TESTING AND DISINFECTION. Test and disinfect water mains, valves, fire hydrants, and appurtenances.

Similar documents
SECTION DISINFECTION OF PIPE AND WATER STORAGE FACILITIES

CLEANING, INSPECTION, AND TESTING OF SEWERS

Section C-1 Pipes and Fittings

Water System Disinfection

Repair and Disinfection of Water Mains Water Protection Program fact sheet

SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL Testing - General

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

Design & Construction Standards, Revised January

STANDARD OPERATING PROCEDURES FOR ALL WATERMAIN DISTRIBUTION REPAIR & INSTALLATION

SANITARY GRAVITY SEWER LINE TESTING. B. Section CCTV Inspection of Gravity Sewer Lines

CHAPTER 4 WELL COMPLETION AND MAINTENANCE

Specifications For Rehabilitation Hudson #1A Hudson #2 Foster Island Well #41

PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET

The Jockey Pump, an Important Part of a Fire Pump System.

Dechlorination of Potable and Superchlorinated Water

SECTION 10 WATER WELL SUPPLY SCOPE OF WORK

SECTION 810 SEWER LINE CLEANING

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

SECTION 3 SANITARY SEWER DESIGN

Corrosivity of Water Supplies

SANITARY SEWER SPECIFICATIONS

Presented By: Fred J. Sánchez Water Quality Operations Supervisor

Sample Test Questions

Adjusting Chemical Levels in a Swimming Pool

MC4-50 Feeding System

STANDARD SPECIFICATIONS SECTION SEWER MAIN AND LATERAL CONNECTION SEALING BY CHEMICAL GROUT

REQUIREMENTS FOR SEPTIC TANK PUMPERS AND CHEMICAL TOILET OPERATORS

Routine Maintenance and Inspection

2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS

Sample Test Questions

AWWA Small Systems Pipe Repair Checklist, as published in July 2008 Opflow Question of the Month

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

Waste Collection Systems

JB ENGINEERING AND CODE CONSULTING, P.C Cardinal Drive Munster, IN Phone: Fax:

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

Code Compliance Guideline: Swimming Pool Chemicals

1. Site plans assist the Fire Department to determine where a potential spill can be contained. The detailed site plan shall include the following:

INNOVATION AND COST EFFECTIVE APPROACH TO POTABLE WATER PIPE REPLACEMENT STRATEGICALLY FOCUSED ON DISTRIBUTION SYSTEM WATER QUALITY IMPROVEMENT By

I. Introduction. 10 minutes

WHITE PLAINS PLUMBING CODE PART 1. GENERAL REQUIREMENTS

CHAPTER. Standpipes and Hose Systems OVERVIEW. Standpipe and Hose Systems Defined

Sanitary Sewer Overflow Response Plan Working Committee SANITARY SEWER OVERFLOW RESPONSE PLAN

The Village of Malta

3M Water Filtration Products. CFS01 Series, CFS02 Series, CFS11 Series, and CFS12 Series Housings. Installation and Instruction Manual For:

Amendments to the 2012 International Plumbing Code

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES SITE UTILITIES

Standard Hydraulic Piping Flushing Procedure

ABC CIRCUITS 10 Circuit Drive Circuit Town, IN SLUG CONTROL PLAN

SECTION FACILITY STORM DRAINAGE PIPING

Most agencies think about cleaning because of debris in the line.

What To Do When Your Well is Flooded. Common Sense Steps To Take If Your Well Is Covered by Flood Water

Design Criteria & Service Goals

Standard Operating Procedures for Water Line Response and Repair. 2/12/2014 Illinois State University Environmental Health and Safety

SECTION DUCTILE IRON PIPE AND FITTINGS

RULES OF THE DEPARTMENT OF PUBLIC HEALTH CHAPTER PORTABLE SANITATION CONTRACTORS

For a building with a crawl space, see Figure

AKRON EDUCTORS TROUBLESHOOTING GUIDE OPERATION & THEORY OF EDUCTORS GENERAL OPERATING AND MAINTENANCE INSTRUCTIONS

TECHNICAL SPECIFICATIONS FOR LIQUID SODIUM HYPOCHLORITE

Georgia State Amendments to the International Plumbing Code

7. Codes of practice for plumbing

HERNDON/MUNCEY, INC. Office: (281) INVESTIGATIVE PLUMBING

PNWS-AWWA PRESENTATION May 9, 2013 Spokane, Washington. Water Operations Stormwater Best Management Practices

DRINKING WATER SUPPLY CONTINGENCY PLAN WATER SUPPLY CONTINGENCY PLAN FOR: VILLAGE OF WARSAW DATE:

SECTION GROUND WATER STORAGE TANKS

MS-3/2009 HDPE (High Density Polyethylene) Pipe and Fittings Specification for Buried Potable Water

