Design-Bid-Build versus Design-Build: The client s choice



Similar documents
THE BEST CRITERIA FOR THE SELECTION OF CONTRACTORS IN THE DUTCH CONSTRUCTION INDUSTRY!

Value Creation by Process-Oriented Project Management

Contracting Practices in Mega Projects

The Role of Construction Managers. FIDIC offers two contributions on the question of the role of a construction manager in a construction contract:

Assessment of Critical Success Factors for Construction Projects in Pakistan

Comparing Procurement Methods for Design-Build Projects

Maintenance performance improvement with System Dynamics:

Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector

Incorporating research in professional bachelor programmes

Ph. D. thesis summary. by Aleksandra Rutkowska, M. Sc. Stock portfolio optimization in the light of Liu s credibility theory

The Talent on Demand Approach. Talent management is the process through which employers anticipate and meet

The End of Primary School Test Marleen van der Lubbe, Cito, The Netherlands

Pre-Sales Requirements Engineering based on Miller Heiman s Sales Approach

Conducting Formative Research

IT Sourcing. White Paper IT Advisory

75 Questions to Ask When Hiring a Church Architect

Multiproject Scheduling in Construction Industry

The FIDIC Suite of Contracts

Building Capital Projects in Tough Times John Lynch, State of Washington

Good Corporate Governance pays off! Well-governed companies perform better on the stock market

Social Return on Investment

POSITION PAPER TENURE TRACK

DEVELOPMENT OF CONSTRUCTION BEST PRACTICE EXPERT SYSTEM

The Contract Scorecard

SUPPLY CHAIN PARTNERSHIP WITHIN HOUSING RENOVATION APPROACHES AND EXPECTATIONS IN THE DUTCH HOUSING ASSOCIATION SECTOR

Procurement Routes. Curtin University of Technology

Market Research Methodology

How to get value for money from service providers on major projects

Human Resource Information System Contributes to the Management of Competence and Knowledge

Consultancy Services Proposal

Framework for initial accreditation of new Associate degree programmes

TOLKEN IN HET PUBLIEK DOMEIN. Summary

RISK MITIGATION IN FAST TRACKING PROJECTS

cons of the handbook, and uniformity and professionalism. 3. telephone interviews with two other organisations involved in youth probation, the Child

Organizing 3D Building Information Models with the help of Work Breakdown Structures to improve the Clash Detection process

A Study of the Application of Supply Chain Management in Construction Industry

Contracting Strategy of a Project

TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG

Code Banken. 9 september 2010

Common InfraBIM requirements YIV2015

RandstadRail: Increase in Public Transport Quality by Controlling Operations

DESIGN IS GOOD BUSINESS

School Construction Projects

On-Site Examination Policy for Fiscal Examination Policy for Fiscal 2016" briefly reviews on-site examinations carried out in

DYNAMIC CONTRACTING: An Asset Management Tool in Controlling Infrastructure Maintenance Activities

How the Ministry of Education managed the 2008 national school bus transport tender process. Report to the Ministry of Education October 2009

Assessing Your Information Technology Organization

Earned value theory or earned value management

Assessment frameworks for the higher education accreditation system Programme assessment (limited/extensive)

ACM s analysis of the sustainability arrangements concerning the Chicken of Tomorrow

AFM and DNB Policy Rule on the Application and Implementation of the Wfm BES and Wwft BES 2012

New Business Models in Construction

How To Write An Integrated Construction Project

Consulting Performance, Rewards & Talent. Measuring the Business Impact of Employee Selection Systems

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO

Dutch Labour Standards Foundation The Standard for reliability. Information set about Standard NEN 4400 and the Labour Standards Register

Developing a Public-Private Partnership Framework: Policies and PPP Units

How to Write the Construction Management RFQ/RFP

Project Execution in EPC/Turnkeys Contracts and The PM Roles and Responsibilities. By George E. Baram P.Eng, M.Eng, PMP, CCE Fellow AACE International

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

Terms of Reference for consulting services financed under a World Bank executed Trust Fund

(1) risks should be allocated to the party that is in the position to control them and

EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS

THE RISKS OF OUTSOURCING TRANSPORT FUNCTIONS IN RELATIONS BETWEEN THE COOPERATION FIRMS

Core Capacity Analysis Of Top Performing Agents at Berkshire Hathaway HomeServices

Professionsbachelor i Innovation og Entrepreneurship Bachelor of Innovation and Entrepreneurship

Gender Sensitive Data Gathering Methods

Investment Appraisal INTRODUCTION

Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents

Research on Tech SME Intellectual Property Innovation Mode

A COMPARATIVE STUDY OF WORKFORCE DIVERSITY IN SERVICE AND MANUFACTURING SECTORS IN INDIA

Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel

Evaluating Project Delivery Options

California State University, Los Angeles Department of Sociology. Guide to Preparing a Masters Thesis Proposal

An Introduction to Sales Force Motivation

SKANSKA SPECIFICATIONS TO GENERAL CONDITIONS FOR BUILDING CONTRACTS 1998

THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE. John R. Lethbridge

A Modular Construction System. How to design its Production Process

Helping consumers to manage their money

Transcription:

Design-Bid-Build versus Design-Build: The client s choice Ruben Favié Eindhoven University of Technology (email: r.favie@tue.nl) Job Sijbers Eindhoven University of Technology (email: jobsijbers@hotmail.com) Gaby Abdalla Eindhoven University of Technology (email: g.abdalla@tue.nl) Ger Maas Eindhoven University of Technology (email: g.j.maas@tue.nl) Abstract The aim of the procurement process in construction is to acquire the construction work that meets the client s needs. One of the steps in this process is the functional grouping. The functional grouping of a project is the way in which tasks, responsibilities, liabilities and risks are divided among the construction participants. There are several types of functional groupings for construction projects that are commonly used like Design-Bid-Build or Design- Build. For a client, the choice for a type of functional grouping that fits his needs is difficult to make. In this paper, insight is given in possibilities the client has in the decision making process for choosing a suitable functional grouping for his project. Next to that a comparison is made between the traditional Design-Bid-Build and the more integrated Design-Build. Data has been collected by interviewing construction experts. These experts were clients as well as contractors. Keywords: Design-Bid-Build, Client, Decision making process, Design-Build, Functional composition.

1. Introduction Over the last decades, the Dutch construction sector has been price oriented. This has led to a construction industry in which the participants distrust each other and the several disciplines are highly separated (Maas and Van Eekelen, 2003). The last few years, a structural transition is going on. Programs have been developed, such as the PSIBouw program, that focused on alternative, more integrated procurement strategies in contrast to the more traditional ones. Although the price oriented traditional construction procurement strategy in many cases does not suffice, many large clients still choose for this strategy. As a consequence the client will often not get value for money. It has become increasingly evident over recent years, that an appropriate choice of procurement system, while necessary for project success is not sufficient to ensure it. But appropriate procurement strategies are needed to help to achieve optimal solutions in terms of cost, time and quality (Kumaraswamy and Dissanayaka, 1998). The functional composition, which helps dividing the tasks, responsibilities and risks among participants, is considered to be the most important and leading subsystem of the procurement system (Luu et al., 2005). Therefore it is important for clients to choose the right functional composition. Over the years many different functional compositions have been developed, which makes it difficult for clients to make a considerable choice. A model, developed at the University of Eindhoven (Maas and van Eekelen, 2003) has been taken as a starting point for this research. The functional compositions for construction projects can be divided in more traditional and more integrated functional compositions. To help the client in making a decision for a specific functional composition it is important to get insight in the specific project situation and which type of functional composition fits best for that situation. Therefore the aim of this study is to create insight into the client s considerations for a functional composition by analyzing the factors that influence the client s decision making process and give insight in the differences between two functional groupings in order to guide the client through this process. In paragraph 2, the different steps of the procurement strategy will be explained further in order to present the relationships between these steps (and the functional composition in particular) more clearly. 2. The procurement strategy Many parties are involved in a construction project. The division of roles, tasks and responsibilities is a very important step in the construction process. In literature, the type of organization that follows from the choice of this division is called the functional grouping (Kumaraswamy & Dissanayaka 1998). The names of commonly used functional groupings often refer to the roles and tasks that are outsourced by the client to a contractor. Functional

