Before UTTARAKHAND ELECTRICITY REGULATORY COMMISSION. Coram

Similar documents
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI

Determination of cost of power generation for Dongamahua captive power plant of Jindal Steel & Power Ltd. from FY till FY

BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION BAYS NO , SECTOR 4, PANCHKULA HARYANA

Delhi Electricity Regulatory Commission Viniyamak Bhawan, C Block, Shivalik, Malviya Nagar, New Delhi 17

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION. No. L-1/(3)/2009-CERC Dated the 7 th August 2009

INDEX S. No. PARTICULARS Note:

02 July VIPL Response to balancedata gaps 1 / Queries Set Case 36 of 2015 Data Gaps/Deficiencies on the Petition submitted by VIPL

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO , SECTOR 34-A, CHANDIGARH. Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7.

Government of India Ministry of Power Central Electricity Authority Sewa Bhawan, R.K. Puram New Delhi [ISO: 9001: 2008]

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM IN THE MATTER OF

TDS not deductible on freight chargers shown separately in Goods Purchase Bill

Appellate Tribunal for Electricity (Appellate Jurisdiction) APPEAL No. 297 of 2013

RAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR Petition No. RERC 456/14, 457/14, 458/14, 442/14, 444/14 & 447/14

BEFORE THE MEMBER, MOTOR ACCIDENT CLAIMS TRIBUNAL: CACHAR: SILCHAR: ASSAM

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 7/MP/2013

KERALA STATE ELECTRICITY REGULATORY COMMISSION

IN THE HIGH COURT OF JHARKHAND AT RANCHI

MINUTES OF MEETING OF THE STANDING COMMITTEE OF EXPERTS TO INVESTIGATE THE FAILURE OF 220 KV AND ABOVE VOLTAGE CLASS SUBSTATION EQUIPMENT HELD ON 04

117. Works contract Services

$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI. Judgement delivered on: 30 th November, BAIL APPLN. NO.2333/2015. Versus

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH

PROCEDURE FOR ISSUANCE OF RENEWABLE ENERGY CERTIFICATE TO THE ELIGIBLE ENTITY BY CENTRAL AGENCY

DISCLOSURE DOCUMENT FOR PORTFOLIO MANAGEMENT

IN THE MOTOR ACCIDENT CLAIMS TRIBUNAL SONITPUR, TEZPUR. MAC Case No. 93 of 2010

IN THE COURT OF THE DISTRICT JUDGE-CUM

CENTRAL INFORMATION COMMISSION Appeal No. CIC/AT/A/2009/00422 dated Right to Information Act 2005 Section 19

FOR PROCUREMENT OF MATERIALS UNDER DEPOSIT / APDRP WORKS

Contract Bond No. 37/G.I. Pipe/12-13 dated:

Short Term Training Courses

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

BRAITHWAITE & CO LIMITED (A Government of India Undertaking)

ASSOCIATION OF MUTUAL FUNDS IN INDIA LEVY OF SERVICE TAX VIS-À-VIS MUTUAL FUNDS A GUIDANCE NOTE

BEFORE THE ADJUDICATING OFFICER SECURITIES AND EXCHANGE BOARD OF INDIA, MUMBAI

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI

National Grid Electricity Transmission RIIO-T1: Initial Proposals consultation response Supplementary information Strategic Spares

DELHI METRO RAIL CORPORATION LIMITED. (A Joint Venture of Govt. of India & GNCTD) MASS RAPID TRANSPORT SYSTEM PHASE III. Contract: - CE -16 VOLUME-6

IN THE MOTOR ACCIDENT CLAIMS TRIBUNAL SONITPUR: TEZPUR. MAC Case No. 147 of 2013

DRAFT KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE. No. 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China

CIRCULAR. CIR/CFD/FAC/62/2016 July 05, Sub: Revised Formats for Financial Results and Implementation of Ind-AS by Listed Entities

WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED. (A Govt of West Bengal Enterprise)

Jammu & Kashmir State Electricity Regulatory Commission

TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT

State Insurance and Provident Fund Department (General Insurance Fund) Group Personal Accident Insurance Policy

