PIRU FIRE BURNED AREA EMERGENCY RESPONSE PLAN



Similar documents
Waldo Canyon Fire. Mark Shea Watershed Planning Supervisor August 23, 2012

NPS Burned Area Emergency Response (BAER) and Burned Area Rehabilitation (BAR) in the Southern California Landscape

National Retardant NEPA USFWS Reasonable and Prudent Alternative (RPA) Tracking Sheet

SFPUC Experience with Rim Fire

Wildfire & Flash Flood Recovery Emergency Watershed Protection (EWP) Flood Mitigation Efforts April Fall 2013

Fuels Treatments Reduce Wildfire Suppression Cost Merritt Island National Wildlife Refuge May 2012

Angora Fire Restoration Activities June 24, Presented by: Judy Clot Forest Health Enhancement Program

Colorado Natural Heritage Program

Wildfire & Flash Flood Recovery NACo Justice & Public Safety Symposium January 2014

UNITED STATES OF AMERICA 131 FERC 62,175 FEDERAL ENERGY REGULATORY COMMISSION. United Water Conservation District Project No.

ANGORA FIRE RESTORATION PROJECT

Interagency Burned Area Emergency Response Guidebook Interpretation of Department of the Interior 620 DM 3 and USDA Forest Service Manual 2523

Programs. Department-wide Programs Funding

CALIFORNIA MASTER COOPERATIVE WILDLAND FIRE MANAGEMENT AND STAFFORD ACT RESPONSE AGREEMENT UNITED STATES DEPARTMENT OF THE INTERIOR

THE SECRETARY OF THE INTERIOR WASHINGTON

Untreated (left) and treated (right) Sierra Nevada forests in Amador County, CA. Photos: Sierra Nevada Conservancy

Arizona s Large Fires Suppression vs. Restoration. WESTCAS Fall 2011 Meeting Bruce Hallin Manager, Water Rights and Contracts October 27, 2011

UNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF LAND MANAGEMENT ELKO FIELD OFFICE

Arapaho & Roosevelt National Forests 2013 Flood: Long-term Recovery in a Changed Landscape

U.S. Fish and Wildlife Service will invest $15 million for post-sandy cleanup and marsh restoration on Long Island

MASTER COOPERATIVE WILDLAND FIRE MANAGEMENT AND STAFFORD ACT RESPONSE AGREEMENT. Between UNITED STATES DEPARTMENT OF THE INTERIOR

Repair of Fences Damaged by Bushfire and Fire Control Line Rehabilitation Policy

MONTGOMERY COUNTY, KANSAS EMERGENCY OPERATIONS PLAN. ESF14-Long Term Community Recovery

Wildland Fire. GIS Solutions for Wildland Fire Suppression

SEC PURPOSE. SEC DEFINITIONS. SEC COLLABORATIVE FOREST LANDSCAPE RESTORATION PROGRAM.

ESCAMBIA COUNTY FLOOD RECOVERY: 1- YEAR ANNIVERSARY REPORT

Programs. Department-wide Programs Funding

King Fire Restoration Project, Eldorado National Forest, Placer and El Dorado Counties, Notice of intent to prepare an environmental impact statement.

APPENDIX III: EMERGENCY SUPPORT FUNCTION 3 - PUBLIC WORKS AND ENGINEERING

REPORT TO REGIONAL WATER SUPPLY COMMISSION MEETING OF WEDNESDAY, SEPTEMBER 4, 2013 LEECH WATER SUPPLY AREA RESTORATION UPDATE

2015 CRAIG INTERAGENCY FIRE MANAGEMENT GROUP (CIFMG) ANNUAL OPERATING PLAN

Federal Assistance for Wildfire Response and Recovery

PART I DEPARTMENT OF HUMAN RESOURCES DEVELOPMENT STATE OF HAWAII Class Specifications for the

Recent suggestions to the Natural Resources Commission to help clarify the language of this order have been incorporated into the proposal.

China Protected Areas Leadership Alliance Project

Management Efficiency Assessment on Aviation Activities in the USDA Forest Service. Executive Summary

How To Know If A Forest Service And Bmd Plan Postfire Rehabilitation And Restoration

Nevada Pinyon-Juniper Partnership Proposed Demonstration Area A Brief Introduction. Presented by Jeremy Drew Project Manager Resource Concepts, Inc.

