Contract Language and Documentation



Similar documents
California Civil Code

Kentucky Department of Education Version of Document A

How To Get A Construction Contract In The United States

SURETY. and Title: (Any additional signatures appear on the last page of this Performance Bond.)

SOUTH CAROLINA & NORTH CAROLINA, MECHANIC S LIEN AND PAYMENT BOND CLAIM MANUAL *

California Senate Bill 474 Impact on Owners & Contractors

AIA Document A310 TM 2010

STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION

388 Blohm Ave. PO Box 388 Aromas CA (831) FAX (831) ADDENDUM NO. 1

CSA CONSTRUCTION, INC McAllister Road Houston, Texas SUBCONTRACTOR AGREEMENT

CALIFORNIA CONSTRUCTION CONTRACTS, DEFECTS, AND LITIGATION (1st Edition) November 2015 TABLE OF CONTENTS

COMMENTARY. California s New Subcontractor Defense Regime for Non-Residential Projects: Creating Order or Chaos?

Payment and Performance Surety Bonds in Construction Projects: Perspectives of Owners, Contractors and Sureties

How To Build A House

AIA Document A312 - Electronic Format. Performance Bond

Memorandum Potentially Affected AIA Contract Documents AIA Document A AIA Document B Important Information

IMPORTANT! - Please use the attached Application for Payment. All payment requests must be submitted on our form. Thank you!

Document Comparative

Payment Bonds. Construction Law Survival Manual. Construction Law Survival Manual. Presented by James D. Fullerton

How To Write A Short Form Prime Prime Prime Contract Between A Contractor And Owner

Bond Form Commentary and Comparison

Welcome to the Model Residential Construction Contract Cost Plus

Construction Bonds. Vanessa S. Werden

Document A312" of business) OWNER'S REPRESENTATIVE: (Architect, Engineer or other party:) 500 North Main Street Monroe, North Carolina 28112

UNIVERSITY OF MINNESOTA

RHODE ISLAND CONSTRUCTION LAW PRIMER

COMMERCIAL CONSTRUCTION AGREEMENT. This CONTRACT AGREEMENT ( Contract ) is made on, 20, by and between <> ( Owner ) and <> ( Contractor ).

OWNER S CHECKLIST ISSUES FOR PERFORMANCE AND PAYMENT BONDS Produced by the ABA Forum on the Construction Industry Division 12: Owners and Lenders

STANDARD FORM OF AGREEMENT BETWEEN OWNER AND DESIGN- BUILDER - LUMP SUM

SECTION 2 THE BOEING COMPANY GENERAL PROVISIONS FIXED PRICE SERVICES CONTRACT GP2

Welcome to the Model Residential Construction Contract Lump Sum

What You Should Know About General Agreements of Indemnity and Why You Should Know It

MIGHTY MIKE PLUMBING, INC. PLUMBING GENERAL CONTRACTOR SERVICES PROPOSAL

How To Manage A Power Station

Construction Defect Action Reform Act

Checklist 26: How Owners Can Avoid Litigation on Construction Projects

AN OVERVIEW OF THE CONTRACT SURETY BOND CLAIMS PROCESS

Performance Bonds. Putting Words to Action. Bennett Rainey, Sarah Riedl, Joseph Riegerix, and Evan Rossi

8132. [Operative July 1, 2012] Conditional Waiver and Release in Exchange for Progress Payment; Form. If a claimant is required to execute a waiver

FOR PROPERTY LOSS AND DAMAGE 1

STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment)

CITY OF REDMOND SIDE SEWER CONTRACTOR PERFORMANCE AND WARRANTY BOND

AIA Document A312 TM 1984

CHAPTER 23. Contract Management and Administration

IEC Electronics Terms and Conditions

CALIFORNIA NEW MANDATORY NOTICE REQUIREMENTS FOR ENFORCEMENT OF MECHANIC S LIEN RIGHTS

SUBCONTRACT AGREEMENT

SAMPLE SERVICES CONTRACT

PROMOTIONAL AGREEMENT TERMS AND CONDITIONS ALABAMA, GEORGIA, KENTUCKY, MISSISSIPPI, SOUTH CAROLINA, NORTH CAROLINA AND TENNESSEE

