The role of project management offices (PMOs) in healthcare system



Similar documents
WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)?

Effectively Managing EHR Projects: Guidelines for Successful Implementation

MNLARS Project Audit Checklist

Implementing A Global Program Management Office Don Kingsberry, Director Global PMO, Hewlett-Packard Jake Stewart, Manager Global PMO, Hewlett-Packard

Measures and Metrics for PMO Success

Project Knowledge Areas

University of Wisconsin Platteville IT Governance Model Final Report Executive Summary

CDC UNIFIED PROCESS PRACTICES GUIDE

Project Management Office Best Practices

The State of the PMO 2012» A PM SOLUTIONS RESEARCH REPORT

TDWI strives to provide course books that are content-rich and that serve as useful reference documents after a class has ended.

MGMT 4135 Project Management. Chapter-16. Project Oversight

Sound Transit Internal Audit Report - No

Research Report. The Impact of Implementing a Project Management Office Report on the Results of the On-Line Survey

Strategic Plan for the Enterprise Portfolio Project Management Office Governors Office of Information Technology... Ron Huston Director

What you need to know about PMOs

How To Manage Project And Portfolio Management In Microsoft Office 2010

WVU. PROJECT MANAGEMENT LITE Training Manual for Project Managers and Team Members. Robert C. Byrd Health Sciences Center Chancellor s Office

Setting up and operationalisation of Enterprise PMOs

PMP Examination Tasks Puzzle game

Release Management: Effective practices for IT delivery

Creating a project management office (PMO)

PMO Starter Kit. White Paper

Role Reporting Information. Role Family Analyst (Why the family exists and how it adds value to EnergyAustralia)

Appendix A-2 Generic Job Titles for respective categories

Project Management for Everyone

ITS Project Management

EVOLVING THE PROJECT MANAGEMENT OFFICE: A COMPETENCY CONTINUUM

Project Management Office (PMO) Added value instead of administration

Developing a Project Management Office:

FIXING PROJECT MANAGEMENT: A MUST-HAVE

How Technology Supports Project, Program and Portfolio Management

Chapter 4. The IM/IT Portfolio Management Office

Project initiation - 5 Mistakes Portfolio Managers Make

Project Management Best Practice Benchmarks

Risk management and the transition of projects to business as usual

Taking Your PMO to the Next Level:

What Every Project Manager Should Know Trends in Project Governance

2012 National BDPA Technology Conference. Defining Project and PMO Metrics

PMO Director. PMO Director

Creating a Project Management Office (PMO)

October 7, Presented to. The PMI Washington DC Chapter. Pedro Agosto. Director of Client Services, XA Systems, LLC.

WHITE PAPER APRIL Leading an Implementation Campaign to Address the Convergence of Healthcare Reform Initiatives

Project Management Office Charter

Assessing the Appropriate Level of Project, Program, and PMO Structure

Since its inception, the PMO has functioned to support government entities in implementing project management practices through the:

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT OFFICES A PRACTICAL GUIDE TO SETTING UP A PMO (WITH EXAMPLES)

The Manager s Guide to Avoiding 7 Project Portfolio Pitfalls

Prepared for: Prepared by:

Develop Project Charter. Develop Project Management Plan

Selecting a project management methodology

IT Governance (Worthwhile Exercise?) January 10, 2013 Presented by Chad Murphy, CISA

Project Management. An Overview for IT. Author: Kevin Martin & Denise Reeser

Providing standards, methodologies and a set of PM tools. Promoting project management within the organisation

Use of Measurements and Metrics for the Project Management Office (PMO)

Enterprise Business Service Management

Project Management Office (PMO) Charter

Best Practice Methodologies for the Project Management Office (PMO)

Project Management for Implementing the Smart Grid By Power System Engineering, Inc. Abstract PM Methodology Using a Repeatable Project Management

Enterprise Risk Management & Information Technology

Office of the Auditor General AUDIT OF IT GOVERNANCE. Tabled at Audit Committee March 12, 2015

Computing Services Network Project Methodology

INFORMATION TECHNOLOGY PROJECT MANAGER

Project Management Plan for

AGILITY. The competitive advantage of ORGANIZATI talent management. Pmi s PulsE of the ProfEssion in-depth report. March 2013

Information Technology Services Project Management Office Operations Guide

THE COMPLETE PROJECT MANAGEMENT METHODOLOGY AND TOOLKIT

Project Management Improving Performance with KPIs Shelia Darby, MBA, PMP Darby Consulting

A Privacy Officer s Guide to Providing Enterprise De-Identification Services. Phase I

Project Management Office Best Practices

2007 & 2008 Dennis L. Bolles and Darrel G. Hubbard 1

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

A Guide to Successfully Implementing the NIST Cybersecurity Framework. Jerry Beasley CISM and TraceSecurity Information Security Analyst