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : EMPLOYEES COMPENSATION ACT, 1923 FAO 53/2012 Judgment delivered on:

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL NO OF 2012 (Arising out of SLP (C) No.9516 of 2010) VERSUS JUDGMENT

SECURITIES AND EXCHANGE BOARD OF INDIA

Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme

Licence condition handbook

Draft Solar Energy Purchase Agreement (EPA) subject to approval by TNERC

Detailed Vetting Report

Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading. Ramandeep Kaur Aujla S.NO

Jammu & Kashmir State Electricity Regulatory Commission

CENTRAL INFORMATION COMMISSION Club Building (Near Post Office) Old JNU Campus, New Delhi Tel: File No.CIC/DS/A/2011/001995/RM

DELHI TRANSCO LIMITED

a. Proposals shall be submitted in a sealed envelope and addressed as follows:

AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff. Risk Allocation in Construction Contracts

Security Policy Review: Credible Event Management. Scope and Methodology Draft for Industry 2014

To whom application is to be filed

BEFORE THE MEMBER, MOTOR ACCIDENT CLAIMS TRIBUNAL: CACHAR: SILCHAR: ASSAM

Customer-Led Network Revolution Electrical Energy Storage Cost Analysis

TCIL/08/2776/01/2013 Dated: Sub: CAR Insurance Policy for Lakhnadone-Ghansore BOT Road Project

PROCEDURE(S) OF THE NATIONAL GLP OFFICE

CIVIL APPEAL NO. 10 OF 2016 (ARISING OUT OF SLP (CIVIL) NO OF 2015)

2.2 Quality Standards and Compliances The BIS has specified quality standards vide IS 1011:1992. Compliance with PFA Act is necessary.

MAC CASE NO.185/2013: U/S 166 OF THE M.V.ACT. Member, MACT, Golaghat

CODE OF CONDUCT FOR PREVENTION OF INSIDER TRADING. (Amended version as approved by the Board of Directors of the Company)

F.No. 334/8/2016-TRU Government of India Ministry of Finance Department of Revenue (Tax Research Unit)

Updated November 20, Director, System Planning

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

HEADING OF JUDGMENT IN CONSUMER CASES : BEFORE THE PRESIDENT, DISTRICT CONSUMER FORUM, GOLAGHAT. Consumer Protection Case No. 2/2010.

OVERLAPPING OF SERVICE TAX AND VAT

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : COMPENSATION MATTER. Decided on: 02nd March, 2015 MAC.APP. 38/2014 MAC.APP.

DRAFT ORDER (SUO-MOTU)

BASIC CONCEPTS AND FORMULAE

2.1 Compliance with PFA Act is mandatory. Adherence to AGMARK is advisable.

PROFORMA OF POWER OF ATTORNEY BY THE JOINT VENTURE/ CONSORTIUM MEMBERS (Non Judicial Stamp of Rs.100/- duly notarized)

ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION 4 th & 5 th Floors, Singareni Bhavan, Red Hills, Hyderabad O.P.No.

DRAFT DISTRICT MINERAL FOUNDATION TRUST DEED THIS DEED OF TRUST EXECUTED AT ONTHIS THE DAY OF IN THE YEAR TWO THOUSAND FIFTEEN.

VEGETABLE OIL REFINERY

1.0 Objective. 2.0 Background 1/7

TRANSMISSION SERVICE RATE SCHEDULE Effective from 1 April 2015

No. 45TH. Plaintiff EDGEWOOD INDEPENDENT SCHOOL DISTRICT files its Original Petition

HIGH COURT FORM (J) 3 HEADING OF JUDGEMENT IN APPEAL. Dist. Cachar. In the Court of Addl. District Judge, Cachar, Silchar.

allowed. Request for inclusion and consideration of ISO 2008:9001 quality certification. CMMI Level 5 : 10 Marks CMMI Level 3 : 07 marks ISO: 05

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : MOTOR ACCIDENT CLAIMS TRIBUNAL. Date of decision: 12th December, 2012 MAC. APP. 745/2011.

System. Applied Electro-Magnetics Pvt Ltd.