grouping is one of the steps in the whole procurement route that has to be followed for each construction project. Kumaraswamy and Dissanayaka (Kumaraswamy & Dissanayaka 1998) state that a procurement route exists of 5 parts. In order to develop a certain procurement route, the next choices have to made: Work packaging Functional grouping Payment modalities Form of contract Selection methodologies In paragraphs 2.1-2.5 the 5 procurement route steps will be discussed. 2.1 Work packaging There are several reasons for a contractor to cut a large project into a number of smaller projects or just leave the project as it is. For example, one project might be too big or too complex to be executed by one contractor. That can lead to cutting the project into several work packages with each their own characteristics. Work packaging describes the type of project, the size of the project, the function and the location of the project. 2.2 Functional grouping The functional grouping is the result of strategic and tactic considerations concerning the economical functions in the construction process and the division of roles and tasks for the different parties. The functional grouping relates the different construction process phases and relates the different parties that cooperate in the process. The choice for a certain type of functional grouping forms the structure of the project organization consisting of functional and contractual relations and the division of the responsibilities, liabilities and risks. There are a lot of different ways to set up the functional grouping of a construction project. The traditional Design-Bid-Build process (DBB), in which a contractor is contracted based on specifications and drawings is very segmented. After finishing the design, the client hires a contractor who builds the project according to the client s detailed specifications. This means there are two separate groups involved; the design group and the construction group (Ling 2004b) and the process functions designing and building are strictly separated. This means that

the client is responsible for the development of the final design including the detailed construction specifications. These specifications are the basis for the selection of the contractor. During the construction of the project the client normally does the supervision or quantity surveillance to make sure that the contractor executes his tasks properly. Nowadays, more integrated delivery approaches are more and more often used by all types of clients (Regieraad Bouw, 2007 / Pakkala et al, 2007). In the Netherlands, one of the biggest public clients, the Ministry of Transportation, even prescribes the use of Design-Build (DB) contracts for new and reconstruction works (RWS, 2007). DB is a so-called integrated procurement route. This concept has deep historical roots. In ancient times, the master builder had full responsibility for all phases of the project. Nowadays in the DB approach, it would involve a multidisciplinary team (Palaneeswaran & Kumaraswamy 2000). This type of procurement routes, in which one company or consortium of companies is responsible for the design and execution of a project, requires a totally different attitude of the contractor as well as the client. The above-mentioned contractual forms differ from one another in the division of responsibilities, tasks and roles and functions. Next to that, they also differ in the moment on which the contractor is contracted. In the DBB process, the signing of the contract is just before the starting of the realization phase. In a DB contract, the contractor also develops a part of the design. In that case, the contract has to be signed earlier in the process. These shifts in the moment of contracting mean that each time different kind of performances are demanded of the client and the contractor. Therefore, in every single case, an other division of the roles and responsibilities is necessary. 2.3 Payment modalities An important part of the procurement process, that is closely related to the choice of a certain functional grouping, is the choice of a payment modality. For example, the contractor can be hired based on a lump sum, but the client can also choose for a cost-plus-fee payment. An other choice that has to be made is the timing of the payments: per month or when certain milestones are reached. The choice of a payment modality determines, to a large extent, how the client and the contractor cooperate. Working with a lump sum and specifications and drawings that are specified on a high level will be very different than working with paying after the important milestones of the client are achieved. This is also linked largely to the functional grouping and the selection methodology.

2.4 Form of contract In the construction sector, there are a lot of contractual standards that can be used as the basis of every construction project. Internationally, there are the FIDIC contracts. In the Netherlands, the Uniforme Algemene Voorwaarden (UAV) and the UAV for integrated contracts (UAVgc) are usually used. Next to that, choices must be made on which type arbitration will be used in case of problems. 2.5 Selection methodologies If a client has made all the above mentioned choices, then he has to make the choice for the tender procedure. The tender procedure consists of 3 important levels: Tendering procedure Selection and awarding criteria Decision modelling (scoring, weighing) 3. Methodology In order to achieve the goal that is set, the following research questions must be answered: Which factors influence the client s decision making process for a functional composition? What are the distinctive features of the functional compositions DBB and DB? Which criteria determine the difference between the functional compositions DBB and DB? What are the distinctive differences between DBB and DB on these criteria? The research is descriptive and explorative. On the one hand literature survey has taken place in order to find the answers on the first two research questions. On the other hand 12 interviews with experts have taken place to answer the third and fourth question. Information from these interviews has been analyzed. Based on this information a list of differences has been developed, which is the answer to the last research question.