ENTERPRISE RISK MANAGEMENT FRAMEWORK

MANAGED SERVICES FOR THE PROGRAM MANAGEMENT OFFICE

Information Technology Integration Putting IT to work in driving deal success

PM Services. Our Corporate Profile and Credentials

The Integration of Strategic Planning and Portfolio Management

To have or not to have a PMO - is that the right question? Transforming knowledge into action. To have or not to have a PMO 1

Operations, Quality and Lean Six Sigma Solutions

Change Management Trends in Governance Structures

Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management. Introduction. Alfred Sankara, DigiBridge TelCo

Project Management. In this Guide

One IT Governance. Maggie Jesse, Tim Shie. Romy Bolton

Sources Sought Notice for Project Management Oversight Services Reference # FTA-08-PMO. Statement of Capabilities Presented to

Final Report. Audit of the Project Management Framework. December 2014

The PMP Application Process

Establishing a Quality Assurance and Improvement Program

R a p i d I m p l e m e n tat i o n ARIES ARIES METHODOLOGY OVERVIEW

Application Overhaul. Key Initiative Overview

Driving Excellence in Implementation and Beyond The Underlying Quality Principles

Defining a Governance Model for Portals

SENIOR INFORMATION SYSTEMS MANAGER

How To Integrate Hr

A PROJECT MANAGEMENT OFFICE (PMO) FRAMEWORK FOR SUCCESSFUL IMPLEMENTATION OF INFORMATION TECHNOLOGY PROJECTS

Executive Dashboards:

Quick Guide: Meeting ISO Requirements for Asset Management

EDWARDS PROJECT SOLUTIONS NORTH AMERICAN INDUSTRY CERTIFICATION SYSTEM (NAICS) CODES QUALIFICATIONS WITH FULL DESCRIPTIONS

Position Title: Management Info Chief. Working Title: Technical Project Management Section Chief

Transcription:

ISSN: 2347-3215 Volume 3 Number 6 (June-2015) pp. 429-435 www.ijcrar.com The role of project management offices (PMOs) in healthcare system Samad Agha Mohamadi 1, Seyed Yaser Hariri 2, Raheleh Mousavi 3 and Esmaeil Sabzikaran 4* 1 M.A. in Defense Administration and Faculty Member of Command and Control, Khatam Anbia Air Defense University, Tehran, Iran 2 M.A. in Khatam Anbia Air Defense University, Tehran, Iran 3 M.A. in AJA University of Medical Sciences, Tehran, Iran 4 M.A. in Public Administration and Faculty Member of Command and Control, Khatam Anbia Air Defense University, Tehran, Iran *Corresponding author KEYWORDS Management, Healthcare, Office, Project. Introduction A B S T R A C T The main problems of the most healthcare settings is nonexistence of consistence management approach, lack of prioritization, no formal tracking, lack of communications, lack of functional user involvement, as well as absence of on-time or on-budget programs. Thus, these settings need potentially to the systems responsible to scheduling and planning the projects, implementing project servers, training healthcare staffs, and finally improvement of project success rate by standardization of project processes. Here, we tried to describe and review different aspects of these systems term as the project management office (PMOs) in each healthcare system. The presence of inconsistence management programs is one of the main problems in most health care settings that its solving is now challenging. The main incapability of such managements is potentially referred to lack of prioritization, no formal tracking, lack of communications, lack of functional user involvement, as well as absence of ontime or on-budget programs. In this context, the appearance of an appropriate project management system aimed to improve these pitfalls seems to be necessary. These systems are usually structured as project management offices (PMOs) that seek the standards of project processes, describe main responsibilities of chief managers of healthcare systems and train them as well as supervise implementation of various health care processes. The present review came to address the role of PMOs in project management systems with the approach to healthcare management systems. 429