INSURANCE BUILT BY MASTER BUILDERS FOR MASTER BUILDERS. Master Builder. Construction Works Public and Products Liability Insurance

IT Department. Circular No.: MCX-SX/IT/2845/2015 March 30, Market datafeed provided by the Exchange to the members

CHILLY AND TURMERIC POWDER

Early Learning and Child Care Initiative

ICM Project Station Infrastructure and Equipment

AGREEMENT BETWEEN BLUE CROSS & BLUE SHIELD OF MISSISSIPPI, A MUTUAL INSURANCE COMPANY, [CLEARINGHOUSE OR BILLING AGENCY] AND [PROVIDER]

(REVISED)

Delhi Electricity Regulatory Commission Viniyamak Bhawan, C Block, Shivalik, Malviya Nagar, New Delhi 17

Company Profile. Introduction

Notice Limited Tender Enquiry / Notice Inviting Quotations. No.NIQ- / / /JMI/2013 Date:-

v/s. Western India Art Litho Works Pvt. Ltd.

No.DNHPDA/TENDER/107(104)/2014 Dated: EXPRESS OF INTEREST

Transcription:

Before UTTARAKHAND ELECTRICITY REGULATORY COMMISSION Petition No. 10 of 2016 In the Matter of: Investment Approval for Procurement, Erection & Commissioning of 40 MVA, 132/33 kv Transformer and replacing the defective Transformer at 132 /33 kv Sub-station Roorkee. In the Matter of: And Power Transmission Corporation of Uttarakhand Limited (PTCUL) Vidyut Bhawan, Near ISBT Crossing, Saharanpur Road, Majra, Dehradun....Petitioner Coram Shri Subhash Kumar Shri K.P. Singh Chairman Member Date of Order: July 27, 2016 ORDER This Order relates to the Petition filed by Power Transmission Corporation of Uttarakhand Ltd. (hereinafter referred to as PTCUL or the Petitioner ) seeking approval of the Commission for Procurement, Erection & Commissioning of 40 MVA, 132/33 kv Transformer and replacing the defective Transformer at 132 /33 kv Substation Roorkee. 2. The Petitioner vide its letter No. 223/MD/PTCUL/UERC dated 11.02.2016 submitted Petition for seeking approval of the Commission for Procurement, Erection & Commissioning of 40 MVA, 132/33 kv Transformer and replacing the defective Transformer at 132 /33 kv Sub-station Roorkee under UERC (Conduct of Business) Regulations, 2014 and Para 11 of Transmission and Bulk Supply Licence [Licence No. 1 of 2003].

3. On preliminary examination of the Proposal, some deficiencies/ shortcomings, pertaining to the present status, IDC, quantity variation and cost escalation, load etc., were issued by the Commission and thereafter, discussions were held between officers of UERC and PTCUL. On the deficiencies pointed out, PTCUL submitted its clarification/reply vide letters No. 641 dated 21.04.216 & 976 dated 06.06.2016 to the Commission. 4. Summary of the submissions and subsequent clarifications made by the Petitioner is as follows: (1) 132/33 kv Sub-station, Roorkee is having capacity of 100 MVA (2x40 MVA and 1x20 MVA) and all the Transformers are almost 90% loaded. Due to occurrence of major fault in one of the 40 MVA Transformer i.e. Transformer- III, the affected area namely 33 kv Landhora Feeder (connected load- 27 MVA), 33 kv Khera Mughal Feeder (connected load-15 MVA) and 33 kv Devi Bhoomi Industrial Feeder (connected load-5 MVA) was forced for the load shedding as the capacity of remaining Transformers in the Sub-station was not sufficient for catering the load of the faulty Transformer. (2) To deal with the said emergent situation, PTCUL decided to shift a new transformer available at 132 kv S/s Jwalapur to the aforesaid Sub-station. (3) The cost proposed by the Petitioner for the works in the revised DPR and the Sl. No. actual cost incurred (as per purchase order No. 1851 dated 09.09.2015) has been tabulated below: Description Cost claimed by PTCUL in its Revised DPR Cost as per PTCUL s Orders I Supply Supply of 40 MVA 132/33 kv rating T/F with direct temperature measurement system, Nitrogen 1 Injection, Fire prevention cum Extinguishing system 2,96,84,216 2,96,84,216 alongwith online DGA (inclusive of Freight, Insurance, Excise duty & Cess and Sales Tax/VAT) Total I 2,96,84,216 2,96,84,216 II Erection A Work of shifting of defective 40 MVA T/F to nearby plinth 2,70,000 2,50,000 B Work of making plinth for 40 MVA T/F after shifting from main foundation 99,900 99,350 C Shifting work from 132 kv S/s Jwalapur and 5,07,500 5,60,000 Page 2 of 6