NC General Statutes - Chapter 44A Article 3 1

THE NEW MASSACHUSETTS PROMPT PAYMENT ACT AND ITS IMPACT TO NEW HAMPSHIRE CONTRACTORS

PAYMENT/PERFORMANCE BOND. This is the front page of the payment/performance bond issued in compliance with Florida Statutes

Contract Clauses Appendix B: Contract

Standard Terms & Conditions of Quotation and Sale

Maronda Homes Limited Warranty Agreement

Construction Surety Bonds

INSURANCE REQUIREMENTS FOR CONSTRUCTION CONTRACTS ABOVE $25,000

In these conditions "the Company" means Pro Formance Metals Limited

Document A312 TM SURETY. (Name, legal status and principal place of business)

Construction Defect Coverage Recap For 1st Quarter

ON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS

COLLECTING YOUR MONEY THROUGH MECHANIC S LIENS, STOP NOTICES & BONDS

PERFORMANCE BONDS AND LABOUR AND MATERIAL PAYMENT BONDS: WHAT THE CONSTRUCTION INDUSTRY SHOULD KNOW

Document A312 TM SURETY. (Name, legal status and principal place of business)

This page left blank intentionally

TERMS AND CONDITIONS

MORTENSON CANADA CORPORATION PURCHASE AGREEMENT STANDARD TERMS AND CONDITIONS

SUBCONTRACTOR LABOR AND MATERIAL PAYMENT BOND ("Bond") SURETY Address

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

Construction Performance Bond. THIS CONSTRUCTION PERFORMANCE BOND ( Bond ) is dated, is in the penal sum of. Sample Preview CONTRACTOR: Address

Flexible Circuits Inc. Purchase Order Standard Terms and Conditions

ANNUAL SUBCONTRACTOR AGREEMENT. THIS AGREEMENT is made on, 200, between <>, a Minnesota corporation ( Contractor ) and ( Subcontractor ).

PURCHASE TERMS & CONDITIONS (EFFECTIVE MAY 23, 2014)

Claims College School of Construction LEVEL 1

NORTH CAROLINA WEATHERIZATION ASSISTANCE PROGRAM SUBCONTRACTOR AGREEMENT - PLUMBING

CA Home Repair I Page 1

CLAUSES REQUIRED ON ALL HOME IMPROVEMENT CONTRACTS ($ on up)

CALIFORNIA DEPARTMENT OF TRANSPORTATION CONTRACTOR LIABILITY INSURANCE

PURCHASE ORDER TERMS AND CONDITIONS

EXHIBIT B-1 INSURANCE REQUIREMENTS FOR CONSTRUCTION CONTRACTS ABOVE $30,000

D None SeePage 2. AlA Document A312

Construction Bonds on Public Projects (Reprinted with permission from NACM s Manual of Credit and Commercial Laws, 104 th edition)

28. Time is of the essence in this Lease and in each and all of its provisions.

A. For the consideration agreed below to be paid to Contractor by City, Contractor shall provide

Discharge 3/14/2012. Chapter 16 Performance and Discharge Byron Lilly De Anza College Byron Lilly De Anza College

Transcription:

Contract Language and Documentation Charles A. Ray, IV Lanier Ford Shaver & Payne P.C. 2101 West Clinton Ave., Suite 102 Huntsville, AL 35805 256-535-1100 CAR@LanierFord.com www.lanierford.com 2014 1

Agenda Payment issues. Warranties. Change orders. Project delays and inefficiencies. Pay-when-paid clauses. 2

Full-Price Lien Ala. Code 35-11-210. Lien for full amount of materials regardless of whether value of materials exceeds unpaid balance due by owner to general contractor. To defeat, owner must object to services or materials. 3

Form of Notice to Owner Take notice, that the undersigned is about to furnish, your contractor or subcontractor, certain material for the construction, or for the repairing, altering, or beautifying of a building or buildings, or improvement or improvements, on the following described property: and there will become due to the undersigned on account thereof the price of the material, for the payment of which the undersigned will claim a lien. 4