U.S. Fish and Wildlife Service CHARLES M. RUSSELL NWR Outreach Notice

Maryland Emergency Operations Plan

Healthy Forests Resilient Water Supply Vibrant Economy. Ecological Restoration Institute

Table of Contents ESF

Southern California Insect related Tree Mortality. GIS Master Plan September 2003

MINIMUM QUALIFICATION STANDARDS

SUPPLEMENTAL QUALIFICATION STANDARD FOR THE U.S. DEPARTMENT OF AGRICULTURE, FOREST SERVICE AND THE U.S. DEPARTMENT OF THE INTERIOR


1979 SPANISH RANCH FIRE

Interagency Prescribed Fire Planning and Implementation Procedures Guide

CHAPTER 8. FEDERALLY-LISTED ENDANGERED OR THREATENED SPECIES

PUBLIC DRAFT CONTENTS

MONTANA STATE PARKS INCIDENT MANAGEMENT PLAN TEMPLATE

EAST BAY REGIONAL PARK DISTRICT FIRE DEPARTMENT POINT PINOLE GRASSLAND RESTORATION PRESCRIBED FIRE AND SMOKE MANAGEMENT PLAN

Great Basin Geographic Area Incident Management Team Principles

This document provides direction for the Great Basin and supplements the Interagency Incident Business Management Handbook, PMS-902.

Case Study: The History of the San Juan Headwaters Forest Health Partnership

Karuk Tribe Integrating Traditional Ecological Knowledge within Natural Resource Management

Assessing the Environmental, Social, and Economic Impacts of Wildfire

Walter Dasheno Governor Santa Clara Pueblo

Emergency Conservation Program

Forest Service Fire & Aviation Qualification Guide, Chapter 3

PART TWO FINANCE/ADMINISTRATION SECTION

ALBUQUERQUE EMERGENCY OPERATIONS PLAN ANNEX 8 DAMAGE ASSESSMENT AND REPORTING

PRESCRIBED FIRE PLAN

State of Colorado Incident Management System. Incident Management Program Qualifications System Guide

Guidance for Implementation of Federal Wildland Fire Management Policy

Chapter 01 Federal Wildland Fire Management Policy and Guidance Overview

Jefferson Parish Department of Water Emergency Plan

FWS Cultural Resource Management Planning

National Association of State Foresters Forestry Performance Measures for the United States REQUEST FOR PROPOSALS (RFP)

Budget Process. Budget Calendar. The City s fiscal year is July 1 through June 30.

CHAPTER 15 DISASTER COST RECOVERY PROCEDURES

Experience Summary. KINA MURPHY, M.S. Ecologist / Community Planner 9 Stone Ridge Road, Santa Fe, NM Cell: Education / Training

Flood Emergency Response Planning: How to Protect Your Business from a Natural Disaster RIC005

CHAPTER 0340 FIRE PROTECTION POLICIES

1. Water Line Maintenance 2. Sanitary Sewer Maintenance 3. Spill/Leak/Overflow Control, Response, and Containment

Wildlife Habitat Conservation and Management Program

REIMBURSEMENT PROCEDURE for FEMA PUBLIC ASSISTANCE

Public Land Management and Interdependent Collection of Programs

Transcription:

PIRU FIRE BURNED AREA EMERGENCY RESPONSE PLAN AGENCY/UNIT: U.S. Fish and Wildlife Service Hopper Mountain National Wildlife Refuge LOCATION: Ventura County, California DATE: November 4, 2003 Amended June 1, 2004 PREPARED BY: United States Fish & Wildlife Service California/Nevada Burned Area Emergency Response Team Submitted By: /s/ Steve Thompson Date: June 1, 2004 Steve Thompson, Manager California/Nevada Operations Office