The literature review can be found in paragraph 4. This survey has given a broad view on factors that influence the client s choice for a functional composition. By means of a Causeand-Effect Diagram these factors are gathered as shown in Figure 1. Furthermore this review has been used to get insight in distinctive features of both DBB and DB. Based on this literature survey a theoretical framework has been designed for the second part of the research: the interviews. The theoretical framework has been converted to a research model that can be used for gathering and analyzing data from expert-interviews. By gathering and analyzing data it is examined which criteria determine the difference between DBB and DB. Based on these results a list is constructed to guide the client in his decision making process. This list helps clients choosing a more traditional or more integrated functional composition. The interview results can be found in paragraph 5. In paragraph 6 the results of both the literature review and interviews are combined. 4. Literature review 4.1 Factors that influence the choice for a functional composition Factors that influence the choice for a functional composition are shown by the Cause-and- Effect Diagram in Figure 1. Mainly based on Kumaraswamy and Dissanayaka (1998) the factors in this diagram are divided in four categories: The functional composition, the procurement system, the specific project and process situation and project results. These features directly influence the choice for a functional composition. The procurement system consists of four subsystems, work packaging, functional composition, contractual arrangement and team selection (Kumaraswamy and Dissanayaka, 1998; Luu et al., 2005). The functional composition is leading and once the choice for a certain functional composition has been made the choice of the other subsystems will become apparent (Luu et al., 2005). Project and process features in specific project and process situations can be divided in four subcategories; external context, internal organization, project characteristics and client s goals and priorities (PSIBouw, 2005; Luu et al., 2005). The last category, project results can be described in terms of costs, time, quality, client s satisfaction and a rest category (Chan, 2002).

2. Procurement system 4. The project results Work packaging Costs Contractual arrangement Quality Time Division of roles Team selection External context Rest category Project characteristics Internal organization Division of tasks, responsibilities and risks Goals and priorities Satisfaction Insight in the several categories of factors that influence the decision making process of the client 1. Functional composition 3. Specific project and process situation Figure 1: Cause-and-Effect Diagram; Factors that influence the decision making process 4.2 Distinctive features of functional composition DBB and DB The distinctive features of the functional composition can be divided into primary and secondary features. These primary and secondary features are shown in Figure 2. The primary features are features of the functional composition. These are shown in Figure 1. Based on these subcategories five distinctive primary features have been formulated based on Dorée (1996), Kumaraswamy and Dissanayaka (1998) and Regieraad Bouw (2006). These five primary distinctive features are: - Procurement method (Dorée, 1996; Kumaraswamy and Dissanayaka, 1998) - Moment of transferring responsibilities (Dorée, 1996) - Composition of the design team (Dorée, 1996)

- Primary objectives of client and (main) contractor (Regieraad Bouw, 2006) - Structure to control the process (Dorée, 1996) Primary features FUNCTIONAL COMPOSITION DIVISION OF TASKS, RESPONSIBILITIES, RISKS AND ROLES 1: Procurement method 2: Moment of transferring responsibilities 3: Composition of Design team 4: Structure to control the process 5: Primary objectives client and contractor PROCUREMENTSYSTEEM Secondary features Work packaging Contractual arrangements Team selection Project description Incentives and contract conditions Selection criteria Figure 2: Primary and secondary features of a functional composition The secondary features are features of the procurement system. As shown in Figure 2 the procurement method leads to the secondary features of the functional composition. These secondary features are: work packaging, contractual arrangements and team selection (Kumaraswamy and Dissanayaka 1998; Luu et al., 2005). 4.3 Criteria that determine the difference between DBB and DB Based on Luu et al. (2005) and Ng et al. (2002) criteria are defined that determine the difference between functional compositions. Several interviews with experts in the Dutch Construction Industry completed this list of 16 criteria (see table 1). These criteria are divided into three categories: (1) project results, (2) process specific situation and (3) project specific situation. 5. Interviews Based on the criteria from paragraph 4.3 twelve interviews with experts were held in order to determine differences between DBB and DB. Due to the amount of relations in the research model these interviews were semi-structured. One part was a survey in which experts had to give a value to relationships between criteria and functional compositions. The other part consisted of open questions in which experts were asked to declare these relationships. These

