Managing sustainable construction a steering model for the building process

Similar documents
Energy efficiency in renovation processes with focus on time and timing

Project plan for graduate thesis

Governing transitions towards Low-Carbon Transport Systems

Best customer experience

Programme title Master s Programme in Politics and War. Programme title in Swedish Magisterprogrammet i politik och krig

Sustainable Hyllie. Strategies and programmes for a new climate-smart city district. City of Malmö Department of Urban Planning

Author: Sirje Padam, WSP Sweden and Tallinn University of Technology

Sustainable development and strategic transport management in the Øresund region

Research groups on masters level a pedagogical experiment

green public procurement in sweden

CV Ulrika Gunnarsson-Östling

Core Fittings C-Core and CD-Core Fittings

How to plan green neighbourhoods? Kuidas planeerida keskkonnahoidlikku naabruskonda?

Building the Single Market for Green Products. Dr. Michele Galatola Product team leader DG Environment Sustainable Production and Consumption Unit

The course is included in the CPD programme for teachers II.

General Syllabus for Third-Cycle Studies in Business Administration Leading to a Degree of Doctor, 240 Higher Education Credits

Building Product Declarations Ecocycle Council guidelines

Sweden s Road to Modernity: An Economic History


Effects of CEO turnover on company performance

EUROPEAN COMMISSION. Rue de la Loi 200, B-1049 Bruxelles / Wetstraat 200, B-1049 Brussel - Belgium. Telephone: (32-2)

Developing a model of total cost of ownership for evaluation of purchases at Saab Microwave Systems

Social responsibility in procurement. Code of conduct for suppliers


Dialogue for Nature Conservation

Project Portfolio Office April Information and Communications Technology P ROJECT PORTFOLIO O FFICE M AY 2014 D RAFT. Page 1

A. Master of Science Programme (120 credits) in Global Studies (Masterprogram i globala studier)

Programme Syllabus for Software Engineering Master s Programme, 120 credits

ENGLISH. Skånet 2011

The Environmental Management System at the Municipal Bus Company in Uppsala, Sweden

General study plan for postgraduate studies in computer science

C. Wohlin and B. Regnell, "Achieving Industrial Relevance in Software Engineering Education", Proceedings Conference on Software Engineering

SOCIAL SCIENCES CONTRIBUTIONS TO CLIMATE CHANGE RESEARCH

Second Opinion on Nya Svensk FastighetsFinansiering AB s Green Bond framework

MP4 WP4.1 Retroactive evaluation of on-the-ground benefits

Health, Security, Safety and Environment (HSE)

Madame President, Mr. Secretary General, Excellencies, Ladies and Gentlemen, The world of today is facinghuge challenges. But also huge possibilities.

Environmental footprinting of products The policy outlook

PRINCIPLES OF SUSTAINABLE DEVELOPMENT - Vol. III International Standards (ISO 9000 and ISO 14000) Development Information and Knowledge - L.

Rwanda. Strategy for Sweden s development cooperation with MFA

Learning for Collaborative Energy Efficiency in Urban Residential Areas, ClueE

with global applications Higher national employment Lower emissions of greenhouse gases More efficient use of resources

UNICEF s Quality Assurance System for Procurement of Micronutrient Powders (MNP)

Environmental footprinting of products. The policy outlook

Do Swedish property management companies have necessary conditions for environmental management?

Why We Are Reorganising the Swedish Land Registry

How To Complete A Third Cycle Programme In Business Administration

Syllabus Master s Programme in Global Health

AN ANALYSIS OF FOOD SAFETY MANAGEMENT SYSTEMS CERTIFICATION: THE PORTUGUESE CASE

Olli Sulin turku the northern Baltic s most interesting city

Reconciling the brown and the green agenda for water and sanitation

Increasing value through managing supplier relations - A study at Corporate Sourcing Saab AB

Equal Rights and Treatment for Roma in Moldova and Ukraine. Manual

Europe your new place of study

Curriculum for postgraduate studies in Micro-data Analysis

UBC seminar. Halmstad 9 11 May UBC Commissions on Urban Planning, Environment, Energy and Transport. Re-vitalize the city for sustainability

Architecture Landscape architecture Project management.