EXECUTIVE SUMMARY This plan addresses emergency stabilization for fire effects on Hopper Mountain National Wildlife Refuge as a result of the Piru Fire in Ventura County, California. The plan has been prepared in accordance with the Department of the Interior, Departmental Manual, Part 620: Wildland Fire Management, Chapter 3: Burned Area Emergency Stabilization and Rehabilitation (May 20, 2004). This document provides emergency stabilization recommendations for U.S. Fish & Wildlife Service lands within the Piru Fire. The U.S. Forest Service Burned Area Emergency Response Team has addressed U.S. Forest Service lands and other lands impacted by the fire, separately. The primary objectives of the Piru Fire Burned Area Emergency Response Plan are: To prescribe post-fire mitigation measures necessary to protect human life, property, and critical cultural and natural resources. The U.S. Fish & Wildlife Service, Burned Area Emergency Response (BAER) Team has conducted an analysis of fire effects on Hopper Mountain National Wildlife Refuge using ground reconnaissance methods. The plan primarily addresses impacts to minor infrastructure essential to the daily management of the California Condor Recovery Program. While the 2,471 acre Hopper Mountain National Wildlife Refuge represents only a small fraction of the land area utilized by the reintroduced California condor population, the Refuge is a critical management center for the Condor Recovery Program. Captive bred birds are brought to Refuge and are placed in specialized flight pens to get familiar with the area and are introduced to other mature and wild birds. Specialized supplemental feeding stations are located on the Refuge and used on a daily basis to feed wild birds. Feeding stations are tied to specialized condor trapping stations where wild birds are recaptured to replace radio telemetry equipment, collect blood samples, and care for injured or ill birds. Specialized isolation pens are housed at the refuge for care of injured or recovering birds. While no birds and the three main field station buildings were not directly impacted by the wildfire, infrastructure essential to management of the Condor Recovery Program was damaged or destroyed by the Piru Fire. This plan documents that damage and provides specific costs for repairs and replacement of damaged infrastructure items that are appropriate for funding under the Emergency Stabilization fund of the U.S. Department of the Interior. All specifications are fully consistent with the approved management plans for the Hopper Mountain National Wildlife Refuge and the California Condor Recovery Plan. Fire Location The Piru Fire started on October 23, 2003 at approximately 1:30 PM in the Lake Piru Recreation Area east of Hopper Mountain National Wildlife Refuge. The fire suppression effort was managed under a Unified Command with U.S. Forest Service, California Department of Forestry and Fire Protection, Los Angeles County and Ventura County Fire Protection Districts. Fire Management Officer Perry Grissom of Sacramento National Wildlife Refuge Complex was assigned as the U.S. Fish and Wildlife Service representative to the Incident Team. On Saturday October 25, 2003 the Piru Fire was declared 90 percent contained and resources were being released to other major incidents in the Southern California Fire Storm Event. At approximately 3:30 PM Santa Ana winds apparently hit the Piru Fire and it escaped over a major ridgeline. The winds drove the fire down Hopper Canyon and through the refuge. Perry Grissom and two engines crews from the Los Padres National Forest and one crew from Los Angeles County protected the three main buildings of the Hopper Field Station with a combination of hosing down structures and defensible space and by lighting backfires off of this defensible space. Due to suppression tactics used there are no suppression impacts to the refuge. At the time of this plans submission the Piru Fire had consumed 63,991 acres and was not yet fully contained or controlled.