Sl. No. Description Cost claimed by PTCUL in its Revised DPR Cost as per PTCUL s Orders commissioning work of 40 MVA T/F D Supervision of testing & commissioning of 01 No. 40 MVA T/F with Direct Temperature Measurement System, Nitrogen Injection, Fire prevention cum 40,000 40,000 extinguishing system alongwith online DGA make IMP E Work of Erection for 40 MVA T/F (excluding foundation work) with all accessories 8,64,000 8,64,000 F Civil work for making foundation and pit for NIFS system 58,800 58,800 Total II. 18,40,200 18,72,150 Total (I + II) 3,15,24,416 3,15,56,366 3% Contingency charges 9,45,732.48-15% Centage charges 48,70,522.27 - IDC (proposed by the Petitioner for 5 months) 7,00,000.00 - Grand Total 38040671 3,15,56,366 Values in above table are excluding of Service Tax. 5. Copy of extracts of the Minutes of 51 st Board Meeting of the Petitioner Company has been enclosed with the Petition, wherein the Petitioner s Board has approved the proposal with a funding plan of 70% through loan assistance by financial institutions and balance 30% as equity proposed to be funded by GoU. Commission s observations, views and decision 6. In accordance with para 11.3 & 11.5 of Transmission & Bulk Supply Licence [Licence No. 1 of 2003] licensee is required to make an application for obtaining prior approval of the Commission for the scheme involving major investments beyond Rs 250 Lacs. However, in view of immediate restoration of supply of the affected area, the Commission decides to relax the provisions of para 11.3 & 11.5 of Transmission and Bulk Supply Licence. 7. The Commission observed that the Petitioner is augmenting its transmission system on short term need basis and its horizon for transmission planning is devoid of long term planning. Further, the Commission is of the view that the Petitioner is indifferent about compliance of contingency criteria as mentioned in the CEA Manual on Transmission Planning Criteria, 2013. 8. Further, the Commission observed that the Petitioner is frequently approaching the Commission for various augmentation requirements in its network in the Page 3 of 6

Roorkee & Haridwar area which prima-facie indicates Petitioner s lackadaisical approach towards long term planning for catering the power requirements of the area and its non-compliance to the N-1 contingency criteria mentioned in the CEA Manual on Transmission Planning Criteria, 2013. 9. On further examination of the proposal and subsequent submissions/clarifications, the Commission has observed that: (1) The faulty 40 MVA Transformer-III of 132 kv S/s Roorkee got defective and required immediate replacement for avoiding prolonged rostering condition in Landhora, Khera Mughal & Devi Bhoomi Industrial feeders of Roorkee area. PTCUL as an alternate arrangement decided to shift 40 MVA transformer (which was destined for installation at 132 kv S/s Jwalapur) from 132 kv S/s Jwalapur to 132 kv S/s Roorkee for immediate restoration of supply in the affected area. (2) Under the circumstances brought before the Commission in the matter, the Commission observed that for immediate power restoration, shifting of Transformer was justified, however, the Commission is of the view that the 40 MVA Transformer proposed in the instant Petition should be placed at 132/33 kv S/s Jwalapur from where the said capacity of transformer has already been shifted to Roorkee Substation. (3) The Commission observed that the works carried out for installation and commissioning of Transformer are broadly categorized as follows: (i) (ii) Work of shifting of defective 40 MVA Transformer to nearby plinth at 132 kv S/s Roorkee. Work of making plinth for defective 40 MVA Transformer after shifting it from the main foundation. (iii) Shifting of 40 MVA Transformer from 132 kv S/s Jwalapur to 132 kv S/s Roorkee. (iv) Supervision of testing & commissioning of 01 No. 40 MVA Transformer with Direct Temperature Measurement System, Nitrogen Injection, Fire Page 4 of 6