experts were experienced project managers from contractors (2), from consultants (3) and from public clients (7). In table 1, differences between DBB and DB can be seen. The criteria and experts input are discussed in paragraphs 5.1.1 5.1.14. 5.1.1 Time certainty 11 experts state that time certainty is much higher in DB projects. The main reasons for this are the moment of contracting a contractor (which is earlier in a DB project) and close cooperation between design team and realization team. 5.1.2 Total time (preconstruction time and construction time) 10 experts state that the total time in a DB project is in most cases shorter. Better cooperation within a Design and Build firm and the contractor s objective to spend as little time as possible are the main drivers for this. Looking at preconstruction time and construction time separately shows the same results. 5.1.3 Costs certainty 8 experts state that costs certainty in a DB project is higher than in a DBB project. As with time certainty, costs certainty is also better because of the moment of contracting a contractor (which is earlier in a DB project and therefore the amount of money that a client has to spend is known and fixed earlier). Next to that, close cooperation between design team and realization team will make sure that coordination between these two teams will go smoother and faster. 5.1.4 Construction costs 6 experts state that construction costs in a DBB contract are always lower. Three experts state that the construction costs in a DBB are only lower in the right economical phase and 3 state that the construction costs in a DB project are lower. The construction costs in a DBB project are lower because of the price oriented way of tendering. Opposite to that is the fact that total construction costs in a DB project might become lower because of the good cooperation between design and construction teams. 5.1.5 Maintain and operate costs Experts opinions are miscellaneous. Most experts agree that the client s influence on specifications in a DBB project is higher and can therefore lead to better specifications on the field of maintenance. On the other hand, a client can also do this in a DB project.

5.1.6 Quality guarantee 4 experts state that DBB can better guarantee quality. 4 experts state that DB can better guarantee quality and 2 state that both can guarantee quality on an equal level. The influence of a client in DBB can make sure the quality is better guaranteed. Opposite to that, the cooperation in a DB firm can optimize quality. 5.1.7 Price/quality ratio 5 experts state that DB can lead to a better price quality ratio. 2 state that DBB leads to a better price/quality ratio. 3 experts say there is no difference and one states that it depends on the extent in which the contractor is able to use an innovative solution: if that is possible, DB leads to a better price/quality ratio. The last expert states that it depends highly on the economic situation. 5.1.8 Risk for the client 10 experts state that risks for the client are better manageable in a DB project. One says that they are better manageable in a DBB project. One states that it depends on the extent in which partners are able to manage risks. Main reason for this difference is the fact that a client has the possibility to allocate more risks with the contractor. 5.1.9 Flexibility of the client 8 experts state that the flexibility for the client (to change parts of the design) is bigger in a DBB project than in a DB project. This is because the higher level of influence that a client has during the project. 5.1.10 Knowledge of the client Experts opinions are miscellaneous. The knowledge that is needed from a client in a DB project is concentrated in a short period in which his contribution of high level knowledge is big. In a DBB project, knowledge is needed during the whole project. 5.1.11 Capacity of the client The capacity that a client needs to deliver is closely related with the knowledge that is needed. 5.1.12 Client s influence on the project 10 experts state that the client s influence is bigger in a DBB project. This is because of his design-responsibility.