ISO Energy Management System

AUDIT REPORT, SUMMARY. Summary. Vattenfall a competitive leader in energy transition? (RiR 2015:6) SWEDISH NATIONAL AUDIT OFFICE

MOROCCAN SMART CITY DELEGATION TO STOCKHOLM

Karin Grundström, Curriculum Vitae

EMIL Education Information Markup Language A metadata model for education information

Environmental Management System (EMS) in Swedish governmental agencies

MAYFAIR NEIGHBOURHOOD FORUM GENERAL MEETING , MONDAY 5 th OCTOBER 2015 HAMILTON ROOM, FORSTERS LLP, 31 HILL STREET, W1J 5LS

THE FUNDRAISING AND PROJECT MANAGEMENT OFFICE

DCA Certifications Scheme

Bridging the gap - the use of methods from research results for implementation of Sustainable Urban Transport Plans with the example from Lund, Sweden

MBA Dissertation Summary

Application of Environmental Quality Objectives in Regional Scale Infrastructure Projects: a Swedish Example

GEM the first GI Erasmus Mundus Masters Course

Planprocessen i Sverige aktuell debatt och reformförslag

National Energy Benchmarking Framework: Report on Preliminary Working Group Findings

Our risk management framework Reviewed quarterly by our executive committee

Education and degrees

A Citizen s Movement for a Sustainable Future in Uppsala

IAS ACCREDITED INSPECTION AGENCIES: GUIDELINES FOR CONDUCTING INTERNAL AUDITS AND MANAGEMENT REVIEWS. Revised January, 2016

COMPARISON OF DIFFERENT ACCURACY IN A BUILDING LIFE CYCLE ASSESSMENT: A CASE STUDY ON THE THREE DIFFERENT ACCURACY OF INVENTORY

2016/17 Budget proposal Integrated Impact Assessment (IIA)

Economics, Law and Political Science

TRA Q NORDIC RELEASE - JULY 2013

The ISO standard

The Performance Management Process How to establish goals, objectives and KPI s

PHOTO AND FILM SKATEBOARD CARTOONING. Foto: DD, åk 3 SKATEPARK STUDIO PHOTO AND FILM STUDIO

Strategic perspectives on Life Cycle Assessment

Akelius Brainee Program

4.2 Project Procurement and Design

New approaches of river restoration: matching the EU blueprint to safeguard Europe s waters

Process Technology Implications of Procurement Processes: Some Initial Observations

Swedish integration policy for the 21 st century

ISO 9001: 2008 Boosting quality to differentiate yourself from the competition. xxxx November 2008

ÄSSA12, No English Translation Available, 30 credits Svenska som andraspråk 1 A, gy, 30 högskolepoäng First Cycle / Grundnivå

PREREQUISITES FOR HEALTH

A. Master of Science Programme (120 credits) in Development Studies (Masterprogram i utvecklingsstudier)

Strategy for the Work on CPM s LCA Database. Raul Carlson, August 1997

Identify your competencies

Main References Educational Development (Gibbs 2009) Some trends over time

Quality Standards and Certification for TSPs

COMMUNICATIVE LEADERSHIP

Transcription:

Managing sustainable construction a steering model for the building process Urban Persson, Lic Eng 1 1 Pedersen & Persson Project Management and Information. Raketgatan 14. S-22457 Lund. Sweden. Phone: +46 46 13 81 40. E-mail: pedersen.persson@telia.com 1. INTRODUCTION A large part, about 40% according to Rees (1999), of the Earth s turnover of resources is associated with buildings and building construction. But this is not only a question about natural recourses; human resources and economic, social and cultural considerations are also involved. A complex relationship must therefore be taken into consideration when realizing construction projects, since economic and social aspects also affect individual people. A major part of the decisions that affect the final building are made in the building process quite a long time before the building is finished. In order to gain an overall perspective on this relationship during the building process, one solution is to adapt the concept of sustainable development to the construction sector in order to produce sustainable construction, and to steer the building process in this direction and to find the main thread of the sustainability aspects of the project. The purpose of this paper is to propose a model for steering the building process in the direction of sustainable construction. The work has been carried out in the form of a control model that has later been evaluated in case studies. The paper refers mainly to the Swedish construction sector, but it would be possible to adapt the model to the local urban conditions of other industrial countries. Some of the main conditions of the model would probably have to be modified in order to adapt it to other types of local conditions. 2. SUSTAINABLE CONSTRUCTION The terms sustainable development and sustainable construction are relatively new in the construction sector. These terms have no simple definitions and confusion in understanding them is quite common in the sector. According to Agenda 21, sustainable development involves three main factors: ecological, economic and social development. According to Barrow (1997) it is necessary optimize these three main factors in order to achieve sustainable development. Kohler (1999) defined sustainable building in terms of these three factors. Using Kohler s model as a base, Persson (2001) produced an extended definition of sustainable construction including aspects of the urban areas of the industrial countries, actual legislation, the terms of Factor 10, the demands of the local markets and individual human rights of democratic influence.

