Using Microsoft Office to Manage Projects



Similar documents
Advanced Excel 10/20/2011 1

Microsoft Access 2010 handout

O UTLOOK 2003 HELP SHEET MAIL. Opening the program. Mail

Outlook . User Guide IS TRAINING CENTER. 833 Chestnut St, Suite 600. Philadelphia, PA

Introduction to Microsoft Access 2013

Creating and Using Forms in SharePoint

Catholic Archdiocese of Atlanta Outlook 2003 Training

MicroStrategy Desktop

Introduction to Microsoft Access 2010

Module One: Getting Started Opening Outlook Setting Up Outlook for the First Time Understanding the Interface...

Clean Up Rules Quick Steps Search Tools Change Views Export Data Convert to tasks Contact Groups. Outlook Functions

Creating and Managing Online Surveys LEVEL 2

Intellect Platform - Tables and Templates Basic Document Management System - A101

Importing Contacts to Outlook

1. Linking among several worksheets in the same workbook 2. Linking data from one workbook to another

Introduction to Microsoft Access 2003

Excel 2003 Tutorial I

Instructions for Creating an Outlook Distribution List from an Excel File

What is a Mail Merge?

Outlook and Calendaring

USING MS OUTLOOK. Microsoft Outlook

USING MS OUTLOOK WITH FUS

Mail Merge Tutorial (for Word ) By Allison King Spring 2007 (updated Fall 2007)

Revealing the Secrets of Microsoft Project

Outlook 2010 Essentials

USER GUIDE. Unit 2: Synergy. Chapter 2: Using Schoolwires Synergy

How To Use Outlook On A Pc Or Macbook With A Pc (For A Pc) Or Macintosh (For An Ipo) With A Macbook Or Ipo With A Ipo (For Pc) With An Outlook (For Macbook

SHAREPOINT 2010 FOUNDATION FOR END USERS

Archiving and Managing Your Mailbox

Learning Services IT Guide. Access 2013

OUTLOOK TIPS FOR BEGINNERS

Microsoft Office. Mail Merge in Microsoft Word

MICROSOFT ACCESS STEP BY STEP GUIDE

MS Excel Template Building and Mapping for Neat 5

Creating Interactive PDF Forms

Merging Labels, Letters, and Envelopes Word 2013

Introduction to MS WINDOWS XP

PortfolioCenter Export Wizard in Practice: Evaluating IRA Account Holder Ages and Calculating Required Minimum Distribution (RMD) Amounts

Task Force on Technology / EXCEL

MICROSOFT OFFICE ACCESS NEW FEATURES

Crystal Reports Payroll Exercise

6. If you want to enter specific formats, click the Format Tab to auto format the information that is entered into the field.

Finding and Opening Documents

Managing Contacts in Outlook

Search help. More on Office.com: images templates

Microsoft Using an Existing Database Amarillo College Revision Date: July 30, 2008

SECTION 5: Finalizing Your Workbook

Personal Portfolios on Blackboard

MAIL MERGE MADE EASY A STEP-BY-STEP GUIDE FOR LABELS OR MERGES

USING OUTLOOK WITH ENTERGROUP. Microsoft Outlook

Lesson 07: MS ACCESS - Handout. Introduction to database (30 mins)

Outlook. Getting Started Outlook vs. Outlook Express Setting up a profile Outlook Today screen Navigation Pane

Access I Tables, Queries, Forms, Reports. Lourdes Day, Technology Specialist, FDLRS Sunrise

Time Matters and Billing Matters User Guide

DESIGN A WEB SITE USING PUBLISHER Before you begin, plan your Web site

How To Create A Report In Excel

Dynamics CRM for Outlook Basics

Word 2010: Mail Merge to with Attachments

Chapter 2: Clients, charts of accounts, and bank accounts

Outlook 2013 ~ Advanced

Microsoft Outlook 2010

Utilizing Microsoft Access Forms and Reports

Introduction to Microsoft Project 2010

Ohio University Computer Services Center August, 2002 Crystal Reports Introduction Quick Reference Guide