Tenant Lien Ala. Code 35-11-212. Has limited practical application When contractor contracts with tenant (instead of landlord), lien applies to leasehold interest or to improvements if improvements can removed without damage. Matador Holdings, Inc. V. HOPO Realty Investments, LLC, 77 So.3d 139 (Ala. 2011); Lloyd v. Stewart, 60 So.2d 911 (Ala. 1952); cf. Kirkpatrick Concrete Company, Inc. v. Birmingham Realty Co., Inc., 598 So.2d 796 (Ala. 1992) 5

Alternative Avenues for Payment Surety bonds: Performance bonds. Payment bonds. Federal Miller Act (40 U.S.C. 3131). Alabama Little Miller Act (Ala. Code 39-1-1). Prompt Payment to Contractors and Subcontractors Act (Ala. Code 8-29-1). 6

Surety Bonds Usually requirement for general contractor (GC) as part of contract. Generally, guarantees performance by principal (usually GC). 7

Surety Bond Insurance Policy Surety bonds cover economic damages from breach of contract; insurance policies don t. Surety has indemnification rights against principal; insurance carrier cannot assert subrogation rights against insured. 8

Performance Bond Inure to benefit of owner. Surety will not assume GC s role OR pay claims asserted by owner unless GC defaults and GC refuses to remedy default. If dispute arises of whether there is default, surety will typically tender their defense to GC. 9

Payment Bonds Inure to benefit of downstream parties: subcontractors, laborers, suppliers, etc. Guarantees all payments due for services or materials furnished for project. Benefits owner because owner doesn t have to worry about liens being filed against property. 10

Federal Miller Act When contract exceeds $100,000, contractor must post performance and payments bond. Surety must be on U.S. Treasury list of qualified sureties. Civil action to enforce claim after 90 days. Second-tier subcontractor must provide notice to prime contractor within 90 days. Statute of limitations: 1 year. 11

Alabama Little Miller Act When contract exceeds $50,000, contractor must have Performance bond (100% of prime contract amount). Payment bond (50% of prime contract amount). No distinction between first- and secondtier subcontractors or suppliers. Applies to any person. 12

Alabama Little Miller Act (cont.) Notice requirement: 45 days. If surety fails to pay within 45 days, claimant can recover attorney fees and interest on unpaid principal. Statute of limitations: 1 year. 13

Prompt Payment Act Owner required to pay According to contract terms. If no terms, within 30 days after request for payment. Contractor has to pay According to contract terms. If no terms, within 7 days after receiving payment from owner. Interest at 12% a year. Possible attorney fee. 14

Retainage Retainage on private projects capped at 10% of estimated amount of properly performed work until work is 50% complete. After 50% complete, no additional retainage. Downstream retainage may not exceed upstream retainage. 15

Right to Retain Payments Applies when bona fide dispute exists over claimant s right to receive payment. Withholding party must provide written notice of dispute within 5 days of request for payment. 16

Exempt Parties Residential homebuilders. Improvements to residential property consisting of 16 or fewer residential units. Contractors, subcontractors, and subsubcontractors when contract is worth $10,000 or less. Contracts with state or local governments. 17

Warranties Implied warranty of habitability (residential only). Express warranty provided by contractor or builder. 18

Implied Warranty of Habitability An action alleging a breach of warranty is a subset of a breach-of-contract action and each new house constructed within the State of Alabama carries with it an implied warranty of habitability. This implied warranty may, however, be waived or disclaimed via contract. Does not apply to commercial projects. 19

Express Warranty by Contractor or Builder In many cases, a homebuilder will warrant its work in accordance with the standard 2-10 home buyer s warranty which covers workmanship defects for 1 year, systems defects for 2 years, and structural defects for 10 years. Commercial warranties are typically 1 year from substantial completion. Manufacturer s warranties typically inure to owner. 20

Changes to Work: Change Orders Most, if not all, contracts allow an owner to make changes to the project, even after the GC and its subcontractors have commenced construction. Problems rarely arise out of minor changes which do not affect the project schedule or contract amount. On the other hand, changes that involve additional work or require additional time to perform will normally entitle the GC and affected subcontractors to additional compensation and an extension of time to complete the work. In an ideal situation, the effect of such changes will be agreed upon ahead of time and memorialized within a written change order. Without a written change order, disputes are very common. 21