3. THE URBAN MODEL Attention must be paid to the issue of sustainable construction in all the decisions arising out of the complex web of considerations associated with a common construction project. Another obstacle to understanding is that sustainable development and sustainable construction are cross-disciplinary issues concerning all the players involved in the building process. It is easy to hand over a specific question to the next person in the chain of decision makers without formulating any reason, the solve one site syndrome. As the project continues, all the project frames are set without addressing the issues of sustainable construction until it is too late for sustainability considerations. As the major part of the final cost of a construction project is set in the initial phase of the building process (Söderberg and Hansson 1993), the major part of the environmental and sustainability impact of the project is also fixed at the same time (indicated by Reed and Gordon 2000). As the building process continues, the decisions made have less effect of the final cost and the final environmental/sustainability impact of the project. The following modell, the urban model, is proposed for controlling the building process according to the principles for sustainable construction for the urban areas of industrial countries. Its purpose is to create a main thread of sustainability priorities throughout the building process. The model is intended to optimize the sustainability goals and targets of the property owner s organization and of the specific conditions, related to the site and to the purpose, of the actual construction project. The urban model is one aspect of the complete construction management process. 3.1 Structure of the urban model The main structure of the urban model consists of a verifiable sustainability programme, which is set as early as possible in the process. The model includes measurable requirements, which are given priority from an environmental and sustainability point of view. Figure 1 shows the principle of the model and the main information flow. The model is not supposed to be static with all its requirements fixed at the programme stage. The function of the model is to be dynamic and to allow requirements to be changed as decisions and conditions changes during the building process. After the end of the project, the model supports the planning of maintenance and could be used as a base of sustainability information for users and tenants. The model has to be compatible with the environmental management system of the property owner s organization. The principle of the urban model can be described by three main boxes, containing the specific conditions for the project, the general conditions of the property owner s organization and the sustainability programme for the project. The last-mentioned box act as a synthesis of the two first-mentioned and its concepts correspond to the environmental management standard of EN ISO 14001 (1996). The specific conditions for the project contain parts of the sustainability review, significant sustainability aspects and documented decisions made during the building process. The sustainability review is a review of the conditions specific of the site and surroundings of the building described in ecological, economic and social terms. With the sustainability review as a base, an evaluation of sustainability impacts is done, and significant sustainability aspects are set. The process of documenting decisions during the building process changes the

conditions for the final product - the building - and the conditions for sustainability targets on a continuous basis. Figure 1 The principle of the urban model. The general conditions of the property owner s organization include the project-related conditions, which are directly linked to the organization and its way of working. A main condition is the property owner s environmental policy and environmental management system, containing environmental objectives and the relevant parts of environmental targets. The general conditions of the property owner s organization also include conditions from