ISSUES AND OBJECTIVES The BAER Team was assembled on Tuesday October 28, 2003 at the Hopper Mountain National Wildlife Refuge Complex and with the approval of the Incident Command Team initiated preliminary damage assessments and photo documentation of all impacts to refuge infrastructure. The Team provided daily briefings for the California/Nevada Operations Office, Regional Office, and maintained communications with the Directors Office in Washington, DC. Issues identified by the Team included: Boundary, Entrance, and Refuge Closure Sign Damage Water System Repairs Radio Repeater Repair/Replacement Flight Pen and Blind Replacement Removal of Burnt Debris Feeding Station Repairs (electric fence system) Supplement Feeding Equipment Replacement (freezer, thaw locker) Storage Shed Replacement Isolation Pen and Blind Repairs Gate Repairs Trapping Station Repairs Monitoring Control of Noxious Weed Population Hazardous Tree Mitigation Water Buffalo Replacement Telephone Line Marker Repairs Accept for management of noxious weeds, each of the above issues directly relates to mitigating impacts of the Piru Fire to management and recovery of the Federal endangered California condor and is therefore fundable under the U.S. Department of the Interior, Burned Area Emergency Stabilization fund. Implementation of the repairs to California condor infrastructure damaged by the fire should be initiated as quickly as possible through the Implementation Leader designated for the project. It will be important for the Implementation Leader to coordinate the recommended activities, track budgets, coordinate contracts, and prepare accomplishment reports for the emergency stabilization funding. This Burned Area Emergency Response Plan is the initial funding request for both Emergency Stabilization funds. Additional supplemental requests may be made after this document has been reviewed and approved. It is recommended that supplemental requests be made on an as needed basis. The Emergency Stabilization Funds for this plan extends over one year from the date of containment of the fire. At the conclusion of the funding period, a final Accomplishment Report will be due to the approval authority. The Accomplishment Report will document the funding received (initial and supplemental funding), treatments installed, the effectiveness of the installed

treatments, and the results of monitoring activities. This Plan was submitted to the approving official, in accordance with Department and Service policy.

U.S. FISH & WILDLIFE SERVICE BURNED AREA EMERGNECY RESPONSE PLAN PART I REVIEW AND APPROVAL I. EMERGENCY STABILIZATION CONCURRENCE Concur Concur with Revision Disapproved Explanation for Revision or Disapproval: /s/ Dan Walsworth June 1, 2004 Refuge Supervisor Date II. EMERGENCY STABILIZATION CONCURRENCE Concur Explanation for Revision or Disapproval: Concur with Revision Disapproved /s/ Pam Ensley June 1, 2004 Region 1, FMO, FWS Date III. EMERGENCY STABILIZATION APPROVAL Approved X Approved with Revision Disapproved Explanation for Revision or Disapproval: /s/ Steve Thompson June 1, 2004 Manager, California/Nevada Operations, FWS Date

U.S. Fish and Wildlife Service Burned Area Emergency Response PART B Nature of Plan

U.S. FISH & WILDLIFE SERVICE BURNED AREA EMERGENCY RESPONE TEAM PART C EMERGENCY STABILIZATION ASSESSMENT I. Emergency Stabilization Objectives: Locate and stabilize severely burned slopes which pose a direct threat to human life, property or critically important cultural and natural resources. Conduct immediate post-burn reconnaissance for fire suppression related impacts to threatened and endangered (T&E) species, and cultural sites.

U.S. FISH & WILDLIFE SERVICE BURNED AREA EMERGENCY RESPONSE TEAM PART D TEAM ORGANIZATIONS, TEAM MEMBERS, RESOURCE ADVISORS I. BAER TEAM MEMBERS POSITION Team Leader Wildlife Environmental Protection & Compliance TEAM MEMBER / AGENCY Richard Hadley, FWS Marc Weitzel, Project Leader Hopper Mtn. NWRC Greg Austin, Deputy Project Leader Hopper NWRC Dan Tappe, Wildlife Biologist, Hopper Mtn. NWR Richard Posey, Wildlife Biologist, Hopper Mtn. NWR Mark Hall, Refuge Ops Spec., Hopper Mt. NWR Richard Hadley, FWS GIS Computer / Documentation Denise Stockton, I&E Specialist, Hopper Mtn. NWRC Miscellaneous Support Personnel Information Denise Stockton, I&E Specialist, Hopper Mtn. NWRC IV. Resource Advisors: (Note: Resource Advisors are individuals who assisted the BAER Team with the preparation of this plan. See Part H of this plan for a full list of agencies and individuals who were consulted or otherwise contributed to the development of this plan. NAME AFFILIATION, SPECIALTY See Team Members Above

U.S. FISH & WILDLIFE SERVICE BURNED AREA EMERGENCY RESPONSE PLAN PART D SUMMARY OF APPROVAL AUTHORITIES ACTIVITIES REQUIRING REGIONAL OFFICE APPROVAL COST Emergency Stabilization Requests Replace Fire Hydrant / Hose Station $3,770 Hazard Tree Mitigation $10,000 TOTAL 13,770