prevention cum extinguishing system alongwith online DGA make IMP. (v) Work of Erection for 40 MVA Transformer (excluding foundation work) with all accessories. (vi) Civil work for making foundation and pit for NIFS system. (4) On examining the financial aspects of the proposal, it has been observed that the Petitioner has claimed contingency @ 3% and centage charges @15% on the total project cost. Since, the work has already been executed and actual cost incurred in the project is known to the Commission, therefore, the Commission has decides not to allow the same. Further, with regard to IDC, the Commission observed that the IDC amount has already been allowed by the Commission while allowing the investment for increasing capacity of 132/33 kv S/s Jwalapur from 2x40 MVA to 3x40 MVA in the Order dated 23.07.2015. Furthermore, the time taken in installation and commissioning of the Transformer was only nine days and for this duration of execution, the impact of which on IDC already allowed earlier vide the said Order works out to be negligible, therefore, the Commission has not considered the same. (5) The Commission observed that the rate for supply of 40 MVA, 132/33 kv Transformer in the Schedule of Rates (SoR) of PTCUL for FY 2014-15 is Rs. 3,28,31,982/-, whereas, the proposed cost in the revised DPR is as per PTCUL s purchase order No. 1851 dated 09.09.2015, i.e Rs. 2,96,84,216/. Hence, the Commission has considered the actual cost of supply of the transformer at which purchase order was issued by PTCUL. Further, the cost of erection of 40 MVA Transformer as per SoR of PTCUL for FY 2014-15 is Rs. 5,51,761. Thus, the total cost as per SoR for supply & erection of 40 MVA Transformer is Rs. 3,33,83,743 [Rs. 3,28,31,982 (for supply)+ Rs. 5,51,761(for erection)], inclusive of all the taxes. 10. Since, the cost actually incurred in supply, erection and commissioning of the Transformer is Rs. 3,15,56,366 (exclusive of Service Tax), and the same is less than Page 5 of 6

the cost of supply, erection & commissioning of 40 MVA Transformer as per SoR of PTCUL for FY 2014-15 i.e. Rs. 3,33,83,743 (inclusive of all the taxes), therefore, the Commission has decided to grant approval for the investment of Rs. 3,15,56,366 only and the same has been presented in the Table given below: S. No. Description Cost considered by the Commission I Supply 1 Supply of 40 MVA 132/33 kv rating T/F with direct temperature measurement system, Nitrogen Injection, Fire prevention cum Extinguishing system alongwith online DGA 2,96,84,216 (inclusive of Freight, Insurance, Excise duty & Cess and Sales Tax/VAT) Total I 2,96,84,216 II Erection A Work of shifting of defective 40 MVA T/F to nearby plinth 2,50,000 B Work of making plinth for 40 MVA T/F after shifting from main foundation 99,350 C Shifting work from 132 kv S/s Jwalapur and commissioning work of 40 MVA T/F 5,60,000 D Supervision of testing & commissioning of 01 No. 40 MVA T/F with Direct Temperature Measurement System, Nitrogen Injection, Fire prevention cum extinguishing system alongwith 40,000 online DGA make IMP E Work of Erection for 40 MVA T/F (excluding foundation work) with all accessories 8,64,000 F Civil work for making foundation and pit for NIFS system 58,800 Total II 18,72,150 Total (I + II) 3,15,56,366 3% Contingency charges - 15% Centage charges - IDC (proposed by the Petitioner for 5 months) - Grand Total 3,15,56,366 Values in above table are excluding of Service Tax. 11. In view of the observations made at para 8 above, the Commission also directs the Petitioner to conduct a comprehensive system study for the Roorkee and Haridwar area and submit its report within 1 month of this Order covering the long term planning in the area. Ordered accordingly. (K.P. Singh) Member (Subhash Kumar) Chairman Page 6 of 6