relevant general descriptions, standard solutions and standard blueprints according to the activities of the organization. The sustainability programme for the project, which is a result of an analysis and of prioritizing the specific conditions of the project and of the general conditions of the organization, consists of three main parts: the sustainability objectives, priority of the sustainability objectives and the sustainability targets. The sustainability objectives for the project depend on the environmental policy of the organization and the significant sustainability aspects of the sustainability review. This main part decides the direction of the project in a sustainability point of view; it formulates the main thread of the project as regards sustainability. Priority of the sustainability objectives is a relative order of preference of sustainability objectives because of preparation for forthcoming relative conflicts and to meet other forthcoming demands of the project. The sustainability targets are sustainability objectives in detailed and measurable units at levels from those of the system to those of single components. The methods of verification of the measurable sustainability targets are also established. It is possible to adjust the sustainability targets during the building process with confirmation in connection with documented decisions. A plan of sustainability checks is drawn up by all players involved in the project, based on the verifiable sustainability targets. The aim is to verify all the sustainability targets according to the methods mentioned in the sustainability programme for the project. Divergence and change of verification are a part of the documented decisions. The plan of sustainability checks is a part of the plan of quality checks. The sustainability programme for the project and the verifications according to the plans of sustainability checks act as the basis of the final documents for the project together with other documentation related to the project. From the final documents, sustainability information for the project is able to find its way to the property owner s organization for operation and maintenance, to users and to tenants, according to the organization s environmental management system. The property owner s organization for operation and maintenance exerts influence on the project through documented decisions based on its experience of operation and preventive maintenance. It is important to have continuous dialogue between users/tenants and the property owner during the process. In this way the users/tenants can influence the sustainability targets. The international standard for environmental management system, EN ISO 14001 (1996), is the basis of the main structure and the terms of environmental (sustainability) objectives and environmental (sustainability) targets. If the organization uses this standard for environmental management, it will find it easier to apply the model when it comes to environmental objectives, environmental targets and to adapting the final project to the organization s way of operating the building.

3.2 Case studies Persson (2001) tried the urban model in three case studies. One study concerned "Futurum", a general concept for the green building of apartments in urban areas by Riksbyggen and Lund Institute of Technology. One study concerned a new commercial building, an office, "Tyrenshuset" by Whilborgs and Tyréns, Malmö, Sweden. The third study related to a major maintenance project for apartments by LKF, Lund, Sweden. Figure 2 shows the significant sustainability aspects as a result of the case studies. Figure 2 The significant sustainability aspects of the case studies of the urban model 4. CONCLUSION The results of the case studies indicate that a sustainable construction requires optimization of the general significant sustainability aspects of ecological design, relevant rent for the users/tenants, low operating costs, co-operation between the property owner and the users/tenants and finally a well documented risk analysis of the indoor environment. The procedure for steering construction in a sustainable direction depends on the specific nature of the construction project itself. The main aspect of sustainable construction is to steer the construction process from an overall perspective with respect to the level of sustainability potential that the property owner is able to achieve, the specific conditions for the project and the level of the organization s environmental management system. The urban model has the potential to make the environmental objectives of the organization accord with the sustainability objectives of the specific construction project and with the environmental objectives of the operational organization. Coupling these factors together with a sustainable building process ensures that the organization s demands for continual improvement is met and that the project s ecological, economic and social aspects are optimized.

The urban model needs to be improved to make it an easily managed, project-flexible and user-friendly tool. The model also needs to be evaluated in more case studies of different types of construction projects. 5. REFERENCES Barrow, Chris J. 1997. Environmental and social impact assessment, an introduction. Arnold, London. EN ISO 14001:1996. Environmental managements systems Specification with guidance for use, SIS Förlag, Stocholm. Kohler, Niklaus. 1999. The relevance of Green Building Challenge: an observers perspective. Building Research & Information, Vol. 27, no. 4/5, pp. 309-320. Persson, Urban. 2001. Att styra ett hållbart byggande En definition av och en styrmodell för ett hållbart byggande (Swedish only). Department of Construction Management, Lund Institute of Technology, Lund. Report TVBP-01/1011 Reed, William G. and Gordon, Elliot B. 2000. Integrated design and building process: what research and methodologies are needed? Building Research & Information, Vol. 28, no. 5/6, pp. 325-337. Rees, William E. 1999. The built environment and the ecosphere: a global perspective. Building Research & Information, Vol. 27, no. 4/5, pp. 206-220. Söderberg, Jan and Hansson, Fredrik. 1993. Byggprocessen (Swedish only). Department of Construction Management, Lund Institute of Technology, Lund.