5.1.13 Product complexity 10 experts state that a DB contract is more suited for projects with high complexity. Main reason for this is that coordination between design team and construction team is easier in a DB contract. Next to that, risks in a complex project are high. These risks can easier be allocated with the contractor in DB contract. 5.1.14 Process complexity All experts state that complexity related to coordination between the different stakeholders Can better be managed in a DB contract. Next to that, all experts also agree that complexity on the field of the project s environment (e.g. licenses) can better be managed by the client. 6. Results and discussion The results of this research are combined in table 1. Clients can use this as a first step or a guide in making a choice for a certain functional composition. Compared to the model of Maas and Van Eekelen (2003), in this paper only two functional compositions have been compared. Therefore a client can only conclude that a more traditional or a more integrated functional composition suits a specific project and process situation. The results from this research are not valid in all situations. This means that some factors not taken into account in this study can strongly influence the differences between DBB and DB. The results that are shown are only valid under normal circumstances. This guide for clients has been designed, based on literature and research in practice. The list itself has not been validated yet. Therefore this list must still be validated by experts or by means of a few case studies. Clients still lack insight into the complexity of a construction process and are not able to choose the right functional composition. Research at this subject is still needed to give different insights into this complexity and thereby helping a client in making the right choice.

Table 1: Differences between Design-Bid-Build and Design-Build Criterion Variable D-B-B D-B Time Time Certainty - ++ Total Time - + Preconstruction Time - + Construction Time - + Costs Costs Certainty - ++ Construction costs + - Maintain and Operate costs +/- +/- Quality Quality guarantee +/- +/- Price/quality ratio +/- +/- Risk Risks for the client - ++ Process Flexibility of the client ++ - Knowledge +/- +/- Capacity +/- +/- Influence + - Project Product Complexity - ++ Process complexity / Uncertainty +/- +/- 7. Conclusion This research gives clients insight in factors that influence the decision for a certain functional composition. It helps clients in making the first steps in the decision making process.

Besides that, this research shows what factors influence the project results. Based on the criteria in this research insight is created in differences between more traditional and more integrated functional compositions. Thereby the first steps of the decision making process have been made transparent. This list can be used in every type of project. However this research is limited to those situations where only the Design phase and Construction phase will be considered when choosing the most suitable functional composition. 8. References Chan, A.P.C. et al. (2002), Framework of success criteria for Design/Build projects. Journal of Management in Engineering, 18 (3), pp. 120-128. Dorée, A.G. (1996), Gemeentelijk aanbesteden: een onderzoek naar de samenwerking tussen diensten gemeentewerken en aannemers in de grond-, weg- en waterbouwsector. Enschede: Universiteit Twente. Kumaraswamy, M.M. & Dissanayaka, S.M. (1998), Linking procurement systems to project priorities. Building Research & Information, 26 (4), pp. 223 238. Ling, F. Y. Y. (2004), "How project managers can better control the performance of designbuild projects". International Journal of Project Management, vol. 22, no. 6, pp. 477-488. Luu, D.T. et al. (2005), Formulating procurement selection criteria through case-based reasoning approach. Journal of Computing in Civil Engineering, 19 (3), pp. 269 276. Maas, G.J. & Eekelen, B. van (2003), Reisgids naar de Future Site : inleiding in de bouwprocesleer. Eindhoven: Technische Universiteit Eindhoven. Ng, S.T. et al. (2002), Fuzzy membership functions of procurement selection criteria. Construction Management and Economics, 20, pp. 285-296. Pakkala, P.A., De Jong, W.M., Aijo, J. (2007) International Overview of Innovative Contracting Practices for Roads. Finnish Road Administration, Helsinki. Palaneeswaran, E. & Kumaraswamy, M. M. (2000), "Contractor selection for design/build projects". Journal of Construction Engineering and Management-Asce, vol. 126, no. 5, pp. 331-339. PSIBouw (2005), Overwegingen bij uitbestedingsstrategieën. Gouda: PSIBouw Programmabureau.

Regieraad Bouw (2006), Beter aanbesteden in de bouw. Gouda: Regieraad Bouw. Regieraad Bouw (2007), Opdrachtgevers aan het woord meting 2007. Gouda: Regieraad Bouw. Rijkswaterstaat (2007), Handreiking Systeemgerichte Contractbeheersing versie 2007. Utrecht: Rijkswaterstaat.