairman Rachel T. McGuckian Patrick H. Murray Charles
More informationPHASE 5: DESIGN PHASE
PHASE 5: DESIGN PHASE During the Design Phase, the system is designed to satisfy the requirements identified in the previous phases. The requirements identified in the Requirements Analysis Phase are transformed
More informationIT Project Management Practices Guide
IT Project Management Practices Guide Introduction The IT Project Management Practices Guide (Guide) contains a repeatable, institutionwide approach for the management of application development and/or
More informationDallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010
Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning
More informationPMO Starter Kit. White Paper
PMO Starter Kit White Paper January 2011 TABLE OF CONTENTS 1. ABOUT THE PMO STARTER KIT...3 2. INTRODUCTION TO THE PMO STARTER KIT WHITE PAPER...3 3. PMO DEVELOPMENT ROADMAP...4 4. PLAN PHASE...5 4.1 CREATE
More informationLocation: [North America] [United States] [Home Working, United States]
Architect II Location: [North America] [United States] [Home Working, United States] Category: Information Technology Job Type: Fixed term, Full-time PURPOSE OF POSITION: The Architect II role is expected
More informationKMS Implementation Roadmap
KMS Implementation Roadmap Sample Excerpt Prepared by: The Knowledge Compass, Inc. TABLE OF CONTENTS 1. EXECUTIVE SUMMARY 5 1.1 Overview 5 1.2 Project Goals & Objectives 5 1.3 Implementation Approach 5
More informationProject Management Guidelines
Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.
More informationCrosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
More informationOE PROJECT CHARTER TEMPLATE
PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,
More informationPMP Examination Tasks Puzzle game
PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in
More informationGuide to Enterprise Life Cycle Processes, Artifacts, and Reviews
Department of Health and Human Services Centers for Medicare & Medicaid Services Center for Consumer Information and Insurance Oversight Guide to Enterprise Life Cycle Processes, Artifacts, and Reviews
More informationQlik UKI Consulting Services Catalogue
Qlik UKI Consulting Services Catalogue The key to a successful Qlik project lies in the right people, the right skills, and the right activities in the right order www.qlik.co.uk Table of Contents Introduction
More informationDevelop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
More informationCalifornia Department of Mental Health Information Technology Attention: MHSA-IT 1600 9 th Street, Room 141 Sacramento, CA 95814
IT Project Status Report For an MHSA-Funded IT Project Please send the Signed Original to the following address: California Department of Mental Health Information Technology Attention: MHSA-IT 1600 9
More informationCisco Unified Communications and Collaboration technology is changing the way we go about the business of the University.
Data Sheet Cisco Optimization s Optimize Your Solution using Cisco Expertise and Leading Practices Optimizing Your Business Architecture Today, enabling business innovation and agility is about being able
More informationInformation Technology Project Oversight Framework
i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11
More informationAppeals Case Management System Project. Scope Management Plan. November 20, 2014
Appeals Case Management System Project Version 1.0 Health and Human Services Agency, Office of Systems Integration Template Revision History REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF
More informationUnderstand why, when and how-to to formally close a project
Project Closure Purpose: Understand why, when and how-to to formally close a project Audience: Project managers, project sponsors, team members and other key stakeholders Learning Objectives: Describe
More informationInformation Technology Services Project Management Office Operations Guide
Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...
More informationHow To Manage Project And Portfolio Management In Microsoft Office 2010
Enterprise Project Management SOLUTIONS THAT LAST Challenges in PPM What is a Project? Why Project Management? Challenges in Project and Portfolio Management (PPM) Problems for PM and PPM Leaders Presentation
More informationDepartment of Technology Services
Department of Technology Services 2016-2019 Strategic Plan DTS Dept. of Technology Services Utah Code 63F- 1-203 explicitly requires the Chief Information Officer (CIO) to prepare an executive branch strategic
More information5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter
Develop Project Charter Develop Preliminary Project Scope Statement Develop Project Management Plan Scope Planning PROCESS GROUP: INITIATION 4.1 The project charter serves as the input document for the
More informationProject Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
More informationThe Danwood Group Professional Services Offering DANWOOD
The Danwood Group Professional Services Offering DANWOOD Our Professional Services Our Professional Services department can provide you with a variety of services from Audit and Assessment to Technical
More informationHow To Be An Architect
February 9, 2015 February 9, 2015 Page i Table of Contents General Characteristics... 1 Career Path... 3 Typical Common Responsibilities for the ure Role... 4 Typical Responsibilities for Enterprise ure...