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING

Indiana Department of Environmental Management. Well Disinfection

1. Water Line Maintenance 2. Sanitary Sewer Maintenance 3. Spill/Leak/Overflow Control, Response, and Containment

BULK WATER HAULING GUIDELINES

WATER MEASUREMENT USING TWO INCH (50 mm) DRAIN TESTS

Emergency/Disaster Response Plan

Keep the Water Moving Rehabilitation of a 1-million Gallon Water Storage Tank

CHAPTER 26 PLUMBING CODE

RESERVOIR DESIGN AND STORAGE VOLUME

MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT

2-Party Shared Well Users Agreement (If Applicable)

pvc well casing & drop pipe

INSTRUCTIONS/INFORMATION HOW TO PROPERLY FILL OUT THE INDIVIDUAL MECHANICAL TREATMENT PLANT WARRANTY INSPECTION / SERVICE REPORT

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

Ground Water Rule Request for 4-log Certification Chlorination

FY15 Gravity Sewer and Manhole Rehabilitation

New Jersey Department of Environmental Protection Division of Water Supply & Geoscience. Water Main Break. Guidance Manual

DRINKING WATER SUPPLY CONTINGENCY PLAN WATER SUPPLY CONTINGENCY PLAN FOR: PWS ID NUMBER: COUNTY: POPULATION SERVED: DATE:

812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area.

WATER MAIN CONSTRUCTION TECHNIQUES DEPARTMENT OF PUBLIC WORKS WATER & WASTEWATER DIVISION

Disinfecting Your Private Well

CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM

Transcription:

TESTING AND DISINFECTION PART 1 - GENERAL 1.01 SECTION INCLUDES A. Pressure and Leak Testing of Water System B. Disinfection of Potable Water Systems 1.02 DESCRIPTION OF WORK Test and disinfect water mains, valves, fire hydrants, and appurtenances. 1.03 SUBMITTALS Comply with Division 1 - General Provisions and Covenants. 1.04 SUBSTITUTIONS Comply with Division 1 - General Provisions and Covenants. 1.05 DELIVERY, STORAGE, AND HANDLING Comply with Division 1 - General Provisions and Covenants. 1.06 SCHEDULING AND CONFLICTS Comply with Division 1 - General Provisions and Covenants, as well as the following: A. Notify the Engineer two working days in advance of testing or disinfection operations to coordinate the operations. B. The Engineer or his/her representative is required to be in attendance during testing or disinfection. 1.07 SPECIAL REQUIREMENTS None. 1.08 MEASUREMENT AND PAYMENT Testing and disinfection of water systems is incidental to the construction of pipe and fittings. 1 Revised: 2015 Edition

PART 2 - PRODUCTS 2.01 DISINFECTION AGENT - CHLORINE A. Liquid Chlorine complying with AWWA B300 and AWWA B301. B. Sodium Hypochlorite complying with AWWA B300. C. Calcium Hypochlorite complying with AWWA B300. D. All disinfecting agents to be NSF 60 certified. Supply and store in the original container. 2 Revised: 2009 Edition

PART 3 - EXECUTION 3.01 SEQUENCE OF TESTING AND DISINFECTION Perform operations according to AWWA C651 in the sequence below. Successfully complete each operation before continuing to the next operation. The Jurisdiction will provide reasonable quantities of water for flushing and testing. A. Continuous-Feed or Slug Method (After Water Main Installation): The sequence of testing and disinfection may be modified with approval of the Engineer. 1. Perform initial flush. 2. Perform disinfection. 3. Flush after disinfection. 4. Perform pressure and leak testing. B. Tablet Method (Concurrent with Water Main Installation): Use this method only if approved by the Engineer. Modify the procedure for flushing, disinfection, and pressure and leak testing as needed if tablet method is used. 1. Perform disinfection. 2. Flush after disinfection. 3. Perform pressure and leak testing. 3.02 INITIAL FLUSHING A. Flushing: 1. Coordinate flushing with the Jurisdiction. 2. Flush pipe prior to disinfection using potable water. 3. Measure flushing velocity. 4. Obtain a minimum flushing velocity of 3 feet per second in the pipe to be disinfected. B. Minimum Flushing Rate: According to AWWA C651, Table 3, based on 40 psi residual pressure (see table below). Table 5030.01: Minimum Flushing Rate Pipe Diameter Flow Rate for Flushing Number of Taps 2 Number of 2 1/2 Fire (inches) (gpm) 1 1 1/2 2 Hydrant Outlets 1 4 120 1 - - 1 6 260-1 - 1 8 470-2 - 1 10 730-3 2 1 12 1,060 - - 3 2 16 1,880 - - 5 2 1 With a 40 psi pressure in the main with the fire hydrant flowing to atmosphere, a 2 1/2 inch fire hydrant outlet will discharge approximately 1,000 gpm; and a 4 1/2 inch fire hydrant outlet will discharge approximately 2,500 gpm. 2 Number of taps on pipe based on discharge through 5 feet of galvanized iron pipe with one 90 eow. C. Property Protection: Protect public and private property from damage during flushing operations. 3 Revised: 2016 Edition