Project management office: A means for system integration The project management office (PMOs) is one of the main components of management body for the projects and portfolios within its scope [1]. The first applicable step of PMOs in each project is to define and prioritize the goals of target organization that performing this step is necessary to organize its further steps. In fact, the second step is defining what constitutes a project, how projects interrelate into a program and then identifying how these programs pursue clearly outlined portfolio objectives such as the main priorities of a hospital [2]. PMOs have a critical role for defining and structuring the best programs for managing and implementing projects managers responsibilities [3]. The best programs are usually defined as a group of interrelated projects and subprojects to obtain benefits and a level of control not possible by an individual project management [4]. In this regard, a portfolio describes a collection of programs, projects and other works that are grouped together to facilitate effective management of the work entailed in order to meet strategic business objectives [4,5]. Thus, the type and complexity of a PMO in an organization is directly dependant to the portfolio complexity and worthiness of project managers. The Project Lifecycle and Tools The PMO s operation in a specific project is usually framed around the lifecycle of that project. The main categories inherent in a lifecycle include the initiating phase, planning phase, executing and controlling phase and, finally, the closing phase [6]. Depending on the complexity and scope of target organization, it may also have an identification phase. In case the project chronology and timetable is setting up through a lifecycle, definition and description of all activities, deliverables, and decisions that occur at each phase is necessary. In this section, we describe the different phases of PMOs necessary to achieve its goals [10]: a) Initiation phase: this stage can be got on using project charters that should define the project at a high level and include the components of problem statement, project objectives and goals, team leads and members, expected benefits, constraints, and dependencies. b) Planning phase: in this step, the project manager should describe and highlight his or her expected project outcome, the work steps, expectations of the project team members, the time of work performance, any costs associated with the work, and the time of the team meetings. Totally, the main tool using in this step is the work plan that can be perfectly as all project related tasks and key milestones with specific timeframes. On the other hand, in a perfect work plan, responsibilities of all team members for each task are minutely listed. c) Execution phase: in this phase, the required initiatives and tasks are realized and set out in the specific work plan on a clear coordination and communication. In this step, in fact, the PMO is responsible for getting the project moving and tracking implementation. For effective planning, regular meetings should be set up by project manager and PMO. d) Monitoring and controlling phase: the main role of this phase is monitoring the Key Performance Indicators that should have a target established and be measured on a weekly basis. Key Performance Indicators can be managed through dashboards which help visualize project 430

progress and keep track of goals, budget, and schedule. e) Closing phase: For closing a project, the main activities should be to review project performance and discuss lessons learned; the project manager should consider archiving project files in a centralized database so that materials can be easily accessed for future projects; and the team itself should finally receive recognition and celebrate its achievements. The role of project management offices in healthcare systems Project management offices (PMOs) are regional resources established for managing and overseeing the performance of strategic priority projects for any structured private or governmental health organizations [11]. These offices are usually consist of expert project managers, analysts, specialist of process improvement, and trained administrative staffs acknowledged to different aspects of healthcare priorities and needs. In healthcare systems, these offices potentially focused on clinical and healthcare service delivery projects that span multiple sites and programs [11,12]. The main goal of the PMOs in healthcare organizations is increase of effectiveness and efficiency of healthcare services by aligning sanitary and medical needs and resources, integrating services across sectors, increased service quality and evidence-based practice in clinical settings, emphasizing health promotion and prevention, and improved accountability in health management systems [13]. Thus, main key components of PMOs in healthcare systems can be organized as: prevention and promotion, treatment and support, community, health system staff, accountability in healthcare management system, as well as research and education. The main structure of PMOs in healthcare systems is based on delivery of successful heath projects in health systems and organizations [14]. For this aim, PMOs apply two approaches including 1) project management approach and infrastructure, and 2) selection of strategic integration projects [15]. The term of the PMOs infrastructure is referred to the creation of the PMO, competencies in project management, analysis, and process improvement, Knowledge of the entire system, and disciplined approach to project management [16]. In healthcare systems, infrastructure should be structured to produce standardized tools and templates for healthcare management projects, identification and monitoring of project metrics, leadership alignment on healthcare projects, clarity of roles and responsibilities in different health management subgroups, focus on execution, and introduction of new approaches to problem solving in healthcare systems [15,16]. For instance, with respect to the role of PMOs in projects of process standardization in nursing services, the main PMOs goals should be approached to critical care chief nursing education and Infection control practices. In total, around healthcare systems, PMOs responsibilities should be covered education and training, especial consultation, and healthcare processes improvement. Responsibilities of PMOs in healthcare systems The responsibilities of PMOs in the healthcare settings can be described as the main duties, risk management, financial Management, and staff Management. With respect to the main duties, a PMO should manage the full healthcare project management lifestyle [13-16]. On the other hand, the PMOs is responsible for managing 431