U.S. FISH & WILDLIFE SERVICE BURNED AREA EMERGNECY RESPONSE PLAN PIRU FIRE PART E SUMMARY OF ACTIVITIES The SUMMARY OF ACTIVITIES table identifies trackable emergency stabilization. Only trackable expenditures are displayed in the total cost column. TREATMENT SPECIFICATION UNIT UNIT COST # OF UNITS IMPLEMENTATION METHOD SPECIFICATION TOTAL S-2 Replace Fire Hydrant / Hose Station S-3 Hazardous Tree Mitigation Hydrant Tree $3,770 1 C - - C $3,770 $10,000 TOTALS $13,770

INTERAGENCY BURNED AREA EMERGENCY STABILIZATION & REHABILITATION PLAN PART F - SPECIFICATION SPECIFICATION TITLE: Replace Fire Hydrant / Hose Station JURSIDICTIONS: FWS PART E: LINE ITEM: S-2 Replace Fire Hydrant / Hose Station FISCAL YEAR: 2004 ESR REFERENCE #: Safety SPECIFICATION TYPE: ES I. WORK TO BE DONE A. Provide a Brief General Description of Treatment Replace fire hydrant and hose damaged and now leaking after the fire. B. Describe Specific Treatment Location or General Description of Suitable Sites for Treatment Hydrant at fire Hopper Mountain Field Station. C. Provide and Number Detailed Design/Construction Specifications 1. Purchase hydrant, hose, etc. 2. Contract with plumber for repairs. 3. Contract with carpenter to construct hose box. D. Describe Purpose of Treatment Specification What Resource will be Protected Required for structural protection at the Hopper Mountain NWR field station. E. Describe Treatment Effectiveness Monitoring Inspect contracted work prior to acceptance and payment II. LABOR, EQUIPMENT, MATERIALS, AND OTHER COST: PERSONNEL SERVICES (Grade @ Cost/Hours X # Hours X # Fiscal Years = Cost/Item Do not include contract personnel costs here (see contractor services below). TOTAL PERSONNEL SERVICE COST EQUIPMENT PURCHASE, LEASE, OR RENTAL (Item @ Cost/Hours or Cost/Day or # Days X # Fiscal Years = Cost/Item) Note: Purchase requires written justification that demonstrates cost/item benefits over lease or rental. TOTAL EQUIPMENT PURCHASE, LEASE, OR RENTAL COST MATERIAL AND SUPPLIES (Item @ Cost/Each X Quantity X # Fiscal Years = Cost/Item) Purchase materials necessary to replace hydrant. Purchase materials to replace hose box. TOTAL MATERIAL AND SUPPLY COST TRAVEL COST (Personnel or Equipment @ Rate X Round Trips X # Fiscal Years = Cost/Item $500 $550 $1050 TOTAL TRAVEL COST CONTRACT COST (Labor or Equipment @ Cost/Hour X # Hours X # Fiscal Years = Cost/Item) Contracted plumber @ $90/hr x 813.5 hours = $720 Contracted carpenter @ $75/hr x 20.4 hours = $375 COST /ITEM $1220 $1530 TOTAL CONTRACT COST $2750

SPECIFICATION COST SUMMARY FISCAL YEAR UNIT UNIT COST # OF UNITS COST FUNDING SOURCE METHOD 2004 Hydrant $3,770 1 $3,770 ES C - - - - - - - TOTAL - - - $3,770 ES C FUNDING SOURCES F= Fire Suppression ESR = Emergency Stabilization & Rehab. OP/O = Agency Operating Fund EWP = Emergency Watershed Program SPECIFICATION TYPE ES = Emergency Stabilization R = Rehabilitation FS = Fire Suppression METHOD OF COMPLETION P = Agency Personnel Services C = Contract EFC = Emergency Fire Contract FC = Crew Labor Assigned to Fire SOURCE OF COST ESTIMATES Put Letter (P,M,T,C, or F) Next to Appropriate Cost Estimate Source (1-5) Below 1. Estimate obtained from 2-3 independent contractual sources. 2. Documented cost figures from similar project work obtained from local agency sources. M/C 3. Estimate supported by cost guides from independent sources or other federal agencies. 4. Estimates based upon government wage rates and material cost. 5. No cost estimate required cost charged to Fire Suppression Account (not tracked in plan) P = Personnel Services M = Materials/Supplies T = Travel C = Contract F = Suppression I. RELEVANT DETAILS, MAPS, AND DOCUMENTATION INCLUDED IN THIS REPORT List Relevant Documentation and Cross-References within ESR Plan See Photo documentation at end; Figure 2 Melted PVC Pipe