Results CRM 2012 User Manual

Microsoft Outlook 2007 Calendar Features

Microsoft Word 2010 Mail Merge (Level 3)

Virtual Communities Operations Manual

This document is provided "as-is". Information and views expressed in this document, including URLs and other Internet Web site references, may

How to make a line graph using Excel 2007

Create a Poster Using Publisher

EXCEL PIVOT TABLE David Geffen School of Medicine, UCLA Dean s Office Oct 2002

Intellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102

OUTLOOK 2010 TIPS TABLE OF CONTENTS 1. SEND A BLIND CARBON COPY MARQUETTE UNIVERSITY IT SERVICES

Contact Manager HELP GUIDE

Microsoft Access 2010 Part 1: Introduction to Access

Excel Reports User Guide

EXCEL Using Excel for Data Query & Management. Information Technology. MS Office Excel 2007 Users Guide. IT Training & Development

Microsoft Outlook 2010 The Essentials

Migrating to Excel 2010 from Excel Excel - Microsoft Office 1 of 1

Adding the BU IMAP Inbox 1. Along the left side of the screen, there is a Mail column. Look for the All Mail Folders section.

SharePoint Online Quick Reference

ACCESS Importing and Exporting Data Files. Information Technology. MS Access 2007 Users Guide. IT Training & Development (818)

Outlook Web Access. PRECEDED by v\

Staying Organized with the Outlook Journal

Outlook Web Access (OWA) Cheat Sheet

Decision Support AITS University Administration. Web Intelligence Rich Client 4.1 User Guide

MICROSOFT ACCESS 2003 TUTORIAL

MICROSOFT OUTLOOK 2010 WORK WITH CONTACTS

Creating tables in Microsoft Access 2007

Outlook XP Only

OUTLOOK 2003: HOW TO GET OUT OF JAIL

TheEducationEdge. Export Guide

Section 4. Mastering Folders

Using Excel As A Database

emarketing Manual- Creating a New

CJA 20. Automated Billing Program Attorney Training Guide EXCEL BILLING FOR CJA CASES. Page 1

WSDOT ProjectWise V8i Training 101

REAL ESTATE CLIENT MANAGEMENT QUICK START GUIDE

ANCS+ 8.0 Remote Training: ANCS+ 8.0, Import/Export

Transcription:

(or, Why You Don t Need MS Project) Using Microsoft Office to Manage Projects will explain how to use two applications in the Microsoft Office suite to document your project plan and assign and track tasks. Basic project management techniques are not covered. If you would like to develop skills in project management many colleges and universities have such courses in their business programs and continuing education services. You can also try www.primelearning.com for an online course in Fundamentals of Project Management. Contents Project Planning with Excel...2 Getting Started...2 Quick Tour...2 Basics...2 Planning Grid...3 Gantt Chart...3 Task Management in Outlook...5 Set up...5 Creating Tasks...6 Assigning and Tracking Tasks...8 Communicating Progress...11 Moving Tasks from Excel to Outlook...13 The Easier Way...13 The Harder Way...20 Printing note: this document is formatted to print double-sided. Please save paper.