More informationDraft Documents RFP 3.2.4
Draft Documents RFP 3.2.4 In accordance with RFP 3.2.4, CNSI includes the required draft documents in the following order: Work Plan: Team CNSI provides a comprehensive draft Work Plan for the Iowa EHR
More informationCisco Network Optimization Service
Service Data Sheet Cisco Network Optimization Service Optimize your network for borderless business evolution and innovation using Cisco expertise and leading practices. New Expanded Smart Analytics Offerings
More informationPHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
More informationOrganization. Project Name. Project Overview Plan Version # Date
Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents
More informationSystems Programmer/Analyst (12203) (31002632)
GENERAL DESCRIPTION OF WORK Positions in this banded class perform specialized work in supporting information technology equipment and systems for the business, research, and instructional functions of
More informationAppendix A-2 Generic Job Titles for respective categories
Appendix A-2 for respective categories A2.1 Job Category Software Engineering/Software Development Competency Level Master 1. Participate in the strategic management of software development. 2. Provide
More informationAddress IT costs and streamline operations with IBM service desk and asset management.
Asset management and service desk solutions To support your IT objectives Address IT costs and streamline operations with IBM service desk and asset management. Highlights Help improve the value of IT
More informationVMware Performance and Capacity Management Accelerator Service
AT A GLANCE The VMware Performance and Capacity Management Accelerator Service rapidly deploys a performance management, capacity optimization, and log management solution focused on a limited predefined
More informationMeasurement Information Model
mcgarry02.qxd 9/7/01 1:27 PM Page 13 2 Information Model This chapter describes one of the fundamental measurement concepts of Practical Software, the Information Model. The Information Model provides
More informationHHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC)
Office of the Chief Information Officer Office of the Assistant Secretary for Resources and Technology Department of Health and Human Services HHS OCIO Policy for Information Technology (IT) Enterprise
More informationFixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions
Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions Today s Business Challenges Adopt leading CRM practices and stream line processes Take advantage
More informationRisk Management Primer
Risk Management Primer Purpose: To obtain strong project outcomes by implementing an appropriate risk management process Audience: Project managers, project sponsors, team members and other key stakeholders
More informationThe Fast Track Project Glossary is organized into four sections for ease of use:
The Fast Track Management Glossary provides a handy reference guide to the fast track management model, encompassing the concepts, steps and strategies used to manage successful projects even in the face
More informationAn Oracle White Paper March 2013. Project Management Office Starter Kit
An Oracle White Paper March 2013 Project Management Office Starter Kit Executive Overview... 1 Introduction... 1 Plan Phase... 2 Create Statement of Purpose and Goals... 2 Define Scope and Target Maturity...
More informationPROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in this Project Scope Statement is implicitly excluded from the project. Create links to referenced documents (e.g., Link_To_ ) by using Insert
More informationTECHNOLOGY SOLUTIONS FOR THE INTERNAL AUDITOR
TECHNOLOGY SOLUTIONS FOR THE INTERNAL AUDITOR (BUY VS BUILD) APRIL 17, 2015 LEVERAGING TECHNOLOGY FOR AUDIT Utilizing Software to Administrate Audit Process 40% 35% 30% 37% Tools Leveraged 32% 36% Yes
More informationTREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION
TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION The Customer Account Data Engine 2 Systems Development Guidelines; However, Process Improvements Are Needed to Address Inconsistencies September 30, Year
More informationIBM Software IBM Business Process Management Suite. Increase business agility with the IBM Business Process Management Suite
IBM Software IBM Business Process Management Suite Increase business agility with the IBM Business Process Management Suite 2 Increase business agility with the IBM Business Process Management Suite We
More informationHow To Create A Help Desk For A System Center System Manager
System Center Service Manager Vision and Planned Capabilities Microsoft Corporation Published: April 2008 Executive Summary The Service Desk function is the primary point of contact between end users and
More informationWHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)?
WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? Due to the often complex and risky nature of projects, many organizations experience pressure for consistency in strategy, communication,
More informationDigital Asset Manager, Digital Curator. Cultural Informatics, Cultural/ Art ICT Manager
Role title Digital Cultural Asset Manager Also known as Relevant professions Summary statement Mission Digital Asset Manager, Digital Curator Cultural Informatics, Cultural/ Art ICT Manager Deals with
More informationProject Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
More informationNFSA Project Management Guidelines
NFSA Project Management Guidelines Project Management Guide Purpose of this Guide This Guide outlines the NFSA Project Management Guidelines, and includes: NFSA Project Life Cycle Governance Roles and
More informationAssessment of NCTD Program Management Framework for Positive Train Control Program
Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation
More informationENTERPRISE PROJECT MANAGEMENT OFFICE
ENTERPRISE PROJECT MANAGEMENT OFFICE QUALITY MANAGEMENT SYSTEM ISO 9001:2008 STATE CHIEF INFORMATION OFFICER CHRIS ESTES DEPUTY STATE CHIEF INFORMATION OFFICER AARON WIENSHIENK DEPARTMENT MANAGER JAMES
More informationProject Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:
Project Audit & Review Checklist The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Relevance (at this time) Theory & Practice (How relevant is this attribute
More informationBiometrics Enterprise Architecture Project Management Plan (BMEA PMP)
Biometrics Enterprise Architecture Project Management Plan (BMEA PMP) Version 1.0 Prepared by: Date: November 24, 2008 Revision History Purpose Revision Date Level 11/17/2009 First Draft 1.0 Responsible
More informationSECTION I PROJECT SUMMARY (TRW)
SECTION I PROJECT SUMMARY (TRW) Table I Summary Agency/Department Information TRW Information Executive Sponsor: Cynthia Lorenzo Received Date: Managers: Ron McCranie/Andy Loveland Status Meeting Date:
More informationIT Project Management Methodology. Project Execution Support Guide. Version 0.3
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Execution Support Guide Version 0.3 Table of Contents 1 INTRODUCTION... 4 1.1 When should Project Execution
More informationIT Financial Management and Cost Recovery
WHITE PAPER November 2010 IT Financial Management and Cost Recovery Patricia Genetin Sr. Principal Consultant/CA Technical Sales David Messineo Sr. Services Architect/CA Services Table of Contents Executive
More informationTHE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
More informationProject Management for Implementing the Smart Grid By Power System Engineering, Inc. Abstract PM Methodology Using a Repeatable Project Management
Project Management for Implementing the Smart Grid By Power System Engineering, Inc. Abstract PM Methodology Using a Repeatable Project Management Approach Project management solutions for the Smart Grid
More informationProject Management Plan. Project Management Plan Guide. Strategic Capital, Infrastructure and Projects
Project Management Plan Guide A guide to completing the Project Management Plan Strategic Capital, Infrastructure and Projects Prepared by: Andrew Segrott / Strategic Capital, Infrastructure and Projects
More informationINTERNAL SERVICES GROUP PMO
Ownership & Awareness Program 1 Program 3 Program 4 Program 5 Program 6 Program 7 Program 2 Cap ability Development Infra structure Program n INTERNAL SERVICES GROUP ESSENTIAL FUNCTIONS Act as an interface
More informationWHITE PAPER. iet ITSM Enables Enhanced Service Management
iet ITSM Enables Enhanced Service Management iet ITSM Enables Enhanced Service Management Need for IT Service Management The focus within the vast majority of large and medium-size companies has shifted
More informationIT SYSTEM LIFE-CYCLE AND PROJECT MANAGEMENT
United States Department of Agriculture Agricultural Marketing Service Directive 3130.8 IT SYSTEM LIFE-CYCLE AND PROJECT MANAGEMENT I. PURPOSE... 1 II. POLICY... 1 III. DEFINITIONS... 1 IV. DOCUMENTATION
More informationCertified Software Quality Engineer (CSQE) Body of Knowledge
Certified Software Quality Engineer (CSQE) Body of Knowledge The topics in this Body of Knowledge include additional detail in the form of subtext explanations and the cognitive level at which the questions
More informationSound Transit Internal Audit Report - No. 2014-3
Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management
More informationSENTINEL AUDIT V: STATUS OF
SENTINEL AUDIT V: STATUS OF THE FEDERAL BUREAU OF INVESTIGATION S CASE MANAGEMENT SYSTEM U.S. Department of Justice Office of the Inspector General Audit Division Audit Report 10-03 November 2009 Redacted
More informationProject Management Office (PMO)
Contents I. Overview of Project Management...4 1. Project Management Guide (PMG)...4 1.1 Introduction...4 1.2 Scope...6 1.3 Project Types...6 2. Document Overview, Tailoring, and Guidance...7 3. The Project
More informationHow To Develop An Enterprise Architecture
OSI Solution Architecture Framework Enterprise Service Center April 2008 California Health and Human Services Agency Revision History REVISION HISTORY REVISION/WORKSITE # DATE OF RELEASE OWNER SUMMARY
More informationErrata 1 st Printing. Errata 2 nd Printing
Errata 1 st Printing NOTE: The following errata only pertain to the first printing of the PMBOK Guide Fifth Edition. In order to verify the print run of your book (or PDF), refer to the bottom of the copyright
More informationA Provance White Paper
The Benefits of Combined IT Service Management and IT Asset Management A Provance White Paper Contents Introduction... 3 IT Service Management... 3 IT Asset Management... 4 People... 4 Processes... 5 Shared
More informationVoteCal Statewide Voter Registration System Project. Master Project Management Plan. Version 1.2
VoteCal Statewide Voter Registration System Project Master Project Management Plan Version 1.2 October 2010 October 2010 i REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF CHANGES 0.1 3/12/2009
More information