implementation of different healthcare policies, monitoring and control of healthcare system to ensure the successful management of the project, and reporting of all corporate initiatives in the healthcare program. In addition, the PMO should lead and supervise staffs to oversee the impacts and interdependencies between works and program [17]. Moreover, it should effectively manage allocation of resources within the projects to meet work fluctuations and budget as well as time constraints in the delivery process for the main purpose of creating a high-performing healthcare team. Overseeing the creation and maintenance of project methodologies and supporting collateral material is another duty of a PMO to ensure all delivery models are operating to the highest quality. Finally, it should develop a client satisfaction program and creates a continuous improvement process to incorporate the needs of successful projects performing [17,18]. Regarding risk management, the PMO in healthcare develops a comprehensive quality assurance or risk management plan to identify risks for managing or eliminating the risk. This management approach help to report and manage major risk profile affect on project timeline, budget or objectives. For financial management, it should provide monthly accruals, forecasts, and project statuses by the due date established that result in maintaining current statements of work, tracking and billing sheets. Finally for staff management, a PMO is responsible for train and supervise healthcare project managers and Project coordinators and it should prepare and report parallel annual feedback of its performance assessment [15-18]. Table.1 Responsibilities and duties of the project management offices (PMOs) Responsibilities of the PMOs Quality assurance Portfolio management Personnel development Methodology Project support Description of the duties - Quality audits - Quality controls - Quality standards - Project selection - Portfolio monitoring - Reporting metrics - Manage skills - Training and development - Certification tracking - Project resource management - Processes & methods - Templates - Forms - Standards - Policies - Vendor management - Monitor ongoing projects - Tools management - Change management - Document publication management - Knowledge management - Website 432

Figure.1 The main goals and targets of the project management offices (PMOs) Figure.2 Optimized Project Management Office Structure 433

Conclusion In most of the healthcare settings, some initial projects are not aligned with healthcare strategies, some projects accompanied with delaying, and some uncontrolled barriers are existed. Under the leadership and supervision of a PMO, the healthcare system objectives are effectively defined and its-related technological projects can be potentially managed. This can finally result in managing, programming, and structuring different loops of projects lifestyles including planning, prioritizing, budgeting, and executing. Finally, the main goals of PMOs in healthcare systems will be implementation of a project portfolio management tool that refining the benefits methodology, and continuing the advancement of the project management methodology. In total, the main goal of the PMOs in healthcare organizations is increase of effectiveness and efficiency of healthcare services by aligning sanitary and medical needs and resources, integrating services across sectors, increased service quality and evidence-based practice in clinical settings, emphasizing health promotion and prevention, and improved accountability in health management systems. In fact, according to this fact that the majority of healthcare systems particularly in developing nations are lack the regulatory system on the quality of health management formed as PMOs, establishment of such managing groups for evaluating and improving the quality of healthcare services and standardizing them is potentially recommended. References [1] Seidl P, J. AHIMA. The art and science of project management, 2003; 74: 33-37. [2] Zimmer, B, T. Project management: a methodology for success. Hosp Mater Manage Q, 1999; 21: 83-89. [3] Stanleigh, M. The strategic importance of the enterprise project management office, Business Improvement Architects, 2012; Available in: [www.bia.com]. [4] Hill, G, M. Evolving the project management office: a competency continuum. Information Management System, 2004; 1: 45-48. [5] Zimmer, B, T. Project management: break through or bust. Hosp Mater Manage Q, 1999; 21: 93-99. [6] Smith, G, R. Project leadership: why project management alone doesn't work. Hosp Mater Manage Q, 1999; 21: 88-92. [7] Isola, M. & Polikaitis, A. & Laureto, R, A. Implementation of a Project Management Office (PMO)- experiences from year 1. J Health Info Manage, 2006; 20: 79-87. [8] Kent, Crawford, J. & Cabanis, Brewin, J. How a Strategic Project Office solves business problems. Chief Project Officer online magazine, 2005; Available in: [www. pmsolutions.com]. [9] Project management group, Occas Pap R Coll Gen Pract, 2002; 81: 29. [10] Hobbs, B. The Multi-Project PMO: A Global Analysis of the Current State of Practice. Project Management Institute, 2012. Available in: [www.pmi.org]. [11] Hobbs, B. & Aubry, M. The project management office (PMO): a quest for understanding. PMI, 2010. Available in: [www.pmi.org]. [12] Pickens, S. & Solak, J. Successful healthcare programs and projects: organization portfolio management 434

essentials. J Health Info Manage, 2005; 19: 19-27. [13] Hills, L, S. Forty project management strategies for the medical practice staff. J Med Pract Manage, 2010; 25: 271-275. [14] Becker, J. & Rhodes, H. Enterprise project management is key to success: addressing the people, process and technology dimensions of healthcare. J Health Info Manage, 2007; 21: 61-66. [15] Barker, M. & Klopper, H. Community participation in primary health care projects of the Mulders drift Health and Development Programmer. Curationis, 2007; 30: 36-47. [16] Stromsikova, D. & Skackova, D. Searching excellence in project management. Bratisl Lek Listy, 2001; 102: 253-259. [17] Morrison, F. The standing operational implementation team--playing a vital role in successful project completion, implementation of operational initiatives, and process improvement. J Health Info Manage, 2005; 19 (1): 28-33. [18] Berry, R. Project management for nurses: guidelines for success. J In Traven Nurse, 1994; 17: 28-34. 435