Project Planning with Excel Many people today use sophisticated project planning tools like Microsoft Project to define activities and assign tasks. These tools also allow project managers and teams to visualize the scale and timeline of their projects. MS Project is, however, expensive to deploy. It is also not very intuitive to use. Most people use it for the planning grid and the Gantt chart view. Most of the features of the program remain unused. Our Excel spreadsheet, Project_Template, has the planning grid and Gantt chart view. It does not link dependent tasks or automatically adjust start and end times, though. Getting Started Find the template, Project_Template_03.xls in the Excellence folder on Fileserver, in the subfolder called Projects. You can also open it by clicking on this hyperlink, \\Fileserver\Excellence\Projects\Project_Template_03.xls. Immediately save the file under a different name and place it, through the Browse window, in a folder where your project information resides. Quick Tour Basics The spreadsheet will support 300 tasks over six months. If your project requires more of either, consider using different spreadsheets for each phase of your project or getting Microsoft Project. Because there are many fields with calculations and they depend on specific data formats to work, most of the cells in the spreadsheet are locked. This means you will not be able to accidentally type over a calculation. The cells where you will be entering information in the planning grid are not locked. Although the spreadsheet is protected, you will still be able to sort and auto-filter in the planning grid. Date fields require a date format in a specific range or will return an error. Column names and status values are consistent with the Tasks component in Microsoft Outlook. This facilitates importing tasks from the Excel spreadsheet into Outlook. For details on how do this, see the chapter on Moving Tasks from Excel to Outlook. Page 2 of 25

Printing has been pre-formatted. Preview the print job by using File > Print from the menu bar instead of the printer icon in the toolbar to see how many and which pages will actually have information on them and choose those to reduce wasted paper and time. Planning Grid Task information is entered in the planning grid. The template has some information filled in as a reminder of how to use the tool. This information can be selected and cleared. There are eight columns in the planning grid section. They are explained in the table below. Column Name Num Subject Owner Notes Start Date Due Date Date Completed Status Description Allows a number or character to be entered to track task order. Can also be used to enter the Work Breakdown Structure (WBS) code. (optional) The name of the task. A short description of what is to be done. The person responsible for completing or following up on the task. Details of the task. (optional) Expected or assigned start date. The bars on the Gantt chart require at least a start date. Expected completion date. Actual completion date. There are several possible statuses in the drop down list, however the Gantt chart only recognizes completed and in progress. Leave not started statuses blank. Gantt Chart Gantt charts, named after Henry Gantt, display items spread over the time between two dates. In project management, they allow us to see the relationships between task time and the project as a whole. They can also provide a visual description of project completion. Page 3 of 25

In our spreadsheet, each column represents one day. Weekends are grayed out. The day of the week is at the top. To conserve space, the date is in m/d/yy format. The first date is pumpkin colored. This field is unlocked. To use the Gantt chart, enter the Sunday of the week you want to start tracking. Typically, this is the week the project begins. The horizontal bars crossing dates to the right correspond to the tasks at the left. Tasks that are completed are gray, in progress tasks are blue, and tasks yet to start are yellow. The right edge of the bar is defined by the due date until a completion date is entered. The window has been frozen at the left edge of the Gantt chart. Scrolling right moves along the dates, while the task information remains in place. The figure below is an example of a spreadsheet with new project information entered. Page 4 of 25

Task Management in Outlook Microsoft Outlook, in addition to Mail, Calendar, and Contacts, has a component called Tasks. Not only can it be used to create and track your tasks, it can be used to assign and track tasks you assign to others. It must, however, be customized to be useful for project task management. Set up This is the default, minimalist view. It is not particularly useful for managing tasks among different projects or different people, but is useful for managing personal tasks. First, you will need the Advanced Toolbar. Go to View > Toolbars > Advanced. Page 5 of 25

The Advanced Toolbar allows you to choose the view, enable the grouping bar, and open the field chooser without having to go to the menu or left navigation bar. Open the field chooser and add the following fields: Company, Priority, Start Date, Date completed, Owner, Status, and % Complete. They can be arranged by dragging the label into position on the header bar. Once there, the labels can be dragged into whatever position is most useful to you. Creating Tasks The task information can now be entered and edited. These are the most common data elements for a task, however, if you want to see more, simply double-click on a task and a full Task window will open. Note that date fields have a calendar control at the arrow and Status is a drop down list. Tasks does not have a field called Project. Use the Company field to name the particular project. Page 6 of 25