INTERAGENCY BURNED AREA EMERGENCY STABILIZATION & REHABILITATION PLAN PART F - SPECIFICATION SPECIFICATION TITLE: Hazardous Tree Mitigation JURSIDICTIONS: FWS PART E: LINE ITEM: S-3 Remove Hazardous Snags and Trees FISCAL YEAR: 2004 ESR REFERENCE #: Safety SPECIFICATION TYPE: ES I. WORK TO BE DONE A. Provide a Brief General Description of Treatment This project would remove burnt trees and snags that pose a risk of falling across roadways and other areas on the refuge where people are working. B. Describe Specific Treatment Location or General Description of Suitable Sites for Treatment See Hopper Mountain NWR map in appendices. C. Provide and Number Detailed Design/Construction Specifications 1. Contract for removal of hazardous trees and snags. D. Describe Purpose of Treatment Specification What Resource will be Protected Removal of hazardous trees will provide continued access to the refuge field station and a safe work environment around the flight pens and field station. E. Describe Treatment Effectiveness Monitoring Inspect contracted work prior to acceptance and payment. II. LABOR, EQUIPMENT, MATERIALS, AND OTHER COST: PERSONNEL SERVICES (Grade @ Cost/Hours X # Hours X # Fiscal Years = Cost/Item Do not include contract personnel costs here (see contractor services below). TOTAL PERSONNEL SERVICE COST EQUIPMENT PURCHASE, LEASE, OR RENTAL (Item @ Cost/Hours or Cost/Day or # Days X # Fiscal Years = Cost/Item) Note: Purchase requires written justification that demonstrates cost/item benefits over lease or rental. TOTAL EQUIPMENT PURCHASE, LEASE, OR RENTAL COST MATERIAL AND SUPPLIES (Item @ Cost/Each X Quantity X # Fiscal Years = Cost/Item) TOTAL MATERIAL AND SUPPLY COST TRAVEL COST (Personnel or Equipment @ Rate X Round Trips X # Fiscal Years = Cost/Item TOTAL TRAVEL COST CONTRACT COST (Labor or Equipment @ Cost/Hour X # Hours X # Fiscal Years = Cost/Item) COST /ITEM Contract removal of burnt trees and snags where required $10,000 TOTAL CONTRACT COST $10,000

SPECIFICATION COST SUMMARY FISCAL YEAR UNIT UNIT COST # OF UNITS COST FUNDING SOURCE METHOD 2004 Trees $10,000 $10,000 ES C - - - - - - - TOTAL - $10,000 $10,000 ES C FUNDING SOURCES F= Fire Suppression ESR = Emergency Stabilization & Rehab. OP/O = Agency Operating Fund EWP = Emergency Watershed Program SPECIFICATION TYPE ES = Emergency Stabilization R = Rehabilitation FS = Fire Suppression METHOD OF COMPLETION P = Agency Personnel Services C = Contract EFC = Emergency Fire Contract FC = Crew Labor Assigned to Fire SOURCE OF COST ESTIMATES Put Letter (P,M,T,C, or F) Next to Appropriate Cost Estimate Source (1-5) Below 1. Estimate obtained from 2-3 independent contractual sources. 2. Documented cost figures from similar project work obtained from local agency sources. C 3. Estimate supported by cost guides from independent sources or other federal agencies. 4. Estimates based upon government wage rates and material cost. 5. No cost estimate required cost charged to Fire Suppression Account (not tracked in plan) P = Personnel Services M = Materials/Supplies T = Travel C = Contract F = Suppression I. RELEVANT DETAILS, MAPS, AND DOCUMENTATION INCLUDED IN THIS REPORT List Relevant Documentation and Cross-References within ESR Plan No photo documentation