Changes to Work: Owner Directive If an Owner and GC cannot agree upon the effect of a proposed change ahead of time, some contracts provide for an owner directive. This document requires the GC to implement the change in exchange for a reasonable adjustment in the contract amount or an extension of time. This procedure works best when the GC is contractually entitled to full reimbursement of its costs to implement the change and can include those costs within its normal applications for progress payments. 22

Changes to Work: Practical Note Changes to the work or project schedule are hotbeds for litigation if the written change order or owner directive procedures are not used. 23

Project Delays and Labor Inefficiencies Owners, contractors, and subcontractors budget a project in accordance with the project schedule. When a project is delayed and is, thus, not completed within the allotted time, claims for economic losses related to the delay are common. 24

Claims by Owner Delays to revenue-producing projects will often result in lost profit opportunities for the project owner. Liquidated Damages: Most construction contracts anticipate such delays and allow the owner to recover liquidated damages for each day the project is delayed beyond the anticipated or scheduled date of completion. Re-sequencing or acceleration: If delay occurs during project, some construction contracts grant the owner or GC the right to demand that remaining work be re-sequenced or accelerated to make up for lost time. In the absence of a contractual right to re-sequence or accelerate the work, such changes will often result in requests for additional compensation from the GC and or its subcontractors. 25

Claims by Contractors and Subs For delay: When a project is delayed through no fault to the GC or its subcontractors, the GC and its subs may have claims for extended labor and field office overhead during the delay period. The justification for such claims is that the delays increase the contractors costs and, therefore, renders their work less efficient. If these extra costs are not reimbursed, the contractors anticipated profits are diminished. Weather and other acts of god: Most contracts allow for delay or inefficiency claims related to extend periods of bad weather or other natural events (for example, hurricanes, tornadoes, lightning damage, earthquakes, etc.). Concurrent delay: When a contractor contributes to the alleged delay by its own actions or non-actions, the casual link between its damages and the otherwise compensable delay may be broken. No-damage-for-delay-clauses: Many construction contracts limit a contractor s recourse for delays to an extension of time to complete the work, thereby requiring the contractor to waive claims for additional funds related to the delay. 26

Claims for Labor Inefficiencies If the GC or its subcontractors, through no fault of their own, are required to accelerate their work schedule, the resulting increase in labor costs often gives rise to labor inefficiency claims against the owner. These claims are usually based upon the increased labor burden from additional workers or overtime required to comply with the compressed or accelerated schedule. 27

Pay-When-Paid Clauses Requirement that subcontractor is not paid until condition precedent has been met, such as the owner pays the GC OR Mere timing mechanism for subcontract payment. 28

Pay-When-Paid Clauses (cont.) Condition precedents are not favored in contract law and will not be upheld unless there is clear language to support them. If two parties knowingly, clearly, and unequivocally enter into an agreement whereby they agree that the respective liability of the parties will be determined by some type of agreed-upon formula, Alabama law permits the enforcement of that agreement as written. 29

Example: Pay-If-Paid Clause Notwithstanding anything else in this subcontract or the contract documents, the obligation of contractor to make any payment under this subcontract... is subject to the express and absolute condition precedent of payment by owner. It is expressly agreed that contractor and its surety shall have no obligation to pay for any work done on this project until contractor has received payment for such work from owner. Subcontractor expressly assumes the risk of nonpayment by owner. 30

Example: Pay-When-Paid Clause Final payment, consisting of the unpaid balance of the price, shall be made within 45 days after the last of the following to occur: a.... ; b.... ; c. Final payment by owner to contractor under the contract on account of the work. 31

Payment Within Reasonable Time If pay-when-paid clause applies, payment must be made within a reasonable time. 32

Questions? Charles A. Ray, IV Lanier Ford Shaver & Payne P.C. 2101 West Clinton Ave., Suite 102 Huntsville, AL 35805 256-535-1100 CAR@LanierFord.com www.lanierford.com 33