Tasks can be sorted by clicking on any label. The arrow will show the direction of Sort (ascending or descending). In this image, the Owner is sorted in ascending order. You can also group on any label by dragging it to the Grouping area. To separate by Project, drag the Company label into the Grouping area. This will allow you to see all of your tasks by project. If, instead of using the Company field, you decide to create a separate Tasks folder for each project, you won t be able to see the tasks for all of your projects in one view. Keeping on top of the tasks will be more difficult. When completed is picked in Status, % Complete becomes 100% and the entire line is crossed out. Page 7 of 25

Choosing Task Timeline view creates a Gantt chart of your project. The time periods are editable. Here, they are set at Daily. Assigning and Tracking Tasks Creating and tracking your own tasks is helpful, but if you are leading a project, you want to assign and track tasks for your entire team. The reason to use Outlook is that task management is integrated with email AND is not in a separate application like HyperOffice, but is already in an application you use daily. As you create tasks, either from scratch or after importing them from Project_Template.xls (or MS Project for that matter), assigning them to team members within TransCare is as easy as right-clicking on the task and choosing Assign Task. CAVEAT: Don t assign tasks in Outlook unless you know they are aware of how to use Tasks or you warn them and send a copy of this manual. You will probably cause a bit of confusion. Page 8 of 25

A Task Request opens that looks like a meeting appointment or email. Fill it out as you would an email by clicking the To button and choosing a name from the Global Address Book. If you haven t already done so, enter a Due Date, Subject, and any details or notes related to the task. By default the Keep an updated copy of this task on my task list and Send me a status report when the task is complete boxes are checked. Leave them checked. Click Send. This warning pops up to alert you to the fact that the task will now be owned by the receiver. Any updates you enter will be over-ridden by the updates from the owner. This is fine. The task is still visible in your task list. Page 9 of 25

In fact, whenever the new task owner makes a change by entering notes or changing the completion percentage, you will get a notice in your email and the task in your task list will automatically update. Imagine how much easier on both of you this will be to keep abreast of the tasks in the project. It only requires a bit of discipline to make it a habit. When the task owner finishes the task and checks the Complete box or changes the % Complete to 100%, you will get a final Status Report. Page 10 of 25

Communicating Progress Tasks allows more than simply a beginning and an ending communication. By entering progress notes in the task, the task owner can keep the project leader up to date on the task without having to send emails or make phone calls. This image shows a new task. It has one line of notes to begin. In the Details tab, the task creator estimated it will take one hour of work to complete the task. Organizations can use Tasks in Outlook to track expenses related to projects and allocate them to a specific department or bill clients. Now, the task owner is entering an update. He is noting the task is approximately 10% complete and puts in a note. Unfortunately, he overwrote the original note. Page 11 of 25

The task creator sees this after the task owner clicks Save and Close. On the next update, the task owner adds a line before writing. This allows us to track the history of the task progress without having to look up earlier notes. This is the task creator s view. The task is 25% complete and all notes are visible. The task owner and task creator have communicated the task progress without really having to take time out to do so. If the Total Work and Actual Work fields are used, over time the project leader will have a better idea of how long certain tasks actually take and can better plan in the future. Page 12 of 25

Moving Tasks from Excel to Outlook The Excel spreadsheet, Project_Template.xls, provides a means of planning and visualizing an entire project but can t be used to communicate task assignment or progress. Outlook provides a means to assign and track specific tasks among team members but doesn t facilitate planning or plan sharing. Wouldn t it be great if they could be used together? They can. In fact, there are two ways to import tasks from Excel into Outlook without having to write a script in VBA. Which one you choose to use will be based on your comfort level in manipulating Excel spreadsheets. The Easier Way The easier of the two ways requires the user to define named ranges within the spreadsheet which will necessitate turning off cell protection temporarily. Outlook does not support dynamic named ranges, a method of defining ranges by whether or not data exists in cells, so the spreadsheet cannot be set up with the named range as part of the template. If it was set up so, the user would have to delete all of the blank tasks that are created during the import process. Learning how to define the named range prior to importing will take less time. First, unprotect the spreadsheet by going to the menu bar and choosing Tools > Protection > Unprotect Sheet. There is no password, so the sheet will immediately be unprotected. Page 13 of 25