3.03 DISINFECTION A. General: 1. Disinfect according to AWWA C651. The tablet method contained in AWWA C651 is not to be used unless approved by the Engineer. 2. Keep piping to be chlorinated isolated from lines in service and from points of use. 3. Coordinate disinfection and testing with the Engineer. 4. Obtain and test water samples, unless otherwise provided by the Engineer. B. Procedure: 1. Induce a flow of potable water through the pipe. 2. Introduce highly chlorinated water to the pipe at a point within 5 pipe diameters of the pipe's connection to an existing potable system, or within 5 pipe diameters of a closed end, if there is no connection to an existing system. 3. Introduce water containing a minimum of 25 mg/l free chlorine until the entire new pipe contains a minimum of 25 mg/l free chlorine. 4. Retain chlorinated water in the pipe for at least 24 hours and no more than 48 hours. 3.04 FINAL FLUSHING A. Flush pipe using potable water until chlorine residual equals that of the existing potable water system. B. Dispose of chlorinated water to prevent damage to the environment. Dechlorinate highly chlorinated water from testing before releasing into the ground or sewers. Obtain Jurisdiction approval prior to flushing activities. 1. Check with the local sewer department for the conditions of disposal to the sanitary sewer. 2. Chlorine residual of water being disposed will be neutralized by treating with one of the chemicals listed in the following table. Table 5030.02: Amounts of Chemicals Required to Neutralize Various Residual Chlorine Concentrations in 100,000 Gallons of Water Residual Chlorine Concentration mg/l Sulfur Dioxide (SO 2) Sodium Bisulfite (NaHSO 3) Sodium Sulfite (Na 2SO 3) Sodium Thiosulfate (Na 2S 2O 3 + 5H 2O) Ascorbic Acid (C 6O 8H 6) 1 0.8 1.2 1.4 1.2 2.1 2 1.7 2.5 2.9 2.4 4.2 10 8.3 12.5 14.6 12.0 20.9 50 41.7 62.6 73.0 60.0 104 4 Revised: 2009 Edition

3.05 PRESSURE AND LEAK TESTING A. Remove debris from within the pipe. Clean and swab out pipe, if required. B. Secure unrestrained pipe ends against uncontrolled movement. C. Isolate new piping from the existing water system. D. Fill and flush all new piping with potable water. Ensure all trapped air is removed. E. Pressurize the new pipe to the test pressure at the highest point in the isolated system. Do not pressurize to more than 5 psi over the test pressure at the highest point in the isolated system. F. Test and monitor the completed piping system at 1.5 times the system working pressure or 150 psi, whichever is greater, for 2 continuous hours. G. If at any time during the test the pressure drops to 5 psi below the test pressure, repressurize the pipe by pumping in potable water in sufficient quantity to bring the pressure back to the original test pressure. H. Accurately measure the amount of water required to repressurize the system to the test pressure. I. Maximum allowable leakage rate according to AWWA C600: L = (S)(D)(P) 0.5 148,000 Where: L = allowable leakage, in gallons per hour S = length of pipe tested, in feet D = nominal pipe diameter, in inches P = average test pressure, in pounds per square inch The following table assumes an average test pressure (P) of 150 psi and 1,000 feet of test section. Table 5030.03: Maximum Allowable Leakage Rate Pipe Diameter (inches) Allowable Leakage Rate (gallons/hour/1,000 feet of pipe) 4 0.33 6 0.50 8 0.66 10 0.83 12 0.99 14 1.16 16 1.32 18 1.49 20 1.66 24 1.99 30 2.48 36 2.98 J. If the average measured leakage per hour exceeds the maximum allowable leakage rate, repair and retest the water main. 5 Revised: 2012 Edition

3.05 PRESSURE AND LEAK TESTING (Continued) K. If the measured pressure loss does not exceed 5 psi, the test will be considered acceptable. L. Repair all visible leaks regardless of the amount of leakage. 3.06 BACTERIA SAMPLING Test water mains according to AWWA C651, including collection of two consecutive sets of acceptable bacteria samples 24 hours apart. If the initial disinfection procedure fails to produce satisfactory bacteriological results or if other water quality is affected, repeat the disinfection procedure. 3.07 PUTTING WATER MAIN IN SERVICE Put the completed water system in service only after obtaining permission from the Jurisdiction. END OF SECTION 6 Revised: 2010 Edition