Next, highlight the cells you want to import into Tasks, including the headers. Once highlighted, go to the menu bar and choose Insert > Name > Define. The Define Name window will open. Type a name in the Names in workbook box that is NOT a column name. It can be anything that isn t already in use. Page 14 of 25

Once completed, re-protect the spreadsheet by choosing Tools > Protection > Protect Sheet. The Protect Sheet window will open. DO NOT enter a password. If you forget it, you ll never be able to unprotect the spreadsheet. Leave all the permissions as is. Just click on the OK button. The sheet is now protected again and you can close the spreadsheet. Page 15 of 25

Go to your Tasks window in Outlook. (Note: the use of a folder called My Tasks is for illustration only.) On the menu bar, choose File > Import and Export. The Import and Export Wizard will open. Choose Import from another program or file and click the Next button. Page 16 of 25

Choose Microsoft Excel and click the Next button. The Import a File window opens. Click the Browse button to navigate to the file you want to import. Highlight it and click the OK button (or double-click on the file). Page 17 of 25

Select the destination folder. Choose Tasks. Then click the Next button. Outlook will see that there are two named ranges and you will have to choose which one to import by checking the appropriate box. (Note: Stati is the name of the dropdown list for Status in the spreadsheet.) Then, click the Map Custom Fields button to ensure your columns will be recognized and imported into the correct fields in Task. Scroll down the window on the right to make sure your columns have a destination field. Owner cannot be imported into Tasks. If one of the other columns isn t aligned with a field Page 18 of 25

simply click on the column name on the left and drag it over the field name on the right. Once mapping is complete, click OK. Click the Finish button. Your tasks from the spreadsheet are imported and mapped to the correct Task field. Page 19 of 25

Add the project name under Company. Now you can assign tasks to your team. The Harder Way Since Outlook requires Excel to have named ranges for importing, if you don t want to name ranges, you have to save the Excel spreadsheet as something else. We will convert Excel to Comma Separated Values (.csv) to facilitate the import process. We don t want all the columns, most of which are days in the Gantt chart, so we will copy the data we want and paste it into a new spreadsheet. Highlight the cells you want to import, including the headers. Page 20 of 25

Open a new workbook and paste the data in cell A1. Don t worry about formatting; we won t be using this spreadsheet for anything except transferring the data to Outlook. Save the new workbook with any name you will remember. Under Save as type: choose CSV (Comma delimited)(*.csv). Excel will warn you that CSV doesn t support multiple sheets. That s okay, you are only using the first one. Click OK. Excel will now warn you that not all features (like formulas) are compatible with CSV. That s okay, too. Click Yes. Page 21 of 25

Now, close the file. When asked if you want to save, click No. If you click Yes, you will have to go through the same save process and questions as you just completed. Go to Tasks in Outlook and choose File > Import and Export from the menu bar. Choose Import from another program or file and click Next. Page 22 of 25

Choose Comma Separated Values (Windows) and click Next. Find the file by clicking the Browse button and navigating to the file. Select the Tasks folder as the destination. Page 23 of 25

Click the Map Custom Fields button to ensure your columns will be inserted into the correct Task fields. Scroll down the window on the right to make sure your columns have a destination field. Owner cannot be imported into Tasks. If one of the other columns isn t aligned with a field simply click on the column name on the left and drag it over the field name on the right. Once mapping is complete, click OK. Click Finish on the Import Wizard window. Page 24 of 25

Your tasks from the spreadsheet are imported and mapped to the correct Task field. Add the project name under Company. Now you can assign tasks to your team. Page 25 of 25